Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL09 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:12 PM
· 5201 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
1
Completed
0
In Progress
1
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL09.MILE.1570 |
Overall Duration - FDN to SC DHD & DHC - (LOE) | Overall Durations Summary | Not Started | 09/14/26 | 06/22/28 | 553.8 | 553.8 |
|
75.0 |
RPL09.MR.1260 |
RPL09.MR - Mobilization Complete | Make Ready | Not Started | 09/14/26 | 09/14/26 | 0.0 | 0.0 |
|
100.0 |
RPL09.MR.1261 |
RPL09.MR - Site Checklist & Control Handoff | Make Ready | Not Started | 09/14/26 | 09/15/26 | 2.5 | 2.5 |
|
651.2 |
RPL09.SUB.1000 |
RPL09.SubStructure.BLDG - Install Deep/Foundations/Gradebeams/Stemwalls/UG Utilities - WBS Summary | SubStructure | Not Started | 09/14/26 | 11/06/26 | 50.0 | 50.0 |
|
141.2 |
RPL09.SUB.DHAB.01020 |
RPL09.SubStructure.DHAB - Install Deep/Foundations/Gradebeams/Stemwalls/UG Utilities - WBS Summary | DH B & DH A | Not Started | 09/14/26 | 10/30/26 | 43.8 | 43.8 |
|
100.0 |
RPL09.SUB.DHAB.01070 |
RPL09.SubStructure.DHAB - Install UG Utilities - WBS Summary | Underground | Not Started | 09/14/26 | 10/30/26 | 43.8 | 43.8 |
|
100.0 |
RPL09.SUB.DHAB.01090 |
RPL09.SubStructure.DHAB - Install UG Utilities - Electrical/Testing and Pathway Verification and Backfill - Part 1 | Underground | Not Started | 09/14/26 | 10/01/26 | 17.5 | 17.5 |
|
100.0 |
RPL09.SUB.SSB.01000 |
RPL09.SubStructure.SSB - Install Drilled Piers - Grid lines 6-01/6-10 | Foundations | Not Started | 09/14/26 | 09/17/26 | 5.0 | 5.0 |
|
100.0 |
RPL09.SUB.SSB.01010 |
RPL09.SubStructure.SSB - Install Deep/Foundations/Gradebeams/Stemwalls - WBS Summary | Foundations | Not Started | 09/14/26 | 10/13/26 | 27.5 | 27.5 |
|
106.2 |
RPL09.SUB.SSB.01020 |
RPL09.SubStructure.SSB - Install Deep/Foundations/Gradebeams/Stemwalls/UG Utilities - WBS Summary | SSB | Not Started | 09/14/26 | 10/16/26 | 31.2 | 31.2 |
|
102.5 |
RPL09.SUB.SSB.01140 |
RPL09.SubStructure.SSB - Piers Protection Concrete Capping | Foundations | Not Started | 09/14/26 | 09/17/26 | 5.0 | 5.0 |
|
105.0 |
RPL.09.D.92110.XG |
Trestle Construction Ready - SSB-1 - East side | Give Milestones (XREFs) | Not Started | 09/15/26 | 09/15/26 | 0.0 | 0.0 |
|
651.2 |
RPL.09.D.92120.XG |
Trestle Construction Ready - SSB-1 - West side | Give Milestones (XREFs) | Not Started | 09/15/26 | 09/15/26 | 0.0 | 0.0 |
|
651.2 |
RPL.09.D.92130.XG |
Trestle Construction Ready - SSB-1 - North | Give Milestones (XREFs) | Not Started | 09/15/26 | 09/15/26 | 0.0 | 0.0 |
|
651.2 |
RPL09.CFCI.4830 |
RPL09 - Submittals Prep & Submit for Review - Carpet | (CFCI) Div. 09 - Carpet | Not Started | 09/15/26 | 10/12/26 | 25.0 | 25.0 |
|
371.2 |
RPL09.CFCI.4880 |
RPL09 - Submittals Review & Approval -Epoxy Flooring (Spec 09 67 23) XX | (CFCI) Div. 09 - Epoxy Flooring | Not Started | 09/15/26 | 10/12/26 | 25.0 | 25.0 |
