Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL09 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:12 PM
· 5201 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
0
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL09.INT.DHA.02400 |
RPL09.Interior.DHA - Priority - IMP Exterior Inwall Rough-In | OverHead | Not Started | 02/19/27 | 02/25/27 | 6.2 | 6.2 |
|
111.2 |
RPL09.INT.DHB.02140 |
RPL09.Interior.DHB - Priority - Install Unistruts & Hangers (All Trades) | OverHead | Not Started | 02/19/27 | 02/25/27 | 6.2 | 6.2 |
|
98.8 |
RPL09.INT.DHB.02340 |
RPL09.Interior.DHB - Priority - Install IMP Exterior Inwall Rough-In (These walls available early) | OverHead | Not Started | 02/19/27 | 02/25/27 | 6.2 | 6.2 |
|
98.8 |
RPL09.INT.SSB.01050 |
RPL09.Interior.SSB - Priority - (P1) Frame Walls (Frame full height Walls) | Priority Wall - P1 | Not Started | 02/19/27 | 02/25/27 | 6.2 | 6.2 |
|
198.8 |
RPL09.INT.SSB.06840 |
RPL09.Interior.SSB - Priority - (P1) Frame Reamining Walls | Priority Wall - P1 | Not Started | 02/19/27 | 02/23/27 | 3.8 | 3.8 |
|
241.2 |
RPL09.INT.SSBC.06700 |
RPL09.Interior.SSBC - Priority GL9.04 - (P0) Tape Finish Paint (Both SIdes) | Priority Wall Grid Line 9-04 | Not Started | 02/19/27 | 02/25/27 | 6.2 | 6.2 |
|
155.0 |
RPL09.STR.DHAB.01260 |
RPL09.Structure.DHAB - Install SOG Sealer and Cure | F/R/P | Not Started | 02/19/27 | 02/20/27 | 2.5 | 2.5 |
|
171.2 |
RPL09.WA.OFE.01000 |
RPL09.WA - Weather Allowance - FDN to OFE | Weather Allowance | Not Started | 02/20/27 | 03/07/27 | 20.0 | 20.0 |
|
152.5 |
RPL09.EY.SSB.01160 |
RPL09.EY.SSB - Install Electrical Tie-ins (include penetration detail) | Tie-ins | Not Started | 02/22/27 | 03/19/27 | 25.0 | 25.0 |
|
142.5 |
RPL09.EY.SSB.01170 |
RPL09.EY.SSB - Install Mechanical Main (include penetration detail) | Tie-ins | Not Started | 02/22/27 | 03/12/27 | 18.8 | 18.8 |
|
136.2 |
RPL09.INT.CTRC.01020 |
RPL09.Interior.Center-Corridor - Install Priority OH, Walls, OFE and Fitout - WBS Summary | Center Corridor | Not Started | 02/22/27 | 10/27/27 | 217.5 | 217.5 |
|
133.8 |
RPL09.INT.CTRC.03460 |
RPL09.Interior.Center-Corridor - Priority - Priority - WBS Summary | Priority Walls & Overhead | Not Started | 02/22/27 | 05/06/27 | 66.2 | 66.2 |
|
185.0 |
RPL09.INT.CTRC.1020 |
RPL09.Interior.Center-Corridor - Priority - Install Priority Soffit for Wall Tie-Ins/ Rock & HoW & Draft Blanket | Priority Walls & Overhead | Not Started | 02/22/27 | 02/26/27 | 6.2 | 6.2 |
|
118.8 |
RPL09.INT.CTRC.7740 |
RPL09.Interior.Center-Corridor - Priority - Install IMP Exterior Inwall Rough-In | Priority Walls & Overhead | Not Started | 02/22/27 | 02/26/27 | 6.2 | 6.2 |
|
125.0 |
RPL09.STR.DHCD.01140 |
RPL09.Structure.DHCD - SOG F/R/P #8 - Grid lines 6-25/6-28 | F/R/P | Not Started | 02/22/27 | 02/26/27 | 6.2 | 6.2 |
|
157.5 |
GCD.RPL09.3985 |
