Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260412.xer · Uploaded Apr 16, 2026 12:51 PM · 8408 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
0
Completed
0
In Progress
3
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL10.SKN.SSB.01390 RPL10.SKIN.BLDG - Install Coping Skin Not Started 04/21/26 04/27/26 6.2 6.2
0%
343.8
RPL10.CTRC.BB.3315 RPL10.Int.Build Back.Center-Corr - LO #13 - P6 Hang Drywall (Around 30"" Mech Pipe) Build Back Interior Leave Out Wall #12 #13 @ 30"" Mech Piping (Center Corr) Not Started 04/22/26 04/23/26 2.5 2.5
0%
140.0
RPL10.EY.EF2.01160 RPL10.EY.EF2 - Install RPL-3 FSP Columns F/R/P Fiber Support Platform - RPL-3 Not Started 04/22/26 04/28/26 6.2 6.2
0%
225.0
RPL10.EY.NS2.01240 RPL10.EY.NS2 - Install GS.IDF Hut (1x GS.IDF) NX06 (04.22.26) OFE Not Started 04/22/26 04/28/26 6.2 6.2
0%
31.2
RPL10.EY.NS4.01210 RPL10.EY.NS4 - Tent Temp Conditioning Startup and Available (Including Acclimation) (04/10/26) Tent and Temp Conditions Not Started 04/22/26 04/29/26 7.5 7.5
0%
115.0
RPL10.INT.ENDC.01010 RPL10.Interior.End-Corridor - Priority - Install Duct (Highside OH space) Priority Walls & OverHead Not Started 04/22/26 05/05/26 12.5 12.5
0%
115.0
RPL10.INT.NS1.01750 RPL10.Interior.NS1 - Control Fault Domain 3 SQ4.1 - Install LV Side Aisle Cable Tray LV Side Tie-ins Not Started 04/22/26 04/27/26 5.0 5.0
0%
127.5
RPL10.INT.NS2.01130 RPL10.Interior.NS2 - Control Fault Domain 6 SQ1.2 - Install Duct (LV Side) LV Side Tie-ins Not Started 04/22/26 04/28/26 6.2 6.2
0%
31.2
RPL10.INT.NS2.01160 RPL10.Interior.NS2 - Tie-ins - Control Fault Domain 6 SQ1.2 - WBS Summary Tie-Ins NS2 Control Fault Domain 6 Not Started 04/22/26 07/06/26 65.0 65.0
0%
16.2
RPL10.MCUP.LP2.1560 RPL10.MCUP.Loop 2 - Tie-in Electrical (LOE) Tie-Ins Electrical Not Started 04/22/26 05/29/26 33.8 33.8
0%
130.0
RPL10.MCUP.LP2.1620 RPL10.MCUP.Loop 2 - Tie-in Electrical #2 Tie-Ins Electrical Not Started 04/22/26 05/04/26 11.2 11.2
0%
137.5
RPL10.SSB.BB.1120 RPL10.Ext.Build Back.SSB - LO #5 - Install Exterior Backing, In Wall Build Back Exterior Leave Out Wall #5 (East SSB) Not Started 04/22/26 04/27/26 5.0 5.0
0%
441.2
RPL10.WP2.01010 RPL10.Conn SSB - Construction Cx Server Ready - At GSMDF WP2 (GS/CARRIER/SFZ - INF, CAB [ISP/OSP], NET) Not Started 04/22/26 04/22/26 0.0 0.0
0%
45.0
RPL10.WP4.08420 RPL10.Conn 10GSMDF2 Pull/Install Fanout (MMC<>UPC) [PON] Pre ORv3 Rack Not Started 04/22/26 04/27/26 5.0 5.0
0%
187.5
RPL10.CTRC.BB.2020 RPL10.Int.Build Back.Center-Corr - LO #12 - P3 Hang Drywall (Around 30"" Mech Pipe) Build Back Interior Leave Out Wall #12 #13 @ 30"" Mech Piping (Center Corr) Not Started 04/23/26 04/24/26 2.5 2.5