|
427.5 |
RPL09.CFCI.5060 |
RPL09 - Fabricate / Deliver - Interior Painting (Spec 09 91 23) XX | (CFCI) Div. 09 - Painting | Not Started | 09/15/26 | 10/12/26 | 25.0 | 25.0 |
|
408.8 |
RPL09.CFCI.5070 |
RPL09 - Submittals Review & Approval - Specialities | (CFCI) Div. 10 - Specialities | Not Started | 09/15/26 | 10/12/26 | 25.0 | 25.0 |
|
357.5 |
RPL09.SUB.SSB.01040 |
RPL09.SubStructure.SSB - Install Foundations/Anchor Bolts and Gradebeams - Grid lines 6-01/6-10 | Foundations | Not Started | 09/15/26 | 10/05/26 | 18.8 | 18.8 |
|
103.8 |
RPL09.SUB.SSB.01050 |
RPL09.SubStructure.SSB - Install UG Utilities - Plumbing/Testing/Backfill - Part 1 | Underground | Not Started | 09/16/26 | 09/28/26 | 11.2 | 11.2 |
|
102.5 |
RPL09.SUB.SSB.01060 |
RPL09.SubStructure.SSB - Install UG Utilities - WBS Summary | Underground | Not Started | 09/16/26 | 10/16/26 | 28.8 | 28.8 |
|
102.5 |
RPL09.SUB.SSB.01090 |
RPL09.SubStructure.SSB - Install UG Utilities - Electrical/Testing and Pathway Verification and Backfill - Part 1 | Underground | Not Started | 09/16/26 | 09/28/26 | 11.2 | 11.2 |
|
102.5 |
RPL09.SUB.DHAB.01000 |
RPL09.SubStructure.DHAB - Install Drilled Piers - Grid lines 6-10/6-23 | Foundations | Not Started | 09/18/26 | 09/24/26 | 6.2 | 6.2 |
|
100.0 |
RPL09.SUB.DHAB.01010 |
RPL09.SubStructure.DHAB - Install Deep/Foundations/Gradebeams/Stemwalls - WBS Summary | Foundations | Not Started | 09/18/26 | 10/15/26 | 25.0 | 25.0 |
|
113.8 |
RPL09.SUB.DHAB.01130 |
RPL09.SubStructure.DHAB - Piers Protection Concrete Capping | Foundations | Not Started | 09/18/26 | 09/24/26 | 6.2 | 6.2 |
|
105.0 |
RPL09.SUB.SSB.01030 |
RPL09.SubStructure.SSB - Foundation For Storm Shelter Rebar CMU | Foundations | Not Started | 09/18/26 | 09/24/26 | 6.2 | 6.2 |
|
110.0 |
RPL09.SUB.DHAB.01030 |
RPL09.SubStructure.DHAB - Install Foundations/Anchor Bolts and Gradebeams - Grid lines 6-10/6-23 | Foundations | Not Started | 09/21/26 | 10/06/26 | 15.0 | 15.0 |
|
117.5 |
RPL.09.D.70120.XR |
External Tie from RPL07 - Interior SSB/Corridor Crew Flow (RPL07.INT.ENDC.01120)* | Internal Milestones (XREFs) | Not Started | 09/22/26 | 09/22/26 | 0.0 | 0.0 |
|
323.8 |
RPL09.CFCI.5370 |
Campus - Fabricate / Deliver - Landscaping / Irrigation | (CFCI) Div. 32 - Landscape/ Irrigation | Not Started | 09/22/26 | 12/17/26 | 75.0 | 75.0 |
|
533.8 |
RPL09.SUB.DHAB.01060 |
RPL09.SubStructure.DHAB - Install UG Utilities - Plumbing/Testing/Backfill - Part 1 | Underground | Not Started | 09/22/26 | 10/01/26 | 10.0 | 10.0 |
|
100.0 |
RPL.09.D.94310.XR |
Water Available for Pressure Testing | Receive Milestones (XREFs) | Not Started | 09/23/26 | 09/23/26 | 0.0 | 0.0 |
|
196.2 |
RPL.09.D.70040.XR |
External Tie from RPL08 - Exterior IMP Crew Flow (RPL08.SKN.N.01050) | Internal Milestones (XREFs) | Not Started | 09/24/26 | 09/24/26 | 0.0 | 0.0 |
|
158.8 |
RPL09.STR.1000 |
