Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL09 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:12 PM
· 5201 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
0
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL09.EY.DHA.01110 |
RPL09.EY.DHA - Install SD, DW, FW UG | Underground | Not Started | 01/08/27 | 01/22/27 | 12.5 | 12.5 |
|
195.0 |
RPL09.EY.DHB.01090 |
RPL09.EY.DHB - Install Mechanical UG | Underground | Not Started | 01/08/27 | 01/22/27 | 12.5 | 12.5 |
|
166.2 |
RPL09.EY.DHB.01100 |
RPL09.EY.DHB - Install SD, DW, FW UG | Underground | Not Started | 01/08/27 | 01/22/27 | 12.5 | 12.5 |
|
176.2 |
RPL09.EY.DHD.01030 |
RPL09.EY.DHD - Install Foundations, UG Utilities, OFE - WBS Summary | EY.DHD | Not Started | 01/08/27 | 12/03/27 | 283.8 | 283.8 |
|
271.2 |
RPL09.EY.DHD.01070 |
RPL09.EY.DHD - Install Electrical UG | Underground | Not Started | 01/08/27 | 01/22/27 | 12.5 | 12.5 |
|
308.8 |
RPL09.EY.DHD.01080 |
RPL09.EY.DHD - Install UG Utilities - WBS Summary | Underground | Not Started | 01/08/27 | 10/19/27 | 246.2 | 246.2 |
|
202.5 |
RPL09.INT.DHB.02160 |
RPL09.Interior.DHBADC - Priority - Install Fixed Draft/Smoke Curtain (#5) | Early Priority OH MEPF | Not Started | 01/08/27 | 01/21/27 | 11.2 | 11.2 |
|
143.8 |
RPL09.CON.WP2.07460 |
RPL09.Conn - Ext. GSIDF9X02 - Install Copper, WAPs, Security Camera & Access Control | Cabling | Not Started | 01/11/27 | 01/27/27 | 15.0 | 15.0 |
|
368.8 |
RPL09.CON.WP2.07600 |
RPL09.Conn - Ext. GSIDF9X03 (mCUP yard) - WBS Summary | Ext. IDF HUT - GSIDF9X03 | Not Started | 01/11/27 | 07/19/27 | 163.8 | 163.8 |
|
390.0 |
RPL09.CON.WP2.08400 |
RPL09.Conn - Ext. GSIDF9X03 - Install Infrastructure (Racks, Waterfalls etc.) | Infrastructure | Not Started | 01/11/27 | 01/15/27 | 6.2 | 6.2 |
|
362.5 |
RPL09.MCUP.LP1.1780 |
RPL09.MCUP.Loop 1 - Tie-in EPMS #3 | Tie-Ins EPMS | Not Started | 01/11/27 | 01/21/27 | 10.0 | 10.0 |
|
185.0 |
RPL09.MCUP.LP1.1800 |
RPL09.MCUP.Loop 1 - Tie-in BMS #3 | Tie-Ins BMS | Not Started | 01/11/27 | 01/21/27 | 10.0 | 10.0 |
|
191.2 |
RPL09.MCUP.LP1.1960 |
RPL09.MCUP.Loop 1 - Tie-in Electrical #4 | Tie-Ins Electrical | Not Started | 01/11/27 | 01/25/27 | 12.5 | 12.5 |
|
182.5 |
RPL09.SKN.N.01060 |
RPL09.SKIN.North - Install IMP EJ - Grid lines 6-22/6-23 | DBC Move 3 - Grid (6-21 / 6-28) | Not Started | 01/11/27 | 01/15/27 | 6.2 | 6.2 |
|
115.0 |
RPL09.SKN.N.01100 |
RPL09.SKIN.North - Secure All Exterior Mounted Boxes and Devices on Skin | IMP System | Not Started | 01/11/27 | 02/08/27 | 25.0 | 25.0 |
|
408.8 |
RPL09.SKN.N.01140 |
