Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260412.xer
· Uploaded Apr 16, 2026 12:51 PM
· 8408 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
3
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL10.INT.NS1.01910 |
RPL10.Interior.NS1 - Control Fault Domain 1 SQ6.1 - Install Duct (LV Side) | LV Side Tie-ins | Not Started | 04/29/26 | 05/04/26 | 5.0 | 5.0 |
|
92.5 |
RPL10.INT.NS1.01940 |
RPL10.Interior.NS1 - Tie-ins - Control Fault Domain 1 SQ6.1 - WBS Summary | Tie-Ins NS1 Control Fault Domain 1 | Not Started | 04/29/26 | 09/10/26 | 117.5 | 117.5 |
|
37.5 |
RPL10.INT.NS2.01260 |
RPL10.Interior.NS2 - Control Fault Domain 5 SQ2.2 - Install Duct (LV Side) | LV Side Tie-ins | Not Started | 04/29/26 | 05/04/26 | 5.0 | 5.0 |
|
35.0 |
RPL10.INT.NS2.01300 |
RPL10.Interior.NS2 - Tie-ins - Control Fault Domain 5 SQ2.2 - WBS Summary | Tie-Ins NS2 Control Fault Domain 5 | Not Started | 04/29/26 | 08/03/26 | 83.8 | 83.8 |
|
1.2 |
RPL10.INT.NS4.02020 |
RPL10.Interior.NS4 - OFE - Ancillary Skids - Set / Place / Anchor (04.29.26) | OFE | Not Started | 04/29/26 | 05/04/26 | 5.0 | 5.0 |
|
137.5 |
RPL10.INT.NS4.02440 |
RPL10.Interior.NS43 - Temp Conditions - Drop Curtains (from Corridor to EJ) | Temp Conditions | Not Started | 04/29/26 | 04/30/26 | 2.5 | 2.5 |
|
103.8 |
RPL10.INT.ENDC.01160 |
RPL10.Interior.End-Corridor - OFE - NS4 (1x GS.IDF) N43 (04.24.26) | OFE | Not Started | 04/30/26 | 05/06/26 | 6.2 | 6.2 |
|
217.5 |
RPL10.INT.ENDC.01190 |
RPL10.Interior.End-Corridor - OFE - NS3 (1x GS.IDF) N33 (04.24.26) | OFE | Not Started | 04/30/26 | 05/06/26 | 6.2 | 6.2 |
|
217.5 |
RPL10.INT.NS1.01355 |
RPL10.Interior.NS1 - Control Fault Domain 5 SQ2.1 - Install Duct (MES Side) | Remaining Tie-ins post Mech Side Aisle install | Not Started | 04/30/26 | 05/28/26 | 25.0 | 25.0 |
|
30.0 |
RPL10.INT.NS1.01360 |
RPL10.Interior.NS1 - Control Fault Domain 5 SQ2.1 - Install Vesda / FA | Remaining Tie-ins post Mech Side Aisle install | Not Started | 04/30/26 | 05/28/26 | 25.0 | 25.0 |
|
51.2 |
RPL10.INT.NS1.01370 |
RPL10.Interior.NS1 - Control Fault Domain 5 SQ2.1 - Install FW | Remaining Tie-ins post Mech Side Aisle install | Not Started | 04/30/26 | 05/28/26 | 25.0 | 25.0 |
|
30.0 |
RPL10.INT.NS1.02220 |
RPL10.Interior.NS1 - Control Fault Domain 5 SQ2.1 - Install TW | Remaining Tie-ins post Mech Side Aisle install | Not Started | 04/30/26 | 05/28/26 | 25.0 | 25.0 |
|
30.0 |
RPL10.INT.NS1.02500 |
