Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL09 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:12 PM
· 5201 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
0
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL09.EY.DHA.01010 |
RPL09.EY.DHA - Install F/R/P Equipment Pads - 1-12 (Grid 6-01/6-16) (12'' Larger For Tolerance) | Foundations | Not Started | 12/22/26 | 01/21/27 | 25.0 | 25.0 |
|
165.0 |
RPL09.EY.DHA.01020 |
RPL09.EY.DHA - Install Foundations - WBS Summary | Foundations | Not Started | 12/22/26 | 01/28/27 | 31.2 | 31.2 |
|
165.0 |
RPL09.EY.DHA.01030 |
RPL09.EY.DHA - Install Foundations, UG Utilities, OFE- WBS Summary | EY.DHA | Not Started | 12/22/26 | 08/16/27 | 203.8 | 203.8 |
|
365.0 |
RPL09.EY.ENDC.1630 |
RPL09.EY.DHD.T2 - Install F/R/P Tent1 Slab | Tent 2 | Not Started | 12/22/26 | 12/29/26 | 6.2 | 6.2 |
|
141.2 |
RPL09.MCUP.LP1.1520 |
RPL09.MCUP.Loop 1 - Set Electrical Skids #2 | OFE | Not Started | 12/22/26 | 12/23/26 | 2.5 | 2.5 |
|
196.2 |
RPL09.MCUP.LP1.1880 |
RPL09.MCUP.Loop 1 - Tie-in Mechanical #3 | Tie-Ins Mechanical | Not Started | 12/22/26 | 01/11/27 | 16.2 | 16.2 |
|
200.0 |
RPL09.MCUP.LP1.2220 |
RPL09.MCUP.Loop 1 - Set Facility Water Pipe Rack (mCUP4) | OFE | Not Started | 12/22/26 | 01/04/27 | 10.0 | 10.0 |
|
200.0 |
RPL09.SKN.N.01030 |
RPL09.SKIN.North - Install IMP - Flashing,Panels & Caulking - Grid lines 6-07/6-14 (with temp closures for openings) | DBC Move 2 - Grid (6-07 / 6-21) | Not Started | 12/22/26 | 12/23/26 | 2.5 | 2.5 |
|
105.0 |
RPL09.SKN.S.01010 |
RPL09.SKIN.South - Install IMP Insulated Metal Panels System - WBS Summary | DBC Move 3 - Grid (6-21 / 6-28) | Not Started | 12/22/26 | 01/15/27 | 21.2 | 21.2 |
|
495.0 |
RPL09.SKN.S.01040 |
RPL09.SKIN.South - Install IMP EJ - Grid lines 6-09/6-10 | DBC Move 2 - Grid (6-07 / 6-21) | Not Started | 12/22/26 | 12/29/26 | 6.2 | 6.2 |
|
120.0 |
RPL09.SKN.S.01140 |
RPL09.SKIN.South - Install Stair Tower (DH A) | DBC Move 3 - Grid (6-21 / 6-28) | Not Started | 12/22/26 | 12/23/26 | 2.5 | 2.5 |
|
228.8 |
RPL09.STR.DHAB.01060 |
RPL09.Structure.DHAB - Adjust MEP Verts and Grounding wire | Prep | Not Started | 12/22/26 | 12/29/26 | 6.2 | 6.2 |
|
113.8 |
RPL09.STR.DHAB.01070 |
RPL09.Structure.DHAB - Install Remaining UG and Subgrade Prep - WBS Summary | Prep | Not Started | 12/22/26 | 01/11/27 | 16.2 | 16.2 |
|
113.8 |
RPL09.STR.DHCD.01035 |
RPL09.Structure.DHCD - Install Decking & Detailing turnover #8 - Grid lines 6-25/6-28 | Steel and Decking | Not Started | 12/22/26 | 12/24/26 | 3.8 | 3.8 |
|
118.8 |
RPL.GF.D.N9140.XG |
GS.IDF Hut 1 Install Complete for RPL 9 | Give Milestones (XREFs) | Not Started | 12/23/26 | 12/23/26 | 0.0 | 0.0 |
