Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260412.xer · Uploaded Apr 16, 2026 12:51 PM · 8408 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
99
Completed
1
In Progress
100
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL10.FEN.NS3.1430 EF1-W Row 3,5 <>FEN NS3 Odd Row #: Path3 - 432f JXSW<>SSW Trunks Permlink Testing [Tier 4] NS<>DH JXSW<>SSW Trunks Complete 10/17/24 10/17/24 16.2 0.0
100%
0.0
RPL10.FEN.NS3.1440 EF2-W Row 3,5 <>FEN NS3 Even Row #: Path4 - 432f JXSW<>SSW Trunks Permlink Testing [Tier 4] NS<>DH JXSW<>SSW Trunks Complete 10/17/24 10/17/24 16.2 0.0
100%
0.0
RPL10.FEN.NS3.1450 FEN NS3: PON Management In-Row Cable Pull PON Management Complete 10/17/24 10/17/24 5.0 0.0
100%
0.0
RPL10.FEN.NS3.1460 FEN NS3: PON Management In-Row Cable Install PON Management Complete 10/17/24 10/17/24 7.5 0.0
100%
0.0
RPL10.FEN.NS4.1000 EF1-E Row 3,5 <>FEN NS4 Odd Row #: Path1 - 432f JXSW<>SSW Trunks Pull [Tier 4] NS<>DH JXSW<>SSW Trunks Complete 10/17/24 10/17/24 15.0 0.0
100%
0.0
RPL10.FEN.NS4.1010 EF2-E Row 3,5 <>FEN NS4 Even Row #: Path2 - 432f JXSW<>SSW Trunks Pull [Tier 4] NS<>DH JXSW<>SSW Trunks Complete 10/17/24 10/17/24 15.0 0.0
100%
0.0
RPL10.FEN.NS4.1020 EF1-W Row 3,5 <>FEN NS4 Odd Row #: Path3 - 432f JXSW<>SSW Trunks Pull [Tier 4] NS<>DH JXSW<>SSW Trunks Complete 10/17/24 10/17/24 15.0 0.0
100%
0.0
RPL10.FEN.NS4.1030 EF2-W Row 3,5 <>FEN NS4 Even Row #: Path4 - 432f JXSW<>SSW Trunks Pull [Tier 4] NS<>DH JXSW<>SSW Trunks Complete 10/17/24 10/17/24 15.0 0.0
100%
0.0
RPL10.FEN.NS4.1040 FEN NS4: SSW<>XSW 8MMC24P<>8MMC24R Ext Trunks Pull [Tier 2.2] Megapod In-Row/across Cold Aisle Cabling Complete 10/17/24 10/17/24 17.5 0.0
100%
0.0
RPL10.FEN.NS4.1050 FEN NS1: Row3-6 SSW<>JXSW 8MMC24R<>24MMC8P Pull [Tier 2] Network Suite [SSW<>JXSW] Multi Drop Cable Complete 10/17/24 10/17/24 5.0 0.0
100%
0.0
RPL10.FEN.NS4.1060 FEN NS2: Row3-6 SSW<>JXSW 8MMC24R<>24MMC8P Pull [Tier 2] Network Suite [SSW<>JXSW] Multi Drop Cable Complete 10/17/24 10/17/24 5.0 0.0
100%
0.0
RPL10.FEN.NS4.1070 FEN NS3: Row3-6 SSW<>JXSW 8MMC24R<>24MMC8P Pull [Tier 2] Network Suite [SSW<>JXSW] Multi Drop Cable Complete 10/17/24 10/17/24 5.0 0.0
100%
0.0
RPL10.FEN.NS4.1080 FEN NS4: Row3-6 SSW<>JXSW 8MMC24R<>24MMC8P Pull [Tier 2] Network Suite [SSW<>JXSW] Multi Drop Cable Complete 10/17/24 10/17/24 5.0 0.0
100%
0.0
RPL10.FEN.NS4.1090 FEN NS4: 384f End Row IDF<>IDF SSW<>FSW Trunks Pull [Tier 3] End Row IDF<>IDF Trunk Complete 10/17/24 10/17/24 1.2 0.0
100%
0.0