RPL10.Interior.NS1 - OFE - Control Fault Domain 5 SQ2.1 (Mech Side Aisle) | OFE NS1 Control Fault Domain 5 | Not Started | 04/30/26 | 05/18/26 | 16.2 | 16.2 |
|
-1.2 |
RPL10.INT.NS2.01113 |
RPL10.Interior.NS2 - MES Skids - CDU Tie-Ins ( 2 per day) | NS2 - MES Skids | Not Started | 04/30/26 | 06/03/26 | 30.0 | 30.0 |
|
157.5 |
RPL10.INT.NS2.01630 |
RPL10.Interior.NS2 - OFE - Control Fault Domain 2 SQ5.2 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | OFE NS2 Control Fault Domain 2 | Not Started | 04/30/26 | 08/13/26 | 92.5 | 92.5 |
|
-25.0 |
RPL10.INT.NS2.02685 |
RPL10.Interior.NS2 - OFE - Control Fault Domain 2 SQ5.2 (LV Side Aisle) | OFE NS2 Control Fault Domain 2 | Not Started | 04/30/26 | 05/05/26 | 5.0 | 5.0 |
|
43.8 |
RPL10.MCUP.LP2.2000 |
RPL10.MCUP.Loop 2 - Tie-in Electrical #8 | Tie-Ins Electrical | Not Started | 04/30/26 | 05/12/26 | 11.2 | 11.2 |
|
130.0 |
RPL10.MCUP.LP2.2740 |
RPL10.MCUP.Loop 2 - Condenser Water Tie-in Mechanical #8 | Tie-in Mechanical #8 | Not Started | 04/30/26 | 05/11/26 | 10.0 | 10.0 |
|
130.0 |
RPL10.SSB.BB.1125 |
RPL10.Ext.Build Back.SSB - LO #5 - Hang Exterior Drywall, Paint | Build Back Exterior Leave Out Wall #5 (East SSB) | Not Started | 04/30/26 | 05/06/26 | 6.2 | 6.2 |
|
441.2 |
RPL10.WP2.GSIDF.1210 |
CorpNet & FacNet Available - EF | Network | Not Started | 04/30/26 | 04/30/26 | 0.0 | 0.0 |
|
245.0 |
RPL.10.D.X1440.XR |
Ready for Fiber Support Platform Construction - AI 2 (TCCO est Release 01-May-26) | Connectivity (XREFs) | Not Started | 05/01/26 | 05/01/26 | 0.0 | 0.0 |
|
216.2 |
RPL10.INT.CTRC.01280 |
RPL10.Interior.Center-Corridor - BoW - Install Duct and Drops | Balance of Walls & OverHead | Not Started | 05/01/26 | 05/07/26 | 6.2 | 6.2 |
|
127.5 |
RPL10.INT.CTRC.01320 |
RPL10.Interior.Center-Corridor - BoW - MEPF Frame Hard Lid Rough In/Close of Inspection | Balance of Walls & OverHead | Not Started | 05/01/26 | 05/07/26 | 6.2 | 6.2 |
|
112.5 |
RPL10.INT.CTRC.01330 |
RPL10.Interior.Center-Corridor - BoW - Hang Drywall BoW | Balance of Walls & OverHead | Not Started | 05/01/26 | 05/11/26 | 8.8 | 8.8 |
|
110.0 |
RPL10.INT.CTRC.01850 |
RPL10.Interior.Center-Corridor - BoW - Install VAV's/Duct Branches | Balance of Walls & OverHead | Not Started | 05/01/26 | 05/06/26 | 5.0 | 5.0 |
|
123.8 |
RPL10.INT.CTRC.01870 |
RPL10.Interior.Center-Corridor - BoW - Install Split Systems/Humidifiers | Balance of Walls & OverHead | Not Started | 05/01/26 | 05/06/26 | 5.0 | 5.0 |
|
143.8 |
RPL10.INT.EF1.01150 |
