Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL09 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:12 PM · 5201 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
0
Completed
0
In Progress
0
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL09.STR.DHCD.01020 RPL09.Structure.DHCD - Erect Steel/Joist/Decking, Remaining UG/SOG - WBS Summary DH D & DH C Not Started 11/09/26 03/14/27 103.8 103.8
0%
180.0
RPL09.STR.DHCD.01170 RPL09.Structure.DHCD - Crane Road Prep - Grid Lines 6-23/6-28 Steel and Decking Not Started 11/09/26 11/12/26 3.8 3.8
0%
141.2
RPL09.CFCI.5290 RPL09 - Fabricate / Deliver - Carpet Tile (CFCI) Div. 09 - Carpet Not Started 11/10/26 01/11/27 50.0 50.0
0%
371.2
RPL09.MCUP.LP1.1180 RPL09.MCUP.Loop 1 - Cure for Pads Foundations Not Started 11/11/26 11/17/26 8.8 8.8
0%
280.0
RPL09.LOG.1000 MCUP 500 Ton Crane Mobilization 300 Ton Crane Not Started 11/12/26 11/17/26 5.0 5.0
0%
200.0
RPL09.MCUP.LP1.1200 RPL09.MCUP.Loop 1 - OFE - WBS Summary OFE Not Started 11/12/26 01/15/27 53.8 53.8
0%
188.8
RPL09.MCUP.LP1.2160 RPL09.MCUP.Loop 1 - Set Facility Water Pipe Rack (mCUP1) OFE Not Started 11/12/26 11/25/26 12.5 12.5
0%
200.0
RPL09.MCUP.LP2.1020 RPL09.MCUP.Loop 2 - Install Foundations - WBS Summary Foundations Not Started 11/12/26 12/02/26 16.2 16.2
0%
351.2
RPL09.MCUP.LP2.1160 RPL09.MCUP.Loop 2 - F/R/P Pads (12'' larger) Foundations Not Started 11/12/26 11/25/26 12.5 12.5
0%
350.0
RPL09.LOG.1120 Dry Cooler 230 Ton Crane Mobilization 100 Ton Crane Not Started 11/13/26 11/17/26 3.8 3.8
0%
190.0
RPL09.STR.DHCD.01190 RPL09.Structure.DHCD - Steel Shake out - Grid Lines 6-23/6-28 Steel and Decking Not Started 11/13/26 11/19/26 6.2 6.2
0%
141.2
ICM.B9.1830 [SSDCB4] Delivery of PTX - Pad Mounted Transformers (First Delivery) Construction Not Started 11/16/26 11/16/26 0.0 0.0
0%
222.5
ICM.B9.1835 [SSDCB4] Delivery of FCA - Fan Coil Assembly (First Delivery) Construction Not Started 11/16/26 11/16/26 0.0 0.0
0%
191.2
ICM.B9.1860 [SSDCB4] Delivery of Dry Cooling Towers (First Delivery) Construction Not Started 11/16/26 11/16/26 0.0 0.0
0%
191.2
RPL09.STR.DHAB.01000 RPL09.Structure.DHAB - Install Erect Steel Columns and Beams, Erect Joist Grid Lines 6-11/6-23 Steel and Decking Not Started 11/17/26 11/30/26 10.0 10.0
0%
112.5
RPL09.STR.SSB.01060 RPL09.Structure.SSB - Install Decking & Detailing turnover #1 - Grid lines 6-01/6-04 Steel and Decking Not Started 11/17/26 11/20/26 5.0 5.0
0%
98.8
GCD.RPL09.1182 Start mCUP Unit Set-In-Place - RPL09 Construction Milestones Not Started 11/18/26 11/18/26 0.0 0.0
0%
446.2
RPL09.MCUP.FWM.01000 RPL09.MCUP.FWM - Install PTX FWM Not Started 11/18/26 11/20/26 3.8 3.8
0%
221.2
RPL09.MCUP.FWM.01010 RPL09.MCUP.FWM - Install FWM FWM Not Started 11/18/26 11/20/26 3.8 3.8
0%
221.2
