Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL09 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:12 PM
· 5201 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
0
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
GCD.RPL09.1020 |
Weather tight SSB and DHA&B | Construction Milestones | Not Started | 01/28/27 | 01/28/27 | 0.0 | 0.0 |
|
387.5 |
RPL09.EY.SSB.01200 |
RPL09.EY.SSB - Install LD F/R/P Loading Dock Ramp | Loading Dock | Not Started | 01/28/27 | 02/08/27 | 10.0 | 10.0 |
|
282.5 |
RPL09.INT.SSB.06640 |
RPL09.Interior.SSB - Priority - Install IMP Exterior Inwall Rough-In | Priority Walls and OverHead | Not Started | 01/28/27 | 02/03/27 | 6.2 | 6.2 |
|
138.8 |
RPL09.INT.SSBC.01030 |
RPL09.Interior.SSB-Corridor - Priority - Install Fire Sprinkler (Highside OH space) | Early Priority OH MEPF | Not Started | 01/28/27 | 01/28/27 | 1.2 | 1.2 |
|
151.2 |
RPL09.INT.SSBC.01040 |
RPL09.Interior.SSB-Corridor - Priority - Install Temp Lighting (Show In Model) | Early Priority OH MEPF | Not Started | 01/28/27 | 02/01/27 | 3.8 | 3.8 |
|
151.2 |
RPL.09.D.94210.XR |
FW Water Available for mCUP Flush/Fill - Utility connections | Receive Milestones (XREFs) | Not Started | 01/29/27 | 01/29/27 | 0.0 | 0.0 |
|
216.2 |
RPL.09.D.94410.XR |
Discharge Available for Fill/Flush Cx - Utility connections | Receive Milestones (XREFs) | Not Started | 01/29/27 | 01/29/27 | 0.0 | 0.0 |
|
216.2 |
RPL09.EY.DHA.01530 |
RPL09.EY.DHA - Set GS.IDF Hut (1x GS.IDF) XX04 | OFE | Not Started | 01/29/27 | 02/04/27 | 6.2 | 6.2 |
|
336.2 |
RPL09.INT.CTRC.1180 |
RPL09.Interior.Center-Corridor - Priority - Install Duct (Highside OH space) | Early Priority OH MEPF | Not Started | 01/29/27 | 02/08/27 | 8.8 | 8.8 |
|
223.8 |
RPL09.INT.DHA.01020 |
RPL09.Interior.DHA - Install Priority OH, Walls, OFE and Tie-ins - WBS Summary | DHA | Not Started | 01/29/27 | 10/05/27 | 216.2 | 216.2 |
|
172.5 |
RPL09.INT.DHA.03380 |
RPL09.Interior.DHA - Temp Conditions - Drop Curtains (from Corridor to EJ) | Temp Conditions | Not Started | 01/29/27 | 02/09/27 | 10.0 | 10.0 |
|
105.0 |
RPL09.INT.DHB.01020 |
RPL09.Interior.DHB - Install Priority OH, Walls, OFE and Tie-ins - WBS Summary | DHB | Not Started | 01/29/27 | 09/07/27 | 191.2 | 191.2 |
|
186.2 |
RPL09.INT.DHB.01030 |
RPL09.Interior.DHB - Priority - Install Fire Sprinkler | Early Priority OH MEPF | Not Started | 01/29/27 | 02/04/27 | 6.2 | 6.2 |
|
151.2 |
RPL09.INT.DHB.01060 |
RPL09.Interior.DHB - Temp Conditions - Drop Curtains (from Corridor to EJ) | Temp Conditions | Not Started | 01/29/27 | 02/08/27 | 8.8 | 8.8 |
|
106.2 |
RPL09.INT.SSBC.06600 |
RPL09.Interior.SSB-Corridor - Priority - Install Backing at Exterior Wall | Priority Walls & Overhead | Not Started | 01/29/27 | 01/29/27 | 1.2 | 1.2 |
