Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL09 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:12 PM · 5201 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
0
Completed
0
In Progress
0
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL09.EY.DHA.01010 RPL09.EY.DHA - Install F/R/P Equipment Pads - 1-12 (Grid 6-01/6-16) (12'' Larger For Tolerance) Foundations Not Started 12/22/26 01/21/27 25.0 25.0
0%
165.0
RPL09.EY.DHA.01020 RPL09.EY.DHA - Install Foundations - WBS Summary Foundations Not Started 12/22/26 01/28/27 31.2 31.2
0%
165.0
RPL09.EY.DHA.01030 RPL09.EY.DHA - Install Foundations, UG Utilities, OFE- WBS Summary EY.DHA Not Started 12/22/26 08/16/27 203.8 203.8
0%
365.0
RPL09.EY.ENDC.1630 RPL09.EY.DHD.T2 - Install F/R/P Tent1 Slab Tent 2 Not Started 12/22/26 12/29/26 6.2 6.2
0%
141.2
RPL09.MCUP.LP1.1520 RPL09.MCUP.Loop 1 - Set Electrical Skids #2 OFE Not Started 12/22/26 12/23/26 2.5 2.5
0%
196.2
RPL09.MCUP.LP1.1880 RPL09.MCUP.Loop 1 - Tie-in Mechanical #3 Tie-Ins Mechanical Not Started 12/22/26 01/11/27 16.2 16.2
0%
200.0
RPL09.MCUP.LP1.2220 RPL09.MCUP.Loop 1 - Set Facility Water Pipe Rack (mCUP4) OFE Not Started 12/22/26 01/04/27 10.0 10.0
0%
200.0
RPL09.SKN.N.01030 RPL09.SKIN.North - Install IMP - Flashing,Panels & Caulking - Grid lines 6-07/6-14 (with temp closures for openings) DBC Move 2 - Grid (6-07 / 6-21) Not Started 12/22/26 12/23/26 2.5 2.5
0%
105.0
RPL09.SKN.S.01010 RPL09.SKIN.South - Install IMP Insulated Metal Panels System - WBS Summary DBC Move 3 - Grid (6-21 / 6-28) Not Started 12/22/26 01/15/27 21.2 21.2
0%
495.0
RPL09.SKN.S.01040 RPL09.SKIN.South - Install IMP EJ - Grid lines 6-09/6-10 DBC Move 2 - Grid (6-07 / 6-21) Not Started 12/22/26 12/29/26 6.2 6.2
0%
120.0
RPL09.SKN.S.01140 RPL09.SKIN.South - Install Stair Tower (DH A) DBC Move 3 - Grid (6-21 / 6-28) Not Started 12/22/26 12/23/26 2.5 2.5
0%
228.8
RPL09.STR.DHAB.01060 RPL09.Structure.DHAB - Adjust MEP Verts and Grounding wire Prep Not Started 12/22/26 12/29/26 6.2 6.2
0%
113.8
RPL09.STR.DHAB.01070 RPL09.Structure.DHAB - Install Remaining UG and Subgrade Prep - WBS Summary Prep Not Started 12/22/26 01/11/27 16.2 16.2
0%
113.8
RPL09.STR.DHCD.01035 RPL09.Structure.DHCD - Install Decking & Detailing turnover #8 - Grid lines 6-25/6-28 Steel and Decking Not Started 12/22/26 12/24/26 3.8 3.8
0%
118.8
RPL.GF.D.N9140.XG GS.IDF Hut 1 Install Complete for RPL 9 Give Milestones (XREFs) Not Started 12/23/26 12/23/26 0.0 0.0
0%
566.2
RPL09.EY.DHA.01060 RPL09.EY.DHA - Install Electrical UG Underground Not Started 12/23/26 01/07/27 12.5 12.5
0%
185.0
RPL09.EY.DHA.01070 RPL09.EY.DHA - Install UG Utilities - WBS Summary Underground Not Started 12/23/26 02/05/27 37.5 37.5
0%
185.0
RPL09.EY.DHB.01030 RPL09.EY.DHB - Install Foundations, UG Utilities, OFE - WBS Summary EY.DHB Not Started 12/23/26 08/02/27 190.0 190.0