|
566.2 |
RPL09.EY.DHA.01060 |
RPL09.EY.DHA - Install Electrical UG | Underground | Not Started | 12/23/26 | 01/07/27 | 12.5 | 12.5 |
|
185.0 |
RPL09.EY.DHA.01070 |
RPL09.EY.DHA - Install UG Utilities - WBS Summary | Underground | Not Started | 12/23/26 | 02/05/27 | 37.5 | 37.5 |
|
185.0 |
RPL09.EY.DHB.01030 |
RPL09.EY.DHB - Install Foundations, UG Utilities, OFE - WBS Summary | EY.DHB | Not Started | 12/23/26 | 08/02/27 | 190.0 | 190.0 |
|
377.5 |
RPL09.EY.DHB.01060 |
RPL09.EY.DHB - Install Electrical UG | Underground | Not Started | 12/23/26 | 01/07/27 | 12.5 | 12.5 |
|
166.2 |
RPL09.EY.DHB.01070 |
RPL09.EY.DHB - Install UG Utilities - WBS Summary | Underground | Not Started | 12/23/26 | 02/05/27 | 37.5 | 37.5 |
|
166.2 |
RPL09.EY.SSB.01070 |
RPL09.EY.SSB - Install Mechanical UG | Underground | Not Started | 12/23/26 | 12/30/26 | 6.2 | 6.2 |
|
172.5 |
RPL09.STR.SSB.01130 |
RPL09.Structure.SSB - Asphalt Emulsion and Wrap Steel Columns | Prep | Not Started | 12/23/26 | 12/29/26 | 5.0 | 5.0 |
|
98.8 |
GCD.RPL09.1320 |
Steel Complete - RPL09 | Construction Milestones | Not Started | 12/24/26 | 12/24/26 | 0.0 | 0.0 |
|
146.2 |
GCD.RPL09.1456 |
Start RPL09 EY RMU Equipment Pad Placement - RPL09 | Construction Milestones | Not Started | 12/24/26 | 12/24/26 | 0.0 | 0.0 |
|
416.2 |
RPL09.CON.WP2.07000 |
RPL09.Conn - Ext. GSIDFs - WBS Summary | GS.IDF (Exterior) | Not Started | 12/24/26 | 07/27/27 | 183.8 | 183.8 |
|
382.5 |
RPL09.CON.WP2.07200 |
RPL09.Conn - Ext. GSIDF9X01 (mCUP yard) - WBS Summary | Ext. IDF HUT - GSIDF9X01 | Not Started | 12/24/26 | 07/19/27 | 176.2 | 176.2 |
|
390.0 |
RPL09.CON.WP2.07220 |
RPL09.Conn - Ext. GSIDF9X01 - Install Infrastructure (Racks, Waterfalls etc.) | Infrastructure | Not Started | 12/24/26 | 12/31/26 | 6.2 | 6.2 |
|
375.0 |
RPL09.EY.DHB.01010 |
RPL09.EY.DHB - Install F/R/P Equipment Pads - 1-12(Grid 6-01/6-16) (12'' Larger For Tolerance) | Foundations | Not Started | 12/24/26 | 01/25/27 | 25.0 | 25.0 |
|
143.8 |
RPL09.EY.DHB.01020 |
RPL09.EY.DHB - Install Foundations - WBS Summary | Foundations | Not Started | 12/24/26 | 02/01/27 | 31.2 | 31.2 |
|
143.8 |
RPL09.EY.ENDC.1350 |
RPL09.EY.DHD.T1 - Install Saw Cut and Cure | Tent 1 | Not Started | 12/24/26 | 12/30/26 | 8.8 | 8.8 |
|
210.0 |
RPL09.MCUP.LP1.1260 |
RPL09.MCUP.Loop 1 - Set GS.IDF Hut (1x GS.IDF) XX02 (ROJ12.16.26) | OFE | Not Started | 12/24/26 | 12/31/26 | 6.2 | 6.2 |
|
188.8 |
RPL09.MCUP.LP1.1420 |
RPL09.MCUP.Loop 1 - Tie-in Electrical - WBS Summary | Tie-Ins Electrical | Not Started | 12/24/26 | 01/25/27 | 25.0 | 25.0 |
|
182.5 |
RPL09.MCUP.LP1.1480 |
