Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260412.xer · Uploaded Apr 16, 2026 12:51 PM · 8408 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
0
Completed
0
In Progress
0
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL.GF.D.G4620.XG Rack & Cabinets Complete - DHB - RPL6 Give Milestones (XREFs) Not Started 05/07/26 05/07/26 0.0 0.0
0%
455.0
RPL10.INT.CTRC.01220 RPL10.Interior.Center-Corridor - BoW - Install Controls / EPMS / BMS OH and In-wall *EPMS Separate Activty Balance of Walls & OverHead Not Started 05/07/26 05/12/26 5.0 5.0
0%
123.8
RPL10.INT.NS1.01390 RPL10.Interior.NS1 - Control Fault Domain 5 SQ2.1 - Pull BMS from panel to devices Remaining Tie-ins post Mech Side Aisle install Not Started 05/07/26 06/04/26 25.0 25.0
0%
51.2
RPL10.INT.NS1.01400 RPL10.Interior.NS1 - Control Fault Domain 5 SQ2.1 - Pull EPMS from panel to devices Remaining Tie-ins post Mech Side Aisle install Not Started 05/07/26 06/04/26 25.0 25.0
0%
51.2
RPL10.INT.NS1.01410 RPL10.Interior.NS1 - Control Fault Domain 5 SQ2.1 - Set UPS and Panel (2) Remaining Tie-ins post Mech Side Aisle install Not Started 05/07/26 06/04/26 25.0 25.0
0%
30.0
RPL10.INT.NS2.01510 RPL10.Interior.NS2 - Control Fault Domain 4 SQ3.2 - Install LV Side Aisle HAC Busway LV Side Tie-ins Not Started 05/07/26 05/12/26 5.0 5.0
0%
76.2
RPL10.INT.NS4.01090 RPL10.Interior.NS4 - LV Skids and TopHat Tie-ins (LOE) NS4 - LV Skids and TopHat Not Started 05/07/26 06/12/26 32.5 32.5
0%
165.0
RPL10.INT.NS4.01091 RPL10.Interior.NS4 - LV Skids and TopHat - Set & Anchor Interconnects NS4 - LV Skids and TopHat Not Started 05/07/26 06/02/26 22.5 22.5
0%
165.0
RPL10.INT.SSB.01860 RPL10.Interior.SSB - Kitchen & Office Spaces - Flooring Kitchen and Office Spaces Not Started 05/07/26 05/15/26 8.8 8.8
0%
153.8
RPL10.INT.SSB.02560 RPL10.Interior.SSB - BoW - ACT - Device Tiles Balance of Walls and OverHead Not Started 05/07/26 05/15/26 8.8 8.8
0%
160.0
RPL10.INT.SSB.02580 RPL10.Interior.SSB - BoW - ACT - MEP Devices Balance of Walls and OverHead Not Started 05/07/26 05/15/26 8.8 8.8
0%
160.0
RPL10.INT.SSB.04380 RPL10.Interior.SSB - BoW - Install Lights in ACT Ceiling Balance of Walls and OverHead Not Started 05/07/26 05/11/26 3.0 3.0
0%
200.8
RPL10.SSB.BB.1130 RPL10.Ext.Build Back.SSB - LO #5 - Hang, Tape and Finish Build Back Exterior Leave Out Wall #5 (East SSB) Not Started 05/07/26 05/13/26 6.2 6.2
0%
441.2
RPL10.WP2.01050 RPL10.Conn SSB - Install GS Cabling - Misc Scope (ME to Confirm) WP2 (GS/CARRIER/SFZ - INF, CAB [ISP/OSP], NET) Not Started 05/07/26 05/20/26 12.5 12.5
0%
71.2
RPL10.WP2.GSIDF.1680 RPL10.Conn IDF Huts - (GSMDF to GSIDF) NS4 N43 WBS Summary GSIDFN43 Not Started 05/07/26 06/15/26 33.8 33.8
0%
465.0
RPL10.WP2.GSIDF.1700 RPL10.Conn GSIDFN43 Set Infrastructure (Racks, Waterfalls etc.) Infrastructure Not Started 05/07/26 05/13/26 6.2 6.2
0%
217.5
RPL10.WP2.GSIDF.1920 RPL10.Conn IDF Huts - (GSMDF to GSIDF) NS3 N33 WBS Summary GSIDFN33 Not Started 05/07/26 06/15/26 33.8 33.8
0%
465.0