RPL09.MCUP.FWM.01030 RPL09.MCUP.FWM - Install MVS FWM Not Started 11/18/26 11/20/26 3.8 3.8
0%
221.2
RPL09.MCUP.LP1.1220 RPL09.MCUP.Loop 1 - Set mCup #1 & #2 - Dry Coolers (12) (4 per week) OFE Not Started 11/18/26 12/10/26 18.8 18.8
0%
190.0
RPL09.MCUP.LP1.1340 RPL09.MCUP.Loop 1 - Set mCUPs XXMY.MCUP.01 (1 per 5 days) OFE Not Started 11/18/26 11/24/26 6.2 6.2
0%
200.0
RPL09.SKIN.01000 RPL09.SKIN.BLDG - Install Insulated Metal Panels (IMP), Roof, Windows, Doors, Louvers - WBS Summary Skin Not Started 11/19/26 11/04/27 301.2 301.2
0%
256.2
RPL09.SKN.W.01000 RPL09.SKIN - Install Metal Panel Sealant & Starter Flashing - West North South East IMP System Not Started 11/19/26 12/04/26 12.5 12.5
0%
111.2
RPL09.STR.DHAB.01015 RPL09.Structure.DHAB - Install Decking & Detailing turnover #2 - Grid lines 6-04/6-07 Steel and Decking Not Started 11/23/26 11/25/26 3.8 3.8
0%
98.8
RPL09.MCUP.LP1.1380 RPL09.MCUP.Loop 1 - Set mCUPs XXMY.MCUP.02 (1 per 5 days) OFE Not Started 11/25/26 12/03/26 6.2 6.2
0%
200.0
RPL09.MCUP.LP2.1180 RPL09.MCUP.Loop 2 - Cure for Pads Foundations Not Started 11/26/26 12/02/26 8.8 8.8
0%
517.5
GCD.RPL09.1380 IMP Start - RPL09 Construction Milestones Not Started 11/30/26 11/30/26 0.0 0.0
0%
438.8
RPL09.MCUP.LP1.2180 RPL09.MCUP.Loop 1 - Set Facility Water Pipe Rack (mCUP2) OFE Not Started 11/30/26 12/09/26 10.0 10.0
0%
200.0
RPL09.SKN.W.01005 RPL09.SKIN.West - Install IMP - Flashing,Panels & Caulking - Gird lines 6A/6F (with temp closures for openings) DBC Move 1 - Grid (6-01 / 6-07) Not Started 11/30/26 12/01/26 2.5 2.5
0%
107.5
RPL09.SKN.W.01010 RPL09.SKIN.West - Install IMP Insulated Metal Panels System - WBS Summary DBC Move 1 - Grid (6-01 / 6-07) Not Started 11/30/26 12/09/26 10.0 10.0
0%
111.2
RPL09.STR.DHAB.01025 RPL09.Structure.DHAB - Install Decking & Detailing turnover #3 - Grid lines 6-07/6-10 Steel and Decking Not Started 11/30/26 12/02/26 3.8 3.8
0%
98.8
RPL09.STR.DHCD.01000 RPL09.Structure.DHCD - Install Erect Steel Columns and Beams, Erect Joist - Grid Lines 6-23/6-28 Steel and Decking Not Started 12/01/26 12/09/26 8.8 8.8
0%
135.0
RPL09.EY.SSB.01000 RPL09.EY.SSB - Install F/R/P Equipment Pads Foundations Not Started 12/02/26 12/15/26 12.5 12.5
0%
166.2
RPL09.EY.SSB.01010 RPL09.EY.SSB - Install Foundations - WBS Summary Foundations Not Started 12/02/26 12/22/26 18.8 18.8
0%
197.5
RPL09.EY.SSB.01020 RPL09.EY.SSB - Install Foundations, UG Utilities, OFE - WBS Summary EY.SSB Not Started 12/02/26 11/15/27 300.0 300.0
0%
286.2
RPL09.EY.SSB.01030 RPL09.EY.BLDG - Install Foundations, UG Utilities, OFE- WBS Summary Electrical Yard Not Started 12/02/26 02/02/28 363.8 363.8
0%
222.5
RPL09.EY.SSB.01100 RPL09.EY.SSB - OFE - WBS Summary OFE Not Started 12/02/26 01/11/27 33.8 33.8
0%
191.2
RPL09.EY.SSB.01380 RPL09.EY.SSB - Install Wall Mounted AC units (5) - CFCI OFE Not Started 12/02/26 12/10/26 8.8 8.8
