Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL09 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:12 PM
· 5201 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
0
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL09.STR.DHCD.01020 |
RPL09.Structure.DHCD - Erect Steel/Joist/Decking, Remaining UG/SOG - WBS Summary | DH D & DH C | Not Started | 11/09/26 | 03/14/27 | 103.8 | 103.8 |
|
180.0 |
RPL09.STR.DHCD.01170 |
RPL09.Structure.DHCD - Crane Road Prep - Grid Lines 6-23/6-28 | Steel and Decking | Not Started | 11/09/26 | 11/12/26 | 3.8 | 3.8 |
|
141.2 |
RPL09.CFCI.5290 |
RPL09 - Fabricate / Deliver - Carpet Tile | (CFCI) Div. 09 - Carpet | Not Started | 11/10/26 | 01/11/27 | 50.0 | 50.0 |
|
371.2 |
RPL09.MCUP.LP1.1180 |
RPL09.MCUP.Loop 1 - Cure for Pads | Foundations | Not Started | 11/11/26 | 11/17/26 | 8.8 | 8.8 |
|
280.0 |
RPL09.LOG.1000 |
MCUP 500 Ton Crane Mobilization | 300 Ton Crane | Not Started | 11/12/26 | 11/17/26 | 5.0 | 5.0 |
|
200.0 |
RPL09.MCUP.LP1.1200 |
RPL09.MCUP.Loop 1 - OFE - WBS Summary | OFE | Not Started | 11/12/26 | 01/15/27 | 53.8 | 53.8 |
|
188.8 |
RPL09.MCUP.LP1.2160 |
RPL09.MCUP.Loop 1 - Set Facility Water Pipe Rack (mCUP1) | OFE | Not Started | 11/12/26 | 11/25/26 | 12.5 | 12.5 |
|
200.0 |
RPL09.MCUP.LP2.1020 |
RPL09.MCUP.Loop 2 - Install Foundations - WBS Summary | Foundations | Not Started | 11/12/26 | 12/02/26 | 16.2 | 16.2 |
|
351.2 |
RPL09.MCUP.LP2.1160 |
RPL09.MCUP.Loop 2 - F/R/P Pads (12'' larger) | Foundations | Not Started | 11/12/26 | 11/25/26 | 12.5 | 12.5 |
|
350.0 |
RPL09.LOG.1120 |
Dry Cooler 230 Ton Crane Mobilization | 100 Ton Crane | Not Started | 11/13/26 | 11/17/26 | 3.8 | 3.8 |
|
190.0 |
RPL09.STR.DHCD.01190 |
RPL09.Structure.DHCD - Steel Shake out - Grid Lines 6-23/6-28 | Steel and Decking | Not Started | 11/13/26 | 11/19/26 | 6.2 | 6.2 |
|
141.2 |
ICM.B9.1830 |
[SSDCB4] Delivery of PTX - Pad Mounted Transformers (First Delivery) | Construction | Not Started | 11/16/26 | 11/16/26 | 0.0 | 0.0 |
|
222.5 |
ICM.B9.1835 |
[SSDCB4] Delivery of FCA - Fan Coil Assembly (First Delivery) | Construction | Not Started | 11/16/26 | 11/16/26 | 0.0 | 0.0 |
|
191.2 |
ICM.B9.1860 |
[SSDCB4] Delivery of Dry Cooling Towers (First Delivery) | Construction | Not Started | 11/16/26 | 11/16/26 | 0.0 | 0.0 |
|
191.2 |
RPL09.STR.DHAB.01000 |
RPL09.Structure.DHAB - Install Erect Steel Columns and Beams, Erect Joist Grid Lines 6-11/6-23 | Steel and Decking | Not Started | 11/17/26 | 11/30/26 | 10.0 | 10.0 |
|
112.5 |
RPL09.STR.SSB.01060 |
RPL09.Structure.SSB - Install Decking & Detailing turnover #1 - Grid lines 6-01/6-04 | Steel and Decking | Not Started | 11/17/26 | 11/20/26 | 5.0 | 5.0 |