RPL09.SKIN.North - Install Stair Tower (DH D) | DBC Move 2 - Grid (6-07 / 6-21) | Not Started | 01/11/27 | 01/12/27 | 2.5 | 2.5 |
|
498.8 |
RPL09.SKN.S.01100 |
RPL09.SKIN.South - Secure All Exterior Mounted Boxes and Devices on Skin | IMP System | Not Started | 01/11/27 | 02/08/27 | 25.0 | 25.0 |
|
408.8 |
RPL09.EY.DHD.01130 |
RPL09.EY.DHD - Install Grounding UG | Underground | Not Started | 01/12/27 | 01/26/27 | 12.5 | 12.5 |
|
327.5 |
RPL09.EY.SSB.02060 |
RPL09.EY.SSB - Install Remaining Permanent Duct with insulation to AHU Units | Temp Conditions | Not Started | 01/12/27 | 01/22/27 | 10.0 | 10.0 |
|
191.2 |
RPL09.INT.SSB.01006 |
RPL09.Interior - Priority - Install Hangers Support (Center Corr to End Corr) (All Trades) | Early Priority OH MEPF | Not Started | 01/12/27 | 01/26/27 | 12.5 | 12.5 |
|
153.8 |
RPL09.MCUP.LP1.1640 |
RPL09.MCUP.Loop 1 - Set Electrical Skids #3 | OFE | Not Started | 01/12/27 | 01/13/27 | 2.5 | 2.5 |
|
182.5 |
RPL09.SKN.DHAB.01120 |
RPL09.SKIN.DHAB - Install Roof System - Final Roof | Roofing | Not Started | 01/12/27 | 01/28/27 | 15.0 | 15.0 |
|
215.0 |
RPL09.SKN.SSB.01140 |
RPL09.SKIN.SSB - Install Roof System - Install EJ | Roofing | Not Started | 01/12/27 | 01/19/27 | 6.2 | 6.2 |
|
146.2 |
RPL09.STR.DHCD.01090 |
RPL09.Structure.DHCD - Asphalt Emulsion and Wrap Steel Columns | Prep | Not Started | 01/12/27 | 01/14/27 | 3.8 | 3.8 |
|
130.0 |
RPL09.MCUP.LP1.1900 |
RPL09.MCUP.Loop 1 - Tie-in EPMS #4 | Tie-Ins EPMS | Not Started | 01/13/27 | 01/25/27 | 10.0 | 10.0 |
|
182.5 |
RPL09.MCUP.LP1.1940 |
RPL09.MCUP.Loop 1 - Tie-in BMS #4 | Tie-Ins BMS | Not Started | 01/13/27 | 01/25/27 | 10.0 | 10.0 |
|
188.8 |
RPL09.SKN.DHAB.01040 |
RPL09.SKIN.DHAB - Install Louvers | Glazing, Doors and Ext Devices | Not Started | 01/13/27 | 01/20/27 | 6.2 | 6.2 |
|
131.2 |
RPL09.SKN.DHAB.01110 |
RPL09.SKIN.DHAB - Install Scupper and Downspouts | Glazing, Doors and Ext Devices | Not Started | 01/13/27 | 01/20/27 | 6.2 | 6.2 |
|
376.2 |
RPL09.EY.ENDC.02080 |
RPL09.EY.End - Install Temp Duct to Permanent Duct | Temp Conditions | Not Started | 01/14/27 | 01/21/27 | 6.2 | 6.2 |
|
383.8 |
RPL09.INT.SSBC.01011 |
RPL09.Interior.SSB-Corridor - Priority - Install Duct (Highside OH space) | Early Priority OH MEPF | Not Started | 01/14/27 | 01/21/27 | 6.2 | 6.2 |
|
105.0 |
RPL09.INT.SSBC.01020 |
RPL09.Interior.SSB-Corridor - Install Priority OH, Walls, OFE and Fitout - WBS Summary | SSB Corridor | Not Started | 01/14/27 | 09/03/27 | 202.5 | 202.5 |
|
185.0 |
RPL09.INT.SSBC.02420 |
RPL09.Interior.SSBC - Priority GL9.04 - (P0) Apply Intumescent Paint to Deck | Priority Wall Grid Line 9-04 | Not Started | 01/14/27 | 02/04/27 | 18.8 | 18.8 |
