Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260412.xer
· Uploaded Apr 16, 2026 12:51 PM
· 8408 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
0
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL.GF.D.G4620.XG |
Rack & Cabinets Complete - DHB - RPL6 | Give Milestones (XREFs) | Not Started | 05/07/26 | 05/07/26 | 0.0 | 0.0 |
|
455.0 |
RPL10.INT.CTRC.01220 |
RPL10.Interior.Center-Corridor - BoW - Install Controls / EPMS / BMS OH and In-wall *EPMS Separate Activty | Balance of Walls & OverHead | Not Started | 05/07/26 | 05/12/26 | 5.0 | 5.0 |
|
123.8 |
RPL10.INT.NS1.01390 |
RPL10.Interior.NS1 - Control Fault Domain 5 SQ2.1 - Pull BMS from panel to devices | Remaining Tie-ins post Mech Side Aisle install | Not Started | 05/07/26 | 06/04/26 | 25.0 | 25.0 |
|
51.2 |
RPL10.INT.NS1.01400 |
RPL10.Interior.NS1 - Control Fault Domain 5 SQ2.1 - Pull EPMS from panel to devices | Remaining Tie-ins post Mech Side Aisle install | Not Started | 05/07/26 | 06/04/26 | 25.0 | 25.0 |
|
51.2 |
RPL10.INT.NS1.01410 |
RPL10.Interior.NS1 - Control Fault Domain 5 SQ2.1 - Set UPS and Panel (2) | Remaining Tie-ins post Mech Side Aisle install | Not Started | 05/07/26 | 06/04/26 | 25.0 | 25.0 |
|
30.0 |
RPL10.INT.NS2.01510 |
RPL10.Interior.NS2 - Control Fault Domain 4 SQ3.2 - Install LV Side Aisle HAC Busway | LV Side Tie-ins | Not Started | 05/07/26 | 05/12/26 | 5.0 | 5.0 |
|
76.2 |
RPL10.INT.NS4.01090 |
RPL10.Interior.NS4 - LV Skids and TopHat Tie-ins (LOE) | NS4 - LV Skids and TopHat | Not Started | 05/07/26 | 06/12/26 | 32.5 | 32.5 |
|
165.0 |
RPL10.INT.NS4.01091 |
RPL10.Interior.NS4 - LV Skids and TopHat - Set & Anchor Interconnects | NS4 - LV Skids and TopHat | Not Started | 05/07/26 | 06/02/26 | 22.5 | 22.5 |
|
165.0 |
RPL10.INT.SSB.01860 |
RPL10.Interior.SSB - Kitchen & Office Spaces - Flooring | Kitchen and Office Spaces | Not Started | 05/07/26 | 05/15/26 | 8.8 | 8.8 |
|
153.8 |
RPL10.INT.SSB.02560 |
RPL10.Interior.SSB - BoW - ACT - Device Tiles | Balance of Walls and OverHead | Not Started | 05/07/26 | 05/15/26 | 8.8 | 8.8 |
|
160.0 |
RPL10.INT.SSB.02580 |
RPL10.Interior.SSB - BoW - ACT - MEP Devices | Balance of Walls and OverHead | Not Started | 05/07/26 | 05/15/26 | 8.8 | 8.8 |
|
160.0 |
RPL10.INT.SSB.04380 |
RPL10.Interior.SSB - BoW - Install Lights in ACT Ceiling | Balance of Walls and OverHead | Not Started | 05/07/26 | 05/11/26 | 3.0 | 3.0 |
|
200.8 |
RPL10.SSB.BB.1130 |
RPL10.Ext.Build Back.SSB - LO #5 - Hang, Tape and Finish | Build Back Exterior Leave Out Wall #5 (East SSB) | Not Started | 05/07/26 | 05/13/26 | 6.2 | 6.2 |
|
441.2 |
RPL10.WP2.01050 |
RPL10.Conn SSB - Install GS Cabling - Misc Scope (ME to Confirm) | WP2 (GS/CARRIER/SFZ - INF, CAB [ISP/OSP], NET) | Not Started | 05/07/26 | 05/20/26 | 12.5 | 12.5 |
|
71.2 |