|
157.5 |
RPL09.SKN.DHAB.01130 |
RPL09.SKIN.DHAB - Install Roof System - Install EJ | Roofing | Not Started | 01/29/27 | 02/01/27 | 2.5 | 2.5 |
|
215.0 |
RPL09.SKN.DHAB.01140 |
RPL09.SKIN.DHAB - Install Perm Doors | Glazing, Doors and Ext Devices | Not Started | 01/29/27 | 02/01/27 | 2.5 | 2.5 |
|
346.2 |
RPL09.STR.DHAB.01100 |
RPL09.Structure.DHAB - SOG F/R/P #5 - Grid lines 6-14/6-18 | F/R/P | Not Started | 01/29/27 | 02/04/27 | 6.2 | 6.2 |
|
98.8 |
RPL09.INT.SSB.02840 |
RPL09.Interior.SSB - Priority - Tape Finish Paint Priority Soffit (Top Out) | Priority Walls and OverHead | Not Started | 02/01/27 | 02/12/27 | 12.5 | 12.5 |
|
202.5 |
RPL09.INT.SSBC.06620 |
RPL09.Interior.SSB-Corridor - Priority - QC - Backings/Walls | Priority Walls & Overhead | Not Started | 02/01/27 | 02/02/27 | 2.5 | 2.5 |
|
177.5 |
RPL09.INT.SSBC.06720 |
RPL09.Interior.SSB-Corridor - Priority - Install Drywall at Exterior Walls for SSB Electrical Room | Priority Walls & Overhead | Not Started | 02/01/27 | 02/02/27 | 2.5 | 2.5 |
|
157.5 |
RPL09.MCUP.LP2.1420 |
RPL09.MCUP.Loop 2 - Tie-in SD, DW | Tie-ins | Not Started | 02/01/27 | 02/22/27 | 18.8 | 18.8 |
|
470.0 |
RPL09.CX.1180 |
RPL09.CX.BLDG - L3, L4, IST - WBS Summary | Commissioning | Not Started | 02/02/27 | 10/03/28 | 522.5 | 522.5 |
|
12.5 |
RPL09.CX.MCUP.01000 |
RPL09.CX.mCup Loop 1 - L3, L4, IST - WBS Summary | mCUP 1-4 | Not Started | 02/02/27 | 08/26/27 | 180.0 | 180.0 |
|
355.0 |
RPL09.CX.MCUP.01350 |
RPL09.CX.mCup Loop 1 - L3/L4 - mCUP - Flush and Fill - Temp Flush Skid (PR) | Fill and Flush | Not Started | 02/02/27 | 02/08/27 | 6.2 | 6.2 |
|
213.8 |
RPL09.INT.DHB.01040 |
RPL09.Interior.DHB - Priority - Install Temp Lighting | Early Priority OH MEPF | Not Started | 02/02/27 | 02/04/27 | 3.8 | 3.8 |
|
151.2 |
RPL09.INT.SSB.06560 |
RPL09.Interior.SSB - Priority - Install Backing at Exterior Wall | Priority Walls and OverHead | Not Started | 02/02/27 | 02/08/27 | 6.2 | 6.2 |
|
138.8 |
RPL09.CON.WP2.09180 |
RPL09.Conn - CorpNet & FacNet Available (mCUP) - All IDFs | WP#02 GS | Not Started | 02/03/27 | 02/03/27 | 0.0 | 0.0 |
|
532.5 |
RPL09.Conn.MS.01080 |
RPL09.Conn Wifi Ready - mCUP Yard (Pred from RPL10 CorpNet needed?) | Connectivity Milestones | Not Started | 02/03/27 | 02/03/27 | 0.0 | 0.0 |
|
362.5 |
RPL09.INT.SSBC.06740 |
RPL09.Interior.SSB-Corridor - Priority - Frame, Hang Drywall, Tape Finish Paint for SSB Electrical Room | Priority Walls & Overhead | Not Started | 02/03/27 | 02/11/27 | 8.8 | 8.8 |
|
178.8 |
RPL09.MCUP.LP2.1980 |
RPL09.MCUP.Loop 2 - Tie-in BMS #6 | Tie-Ins BMS | Not Started | 02/03/27 | 02/12/27 | 10.0 | 10.0 |
|
325.0 |