|
113.8 |
RPL09.MCUP.LP1.1680 |
RPL09.MCUP.Loop 1 - Set Electrical Skids #4 | OFE | Not Started | 01/14/27 | 01/15/27 | 2.5 | 2.5 |
|
182.5 |
RPL09.STR.DHAB.01170 |
RPL09.Structure.DHAB - SOG F/R/P #3 - Grid lines 6-07/6-11 | F/R/P | Not Started | 01/14/27 | 01/21/27 | 6.2 | 6.2 |
|
98.8 |
RPL09.STR.SSB.01250 |
RPL09.Structure.SSB - Moisture requirements for floor Sealer | F/R/P | Not Started | 01/14/27 | 01/20/27 | 8.8 | 8.8 |
|
200.0 |
RPL.09.D.93750.XG |
RMUs Set - mCUP Loop 1 | Give Milestones (XREFs) | Not Started | 01/15/27 | 01/15/27 | 0.0 | 0.0 |
|
547.5 |
RPL09.MCUP.LP2.2120 |
RPL09.MCUP.Loop 2 - Set Facility Water Pipe Rack (mCUP6) | OFE | Not Started | 01/15/27 | 01/29/27 | 12.5 | 12.5 |
|
331.2 |
RPL09.CON.WP2.08520 |
RPL09.Conn - Ext. GSIDF9X03 - Install Copper, WAPs, Security Camera & Access Control | Cabling | Not Started | 01/19/27 | 02/03/27 | 15.0 | 15.0 |
|
362.5 |
RPL09.MCUP.LP1.1820 |
RPL09.MCUP.Loop 1 - Install Hardscape and Landscape - WBS Summary | Hardscape and Landscape | Not Started | 01/19/27 | 03/23/27 | 56.2 | 56.2 |
|
491.2 |
RPL09.MCUP.LP1.1840 |
RPL09.MCUP.Loop 1 - Install Sleeves MEPL | Hardscape and Landscape | Not Started | 01/19/27 | 01/25/27 | 6.2 | 6.2 |
|
491.2 |
RPL09.MCUP.LP1.2020 |
RPL09.MCUP.Loop 1 - Tie-in - MV Loop 2 L2 Checklist Completion | Tie-ins | Not Started | 01/19/27 | 02/01/27 | 12.5 | 12.5 |
|
182.5 |
RPL09.MCUP.LP1.2080 |
RPL09.MCUP.Loop 1 - Tie-in - Mechanical L2 Checklist Completion | Tie-ins | Not Started | 01/19/27 | 02/01/27 | 12.5 | 12.5 |
|
188.8 |
RPL09.MCUP.LP2.1400 |
RPL09.MCUP.Loop 2 - Tie-ins - WBS Summary | Tie-ins | Not Started | 01/19/27 | 02/22/27 | 30.0 | 30.0 |
|
470.0 |
RPL09.MCUP.LP2.1560 |
RPL09.MCUP.Loop 2 - Tie-in Electrical - WBS Summary | Tie-Ins Electrical | Not Started | 01/19/27 | 02/03/27 | 15.0 | 15.0 |
|
327.5 |
RPL09.MCUP.LP2.1580 |
RPL09.MCUP.Loop 2 - Tie-in Mechanical - WBS Summary | Tie-Ins Mechanical | Not Started | 01/19/27 | 02/12/27 | 23.8 | 23.8 |
|
325.0 |
RPL09.MCUP.LP2.1600 |
RPL09.MCUP.Loop 1 - Tie-in Mechanical #5 | Tie-Ins Mechanical | Not Started | 01/19/27 | 02/04/27 | 16.2 | 16.2 |
|
332.5 |
RPL09.MCUP.LP2.1620 |
RPL09.MCUP.Loop 2 - Tie-in Electrical #5 | Tie-Ins Electrical | Not Started | 01/19/27 | 02/01/27 | 12.5 | 12.5 |
|
330.0 |
RPL09.SKN.DHCD.01010 |
RPL09.SKIN.DHCD - IMP, Roof, Windows, Doors, Ext Devices - WBS Summary | DH C & DH D | Not Started | 01/19/27 | 11/01/27 | 250.0 | 250.0 |
|
260.0 |
RPL09.SKN.DHCD.01070 |
RPL09.SKIN.DHCD - Install Roof System - Exterior Wall Sheething | Roofing | Not Started | 01/19/27 | 01/22/27 | 5.0 | 5.0 |