RPL09.Structure.BLDG - Erect Steel/Joist/Decking, Remaining UG/SOG - WBS Summary | Structure | Not Started | 09/25/26 | 03/14/27 | 142.5 | 142.5 |
|
180.0 |
RPL09.STR.SSB.01000 |
RPL09.Structure.SSB - Install Storm Shelter Rebar, CMU | Storm Shelter | Not Started | 09/25/26 | 10/06/26 | 10.0 | 10.0 |
|
110.0 |
RPL09.STR.SSB.01010 |
RPL09.Structure.SSB - Erect Steel/Joist/Decking, Remaining UG/SOG - WBS Summary | SSB | Not Started | 09/25/26 | 01/22/27 | 100.0 | 100.0 |
|
196.2 |
RPL09.SUB.DHCD.01000 |
RPL09.SubStructure.DHCD - Install Drilled Piers - Grid lines 6-23/6-28 | Foundations | Not Started | 09/25/26 | 09/30/26 | 5.0 | 5.0 |
|
117.5 |
RPL09.SUB.DHCD.01010 |
RPL09.SubStructure.DHCD - Install Deep/Foundations/Gradebeams/Stemwalls - WBS Summary | Foundations | Not Started | 09/25/26 | 10/16/26 | 20.0 | 20.0 |
|
160.0 |
RPL09.SUB.DHCD.01020 |
RPL09.SubStructure.DHCD - Install Deep/Foundations/Gradebeams/Stemwalls/UG Utilities - WBS Summary | DH D & DH C | Not Started | 09/25/26 | 11/06/26 | 38.8 | 38.8 |
|
141.2 |
RPL09.SUB.DHCD.01130 |
RPL09.SubStructure.DHCD - Piers Protection Concrete Capping | Foundations | Not Started | 09/25/26 | 09/30/26 | 5.0 | 5.0 |
|
118.8 |
RPL09.SUB.SSB.01120 |
RPL09.SubStructure.SSB - Scan, Install Backfill - Grid lines 6-01/6-10 (1st Layer Backfill) | Underground | Not Started | 09/25/26 | 10/01/26 | 6.2 | 6.2 |
|
102.5 |
RPL09.MCUP.LP1.2140 |
RPL09.MCUP.Loop 1 - Mechanical Pipe Hydro Testing | Mechanical UG | Not Started | 09/28/26 | 10/06/26 | 8.8 | 8.8 |
|
192.5 |
RPL09.MCUP.LP2.1000 |
RPL09.MCUP.Loop 2 - Install Foundations, UG Utilities, OFE - WBS Summary | mCup Loop 2 | Not Started | 09/28/26 | 04/16/27 | 171.2 | 171.2 |
|
470.0 |
RPL09.MCUP.LP2.1060 |
RPL09.MCUP.Loop 2 - Install UG Utilities - WBS Summary | Underground | Not Started | 09/28/26 | 10/30/26 | 31.2 | 31.2 |
|
380.0 |
RPL09.MCUP.LP2.1080 |
RPL09.MCUP.Loop 2 - Install Mechanical UG | Mechanical UG | Not Started | 09/28/26 | 10/06/26 | 8.8 | 8.8 |
|
238.8 |
RPL09.SUB.DHCD.01030 |
RPL09.SubStructure.DHCD - Install Foundations/Anchor Bolts and Gradebeams - Grid lines 6-23/6-28 | Foundations | Not Started | 09/28/26 | 10/07/26 | 10.0 | 10.0 |
|
117.5 |
RPL09.SUB.DHCD.01060 |
RPL09.SubStructure.DHCD - Install UG Utilities - Plumbing/Testing/Backfill - Part 1 | Underground | Not Started | 09/29/26 | 10/08/26 | 10.0 | 10.0 |
|
142.5 |
RPL09.SUB.DHCD.01070 |
RPL09.SubStructure.DHCD - Install UG Utilities - WBS Summary | Underground | Not Started | 09/29/26 | 11/06/26 | 36.2 | 36.2 |
|
141.2 |
RPL09.SUB.DHAB.01110 |
RPL09.SubStructure.DHAB - Scan, Install Backfill - Grid lines 6-10/6-23 (1st Layer Backfill) | Underground | Not Started | 10/01/26 | 10/08/26 | 7.5 | 7.5 |
|
100.0 |
RPL09.SUB.DHCD.01090 |
RPL09.SubStructure.DHCD - Install UG Utilities - Electrical/Testing and Pathway Verification and Backfill - Part 1 | Underground | Not Started | 10/01/26 | 10/08/26 | 7.5 | 7.5 |
|
142.5 |