|
98.8 |
GCD.RPL09.1182 |
Start mCUP Unit Set-In-Place - RPL09 | Construction Milestones | Not Started | 11/18/26 | 11/18/26 | 0.0 | 0.0 |
|
446.2 |
RPL09.MCUP.FWM.01000 |
RPL09.MCUP.FWM - Install PTX | FWM | Not Started | 11/18/26 | 11/20/26 | 3.8 | 3.8 |
|
221.2 |
RPL09.MCUP.FWM.01010 |
RPL09.MCUP.FWM - Install FWM | FWM | Not Started | 11/18/26 | 11/20/26 | 3.8 | 3.8 |
|
221.2 |
RPL09.MCUP.FWM.01030 |
RPL09.MCUP.FWM - Install MVS | FWM | Not Started | 11/18/26 | 11/20/26 | 3.8 | 3.8 |
|
221.2 |
RPL09.MCUP.LP1.1220 |
RPL09.MCUP.Loop 1 - Set mCup #1 & #2 - Dry Coolers (12) (4 per week) | OFE | Not Started | 11/18/26 | 12/10/26 | 18.8 | 18.8 |
|
190.0 |
RPL09.MCUP.LP1.1340 |
RPL09.MCUP.Loop 1 - Set mCUPs XXMY.MCUP.01 (1 per 5 days) | OFE | Not Started | 11/18/26 | 11/24/26 | 6.2 | 6.2 |
|
200.0 |
RPL09.SKIN.01000 |
RPL09.SKIN.BLDG - Install Insulated Metal Panels (IMP), Roof, Windows, Doors, Louvers - WBS Summary | Skin | Not Started | 11/19/26 | 11/04/27 | 301.2 | 301.2 |
|
256.2 |
RPL09.SKN.W.01000 |
RPL09.SKIN - Install Metal Panel Sealant & Starter Flashing - West North South East | IMP System | Not Started | 11/19/26 | 12/04/26 | 12.5 | 12.5 |
|
111.2 |
RPL09.STR.DHAB.01015 |
RPL09.Structure.DHAB - Install Decking & Detailing turnover #2 - Grid lines 6-04/6-07 | Steel and Decking | Not Started | 11/23/26 | 11/25/26 | 3.8 | 3.8 |
|
98.8 |
RPL09.MCUP.LP1.1380 |
RPL09.MCUP.Loop 1 - Set mCUPs XXMY.MCUP.02 (1 per 5 days) | OFE | Not Started | 11/25/26 | 12/03/26 | 6.2 | 6.2 |
|
200.0 |
RPL09.MCUP.LP2.1180 |
RPL09.MCUP.Loop 2 - Cure for Pads | Foundations | Not Started | 11/26/26 | 12/02/26 | 8.8 | 8.8 |
|
517.5 |
GCD.RPL09.1380 |
IMP Start - RPL09 | Construction Milestones | Not Started | 11/30/26 | 11/30/26 | 0.0 | 0.0 |
|
438.8 |
RPL09.MCUP.LP1.2180 |
RPL09.MCUP.Loop 1 - Set Facility Water Pipe Rack (mCUP2) | OFE | Not Started | 11/30/26 | 12/09/26 | 10.0 | 10.0 |
|
200.0 |
RPL09.SKN.W.01005 |
RPL09.SKIN.West - Install IMP - Flashing,Panels & Caulking - Gird lines 6A/6F (with temp closures for openings) | DBC Move 1 - Grid (6-01 / 6-07) | Not Started | 11/30/26 | 12/01/26 | 2.5 | 2.5 |
|
107.5 |
RPL09.SKN.W.01010 |
RPL09.SKIN.West - Install IMP Insulated Metal Panels System - WBS Summary | DBC Move 1 - Grid (6-01 / 6-07) | Not Started | 11/30/26 | 12/09/26 | 10.0 | 10.0 |
|
111.2 |
RPL09.STR.DHAB.01025 |
RPL09.Structure.DHAB - Install Decking & Detailing turnover #3 - Grid lines 6-07/6-10 | Steel and Decking | Not Started | 11/30/26 | 12/02/26 | 3.8 | 3.8 |
|
98.8 |
RPL09.STR.DHCD.01000 |