|
115.0 |
RPL09.SKN.DHCD.01080 |
RPL09.SKIN.DHCD - Install Roof System - WBS Summary | Roofing | Not Started | 01/19/27 | 02/19/27 | 28.8 | 28.8 |
|
481.2 |
RPL09.INT.SSBC.01000 |
RPL09.Interior.SSB-Corridor - Priority - WBS Summary | Priority Walls & Overhead | Not Started | 01/20/27 | 03/16/27 | 48.8 | 48.8 |
|
151.2 |
RPL09.INT.SSBC.03240 |
RPL09.Interior.SSB-Corridor - Priority - Install Priority Soffit for Wall Tie-Ins/ Rock & HoW & Draft Blanket | Priority Walls & Overhead | Not Started | 01/20/27 | 01/26/27 | 6.2 | 6.2 |
|
113.8 |
RPL09.INT.SSB.01000 |
RPL09.Interior.SSB - Priority - WBS Summary | Priority Walls and OverHead | Not Started | 01/21/27 | 03/09/27 | 41.2 | 41.2 |
|
327.5 |
RPL09.INT.SSB.01020 |
RPL09.Interior.SSB - Install Priority OH, Walls and Fitout - WBS Summary | SSB | Not Started | 01/21/27 | 08/31/27 | 193.8 | 193.8 |
|
251.2 |
RPL09.INT.SSB.01030 |
RPL09.Interior.SSB - Priority - Install Fire Sprinkler (Highside OH space) | Early Priority OH MEPF | Not Started | 01/21/27 | 01/27/27 | 6.2 | 6.2 |
|
151.2 |
RPL09.INT.SSB.01040 |
RPL09.Interior.SSB - Priority - Install Temp Lighting (Show In Model) | Early Priority OH MEPF | Not Started | 01/21/27 | 01/27/27 | 6.2 | 6.2 |
|
151.2 |
RPL09.INT.SSB.03180 |
RPL09.Interior.SSB - Priority - Install Priority Soffit for Wall Tie-Ins/ Rock & HoW & Draft Blanket | Priority Walls and OverHead | Not Started | 01/21/27 | 02/03/27 | 12.5 | 12.5 |
|
138.8 |
RPL09.MCUP.LP2.1680 |
RPL09.MCUP.Loop 2 - Tie-in EPMS - WBS Summary | Tie-Ins EPMS | Not Started | 01/21/27 | 02/03/27 | 12.5 | 12.5 |
|
327.5 |
RPL09.MCUP.LP2.1700 |
RPL09.MCUP.Loop 2 - Tie-in EPMS #5 | Tie-Ins EPMS | Not Started | 01/21/27 | 02/01/27 | 10.0 | 10.0 |
|
330.0 |
RPL09.MCUP.LP2.2000 |
RPL09.MCUP.Loop 2 - Tie-in Electrical #6 | Tie-Ins Electrical | Not Started | 01/21/27 | 02/03/27 | 12.5 | 12.5 |
|
327.5 |
RPL09.SKN.DHAB.01050 |
RPL09.SKIN.DHAB - Install Lighting | Glazing, Doors and Ext Devices | Not Started | 01/21/27 | 01/26/27 | 5.0 | 5.0 |
|
346.2 |
RPL09.STR.SSB.01270 |
RPL09.Structure.SSB - Install SOG Sealer and Cure | F/R/P | Not Started | 01/21/27 | 01/22/27 | 2.5 | 2.5 |
|
285.0 |
RPL09.EY.DHA.01130 |
RPL09.EY.DHA - Cure (High Early Mix) | Foundations | Not Started | 01/22/27 | 01/28/27 | 8.8 | 8.8 |
|
240.0 |
RPL09.EY.DHC.01010 |
RPL09.EY.DHC - Install F/R/P Equipment Pads - 1-10 (Grid 6-17/6-28) (12'' Larger For Tolerance) | Foundations | Not Started | 01/22/27 | 02/11/27 | 18.8 | 18.8 |
|
295.0 |
RPL09.EY.DHC.01020 |
RPL09.EY.DHC - Install Foundations - WBS Summary | Foundations | Not Started | 01/22/27 | 11/04/27 | 250.0 | 250.0 |