RPL09.SKN.DHCD.01110 |
RPL09.SKIN.DHCD - Install Roof System - Final Roof | Roofing | Not Started | 02/03/27 | 02/19/27 | 15.0 | 15.0 |
|
481.2 |
RPL.GF.D.N9170.XG |
GS.IDF Hut 4 Install Complete for RPL 9 | Give Milestones (XREFs) | Not Started | 02/04/27 | 02/04/27 | 0.0 | 0.0 |
|
531.2 |
RPL09.MCUP.LP2.2040 |
RPL09.MCUP.Loop 2 - Tie-in - MV Loop 2 L2 Checklist Completion | Tie-ins | Not Started | 02/04/27 | 02/10/27 | 6.2 | 6.2 |
|
327.5 |
RPL.GF.D.N9170.XR |
Natural Gas Available for Fill/Flush Cx - Utility connections | Receive Milestones (XREFs) | Not Started | 02/05/27 | 02/05/27 | 0.0 | 0.0 |
|
216.2 |
RPL09.CON.WP2.07800 |
RPL09.Conn - Ext. GSIDF9X04 (South Elec Yard) - WBS Summary | Ext. IDF HUT - GSIDF9X04 | Not Started | 02/05/27 | 07/27/27 | 148.8 | 148.8 |
|
382.5 |
RPL09.CON.WP2.08460 |
RPL09.Conn - Ext. GSIDF9X04 - Install Infrastructure (Racks, Waterfalls etc.) ??pred?? | Infrastructure | Not Started | 02/05/27 | 02/11/27 | 6.2 | 6.2 |
|
336.2 |
RPL09.EY.ENDC.1390 |
RPL09.EY.DHD.T1 - Install Panels | Tent 1 | Not Started | 02/05/27 | 02/11/27 | 6.2 | 6.2 |
|
142.5 |
RPL09.EY.ENDC.1410 |
RPL09.EY.DHD.T1 - Install Heating and Cooling Equipment | Tent 1 | Not Started | 02/05/27 | 02/11/27 | 6.2 | 6.2 |
|
138.8 |
RPL09.EY.ENDC.1430 |
RPL09.EY.DHD.T1 - Install Overhead Doors | Tent 1 | Not Started | 02/05/27 | 02/11/27 | 6.2 | 6.2 |
|
146.2 |
RPL09.EY.ENDC.1450 |
RPL09.EY.DHD.T1 - Install Tent Fit-out | Tent 1 | Not Started | 02/05/27 | 02/19/27 | 12.5 | 12.5 |
|
140.0 |
RPL09.EY.ENDC.1690 |
RPL09.EY.DHD.T2 - Install Panels | Tent 2 | Not Started | 02/05/27 | 02/11/27 | 6.2 | 6.2 |
|
145.0 |
RPL09.EY.ENDC.1710 |
RPL09.EY.DHD.T2 - Install Heating and Cooling Equipment | Tent 2 | Not Started | 02/05/27 | 02/11/27 | 6.2 | 6.2 |
|
141.2 |
RPL09.EY.ENDC.1730 |
RPL09.EY.DHD.T2 - Install Overhead Doors | Tent 2 | Not Started | 02/05/27 | 02/11/27 | 6.2 | 6.2 |
|
148.8 |
RPL09.EY.ENDC.1750 |
RPL09.EY.DHD.T2 - Install Tent Fit-out | Tent 2 | Not Started | 02/05/27 | 02/19/27 | 12.5 | 12.5 |
|
142.5 |
RPL09.INT.DHA.01030 |
RPL09.Interior.DHA - Priority - Install Fire Sprinkler | Early Priority OH MEPF | Not Started | 02/05/27 | 02/11/27 | 6.2 | 6.2 |
|
218.8 |
RPL09.INT.DHB.01090 |
RPL09.Interior.DHB - Temp Conditions - Install Early Temp Conditions | Temp Conditions | Not Started | 02/05/27 | 02/08/27 | 2.5 | 2.5 |
|
106.2 |
RPL09.INT.SSBC.03280 |
RPL09.Interior.SSBC - Priority GL9.04 - (P0) Frame Walls (All full height Walls) | Priority Wall Grid Line 9-04 | Not Started | 02/05/27 | 02/11/27 | 6.2 | 6.2 |
|
155.0 |
RPL09.INT.SSBC.03500 |
RPL09.Interior.SSB-Corridor - Priority - Install Drywall at Exterior Walls | Priority Walls & Overhead | Not Started | 02/05/27 | 02/09/27 | 3.8 | 3.8 |