RPL10.WP2.GSIDF.1940 RPL10.Conn GSIDFN33 Set Infrastructure (Racks, Waterfalls etc.) Infrastructure Not Started 05/07/26 05/13/26 6.2 6.2
0%
217.5
RPL10.WP4.027240 RPL10.Conn NS1.CFD6.48<>06-10 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] Prefab Not Started 05/07/26 05/11/26 3.8 3.8
0%
147.5
RPL10.WP4.028420 RPL10.Conn NS2.CFD6.48<>03-05 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] Prefab Not Started 05/07/26 05/08/26 2.5 2.5
0%
156.2
RPL10.WP4.NS2.01080 RPL10.Conn NS2.CFD6 Network - WBS Summary Network Not Started 05/07/26 12/24/26 200.0 200.0
0%
23.8
RPL10.CTRC.BB.3235 RPL10.Int.Build Back.Center-Corr - Interior Leave Out (Center Corridor) #12, #13, WBS Summary Build Back Interior Leave Out Wall #12 #13 (Center Corr) Not Started 05/08/26 06/29/26 45.0 45.0
0%
160.0
RPL10.CTRC.BB.3255 RPL10.Int.Build Back.Center-Corr - LO #12,13 - MEPF - In Wall, OH, Lowside, Lights Build Back Interior Leave Out Wall #12 #13 (Center Corr) Not Started 05/08/26 06/05/26 25.0 25.0
0%
160.0
RPL10.EY.EF1.01250 RPL10.EY.EF1 - Install Sleeves MEPL Hardscape and Landscape Not Started 05/08/26 05/14/26 6.2 6.2
0%
453.8
RPL10.EY.EF1.01260 RPL10.EY.EF1 - Install Hardscape and Landscape - WBS Summary Hardscape and Landscape Not Started 05/08/26 08/25/26 95.0 95.0
0%
402.5
RPL10.EY.ENDC.01145 RPL10.EY.End - Install Mechanical Tie-ins Tie-ins Not Started 05/08/26 05/21/26 12.5 12.5
0%
276.2
RPL10.INT.EF1.01170 RPL10.Interior.EF1 - CFCI - Set South CRAH Units OFE Not Started 05/08/26 05/14/26 6.2 6.2
0%
118.8
RPL10.INT.EF2.01150 RPL10.Interior.EF2 - CFCI - Set North CRAH Units OFE Not Started 05/08/26 05/14/26 6.2 6.2
0%
130.0
RPL10.INT.NS2.01140 RPL10.Interior.NS2 - Control Fault Domain 6 SQ1.2 - Install Vesda / FA Remaining Tie-ins post Mech Side Aisle install Not Started 05/08/26 06/05/26 25.0 25.0
0%
28.8
RPL10.INT.NS2.01150 RPL10.Interior.NS2 - Control Fault Domain 6 SQ1.2 - Install FW Remaining Tie-ins post Mech Side Aisle install Not Started 05/08/26 06/05/26 25.0 25.0
0%
16.2
RPL10.INT.NS2.01520 RPL10.Interior.NS2 - Control Fault Domain 4 SQ3.2 - Install LV Side Aisle Cable Tray LV Side Tie-ins Not Started 05/08/26 05/13/26 5.0 5.0
0%
98.8
RPL10.INT.NS2.02180 RPL10.Interior.NS2 - Control Fault Domain 6 SQ1.2 - Install TW Remaining Tie-ins post Mech Side Aisle install Not Started 05/08/26 06/05/26 25.0 25.0
0%
16.2
RPL10.INT.NS2.02805 RPL10.Interior.NS2 - Control Fault Domain 6 SQ1.2 - Install Duct (MES Side) Remaining Tie-ins post Mech Side Aisle install Not Started 05/08/26 06/05/26 25.0 25.0
0%
16.2
RPL10.WP2.CMDF1.1100 RPL10.Conn CMDF1 Includes Rack/ Stack/ Patch Network Not Started 05/08/26 05/12/26 3.8 3.8
0%
171.2
DCC.B10.3527 [NWB] Cabling Start : Front End Production Cabling [NWS 1] Connectivity Not Started 05/11/26 05/11/26 0.0 0.0
0%
1966.2
DCC.B10.3529 [NWB] Cabling Start : Back End Production Cabling [NWS 1] Connectivity Not Started 05/11/26 05/11/26 0.0 0.0
0%
1966.2
GCD.RPL10.1827 Delivery of RMU - (First Delivery) - RPL10 - NS43 Construction Milestones Not Started 05/11/26 05/11/26 0.0 0.0
