Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260412.xer
· Uploaded Apr 16, 2026 12:51 PM
· 8408 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
4
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL10.WP4.01300 |
RPL10.Conn NS1.CFD5.13 Pull Duplex Jumper (LC<>LC) [MA<>JXSW] | Pull Duplex Jumper [MA<>JXSW] | Not Started | 06/30/26 | 07/02/26 | 3.8 | 3.8 |
|
143.8 |
RPL10.WP4.027720 |
RPL10.Conn NS1.CFD4.48<>26-30 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] | Prefab | Not Started | 06/30/26 | 07/06/26 | 5.0 | 5.0 |
|
121.2 |
RPL10.WP4.028840 |
RPL10.Conn NS2.CFD4.48<>06-10 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] | Prefab | Not Started | 06/30/26 | 07/02/26 | 3.8 | 3.8 |
|
112.5 |
GCD.RPL10.4605 |
L3/L4 Start EY - NS2 | EY | Not Started | 07/01/26 | 07/01/26 | 0.0 | 0.0 |
|
160.0 |
RPL.10.D.X3820.XR |
100MW (40 MW Initial , 60 MW later) Cx Temp Power to MV Skids RPL10 NS2 Available (DPR Want 06.05.25) | Power (XREFs) | Not Started | 07/01/26 | 07/01/26 | 0.0 | 0.0 |
|
1.2 |
RPL10.CX.NS2.01010 |
RPL10.CX.NS2 - L3/L4 - WBS Summary (Electrical) | NS2 ELECTRICAL | Not Started | 07/01/26 | 12/10/26 | 140.0 | 140.0 |
|
12.5 |
RPL10.CX.NS2.01020 |
RPL10.CX.NS2 - L3/L4 - MV Skids (8) Loop 2 | NS2 ELECTRICAL | Not Started | 07/01/26 | 07/13/26 | 10.0 | 10.0 |
|
1.2 |
RPL10.EY.NS3.01270 |
RPL10.EY.NS3 - Install GS.IDF Hut (1x GS.IDF) NX09 (06.04.26) | OFE | Not Started | 07/01/26 | 07/08/26 | 6.2 | 6.2 |
|
108.8 |
RPL10.EY.NS4.01280 |
RPL10.EY.NS4 - Install BMS Tie-ins | Tie-ins | Not Started | 07/01/26 | 07/15/26 | 12.5 | 12.5 |
|
101.2 |
RPL10.INT.EF1.01590 |
RPL10.Interior.EF1 - Final Punch Walk | Tie-Ins | Not Started | 07/01/26 | 07/02/26 | 2.5 | 2.5 |
|
168.8 |
RPL10.INT.EF2.01550 |
RPL10.Interior.EF2 - EF2 West - Set Passive Panels / Racks | West EF-2 | Not Started | 07/01/26 | 07/08/26 | 6.2 | 6.2 |
|
168.8 |
RPL10.INT.EF2.01570 |
RPL10.Interior.EF2 - L2 Checklist Completion | Tie-Ins | Not Started | 07/01/26 | 07/15/26 | 12.5 | 12.5 |
|
107.5 |
RPL10.INT.NS2.02645 |
RPL10.Interior.NS2 - OFE - Control Fault Domain 3 SQ4.2 (HAC) | OFE NS2 Control Fault Domain 3 | Not Started | 07/01/26 | 07/22/26 | 18.8 | 18.8 |
|
-27.5 |
RPL10.INT.NS3.01115 |
RPL10.Interior.NS3 - MES Skids - EPMS Tie-Ins | NS3 - MES Skids | Not Started | 07/01/26 | 08/04/26 | 30.0 | 30.0 |
|
240.0 |
RPL10.INT.NS3.01770 |