RPL09.SUB.SSB.01070 |
RPL09.SubStructure.SSB - Install Stem Walls - Grid lines 6-01/6-10 | Foundations | Not Started | 10/01/26 | 10/08/26 | 7.5 | 7.5 |
|
106.2 |
RPL09.SUB.SSB.01160 |
RPL09.SubStructure.SSB - Scan, Install Backfill - Grid lines 6-01/6-10 (2nd Layer Backfill) | Underground | Not Started | 10/02/26 | 10/07/26 | 5.0 | 5.0 |
|
102.5 |
RPL09.SUB.SSB.01110 |
RPL09.SubStructure.SSB - Install UG Utilities - BMS/EPMS/Testing and Pathway Verification and Backfill | Underground | Not Started | 10/05/26 | 10/16/26 | 12.5 | 12.5 |
|
102.5 |
RPL09.SUB.DHAB.01040 |
RPL09.SubStructure.DHAB - Install Stem Walls - Grid lines 6-10/6-23 | Foundations | Not Started | 10/06/26 | 10/13/26 | 7.5 | 7.5 |
|
113.8 |
RPL09.SUB.DHCD.01040 |
RPL09.SubStructure.DHCD - Install Stem walls - Grid lines 6-23/6-28 | Foundations | Not Started | 10/06/26 | 10/13/26 | 7.5 | 7.5 |
|
116.2 |
RPL09.STR.SSB.01020 |
RPL09.Structure.SSB - Install Storm Shelter Steel and Decking | Storm Shelter | Not Started | 10/07/26 | 10/13/26 | 6.2 | 6.2 |
|
110.0 |
RPL09.SUB.SSB.01200 |
RPL09.SubStructure.SSB - Install UG Utilities - Electrical/Testing and Pathway Verification and Backfill - Part 2 | Underground | Not Started | 10/07/26 | 10/16/26 | 10.0 | 10.0 |
|
102.5 |
RPL09.SUB.SSB.01180 |
RPL09.SubStructure.SSB - Install UG Utilities - Plumbing/Testing/Backfill - Part 2 | Underground | Not Started | 10/08/26 | 10/16/26 | 8.8 | 8.8 |
|
102.5 |
RPL09.SUB.DHAB.01150 |
RPL09.SubStructure.DHAB - Scan, Install Backfill - Grid lines 6-10/6-23 (2nd Layer Backfill) | Underground | Not Started | 10/09/26 | 10/16/26 | 7.5 | 7.5 |
|
100.0 |
RPL09.SUB.DHCD.01110 |
RPL09.SubStructure.DHCD - Scan, Install Backfill - Grid lines 6-23/6-28 (1st Layer Backfill) | Underground | Not Started | 10/09/26 | 10/16/26 | 7.5 | 7.5 |
|
141.2 |
RPL09.SUB.SSB.01080 |
RPL09.SubStructure.SSB - Strip Form Work And Apply Water Proofing System | Foundations | Not Started | 10/09/26 | 10/13/26 | 3.8 | 3.8 |
|
106.2 |
RPL09.SUB.SSB.01100 |
RPL09.SubStructure.SSB - Install Grounding Wire - Grid lines 6-01/6-10 | Foundations | Not Started | 10/09/26 | 10/13/26 | 3.8 | 3.8 |
|
106.2 |
RPL.09.D.70100.XR |
External Tie from RPL07 - mCup Equipment Crane Crew Flow (RPL08.MCUP.LP2.1500) | Internal Milestones (XREFs) | Not Started | 10/12/26 | 10/12/26 | 0.0 | 0.0 |
|
231.2 |
RPL09.MCUP.LP1.1300 |
RPL09.MCUP.Loop 1 - Install UG Generator Conduit Feed | Electrical UG | Not Started | 10/12/26 | 10/15/26 | 5.0 | 5.0 |
|
227.5 |
RPL09.MCUP.LP1.2120 |
RPL09.MCUP.Loop 1 - Flow Fill & Backfill (Loop 1 & 2) | Foundations | Not Started | 10/12/26 | 11/04/26 | 22.5 | 22.5 |
|
188.8 |
RPL09.MCUP.LP2.1100 |
RPL09.MCUP.Loop 2 - Install Electrical UG | Electrical UG | Not Started | 10/12/26 | 10/30/26 | 18.8 | 18.8 |
|
226.2 |
RPL09.MCUP.LP2.1140 |
RPL09.MCUP.Loop 2 - Install Controls/EPMS/BMS UG | Controls/EPMS/BMS UG | Not Started | 10/12/26 | 10/30/26 | 18.8 | 18.8 |