RPL10.FEN.NS4.1100 FEN NS4: FSW<>SSW 8MMC24P<>8MMC24P In-Row Ext Trunks Pull [Tier 2.2] Megapod In-Row/across Cold Aisle Cabling Complete 10/17/24 10/17/24 3.8 0.0
100%
0.0
RPL10.FEN.NS4.1110 FEN NS4: FSW<>SSW 8MMC24P<>8MMC24R Across Cold-Aisle Ext Trunks Pull [Tier 2.2] Megapod In-Row/across Cold Aisle Cabling Complete 10/17/24 10/17/24 5.0 0.0
100%
0.0
RPL10.FEN.NS4.1120 FEN NS4: FSW<>SSW 16MMC24P<>16MMC24R Across Cold-Aisle Ext Trunks Pull [Tier 2.2] Megapod In-Row/across Cold Aisle Cabling Complete 10/17/24 10/17/24 2.5 0.0
100%
0.0
RPL10.FEN.NS4.1130 FEN NS4: 384f End Row IDF<>IDF FSW<>RSW Trunks Pull [Tier 3] End Row IDF<>IDF Trunk Complete 10/17/24 10/17/24 1.2 0.0
100%
0.0
RPL10.FEN.NS4.1140 FEN NS4: RSW<>FSW 1MMC16P<>LC/DX Pull [Tier 2.2] Megapod In-Row/across Cold Aisle Cabling Complete 10/17/24 10/17/24 3.8 0.0
100%
0.0
RPL10.FEN.NS4.1150 FEN NS4: RSW<>FSW 12MMC24P<>LC/DX Pull [Tier 2.2] Megapod In-Row/across Cold Aisle Cabling Complete 10/17/24 10/17/24 17.5 0.0
100%
0.0
RPL10.FEN.NS4.1160 FEN NS4: RSW<>FSW 12MMC24P<>12MMC24R Pull [Tier 2.2] Megapod In-Row/across Cold Aisle Cabling Complete 10/17/24 10/17/24 5.0 0.0
100%
0.0
RPL10.FEN.NS4.1170 FEN NS4: RSW<>FSW 2MMC24P<>2MMC24R Pull [Tier 2.2] Megapod In-Row/across Cold Aisle Cabling Complete 10/17/24 10/17/24 5.0 0.0
100%
0.0
RPL10.FEN.NS4.1180 FEN NS4: Install ORV3N Infrastructure Complete 10/17/24 10/17/24 8.8 0.0
100%
0.0
RPL10.FEN.NS4.1190 FEN NS4: Install Waterfall Infrastructure Complete 10/17/24 10/17/24 12.5 0.0
100%
0.0
RPL10.FEN.NS4.1200 FEN NS4: Install Rack Power Distribution Units (PDU) Infrastructure Complete 10/17/24 10/17/24 7.5 0.0
100%
0.0
RPL10.FEN.NS4.1210 FEN NS4: Install End Row PDUs Infrastructure Complete 10/17/24 10/17/24 3.8 0.0
100%
0.0
RPL10.FEN.NS4.1220 FEN NS4: Rack & Stack Management & Console Rack & Stack Complete 10/17/24 10/17/24 2.5 0.0
100%
0.0
RPL10.FEN.NS4.1230 FEN NS1: Row3-6 SSW<>JXSW 8MMC24R<>24MMC8P Install [Tier 2] Network Suite [SSW<>JXSW] Multi Drop Cable Complete 10/17/24 10/17/24 8.8 0.0
100%
0.0
RPL10.FEN.NS4.1240 FEN NS2: Row3-6 SSW<>JXSW 8MMC24R<>24MMC8P Install [Tier 2] Network Suite [SSW<>JXSW] Multi Drop Cable Complete 10/17/24 10/17/24 8.8 0.0
100%
0.0
RPL10.FEN.NS4.1250 FEN NS3: Row3-6 SSW<>JXSW 8MMC24R<>24MMC8P Install [Tier 2] Network Suite [SSW<>JXSW] Multi Drop Cable Complete 10/17/24 10/17/24 8.8 0.0
100%
0.0
RPL10.FEN.NS4.1260 FEN NS4: Row3-6 SSW<>JXSW 8MMC24R<>24MMC8P Install [Tier 2] Network Suite [SSW<>JXSW] Multi Drop Cable Complete 10/17/24 10/17/24 10.0 0.0