0%
138.8
RPL10.INT.NS1.01770 RPL10.Interior.NS1 - Control Fault Domain 2 SQ5.1 - Install Duct (LV Side) LV Side Tie-ins Not Started 04/23/26 04/28/26 5.0 5.0
0%
81.2
RPL10.INT.NS1.01800 RPL10.Interior.NS1 - Tie-ins - Control Fault Domain 2 SQ5.1 - WBS Summary Tie-Ins NS1 Control Fault Domain 2 Not Started 04/23/26 08/26/26 110.0 110.0
0%
45.0
RPL10.INT.SSB.01280 RPL10.Interior.SSB - BoW - Duct Drops / Trim out Balance of Walls and OverHead Not Started 04/23/26 05/01/26 8.8 8.8
0%
177.5
RPL10.INT.SSB.01310 RPL10.Interior.SSB - BoW - MEPF Hard Lid Rough Balance of Walls and OverHead Not Started 04/23/26 04/29/26 6.2 6.2
0%
113.8
RPL10.INT.SSBC.02780 RPL10.Interior.SSB-Corridor - BoW - Duct Drops Trim out Balance of Walls & OverHead Not Started 04/23/26 04/28/26 5.0 5.0
0%
66.2
RPL10.INT.SSBC.03000 RPL10.Interior.SSB-Corridor - BoW - Security Trim Out (Both Side of Corridor Wall) Balance of Walls & OverHead Not Started 04/23/26 05/01/26 8.8 8.8
0%
68.8
RPL10.MCUP.LP2.1840 RPL10.MCUP.Loop 2 - Tie-in EPMS #6 Tie-Ins EPMS Not Started 04/23/26 04/30/26 7.5 7.5
0%
141.2
RPL10.MCUP.LP2.1880 RPL10.MCUP.Loop 2 - Tie-in BMS #6 Tie-Ins BMS Not Started 04/23/26 05/01/26 8.8 8.8
0%
141.2
RPL10.CTRC.BB.3335 RPL10.Int.Build Back.Center-Corr - LO #13 - P6 Tape, Float and Paint (Around 30"" Mech Pipe) Build Back Interior Leave Out Wall #12 #13 @ 30"" Mech Piping (Center Corr) Not Started 04/24/26 04/30/26 6.2 6.2
0%
140.0
RPL10.EY.EF1.01560 RPL10.EY.EF1 - Install CU (12) OFE Not Started 04/24/26 04/27/26 2.5 2.5
0%
127.5
RPL10.EY.EF2.01770 RPL10.EY.EF2 - Install Remaining CU (12) OFE Not Started 04/24/26 04/27/26 2.5 2.5
0%
192.5
RPL10.EY.ENDC.01170 RPL10.EY.End - Install Lighting Hardscape and Landscape Not Started 04/24/26 05/14/26 18.8 18.8
0%
453.8
RPL10.INT.CTRC.01180 RPL10.Interior.Center-Corridor - BoW - Install Plumbing Lowside OH and In-wall Balance of Walls & OverHead Not Started 04/24/26 04/30/26 6.2 6.2
0%
123.8
RPL10.INT.CTRC.01300 RPL10.Interior.Center-Corridor - BoW - Frame Hard Lid Balance of Walls & OverHead Not Started 04/24/26 04/30/26 6.2 6.2
0%
112.5
RPL10.INT.CTRC.01930 RPL10.Interior.Center-Corridor - BoW - QC BoW - Backing/In-Wall Balance of Walls & OverHead Not Started 04/24/26 04/30/26 6.2 6.2
0%
110.0
RPL10.INT.NS1.01204 RPL10.Interior.NS1 - MES Skids - BMS Tie-Ins NS1 - MES Skids Not Started 04/24/26 05/28/26 30.0 30.0
0%
161.2
RPL10.INT.NS2.01220 RPL10.Interior.NS2 - Control Fault Domain 6 SQ1.2 - Install LV Side Aisle HAC Busway LV Side Tie-ins Not Started 04/24/26 04/30/26 6.2 6.2