RPL09.MCUP.Loop 1 - Tie-in Electrical #1 | Tie-Ins Electrical | Not Started | 12/24/26 | 01/13/27 | 16.2 | 16.2 |
|
191.2 |
RPL09.MCUP.LP1.1660 |
RPL09.MCUP.Loop 1 - Tie-in SD, DW | Tie-ins | Not Started | 12/24/26 | 01/15/27 | 18.8 | 18.8 |
|
481.2 |
RPL09.MCUP.LP1.1700 |
RPL09.MCUP.Loop 1 - Tie-in Electrical #2 | Tie-Ins Electrical | Not Started | 12/24/26 | 01/13/27 | 16.2 | 16.2 |
|
191.2 |
RPL09.SKN.DHAB.01000 |
RPL09.SKIN.DHAB - Install Temp Doors | Glazing, Doors and Ext Devices | Not Started | 12/24/26 | 12/28/26 | 2.5 | 2.5 |
|
131.2 |
RPL09.SKN.DHAB.01010 |
RPL09.SKIN.DHAB - IMP, Roof, Windows, Doors, Ext Devices - WBS Summary | DH A & DH B | Not Started | 12/24/26 | 02/01/27 | 31.2 | 31.2 |
|
366.2 |
RPL09.SKN.DHAB.01020 |
RPL09.SKIN.DHAB - Install Windows, Doors, Louvers and Ext Devices - WBS Summary | Glazing, Doors and Ext Devices | Not Started | 12/24/26 | 02/01/27 | 31.2 | 31.2 |
|
366.2 |
RPL09.SKN.DHAB.01070 |
RPL09.SKIN.DHAB - Install Roof System - Exterior Wall Sheething and EJ | Roofing | Not Started | 12/24/26 | 12/28/26 | 2.5 | 2.5 |
|
105.0 |
RPL09.SKN.DHAB.01080 |
RPL09.SKIN.DHAB - Install Roof System - WBS Summary | Roofing | Not Started | 12/24/26 | 02/01/27 | 31.2 | 31.2 |
|
215.0 |
RPL09.SKN.N.01040 |
RPL09.SKIN.North - Install IMP EJ - Grid lines 6-09/6-10 | DBC Move 2 - Grid (6-07 / 6-21) | Not Started | 12/24/26 | 12/31/26 | 6.2 | 6.2 |
|
115.0 |
RPL09.SKN.N.01080 |
RPL09.SKIN.North - Install IMP - Flashing,Panels & Caulking - Grid lines 6-14/6-21 (with temp closures for openings) | DBC Move 2 - Grid (6-07 / 6-21) | Not Started | 12/24/26 | 12/28/26 | 2.5 | 2.5 |
|
115.0 |
RPL09.SKN.N.01120 |
RPL09.SKIN.North - Install Stair Tower (DH B) | DBC Move 2 - Grid (6-07 / 6-21) | Not Started | 12/24/26 | 12/28/26 | 2.5 | 2.5 |
|
226.2 |
RPL09.EY.DHA.01560 |
RPL09.EY.DHA - Install Grounding UG | Underground | Not Started | 12/28/26 | 01/11/27 | 12.5 | 12.5 |
|
195.0 |
RPL09.EY.DHB.01540 |
RPL09.EY.DHB - Install Grounding UG | Underground | Not Started | 12/28/26 | 01/11/27 | 12.5 | 12.5 |
|
176.2 |
RPL09.EY.SSB.01080 |
RPL09.EY.SSB - Install BMS UG | Underground | Not Started | 12/28/26 | 01/04/27 | 6.2 | 6.2 |
|
188.8 |
RPL09.INT.1000 |
RPL09.Interior.BLDG - Install Priority OH, Walls, OFE and Fitout - WBS Summary | Interior Build-out | Not Started | 12/28/26 | 02/03/28 | 343.8 | 343.8 |
|
185.0 |
RPL09.INT.SSB.01005 |
RPL09.Interior - Priority - Install Hangers Support (SSB to Center Corr) (All Trades) | Early Priority OH MEPF | Not Started | 12/28/26 | 01/11/27 | 12.5 | 12.5 |
|
105.0 |
RPL09.MCUP.LP2.1360 |
RPL09.MCUP.Loop 2 - Set mCUPs XXMY.MCUP.06 (1 per 5 days) | OFE | Not Started | 12/28/26 | 01/04/27 | 6.2 | 6.2 |