|
211.2 |
RPL09.EY.DHC.01030 |
RPL09.EY.DHC - Install Foundations, UG Utilities, OFE - WBS Summary | EY.DHC | Not Started | 01/22/27 | 12/07/27 | 275.0 | 275.0 |
|
268.8 |
RPL09.EY.ENDC.01150 |
RPL09.EY.End - Tie-ins - WBS Summary | Tie-ins | Not Started | 01/22/27 | 01/04/28 | 296.2 | 296.2 |
|
137.5 |
RPL09.EY.ENDC.01320 |
RPL09.EY.End - Install Duct/ insulation into the building Main (include penetration detail) | Tie-ins | Not Started | 01/22/27 | 02/04/27 | 12.5 | 12.5 |
|
383.8 |
RPL09.EY.SSB.01190 |
RPL09.EY.SSB - Set LD Grade and Prep | Loading Dock | Not Started | 01/22/27 | 01/27/27 | 5.0 | 5.0 |
|
282.5 |
RPL09.INT.DHA.01010 |
RPL09.Interior.DHA - Priority - Install Duct | Early Priority OH MEPF | Not Started | 01/22/27 | 01/28/27 | 6.2 | 6.2 |
|
105.0 |
RPL09.INT.DHB.01010 |
RPL09.Interior.DHB - Priority - Install Duct | Early Priority OH MEPF | Not Started | 01/22/27 | 01/28/27 | 6.2 | 6.2 |
|
105.0 |
RPL09.MCUP.LP2.1440 |
RPL09.MCUP.Loop 2 - Set Electrical Skids #5 | OFE | Not Started | 01/22/27 | 01/25/27 | 2.5 | 2.5 |
|
327.5 |
RPL09.STR.DHAB.01180 |
RPL09.Structure.DHAB - SOG F/R/P #4 - Grid lines 6-11/6-14 | F/R/P | Not Started | 01/22/27 | 01/28/27 | 6.2 | 6.2 |
|
98.8 |
RPL09.EY.DHA.01120 |
RPL09.EY.DHA - Install BMS UG | Underground | Not Started | 01/25/27 | 02/05/27 | 12.5 | 12.5 |
|
185.0 |
RPL09.EY.DHA.01230 |
RPL09.EY.DHA - OFE - MV - WBS Summary | OFE | Not Started | 01/25/27 | 06/28/27 | 135.0 | 135.0 |
|
212.5 |
RPL09.EY.DHA.01540 |
RPL09.EY.DHA - Install AHUs (Qty 1) | OFE | Not Started | 01/25/27 | 02/03/27 | 10.0 | 10.0 |
|
336.2 |
RPL09.EY.DHB.01120 |
RPL09.EY.DHB - Install BMS/EPMS UG | Underground | Not Started | 01/25/27 | 02/05/27 | 12.5 | 12.5 |
|
166.2 |
RPL09.EY.DHC.01050 |
RPL09.EY.DHC - Install Electrical UG | Underground | Not Started | 01/25/27 | 02/05/27 | 12.5 | 12.5 |
|
308.8 |
RPL09.EY.DHC.01060 |
RPL09.EY.DHC - Install UG Utilities - WBS Summary | Underground | Not Started | 01/25/27 | 10/21/27 | 236.2 | 236.2 |
|
211.2 |
RPL09.EY.DHD.01100 |
RPL09.EY.DHD - Install Mechanical UG | Underground | Not Started | 01/25/27 | 02/05/27 | 12.5 | 12.5 |
|
317.5 |
RPL09.EY.DHD.01110 |
RPL09.EY.DHD - Install SD, DW, FW UG | Underground | Not Started | 01/25/27 | 02/05/27 | 12.5 | 12.5 |
|
315.0 |
RPL09.MCUP.LP2.1940 |
RPL09.MCUP.Loop 2 - Tie-in EPMS #6 | Tie-Ins EPMS | Not Started | 01/25/27 | 02/03/27 | 10.0 | 10.0 |
|
327.5 |
RPL09.SKN.DHCD.01090 |
RPL09.SKIN.DHCD - Install Roof System - DenseDeck & Flame Down | Roofing | Not Started | 01/25/27 | 02/02/27 | 8.8 | 8.8 |
|
115.0 |
RPL09.EY.DHB.01130 |