RPL10.Interior.EF1 - CFCI - Set North CRAH Units | OFE | Not Started | 05/01/26 | 05/07/26 | 6.2 | 6.2 |
|
113.8 |
RPL10.INT.NS1.02010 |
RPL10.Interior.NS1 - Control Fault Domain 1 SQ6.1 - Install LV Side Aisle HAC Busway | LV Side Tie-ins | Not Started | 05/01/26 | 05/06/26 | 5.0 | 5.0 |
|
116.2 |
RPL10.INT.NS2.01370 |
RPL10.Interior.NS2 - Control Fault Domain 5 SQ2.2 - Install LV Side Aisle HAC Busway | LV Side Tie-ins | Not Started | 05/01/26 | 05/06/26 | 5.0 | 5.0 |
|
43.8 |
RPL10.INT.NS4.02460 |
RPL10.Interior.NS43 - Temp Conditions - Install Early Temp Conditions | Temp Conditions | Not Started | 05/01/26 | 05/04/26 | 2.5 | 2.5 |
|
103.8 |
RPL10.INT.SSB.01780 |
RPL10.Interior.SSB - Loading Dock and Storage - Install Split Systems/Humidifiers | Loading Dock and Storage | Not Started | 05/01/26 | 05/07/26 | 6.2 | 6.2 |
|
161.2 |
RPL10.INT.SSBC.02860 |
RPL10.Interior.SSB-Corridor - BoW - Install Doors (Verify with Trades before Installation) | Balance of Walls & OverHead | Not Started | 05/01/26 | 05/05/26 | 3.8 | 3.8 |
|
53.8 |
RPL.10.D.X33X0.XR |
Pull and Term mCUP Skids - RPL10 North | Power (XREFs) | Not Started | 05/04/26 | 05/04/26 | 0.0 | 0.0 |
|
35.0 |
RPL.10.D.X33X1.XR |
Pull and Term MV Skids - RPL10 NS1 Loop 1 & 2 | Power (XREFs) | Not Started | 05/04/26 | 05/04/26 | 0.0 | 0.0 |
|
42.5 |
RPL.10.D.X3900.XG |
Ready for MV Cable Pull mCUP South Loop (Loop#2) | Give Milestones (XREFs) | Not Started | 05/04/26 | 05/04/26 | 0.0 | 0.0 |
|
1971.2 |
RPL10.EY.EF1.01140 |
RPL10.EY.EF1 - Install RPL-1 FSP Grounding Wire | Fiber Support Platform - RPL-1 | Not Started | 05/04/26 | 05/05/26 | 2.5 | 2.5 |
|
287.5 |
RPL10.EY.EF1.01160 |
RPL10.EY.EF1 - Install RPL-1 FSP Steel Span Structure Modules | Fiber Support Platform - RPL-1 | Not Started | 05/04/26 | 05/15/26 | 12.5 | 12.5 |
|
202.5 |
RPL10.EY.EF1.01170 |
RPL10.EY.EF1 - Install RPL-1 FSP Road Closure For Steel Erection | Fiber Support Platform - RPL-1 | Not Started | 05/04/26 | 05/15/26 | 12.5 | 12.5 |
|
202.5 |
RPL10.EY.EF1.01180 |
RPL10.EY.EF1 - Install RPL-1 Total Road Closure For Fiber Supprt Platform | Fiber Support Platform - RPL-1 | Not Started | 05/04/26 | 07/14/26 | 62.5 | 62.5 |
|
237.5 |
RPL10.EY.NS1.01290 |
RPL10.EY.NS1 - Install Sleeves MEPL | Hardscape and Landscape | Not Started | 05/04/26 | 05/08/26 | 6.2 | 6.2 |
|
188.8 |
RPL10.EY.NS1.01300 |
RPL10.EY.NS1 - MV Loop 1 - L2 Checklist Completion | Tie-ins | Not Started | 05/04/26 | 05/15/26 | 12.5 | 12.5 |