|
341.2 |
RPL09.STR.DHCD.01060 |
RPL09.Structure.DHCD - Adjust MEP Verts and Grounding wire | Prep | Not Started | 12/28/26 | 01/04/27 | 6.2 | 6.2 |
|
130.0 |
RPL09.STR.DHCD.01070 |
RPL09.Structure.DHCD - Install Remaining UG and Subgrade Prep - WBS Summary | Prep | Not Started | 12/28/26 | 01/14/27 | 16.2 | 16.2 |
|
130.0 |
RPL09.SKN.DHAB.01090 |
RPL09.SKIN.DHAB - Install Roof System - Install Temp Flashing at EJ | Roofing | Not Started | 12/29/26 | 12/30/26 | 2.5 | 2.5 |
|
147.5 |
RPL09.SKN.DHAB.01100 |
RPL09.SKIN.DHAB - Install Roof System - DenseDeck & Flame Down | Roofing | Not Started | 12/29/26 | 01/07/27 | 8.8 | 8.8 |
|
105.0 |
RPL09.SKN.DHAB.01160 |
RPL09.SKIN.DHAB - Install Blocking of Canopy & Backing of Exterior Wall | Glazing, Doors and Ext Devices | Not Started | 12/29/26 | 01/05/27 | 6.2 | 6.2 |
|
131.2 |
RPL09.SKN.S.01080 |
RPL09.SKIN.South - Install IMP - Flashing,Panels & Caulking - Grid lines 6-14/6-21 (with temp closures for openings) | DBC Move 2 - Grid (6-07 / 6-21) | Not Started | 12/29/26 | 12/30/26 | 2.5 | 2.5 |
|
115.0 |
GCD.RPL09.1500 |
Start Slab-On-Grade Concrete - RPL09 | Construction Milestones | Not Started | 12/30/26 | 12/30/26 | 0.0 | 0.0 |
|
412.5 |
RPL09.EY.ENDC.1650 |
RPL09.EY.DHD.T2 - Install Saw Cut and Cure | Tent 2 | Not Started | 12/30/26 | 01/05/27 | 8.8 | 8.8 |
|
207.5 |
RPL09.INT.SSB.01010 |
RPL09.Interior.SSB - Priority - Install Duct (Highside OH space) | Early Priority OH MEPF | Not Started | 12/30/26 | 01/13/27 | 12.5 | 12.5 |
|
105.0 |
RPL09.MCUP.LP1.1540 |
RPL09.MCUP.Loop 1 - Tie-in BMS - WBS Summary | Tie-Ins BMS | Not Started | 12/30/26 | 01/25/27 | 21.2 | 21.2 |
|
188.8 |
RPL09.MCUP.LP1.1560 |
RPL09.MCUP.Loop 1 - Tie-in BMS #1 | Tie-Ins BMS | Not Started | 12/30/26 | 01/13/27 | 12.5 | 12.5 |
|
197.5 |
RPL09.MCUP.LP1.1580 |
RPL09.MCUP.Loop 1 - Tie-in EPMS - WBS Summary | Tie-Ins EPMS | Not Started | 12/30/26 | 01/25/27 | 21.2 | 21.2 |
|
182.5 |
RPL09.MCUP.LP1.1600 |
RPL09.MCUP.Loop 1 - Tie-in EPMS #1 | Tie-Ins EPMS | Not Started | 12/30/26 | 01/13/27 | 12.5 | 12.5 |
|
191.2 |
RPL09.MCUP.LP1.1720 |
RPL09.MCUP.Loop 1 - Tie-in EPMS #2 | Tie-Ins EPMS | Not Started | 12/30/26 | 01/13/27 | 12.5 | 12.5 |
|
191.2 |
RPL09.MCUP.LP1.1740 |
RPL09.MCUP.Loop 1 - Tie-in BMS #2 | Tie-Ins BMS | Not Started | 12/30/26 | 01/13/27 | 12.5 | 12.5 |
|
197.5 |
RPL09.STR.DHAB.01080 |
RPL09.Structure.DHAB - Install AB final grade and Vapor Barrier | Prep | Not Started | 12/30/26 | 01/06/27 | 6.2 | 6.2 |
|
113.8 |
RPL09.STR.SSB.01140 |
RPL09.Structure.SSB - SOG F/R/P #1 - Grid lines 6-01/6-04 | F/R/P | Not Started | 12/30/26 | 01/06/27 | 6.2 | 6.2 |