RPL10.WP2.GSIDF.1680 |
RPL10.Conn IDF Huts - (GSMDF to GSIDF) NS4 N43 WBS Summary | GSIDFN43 | Not Started | 05/07/26 | 06/15/26 | 33.8 | 33.8 |
|
465.0 |
RPL10.WP2.GSIDF.1700 |
RPL10.Conn GSIDFN43 Set Infrastructure (Racks, Waterfalls etc.) | Infrastructure | Not Started | 05/07/26 | 05/13/26 | 6.2 | 6.2 |
|
217.5 |
RPL10.WP2.GSIDF.1920 |
RPL10.Conn IDF Huts - (GSMDF to GSIDF) NS3 N33 WBS Summary | GSIDFN33 | Not Started | 05/07/26 | 06/15/26 | 33.8 | 33.8 |
|
465.0 |
RPL10.WP2.GSIDF.1940 |
RPL10.Conn GSIDFN33 Set Infrastructure (Racks, Waterfalls etc.) | Infrastructure | Not Started | 05/07/26 | 05/13/26 | 6.2 | 6.2 |
|
217.5 |
RPL10.WP4.027240 |
RPL10.Conn NS1.CFD6.48<>06-10 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] | Prefab | Not Started | 05/07/26 | 05/11/26 | 3.8 | 3.8 |
|
147.5 |
RPL10.WP4.028420 |
RPL10.Conn NS2.CFD6.48<>03-05 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] | Prefab | Not Started | 05/07/26 | 05/08/26 | 2.5 | 2.5 |
|
156.2 |
RPL10.WP4.NS2.01080 |
RPL10.Conn NS2.CFD6 Network - WBS Summary | Network | Not Started | 05/07/26 | 12/24/26 | 200.0 | 200.0 |
|
23.8 |
RPL10.CTRC.BB.3235 |
RPL10.Int.Build Back.Center-Corr - Interior Leave Out (Center Corridor) #12, #13, WBS Summary | Build Back Interior Leave Out Wall #12 #13 (Center Corr) | Not Started | 05/08/26 | 06/29/26 | 45.0 | 45.0 |
|
160.0 |
RPL10.CTRC.BB.3255 |
RPL10.Int.Build Back.Center-Corr - LO #12,13 - MEPF - In Wall, OH, Lowside, Lights | Build Back Interior Leave Out Wall #12 #13 (Center Corr) | Not Started | 05/08/26 | 06/05/26 | 25.0 | 25.0 |
|
160.0 |
RPL10.EY.EF1.01250 |
RPL10.EY.EF1 - Install Sleeves MEPL | Hardscape and Landscape | Not Started | 05/08/26 | 05/14/26 | 6.2 | 6.2 |
|
453.8 |
RPL10.EY.EF1.01260 |
RPL10.EY.EF1 - Install Hardscape and Landscape - WBS Summary | Hardscape and Landscape | Not Started | 05/08/26 | 08/25/26 | 95.0 | 95.0 |
|
402.5 |
RPL10.EY.ENDC.01145 |
RPL10.EY.End - Install Mechanical Tie-ins | Tie-ins | Not Started | 05/08/26 | 05/21/26 | 12.5 | 12.5 |
|
276.2 |
RPL10.INT.EF1.01170 |
RPL10.Interior.EF1 - CFCI - Set South CRAH Units | OFE | Not Started | 05/08/26 | 05/14/26 | 6.2 | 6.2 |
|
118.8 |
RPL10.INT.EF2.01150 |
RPL10.Interior.EF2 - CFCI - Set North CRAH Units | OFE | Not Started | 05/08/26 | 05/14/26 | 6.2 | 6.2 |
|
130.0 |
RPL10.INT.NS2.01140 |
RPL10.Interior.NS2 - Control Fault Domain 6 SQ1.2 - Install Vesda / FA | Remaining Tie-ins post Mech Side Aisle install | Not Started | 05/08/26 | 06/05/26 | 25.0 | 25.0 |
|
28.8 |
RPL10.INT.NS2.01150 |
RPL10.Interior.NS2 - Control Fault Domain 6 SQ1.2 - Install FW | Remaining Tie-ins post Mech Side Aisle install | Not Started | 05/08/26 | 06/05/26 | 25.0 | 25.0 |
|
16.2 |
RPL10.INT.NS2.01520 |
RPL10.Interior.NS2 - Control Fault Domain 4 SQ3.2 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 05/08/26 | 05/13/26 | 5.0 | 5.0 |