0%
377.5
RPL09.EY.DHB.01060 RPL09.EY.DHB - Install Electrical UG Underground Not Started 12/23/26 01/07/27 12.5 12.5
0%
166.2
RPL09.EY.DHB.01070 RPL09.EY.DHB - Install UG Utilities - WBS Summary Underground Not Started 12/23/26 02/05/27 37.5 37.5
0%
166.2
RPL09.EY.SSB.01070 RPL09.EY.SSB - Install Mechanical UG Underground Not Started 12/23/26 12/30/26 6.2 6.2
0%
172.5
RPL09.STR.SSB.01130 RPL09.Structure.SSB - Asphalt Emulsion and Wrap Steel Columns Prep Not Started 12/23/26 12/29/26 5.0 5.0
0%
98.8
GCD.RPL09.1320 Steel Complete - RPL09 Construction Milestones Not Started 12/24/26 12/24/26 0.0 0.0
0%
146.2
GCD.RPL09.1456 Start RPL09 EY RMU Equipment Pad Placement - RPL09 Construction Milestones Not Started 12/24/26 12/24/26 0.0 0.0
0%
416.2
RPL09.CON.WP2.07000 RPL09.Conn - Ext. GSIDFs - WBS Summary GS.IDF (Exterior) Not Started 12/24/26 07/27/27 183.8 183.8
0%
382.5
RPL09.CON.WP2.07200 RPL09.Conn - Ext. GSIDF9X01 (mCUP yard) - WBS Summary Ext. IDF HUT - GSIDF9X01 Not Started 12/24/26 07/19/27 176.2 176.2
0%
390.0
RPL09.CON.WP2.07220 RPL09.Conn - Ext. GSIDF9X01 - Install Infrastructure (Racks, Waterfalls etc.) Infrastructure Not Started 12/24/26 12/31/26 6.2 6.2
0%
375.0
RPL09.EY.DHB.01010 RPL09.EY.DHB - Install F/R/P Equipment Pads - 1-12(Grid 6-01/6-16) (12'' Larger For Tolerance) Foundations Not Started 12/24/26 01/25/27 25.0 25.0
0%
143.8
RPL09.EY.DHB.01020 RPL09.EY.DHB - Install Foundations - WBS Summary Foundations Not Started 12/24/26 02/01/27 31.2 31.2
0%
143.8
RPL09.EY.ENDC.1350 RPL09.EY.DHD.T1 - Install Saw Cut and Cure Tent 1 Not Started 12/24/26 12/30/26 8.8 8.8
0%
210.0
RPL09.MCUP.LP1.1260 RPL09.MCUP.Loop 1 - Set GS.IDF Hut (1x GS.IDF) XX02 (ROJ12.16.26) OFE Not Started 12/24/26 12/31/26 6.2 6.2
0%
188.8
RPL09.MCUP.LP1.1420 RPL09.MCUP.Loop 1 - Tie-in Electrical - WBS Summary Tie-Ins Electrical Not Started 12/24/26 01/25/27 25.0 25.0
0%
182.5
RPL09.MCUP.LP1.1480 RPL09.MCUP.Loop 1 - Tie-in Electrical #1 Tie-Ins Electrical Not Started 12/24/26 01/13/27 16.2 16.2
0%
191.2
RPL09.MCUP.LP1.1660 RPL09.MCUP.Loop 1 - Tie-in SD, DW Tie-ins Not Started 12/24/26 01/15/27 18.8 18.8
0%
481.2
RPL09.MCUP.LP1.1700 RPL09.MCUP.Loop 1 - Tie-in Electrical #2 Tie-Ins Electrical Not Started 12/24/26 01/13/27 16.2 16.2
0%
191.2
RPL09.SKN.DHAB.01000 RPL09.SKIN.DHAB - Install Temp Doors Glazing, Doors and Ext Devices Not Started 12/24/26 12/28/26 2.5 2.5
0%
131.2
RPL09.SKN.DHAB.01010 RPL09.SKIN.DHAB - IMP, Roof, Windows, Doors, Ext Devices - WBS Summary DH A & DH B Not Started 12/24/26 02/01/27 31.2 31.2
0%
366.2
RPL09.SKN.DHAB.01020 RPL09.SKIN.DHAB - Install Windows, Doors, Louvers and Ext Devices - WBS Summary Glazing, Doors and Ext Devices Not Started 12/24/26 02/01/27 31.2 31.2
0%
366.2
RPL09.SKN.DHAB.01070 RPL09.SKIN.DHAB - Install Roof System - Exterior Wall Sheething and EJ Roofing Not Started 12/24/26 12/28/26 2.5 2.5