|
30.0 |
RPL10.EY.NS1.01310 |
RPL10.EY.NS1 - MV Loop 2 - L2 Checklist Completion | Tie-ins | Not Started | 05/04/26 | 05/15/26 | 12.5 | 12.5 |
|
72.5 |
RPL10.EY.NS1.01320 |
RPL10.EY.NS1 - Install Hardscape and Landscape - WBS Summary | Hardscape and Landscape | Not Started | 05/04/26 | 10/22/26 | 151.2 | 151.2 |
|
351.2 |
RPL10.EY.NS3.01210 |
RPL10.EY.NS3 - Tent Temp Conditioning Startup and Available (Including Acclimation) (03/27/26) | Tent and Temp Conditions | Not Started | 05/04/26 | 05/11/26 | 7.5 | 7.5 |
|
101.2 |
RPL10.INT.CTRC.01290 |
RPL10.Interior.Center-Corridor - BoW - Remaining Mechanical OFE Tie In | Balance of Walls & OverHead | Not Started | 05/04/26 | 05/06/26 | 3.8 | 3.8 |
|
137.5 |
RPL10.INT.EF1.01410 |
RPL10.Interior.EF1 - EF1 East - Install Lower Trays | East EF-1 | Not Started | 05/04/26 | 05/08/26 | 6.2 | 6.2 |
|
55.0 |
RPL10.INT.EF1.01420 |
RPL10.Interior.EF1 - EF1 East - Install Lighting | East EF-1 | Not Started | 05/04/26 | 05/19/26 | 15.0 | 15.0 |
|
132.5 |
RPL10.INT.EF2.01490 |
RPL10.Interior.EF2 - Tie-ins - EF2 West - WBS Summary | West EF-2 | Not Started | 05/04/26 | 08/11/26 | 87.5 | 87.5 |
|
156.2 |
RPL10.INT.EF2.01525 |
RPL10.Interior.EF2 - EF2 West - Install Wall Mounted Ladder Racks on Full Height EF Walls | West EF-2 | Not Started | 05/04/26 | 05/08/26 | 6.2 | 6.2 |
|
231.2 |
RPL10.INT.NS1.01340 |
RPL10.Interior.NS1 - Control Fault Domain 6 SQ1.1 - Install copper from GS.IDF to BMS and EPMS panels | Remaining Tie-ins post Mech Side Aisle install | Not Started | 05/04/26 | 06/01/26 | 25.0 | 25.0 |
|
40.0 |
RPL10.INT.NS1.02020 |
RPL10.Interior.NS1 - Control Fault Domain 1 SQ6.1 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 05/04/26 | 05/07/26 | 5.0 | 5.0 |
|
146.2 |
RPL10.INT.NS2.01380 |
RPL10.Interior.NS2 - Control Fault Domain 5 SQ2.2 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 05/04/26 | 05/07/26 | 5.0 | 5.0 |
|
43.8 |
RPL10.INT.NS3.01070 |
RPL10.Interior.NS3 - OFE - MES Skids - Set / Place / Anchor | OFE | Not Started | 05/04/26 | 06/01/26 | 25.0 | 25.0 |
|
123.8 |
RPL10.INT.SSB.01360 |
RPL10.Interior.SSB - BoW - Electrical Trim Out | Balance of Walls and OverHead | Not Started | 05/04/26 | 05/08/26 | 6.2 | 6.2 |
|
177.5 |
RPL10.INT.SSB.01380 |
RPL10.Interior.SSB - BoW - Security Trim Out | Balance of Walls and OverHead | Not Started | 05/04/26 | 05/12/26 | 8.8 | 8.8 |
|
177.5 |
RPL10.MCUP.LP2.1980 |