|
175.0 |
RPL09.STR.DHAB.01140 |
RPL09.Structure.DHAB - Zone SOG Cure | F/R/P | Not Started | 02/05/27 | 02/11/27 | 8.8 | 8.8 |
|
143.8 |
RPL09.STR.DHCD.01110 |
RPL09.Structure.DHCD - SOG F/R/P - WBS Summary | F/R/P | Not Started | 02/05/27 | 03/14/27 | 31.2 | 31.2 |
|
180.0 |
RPL09.STR.DHCD.01120 |
RPL09.Structure.DHCD - SOG F/R/P #6 - Grid lines 6-18/6-21 | F/R/P | Not Started | 02/05/27 | 02/11/27 | 6.2 | 6.2 |
|
112.5 |
RPL09.EY.DHC.01090 |
RPL09.EY.DHC - Install Mechanical UG | Underground | Not Started | 02/08/27 | 02/22/27 | 12.5 | 12.5 |
|
308.8 |
RPL09.EY.DHC.01100 |
RPL09.EY.DHC - Install SD, DW, FW UG | Underground | Not Started | 02/08/27 | 02/22/27 | 12.5 | 12.5 |
|
318.8 |
RPL09.EY.ENDC.01000 |
RPL09.EY.End - Install Electrical UG | Underground | Not Started | 02/08/27 | 02/12/27 | 6.2 | 6.2 |
|
361.2 |
RPL09.EY.ENDC.01010 |
RPL09.EY.End - Install UG Utilities - WBS Summary | Underground | Not Started | 02/08/27 | 03/08/27 | 25.0 | 25.0 |
|
370.0 |
RPL09.INT.DHA.03400 |
RPL09.Interior.DHA - Temp Conditions - Install Early Temp Conditions | Temp Conditions | Not Started | 02/08/27 | 02/09/27 | 2.5 | 2.5 |
|
105.0 |
GCD.RPL09.2051 |
MCUP Ready for Energization - (MCUPs Loop 1) | mCup | Not Started | 02/09/27 | 02/09/27 | 0.0 | 0.0 |
|
208.8 |
ICM.B9.1212 |
[SSDCB4] Start Flush & Fill of Chilled Water System | Commissioning | Not Started | 02/09/27 | 02/09/27 | 0.0 | 0.0 |
|
220.0 |
RPL09.CX.MCUP.01150 |
RPL09.CX.mCup Loop 1 - L3/L4 - mCUP - Flush and Fill - mCup Yard & FWM - Loop 1 (mCUPs 1-4) (Phase 1) | Fill and Flush | Not Started | 02/09/27 | 02/16/27 | 6.2 | 6.2 |
|
213.8 |
RPL09.EY.SSB.01210 |
RPL09.EY.SSB - Install LD Electrical In walls | Loading Dock | Not Started | 02/09/27 | 02/12/27 | 5.0 | 5.0 |
|
282.5 |
RPL09.EY.SSB.01220 |
RPL09.EY.SSB - Install LD French Drain (Not Designed) | Loading Dock | Not Started | 02/09/27 | 02/12/27 | 5.0 | 5.0 |
|
292.5 |
RPL09.INT.DHA.01040 |
RPL09.Interior.DHA - Priority - Install Temp Lighting | Early Priority OH MEPF | Not Started | 02/09/27 | 02/11/27 | 3.8 | 3.8 |
|
223.8 |
RPL09.INT.DHB.02360 |
RPL09.Interior.DHB - Temp Conditions - CC West Duct Work Complete for Temp Conditioning (LVs) | Temp Conditions | Not Started | 02/09/27 | 02/10/27 | 2.5 | 2.5 |
|
106.2 |
RPL09.INT.SSB.06580 |
RPL09.Interior.SSB - Priority - QC - Backings/Walls | Priority Walls and OverHead | Not Started | 02/09/27 | 02/16/27 | 6.2 | 6.2 |
|
138.8 |
RPL09.MCUP.LP1.2000 |
RPL09.MCUP.Loop 1 - Install Lighting | Hardscape and Landscape | Not Started | 02/09/27 | 02/23/27 | 12.5 | 12.5 |
|
491.2 |
RPL09.SKN.E.01040 |