0%
105.0
RPL09.SKN.DHAB.01080 RPL09.SKIN.DHAB - Install Roof System - WBS Summary Roofing Not Started 12/24/26 02/01/27 31.2 31.2
0%
215.0
RPL09.SKN.N.01040 RPL09.SKIN.North - Install IMP EJ - Grid lines 6-09/6-10 DBC Move 2 - Grid (6-07 / 6-21) Not Started 12/24/26 12/31/26 6.2 6.2
0%
115.0
RPL09.SKN.N.01080 RPL09.SKIN.North - Install IMP - Flashing,Panels & Caulking - Grid lines 6-14/6-21 (with temp closures for openings) DBC Move 2 - Grid (6-07 / 6-21) Not Started 12/24/26 12/28/26 2.5 2.5
0%
115.0
RPL09.SKN.N.01120 RPL09.SKIN.North - Install Stair Tower (DH B) DBC Move 2 - Grid (6-07 / 6-21) Not Started 12/24/26 12/28/26 2.5 2.5
0%
226.2
RPL09.EY.DHA.01560 RPL09.EY.DHA - Install Grounding UG Underground Not Started 12/28/26 01/11/27 12.5 12.5
0%
195.0
RPL09.EY.DHB.01540 RPL09.EY.DHB - Install Grounding UG Underground Not Started 12/28/26 01/11/27 12.5 12.5
0%
176.2
RPL09.EY.SSB.01080 RPL09.EY.SSB - Install BMS UG Underground Not Started 12/28/26 01/04/27 6.2 6.2
0%
188.8
RPL09.INT.1000 RPL09.Interior.BLDG - Install Priority OH, Walls, OFE and Fitout - WBS Summary Interior Build-out Not Started 12/28/26 02/03/28 343.8 343.8
0%
185.0
RPL09.INT.SSB.01005 RPL09.Interior - Priority - Install Hangers Support (SSB to Center Corr) (All Trades) Early Priority OH MEPF Not Started 12/28/26 01/11/27 12.5 12.5
0%
105.0
RPL09.MCUP.LP2.1360 RPL09.MCUP.Loop 2 - Set mCUPs XXMY.MCUP.06 (1 per 5 days) OFE Not Started 12/28/26 01/04/27 6.2 6.2
0%
341.2
RPL09.STR.DHCD.01060 RPL09.Structure.DHCD - Adjust MEP Verts and Grounding wire Prep Not Started 12/28/26 01/04/27 6.2 6.2
0%
130.0
RPL09.STR.DHCD.01070 RPL09.Structure.DHCD - Install Remaining UG and Subgrade Prep - WBS Summary Prep Not Started 12/28/26 01/14/27 16.2 16.2
0%
130.0
RPL09.SKN.DHAB.01090 RPL09.SKIN.DHAB - Install Roof System - Install Temp Flashing at EJ Roofing Not Started 12/29/26 12/30/26 2.5 2.5
0%
147.5
RPL09.SKN.DHAB.01100 RPL09.SKIN.DHAB - Install Roof System - DenseDeck & Flame Down Roofing Not Started 12/29/26 01/07/27 8.8 8.8
0%
105.0
RPL09.SKN.DHAB.01160 RPL09.SKIN.DHAB - Install Blocking of Canopy & Backing of Exterior Wall Glazing, Doors and Ext Devices Not Started 12/29/26 01/05/27 6.2 6.2
0%
131.2
RPL09.SKN.S.01080 RPL09.SKIN.South - Install IMP - Flashing,Panels & Caulking - Grid lines 6-14/6-21 (with temp closures for openings) DBC Move 2 - Grid (6-07 / 6-21) Not Started 12/29/26 12/30/26 2.5 2.5
0%
115.0
GCD.RPL09.1500 Start Slab-On-Grade Concrete - RPL09 Construction Milestones Not Started 12/30/26 12/30/26 0.0 0.0
0%
412.5
RPL09.EY.ENDC.1650 RPL09.EY.DHD.T2 - Install Saw Cut and Cure Tent 2 Not Started 12/30/26 01/05/27 8.8 8.8
0%
207.5
RPL09.INT.SSB.01010 RPL09.Interior.SSB - Priority - Install Duct (Highside OH space) Early Priority OH MEPF Not Started 12/30/26 01/13/27 12.5 12.5
0%