0%
213.8
RPL09.EY.SSB.02020 RPL09.EY.SSB - Install Temp Conditioning Units - CFCI Temp Conditions Not Started 12/02/26 12/08/26 6.2 6.2
0%
153.8
RPL09.SKN.N.01000 RPL09.SKIN.North - Install IMP - Flashing,Panels & Caulking - Grid lines 6-01/6-07 (with temp closures for openings) DBC Move 1 - Grid (6-01 / 6-07) Not Started 12/02/26 12/04/26 3.8 3.8
0%
111.2
RPL09.SKN.SSB.01000 RPL09.SKIN.SSB - Install Temp Doors Glazing, Doors and Ext Devices Not Started 12/02/26 12/03/26 2.5 2.5
0%
396.2
RPL09.SKN.SSB.01020 RPL09.SKIN.SSB - IMP, Roof, Windows, Doors, Ext Devices - WBS Summary SSB Not Started 12/02/26 04/23/27 122.5 122.5
0%
288.8
RPL09.SKN.SSB.01030 RPL09.SKIN.SSB - Install Windows, Doors, Louvers and Ext Devices - WBS Summary Glazing, Doors and Ext Devices Not Started 12/02/26 04/23/27 122.5 122.5
0%
288.8
RPL09.SKN.SSB.01040 RPL09.SKIN.SSB - Install Louvers Glazing, Doors and Ext Devices Not Started 12/02/26 12/08/26 6.2 6.2
0%
386.2
RPL09.SKN.SSB.01050 RPL09.SKIN.SSB - Install Lighting Glazing, Doors and Ext Devices Not Started 12/02/26 12/07/26 5.0 5.0
0%
387.5
RPL09.SKN.SSB.01080 RPL09.SKIN.SSB - Install Roof System - Exterior Wall Sheathing and EJ Roofing Not Started 12/02/26 12/08/26 6.2 6.2
0%
107.5
RPL09.SKN.SSB.01090 RPL09.SKIN.SSB - Install Roof System - WBS Summary Roofing Not Started 12/02/26 01/19/27 40.0 40.0
0%
146.2
RPL09.SKN.SSB.01170 RPL09.SKIN.SSB - Install Blocking of Canopy & Backing of Exterior Wall Glazing, Doors and Ext Devices Not Started 12/02/26 12/08/26 6.2 6.2
0%
173.8
RPL09.LOG.1020 MCUP 500 Ton Crane Movement 1 300 Ton Crane Not Started 12/03/26 12/03/26 0.0 0.0
0%
200.0
RPL09.STR.DHAB.01030 RPL09.Structure.DHAB - Install Decking & Detailing turnover #4 - Grid lines 6-10/6-14 Steel and Decking Not Started 12/03/26 12/08/26 5.0 5.0
0%
98.8
RPL09.MCUP.LP1.1400 RPL09.MCUP.Loop 1 - Tie-ins - WBS Summary Tie-ins Not Started 12/04/26 02/08/27 55.0 55.0
0%
462.5
RPL09.MCUP.LP1.1440 RPL09.MCUP.Loop 1 - Tie-in Mechanical - WBS Summary Tie-Ins Mechanical Not Started 12/04/26 01/22/27 41.2 41.2
0%
190.0
RPL09.MCUP.LP1.1460 RPL09.MCUP.Loop 1 - Tie-in Mechanical #1 Tie-Ins Mechanical Not Started 12/04/26 12/24/26 18.8 18.8
0%
212.5
RPL09.MCUP.LP1.1500 RPL09.MCUP.Loop 1 - Set mCUPs XXMY.MCUP.03 (1 per 5 days) OFE Not Started 12/04/26 12/10/26 6.2 6.2
0%
200.0
RPL09.SKN.S.01000 RPL09.SKIN.South - Install IMP - Flashing,Panels & Caulking - Grid lines 6-01/6-07 (with temp closures for openings) DBC Move 1 - Grid (6-01 / 6-07) Not Started 12/07/26 12/09/26 3.8 3.8
0%
111.2
RPL09.SKN.W.01040 RPL09.SKIN.West - Secure All Exterior Mounted Boxes and Devices on Skin IMP System Not Started 12/07/26 12/18/26 12.5 12.5
0%
425.0
RPL.09.D.94510.XR Storm Drain Available for Roof Drain Tie-ins Receive Milestones (XREFs) Not Started 12/08/26 12/08/26 0.0 0.0