0%
40.0
RPL10.INT.NS2.01490 RPL10.Interior.NS2 - OFE - Control Fault Domain 3 SQ4.2 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary OFE NS2 Control Fault Domain 3 Not Started 04/24/26 07/23/26 78.8 78.8
0%
-22.5
RPL10.INT.NS2.02485 RPL10.Interior.NS2 - OFE - Control Fault Domain 6 SQ1.2 - (Mech Side Aisle) OFE NS2 Control Fault Domain 6 Not Started 04/24/26 05/19/26 22.5 22.5
0%
-15.0
RPL10.INT.NS2.02625 RPL10.Interior.NS2 - OFE - Control Fault Domain 3 SQ4.2 (LV Side Aisle) OFE NS2 Control Fault Domain 3 Not Started 04/24/26 04/29/26 5.0 5.0
0%
30.0
RPL10.INT.SSB.01250 RPL10.Interior.SSB - Loading Dock and Storage - Install Security Loading Dock and Storage Not Started 04/24/26 05/04/26 8.8 8.8
0%
151.2
RPL10.INT.SSB.01470 RPL10.Interior.SSB - Loading Dock and Storage - Install Unit Heaters Loading Dock and Storage Not Started 04/24/26 04/30/26 6.2 6.2
0%
203.8
RPL10.INT.SSB.01530 RPL10.Interior.SSB - Loading Dock and Storage - Install OverHead Doors Loading Dock and Storage Not Started 04/24/26 05/07/26 12.5 12.5
0%
161.2
RPL10.INT.SSB.01760 RPL10.Interior.SSB - Loading Dock and Storage - Mechanical Tie-In Loading Dock and Storage Not Started 04/24/26 04/30/26 6.2 6.2
0%
161.2
RPL10.INT.SSB.01820 RPL10.Interior.SSB - BoW - Mechanical Tie-In Balance of Walls and OverHead Not Started 04/24/26 04/30/26 6.2 6.2
0%
227.5
RPL10.INT.SSBC.01252 RPL10.Interior.SSB-Corridor - BoW - Install Electrical - Lighitng Inverter Room (10.S2.07) Balance of Walls & OverHead Not Started 04/24/26 05/04/26 8.8 8.8
0%
183.8
RPL10.INT.SSBC.01590 RPL10.Interior.SSB-Corridor - BoW - Install Mechanical Tie-Ins (needs to micro plan) Balance of Walls & OverHead Not Started 04/24/26 04/30/26 6.2 6.2
0%
63.8
RPL10.INT.SSBC.02900 RPL10.Interior.SSB-Corridor - BoW - Final Paint Balance of Walls & OverHead Not Started 04/24/26 04/30/26 6.2 6.2
0%
53.8
RPL10.MCUP.LP2.1660 RPL10.MCUP.Loop 2 - Tie-in BMS (LOE) ??? Check Relation Tie-Ins BMS Not Started 04/24/26 05/29/26 31.2 31.2
0%
130.0
RPL10.MCUP.LP2.1720 RPL10.MCUP.Loop 2 - Tie-in BMS #2 Tie-Ins BMS Not Started 04/24/26 05/06/26 11.2 11.2
0%
137.5
RPL10.EY.EF1.01680 RPL10.EY.EF1 - Install RPL-2 FSP Columns Cap Cure Fiber Support Platform - RPL-2 Not Started 04/25/26 04/29/26 6.2 6.2
0%
311.2
PL10.WP2.GSIDF.1920 RPL10.Conn GSIDFN13 Install & Test Network (FIM) Network Not Started 04/27/26 04/29/26 3.8 3.8
0%
246.2
RPL10.CTRC.BB.2040 RPL10.Int.Build Back.Center-Corr - LO #12 - P3 Tape, Float and Paint (Around 30"" Mech Pipe) Build Back Interior Leave Out Wall #12 #13 @ 30"" Mech Piping (Center Corr) Not Started 04/27/26 05/01/26 6.2 6.2