105.0
RPL09.MCUP.LP1.1540 RPL09.MCUP.Loop 1 - Tie-in BMS - WBS Summary Tie-Ins BMS Not Started 12/30/26 01/25/27 21.2 21.2
0%
188.8
RPL09.MCUP.LP1.1560 RPL09.MCUP.Loop 1 - Tie-in BMS #1 Tie-Ins BMS Not Started 12/30/26 01/13/27 12.5 12.5
0%
197.5
RPL09.MCUP.LP1.1580 RPL09.MCUP.Loop 1 - Tie-in EPMS - WBS Summary Tie-Ins EPMS Not Started 12/30/26 01/25/27 21.2 21.2
0%
182.5
RPL09.MCUP.LP1.1600 RPL09.MCUP.Loop 1 - Tie-in EPMS #1 Tie-Ins EPMS Not Started 12/30/26 01/13/27 12.5 12.5
0%
191.2
RPL09.MCUP.LP1.1720 RPL09.MCUP.Loop 1 - Tie-in EPMS #2 Tie-Ins EPMS Not Started 12/30/26 01/13/27 12.5 12.5
0%
191.2
RPL09.MCUP.LP1.1740 RPL09.MCUP.Loop 1 - Tie-in BMS #2 Tie-Ins BMS Not Started 12/30/26 01/13/27 12.5 12.5
0%
197.5
RPL09.STR.DHAB.01080 RPL09.Structure.DHAB - Install AB final grade and Vapor Barrier Prep Not Started 12/30/26 01/06/27 6.2 6.2
0%
113.8
RPL09.STR.SSB.01140 RPL09.Structure.SSB - SOG F/R/P #1 - Grid lines 6-01/6-04 F/R/P Not Started 12/30/26 01/06/27 6.2 6.2
0%
98.8
RPL09.STR.SSB.01150 RPL09.Structure.SSB - SOG F/R/P - WBS Summary F/R/P Not Started 12/30/26 01/22/27 20.0 20.0
0%
196.2
RPL.GF.D.N9150.XG GS.IDF Hut 2 Install Complete for RPL 9 Give Milestones (XREFs) Not Started 12/31/26 12/31/26 0.0 0.0
0%
560.0
RPL09.EY.SSB.01110 RPL09.EY.SSB - Install LD Electrical UG Loading Dock Not Started 12/31/26 01/06/27 5.0 5.0
0%
282.5
RPL09.EY.SSB.01120 RPL09.EY.SSB - Install AHU (3) - CFCI OFE Not Started 12/31/26 01/11/27 8.8 8.8
0%
191.2
RPL09.EY.SSB.01130 RPL09.EY.SSB - Install SD, DW, FW UG Underground Not Started 12/31/26 01/14/27 12.5 12.5
0%
172.5
RPL09.EY.SSB.01140 RPL09.EY.SSB - Install Loading Dock, UG Utilities, OFE - WBS Summary Loading Dock Not Started 12/31/26 02/25/27 47.5 47.5
0%
282.5
RPL09.SKN.S.01050 RPL09.SKIN.South - Install IMP - Flashing,Panels & Caulking - Grid lines 6-21/6-28 (with temp closures for openings) DBC Move 3 - Grid (6-21 / 6-28) Not Started 12/31/26 01/04/27 2.5 2.5
0%
115.0
RPL.09.D.94160.XG Ready for MV Cable Pull mCUP - Loop#2 (Qty 2)* Give Milestones (XREFs) Not Started 01/04/27 01/04/27 0.0 0.0
0%
558.8
RPL09.CON.WP2.07260 RPL09.Conn - Ext. GSIDF9X01 - Install Copper, WAPs, Security Camera & Access Control Cabling Not Started 01/04/27 01/20/27 15.0 15.0
0%
375.0
RPL09.CON.WP2.07400 RPL09.Conn - Ext. GSIDF9X02 (mCUP yard) - WBS Summary Ext. IDF HUT - GSIDF9X02 Not Started 01/04/27 07/19/27 170.0 170.0
0%
390.0
RPL09.CON.WP2.07420 RPL09.Conn - Ext. GSIDF9X02 - Install Infrastructure (Racks, Waterfalls etc.) Infrastructure Not Started 01/04/27 01/08/27 6.2 6.2
0%
368.8
RPL09.LOG.1160 Dry Cooler 230 Ton Crane Movement 02 100 Ton Crane Not Started 01/04/27 01/04/27 0.0 0.0
0%
325.0
RPL09.MCUP.LP2.1300 RPL09.MCUP.Loop 2 - Set GS.IDF Hut (1x GS.IDF) XX03 (ROJ12.16.26) OFE Not Started 01/04/27 01/08/27 6.2 6.2
0%
336.2