100%
0.0
RPL10.FEN.NS4.1270 EF1-E Row 3,5 <>FEN NS4 Odd Row #: Path1 - 432f JXSW<>SSW Trunks Install [Tier 4] NS<>DH JXSW<>SSW Trunks Complete 10/17/24 10/17/24 8.8 0.0
100%
0.0
RPL10.FEN.NS4.1280 EF2-E Row 3,5 <>FEN NS4 Even Row #: Path2 - 432f JXSW<>SSW Trunks Install [Tier 4] NS<>DH JXSW<>SSW Trunks Complete 10/17/24 10/17/24 8.8 0.0
100%
0.0
RPL10.FEN.NS4.1290 EF2-W Row 3,5 <>FEN NS4 Odd Row #: Path3 - 432f JXSW<>SSW Trunks Install [Tier 4] NS<>DH JXSW<>SSW Trunks Complete 10/17/24 10/17/24 8.8 0.0
100%
0.0
RPL10.FEN.NS4.1300 EF2-W Row 3,5 <>FEN NS4 Even Row #: Path4 - 432f JXSW<>SSW Trunks Install [Tier 4] NS<>DH JXSW<>SSW Trunks Complete 10/17/24 10/17/24 8.8 0.0
100%
0.0
RPL10.FEN.NS4.1310 FEN NS4: SSW<>XSW 8MMC24P<>8MMC24R Ext Trunks Install [Tier 2.2] Megapod In-Row/across Cold Aisle Cabling Complete 10/17/24 10/17/24 27.5 0.0
100%
0.0
RPL10.FEN.NS4.1320 FEN NS4: FSW<>SSW 8MMC24P<>8MMC24P In-Row Ext Trunks Install [Tier 2.2] Megapod In-Row/across Cold Aisle Cabling Complete 10/17/24 10/17/24 6.2 0.0
100%
0.0
RPL10.FEN.NS4.1330 FEN NS4: FSW<>SSW 8MMC24P<>8MMC24R Across Cold-Aisle Ext Trunks Install [Tier 2.2] Megapod In-Row/across Cold Aisle Cabling Complete 10/17/24 10/17/24 6.2 0.0
100%
0.0
RPL10.FEN.NS4.1340 FEN NS4: FSW<>SSW 16MMC24P<>16MMC24R Across Cold-Aisle Ext Trunks Install [Tier 2.2] Megapod In-Row/across Cold Aisle Cabling Complete 10/17/24 10/17/24 7.5 0.0
100%
0.0
RPL10.FEN.NS4.1350 FEN NS4: RSW<>FSW 1MMC16P<>LC/DX Install [Tier 2.2] Megapod In-Row/across Cold Aisle Cabling Complete 10/17/24 10/17/24 3.8 0.0
100%
0.0
RPL10.FEN.NS4.1360 FEN NS4: RSW<>FSW 12MMC24P<>LC/DX Install [Tier 2.2] Megapod In-Row/across Cold Aisle Cabling Complete 10/17/24 10/17/24 5.0 0.0
100%
0.0
RPL10.FEN.NS4.1370 FEN NS4: RSW<>FSW 12MMC24P<>12MMC24R Install [Tier 2.2] Megapod In-Row/across Cold Aisle Cabling Complete 10/17/24 10/17/24 6.2 0.0
100%
0.0
RPL10.FEN.NS4.1380 FEN NS4: RSW<>FSW 2MMC24P<>2MMC24R Install [Tier 2.2] Megapod In-Row/across Cold Aisle Cabling Complete 10/17/24 10/17/24 6.2 0.0
100%
0.0
RPL10.FEN.NS4.1390 FEN NS4: 384f End Row IDF<>IDF SSW<>FSW Trunks Install [Tier 3] End Row IDF<>IDF Trunk Complete 10/17/24 10/17/24 1.2 0.0
100%
0.0
RPL10.FEN.NS4.1400 FEN NS4: 384f End Row IDF<>IDF FSW<>RSW Trunks Install [Tier 3] End Row IDF<>IDF Trunk Complete 10/17/24 10/17/24 1.2 0.0
100%
0.0
RPL10.FEN.NS4.1410 EF1-E Row 3,5 <>FEN NS4 Odd Row #: Path1 - 432f JXSW<>SSW Trunks Permlink Testing [Tier 4] NS<>DH JXSW<>SSW Trunks Complete 10/17/24 10/17/24 15.0 0.0