0%
107.5
JCL.C.1380 RPL10 - Cost Risk LOE-19 Connectivity Package 3A - Front End Infra & Cabling (OSP,OH) Cost LOEs Not Started 05/11/26 08/18/26 87.5 87.5
0%
128.8
RPL.GF.D.N0280.XR Fiber Pulls, Test & Term All Prod EF to EF Complete RPL 10 to AI1 Connectivity (XREFs) Not Started 05/11/26 05/11/26 0.0 0.0
0%
183.8
RPL10.CX.1180 RPL10.CX.BLDG - L3, L4, IST - WBS Summary Commissioning Not Started 05/11/26 07/12/27 366.2 366.2
0%
1587.5
RPL10.CX.MCUP.01000 RPL10.CX.mCup Loop 1 - L3, L4, IST - WBS Summary mCup Loop 1 (mCup #1,#3,#5,#7) Not Started 05/11/26 08/11/26 81.2 81.2
0%
415.0
RPL10.CX.MCUP.01350 RPL10.CX.mCup Loop 1 - L3/L4 - mCUP - Flush and Fill - Temp Flush Skid (PR) Fill and Flush Not Started 05/11/26 05/15/26 6.2 6.2
0%
50.0
RPL10.EY.NS1.01330 RPL10.EY.NS1 - Install Early EY Paving Hardscape and Landscape Not Started 05/11/26 05/15/26 6.2 6.2
0%
188.8
RPL10.EY.SSB.01240 RPL10.EY.SSB - Install BMS Tie-ins Tie-ins Not Started 05/11/26 06/01/26 18.8 18.8
0%
126.2
RPL10.EY.SSB.01260 RPL10.EY.SSB - L2 Checklist Completion Tie-ins Not Started 05/11/26 05/22/26 12.5 12.5
0%
23.8
RPL10.INT.EF1.01430 RPL10.Interior.EF1 - EF1 East - Pull EPMS / BMS from panel to devices East EF-1 Not Started 05/11/26 05/15/26 6.2 6.2
0%
135.0
RPL10.INT.EF1.01440 RPL10.Interior.EF1 - EF1 East - Install copper from GS.IDF to BMS and EPMS panels East EF-1 Not Started 05/11/26 05/15/26 6.2 6.2
0%
135.0
RPL10.INT.EF1.01450 RPL10.Interior.EF1 - EF1 East - Fire Life Safety East EF-1 Not Started 05/11/26 05/19/26 8.8 8.8
0%
200.0
RPL10.INT.NS1.01430 RPL10.Interior.NS1 - Control Fault Domain 6 SQ1.1 - L2 Checklist Completion Remaining Tie-ins post Mech Side Aisle install Not Started 05/11/26 06/08/26 25.0 25.0
0%
40.0
RPL10.INT.NS2.01540 RPL10.Interior.NS2 - Control Fault Domain 3 SQ4.2 - Install Duct (LV Side) LV Side Tie-ins Not Started 05/11/26 05/14/26 5.0 5.0
0%
51.2
RPL10.INT.NS2.01570 RPL10.Interior.NS2 - Tie-ins - Control Fault Domain 3 SQ4.2 - WBS Summary Tie-Ins NS2 Control Fault Domain 3 Not Started 05/11/26 09/08/26 105.0 105.0
0%
23.8
RPL10.INT.NS3.01100 RPL10.Interior.NS3 - Tie-ins - WBS Summary Tie-Ins Not Started 05/11/26 01/26/27 222.5 222.5
0%
120.0
RPL10.INT.NS3.01110 RPL10.Interior.NS3 - MES Skids Tie-ins (LOE) NS3 - MES Skids Not Started 05/11/26 08/04/26 75.0 75.0
0%
240.0
RPL10.INT.NS3.01111 RPL10.Interior.NS3 - MES Skids - Set & Anchor Interconnects NS3 - MES Skids Not Started 05/11/26 06/12/26 30.0 30.0
0%
123.8
RPL10.INT.SSB.01300 RPL10.Interior.SSB - Loading Dock and Storage - Install Fire Life Safety / Fire Alarm Loading Dock and Storage Not Started 05/11/26 05/19/26 8.8 8.8
0%
151.2
RPL10.MCUP.LP1.2060 RPL10.MCUP.Loop 1 - Tie-in - Electrical L2 Checklist Completion Tie-Ins Electrical Not Started 05/11/26 05/21/26 11.2 11.2
0%
17.5
RPL10.WP2.01040 RPL10.Conn SSB - Construction Cx Server Ready - At mCup WP2 (GS/CARRIER/SFZ - INF, CAB [ISP/OSP], NET) Not Started 05/11/26 05/11/26 0.0 0.0
0%
28.8