MCUP Ready for Energization - (MCUPs Loop 2) | mCup | Not Started | 02/23/27 | 02/23/27 | 0.0 | 0.0 |
|
458.8 |
RPL09.CX.MCUP.01020 |
RPL09.CX.mCup Loop 2 - L3, L4, IST - WBS Summary | mCUP 5-6 | Not Started | 02/23/27 | 10/05/27 | 196.2 | 196.2 |
|
321.2 |
RPL09.CX.MCUP.01100 |
RPL09.CX.mCup Loop 2 - L3/L4 - mCUP - Flush and Fill - mCup Yard - Loop 2 (mCUPs 5-6) (Phase 3) | Fill and Flush | Not Started | 02/23/27 | 03/01/27 | 6.2 | 6.2 |
|
356.2 |
RPL09.EY.DHC.01120 |
RPL09.EY.DHC - Install BMS UG | Underground | Not Started | 02/23/27 | 03/08/27 | 12.5 | 12.5 |
|
308.8 |
RPL09.EY.ENDC.01050 |
RPL09.EY.End - Install SD, DW, FW UG | Underground | Not Started | 02/23/27 | 03/08/27 | 12.5 | 12.5 |
|
363.8 |
RPL09.EY.ENDC.1510 |
RPL09.EY.DHD.T1 - Temp Conditioning Startup and Available | Tent 1 | Not Started | 02/23/27 | 02/24/27 | 2.5 | 2.5 |
|
138.8 |
RPL09.EY.ENDC.1810 |
RPL09.EY.DHD.T2 - Temp Conditioning Startup and Available | Tent 2 | Not Started | 02/23/27 | 02/24/27 | 2.5 | 2.5 |
|
141.2 |
RPL09.MCUP.LP2.1520 |
RPL09.MCUP.Loop 2 - Install Hardscape and Landscape - WBS Summary | Hardscape and Landscape | Not Started | 02/23/27 | 04/16/27 | 47.5 | 47.5 |
|
470.0 |
RPL09.MCUP.LP2.1540 |
RPL09.MCUP.Loop 2 - Install Sleeves MEPL | Hardscape and Landscape | Not Started | 02/23/27 | 02/25/27 | 3.8 | 3.8 |
|
470.0 |
RPL09.EY.SSB.01240 |
RPL09.EY.SSB - Install BMS/EPMS Tie-ins | Tie-ins | Not Started | 02/24/27 | 03/16/27 | 18.8 | 18.8 |
|
146.2 |
RPL09.INT.DHA.03440 |
RPL09.Interior.DHA - Priority - Install Backing at Exterior Wall | OverHead | Not Started | 02/24/27 | 02/25/27 | 2.5 | 2.5 |
|
111.2 |
RPL09.INT.DHB.02380 |
RPL09.Interior.DHB - Priority - Install Backing at Exterior Wall | OverHead | Not Started | 02/24/27 | 02/25/27 | 2.5 | 2.5 |
|
98.8 |
RPL09.INT.SSB.01660 |
RPL09.Interior.SSB - Priority - Install Plumbing (Highside OH space) | Priority Walls and OverHead | Not Started | 02/24/27 | 03/02/27 | 6.2 | 6.2 |
|
145.0 |
RPL09.INT.SSB.01680 |
RPL09.Interior.SSB - Priority - Install Mechanical Piping/ Refrigerant (Highside OH space) | Priority Walls and OverHead | Not Started | 02/24/27 | 03/02/27 | 6.2 | 6.2 |
|
138.8 |
RPL09.INT.SSB.03200 |
RPL09.Interior.SSB - Priority - Install Fire Alarm hangers & members (Highside OH space) | Priority Walls and OverHead | Not Started | 02/24/27 | 03/02/27 | 6.2 | 6.2 |
|
333.8 |
RPL09.INT.SSB.06880 |
RPL09.Interior.SSB - Priority - (P1) Install Reamining MEP In-Wall/Backing | Priority Wall - P1 | Not Started | 02/24/27 | 02/26/27 | 3.8 | 3.8 |
|
241.2 |
RPL09.MCUP.LP1.2040 |
RPL09.MCUP.Loop 1 - Install Mcup Paving | Hardscape and Landscape | Not Started | 02/24/27 | 03/09/27 | 12.5 | 12.5 |
|
491.2 |
RPL09.SKN.DHCD.01000 |
RPL09.SKIN.DHCD - Install Temp Doors | Glazing, Doors and Ext Devices | Not Started | 02/24/27 | 02/25/27 | 2.5 | 2.5 |
|
408.8 |
RPL09.SKN.DHCD.01020 |