|
98.8 |
RPL09.STR.SSB.01150 |
RPL09.Structure.SSB - SOG F/R/P - WBS Summary | F/R/P | Not Started | 12/30/26 | 01/22/27 | 20.0 | 20.0 |
|
196.2 |
RPL.GF.D.N9150.XG |
GS.IDF Hut 2 Install Complete for RPL 9 | Give Milestones (XREFs) | Not Started | 12/31/26 | 12/31/26 | 0.0 | 0.0 |
|
560.0 |
RPL09.EY.SSB.01110 |
RPL09.EY.SSB - Install LD Electrical UG | Loading Dock | Not Started | 12/31/26 | 01/06/27 | 5.0 | 5.0 |
|
282.5 |
RPL09.EY.SSB.01120 |
RPL09.EY.SSB - Install AHU (3) - CFCI | OFE | Not Started | 12/31/26 | 01/11/27 | 8.8 | 8.8 |
|
191.2 |
RPL09.EY.SSB.01130 |
RPL09.EY.SSB - Install SD, DW, FW UG | Underground | Not Started | 12/31/26 | 01/14/27 | 12.5 | 12.5 |
|
172.5 |
RPL09.EY.SSB.01140 |
RPL09.EY.SSB - Install Loading Dock, UG Utilities, OFE - WBS Summary | Loading Dock | Not Started | 12/31/26 | 02/25/27 | 47.5 | 47.5 |
|
282.5 |
RPL09.SKN.S.01050 |
RPL09.SKIN.South - Install IMP - Flashing,Panels & Caulking - Grid lines 6-21/6-28 (with temp closures for openings) | DBC Move 3 - Grid (6-21 / 6-28) | Not Started | 12/31/26 | 01/04/27 | 2.5 | 2.5 |
|
115.0 |
RPL.09.D.94160.XG |
Ready for MV Cable Pull mCUP - Loop#2 (Qty 2)* | Give Milestones (XREFs) | Not Started | 01/04/27 | 01/04/27 | 0.0 | 0.0 |
|
558.8 |
RPL09.CON.WP2.07260 |
RPL09.Conn - Ext. GSIDF9X01 - Install Copper, WAPs, Security Camera & Access Control | Cabling | Not Started | 01/04/27 | 01/20/27 | 15.0 | 15.0 |
|
375.0 |
RPL09.CON.WP2.07400 |
RPL09.Conn - Ext. GSIDF9X02 (mCUP yard) - WBS Summary | Ext. IDF HUT - GSIDF9X02 | Not Started | 01/04/27 | 07/19/27 | 170.0 | 170.0 |
|
390.0 |
RPL09.CON.WP2.07420 |
RPL09.Conn - Ext. GSIDF9X02 - Install Infrastructure (Racks, Waterfalls etc.) | Infrastructure | Not Started | 01/04/27 | 01/08/27 | 6.2 | 6.2 |
|
368.8 |
RPL09.LOG.1160 |
Dry Cooler 230 Ton Crane Movement 02 | 100 Ton Crane | Not Started | 01/04/27 | 01/04/27 | 0.0 | 0.0 |
|
325.0 |
RPL09.MCUP.LP2.1300 |
RPL09.MCUP.Loop 2 - Set GS.IDF Hut (1x GS.IDF) XX03 (ROJ12.16.26) | OFE | Not Started | 01/04/27 | 01/08/27 | 6.2 | 6.2 |
|
336.2 |
RPL09.LOG.1100 |
MCUP 500 Ton Crane Demobilization | 300 Ton Crane | Not Started | 01/05/27 | 01/08/27 | 5.0 | 5.0 |
|
553.8 |
RPL09.MCUP.LP1.1980 |
RPL09.MCUP.Loop 1 - Tie-in Mechanical #4 | Tie-Ins Mechanical | Not Started | 01/05/27 | 01/22/27 | 16.2 | 16.2 |
|
190.0 |
RPL09.MCUP.LP2.1220 |
RPL09.MCUP.Loop 2 - Set mCup #5 & #6 - Dry Coolers (12) (4 per week) | OFE | Not Started | 01/05/27 | 01/26/27 | 18.8 | 18.8 |
|
325.0 |
RPL09.MCUP.LP2.2100 |
RPL09.MCUP.Loop 2 - Set Facility Water Pipe Rack (mCUP5) | OFE | Not Started | 01/05/27 | 01/14/27 | 10.0 | 10.0 |
|
331.2 |
