Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL09 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:12 PM · 5201 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
0
Completed
0
In Progress
0
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL09.EY.DHA.01110 RPL09.EY.DHA - Install SD, DW, FW UG Underground Not Started 01/08/27 01/22/27 12.5 12.5
0%
195.0
RPL09.EY.DHB.01090 RPL09.EY.DHB - Install Mechanical UG Underground Not Started 01/08/27 01/22/27 12.5 12.5
0%
166.2
RPL09.EY.DHB.01100 RPL09.EY.DHB - Install SD, DW, FW UG Underground Not Started 01/08/27 01/22/27 12.5 12.5
0%
176.2
RPL09.EY.DHD.01030 RPL09.EY.DHD - Install Foundations, UG Utilities, OFE - WBS Summary EY.DHD Not Started 01/08/27 12/03/27 283.8 283.8
0%
271.2
RPL09.EY.DHD.01070 RPL09.EY.DHD - Install Electrical UG Underground Not Started 01/08/27 01/22/27 12.5 12.5
0%
308.8
RPL09.EY.DHD.01080 RPL09.EY.DHD - Install UG Utilities - WBS Summary Underground Not Started 01/08/27 10/19/27 246.2 246.2
0%
202.5
RPL09.INT.DHB.02160 RPL09.Interior.DHBADC - Priority - Install Fixed Draft/Smoke Curtain (#5) Early Priority OH MEPF Not Started 01/08/27 01/21/27 11.2 11.2
0%
143.8
RPL09.CON.WP2.07460 RPL09.Conn - Ext. GSIDF9X02 - Install Copper, WAPs, Security Camera & Access Control Cabling Not Started 01/11/27 01/27/27 15.0 15.0
0%
368.8
RPL09.CON.WP2.07600 RPL09.Conn - Ext. GSIDF9X03 (mCUP yard) - WBS Summary Ext. IDF HUT - GSIDF9X03 Not Started 01/11/27 07/19/27 163.8 163.8
0%
390.0
RPL09.CON.WP2.08400 RPL09.Conn - Ext. GSIDF9X03 - Install Infrastructure (Racks, Waterfalls etc.) Infrastructure Not Started 01/11/27 01/15/27 6.2 6.2
0%
362.5
RPL09.MCUP.LP1.1780 RPL09.MCUP.Loop 1 - Tie-in EPMS #3 Tie-Ins EPMS Not Started 01/11/27 01/21/27 10.0 10.0
0%
185.0
RPL09.MCUP.LP1.1800 RPL09.MCUP.Loop 1 - Tie-in BMS #3 Tie-Ins BMS Not Started 01/11/27 01/21/27 10.0 10.0
0%
191.2
RPL09.MCUP.LP1.1960 RPL09.MCUP.Loop 1 - Tie-in Electrical #4 Tie-Ins Electrical Not Started 01/11/27 01/25/27 12.5 12.5
0%
182.5
RPL09.SKN.N.01060 RPL09.SKIN.North - Install IMP EJ - Grid lines 6-22/6-23 DBC Move 3 - Grid (6-21 / 6-28) Not Started 01/11/27 01/15/27 6.2 6.2
0%
115.0
RPL09.SKN.N.01100 RPL09.SKIN.North - Secure All Exterior Mounted Boxes and Devices on Skin IMP System Not Started 01/11/27 02/08/27 25.0 25.0
0%
408.8
RPL09.SKN.N.01140 RPL09.SKIN.North - Install Stair Tower (DH D) DBC Move 2 - Grid (6-07 / 6-21) Not Started 01/11/27 01/12/27 2.5 2.5
0%
498.8
RPL09.SKN.S.01100 RPL09.SKIN.South - Secure All Exterior Mounted Boxes and Devices on Skin IMP System Not Started 01/11/27 02/08/27 25.0 25.0
0%
408.8
RPL09.EY.DHD.01130 RPL09.EY.DHD - Install Grounding UG Underground Not Started 01/12/27 01/26/27 12.5 12.5
0%
327.5
RPL09.EY.SSB.02060 RPL09.EY.SSB - Install Remaining Permanent Duct with insulation to AHU Units Temp Conditions Not Started 01/12/27 01/22/27 10.0 10.0