RPL10.Interior.NS3 - OFE - Control Fault Domain 6 SQ12.2 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | OFE NS3 Control Fault Domain 6 | Not Started | 07/01/26 | 12/07/26 | 136.2 | 136.2 |
|
67.5 |
RPL10.INT.NS3.01790 |
RPL10.Interior.NS3 - Control Fault Domain 5 SQ11.2 - Install LV Side Aisle HAC Busway | LV Side Tie-ins | Not Started | 07/01/26 | 07/07/26 | 5.0 | 5.0 |
|
207.5 |
RPL10.INT.NS3.02800 |
RPL10.Interior.NS3 - OFE - Control Fault Domain 6 SQ12.2 (LV Side Aisle) | OFE NS3 Control Fault Domain 6 | Not Started | 07/01/26 | 07/08/26 | 6.2 | 6.2 |
|
188.8 |
RPL10.INT.SSB.01600 |
RPL10.Interior.SSB - Loading Dock and Storage - Mechanical L2 Checklist Completion | Loading Dock and Storage | Not Started | 07/01/26 | 07/15/26 | 12.5 | 12.5 |
|
151.2 |
RPL10.W3B.FE.011591 |
RPL10.Conn EF1F<>NS2.CFD6 (P2-3) Pull Fiber Trunk (384F) [EF<>SSW] | EF1F<>NS2.1 (P2-3) [EF<>SSW] | Not Started | 07/01/26 | 07/07/26 | 5.0 | 5.0 |
|
31.2 |
RPL10.WP2.01100 |
RPL10.Conn GSMDF Stable Power & Stable Conditioning | Supporting Services Building | Not Started | 07/01/26 | 07/01/26 | 0.0 | 0.0 |
|
163.8 |
RPL10.WP3A.EF1F.1085 |
RPL10.Conn EF1F(LIU)<>EF1B(MBOX) Pull/Install/Test OSP Cabling (for RPL01) - P2 | EF1F<>EF1B | Not Started | 07/01/26 | 07/09/26 | 7.5 | 7.5 |
|
198.8 |
RPL10.WP3B.FE.02100 |
RPL10.Conn EF1F<>NS2.CFD6 (P2-3) Pull/Install/Test - WBS Summary | EF1F<>NS2.1 (P2-3) [EF<>SSW] | Not Started | 07/01/26 | 07/15/26 | 12.5 | 12.5 |
|
48.8 |
RPL10.WP4.028720 |
RPL10.Conn NS2.CFD5.48<>26-30 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] | Prefab | Not Started | 07/01/26 | 07/07/26 | 5.0 | 5.0 |
|
131.2 |
GCD.RPL10.2606 |
L3/L4 Start - NS1 Rows 33-40 | NS | Not Started | 07/02/26 | 07/02/26 | 0.0 | 0.0 |
|
147.5 |
RPL10.CX.NS1.01080 |
RPL10.CX.NS1 - L3/L4 - Elec. Domain 10/09 | NS1 ELECTRICAL | Not Started | 07/02/26 | 07/08/26 | 5.0 | 5.0 |
|
35.0 |
RPL10.CX.NS1.01280 |
RPL10.CX.NS1 - L3/L4 - Control Fault Domain 6 - TW Flush and Fill | NS1 Control Fault Domain 6 | Not Started | 07/02/26 | 07/14/26 | 10.0 | 10.0 |
|
25.0 |
RPL10.INT.NS3.01810 |
RPL10.Interior.NS3 - Control Fault Domain 5 SQ11.2 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 07/02/26 | 07/08/26 | 5.0 | 5.0 |
|
207.5 |
RPL10.W3B.FE.011961 |
RPL10.Conn EF1B<>NS1.CFD6 (P2-3) Install Fiber Trunk (384F) [EF<>SSW] | EF1B<>NS1.1 (P2-3) [EF<>SSW] | Not Started | 07/02/26 | 07/06/26 | 2.5 | 2.5 |
|
21.2 |
RPL10.W3B.FE.012911 |
RPL10.Conn EF2B<>NS2.CFD6 (P1-4) Test Fiber Trunk (384F) [EF<>SSW] | EF2B<>NS2.1 (P1-4) [EF<>SSW] | Not Started | 07/02/26 | 07/06/26 | 2.5 | 2.5 |