|
98.8 |
RPL10.INT.NS2.02180 |
RPL10.Interior.NS2 - Control Fault Domain 6 SQ1.2 - Install TW | Remaining Tie-ins post Mech Side Aisle install | Not Started | 05/08/26 | 06/05/26 | 25.0 | 25.0 |
|
16.2 |
RPL10.INT.NS2.02805 |
RPL10.Interior.NS2 - Control Fault Domain 6 SQ1.2 - Install Duct (MES Side) | Remaining Tie-ins post Mech Side Aisle install | Not Started | 05/08/26 | 06/05/26 | 25.0 | 25.0 |
|
16.2 |
RPL10.WP2.CMDF1.1100 |
RPL10.Conn CMDF1 Includes Rack/ Stack/ Patch | Network | Not Started | 05/08/26 | 05/12/26 | 3.8 | 3.8 |
|
171.2 |
DCC.B10.3527 |
[NWB] Cabling Start : Front End Production Cabling [NWS 1] | Connectivity | Not Started | 05/11/26 | 05/11/26 | 0.0 | 0.0 |
|
1966.2 |
DCC.B10.3529 |
[NWB] Cabling Start : Back End Production Cabling [NWS 1] | Connectivity | Not Started | 05/11/26 | 05/11/26 | 0.0 | 0.0 |
|
1966.2 |
GCD.RPL10.1827 |
Delivery of RMU - (First Delivery) - RPL10 - NS43 | Construction Milestones | Not Started | 05/11/26 | 05/11/26 | 0.0 | 0.0 |
|
107.5 |
JCL.C.1380 |
RPL10 - Cost Risk LOE-19 Connectivity Package 3A - Front End Infra & Cabling (OSP,OH) | Cost LOEs | Not Started | 05/11/26 | 08/18/26 | 87.5 | 87.5 |
|
128.8 |
RPL.GF.D.N0280.XR |
Fiber Pulls, Test & Term All Prod EF to EF Complete RPL 10 to AI1 | Connectivity (XREFs) | Not Started | 05/11/26 | 05/11/26 | 0.0 | 0.0 |
|
183.8 |
RPL10.CX.1180 |
RPL10.CX.BLDG - L3, L4, IST - WBS Summary | Commissioning | Not Started | 05/11/26 | 07/12/27 | 366.2 | 366.2 |
|
1587.5 |
RPL10.CX.MCUP.01000 |
RPL10.CX.mCup Loop 1 - L3, L4, IST - WBS Summary | mCup Loop 1 (mCup #1,#3,#5,#7) | Not Started | 05/11/26 | 08/11/26 | 81.2 | 81.2 |
|
415.0 |
RPL10.CX.MCUP.01350 |
RPL10.CX.mCup Loop 1 - L3/L4 - mCUP - Flush and Fill - Temp Flush Skid (PR) | Fill and Flush | Not Started | 05/11/26 | 05/15/26 | 6.2 | 6.2 |
|
50.0 |
RPL10.EY.NS1.01330 |
RPL10.EY.NS1 - Install Early EY Paving | Hardscape and Landscape | Not Started | 05/11/26 | 05/15/26 | 6.2 | 6.2 |
|
188.8 |
RPL10.EY.SSB.01240 |
RPL10.EY.SSB - Install BMS Tie-ins | Tie-ins | Not Started | 05/11/26 | 06/01/26 | 18.8 | 18.8 |
|
126.2 |
RPL10.EY.SSB.01260 |
RPL10.EY.SSB - L2 Checklist Completion | Tie-ins | Not Started | 05/11/26 | 05/22/26 | 12.5 | 12.5 |
|
23.8 |
RPL10.INT.EF1.01430 |
RPL10.Interior.EF1 - EF1 East - Pull EPMS / BMS from panel to devices | East EF-1 | Not Started | 05/11/26 | 05/15/26 | 6.2 | 6.2 |
|
135.0 |
RPL10.INT.EF1.01440 |
RPL10.Interior.EF1 - EF1 East - Install copper from GS.IDF to BMS and EPMS panels | East EF-1 | Not Started | 05/11/26 | 05/15/26 | 6.2 | 6.2 |
|
135.0 |
RPL10.INT.EF1.01450 |
RPL10.Interior.EF1 - EF1 East - Fire Life Safety | East EF-1 | Not Started | 05/11/26 | 05/19/26 | 8.8 | 8.8 |
|
200.0 |
RPL10.INT.NS1.01430 |