0%
191.2
RPL09.INT.SSB.01006 RPL09.Interior - Priority - Install Hangers Support (Center Corr to End Corr) (All Trades) Early Priority OH MEPF Not Started 01/12/27 01/26/27 12.5 12.5
0%
153.8
RPL09.MCUP.LP1.1640 RPL09.MCUP.Loop 1 - Set Electrical Skids #3 OFE Not Started 01/12/27 01/13/27 2.5 2.5
0%
182.5
RPL09.SKN.DHAB.01120 RPL09.SKIN.DHAB - Install Roof System - Final Roof Roofing Not Started 01/12/27 01/28/27 15.0 15.0
0%
215.0
RPL09.SKN.SSB.01140 RPL09.SKIN.SSB - Install Roof System - Install EJ Roofing Not Started 01/12/27 01/19/27 6.2 6.2
0%
146.2
RPL09.STR.DHCD.01090 RPL09.Structure.DHCD - Asphalt Emulsion and Wrap Steel Columns Prep Not Started 01/12/27 01/14/27 3.8 3.8
0%
130.0
RPL09.MCUP.LP1.1900 RPL09.MCUP.Loop 1 - Tie-in EPMS #4 Tie-Ins EPMS Not Started 01/13/27 01/25/27 10.0 10.0
0%
182.5
RPL09.MCUP.LP1.1940 RPL09.MCUP.Loop 1 - Tie-in BMS #4 Tie-Ins BMS Not Started 01/13/27 01/25/27 10.0 10.0
0%
188.8
RPL09.SKN.DHAB.01040 RPL09.SKIN.DHAB - Install Louvers Glazing, Doors and Ext Devices Not Started 01/13/27 01/20/27 6.2 6.2
0%
131.2
RPL09.SKN.DHAB.01110 RPL09.SKIN.DHAB - Install Scupper and Downspouts Glazing, Doors and Ext Devices Not Started 01/13/27 01/20/27 6.2 6.2
0%
376.2
RPL09.EY.ENDC.02080 RPL09.EY.End - Install Temp Duct to Permanent Duct Temp Conditions Not Started 01/14/27 01/21/27 6.2 6.2
0%
383.8
RPL09.INT.SSBC.01011 RPL09.Interior.SSB-Corridor - Priority - Install Duct (Highside OH space) Early Priority OH MEPF Not Started 01/14/27 01/21/27 6.2 6.2
0%
105.0
RPL09.INT.SSBC.01020 RPL09.Interior.SSB-Corridor - Install Priority OH, Walls, OFE and Fitout - WBS Summary SSB Corridor Not Started 01/14/27 09/03/27 202.5 202.5
0%
185.0
RPL09.INT.SSBC.02420 RPL09.Interior.SSBC - Priority GL9.04 - (P0) Apply Intumescent Paint to Deck Priority Wall Grid Line 9-04 Not Started 01/14/27 02/04/27 18.8 18.8
0%
113.8
RPL09.MCUP.LP1.1680 RPL09.MCUP.Loop 1 - Set Electrical Skids #4 OFE Not Started 01/14/27 01/15/27 2.5 2.5
0%
182.5
RPL09.STR.DHAB.01170 RPL09.Structure.DHAB - SOG F/R/P #3 - Grid lines 6-07/6-11 F/R/P Not Started 01/14/27 01/21/27 6.2 6.2
0%
98.8
RPL09.STR.SSB.01250 RPL09.Structure.SSB - Moisture requirements for floor Sealer F/R/P Not Started 01/14/27 01/20/27 8.8 8.8
0%
200.0
RPL.09.D.93750.XG RMUs Set - mCUP Loop 1 Give Milestones (XREFs) Not Started 01/15/27 01/15/27 0.0 0.0
0%
547.5
RPL09.MCUP.LP2.2120 RPL09.MCUP.Loop 2 - Set Facility Water Pipe Rack (mCUP6) OFE Not Started 01/15/27 01/29/27 12.5 12.5
0%
331.2
RPL09.CON.WP2.08520 RPL09.Conn - Ext. GSIDF9X03 - Install Copper, WAPs, Security Camera & Access Control Cabling Not Started 01/19/27 02/03/27 15.0 15.0
0%
362.5
RPL09.MCUP.LP1.1820 RPL09.MCUP.Loop 1 - Install Hardscape and Landscape - WBS Summary Hardscape and Landscape Not Started 01/19/27 03/23/27 56.2 56.2