|
50.0 |
RPL10.W3B.FE.013281 |
RPL10.Conn EF2F<>NS1.CFD6 (P1-4) Test Fiber Trunk (384F) [EF<>SSW] | EF2F<>NS1.1 (P1-4) [EF<>SSW] | Not Started | 07/02/26 | 07/06/26 | 2.5 | 2.5 |
|
41.2 |
RPL10.WP4.027860 |
RPL10.Conn NS1.CFD3.48<>11-15 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] | Prefab | Not Started | 07/02/26 | 07/09/26 | 6.2 | 6.2 |
|
102.5 |
RPL10.WP4.NS1.01260 |
RPL10.Conn NS1.CFD5 Network - WBS Summary | Network | Not Started | 07/02/26 | 10/07/26 | 85.0 | 85.0 |
|
23.8 |
RPL10.WP4.NS1.01280 |
RPL10.Conn NS1.CFD5 Network Suite [JXSW<>MA] Trunks | Pre ORv3 Rack | Not Started | 07/02/26 | 07/14/26 | 10.0 | 10.0 |
|
48.8 |
RPL10.INT.EF1.01310 |
RPL10.Interior.EF1 - South CRAH Gallery - Leak Detection / Heat Trace | South CRAH Gallery | Not Started | 07/06/26 | 07/10/26 | 6.2 | 6.2 |
|
87.5 |
RPL10.INT.NS1.01670 |
RPL10.Interior.NS1 - Control Fault Domain 3 SQ4.1 - Pull BMS from panel to devices | Remaining Tie-ins post Mech Side Aisle install | Not Started | 07/06/26 | 07/31/26 | 25.0 | 25.0 |
|
21.2 |
RPL10.INT.NS1.01680 |
RPL10.Interior.NS1 - Control Fault Domain 3 SQ4.1 - Pull EPMS from panel to devices | Remaining Tie-ins post Mech Side Aisle install | Not Started | 07/06/26 | 07/31/26 | 25.0 | 25.0 |
|
21.2 |
RPL10.INT.NS1.01690 |
RPL10.Interior.NS1 - Control Fault Domain 3 SQ4.1 - Set UPS and Panel (2) | Remaining Tie-ins post Mech Side Aisle install | Not Started | 07/06/26 | 07/31/26 | 25.0 | 25.0 |
|
15.0 |
RPL10.INT.NS1.02680 |
RPL10.Interior.NS1 - OFE - Control Fault Domain 2 SQ5.1 (Mech Side Aisle) | OFE NS1 Control Fault Domain 2 | Not Started | 07/06/26 | 07/22/26 | 16.2 | 16.2 |
|
-8.8 |
RPL10.W3B.FE.012511 |
RPL10.Conn EF2F<>NS2.CFD6 (P1-4) Install Fiber Trunk (384F) [EF<>SSW] | EF2F<>NS2.1 (P1-4) [EF<>SSW] | Not Started | 07/06/26 | 07/07/26 | 2.5 | 2.5 |
|
28.8 |
RPL10.WP3A.EF1F.1010 |
RPL10.Conn EF1F(LIU)<>EF1F(MBOX) Pull/Install/Test OSP Cabling (for RPL01) - P3 | EF1F<>EF1F | Not Started | 07/06/26 | 07/09/26 | 5.0 | 5.0 |
|
218.8 |
RPL10.WP3A.EF1F.1045 |
RPL10.Conn EF1F(LIU)<>EF2F(MBOX) Pull/Install/Test OSP Cabling (for RPL01) - P2 | EF1F<>EF2F | Not Started | 07/06/26 | 07/15/26 | 10.0 | 10.0 |
|
178.8 |
RPL10.WP4.01320 |
RPL10.Conn NS1.CFD5.14 Pull Duplex Jumper (LC<>LC) [MA<>JXSW] | Pull Duplex Jumper [MA<>JXSW] | Not Started | 07/06/26 | 07/08/26 | 3.8 | 3.8 |
|
143.8 |
RPL10.WP4.028860 |