0%
108.8
RPL09.SKN.SSB.01070 RPL09.SKIN.SSB - Install Security Glazing, Doors and Ext Devices Not Started 12/08/26 12/09/26 2.5 2.5
0%
387.5
RPL09.EY.SSB.02040 RPL09.EY.SSB - Install Temp Duct to Permanent Duct Temp Conditions Not Started 12/09/26 12/15/26 6.2 6.2
0%
153.8
RPL09.SKN.SSB.01060 RPL09.SKIN.SSB - Install Awning over Doors Glazing, Doors and Ext Devices Not Started 12/09/26 12/15/26 6.2 6.2
0%
392.5
RPL09.SKN.SSB.01075 RPL09.SKIN.SSB - QC Blocking Glazing, Doors and Ext Devices Not Started 12/09/26 12/10/26 2.5 2.5
0%
383.8
RPL09.SKN.SSB.01100 RPL09.SKIN.SSB - Install Roof System - Install Temp Flashing at EJ Roofing Not Started 12/09/26 12/10/26 2.5 2.5
0%
152.5
RPL09.SKN.SSB.01110 RPL09.SKIN.SSB - Install Roof System - DenseDeck & Flame Down Roofing Not Started 12/09/26 12/17/26 8.8 8.8
0%
107.5
RPL09.STR.DHAB.01035 RPL09.Structure.DHAB - Install Decking & Detailing turnover #5 - Grid lines 6-14/6-18 Steel and Decking Not Started 12/09/26 12/11/26 3.8 3.8
0%
105.0
RPL09.STR.SSB.01100 RPL09.Structure.SSB - Adjust MEP Verts and Grounding wire Prep Not Started 12/09/26 12/15/26 6.2 6.2
0%
98.8
RPL09.STR.SSB.01110 RPL09.Structure.SSB - Install Remaining UG and Subgrade Prep - WBS Summary Prep Not Started 12/09/26 12/29/26 17.5 17.5
0%
98.8
RPL09.EY.ENDC.01020 RPL09.EY.End - Install Foundations, UG Utilities, OFE - WBS Summary EY.EC Not Started 12/10/26 02/02/28 356.2 356.2
0%
222.5
RPL09.EY.ENDC.01300 RPL09.EY.DHD.T1 - Install Shallow Tent UG Tent 1 Not Started 12/10/26 12/14/26 3.8 3.8
0%
141.2
RPL09.LOG.1140 Dry Cooler 230 Ton Crane Movement 01 100 Ton Crane Not Started 12/10/26 12/10/26 0.0 0.0
0%
190.0
RPL09.LOG.1860 Steel Crane #1 Demobilzation Steel Crane 1 Not Started 12/10/26 12/10/26 0.0 0.0
0%
160.0
RPL09.LOG.1880 Steel Crane #2 Demobilization Steel Crane 2 Not Started 12/10/26 12/10/26 0.0 0.0
0%
160.0
RPL09.MCUP.LP1.2200 RPL09.MCUP.Loop 1 - Set Facility Water Pipe Rack (mCUP3) OFE Not Started 12/10/26 12/21/26 10.0 10.0
0%
200.0
RPL09.MCUP.LP1.1280 RPL09.MCUP.Loop 1 - Set MTRs (4 per day) OFE Not Started 12/11/26 12/17/26 6.2 6.2
0%
190.0
RPL09.MCUP.LP1.1320 RPL09.MCUP.Loop 1 - Set mCup #3 & #4 - Dry Coolers (12) (4 per week) OFE Not Started 12/11/26 01/04/27 18.8 18.8
0%
190.0
RPL09.MCUP.LP1.1620 RPL09.MCUP.Loop 1 - Set mCUPs XXMY.MCUP.04 (1 per 5 days) OFE Not Started 12/11/26 12/17/26 6.2 6.2
0%
200.0
RPL09.MCUP.LP1.1760 RPL09.MCUP.Loop 1 - Tie-in Mechanical #2 Tie-Ins Mechanical Not Started 12/11/26 01/04/27 18.8 18.8
0%
206.2
RPL09.STR.DHCD.01015 RPL09.Structure.DHCD - Install Decking & Detailing turnover #6 - Grid lines 6-18/6-21 Steel and Decking Not Started 12/14/26 12/16/26 3.8 3.8
0%
105.0
RPL09.EY.ENDC.01360 RPL09.EY.DHD.T2 - Install Shallow Tent UG Tent 2 Not Started 12/15/26 12/17/26 3.8 3.8
0%
141.2