RPL10.Interior.NS1 - Control Fault Domain 6 SQ1.1 - L2 Checklist Completion | Remaining Tie-ins post Mech Side Aisle install | Not Started | 05/11/26 | 06/08/26 | 25.0 | 25.0 |
|
40.0 |
RPL10.INT.NS2.01540 |
RPL10.Interior.NS2 - Control Fault Domain 3 SQ4.2 - Install Duct (LV Side) | LV Side Tie-ins | Not Started | 05/11/26 | 05/14/26 | 5.0 | 5.0 |
|
51.2 |
RPL10.INT.NS2.01570 |
RPL10.Interior.NS2 - Tie-ins - Control Fault Domain 3 SQ4.2 - WBS Summary | Tie-Ins NS2 Control Fault Domain 3 | Not Started | 05/11/26 | 09/08/26 | 105.0 | 105.0 |
|
23.8 |
RPL10.INT.NS3.01100 |
RPL10.Interior.NS3 - Tie-ins - WBS Summary | Tie-Ins | Not Started | 05/11/26 | 01/26/27 | 222.5 | 222.5 |
|
120.0 |
RPL10.INT.NS3.01110 |
RPL10.Interior.NS3 - MES Skids Tie-ins (LOE) | NS3 - MES Skids | Not Started | 05/11/26 | 08/04/26 | 75.0 | 75.0 |
|
240.0 |
RPL10.INT.NS3.01111 |
RPL10.Interior.NS3 - MES Skids - Set & Anchor Interconnects | NS3 - MES Skids | Not Started | 05/11/26 | 06/12/26 | 30.0 | 30.0 |
|
123.8 |
RPL10.INT.SSB.01300 |
RPL10.Interior.SSB - Loading Dock and Storage - Install Fire Life Safety / Fire Alarm | Loading Dock and Storage | Not Started | 05/11/26 | 05/19/26 | 8.8 | 8.8 |
|
151.2 |
RPL10.MCUP.LP1.2060 |
RPL10.MCUP.Loop 1 - Tie-in - Electrical L2 Checklist Completion | Tie-Ins Electrical | Not Started | 05/11/26 | 05/21/26 | 11.2 | 11.2 |
|
17.5 |
RPL10.WP2.01040 |
RPL10.Conn SSB - Construction Cx Server Ready - At mCup | WP2 (GS/CARRIER/SFZ - INF, CAB [ISP/OSP], NET) | Not Started | 05/11/26 | 05/11/26 | 0.0 | 0.0 |
|
28.8 |
RPL10.WP2.CMDF1.1020 |
RPL10.Conn CMDF1 Install & Test Network (FIM) | Network | Not Started | 05/11/26 | 05/15/26 | 6.2 | 6.2 |
|
203.8 |
RPL10.WP2.CMDF2.1060 |
RPL10.Conn CMDF2 Includes Rack/ Stack/ Patch | Network | Not Started | 05/11/26 | 05/13/26 | 3.8 | 3.8 |
|
170.0 |
RPL10.WP2.GSIDF.2060 |
RPL10.Conn GSIDFNX01 Install Cabling (Pull, Splice & terminate) | Cabling | Not Started | 05/11/26 | 05/15/26 | 6.2 | 6.2 |
|
227.5 |
RPL10.WP2.GSIDF.2140 |
RPL10.Conn GSIDFNX02 Install Cabling (Pull, Splice & terminate) | Cabling | Not Started | 05/11/26 | 05/15/26 | 6.2 | 6.2 |
|
30.0 |
RPL10.WP2.GSIDF.2860 |
RPL10.Conn GSIDFNX11 Install & Test Network (FIM) | Network | Not Started | 05/11/26 | 05/13/26 | 3.8 | 3.8 |
|
233.8 |
RPL10.WP2.GSIDF.2940 |
RPL10.Conn GSIDFNX12 Install & Test Network (FIM) | Network | Not Started | 05/11/26 | 05/13/26 | 3.8 | 3.8 |
|
233.8 |
RPL10.WP2.GSIDF.3480 |
RPL10.Conn GSIDFNX11 Install Copper, WAPs, Security Camera & Access Control | Cabling | Not Started | 05/11/26 | 05/13/26 | 3.8 | 3.8 |
|
492.5 |
RPL10.WP2.GSIDF.3500 |
RPL10.Conn GSIDFNX12 Install Copper, WAPs, Security Camera & Access Control | Cabling | Not Started | 05/11/26 | 05/22/26 | 12.5 | 12.5 |
|
483.8 |
RPL10.WP3A.EF.01020 |