RPL10.Conn NS2.CFD4.48<>11-15 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] | Prefab | Not Started | 07/06/26 | 07/10/26 | 6.2 | 6.2 |
|
112.5 |
RPL10.CX.NS2.01320 |
RPL10.CX.NS2 - L3/L4 - Control Fault Domain 5 - FW Flush and Fill | NS2 Control Fault Domain 5 | Not Started | 07/07/26 | 07/15/26 | 8.8 | 8.8 |
|
23.8 |
RPL10.ENDC.BB.4335 |
RPL10.Int.Build Back.End-Corr - LO #14 - Arch Finishes - Hang Drywall, Paint, Final Finishes | Build Back Interior Leave Out Wall #14 (End Corr) | Not Started | 07/07/26 | 08/03/26 | 25.0 | 25.0 |
|
230.0 |
RPL10.INT.CTRC.01490 |
RPL10.Interior.Center-Corridor - BoW - Final Punch Walk | Balance of Walls & OverHead | Not Started | 07/07/26 | 07/08/26 | 2.5 | 2.5 |
|
165.0 |
RPL10.INT.NS2.01440 |
RPL10.Interior.NS2 - Control Fault Domain 4 SQ3.2 - Pull BMS from panel to devices | Remaining Tie-ins post Mech Side Aisle install | Not Started | 07/07/26 | 08/03/26 | 25.0 | 25.0 |
|
5.0 |
RPL10.INT.NS2.01450 |
RPL10.Interior.NS2 - Control Fault Domain 4 SQ3.2 - Pull EPMS from panel to devices | Remaining Tie-ins post Mech Side Aisle install | Not Started | 07/07/26 | 08/03/26 | 25.0 | 25.0 |
|
5.0 |
RPL10.INT.NS2.01460 |
RPL10.Interior.NS2 - Control Fault Domain 4 SQ3.2 - Set UPS and Panel (2) and GS.IDF N22 | Remaining Tie-ins post Mech Side Aisle install | Not Started | 07/07/26 | 08/03/26 | 25.0 | 25.0 |
|
-1.2 |
RPL10.INT.NS2.01480 |
RPL10.Interior.NS2 - Control Fault Domain 5 SQ2.2 - L2 Checklist Completion | Remaining Tie-ins post Mech Side Aisle install | Not Started | 07/07/26 | 08/03/26 | 25.0 | 25.0 |
|
1.2 |
RPL10.INT.NS2.02665 |
RPL10.Interior.NS2 - OFE - Control Fault Domain 3 SQ4.2 (Mech Side Aisle) | OFE NS2 Control Fault Domain 3 | Not Started | 07/07/26 | 07/23/26 | 16.2 | 16.2 |
|
-22.5 |
RPL10.INT.NS3.01830 |
RPL10.Interior.NS3 - Control Fault Domain 6 SQ12.2 - Install Duct (LV Side) | LV Side Tie-ins | Not Started | 07/07/26 | 07/10/26 | 5.0 | 5.0 |
|
190.0 |
RPL10.INT.NS3.01860 |
RPL10.Interior.NS3 - Tie-ins - Control Fault Domain 6 SQ12.2 - WBS Summary | Tie-Ins NS3 Control Fault Domain 6 | Not Started | 07/07/26 | 01/25/27 | 172.5 | 172.5 |
|
75.0 |
RPL10.W3B.FE.011166 |
RPL10.Conn EF1B<>NS1.CFD5 (P2-3) Pull Fiber Trunk (384F) [EF<>SSW] | EF1B<>NS1.2 (P2-3) [EF<>SSW] | Not Started | 07/07/26 | 07/08/26 | 2.5 | 2.5 |
|
35.0 |
RPL10.W3B.FE.012361 |
RPL10.Conn EF1F<>NS1.CFD6 (P2-3) Install Fiber Trunk (384F) [EF<>SSW] | EF1F<>NS1.1 (P2-3) [EF<>SSW] | Not Started | 07/07/26 | 07/08/26 | 2.5 | 2.5 |