RPL09.Structure.DHCD - Install Erect Steel Columns and Beams, Erect Joist - Grid Lines 6-23/6-28 | Steel and Decking | Not Started | 12/01/26 | 12/09/26 | 8.8 | 8.8 |
|
135.0 |
RPL09.EY.SSB.01000 |
RPL09.EY.SSB - Install F/R/P Equipment Pads | Foundations | Not Started | 12/02/26 | 12/15/26 | 12.5 | 12.5 |
|
166.2 |
RPL09.EY.SSB.01010 |
RPL09.EY.SSB - Install Foundations - WBS Summary | Foundations | Not Started | 12/02/26 | 12/22/26 | 18.8 | 18.8 |
|
197.5 |
RPL09.EY.SSB.01020 |
RPL09.EY.SSB - Install Foundations, UG Utilities, OFE - WBS Summary | EY.SSB | Not Started | 12/02/26 | 11/15/27 | 300.0 | 300.0 |
|
286.2 |
RPL09.EY.SSB.01030 |
RPL09.EY.BLDG - Install Foundations, UG Utilities, OFE- WBS Summary | Electrical Yard | Not Started | 12/02/26 | 02/02/28 | 363.8 | 363.8 |
|
222.5 |
RPL09.EY.SSB.01100 |
RPL09.EY.SSB - OFE - WBS Summary | OFE | Not Started | 12/02/26 | 01/11/27 | 33.8 | 33.8 |
|
191.2 |
RPL09.EY.SSB.01380 |
RPL09.EY.SSB - Install Wall Mounted AC units (5) - CFCI | OFE | Not Started | 12/02/26 | 12/10/26 | 8.8 | 8.8 |
|
213.8 |
RPL09.EY.SSB.02020 |
RPL09.EY.SSB - Install Temp Conditioning Units - CFCI | Temp Conditions | Not Started | 12/02/26 | 12/08/26 | 6.2 | 6.2 |
|
153.8 |
RPL09.SKN.N.01000 |
RPL09.SKIN.North - Install IMP - Flashing,Panels & Caulking - Grid lines 6-01/6-07 (with temp closures for openings) | DBC Move 1 - Grid (6-01 / 6-07) | Not Started | 12/02/26 | 12/04/26 | 3.8 | 3.8 |
|
111.2 |
RPL09.SKN.SSB.01000 |
RPL09.SKIN.SSB - Install Temp Doors | Glazing, Doors and Ext Devices | Not Started | 12/02/26 | 12/03/26 | 2.5 | 2.5 |
|
396.2 |
RPL09.SKN.SSB.01020 |
RPL09.SKIN.SSB - IMP, Roof, Windows, Doors, Ext Devices - WBS Summary | SSB | Not Started | 12/02/26 | 04/23/27 | 122.5 | 122.5 |
|
288.8 |
RPL09.SKN.SSB.01030 |
RPL09.SKIN.SSB - Install Windows, Doors, Louvers and Ext Devices - WBS Summary | Glazing, Doors and Ext Devices | Not Started | 12/02/26 | 04/23/27 | 122.5 | 122.5 |
|
288.8 |
RPL09.SKN.SSB.01040 |
RPL09.SKIN.SSB - Install Louvers | Glazing, Doors and Ext Devices | Not Started | 12/02/26 | 12/08/26 | 6.2 | 6.2 |
|
386.2 |
RPL09.SKN.SSB.01050 |
RPL09.SKIN.SSB - Install Lighting | Glazing, Doors and Ext Devices | Not Started | 12/02/26 | 12/07/26 | 5.0 | 5.0 |
|
387.5 |
RPL09.SKN.SSB.01080 |
RPL09.SKIN.SSB - Install Roof System - Exterior Wall Sheathing and EJ | Roofing | Not Started | 12/02/26 | 12/08/26 | 6.2 | 6.2 |
|
107.5 |
RPL09.SKN.SSB.01090 |
RPL09.SKIN.SSB - Install Roof System - WBS Summary | Roofing | Not Started | 12/02/26 | 01/19/27 | 40.0 | 40.0 |
|
146.2 |
RPL09.SKN.SSB.01170 |