RPL09.LOG.1100 MCUP 500 Ton Crane Demobilization 300 Ton Crane Not Started 01/05/27 01/08/27 5.0 5.0
0%
553.8
RPL09.MCUP.LP1.1980 RPL09.MCUP.Loop 1 - Tie-in Mechanical #4 Tie-Ins Mechanical Not Started 01/05/27 01/22/27 16.2 16.2
0%
190.0
RPL09.MCUP.LP2.1220 RPL09.MCUP.Loop 2 - Set mCup #5 & #6 - Dry Coolers (12) (4 per week) OFE Not Started 01/05/27 01/26/27 18.8 18.8
0%
325.0
RPL09.MCUP.LP2.2100 RPL09.MCUP.Loop 2 - Set Facility Water Pipe Rack (mCUP5) OFE Not Started 01/05/27 01/14/27 10.0 10.0
0%
331.2
RPL09.SKN.E.01000 RPL09.SKIN.East - Install IMP Insulated Metal Panels - Gird lines 6A/6F (with temp closures for openings) DBC Move 3 - Grid (6-21 / 6-28) Not Started 01/05/27 01/06/27 2.5 2.5
0%
115.0
RPL09.SKN.S.01070 RPL09.SKIN.South - Install IMP EJ - Grid lines 6-22/6-23 DBC Move 3 - Grid (6-21 / 6-28) Not Started 01/05/27 01/11/27 6.2 6.2
0%
120.0
RPL09.SKN.S.01120 RPL09.SKIN.South - Install Stair Tower (DH C) DBC Move 3 - Grid (6-21 / 6-28) Not Started 01/05/27 01/06/27 2.5 2.5
0%
503.8
RPL09.STR.DHCD.01080 RPL09.Structure.DHCD - Install AB final grade and Vapor Barrier Prep Not Started 01/05/27 01/11/27 6.2 6.2
0%
130.0
RPL09.SKN.DHAB.01030 RPL09.SKIN.DHAB - Install Awning over Doors Glazing, Doors and Ext Devices Not Started 01/06/27 01/12/27 6.2 6.2
0%
131.2
RPL09.EY.ENDC.02100 RPL09.EY.End - Install Temp Conditioning Units - CFCI Temp Conditions Not Started 01/07/27 01/13/27 6.2 6.2
0%
383.8
RPL09.EY.ENDC.1370 RPL09.EY.DHD.T1 - Install Tent Tent 1 Not Started 01/07/27 02/04/27 25.0 25.0
0%
138.8
RPL09.EY.ENDC.1670 RPL09.EY.DHD.T2 - Install Tent Tent 2 Not Started 01/07/27 02/04/27 25.0 25.0
0%
141.2
RPL09.EY.SSB.01150 RPL09.EY.SSB - Install LD Mechanical UG Loading Dock Not Started 01/07/27 01/21/27 12.5 12.5
0%
282.5
RPL09.MCUP.LP1.1860 RPL09.MCUP.Loop 1 - Tie-in Electrical #3 Tie-Ins Electrical Not Started 01/07/27 01/21/27 12.5 12.5
0%
185.0
RPL09.SKN.N.01050 RPL09.SKIN.North - Install IMP - Flashing,Panels & Caulking - Grid lines 6-21/6-28 (with temp closures for openings) DBC Move 3 - Grid (6-21 / 6-28) Not Started 01/07/27 01/08/27 2.5 2.5
0%
115.0
RPL09.STR.DHAB.01090 RPL09.Structure.DHAB - Asphalt Emulsion and Wrap Steel Columns Prep Not Started 01/07/27 01/11/27 3.8 3.8
0%
113.8
RPL09.STR.DHAB.01110 RPL09.Structure.DHAB - SOG F/R/P - Grid Lines 6-11/6-23 - WBS Summary F/R/P Not Started 01/07/27 02/20/27 37.5 37.5
0%
118.8
RPL09.STR.DHAB.01160 RPL09.Structure.DHAB - SOG F/R/P #2 - Grid lines 6-04/6-07 F/R/P Not Started 01/07/27 01/13/27 6.2 6.2
0%
98.8
RPL09.STR.SSB.01190 RPL09.Structure.SSB - Zone SOG Cure F/R/P Not Started 01/07/27 01/13/27 8.8 8.8
0%
172.5
RPL.GF.D.N9160.XG GS.IDF Hut 3 Install Complete for RPL 9 Give Milestones (XREFs) Not Started 01/08/27 01/08/27 0.0 0.0
0%
553.8
RPL09.EY.DHA.01100 RPL09.EY.DHA - Install Mechanical UG Underground Not Started 01/08/27 01/22/27 12.5 12.5
0%
185.0