|
21.2 |
RPL10.W3B.FE.012761 |
RPL10.Conn EF1B<>NS1.CFD6 (P2-3) Test Fiber Trunk (384F) [EF<>SSW] | EF1B<>NS1.1 (P2-3) [EF<>SSW] | Not Started | 07/07/26 | 07/08/26 | 2.5 | 2.5 |
|
41.2 |
RPL10.WP2.GSIDF.2780 |
RPL10.Conn GSIDFNX10 Install & Test Network (FIM) | Network | Not Started | 07/07/26 | 07/09/26 | 3.8 | 3.8 |
|
185.0 |
RPL10.WP2.GSIDF.3460 |
RPL10.Conn GSIDFNX10 Install Copper, WAPs, Security Camera & Access Control | Cabling | Not Started | 07/07/26 | 07/09/26 | 3.8 | 3.8 |
|
443.8 |
RPL10.WP3B.FE.01175 |
RPL10.Conn EF1B<>NS1.CFD5 (P2-3) Pull/Install/Test - WBS Summary* | EF1B<>NS1.2 (P2-3) [EF<>SSW] | Not Started | 07/07/26 | 08/04/26 | 26.2 | 26.2 |
|
35.0 |
RPL10.WP4.027740 |
RPL10.Conn NS1.CFD4.48<>31-35 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] | Prefab | Not Started | 07/07/26 | 07/09/26 | 3.8 | 3.8 |
|
121.2 |
RPL10.WP4.NS2.01380 |
RPL10.Conn NS2.CFD6 Infrastructure - WBS Summary | Infrastructure | Not Started | 07/07/26 | 07/10/26 | 5.0 | 5.0 |
|
60.0 |
RPL10.WP4.NS2.01400 |
RPL10.Conn NS2.CFD6 Infrastructure | Infrastructure | Not Started | 07/07/26 | 07/10/26 | 5.0 | 5.0 |
|
60.0 |
DCC.B10.3547 |
[NWB] Cabling Start : Front End Production Cabling [NWS 3] | Connectivity | Not Started | 07/08/26 | 07/08/26 | 0.0 | 0.0 |
|
1916.2 |
DCC.B10.3549 |
[NWB] Cabling Start : Back End Production Cabling [NWS 3] | Connectivity | Not Started | 07/08/26 | 07/08/26 | 0.0 | 0.0 |
|
1916.2 |
GCD.RPL10.5745 |
[RPL10] TC Ready: All General Services [RPL10-Exterior IDFs] | TC Ready: General Services | Not Started | 07/08/26 | 07/08/26 | 0.0 | 0.0 |
|
186.2 |
RPL.GF.D.N0610.XG |
GS.IDF Hut Install Complete (03, 04, 08, 09, 10) | Give Milestones (XREFs) | Not Started | 07/08/26 | 07/08/26 | 0.0 | 0.0 |
|
1915.0 |
RPL10.CTRC.BB.1460 |
RPL10.Int.Build Back.Center-Corr - LO #6,8 - Final Clean | Build Back Interior Leave Out Wall #6 #8 (Center Corr) | Not Started | 07/08/26 | 07/13/26 | 5.0 | 5.0 |
|
145.0 |
RPL10.CX.NS1.01380 |
RPL10.CX.NS1 - L3/L4 - Control Fault Domain 4 - FW Flush and Fill | NS1 Control Fault Domain 4 | Not Started | 07/08/26 | 07/16/26 | 8.8 | 8.8 |
|
37.5 |
RPL10.INT.EF1.01527 |
RPL10.Interior.EF1 - EF1 West - Install OH Tier1 Ladder Racks | West EF-1 | Not Started | 07/08/26 | 07/14/26 | 6.2 | 6.2 |
|
168.8 |
RPL10.INT.ENDC.01260 |
RPL10.Interior.End-Corridor - BoW - Install Cable Tray | Balance of Walls & Overhead | Not Started | 07/08/26 | 07/14/26 | 6.2 | 6.2 |
|
252.5 |