RPL10.MCUP.Loop 2 - Tie-in BMS #8 | Tie-Ins BMS | Not Started | 05/04/26 | 05/14/26 | 11.2 | 11.2 |
|
130.0 |
RPL10.SSBC.BB.1000 |
RPL10.Int.Build Back.SSB-Corr - LO #2,3,4 - MEPF Trim Out | Build Back Interior Leave Out Wall #2 #3 #4 (SSB Corr) | Not Started | 05/04/26 | 05/22/26 | 18.8 | 18.8 |
|
183.8 |
RPL10.WP2.GSIDF.1580 |
RPL10.Conn GSIDFN41 Install & Test Network (FIM) | Network | Not Started | 05/04/26 | 05/06/26 | 3.8 | 3.8 |
|
240.0 |
RPL10.WP2.GSIDF.1820 |
RPL10.Conn GSIDFN31 Install & Test Network (FIM) | Network | Not Started | 05/04/26 | 05/06/26 | 3.8 | 3.8 |
|
240.0 |
RPL10.WP2.GSIDF.2020 |
RPL10.Conn IDF Huts - (GSMDF to GSIDF) NS1 NX01 WBS Summary | GSIDFNX01 | Not Started | 05/04/26 | 05/20/26 | 16.2 | 16.2 |
|
486.2 |
RPL10.WP2.GSIDF.2040 |
RPL10.Conn GSIDFNX01 Set Infrastructure (Racks, Waterfalls etc.) | Infrastructure | Not Started | 05/04/26 | 05/08/26 | 6.2 | 6.2 |
|
227.5 |
RPL10.WP2.GSIDF.2100 |
RPL10.Conn IDF Huts - (GSMDF to GSIDF) NS1 NX02 WBS Summary | GSIDFNX02 | Not Started | 05/04/26 | 05/20/26 | 16.2 | 16.2 |
|
486.2 |
RPL10.WP2.GSIDF.2120 |
RPL10.Conn GSIDFNX02 Set Infrastructure (Racks, Waterfalls etc.) | Infrastructure | Not Started | 05/04/26 | 05/08/26 | 6.2 | 6.2 |
|
30.0 |
RPL10.WP2.GSIDF.3160 |
RPL10.Conn GSIDFN41 Install Copper, WAPs, Security Camera & Access Control | Cabling | Not Started | 05/04/26 | 05/19/26 | 15.0 | 15.0 |
|
312.5 |
RPL10.WP2.GSIDF.3220 |
RPL10.Conn GSIDFN31 Install Copper, WAPs, Security Camera & Access Control | Cabling | Not Started | 05/04/26 | 05/19/26 | 15.0 | 15.0 |
|
312.5 |
RPL10.WP4.027220 |
RPL10.Conn NS1.CFD6.48<>03-05 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] | Prefab | Not Started | 05/04/26 | 05/06/26 | 3.8 | 3.8 |
|
147.5 |
RPL10.WP4.027420 |
RPL10.Conn NS1.CFD5.48<>03-05 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] | Prefab | Not Started | 05/04/26 | 05/05/26 | 2.5 | 2.5 |
|
148.8 |
RPL10.WP4.NS1.01800 |
RPL10.Conn NS1.CFD6 Network - WBS Summary | Network | Not Started | 05/04/26 | 11/16/26 | 171.2 | 171.2 |
|
45.0 |
RPL10.WP4.NS1.02480 |
RPL10.Conn NS1.CFD5 Network - WBS Summary | Network | Not Started | 05/04/26 | 11/18/26 | 173.8 | 173.8 |
|
42.5 |
JCL.C.1320 |
RPL10 - Cost Risk LOE-17 Site | Cost LOEs | Not Started | 05/05/26 | 03/02/27 | 257.5 | 257.5 |
|
243.8 |
RPL.GF.D.N0125.XR |
4 of 4 Fiber Test Complete CAV2/3 to GS.EF2/ Prod.EF2B | Connectivity (XREFs) | Not Started | 05/05/26 | 05/05/26 | 0.0 | 0.0 |
|
170.0 |
RPL.GF.D.N0600.XG |