0%
138.8
RPL10.EY.EF1.01230 RPL10.EY.EF1 - Install RPL-2 FSP Grounding Wire Fiber Support Platform - RPL-2 Not Started 04/27/26 04/28/26 2.5 2.5
0%
293.8
RPL10.EY.NS3.01140 RPL10.EY.NS3 - Install Tent Electrical Panels Tent and Temp Conditions Not Started 04/27/26 05/01/26 6.2 6.2
0%
101.2
RPL10.EY.NS3.01150 RPL10.EY.NS3 - Install Tent Heating and Cooling Equipment Tent and Temp Conditions Not Started 04/27/26 05/01/26 6.2 6.2
0%
107.5
RPL10.EY.NS3.01160 RPL10.EY.NS3 - Install Tent Overhead Doors Tent and Temp Conditions Not Started 04/27/26 05/01/26 6.2 6.2
0%
107.5
RPL10.EY.NS3.01190 RPL10.EY.NS3 - Install Tent Mechanical Tie-ins Tent and Temp Conditions Not Started 04/27/26 05/04/26 7.5 7.5
0%
107.5
RPL10.INT.CTRC.01260 RPL10.Interior.Center-Corridor - BoW - Remaining Electrical OFE Tie In Balance of Walls & OverHead Not Started 04/27/26 05/01/26 6.2 6.2
0%
137.5
RPL10.INT.EF1.01380 RPL10.Interior.EF1 - EF1 East - Install Upper Trays East EF-1 Not Started 04/27/26 05/01/26 6.2 6.2
0%
55.0
RPL10.INT.EF1.01390 RPL10.Interior.EF1 - CFCI - Install CFCI Prefab Cable Rack - EF1 West OFE Not Started 04/27/26 05/22/26 25.0 25.0
0%
30.0
RPL10.INT.EF2.01400 RPL10.Interior.EF2 - Tie-ins - EF2 East - WBS Summary East EF-2 Not Started 04/27/26 07/28/26 81.2 81.2
0%
162.5
RPL10.INT.EF2.01435 RPL10.Interior.EF2 - EF2 East - Install Wall Mounted Ladder Racks on Full Height EF Walls East EF-2 Not Started 04/27/26 05/01/26 6.2 6.2
0%
231.2
RPL10.INT.NS1.01300 RPL10.Interior.NS1 - Control Fault Domain 6 SQ1.1 - Install Mechanical Side Aisle Cable Tray Remaining Tie-ins post Mech Side Aisle install Not Started 04/27/26 05/22/26 25.0 25.0
0%
38.8
RPL10.INT.NS1.01870 RPL10.Interior.NS1 - Control Fault Domain 2 SQ5.1 - Install LV Side Aisle HAC Busway LV Side Tie-ins Not Started 04/27/26 04/30/26 5.0 5.0
0%
111.2
RPL10.INT.NS1.02480 RPL10.Interior.NS1 - OFE - Control Fault Domain 5 SQ2.1 (HAC) OFE NS1 Control Fault Domain 5 Not Started 04/27/26 05/15/26 18.8 18.8
0%
-11.2
RPL10.INT.NS2.01210 RPL10.Interior.NS2 - Control Fault Domain 6 SQ1.2 - Install LV Side Aisle Cable Tray LV Side Tie-ins Not Started 04/27/26 05/01/26 6.2 6.2
0%
40.0
RPL10.INT.SSBC.03020 RPL10.Interior.SSB-Corridor - BoW - Plumbing Trim Out Balance of Walls & OverHead Not Started 04/27/26 05/05/26 8.8 8.8
0%
68.8
RPL10.INT.SSBC.03040 RPL10.Interior.SSB-Corridor - BoW - Fire Life Safety Trim Out / Fire Alarm Trim Out Balance of Walls & OverHead Not Started 04/27/26 05/08/26 12.5 12.5
0%
68.8