RPL10.INT.ENDC.01270 |
RPL10.Interior.End-Corridor - BoW - Install Tile | Balance of Walls & Overhead | Not Started | 07/08/26 | 07/16/26 | 8.8 | 8.8 |
|
172.5 |
RPL10.INT.ENDC.1460 |
RPL10.Interior.End-Corridor - BoW - Frame Hard Lid | Balance of Walls & Overhead | Not Started | 07/08/26 | 07/14/26 | 6.2 | 6.2 |
|
180.0 |
RPL10.INT.ENDC.1600 |
RPL10.Interior.End-Corridor - BoW - Electrical Trim Out (incl Lights) | Balance of Walls & Overhead | Not Started | 07/08/26 | 07/17/26 | 10.0 | 10.0 |
|
186.2 |
RPL10.INT.ENDC.1900 |
RPL10.Interior.End-Corridor - BoW - F/R/P Pads | Balance of Walls & Overhead | Not Started | 07/08/26 | 07/14/26 | 6.2 | 6.2 |
|
148.8 |
RPL10.INT.ENDC.6200 |
RPL10.Interior.End-Corridor - BoW - Install Fire Safing/ Seal all Penetrations (Lowside space) | Balance of Walls & Overhead | Not Started | 07/08/26 | 07/13/26 | 5.0 | 5.0 |
|
183.8 |
RPL10.INT.ENDC.6460 |
RPL10.Interior.End-Corridor - BoW - Install Fire Alarm Panel | Balance of Walls & Overhead | Not Started | 07/08/26 | 07/09/26 | 2.5 | 2.5 |
|
246.2 |
RPL10.INT.SSB.02200 |
RPL10.Interior.SSB - Kitchen & Office Spaces - Mechanical L2 Checklist Completion | Kitchen and Office Spaces | Not Started | 07/08/26 | 07/21/26 | 12.5 | 12.5 |
|
153.8 |
RPL10.SKN.EF12.01040 |
RPL10.SKIN.EF12 - Install Louvers | Glazing, Doors and Ext Devices | Not Started | 07/08/26 | 07/14/26 | 6.2 | 6.2 |
|
235.0 |
RPL10.SKN.EF12.01110 |
RPL10.SKIN.EF12 - Install Scupper and Downspouts | Glazing, Doors and Ext Devices | Not Started | 07/08/26 | 07/14/26 | 6.2 | 6.2 |
|
238.8 |
RPL10.SKN.NS12.01050 |
RPL10.SKIN.NS12 - Install Lighting | Glazing, Doors and Ext Devices | Not Started | 07/08/26 | 07/13/26 | 5.0 | 5.0 |
|
125.0 |
RPL10.SKN.NS43.01030 |
RPL10.SKIN.NS43 - Install Awning over Doors | Glazing, Doors and Ext Devices | Not Started | 07/08/26 | 07/14/26 | 6.2 | 6.2 |
|
228.8 |
RPL10.W3B.FE.011286 |
RPL10.Conn EF2B<>NS1.CFD5 (P1-4) Pull Fiber Trunk (384F) [EF<>SSW] | EF2B<>NS1.2 (P1-4) [EF<>SSW] | Not Started | 07/08/26 | 07/10/26 | 3.8 | 3.8 |
|
18.8 |
RPL10.W3B.FE.011991 |
RPL10.Conn EF1B<>NS2.CFD6 (P2-3) Install Fiber Trunk (384F) [EF<>SSW] | EF1B<>NS2.1 (P2-3) [EF<>SSW] | Not Started | 07/08/26 | 07/09/26 | 2.5 | 2.5 |
|
28.8 |
RPL10.W3B.FE.013311 |
RPL10.Conn EF2F<>NS2.CFD6 (P1-4) Test Fiber Trunk (384F) [EF<>SSW] | EF2F<>NS2.1 (P1-4) [EF<>SSW] | Not Started | 07/08/26 | 07/09/26 | 2.5 | 2.5 |
|
48.8 |
RPL10.WP3A.EF.07000 |