RPL09.SKIN.East - Secure All Exterior Mounted Boxes and Devices on Skin | IMP System | Not Started | 02/09/27 | 02/23/27 | 12.5 | 12.5 |
|
408.8 |
RPL09.EY.ENDC.01340 |
RPL09.EY.End - Install Grounding UG | Underground | Not Started | 02/10/27 | 02/17/27 | 6.2 | 6.2 |
|
380.0 |
RPL09.INT.DHA.03420 |
RPL09.Interior.DHA - Temp Conditions - CC West Duct Work Complete for Temp Conditioning (LVs) | Temp Conditions | Not Started | 02/10/27 | 02/11/27 | 2.5 | 2.5 |
|
105.0 |
RPL09.INT.SSBC.03260 |
RPL09.Interior.SSB-Corridor - Priority - Tape Finish Paint Priority Soffit both sides (Top Out) | Priority Walls & Overhead | Not Started | 02/10/27 | 02/17/27 | 6.2 | 6.2 |
|
175.0 |
RPL09.INT.SSBC.06660 |
RPL09.Interior.SSBC - Priority GL9.04 - (P0) Install MEP In-Wall/Backing | Priority Wall Grid Line 9-04 | Not Started | 02/10/27 | 02/16/27 | 5.0 | 5.0 |
|
155.0 |
RPL09.MCUP.LP2.2060 |
RPL09.MCUP.Loop 2 - Tie-in - Electrical L2 Checklist Completion | Tie-ins | Not Started | 02/11/27 | 02/18/27 | 6.2 | 6.2 |
|
327.5 |
RPL09.CON.WP2.08540 |
RPL09.Conn - Ext. GSIDF9X04 - Install Copper, WAPs, Security Camera & Access Control (EY-DH A) | Cabling | Not Started | 02/12/27 | 03/02/27 | 15.0 | 15.0 |
|
336.2 |
RPL09.EY.DHC.01130 |
RPL09.EY.DHC - Cure (High Early Mix) | Foundations | Not Started | 02/12/27 | 02/18/27 | 8.8 | 8.8 |
|
435.0 |
RPL09.EY.ENDC.1470 |
RPL09.EY.DHD.T1 - Install Electrical Tie-ins | Tent 1 | Not Started | 02/12/27 | 02/17/27 | 3.8 | 3.8 |
|
142.5 |
RPL09.EY.ENDC.1490 |
RPL09.EY.DHD.T1 - Install Mechanical Tie-ins | Tent 1 | Not Started | 02/12/27 | 02/22/27 | 7.5 | 7.5 |
|
138.8 |
RPL09.EY.ENDC.1770 |
RPL09.EY.DHD.T2 - Install Electrical Tie-ins | Tent 2 | Not Started | 02/12/27 | 02/17/27 | 3.8 | 3.8 |
|
145.0 |
RPL09.EY.ENDC.1790 |
RPL09.EY.DHD.T2 - Install Mechanical Tie-ins | Tent 2 | Not Started | 02/12/27 | 02/22/27 | 7.5 | 7.5 |
|
141.2 |
RPL09.INT.CTRC.1040 |
RPL09.Interior.Center-Corridor - Priority - Install Fire Sprinkler (Highside OH space) | Early Priority OH MEPF | Not Started | 02/12/27 | 02/17/27 | 3.8 | 3.8 |
|
218.8 |
RPL09.INT.CTRC.1060 |
RPL09.Interior.Center-Corridor - Priority - Install Temp Lighting (Show In Model) | Early Priority OH MEPF | Not Started | 02/12/27 | 02/17/27 | 3.8 | 3.8 |
|
223.8 |
RPL09.INT.DHA.03460 |
RPL09.Interior.DHA - Temp Conditions - Temp Conditioning Achieved & Acclimated for West of CC (SSB/DHB/DHA) | Temp Conditions | Not Started | 02/12/27 | 02/19/27 | 6.2 | 6.2 |
|
105.0 |
RPL09.INT.DHB.01000 |
RPL09.Interior.DHB - Priority OH - WBS Summary | OverHead | Not Started | 02/12/27 | 03/24/27 | 35.0 | 35.0 |
|
125.0 |
RPL09.INT.DHB.02100 |
RPL09.Interior.DHB - Priority - Install Mechanical Piping | OverHead | Not Started | 02/12/27 | 03/05/27 | 18.8 | 18.8 |