RPL10.MCUP.LP2.1680 RPL10.MCUP.Loop 2 - Tie-in EPMS (LOE) Tie-Ins EPMS Not Started 04/27/26 05/29/26 30.0 30.0
0%
130.0
RPL10.MCUP.LP2.1700 RPL10.MCUP.Loop 2 - Tie-in EPMS #2 Tie-Ins EPMS Not Started 04/27/26 05/05/26 8.8 8.8
0%
137.5
RPL10.MCUP.LP2.2020 RPL10.MCUP.Loop 2 - Tie-in Mechanical #8 WBS Summary Tie-in Mechanical #8 Not Started 04/27/26 05/11/26 13.8 13.8
0%
130.0
RPL10.MCUP.LP2.2720 RPL10.MCUP.Loop 2 - Facility Water Tie-in Mechanical #8 Tie-in Mechanical #8 Not Started 04/27/26 04/29/26 3.8 3.8
0%
130.0
RPL10.WP2.01030 RPL10.Conn SSB - Early Construction Cx Server Ready - At NS1 (LV) WP2 (GS/CARRIER/SFZ - INF, CAB [ISP/OSP], NET) Not Started 04/27/26 04/27/26 0.0 0.0
0%
75.0
RPL10.WP2.GSIDF.1500 RPL10.Conn GSIDFN23 Install & Test Network (FIM) Network Not Started 04/27/26 04/29/26 3.8 3.8
0%
246.2
RPL10.WP2.GSIDF.3100 RPL10.Conn GSIDFN13 Install Copper, WAPs, Security Camera & Access Control Cabling Not Started 04/27/26 05/12/26 15.0 15.0
0%
203.8
RPL10.WP2.GSIDF.3140 RPL10.Conn GSIDFN23 Install Copper, WAPs, Security Camera & Access Control Cabling Not Started 04/27/26 05/12/26 15.0 15.0
0%
203.8
RPL10.EY.EF1.01210 RPL10.EY.EF1 - Install Mechanical Tie-ins (include penetration detail) Tie-ins Not Started 04/28/26 05/07/26 10.0 10.0
0%
142.5
RPL10.EY.EF1.01220 RPL10.EY.EF1 - Tie-ins - WBS Summary Tie-ins Not Started 04/28/26 06/09/26 37.5 37.5
0%
127.5
RPL10.EY.EF1.01330 RPL10.EY.EF1 - Install Electrical Tie-ins (include penetration detail) Tie-ins Not Started 04/28/26 05/18/26 18.8 18.8
0%
127.5
RPL10.EY.EF2.01620 RPL10.EY.EF2 - Install Remaining Mechanical Tie-ins Tie-ins Not Started 04/28/26 05/07/26 10.0 10.0
0%
192.5
RPL10.EY.EF2.01630 RPL10.EY.EF2 - Install Remaining Electrical Tie-ins Tie-ins Not Started 04/28/26 05/04/26 6.2 6.2
0%
196.2
RPL10.INT.NS1.01890 RPL10.Interior.NS1 - Control Fault Domain 2 SQ5.1 - Install LV Side Aisle Cable Tray LV Side Tie-ins Not Started 04/28/26 05/01/26 5.0 5.0
0%
146.2
RPL10.INT.NS4.01100 RPL10.Interior.NS4 - Tie-ins - WBS Summary Tie-Ins Not Started 04/28/26 01/06/27 217.5 217.5
0%
123.8
RPL10.INT.NS4.01110 RPL10.Interior.NS4 - MES Skids Tie-ins (LOE) NS4 - MES Skids Not Started 04/28/26 07/22/26 75.0 75.0
0%
237.5
RPL10.INT.NS4.01111 RPL10.Interior.NS4 - MES Skids - Set & Anchor Interconnects NS4 - MES Skids Not Started 04/28/26 06/01/26 30.0 30.0
0%
135.0
RPL10.INT.SSB.02540 RPL10.Interior.SSB - BoW - ACT - Ceiling Grid & Wires Balance of Walls and OverHead Not Started 04/28/26 05/06/26 8.8 8.8
0%
71.2
RPL10.INT.SSBC.01360 RPL10.Interior.SSB-Corridor - BoW - Set Equipment / Interior Balance of Walls & OverHead Not Started 04/28/26 05/04/26 6.2 6.2