GS.IDF Hut Install Complete (01, 02, 06, 07) | Give Milestones (XREFs) | Not Started | 05/05/26 | 05/05/26 | 0.0 | 0.0 |
|
1970.0 |
RPL10.INT.NS2.01400 |
RPL10.Interior.NS2 - Control Fault Domain 4 SQ3.2 - Install Duct (LV Side) | LV Side Tie-ins | Not Started | 05/05/26 | 05/08/26 | 5.0 | 5.0 |
|
46.2 |
RPL10.INT.NS2.01430 |
RPL10.Interior.NS2 - Tie-ins - Control Fault Domain 4 SQ3.2 (including IDF) - WBS Summary | Tie-Ins NS2 Control Fault Domain 4 | Not Started | 05/05/26 | 08/17/26 | 91.2 | 91.2 |
|
16.2 |
RPL10.INT.NS3.02020 |
RPL10.Interior.NS3 - OFE - Ancillary Skids - Set / Place / Anchor (04.29.26) | OFE | Not Started | 05/05/26 | 05/08/26 | 5.0 | 5.0 |
|
137.5 |
RPL10.INT.NS4.01060 |
RPL10.Interior.NS4 - OFE - LV Skids and TopHat - Set / Place / Anchor (04.22.26) (Rev-05.04.26) | OFE | Not Started | 05/05/26 | 06/02/26 | 25.0 | 25.0 |
|
103.8 |
RPL10.INT.SSB.01270 |
RPL10.Interior.SSB - Loading Dock and Storage - Install Controls / EPMS / BMS *Separate EPMS *Whats Scope Check Trade | Loading Dock and Storage | Not Started | 05/05/26 | 05/08/26 | 5.0 | 5.0 |
|
151.2 |
RPL10.INT.SSBC.01390 |
RPL10.Interior.SSB-Corridor - BoW - Install Battery | Balance of Walls & OverHead | Not Started | 05/05/26 | 05/18/26 | 12.5 | 12.5 |
|
42.5 |
RPL10.MCUP.LP1.2100 |
RPL10.MCUP.Loop 1 - Install Exterior Signage | Hardscape and Landscape | Not Started | 05/05/26 | 05/18/26 | 12.5 | 12.5 |
|
488.8 |
RPL10.MCUP.LP2.1520 |
RPL10.MCUP.Loop 2 - Install Hardscape and Landscape - WBS Summary | Hardscape and Landscape | Not Started | 05/05/26 | 06/16/26 | 37.5 | 37.5 |
|
463.8 |
RPL10.MCUP.LP2.1540 |
RPL10.MCUP.Loop 2 - Install Sleeves MEPL | Hardscape and Landscape | Not Started | 05/05/26 | 05/11/26 | 6.2 | 6.2 |
|
477.5 |
RPL10.MCUP.LP2.1640 |
RPL10.MCUP.Loop 2 - Install Site Grading for Paving *Start 05/08 | Hardscape and Landscape | Not Started | 05/05/26 | 05/26/26 | 18.8 | 18.8 |
|
463.8 |
RPL10.MCUP.LP2.1760 |
RPL10.MCUP.Loop 2 - Install Lighting | Hardscape and Landscape | Not Started | 05/05/26 | 05/15/26 | 11.2 | 11.2 |
|
477.5 |
RPL10.MCUP.LP2.1940 |
RPL10.MCUP.Loop 2 - Tie-in EPMS #8 | Tie-Ins EPMS | Not Started | 05/05/26 | 05/13/26 | 8.8 | 8.8 |
|
130.0 |
RPL10.WP2.CMDF1.1010 |
RPL10.Conn CMDF1 Install Cabling (Pull, Splice & terminate) | Cabling | Not Started | 05/05/26 | 05/08/26 | 5.0 | 5.0 |
|
171.2 |
RPL10.WP2.CMDF2.1020 |
RPL10.Conn CMDF2 Install Cabling (Pull, Splice & terminate) | Cabling | Not Started | 05/05/26 | 05/11/26 | 6.2 | 6.2 |