100%
0.0
RPL10.FEN.NS4.1420 EF2-E Row 3,5 <>FEN NS4 Even Row #: Path2 - 432f JXSW<>SSW Trunks Permlink Testing [Tier 4] NS<>DH JXSW<>SSW Trunks Complete 10/17/24 10/17/24 15.0 0.0
100%
0.0
RPL10.FEN.NS4.1430 EF1-W Row 3,5 <>FEN NS4 Odd Row #: Path3 - 432f JXSW<>SSW Trunks Permlink Testing [Tier 4] NS<>DH JXSW<>SSW Trunks Complete 10/17/24 10/17/24 15.0 0.0
100%
0.0
RPL10.FEN.NS4.1440 EF2-W Row 3,5 <>FEN NS4 Even Row #: Path4 - 432f JXSW<>SSW Trunks Permlink Testing [Tier 4] NS<>DH JXSW<>SSW Trunks Complete 10/17/24 10/17/24 16.2 0.0
100%
0.0
RPL10.FEN.NS4.1450 FEN NS4: PON Management In-Row Cable Pull PON Management Complete 10/17/24 10/17/24 3.8 0.0
100%
0.0
RPL10.FEN.NS4.1460 FEN NS4: PON Management In-Row Cable Install PON Management Complete 10/17/24 10/17/24 5.0 0.0
100%
0.0
RPL10.INT.CTRC.01080 RPL10.Interior.Center-Corridor - Priority Walls - Electrical OBSOLETE Obsolete Complete 10/17/24 10/17/24 6.2 0.0
100%
0.0
RPL10.INT.CTRC.01110 RPL10.Interior.Center-Corridor - Priority Walls - Controls / EPMS / BMS OBSOLETE Obsolete Complete 10/17/24 10/17/24 5.0 0.0
100%
0.0
RPL10.INT.CTRC.01160 RPL10.Interior.Center-Corridor - Spoke Parts, Tech, SCR, lnverter Room, UPS Gallery, Bathrooms, etc.) - OBSOLETE Obsolete Active 10/17/24 07/27/32 2448.8 0.0
100%
0.0
RPL10.INT.CTRC.01450 RPL10.Interior.Center-Corridor - BoW - Install DAS ***OBSOLETE*** Obsolete Complete 10/17/24 10/17/24 6.2 0.0
100%
0.0
RPL10.INT.CTRC.01570 RPL10.Interior.Center-Corridor - Priority Walls - Install Plumbing OBSOLETE Obsolete Complete 10/17/24 10/17/24 12.5 0.0
100%
0.0
RPL10.INT.CTRC.01950 RPL10.Interior.Center-Corridor - Priority - Install Drywall at Exterior Walls (Highside OH space) OBSOLETE Obsolete Complete 10/17/24 10/17/24 6.2 0.0
100%
0.0
RPL10.INT.CTRC.05420 RPL10.Interior.CTRC - Priority - Grid line 10-25 - P3 - Frame Pony Wall OBSOLETE Priority Wall (P3) - Grid Line 10-25 Complete 10/17/24 10/17/24 6.2 0.0
100%
0.0
RPL10.INT.CTRC.05440 RPL10.Interior.CTRC - Priority - Grid line 10-25 - P3 - MEP OH Pentrations OBSOLETE Priority Wall (P3) - Grid Line 10-25 Complete 10/17/24 10/17/24 6.2 0.0
100%
0.0
RPL10.INT.CTRC.05460 RPL10.Interior.CTRC - Priority - Grid line 10-25 - P3 - Hang Drywall Pony Wall (both sides)OBSOLETE Priority Wall (P3) - Grid Line 10-25 Complete 10/17/24 10/17/24 7.5 0.0
100%
0.0
RPL10.INT.CTRC.05480 RPL10.Interior.CTRC - Priority - Grid line 10-25 - P3 - Tape Float Paint Pony Wall (both sides) OBSOLETE Priority Wall (P3) - Grid Line 10-25 Complete 10/17/24 10/17/24 12.5 0.0