RPL10.Conn EF1F Infrasturcture 1 (Racks & Vertical Cable Manager, Ladder Racks) | Infrastructure & Cabling | Not Started | 05/11/26 | 06/08/26 | 25.0 | 25.0 |
|
121.2 |
RPL10.WP3A.EF.02000 |
RPL10.Conn EF1F OSP Pathway - WBS Summary | Infrastructure & Cabling | Not Started | 05/11/26 | 06/22/26 | 37.5 | 37.5 |
|
208.8 |
RPL10.WP4.027460 |
RPL10.Conn NS1.CFD5.48<>11-15 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] | Prefab | Not Started | 05/11/26 | 05/15/26 | 6.2 | 6.2 |
|
148.8 |
RPL10.WP4.028440 |
RPL10.Conn NS2.CFD6.48<>06-10 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] | Prefab | Not Started | 05/11/26 | 05/13/26 | 3.8 | 3.8 |
|
156.2 |
RPL.GF.D.N0250.XR |
Fiber Pulls, Test & Term All Prod EF to EF Complete RPL 10 to RPL6 | Connectivity (XREFs) | Not Started | 05/12/26 | 05/12/26 | 0.0 | 0.0 |
|
232.5 |
RPL10.CFCI.5110 |
RPL10 - Submittal Rvw/App'l - Carpet | (CFCI) Div. 09 - Carpet | Not Started | 05/12/26 | 06/09/26 | 25.0 | 25.0 |
|
146.2 |
RPL10.CFCI.5140 |
RPL10- Fabricate / Deliver -Epoxy Flooring (Spec 09 67 23) | (CFCI) Div. 09 - Epoxy Flooring | Not Started | 05/12/26 | 06/09/26 | 25.0 | 25.0 |
|
171.2 |
RPL10.CFCI.5260 |
RPL10 - Fabricate / Deliver - Specialities | (CFCI) Div. 10 - Specialities | Not Started | 05/12/26 | 06/09/26 | 25.0 | 25.0 |
|
113.8 |
RPL10.EY.NS4.01220 |
RPL10.EY.NS4 - Install MV, RMUs & Electrical Panels (15) | OFE | Not Started | 05/12/26 | 06/09/26 | 25.0 | 25.0 |
|
107.5 |
RPL10.EY.NS4.01230 |
RPL10.EY.NS4 - OFE - MV - WBS Summary | OFE | Not Started | 05/12/26 | 06/30/26 | 43.8 | 43.8 |
|
101.2 |
RPL10.INT.CTRC.01650 |
RPL10.Interior.Center-Corridor - BoW - Tape, Float and Paint BoW | Balance of Walls & OverHead | Not Started | 05/12/26 | 05/15/26 | 5.0 | 5.0 |
|
110.0 |
RPL10.INT.CTRC.07720 |
RPL10.Interior.Center-Corridor - Priority - Install Exterior Wall Drywall, Tape, Float, Paint (Remaining) | Priority Walls & OverHead | Not Started | 05/12/26 | 05/14/26 | 3.8 | 3.8 |
|
111.2 |
RPL10.INT.ENDC.6440 |
RPL10.Interior.End-Corridor - BoW - BoW Tape, Float and Paint Priority Soffit, Fire Safing Both Sides | Balance of Walls & Overhead | Not Started | 05/12/26 | 05/18/26 | 6.2 | 6.2 |
|
148.8 |
RPL10.INT.NS2.01114 |
RPL10.Interior.NS2 - MES Skids - BMS Tie-Ins ( 2 per day) | NS2 - MES Skids | Not Started | 05/12/26 | 06/15/26 | 30.0 | 30.0 |
|
157.5 |
RPL10.INT.NS3.01060 |
RPL10.Interior.NS3 - OFE - LV Skids and TopHat - Set / Place / Anchor (04.30.26) (Rev-05.11.26) | OFE | Not Started | 05/12/26 | 06/09/26 | 25.0 | 25.0 |
|
101.2 |
RPL10.INT.NS4.01112 |
RPL10.Interior.NS4 - MES Skids - Piping Tie-Ins & Inspections | NS4 - MES Skids | Not Started | 05/12/26 | 06/15/26 | 30.0 | 30.0 |
|
135.0 |
RPL10.MCUP.LP2.1860 |
RPL10.MCUP.Loop 2 - Install Mcup Paving *Start 05/15 | Hardscape and Landscape | Not Started | 05/12/26 | 06/02/26 | 18.8 | 18.8 |