RPL09.EY.ENDC.1310 RPL09.EY.DHD.T1 - Install Final Grading Tent 1 Not Started 12/15/26 12/16/26 2.5 2.5
0%
142.5
RPL09.EY.SSB.01040 RPL09.EY.SSB - Install Electrical UG Underground Not Started 12/16/26 12/22/26 6.2 6.2
0%
166.2
RPL09.EY.SSB.01050 RPL09.EY.SSB - Install Cure (High Early Mix) Foundations Not Started 12/16/26 12/22/26 8.8 8.8
0%
288.8
RPL09.EY.SSB.01060 RPL09.EY.SSB - Install UG Utilities - WBS Summary Underground Not Started 12/16/26 01/14/27 25.0 25.0
0%
178.8
RPL09.EY.SSB.01180 RPL09.EY.SSB - Tie-ins - WBS Summary Tie-ins Not Started 12/16/26 04/12/27 98.8 98.8
0%
136.2
RPL09.EY.SSB.01400 RPL09.EY.SSB - Install Duct/ insulation into the building Main (include penetration detail) Tie-ins Not Started 12/16/26 01/07/27 18.8 18.8
0%
172.5
RPL09.STR.SSB.01120 RPL09.Structure.SSB - Install AB final grade and Vapor Barrier Prep Not Started 12/16/26 12/22/26 6.2 6.2
0%
98.8
RPL.09.D.94120.XG Ready for MV Cable Pull mCUP - Loop#1 (Qty 4)* Give Milestones (XREFs) Not Started 12/17/26 12/17/26 0.0 0.0
0%
571.2
RPL09.EY.ENDC.1330 RPL09.EY.DHD.T1 - Install F/R/P Tent1 Slab Tent 1 Not Started 12/17/26 12/23/26 6.2 6.2
0%
142.5
RPL09.LOG.1040 MCUP 500 Ton Crane Movement 2 300 Ton Crane Not Started 12/17/26 12/17/26 0.0 0.0
0%
341.2
RPL09.MCUP.LP1.1240 RPL09.MCUP.Loop 1 - Set GS.IDF Hut (1x GS.IDF) XX01 (ROJ12.16.26) OFE Not Started 12/17/26 12/23/26 6.2 6.2
0%
188.8
RPL09.SKN.N.01010 RPL09.SKIN.North - Install IMP Insulated Metal Panels System - WBS Summary DBC Move 2 - Grid (6-07 / 6-21) Not Started 12/17/26 01/12/27 21.2 21.2
0%
498.8
RPL09.SKN.S.01030 RPL09.SKIN.South - Install IMP - Flashing,Panels & Caulking - Grid lines 6-07/6-14 (with temp closures for openings) DBC Move 2 - Grid (6-07 / 6-21) Not Started 12/17/26 12/21/26 3.8 3.8
0%
105.0
RPL09.STR.DHCD.01025 RPL09.Structure.DHCD - Install Decking & Detailing turnover #7 - Grid lines 6-21/6-25 Steel and Decking Not Started 12/17/26 12/21/26 3.8 3.8
0%
113.8
RPL09.EY.ENDC.1610 RPL09.EY.DHD.T2 - Install Final Grading Tent 2 Not Started 12/18/26 12/21/26 2.5 2.5
0%
141.2
RPL09.EY.SSB.01420 RPL09.EY.SSB - Install Grounding UG Underground Not Started 12/18/26 12/24/26 6.2 6.2
0%
188.8
RPL09.MCUP.LP1.1360 RPL09.MCUP.Loop 1 - Set Electrical Skids #1 OFE Not Started 12/18/26 12/21/26 2.5 2.5
0%
196.2
RPL09.MCUP.LP2.1200 RPL09.MCUP.Loop 2 - OFE - WBS Summary OFE Not Started 12/18/26 01/29/27 35.0 35.0
0%
331.2
RPL09.MCUP.LP2.1280 RPL09.MCUP.Loop 2 - Set mCUPs XXMY.MCUP.05 (1 per 5 days) OFE Not Started 12/18/26 12/24/26 6.2 6.2
0%
341.2
RPL09.SKN.SSB.01120 RPL09.SKIN.SSB - Install Scupper and Downspouts Glazing, Doors and Ext Devices Not Started 12/18/26 12/24/26 6.2 6.2
0%
390.0
RPL09.SKN.SSB.01130 RPL09.SKIN.SSB - Install Roof System - Final Roof Roofing Not Started 12/18/26 01/11/27 18.8 18.8
0%
146.2