|
170.0 |
RPL10.WP2.MDF1.1240 |
RPL10.Conn C.MDF1 <> GS.MDF1 - Pull, Splice, Terminate & Test | Cabling | Not Started | 05/05/26 | 05/08/26 | 5.0 | 5.0 |
|
173.8 |
RPL10.WP2.MDF2.1240 |
RPL10.Conn C.MDF2 <> GS.MDF2 - Pull, Splice, Terminate & Test | Cabling | Not Started | 05/05/26 | 05/08/26 | 5.0 | 5.0 |
|
173.8 |
RPL10.EY.EF2.01220 |
RPL10.EY.EF2 - Install RPL-3 Total Road Closure For Fiber Supprt Platform | Fiber Support Platform - RPL-3 | Not Started | 05/06/26 | 07/16/26 | 62.5 | 62.5 |
|
247.5 |
RPL10.EY.EF2.01380 |
RPL10.EY.EF2 - Install BMS Tie-ins | Tie-ins | Not Started | 05/06/26 | 05/12/26 | 6.2 | 6.2 |
|
150.0 |
RPL10.EY.NS2.01280 |
RPL10.EY.NS2 - Install BMS Tie-ins | Tie-ins | Not Started | 05/06/26 | 05/19/26 | 12.5 | 12.5 |
|
31.2 |
RPL10.INT.ENDC.01060 |
RPL10.Interior.End-Corridor - Balance of Walls & Overhead (Restroom, Janitor, Fire Riser, Humidifier) - WBS Summary | Balance of Walls & Overhead | Not Started | 05/06/26 | 10/02/26 | 131.2 | 131.2 |
|
190.0 |
RPL10.INT.ENDC.6420 |
RPL10.Interior.End-Corridor - BoW - BoW Frame Priority Soffit and Hang Drywall | Balance of Walls & Overhead | Not Started | 05/06/26 | 05/11/26 | 5.0 | 5.0 |
|
148.8 |
RPL10.INT.NS1.01205 |
RPL10.Interior.NS1 - MES Skids - EPMS Tie-Ins | NS1 - MES Skids | Not Started | 05/06/26 | 06/09/26 | 30.0 | 30.0 |
|
161.2 |
RPL10.INT.NS2.01790 |
RPL10.Interior.NS2 - OFE - Control Fault Domain 1 SQ6.2 (LV Side Aisle, HAC, Mech Side Aisle) | OFE NS2 Control Fault Domain 1 | Not Started | 05/06/26 | 09/03/26 | 106.2 | 106.2 |
|
-27.5 |
RPL10.INT.NS2.02745 |
RPL10.Interior.NS2 - OFE - Control Fault Domain 1 SQ6.2 (LV Side Aisle) | OFE NS2 Control Fault Domain 1 | Not Started | 05/06/26 | 05/11/26 | 5.0 | 5.0 |
|
57.5 |
RPL10.INT.SSB.01390 |
RPL10.Interior.SSB - BoW - Plumbing Trim Out | Balance of Walls and OverHead | Not Started | 05/06/26 | 05/12/26 | 6.2 | 6.2 |
|
215.0 |
RPL10.INT.SSB.01400 |
RPL10.Interior.SSB - BoW - Fire Life Safety Trim Out / Fire Alarm Trim Out | Balance of Walls and OverHead | Not Started | 05/06/26 | 05/14/26 | 8.8 | 8.8 |
|
215.0 |
RPL10.INT.SSBC.03060 |
RPL10.Interior.SSB-Corridor - BoW - Asset Tagging | Balance of Walls & OverHead | Not Started | 05/06/26 | 05/12/26 | 6.2 | 6.2 |
|
53.8 |
RPL10.WP4.027440 |
RPL10.Conn NS1.CFD5.48<>06-10 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] | Prefab | Not Started | 05/06/26 | 05/08/26 | 3.8 | 3.8 |
|
148.8 |