0%
491.2
RPL09.MCUP.LP1.1840 RPL09.MCUP.Loop 1 - Install Sleeves MEPL Hardscape and Landscape Not Started 01/19/27 01/25/27 6.2 6.2
0%
491.2
RPL09.MCUP.LP1.2020 RPL09.MCUP.Loop 1 - Tie-in - MV Loop 2 L2 Checklist Completion Tie-ins Not Started 01/19/27 02/01/27 12.5 12.5
0%
182.5
RPL09.MCUP.LP1.2080 RPL09.MCUP.Loop 1 - Tie-in - Mechanical L2 Checklist Completion Tie-ins Not Started 01/19/27 02/01/27 12.5 12.5
0%
188.8
RPL09.MCUP.LP2.1400 RPL09.MCUP.Loop 2 - Tie-ins - WBS Summary Tie-ins Not Started 01/19/27 02/22/27 30.0 30.0
0%
470.0
RPL09.MCUP.LP2.1560 RPL09.MCUP.Loop 2 - Tie-in Electrical - WBS Summary Tie-Ins Electrical Not Started 01/19/27 02/03/27 15.0 15.0
0%
327.5
RPL09.MCUP.LP2.1580 RPL09.MCUP.Loop 2 - Tie-in Mechanical - WBS Summary Tie-Ins Mechanical Not Started 01/19/27 02/12/27 23.8 23.8
0%
325.0
RPL09.MCUP.LP2.1600 RPL09.MCUP.Loop 1 - Tie-in Mechanical #5 Tie-Ins Mechanical Not Started 01/19/27 02/04/27 16.2 16.2
0%
332.5
RPL09.MCUP.LP2.1620 RPL09.MCUP.Loop 2 - Tie-in Electrical #5 Tie-Ins Electrical Not Started 01/19/27 02/01/27 12.5 12.5
0%
330.0
RPL09.SKN.DHCD.01010 RPL09.SKIN.DHCD - IMP, Roof, Windows, Doors, Ext Devices - WBS Summary DH C & DH D Not Started 01/19/27 11/01/27 250.0 250.0
0%
260.0
RPL09.SKN.DHCD.01070 RPL09.SKIN.DHCD - Install Roof System - Exterior Wall Sheething Roofing Not Started 01/19/27 01/22/27 5.0 5.0
0%
115.0
RPL09.SKN.DHCD.01080 RPL09.SKIN.DHCD - Install Roof System - WBS Summary Roofing Not Started 01/19/27 02/19/27 28.8 28.8
0%
481.2
RPL09.INT.SSBC.01000 RPL09.Interior.SSB-Corridor - Priority - WBS Summary Priority Walls & Overhead Not Started 01/20/27 03/16/27 48.8 48.8
0%
151.2
RPL09.INT.SSBC.03240 RPL09.Interior.SSB-Corridor - Priority - Install Priority Soffit for Wall Tie-Ins/ Rock & HoW & Draft Blanket Priority Walls & Overhead Not Started 01/20/27 01/26/27 6.2 6.2
0%
113.8
RPL09.INT.SSB.01000 RPL09.Interior.SSB - Priority - WBS Summary Priority Walls and OverHead Not Started 01/21/27 03/09/27 41.2 41.2
0%
327.5
RPL09.INT.SSB.01020 RPL09.Interior.SSB - Install Priority OH, Walls and Fitout - WBS Summary SSB Not Started 01/21/27 08/31/27 193.8 193.8
0%
251.2
RPL09.INT.SSB.01030 RPL09.Interior.SSB - Priority - Install Fire Sprinkler (Highside OH space) Early Priority OH MEPF Not Started 01/21/27 01/27/27 6.2 6.2
0%
151.2
RPL09.INT.SSB.01040 RPL09.Interior.SSB - Priority - Install Temp Lighting (Show In Model) Early Priority OH MEPF Not Started 01/21/27 01/27/27 6.2 6.2
0%
151.2
RPL09.INT.SSB.03180 RPL09.Interior.SSB - Priority - Install Priority Soffit for Wall Tie-Ins/ Rock & HoW & Draft Blanket Priority Walls and OverHead Not Started 01/21/27 02/03/27 12.5 12.5
0%
138.8