100%
0.0
RPL10.INT.CTRC.05500 RPL10.Interior.CTRC - Priority - Grid line 10-25 - P3 - Remaining Hangers & Strut (All Trades) OBSOLETE Priority Wall (P3) - Grid Line 10-25 Complete 10/17/24 10/17/24 6.2 0.0
100%
0.0
RPL10.INT.CTRC.05520 RPL10.Interior.CTRC - Priority - Grid line 10-25 - P3 - Frame Remaining Wall OBSOLETE Priority Wall (P3) - Grid Line 10-25 Complete 10/17/24 10/17/24 6.2 0.0
100%
0.0
RPL10.INT.CTRC.05540 RPL10.Interior.CTRC - Priority - Grid line 10-25 - P3 - Mechanical Inwall OBSOLETE Priority Wall (P3) - Grid Line 10-25 Complete 10/17/24 10/17/24 5.0 0.0
100%
0.0
RPL10.INT.CTRC.05560 RPL10.Interior.CTRC - Priority - Grid line 10-25 - P3 - Electrical Inwall OBSOLETE Priority Wall (P3) - Grid Line 10-25 Complete 10/17/24 10/17/24 5.0 0.0
100%
0.0
RPL10.INT.CTRC.05580 RPL10.Interior.CTRC - Priority - Grid line 10-25 - P3 - Fire Alarm/ BMS inwall OBSOLETE Priority Wall (P3) - Grid Line 10-25 Complete 10/17/24 10/17/24 5.0 0.0
100%
0.0
RPL10.INT.CTRC.05600 RPL10.Interior.CTRC - Priority - Grid line 10-25 - P3 - Backing Wall OBSOLETE Priority Wall (P3) - Grid Line 10-25 Complete 10/17/24 10/17/24 5.0 0.0
100%
0.0
RPL10.INT.CTRC.05620 RPL10.Interior.CTRC - Priority - Grid line 10-25 - P3 - One Side Drywall Remaining Wall OBSOLETE Priority Wall (P3) - Grid Line 10-25 Complete 10/17/24 10/17/24 7.5 0.0
100%
0.0
RPL10.INT.CTRC.05640 RPL10.Interior.CTRC - Priority - Grid line 10-25 - P3 - Tape Float Paint One Side Remaining Wall OBSOLETE Priority Wall (P3) - Grid Line 10-25 Complete 10/17/24 10/17/24 15.0 0.0
100%
0.0
RPL10.INT.CTRC.05660 RPL10.Interior.CTRC - Priority - Grid line 10-25 - P3 - Two Side Drywall Remaining Wall OBSOLETE Priority Wall (P3) - Grid Line 10-25 Complete 10/17/24 10/17/24 7.5 0.0
100%
0.0
RPL10.INT.CTRC.05680 RPL10.Interior.CTRC - Priority - Grid line 10-25 - P3 - Tape Float Paint Two Side Remaining Wall OBSOLETE Priority Wall (P3) - Grid Line 10-25 Complete 10/17/24 10/17/24 15.0 0.0
100%
0.0
RPL10.INT.CTRC.05700 RPL10.Interior.CTRC - Priority - Grid line 10-16 - P4 - Frame Pony Wall OBSOLETE Priority Wall (P4) - Grid Line 10-D Complete 10/17/24 10/17/24 6.2 0.0
100%
0.0
RPL10.INT.CTRC.05720 RPL10.Interior.CTRC - Priority - Grid line 10-16 - P4 - MEP OH Pentrations OBSOLETE Priority Wall (P4) - Grid Line 10-D Complete 10/17/24 10/17/24 6.2 0.0
100%
0.0
RPL10.INT.CTRC.05740 RPL10.Interior.CTRC - Priority - Grid line 10-16 - P4 - Frame Remaining Wall OBSOLETE Priority Wall (P4) - Grid Line 10-D Complete 10/17/24 10/17/24 6.2 0.0