RPL10.WP2.CMDF1.1020 RPL10.Conn CMDF1 Install & Test Network (FIM) Network Not Started 05/11/26 05/15/26 6.2 6.2
0%
203.8
RPL10.WP2.CMDF2.1060 RPL10.Conn CMDF2 Includes Rack/ Stack/ Patch Network Not Started 05/11/26 05/13/26 3.8 3.8
0%
170.0
RPL10.WP2.GSIDF.2060 RPL10.Conn GSIDFNX01 Install Cabling (Pull, Splice & terminate) Cabling Not Started 05/11/26 05/15/26 6.2 6.2
0%
227.5
RPL10.WP2.GSIDF.2140 RPL10.Conn GSIDFNX02 Install Cabling (Pull, Splice & terminate) Cabling Not Started 05/11/26 05/15/26 6.2 6.2
0%
30.0
RPL10.WP2.GSIDF.2860 RPL10.Conn GSIDFNX11 Install & Test Network (FIM) Network Not Started 05/11/26 05/13/26 3.8 3.8
0%
233.8
RPL10.WP2.GSIDF.2940 RPL10.Conn GSIDFNX12 Install & Test Network (FIM) Network Not Started 05/11/26 05/13/26 3.8 3.8
0%
233.8
RPL10.WP2.GSIDF.3480 RPL10.Conn GSIDFNX11 Install Copper, WAPs, Security Camera & Access Control Cabling Not Started 05/11/26 05/13/26 3.8 3.8
0%
492.5
RPL10.WP2.GSIDF.3500 RPL10.Conn GSIDFNX12 Install Copper, WAPs, Security Camera & Access Control Cabling Not Started 05/11/26 05/22/26 12.5 12.5
0%
483.8
RPL10.WP3A.EF.01020 RPL10.Conn EF1F Infrasturcture 1 (Racks & Vertical Cable Manager, Ladder Racks) Infrastructure & Cabling Not Started 05/11/26 06/08/26 25.0 25.0
0%
121.2
RPL10.WP3A.EF.02000 RPL10.Conn EF1F OSP Pathway - WBS Summary Infrastructure & Cabling Not Started 05/11/26 06/22/26 37.5 37.5
0%
208.8
RPL10.WP4.027460 RPL10.Conn NS1.CFD5.48<>11-15 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] Prefab Not Started 05/11/26 05/15/26 6.2 6.2
0%
148.8
RPL10.WP4.028440 RPL10.Conn NS2.CFD6.48<>06-10 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] Prefab Not Started 05/11/26 05/13/26 3.8 3.8
0%
156.2
RPL.GF.D.N0250.XR Fiber Pulls, Test & Term All Prod EF to EF Complete RPL 10 to RPL6 Connectivity (XREFs) Not Started 05/12/26 05/12/26 0.0 0.0
0%
232.5
RPL10.CFCI.5110 RPL10 - Submittal Rvw/App'l - Carpet (CFCI) Div. 09 - Carpet Not Started 05/12/26 06/09/26 25.0 25.0
0%
146.2
RPL10.CFCI.5140 RPL10- Fabricate / Deliver -Epoxy Flooring (Spec 09 67 23) (CFCI) Div. 09 - Epoxy Flooring Not Started 05/12/26 06/09/26 25.0 25.0
0%
171.2
RPL10.CFCI.5260 RPL10 - Fabricate / Deliver - Specialities (CFCI) Div. 10 - Specialities Not Started 05/12/26 06/09/26 25.0 25.0
0%
113.8
RPL10.EY.NS4.01220 RPL10.EY.NS4 - Install MV, RMUs & Electrical Panels (15) OFE Not Started 05/12/26 06/09/26 25.0 25.0
0%
107.5
RPL10.EY.NS4.01230 RPL10.EY.NS4 - OFE - MV - WBS Summary OFE Not Started 05/12/26 06/30/26 43.8 43.8
0%
101.2
RPL10.INT.CTRC.01650 RPL10.Interior.Center-Corridor - BoW - Tape, Float and Paint BoW Balance of Walls & OverHead Not Started 05/12/26 05/15/26 5.0 5.0
0%
110.0
RPL10.INT.CTRC.07720 RPL10.Interior.Center-Corridor - Priority - Install Exterior Wall Drywall, Tape, Float, Paint (Remaining) Priority Walls & OverHead Not Started 05/12/26 05/14/26 3.8 3.8
0%
111.2
RPL10.INT.ENDC.6440 RPL10.Interior.End-Corridor - BoW - BoW Tape, Float and Paint Priority Soffit, Fire Safing Both Sides Balance of Walls & Overhead Not Started 05/12/26 05/18/26 6.2 6.2
0%
148.8