|
463.8 |
RPL10.WP2.CMDF2.1040 |
RPL10.Conn CMDF2 Install & Test Network (FIM) | Network | Not Started | 05/12/26 | 05/18/26 | 6.2 | 6.2 |
|
202.5 |
RPL10.WP4.027260 |
RPL10.Conn NS1.CFD6.48<>11-15 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] | Prefab | Not Started | 05/12/26 | 05/18/26 | 6.2 | 6.2 |
|
147.5 |
JCL.C.1280 |
RPL10 - Cost Risk LOE-15 Security Systems | Cost LOEs | Not Started | 05/13/26 | 01/12/27 | 208.8 | 208.8 |
|
78.8 |
RPL.10.D.X33X7.XR |
Cable Pull to Concrete Pad - RPL10 NS4 Loop 1 & 2 | Power (XREFs) | Not Started | 05/13/26 | 05/13/26 | 0.0 | 0.0 |
|
33.8 |
RPL.10.D.X4420.XR |
Natural Gas Available for Fill/Flush Cx - Utility connections (L3/L4) | Water / Gas Available (XREFs) | Not Started | 05/13/26 | 05/13/26 | 0.0 | 0.0 |
|
51.2 |
RPL.GF.D.G4620.XG |
Rack & Cabinets Complete - DHB - RPL6 | Give Milestones (XREFs) | Not Started | 05/13/26 | 05/13/26 | 0.0 | 0.0 |
|
227.0 |
RPL10.EY.EF2.01410 |
RPL10.EY.EF2 - Install Sleeves MEPL | Hardscape and Landscape | Not Started | 05/13/26 | 05/19/26 | 6.2 | 6.2 |
|
443.8 |
RPL10.EY.EF2.01420 |
RPL10.EY.EF2 - Early L2 Checklist Completion | Tie-ins | Not Started | 05/13/26 | 05/27/26 | 12.5 | 12.5 |
|
150.0 |
RPL10.EY.EF2.01430 |
RPL10.EY.EF2 - Install Hardscape and Landscape - WBS Summary | Hardscape and Landscape | Not Started | 05/13/26 | 09/01/26 | 97.5 | 97.5 |
|
396.2 |
RPL10.EY.NS2.01290 |
RPL10.EY.NS2 - MV Loop 1 - L2 Checklist Completion | Tie-ins | Not Started | 05/13/26 | 05/27/26 | 12.5 | 12.5 |
|
31.2 |
RPL10.INT.CTRC.01170 |
RPL10.Interior.Center-Corridor - BoW - Install Doors Frame | Balance of Walls & OverHead | Not Started | 05/13/26 | 05/19/26 | 6.2 | 6.2 |
|
123.8 |
RPL10.INT.NS2.01650 |
RPL10.Interior.NS2 - Control Fault Domain 3 SQ4.2 - Install LV Side Aisle HAC Busway | LV Side Tie-ins | Not Started | 05/13/26 | 05/18/26 | 5.0 | 5.0 |
|
81.2 |
RPL10.OFCI.6860 |
OFCI - Delivery ROJ: FE Fiber for CFD NS1.4 (ROJ ) (RVCD ) | NS1 | Not Started | 05/13/26 | 06/03/26 | 18.8 | 18.8 |
|
68.8 |
RPL10.SKN.SSB.01070 |
RPL10.SKIN.SSB - Install Security | Glazing, Doors and Ext Devices | Not Started | 05/13/26 | 05/14/26 | 2.5 | 2.5 |
|
177.5 |
DCC.B10.3200 |
[NWB] CorpNet/Security/FacNet Ready [GS-CORE] | Connectivity | Not Started | 05/14/26 | 05/14/26 | 0.0 | 0.0 |
|
170.0 |
DCC.B10.3225 |
[NWB] CorpNet/Security/FacNet Ready [NWS 1] | Connectivity | Not Started | 05/14/26 | 05/14/26 | 0.0 | 0.0 |
|
233.8 |
DCC.B10.3235 |
[NWB] CorpNet/Security/FacNet Ready [NWS 2] | Connectivity | Not Started | 05/14/26 | 05/14/26 | 0.0 | 0.0 |
|
233.8 |
RPL.GF.D.N0115.XR |
2 of 4 Fiber Test Complete (CAV1/4) MMH to GS.EF1/ Prod.EF1F | Connectivity (XREFs) | Not Started | 05/14/26 | 05/14/26 | 0.0 | 0.0 |
|
170.0 |