0%
42.5
RPL10.MCUP.LP1.2020 RPL10.MCUP.Loop 1 - Tie-in - MV Loop L2 Checklist Completion Tie-Ins Electrical Not Started 04/28/26 05/08/26 11.2 11.2
0%
17.5
RPL10.MCUP.LP1.2080 RPL10.MCUP.Loop 1 - Tie-in - Mechanical L2 Checklist Completion Tie-Ins Mechanical Not Started 04/28/26 05/08/26 11.2 11.2
0%
28.8
RPL10.SKN.SSB.01410 RPL10.SKIN.BLDG - Install Lightning Protection Skin Not Started 04/28/26 05/04/26 6.2 6.2
0%
343.8
RPL10.SSB.BB.1240 RPL10.Ext.Build Back.SSB - LO #5 - Install Security Lowside OH Build Back Exterior Leave Out Wall #5 (East SSB) Not Started 04/28/26 05/01/26 5.0 5.0
0%
451.2
RPL10.SSB.BB.1300 RPL10.Ext.Build Back.SSB - LO #5 - Install Electrical Lowside OH Build Back Exterior Leave Out Wall #5 (East SSB) Not Started 04/28/26 05/01/26 5.0 5.0
0%
451.2
RPL10.SSB.BB.1320 RPL10.Ext.Build Back.SSB - LO #5 - Install Controls / EPMS / BMS Lowside OH Build Back Exterior Leave Out Wall #5 (East SSB) Not Started 04/28/26 05/01/26 5.0 5.0
0%
451.2
RPL10.SSB.BB.1360 RPL10.Ext.Build Back.SSB - LO #5 - Install Frame, Doors, Hardware Build Back Exterior Leave Out Wall #5 (East SSB) Not Started 04/28/26 04/29/26 2.5 2.5
0%
441.2
RPL10.WP2.CMDF1.1000 RPL10.Conn CMDF1 Install Infrastructure Racks, Tier1 Infrastructure Not Started 04/28/26 05/04/26 6.2 6.2
0%
171.2
RPL10.WP2.CMDF2.1000 RPL10.Conn CMDF2 Install Infrastructure Racks, Tier1 Infrastructure Not Started 04/28/26 05/04/26 6.2 6.2
0%
170.0
RPL10.WP2.GSIDF.1200 RPL10.Conn GSIDFNE1 Install & Test Network (FIM) Network Not Started 04/28/26 04/30/26 3.8 3.8
0%
161.2
RPL10.WP2.GSIDF.3000 RPL10.Conn GSIDFNX13 Install & Test Network (FIM) Network Not Started 04/28/26 04/30/26 3.8 3.8
0%
245.0
RPL10.WP2.GSIDF.3060 RPL10.Conn GSIDFNE1 Install Copper, WAPs, Security Camera & Access Control Cabling Not Started 04/28/26 05/18/26 18.8 18.8
0%
488.8
RPL10.WP2.GSIDF.3520 RPL10.Conn GSIDFNX13 Install Copper, WAPs, Security Camera & Access Control Cabling Not Started 04/28/26 05/11/26 12.5 12.5
0%
495.0
RPL10.EY.EF2.01190 RPL10.EY.EF2 - Install RPL-3 FSP Grounding Wire Fiber Support Platform - RPL-3 Not Started 04/29/26 04/30/26 2.5 2.5
0%
303.8
RPL10.EY.EF2.01810 RPL10.EY.EF2 - Install RPL-3 FSP Columns Cap Erect Shoring & Decking & F/R/P Fiber Support Platform - RPL-3 Not Started 04/29/26 05/05/26 6.2 6.2
0%
225.0
RPL10.EY.NS2.01270 RPL10.EY.NS2 - Install GS.IDF Hut (1x GS.IDF) NX07 (04.22.26) OFE Not Started 04/29/26 05/05/26 6.2 6.2
0%
31.2
RPL10.EY.NS3.01180 RPL10.EY.NS3 - Install Tent Electrical Tie-ins Tent and Temp Conditions Not Started 04/29/26 05/01/26 3.8 3.8
0%
101.2