RPL09.MCUP.LP2.1680 RPL09.MCUP.Loop 2 - Tie-in EPMS - WBS Summary Tie-Ins EPMS Not Started 01/21/27 02/03/27 12.5 12.5
0%
327.5
RPL09.MCUP.LP2.1700 RPL09.MCUP.Loop 2 - Tie-in EPMS #5 Tie-Ins EPMS Not Started 01/21/27 02/01/27 10.0 10.0
0%
330.0
RPL09.MCUP.LP2.2000 RPL09.MCUP.Loop 2 - Tie-in Electrical #6 Tie-Ins Electrical Not Started 01/21/27 02/03/27 12.5 12.5
0%
327.5
RPL09.SKN.DHAB.01050 RPL09.SKIN.DHAB - Install Lighting Glazing, Doors and Ext Devices Not Started 01/21/27 01/26/27 5.0 5.0
0%
346.2
RPL09.STR.SSB.01270 RPL09.Structure.SSB - Install SOG Sealer and Cure F/R/P Not Started 01/21/27 01/22/27 2.5 2.5
0%
285.0
RPL09.EY.DHA.01130 RPL09.EY.DHA - Cure (High Early Mix) Foundations Not Started 01/22/27 01/28/27 8.8 8.8
0%
240.0
RPL09.EY.DHC.01010 RPL09.EY.DHC - Install F/R/P Equipment Pads - 1-10 (Grid 6-17/6-28) (12'' Larger For Tolerance) Foundations Not Started 01/22/27 02/11/27 18.8 18.8
0%
295.0
RPL09.EY.DHC.01020 RPL09.EY.DHC - Install Foundations - WBS Summary Foundations Not Started 01/22/27 11/04/27 250.0 250.0
0%
211.2
RPL09.EY.DHC.01030 RPL09.EY.DHC - Install Foundations, UG Utilities, OFE - WBS Summary EY.DHC Not Started 01/22/27 12/07/27 275.0 275.0
0%
268.8
RPL09.EY.ENDC.01150 RPL09.EY.End - Tie-ins - WBS Summary Tie-ins Not Started 01/22/27 01/04/28 296.2 296.2
0%
137.5
RPL09.EY.ENDC.01320 RPL09.EY.End - Install Duct/ insulation into the building Main (include penetration detail) Tie-ins Not Started 01/22/27 02/04/27 12.5 12.5
0%
383.8
RPL09.EY.SSB.01190 RPL09.EY.SSB - Set LD Grade and Prep Loading Dock Not Started 01/22/27 01/27/27 5.0 5.0
0%
282.5
RPL09.INT.DHA.01010 RPL09.Interior.DHA - Priority - Install Duct Early Priority OH MEPF Not Started 01/22/27 01/28/27 6.2 6.2
0%
105.0
RPL09.INT.DHB.01010 RPL09.Interior.DHB - Priority - Install Duct Early Priority OH MEPF Not Started 01/22/27 01/28/27 6.2 6.2
0%
105.0
RPL09.MCUP.LP2.1440 RPL09.MCUP.Loop 2 - Set Electrical Skids #5 OFE Not Started 01/22/27 01/25/27 2.5 2.5
0%
327.5
RPL09.STR.DHAB.01180 RPL09.Structure.DHAB - SOG F/R/P #4 - Grid lines 6-11/6-14 F/R/P Not Started 01/22/27 01/28/27 6.2 6.2
0%
98.8
RPL09.EY.DHA.01120 RPL09.EY.DHA - Install BMS UG Underground Not Started 01/25/27 02/05/27 12.5 12.5
0%
185.0
RPL09.EY.DHA.01230 RPL09.EY.DHA - OFE - MV - WBS Summary OFE Not Started 01/25/27 06/28/27 135.0 135.0
0%
212.5
RPL09.EY.DHA.01540 RPL09.EY.DHA - Install AHUs (Qty 1) OFE Not Started 01/25/27 02/03/27 10.0 10.0
0%
336.2
RPL09.EY.DHB.01120 RPL09.EY.DHB - Install BMS/EPMS UG Underground Not Started 01/25/27 02/05/27 12.5 12.5
0%
166.2
RPL09.EY.DHC.01050 RPL09.EY.DHC - Install Electrical UG Underground Not Started 01/25/27 02/05/27 12.5 12.5
0%
308.8
RPL09.EY.DHC.01060 RPL09.EY.DHC - Install UG Utilities - WBS Summary Underground Not Started 01/25/27 10/21/27 236.2 236.2
0%
211.2