RPL09.SKN.E.01000 |
RPL09.SKIN.East - Install IMP Insulated Metal Panels - Gird lines 6A/6F (with temp closures for openings) | DBC Move 3 - Grid (6-21 / 6-28) | Not Started | 01/05/27 | 01/06/27 | 2.5 | 2.5 |
|
115.0 |
RPL09.SKN.S.01070 |
RPL09.SKIN.South - Install IMP EJ - Grid lines 6-22/6-23 | DBC Move 3 - Grid (6-21 / 6-28) | Not Started | 01/05/27 | 01/11/27 | 6.2 | 6.2 |
|
120.0 |
RPL09.SKN.S.01120 |
RPL09.SKIN.South - Install Stair Tower (DH C) | DBC Move 3 - Grid (6-21 / 6-28) | Not Started | 01/05/27 | 01/06/27 | 2.5 | 2.5 |
|
503.8 |
RPL09.STR.DHCD.01080 |
RPL09.Structure.DHCD - Install AB final grade and Vapor Barrier | Prep | Not Started | 01/05/27 | 01/11/27 | 6.2 | 6.2 |
|
130.0 |
RPL09.SKN.DHAB.01030 |
RPL09.SKIN.DHAB - Install Awning over Doors | Glazing, Doors and Ext Devices | Not Started | 01/06/27 | 01/12/27 | 6.2 | 6.2 |
|
131.2 |
RPL09.EY.ENDC.02100 |
RPL09.EY.End - Install Temp Conditioning Units - CFCI | Temp Conditions | Not Started | 01/07/27 | 01/13/27 | 6.2 | 6.2 |
|
383.8 |
RPL09.EY.ENDC.1370 |
RPL09.EY.DHD.T1 - Install Tent | Tent 1 | Not Started | 01/07/27 | 02/04/27 | 25.0 | 25.0 |
|
138.8 |
RPL09.EY.ENDC.1670 |
RPL09.EY.DHD.T2 - Install Tent | Tent 2 | Not Started | 01/07/27 | 02/04/27 | 25.0 | 25.0 |
|
141.2 |
RPL09.EY.SSB.01150 |
RPL09.EY.SSB - Install LD Mechanical UG | Loading Dock | Not Started | 01/07/27 | 01/21/27 | 12.5 | 12.5 |
|
282.5 |
RPL09.MCUP.LP1.1860 |
RPL09.MCUP.Loop 1 - Tie-in Electrical #3 | Tie-Ins Electrical | Not Started | 01/07/27 | 01/21/27 | 12.5 | 12.5 |
|
185.0 |
RPL09.SKN.N.01050 |
RPL09.SKIN.North - Install IMP - Flashing,Panels & Caulking - Grid lines 6-21/6-28 (with temp closures for openings) | DBC Move 3 - Grid (6-21 / 6-28) | Not Started | 01/07/27 | 01/08/27 | 2.5 | 2.5 |
|
115.0 |
RPL09.STR.DHAB.01090 |
RPL09.Structure.DHAB - Asphalt Emulsion and Wrap Steel Columns | Prep | Not Started | 01/07/27 | 01/11/27 | 3.8 | 3.8 |
|
113.8 |
RPL09.STR.DHAB.01110 |
RPL09.Structure.DHAB - SOG F/R/P - Grid Lines 6-11/6-23 - WBS Summary | F/R/P | Not Started | 01/07/27 | 02/20/27 | 37.5 | 37.5 |
|
118.8 |
RPL09.STR.DHAB.01160 |
RPL09.Structure.DHAB - SOG F/R/P #2 - Grid lines 6-04/6-07 | F/R/P | Not Started | 01/07/27 | 01/13/27 | 6.2 | 6.2 |
|
98.8 |
RPL09.STR.SSB.01190 |
RPL09.Structure.SSB - Zone SOG Cure | F/R/P | Not Started | 01/07/27 | 01/13/27 | 8.8 | 8.8 |
|
172.5 |
RPL.GF.D.N9160.XG |
GS.IDF Hut 3 Install Complete for RPL 9 | Give Milestones (XREFs) | Not Started | 01/08/27 | 01/08/27 | 0.0 | 0.0 |
|
553.8 |
RPL09.EY.DHA.01100 |
RPL09.EY.DHA - Install Mechanical UG | Underground | Not Started | 01/08/27 | 01/22/27 | 12.5 | 12.5 |
|
185.0 |