|
112.5 |
RPL09.INT.SSBC.06640 |
RPL09.Interior.SSBC - Priority GL9.04 - (P0) Install IMP Wall | Priority Wall Grid Line 9-04 | Not Started | 02/12/27 | 02/18/27 | 5.0 | 5.0 |
|
161.2 |
RPL09.INT.SSBC.06680 |
RPL09.Interior.SSBC - Priority GL9.04 - (P0) Hang Drywall (Both SIdes) | Priority Wall Grid Line 9-04 | Not Started | 02/12/27 | 02/18/27 | 5.0 | 5.0 |
|
155.0 |
RPL09.STR.DHAB.01240 |
RPL09.Structure.DHAB - Moisture requirements for floor Sealer | F/R/P | Not Started | 02/12/27 | 02/18/27 | 8.8 | 8.8 |
|
143.8 |
RPL09.STR.DHCD.01130 |
RPL09.Structure.DHCD - SOG F/R/P #7 - Grid lines 6-21/6-25 | F/R/P | Not Started | 02/12/27 | 02/19/27 | 6.2 | 6.2 |
|
118.8 |
RPL09.EY.ENDC.01030 |
RPL09.EY.End - Install Mechanical UG | Underground | Not Started | 02/16/27 | 02/22/27 | 6.2 | 6.2 |
|
361.2 |
RPL09.EY.SSB.01230 |
RPL09.EY.SSB - Install LD F/R/P Loading Dock Walls | Loading Dock | Not Started | 02/16/27 | 02/25/27 | 10.0 | 10.0 |
|
282.5 |
RPL09.MCUP.LP2.2080 |
RPL09.MCUP.Loop 2 - Tie-in - Mechanical L2 Checklist Completion | Tie-ins | Not Started | 02/16/27 | 02/22/27 | 6.2 | 6.2 |
|
325.0 |
ICM.B9.1750 |
[SSDCB4] Room Ready for GS.MDF Module Placement | Construction | Not Started | 02/17/27 | 02/17/27 | 0.0 | 0.0 |
|
175.0 |
RPL09.CX.MCUP.01190 |
RPL09.CX.mCup Loop 1 - L3/L4 - mCUP - Flush and Fill - mCup1 and Dry Coolers | Fill and Flush | Not Started | 02/17/27 | 02/24/27 | 7.5 | 7.5 |
|
213.8 |
RPL09.CX.MCUP.01210 |
RPL09.CX.mCup Loop 1 - L3/L4 - mCUP - Flush and Fill - mCup2 and Dry Coolers | Fill and Flush | Not Started | 02/17/27 | 02/24/27 | 7.5 | 7.5 |
|
213.8 |
RPL09.EY.DHD.01120 |
RPL09.EY.DHD - Cure (High Early Mix) | Foundations | Not Started | 02/17/27 | 02/23/27 | 8.8 | 8.8 |
|
403.8 |
RPL09.INT.SSB.06540 |
RPL09.Interior.SSB - Priority - Install Drywall at Exterior Walls | Priority Walls and OverHead | Not Started | 02/17/27 | 03/02/27 | 12.5 | 12.5 |
|
138.8 |
RPL09.EY.ENDC.01040 |
RPL09.EY.End - Install BMS UG | Underground | Not Started | 02/18/27 | 02/24/27 | 6.2 | 6.2 |
|
380.0 |
RPL09.INT.DHD.01030 |
RPL09.Interior.DHD - Priority - Install Fire Sprinkler | Early Priority OH MEPF | Not Started | 02/18/27 | 02/24/27 | 6.2 | 6.2 |
|
218.8 |
RPL09.INT.DHD.01040 |
RPL09.Interior.DHD - Priority - Install Temp Lighting | Early Priority OH MEPF | Not Started | 02/18/27 | 02/22/27 | 3.8 | 3.8 |
|
223.8 |
RPL09.INT.DHA.01000 |
RPL09.Interior.DHA - Priority OH - WBS Summary | OverHead | Not Started | 02/19/27 | 04/26/27 | 57.5 | 57.5 |
|
313.8 |
RPL09.INT.DHA.01980 |
RPL09.Interior.DHA - Priority - Install Unistruts & Hangers (All Trades) | OverHead | Not Started | 02/19/27 | 02/25/27 | 6.2 | 6.2 |
|
111.2 |