RPL10.Conn EF2B Infrastructure - WBS Summary | Infrastructure & Cabling | Not Started | 07/08/26 | 08/18/26 | 37.5 | 37.5 |
|
158.8 |
RPL10.WP3A.EF.07020 |
RPL10.Conn EF2B Infrasturcture 1 (Racks & Vertical Cable Manager,Ladder Racks) | Infrastructure & Cabling | Not Started | 07/08/26 | 08/04/26 | 25.0 | 25.0 |
|
128.8 |
RPL10.WP3A.EF.08000 |
RPL10.Conn EF2B Pathway - WBS Summary | Infrastructure & Cabling | Not Started | 07/08/26 | 08/18/26 | 37.5 | 37.5 |
|
158.8 |
RPL10.WP3A.EF.08320 |
RPL10.Conn EF1B Pull and Install OSP Cable for RPL02 | RPL-2 | Not Started | 07/08/26 | 07/21/26 | 12.5 | 12.5 |
|
133.8 |
RPL10.WP3A.EF.08400 |
RPL10.Conn EF1B Pull and Install OSP Cable for RPL07 | RPL-7 | Not Started | 07/08/26 | 07/13/26 | 5.0 | 5.0 |
|
191.2 |
RPL10.WP3A.EF1F.1125 |
RPL10.Conn EF1F(LIU)<>EF2B(MBOX) Pull/Install/Test OSP Cabling (for RPL01) - P2 | EB1F<>EF2B | Not Started | 07/08/26 | 07/21/26 | 12.5 | 12.5 |
|
158.8 |
RPL10.WP3B.FE.01155 |
RPL10.Conn EF2B<>NS1.CFD5 (P1-4) Pull/Install/Test - WBS Summary | EF2B<>NS1.2 (P1-4) [EF<>SSW] | Not Started | 07/08/26 | 07/17/26 | 10.0 | 10.0 |
|
40.0 |
RPL10.WP4.028020 |
RPL10.Conn NS1.CFD2.48<>03-05 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] | Prefab | Not Started | 07/08/26 | 07/09/26 | 2.5 | 2.5 |
|
92.5 |
RPL10.WP4.028740 |
RPL10.Conn NS2.CFD5.48<>31-35 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] | Prefab | Not Started | 07/08/26 | 07/10/26 | 3.8 | 3.8 |
|
131.2 |
RPL10.WP4.NS1.03280 |
RPL10.Conn NS1.CFD2 Network - WBS Summary | Network | Not Started | 07/08/26 | 12/07/26 | 131.2 | 131.2 |
|
28.8 |
RPL.GF.D.N0240.XR |
Fiber Pulls, Test & Term All Prod EF to EF Complete RPL 10 to RPL9 | Connectivity (XREFs) | Not Started | 07/09/26 | 07/09/26 | 0.0 | 0.0 |
|
190.0 |
RPL.GF.D.N0310.XR |
Fiber Pulls, Test & Term All Prod EF to EF Complete RPL 10 to AI5 | Connectivity (XREFs) | Not Started | 07/09/26 | 07/09/26 | 0.0 | 0.0 |
|
152.5 |
RPL10.Conn.MS.01130 |
CorpNet & FacNet Available - mCUP | Connectivity Milestones | Not Started | 07/09/26 | 07/09/26 | 0.0 | 0.0 |
|
185.0 |
RPL10.Conn.MS.01530 |
Wifi Ready - End Corridor | Connectivity Milestones | Not Started | 07/09/26 | 07/09/26 | 0.0 | 0.0 |
|
443.8 |
RPL10.EY.NS3.01280 |
RPL10.EY.NS3 - Install BMS Tie-ins | Tie-ins | Not Started | 07/09/26 | 07/22/26 | 12.5 | 12.5 |
|
108.8 |
RPL10.EY.NS4.01290 |
RPL10.EY.NS4 - MV Loop 1 - L2 Checklist Completion | Tie-ins | Not Started | 07/09/26 | 07/22/26 | 12.5 | 12.5 |
|
101.2 |