RPL09.SKIN.SSB - Install Blocking of Canopy & Backing of Exterior Wall | Glazing, Doors and Ext Devices | Not Started | 12/02/26 | 12/08/26 | 6.2 | 6.2 |
|
173.8 |
RPL09.LOG.1020 |
MCUP 500 Ton Crane Movement 1 | 300 Ton Crane | Not Started | 12/03/26 | 12/03/26 | 0.0 | 0.0 |
|
200.0 |
RPL09.STR.DHAB.01030 |
RPL09.Structure.DHAB - Install Decking & Detailing turnover #4 - Grid lines 6-10/6-14 | Steel and Decking | Not Started | 12/03/26 | 12/08/26 | 5.0 | 5.0 |
|
98.8 |
RPL09.MCUP.LP1.1400 |
RPL09.MCUP.Loop 1 - Tie-ins - WBS Summary | Tie-ins | Not Started | 12/04/26 | 02/08/27 | 55.0 | 55.0 |
|
462.5 |
RPL09.MCUP.LP1.1440 |
RPL09.MCUP.Loop 1 - Tie-in Mechanical - WBS Summary | Tie-Ins Mechanical | Not Started | 12/04/26 | 01/22/27 | 41.2 | 41.2 |
|
190.0 |
RPL09.MCUP.LP1.1460 |
RPL09.MCUP.Loop 1 - Tie-in Mechanical #1 | Tie-Ins Mechanical | Not Started | 12/04/26 | 12/24/26 | 18.8 | 18.8 |
|
212.5 |
RPL09.MCUP.LP1.1500 |
RPL09.MCUP.Loop 1 - Set mCUPs XXMY.MCUP.03 (1 per 5 days) | OFE | Not Started | 12/04/26 | 12/10/26 | 6.2 | 6.2 |
|
200.0 |
RPL09.SKN.S.01000 |
RPL09.SKIN.South - Install IMP - Flashing,Panels & Caulking - Grid lines 6-01/6-07 (with temp closures for openings) | DBC Move 1 - Grid (6-01 / 6-07) | Not Started | 12/07/26 | 12/09/26 | 3.8 | 3.8 |
|
111.2 |
RPL09.SKN.W.01040 |
RPL09.SKIN.West - Secure All Exterior Mounted Boxes and Devices on Skin | IMP System | Not Started | 12/07/26 | 12/18/26 | 12.5 | 12.5 |
|
425.0 |
RPL.09.D.94510.XR |
Storm Drain Available for Roof Drain Tie-ins | Receive Milestones (XREFs) | Not Started | 12/08/26 | 12/08/26 | 0.0 | 0.0 |
|
108.8 |
RPL09.SKN.SSB.01070 |
RPL09.SKIN.SSB - Install Security | Glazing, Doors and Ext Devices | Not Started | 12/08/26 | 12/09/26 | 2.5 | 2.5 |
|
387.5 |
RPL09.EY.SSB.02040 |
RPL09.EY.SSB - Install Temp Duct to Permanent Duct | Temp Conditions | Not Started | 12/09/26 | 12/15/26 | 6.2 | 6.2 |
|
153.8 |
RPL09.SKN.SSB.01060 |
RPL09.SKIN.SSB - Install Awning over Doors | Glazing, Doors and Ext Devices | Not Started | 12/09/26 | 12/15/26 | 6.2 | 6.2 |
|
392.5 |
RPL09.SKN.SSB.01075 |
RPL09.SKIN.SSB - QC Blocking | Glazing, Doors and Ext Devices | Not Started | 12/09/26 | 12/10/26 | 2.5 | 2.5 |
|
383.8 |
RPL09.SKN.SSB.01100 |
RPL09.SKIN.SSB - Install Roof System - Install Temp Flashing at EJ | Roofing | Not Started | 12/09/26 | 12/10/26 | 2.5 | 2.5 |
|
152.5 |
RPL09.SKN.SSB.01110 |
RPL09.SKIN.SSB - Install Roof System - DenseDeck & Flame Down | Roofing | Not Started | 12/09/26 | 12/17/26 | 8.8 | 8.8 |
|
107.5 |
RPL09.STR.DHAB.01035 |
RPL09.Structure.DHAB - Install Decking & Detailing turnover #5 - Grid lines 6-14/6-18 | Steel and Decking | Not Started | 12/09/26 | 12/11/26 | 3.8 | 3.8 |