RPL09.EY.DHB - Cure (High Early Mix) | Foundations | Not Started | 01/26/27 | 02/01/27 | 8.8 | 8.8 |
|
208.8 |
RPL09.EY.DHD.01010 |
RPL09.EY.DHD - Install F/R/P Equipment Pads - 1-10 (Grid 6-17/6-28) (12'' Larger For Tolerance) | Foundations | Not Started | 01/26/27 | 02/16/27 | 18.8 | 18.8 |
|
276.2 |
RPL09.EY.DHD.01020 |
RPL09.EY.DHD - Install Foundations - WBS Summary | Foundations | Not Started | 01/26/27 | 11/02/27 | 245.0 | 245.0 |
|
202.5 |
RPL09.INT.SSB.02680 |
RPL09.Interior.SSB - Priority - Install Layout, Unistruts & Hangers (All Trades) | Priority Walls and OverHead | Not Started | 01/26/27 | 02/08/27 | 12.5 | 12.5 |
|
138.8 |
RPL09.MCUP.LP1.1920 |
RPL09.MCUP.Loop 1 - Install Early Mcup Paving | Hardscape and Landscape | Not Started | 01/26/27 | 02/08/27 | 12.5 | 12.5 |
|
491.2 |
RPL09.MCUP.LP1.2060 |
RPL09.MCUP.Loop 1 - Tie-in - Electrical L2 Checklist Completion | Tie-ins | Not Started | 01/26/27 | 02/08/27 | 12.5 | 12.5 |
|
182.5 |
RPL09.MCUP.LP2.1500 |
RPL09.MCUP.Loop 2 - Set Electrical Skids #6 | OFE | Not Started | 01/26/27 | 01/27/27 | 2.5 | 2.5 |
|
327.5 |
RPL09.MCUP.LP2.1660 |
RPL09.MCUP.Loop 2 - Tie-in BMS - WBS Summary | Tie-Ins BMS | Not Started | 01/26/27 | 02/12/27 | 17.5 | 17.5 |
|
325.0 |
RPL09.MCUP.LP2.1720 |
RPL09.MCUP.Loop 2 - Tie-in BMS #5 | Tie-Ins BMS | Not Started | 01/26/27 | 02/04/27 | 10.0 | 10.0 |
|
332.5 |
RPL.09.D.93760.XG |
RMUs Set - mCUP Loop 2 | Give Milestones (XREFs) | Not Started | 01/27/27 | 01/27/27 | 0.0 | 0.0 |
|
538.8 |
RPL09.EY.DHC.01530 |
RPL09.EY.DHC - Install Grounding UG | Underground | Not Started | 01/27/27 | 02/09/27 | 12.5 | 12.5 |
|
318.8 |
RPL09.INT.SSBC.02400 |
RPL09.Interior.SSB-Corridor - Priority - Install Layout, Unistruts & Hangers (All Trades) Both side of Corridor Wall | Priority Walls & Overhead | Not Started | 01/27/27 | 02/01/27 | 5.0 | 5.0 |
|
157.5 |
RPL09.INT.SSBC.03520 |
RPL09.Interior.SSB-Corridor - Priority - Install IMP Exterior Inwall Rough-In | Priority Walls & Overhead | Not Started | 01/27/27 | 01/29/27 | 3.8 | 3.8 |
|
157.5 |
RPL09.LOG.1300 |
Dry Cooler 230 Ton Crane Demobilization | 100 Ton Crane | Not Started | 01/27/27 | 01/29/27 | 3.8 | 3.8 |
|
470.0 |
RPL09.MCUP.LP2.1240 |
RPL09.MCUP.Loop 2 - Set MTRs (4 per day) | OFE | Not Started | 01/27/27 | 01/28/27 | 2.5 | 2.5 |
|
332.5 |
RPL09.MCUP.LP2.2020 |
RPL09.MCUP.Loop 1 - Tie-in Mechanical #6 | Tie-Ins Mechanical | Not Started | 01/27/27 | 02/12/27 | 16.2 | 16.2 |
|
325.0 |
RPL09.SKN.DHAB.01060 |
RPL09.SKIN.DHAB - Install Security | Glazing, Doors and Ext Devices | Not Started | 01/27/27 | 01/28/27 | 2.5 | 2.5 |
|
346.2 |