100%
0.0
RPL10.INT.CTRC.05760 RPL10.Interior.CTRC - Priority - Grid line 10-16 - P4 - Hang Drywall Pony Wall (both sides) OBSOLETE Priority Wall (P4) - Grid Line 10-D Complete 10/17/24 10/17/24 7.5 0.0
100%
0.0
RPL10.INT.CTRC.05780 RPL10.Interior.CTRC - Priority - Grid line 10-16 - P4 - Tape Float Paint Pony Wall (both sides) OBSOLETE Priority Wall (P4) - Grid Line 10-D Complete 10/17/24 10/17/24 12.5 0.0
100%
0.0
RPL10.INT.CTRC.05800 RPL10.Interior.CTRC - Priority - Grid line 10-16 - P4 - One Side Drywall Remaining Wall OBSOLETE Priority Wall (P4) - Grid Line 10-D Complete 10/17/24 10/17/24 7.5 0.0
100%
0.0
RPL10.INT.CTRC.05820 RPL10.Interior.CTRC - Priority - Grid line 10-16 - P4 - Backing Wall OBSOLETE Priority Wall (P4) - Grid Line 10-D Complete 10/17/24 10/17/24 5.0 0.0
100%
0.0
RPL10.INT.CTRC.05840 RPL10.Interior.CTRC - Priority - Grid line 10-16 - P4 - Mechanical Inwall OBSOLETE Priority Wall (P4) - Grid Line 10-D Complete 10/17/24 10/17/24 5.0 0.0
100%
0.0
RPL10.INT.CTRC.05860 RPL10.Interior.CTRC - Priority - Grid line 10-16 - P4 - Electrical Inwall OBSOLETE Priority Wall (P4) - Grid Line 10-D Complete 10/17/24 10/17/24 5.0 0.0
100%
0.0
RPL10.INT.CTRC.05880 RPL10.Interior.CTRC - Priority - Grid line 10-16 - P4 - Tape Float Paint One Side Remaining Wall ***** OBSOLETE Priority Wall (P4) - Grid Line 10-D Complete 10/17/24 10/17/24 15.0 0.0
100%
0.0
RPL10.INT.CTRC.05900 RPL10.Interior.CTRC - Priority - Grid line 10-16 - P4 - Two Side Drywall Remaining Wall OBSOLETE Priority Wall (P4) - Grid Line 10-D Complete 10/17/24 10/17/24 7.5 0.0
100%
0.0
RPL10.INT.CTRC.05920 RPL10.Interior.CTRC - Priority - Grid line 10-16 - P4 - Tape Float Paint Two Side Remaining Wall OBSOLETE Priority Wall (P4) - Grid Line 10-D Complete 10/17/24 10/17/24 15.0 0.0
100%
0.0
RPL10.INT.CTRC.05940 RPL10.Interior.CTRC - Priority - Grid line 10-16 - P4 - Remaining Hangers & Strut (All Trades) OBSOLETE Priority Wall (P4) - Grid Line 10-D Complete 10/17/24 10/17/24 6.2 0.0
100%
0.0
RPL10.INT.CTRC.05960 RPL10.Interior.CTRC - Priority - Grid line 10-16 - P4 - Fire Alarm/ BMS inwall OBSOLETE Priority Wall (P4) - Grid Line 10-D Complete 10/17/24 10/17/24 5.0 0.0
100%
0.0
RPL10.INT.CTRC.05980 RPL10.Interior.CTRC - Priority - Grid line EF1 - P6 - Frame Pony Wall OBSOLETE Priority Wall (P6) - EF1 Walls Complete 10/17/24 10/17/24 6.2 0.0
100%
0.0
RPL10.INT.CTRC.06000 RPL10.Interior.CTRC - Priority - Grid line EF1 - P6 - MEP OH Pentrations OBSOLETE Priority Wall (P6) - EF1 Walls Complete 10/17/24 10/17/24 6.2 0.0