|
105.0 |
RPL09.STR.SSB.01100 |
RPL09.Structure.SSB - Adjust MEP Verts and Grounding wire | Prep | Not Started | 12/09/26 | 12/15/26 | 6.2 | 6.2 |
|
98.8 |
RPL09.STR.SSB.01110 |
RPL09.Structure.SSB - Install Remaining UG and Subgrade Prep - WBS Summary | Prep | Not Started | 12/09/26 | 12/29/26 | 17.5 | 17.5 |
|
98.8 |
RPL09.EY.ENDC.01020 |
RPL09.EY.End - Install Foundations, UG Utilities, OFE - WBS Summary | EY.EC | Not Started | 12/10/26 | 02/02/28 | 356.2 | 356.2 |
|
222.5 |
RPL09.EY.ENDC.01300 |
RPL09.EY.DHD.T1 - Install Shallow Tent UG | Tent 1 | Not Started | 12/10/26 | 12/14/26 | 3.8 | 3.8 |
|
141.2 |
RPL09.LOG.1140 |
Dry Cooler 230 Ton Crane Movement 01 | 100 Ton Crane | Not Started | 12/10/26 | 12/10/26 | 0.0 | 0.0 |
|
190.0 |
RPL09.LOG.1860 |
Steel Crane #1 Demobilzation | Steel Crane 1 | Not Started | 12/10/26 | 12/10/26 | 0.0 | 0.0 |
|
160.0 |
RPL09.LOG.1880 |
Steel Crane #2 Demobilization | Steel Crane 2 | Not Started | 12/10/26 | 12/10/26 | 0.0 | 0.0 |
|
160.0 |
RPL09.MCUP.LP1.2200 |
RPL09.MCUP.Loop 1 - Set Facility Water Pipe Rack (mCUP3) | OFE | Not Started | 12/10/26 | 12/21/26 | 10.0 | 10.0 |
|
200.0 |
RPL09.MCUP.LP1.1280 |
RPL09.MCUP.Loop 1 - Set MTRs (4 per day) | OFE | Not Started | 12/11/26 | 12/17/26 | 6.2 | 6.2 |
|
190.0 |
RPL09.MCUP.LP1.1320 |
RPL09.MCUP.Loop 1 - Set mCup #3 & #4 - Dry Coolers (12) (4 per week) | OFE | Not Started | 12/11/26 | 01/04/27 | 18.8 | 18.8 |
|
190.0 |
RPL09.MCUP.LP1.1620 |
RPL09.MCUP.Loop 1 - Set mCUPs XXMY.MCUP.04 (1 per 5 days) | OFE | Not Started | 12/11/26 | 12/17/26 | 6.2 | 6.2 |
|
200.0 |
RPL09.MCUP.LP1.1760 |
RPL09.MCUP.Loop 1 - Tie-in Mechanical #2 | Tie-Ins Mechanical | Not Started | 12/11/26 | 01/04/27 | 18.8 | 18.8 |
|
206.2 |
RPL09.STR.DHCD.01015 |
RPL09.Structure.DHCD - Install Decking & Detailing turnover #6 - Grid lines 6-18/6-21 | Steel and Decking | Not Started | 12/14/26 | 12/16/26 | 3.8 | 3.8 |
|
105.0 |
RPL09.EY.ENDC.01360 |
RPL09.EY.DHD.T2 - Install Shallow Tent UG | Tent 2 | Not Started | 12/15/26 | 12/17/26 | 3.8 | 3.8 |
|
141.2 |
RPL09.EY.ENDC.1310 |
RPL09.EY.DHD.T1 - Install Final Grading | Tent 1 | Not Started | 12/15/26 | 12/16/26 | 2.5 | 2.5 |
|
142.5 |
RPL09.EY.SSB.01040 |
RPL09.EY.SSB - Install Electrical UG | Underground | Not Started | 12/16/26 | 12/22/26 | 6.2 | 6.2 |
|
166.2 |
RPL09.EY.SSB.01050 |
RPL09.EY.SSB - Install Cure (High Early Mix) | Foundations | Not Started | 12/16/26 | 12/22/26 | 8.8 | 8.8 |
|
288.8 |
RPL09.EY.SSB.01060 |
RPL09.EY.SSB - Install UG Utilities - WBS Summary | Underground | Not Started | 12/16/26 | 01/14/27 | 25.0 | 25.0 |
|