RPL09.EY.DHD.01100 RPL09.EY.DHD - Install Mechanical UG Underground Not Started 01/25/27 02/05/27 12.5 12.5
0%
317.5
RPL09.EY.DHD.01110 RPL09.EY.DHD - Install SD, DW, FW UG Underground Not Started 01/25/27 02/05/27 12.5 12.5
0%
315.0
RPL09.MCUP.LP2.1940 RPL09.MCUP.Loop 2 - Tie-in EPMS #6 Tie-Ins EPMS Not Started 01/25/27 02/03/27 10.0 10.0
0%
327.5
RPL09.SKN.DHCD.01090 RPL09.SKIN.DHCD - Install Roof System - DenseDeck & Flame Down Roofing Not Started 01/25/27 02/02/27 8.8 8.8
0%
115.0
RPL09.EY.DHB.01130 RPL09.EY.DHB - Cure (High Early Mix) Foundations Not Started 01/26/27 02/01/27 8.8 8.8
0%
208.8
RPL09.EY.DHD.01010 RPL09.EY.DHD - Install F/R/P Equipment Pads - 1-10 (Grid 6-17/6-28) (12'' Larger For Tolerance) Foundations Not Started 01/26/27 02/16/27 18.8 18.8
0%
276.2
RPL09.EY.DHD.01020 RPL09.EY.DHD - Install Foundations - WBS Summary Foundations Not Started 01/26/27 11/02/27 245.0 245.0
0%
202.5
RPL09.INT.SSB.02680 RPL09.Interior.SSB - Priority - Install Layout, Unistruts & Hangers (All Trades) Priority Walls and OverHead Not Started 01/26/27 02/08/27 12.5 12.5
0%
138.8
RPL09.MCUP.LP1.1920 RPL09.MCUP.Loop 1 - Install Early Mcup Paving Hardscape and Landscape Not Started 01/26/27 02/08/27 12.5 12.5
0%
491.2
RPL09.MCUP.LP1.2060 RPL09.MCUP.Loop 1 - Tie-in - Electrical L2 Checklist Completion Tie-ins Not Started 01/26/27 02/08/27 12.5 12.5
0%
182.5
RPL09.MCUP.LP2.1500 RPL09.MCUP.Loop 2 - Set Electrical Skids #6 OFE Not Started 01/26/27 01/27/27 2.5 2.5
0%
327.5
RPL09.MCUP.LP2.1660 RPL09.MCUP.Loop 2 - Tie-in BMS - WBS Summary Tie-Ins BMS Not Started 01/26/27 02/12/27 17.5 17.5
0%
325.0
RPL09.MCUP.LP2.1720 RPL09.MCUP.Loop 2 - Tie-in BMS #5 Tie-Ins BMS Not Started 01/26/27 02/04/27 10.0 10.0
0%
332.5
RPL.09.D.93760.XG RMUs Set - mCUP Loop 2 Give Milestones (XREFs) Not Started 01/27/27 01/27/27 0.0 0.0
0%
538.8
RPL09.EY.DHC.01530 RPL09.EY.DHC - Install Grounding UG Underground Not Started 01/27/27 02/09/27 12.5 12.5
0%
318.8
RPL09.INT.SSBC.02400 RPL09.Interior.SSB-Corridor - Priority - Install Layout, Unistruts & Hangers (All Trades) Both side of Corridor Wall Priority Walls & Overhead Not Started 01/27/27 02/01/27 5.0 5.0
0%
157.5
RPL09.INT.SSBC.03520 RPL09.Interior.SSB-Corridor - Priority - Install IMP Exterior Inwall Rough-In Priority Walls & Overhead Not Started 01/27/27 01/29/27 3.8 3.8
0%
157.5
RPL09.LOG.1300 Dry Cooler 230 Ton Crane Demobilization 100 Ton Crane Not Started 01/27/27 01/29/27 3.8 3.8
0%
470.0
RPL09.MCUP.LP2.1240 RPL09.MCUP.Loop 2 - Set MTRs (4 per day) OFE Not Started 01/27/27 01/28/27 2.5 2.5
0%
332.5
RPL09.MCUP.LP2.2020 RPL09.MCUP.Loop 1 - Tie-in Mechanical #6 Tie-Ins Mechanical Not Started 01/27/27 02/12/27 16.2 16.2
0%
325.0
RPL09.SKN.DHAB.01060 RPL09.SKIN.DHAB - Install Security Glazing, Doors and Ext Devices Not Started 01/27/27 01/28/27 2.5 2.5
0%
346.2