RPL10.INT.NS2.01114 RPL10.Interior.NS2 - MES Skids - BMS Tie-Ins ( 2 per day) NS2 - MES Skids Not Started 05/12/26 06/15/26 30.0 30.0
0%
157.5
RPL10.INT.NS3.01060 RPL10.Interior.NS3 - OFE - LV Skids and TopHat - Set / Place / Anchor (04.30.26) (Rev-05.11.26) OFE Not Started 05/12/26 06/09/26 25.0 25.0
0%
101.2
RPL10.INT.NS4.01112 RPL10.Interior.NS4 - MES Skids - Piping Tie-Ins & Inspections NS4 - MES Skids Not Started 05/12/26 06/15/26 30.0 30.0
0%
135.0
RPL10.MCUP.LP2.1860 RPL10.MCUP.Loop 2 - Install Mcup Paving *Start 05/15 Hardscape and Landscape Not Started 05/12/26 06/02/26 18.8 18.8
0%
463.8
RPL10.WP2.CMDF2.1040 RPL10.Conn CMDF2 Install & Test Network (FIM) Network Not Started 05/12/26 05/18/26 6.2 6.2
0%
202.5
RPL10.WP4.027260 RPL10.Conn NS1.CFD6.48<>11-15 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] Prefab Not Started 05/12/26 05/18/26 6.2 6.2
0%
147.5
JCL.C.1280 RPL10 - Cost Risk LOE-15 Security Systems Cost LOEs Not Started 05/13/26 01/12/27 208.8 208.8
0%
78.8
RPL.10.D.X33X7.XR Cable Pull to Concrete Pad - RPL10 NS4 Loop 1 & 2 Power (XREFs) Not Started 05/13/26 05/13/26 0.0 0.0
0%
33.8
RPL.10.D.X4420.XR Natural Gas Available for Fill/Flush Cx - Utility connections (L3/L4) Water / Gas Available (XREFs) Not Started 05/13/26 05/13/26 0.0 0.0
0%
51.2
RPL.GF.D.G4620.XG Rack & Cabinets Complete - DHB - RPL6 Give Milestones (XREFs) Not Started 05/13/26 05/13/26 0.0 0.0
0%
227.0
RPL10.EY.EF2.01410 RPL10.EY.EF2 - Install Sleeves MEPL Hardscape and Landscape Not Started 05/13/26 05/19/26 6.2 6.2
0%
443.8
RPL10.EY.EF2.01420 RPL10.EY.EF2 - Early L2 Checklist Completion Tie-ins Not Started 05/13/26 05/27/26 12.5 12.5
0%
150.0
RPL10.EY.EF2.01430 RPL10.EY.EF2 - Install Hardscape and Landscape - WBS Summary Hardscape and Landscape Not Started 05/13/26 09/01/26 97.5 97.5
0%
396.2
RPL10.EY.NS2.01290 RPL10.EY.NS2 - MV Loop 1 - L2 Checklist Completion Tie-ins Not Started 05/13/26 05/27/26 12.5 12.5
0%
31.2
RPL10.INT.CTRC.01170 RPL10.Interior.Center-Corridor - BoW - Install Doors Frame Balance of Walls & OverHead Not Started 05/13/26 05/19/26 6.2 6.2
0%
123.8
RPL10.INT.NS2.01650 RPL10.Interior.NS2 - Control Fault Domain 3 SQ4.2 - Install LV Side Aisle HAC Busway LV Side Tie-ins Not Started 05/13/26 05/18/26 5.0 5.0
0%
81.2
RPL10.OFCI.6860 OFCI - Delivery ROJ: FE Fiber for CFD NS1.4 (ROJ ) (RVCD ) NS1 Not Started 05/13/26 06/03/26 18.8 18.8
0%
68.8
RPL10.SKN.SSB.01070 RPL10.SKIN.SSB - Install Security Glazing, Doors and Ext Devices Not Started 05/13/26 05/14/26 2.5 2.5
0%
177.5
DCC.B10.3200 [NWB] CorpNet/Security/FacNet Ready [GS-CORE] Connectivity Not Started 05/14/26 05/14/26 0.0 0.0
0%
170.0
DCC.B10.3225 [NWB] CorpNet/Security/FacNet Ready [NWS 1] Connectivity Not Started 05/14/26 05/14/26 0.0 0.0
0%
233.8
DCC.B10.3235 [NWB] CorpNet/Security/FacNet Ready [NWS 2] Connectivity Not Started 05/14/26 05/14/26 0.0 0.0
0%
233.8
RPL.GF.D.N0115.XR 2 of 4 Fiber Test Complete (CAV1/4) MMH to GS.EF1/ Prod.EF1F Connectivity (XREFs) Not Started 05/14/26 05/14/26 0.0 0.0
0%
170.0