178.8 |
RPL09.EY.SSB.01180 |
RPL09.EY.SSB - Tie-ins - WBS Summary | Tie-ins | Not Started | 12/16/26 | 04/12/27 | 98.8 | 98.8 |
|
136.2 |
RPL09.EY.SSB.01400 |
RPL09.EY.SSB - Install Duct/ insulation into the building Main (include penetration detail) | Tie-ins | Not Started | 12/16/26 | 01/07/27 | 18.8 | 18.8 |
|
172.5 |
RPL09.STR.SSB.01120 |
RPL09.Structure.SSB - Install AB final grade and Vapor Barrier | Prep | Not Started | 12/16/26 | 12/22/26 | 6.2 | 6.2 |
|
98.8 |
RPL.09.D.94120.XG |
Ready for MV Cable Pull mCUP - Loop#1 (Qty 4)* | Give Milestones (XREFs) | Not Started | 12/17/26 | 12/17/26 | 0.0 | 0.0 |
|
571.2 |
RPL09.EY.ENDC.1330 |
RPL09.EY.DHD.T1 - Install F/R/P Tent1 Slab | Tent 1 | Not Started | 12/17/26 | 12/23/26 | 6.2 | 6.2 |
|
142.5 |
RPL09.LOG.1040 |
MCUP 500 Ton Crane Movement 2 | 300 Ton Crane | Not Started | 12/17/26 | 12/17/26 | 0.0 | 0.0 |
|
341.2 |
RPL09.MCUP.LP1.1240 |
RPL09.MCUP.Loop 1 - Set GS.IDF Hut (1x GS.IDF) XX01 (ROJ12.16.26) | OFE | Not Started | 12/17/26 | 12/23/26 | 6.2 | 6.2 |
|
188.8 |
RPL09.SKN.N.01010 |
RPL09.SKIN.North - Install IMP Insulated Metal Panels System - WBS Summary | DBC Move 2 - Grid (6-07 / 6-21) | Not Started | 12/17/26 | 01/12/27 | 21.2 | 21.2 |
|
498.8 |
RPL09.SKN.S.01030 |
RPL09.SKIN.South - Install IMP - Flashing,Panels & Caulking - Grid lines 6-07/6-14 (with temp closures for openings) | DBC Move 2 - Grid (6-07 / 6-21) | Not Started | 12/17/26 | 12/21/26 | 3.8 | 3.8 |
|
105.0 |
RPL09.STR.DHCD.01025 |
RPL09.Structure.DHCD - Install Decking & Detailing turnover #7 - Grid lines 6-21/6-25 | Steel and Decking | Not Started | 12/17/26 | 12/21/26 | 3.8 | 3.8 |
|
113.8 |
RPL09.EY.ENDC.1610 |
RPL09.EY.DHD.T2 - Install Final Grading | Tent 2 | Not Started | 12/18/26 | 12/21/26 | 2.5 | 2.5 |
|
141.2 |
RPL09.EY.SSB.01420 |
RPL09.EY.SSB - Install Grounding UG | Underground | Not Started | 12/18/26 | 12/24/26 | 6.2 | 6.2 |
|
188.8 |
RPL09.MCUP.LP1.1360 |
RPL09.MCUP.Loop 1 - Set Electrical Skids #1 | OFE | Not Started | 12/18/26 | 12/21/26 | 2.5 | 2.5 |
|
196.2 |
RPL09.MCUP.LP2.1200 |
RPL09.MCUP.Loop 2 - OFE - WBS Summary | OFE | Not Started | 12/18/26 | 01/29/27 | 35.0 | 35.0 |
|
331.2 |
RPL09.MCUP.LP2.1280 |
RPL09.MCUP.Loop 2 - Set mCUPs XXMY.MCUP.05 (1 per 5 days) | OFE | Not Started | 12/18/26 | 12/24/26 | 6.2 | 6.2 |
|
341.2 |
RPL09.SKN.SSB.01120 |
RPL09.SKIN.SSB - Install Scupper and Downspouts | Glazing, Doors and Ext Devices | Not Started | 12/18/26 | 12/24/26 | 6.2 | 6.2 |
|
390.0 |
RPL09.SKN.SSB.01130 |
RPL09.SKIN.SSB - Install Roof System - Final Roof | Roofing | Not Started | 12/18/26 | 01/11/27 | 18.8 | 18.8 |
|
146.2 |