100%
0.0
RPL10.INT.CTRC.06020 RPL10.Interior.CTRC - Priority - Grid line EF1 - P6 - Frame Remaining Wall OBSOLETE Priority Wall (P6) - EF1 Walls Complete 10/17/24 10/17/24 6.2 0.0
100%
0.0
RPL10.INT.CTRC.06040 RPL10.Interior.CTRC - Priority - Grid line EF1 - P6 - Hang Drywall Pony Wall (both sides) OBSOLETE Priority Wall (P6) - EF1 Walls Complete 10/17/24 10/17/24 7.5 0.0
100%
0.0
RPL10.INT.CTRC.06060 RPL10.Interior.CTRC - Priority - Grid line EF1 - P6 - Tape Float Paint Pony Wall (both sides) OBSOLETE Priority Wall (P6) - EF1 Walls Complete 10/17/24 10/17/24 12.5 0.0
100%
0.0
RPL10.INT.CTRC.06080 RPL10.Interior.CTRC - Priority - Grid line EF1 - P6 - One Side Drywall Remaining Wall OBSOLETE Priority Wall (P6) - EF1 Walls Complete 10/17/24 10/17/24 7.5 0.0
100%
0.0
RPL10.INT.CTRC.06100 RPL10.Interior.CTRC - Priority - Grid line EF1 - P6 - Backing Wall OBSOLETE Priority Wall (P6) - EF1 Walls Complete 10/17/24 10/17/24 5.0 0.0
100%
0.0
RPL10.INT.CTRC.06120 RPL10.Interior.CTRC - Priority - Grid line EF1 - P6 - Mechanical Inwall OBSOLETE Priority Wall (P6) - EF1 Walls Complete 10/17/24 10/17/24 5.0 0.0
100%
0.0
RPL10.INT.CTRC.06140 RPL10.Interior.CTRC - Priority - Grid line EF1 - P6 - Electrical Inwall OBSOLETE Priority Wall (P6) - EF1 Walls Complete 10/17/24 10/17/24 5.0 0.0
100%
0.0
RPL10.INT.CTRC.06160 RPL10.Interior.CTRC - Priority - Grid line EF1 - P6 - Tape Float Paint One Side Remaining Wall OBSOLETE Priority Wall (P6) - EF1 Walls Complete 10/17/24 10/17/24 15.0 0.0
100%
0.0
RPL10.INT.CTRC.06180 RPL10.Interior.CTRC - Priority - Grid line EF1 - P6 - Two Side Drywall Remaining Wall OBSOLETE Priority Wall (P6) - EF1 Walls Complete 10/17/24 10/17/24 7.5 0.0
100%
0.0
RPL10.INT.CTRC.06200 RPL10.Interior.CTRC - Priority - Grid line EF1 - P6 - Tape Float Paint Two Side Remaining Wall OBSOLETE Priority Wall (P6) - EF1 Walls Complete 10/17/24 10/17/24 15.0 0.0
100%
0.0
RPL10.INT.CTRC.06220 RPL10.Interior.CTRC - Priority - Grid line EF1 - P6 - Remaining Hangers & Strut (All Trades) OBSOLETE Priority Wall (P6) - EF1 Walls Complete 10/17/24 10/17/24 6.2 0.0
100%
0.0
RPL10.INT.CTRC.06240 RPL10.Interior.CTRC - Priority - Grid line EF1 - P6 - Fire Alarm/ BMS inwall OBSOLETE Priority Wall (P6) - EF1 Walls Complete 10/17/24 10/17/24 5.0 0.0
100%
0.0
RPL10.INT.CTRC.06260 RPL10.Interior.CTRC - Priority - Grid line EF2 - P6 - Frame Pony Wall OBSOLETE Priority Wall (P6) - EF2 Walls Complete 10/17/24 10/17/24 6.2 0.0
100%
0.0