|
235.0 |
RPL09.CFCI.5110 |
RPL09 - Submittals Review & Approval - Carpet | (CFCI) Div. 09 - Carpet | Not Started | 10/13/26 | 11/09/26 | 25.0 | 25.0 |
|
371.2 |
RPL09.CFCI.5140 |
RPL09 - Fabricate / Deliver -Epoxy Flooring (Spec 09 67 23) XX | (CFCI) Div. 09 - Epoxy Flooring | Not Started | 10/13/26 | 11/02/26 | 18.8 | 18.8 |
|
427.5 |
RPL09.CFCI.5260 |
RPL09 - Fabricate / Deliver - Specialities | (CFCI) Div. 10 - Specialities | Not Started | 10/13/26 | 11/24/26 | 37.5 | 37.5 |
|
357.5 |
RPL09.MCUP.LP1.1100 |
RPL09.MCUP.Loop 1 - F/R/P Pads (12'' larger) | Foundations | Not Started | 10/14/26 | 11/10/26 | 25.0 | 25.0 |
|
188.8 |
RPL09.STR.SSB.01030 |
RPL09.Structure.SSB - Install Storm Shelter F/R/P Deck | Storm Shelter | Not Started | 10/14/26 | 10/20/26 | 6.2 | 6.2 |
|
110.0 |
RPL09.SUB.DHAB.01050 |
RPL09.SubStructure.DHAB - Strip Form Work And Apply Water Proofing System | Foundations | Not Started | 10/14/26 | 10/15/26 | 2.5 | 2.5 |
|
113.8 |
RPL09.SUB.DHAB.01080 |
RPL09.SubStructure.DHAB - Install Grounding Wire - Grid lines 6-10/6-23 | Foundations | Not Started | 10/14/26 | 10/15/26 | 2.5 | 2.5 |
|
113.8 |
RPL09.SUB.DHCD.01050 |
RPL09.SubStructure.DHCD - Strip Form Work And Apply Water Proofing System | Foundations | Not Started | 10/14/26 | 10/16/26 | 3.8 | 3.8 |
|
160.0 |
RPL09.SUB.DHCD.01080 |
RPL09.SubStructure.DHCD - Install Grounding Wire - Grid lines 6-23/6-28 | Foundations | Not Started | 10/15/26 | 10/16/26 | 2.5 | 2.5 |
|
160.0 |
RPL06.SUCC |
SUCC | Obsolete | Complete | 10/17/26 | 10/17/26 | 0.0 | 0.0 |
|
0.0 |
RPL09.LOG.1340 |
Steel Crane #1 Mobilization | Steel Crane 1 | Not Started | 10/19/26 | 10/19/26 | 0.0 | 0.0 |
|
203.8 |
RPL09.LOG.1360 |
Steel Crane #2 Mobilization | Steel Crane 2 | Not Started | 10/19/26 | 10/19/26 | 0.0 | 0.0 |
|
203.8 |
RPL09.STR.SSB.01050 |
RPL09.Structure.SSB - Erect Steel/Joist/Decking - WBS Summary | Steel and Decking | Not Started | 10/19/26 | 11/20/26 | 30.0 | 30.0 |
|
98.8 |
RPL09.STR.SSB.01210 |
RPL09.Structure.SSB - Crane Road Prep - Grid lines 6-01/6-10 | Steel and Decking | Not Started | 10/19/26 | 10/21/26 | 3.8 | 3.8 |
|
102.5 |
RPL09.SUB.DHAB.01100 |
RPL09.SubStructure.DHAB - Install UG Utilities - BMS/EPMS/Testing and Pathway Verification and Backfill (new GS scope) | Underground | Not Started | 10/19/26 | 10/30/26 | 12.5 | 12.5 |
|
100.0 |
RPL09.SUB.DHAB.01170 |
RPL09.SubStructure.DHAB - Install UG Utilities - Plumbing/Testing/Backfill - Part 2 | Underground | Not Started | 10/19/26 | 10/28/26 | 10.0 | 10.0 |
|
100.0 |
RPL09.SUB.DHCD.01190 |
RPL09.SubStructure.DHCD - Scan, Install Backfill - Grid lines 6-23/6-28 (2nd Layer Backfill) | Underground | Not Started | 10/19/26 | 10/26/26 | 7.5 | 7.5 |
|
141.2 |
RPL09.STR.SSB.01230 |
RPL09.Structure.SSB - Steel Shake out - Grid lines 6-01/6-10 | Steel and Decking | Not Started | 10/22/26 | 10/28/26 | 6.2 | 6.2 |
|
102.5 |
RPL09.SUB.DHAB.01190 |
RPL09.SubStructure.DHAB - Install UG Utilities - Electrical/Testing and Pathway Verification and Backfill - Part 2 | Underground | Not Started | 10/22/26 | 10/29/26 | 7.5 | 7.5 |
|
100.0 |
RPL.09.D.70060.XR |
External Tie from RPL08 - Roofing DenseDeck & Flame Down Crew Flow (RPL08.SKN.DHCD.01090) | Internal Milestones (XREFs) | Not Started | 10/26/26 | 10/26/26 | 0.0 | 0.0 |
|
142.5 |
RPL09.MCUP.LP2.1120 |
RPL09.MCUP.Loop 2 - Install Grounding Wire, Grounding Rod, Exothermic Weld & Backfill | Grounding UG | Not Started | 10/26/26 | 10/30/26 | 6.2 | 6.2 |
|
226.2 |
RPL.09.D.70080.XR |
External Tie from RPL08 - EY MV Concrete Foundations Crew Flow (RPL08.EY.DHC.01010)* | Internal Milestones (XREFs) | Not Started | 10/27/26 | 10/27/26 | 0.0 | 0.0 |
|
191.2 |
RPL09.MCUP.LP2.1260 |
RPL09.MCUP.Loop 2 - Install UG Generator Conduit Feed | Electrical UG | Not Started | 10/27/26 | 10/30/26 | 5.0 | 5.0 |
|
380.0 |
RPL09.SUB.DHCD.01150 |
RPL09.SubStructure.DHCD - Install UG Utilities - Plumbing/Testing/Backfill - Part 2 | Underground | Not Started | 10/27/26 | 11/04/26 | 8.8 | 8.8 |
|
141.2 |
RPL09.SUB.DHCD.01100 |
RPL09.SubStructure.DHCD - Install UG Utilities - BMS/EPMS/Testing and Pathway Verification and Backfill (new GS Scope) | Underground | Not Started | 10/28/26 | 11/06/26 | 10.0 | 10.0 |
|
141.2 |
RPL09.SUB.DHCD.01170 |
RPL09.SubStructure.DHCD - Install UG Utilities - Electrical/Testing and Pathway Verification and Backfill - Part 2 | Underground | Not Started | 10/29/26 | 11/05/26 | 7.5 | 7.5 |
|
141.2 |
RPL09.STR.DHAB.01010 |
RPL09.Structure.DHAB - Erect Steel/Joist/Decking - WBS Summary | Steel and Decking | Not Started | 11/02/26 | 12/11/26 | 33.8 | 33.8 |
|
105.0 |
RPL09.STR.DHAB.01020 |
RPL09.Structure.DHAB - Erect Steel/Joist/Decking, Remaining UG/SOG - WBS Summary | DH B & DH A | Not Started | 11/02/26 | 02/20/27 | 91.2 | 91.2 |
|
118.8 |
RPL09.STR.DHAB.01200 |
RPL09.Structure.DHAB - Crane Road Prep - Grid Lines 6-11/6-23 | Steel and Decking | Not Started | 11/02/26 | 11/04/26 | 3.8 | 3.8 |
|
115.0 |
GCD.RPL09.1360 |
Steel Erection Start - RPL09 | Construction Milestones | Not Started | 11/03/26 | 11/03/26 | 0.0 | 0.0 |
|
458.8 |
RPL09.CFCI.3560 |
RPL09 - Fabricate / Deliver - Structural Steel | (CFCI) Div. 05 - Structural Steel | Not Started | 11/03/26 | 11/03/26 | 0.0 | 0.0 |
|
98.8 |
RPL09.STR.SSB.01040 |
RPL09.Structure.SSB - Install Erect Steel Columns and Beams, Erect Joist - Grid lines 6-01/6-10 | Steel and Decking | Not Started | 11/03/26 | 11/16/26 | 11.2 | 11.2 |
|
98.8 |
RPL09.STR.DHAB.01220 |
RPL09.Structure.DHAB - Steel Shake out - Grid Lines 6-11/6-23 | Steel and Decking | Not Started | 11/05/26 | 11/12/26 | 6.2 | 6.2 |
|
115.0 |
RPL09.STR.DHCD.01010 |
RPL09.Structure.DHCD - Erect Steel/Joist/Decking - WBS Summary | Steel and Decking | Not Started | 11/09/26 | 12/24/26 | 38.8 | 38.8 |
|
121.2 |