RPL09.SKIN.DHCD - Install Windows, Doors, Louvers and Ext Devices - WBS Summary | Glazing, Doors and Ext Devices | Not Started | 02/24/27 | 11/01/27 | 218.8 | 218.8 |
|
222.5 |
RPL09.CX.MCUP.01230 |
RPL09.CX.mCup Loop 1 - L3/L4 - mCUP - Flush and Fill - mCup3 and Dry Coolers | Fill and Flush | Not Started | 02/25/27 | 03/04/27 | 7.5 | 7.5 |
|
213.8 |
RPL09.CX.MCUP.01250 |
RPL09.CX.mCup Loop 1 - L3/L4 - mCUP - Flush and Fill - mCup4 and Dry Coolers | Fill and Flush | Not Started | 02/25/27 | 03/04/27 | 7.5 | 7.5 |
|
216.2 |
RPL09.INT.DHC.01030 |
RPL09.Interior.DHC - Priority - Install Fire Sprinkler | Early Priority OH MEPF | Not Started | 02/25/27 | 03/03/27 | 6.2 | 6.2 |
|
218.8 |
GCD.RPL09.1280 |
Interior fit-out Start RPL09 - DHA&B | Construction Milestones | Not Started | 02/26/27 | 02/26/27 | 0.0 | 0.0 |
|
363.8 |
RPL09.INT.DHA.02380 |
RPL09.Interior.DHA - Priority - Install Drywall at Exterior Walls | OverHead | Not Started | 02/26/27 | 03/08/27 | 8.8 | 8.8 |
|
111.2 |
RPL09.INT.DHB.02320 |
RPL09.Interior.DHB - Priority - Install Drywall at Exterior Walls | OverHead | Not Started | 02/26/27 | 03/08/27 | 8.8 | 8.8 |
|
98.8 |
RPL09.INT.SSB.01170 |
RPL09.Interior.SSB - Loading Dock and Storage - WBS Summary | Loading Dock and Storage | Not Started | 02/26/27 | 08/09/27 | 142.5 | 142.5 |
|
208.8 |
RPL09.INT.SSB.02900 |
RPL09.Interior.SSB - Loading Dock and Storage - Pre Priority OH & Walls Tasks (Unistruts,Hangers,Track) | Loading Dock and Storage | Not Started | 02/26/27 | 03/04/27 | 6.2 | 6.2 |
|
208.8 |
RPL09.INT.SSB.06780 |
RPL09.Interior.SSB - Priority - (P1) Install MEP In-Wall/Backing | Priority Wall - P1 | Not Started | 02/26/27 | 03/03/27 | 5.0 | 5.0 |
|
235.0 |
RPL09.MCUP.LP2.1640 |
RPL09.MCUP.Loop 2 - Install Early Mcup Paving | Hardscape and Landscape | Not Started | 02/26/27 | 03/11/27 | 12.5 | 12.5 |
|
470.0 |
RPL09.SKN.DHCD.01140 |
RPL09.SKIN.DHCD - Install Blocking of Canopy & Backing of Exterior Wall | Glazing, Doors and Ext Devices | Not Started | 02/26/27 | 03/04/27 | 6.2 | 6.2 |
|
408.8 |
RPL09.STR.DHCD.01150 |
RPL09.Structure.DHCD - Zone SOG Cure | F/R/P | Not Started | 02/27/27 | 03/05/27 | 8.8 | 8.8 |
|
226.2 |
ICM.B9.1840 |
[SSDCB4] Delivery of DES - Data Hall Electrical Room Skid (First Delivery) | Construction | Not Started | 03/01/27 | 03/01/27 | 0.0 | 0.0 |
|
165.0 |
ICM.B9.1855 |
[SSDCB4] Delivery of MES - Multi Trade Rack (First Delivery) | Construction | Not Started | 03/01/27 | 03/01/27 | 0.0 | 0.0 |
|
152.5 |
RPL09.INT.CTRC.1000 |
RPL09.Interior.Center-Corridor - Priority - Install Unistruts & Hangers (All Trades) Both side of Corridor Wall | Priority Walls & Overhead | Not Started | 03/01/27 | 03/05/27 | 6.2 | 6.2 |
|
118.8 |
RPL09.INT.DHC.01040 |
RPL09.Interior.DHC - Priority - Install Temp Lighting | Early Priority OH MEPF | Not Started | 03/01/27 | 03/03/27 | 3.8 | 3.8 |
|
218.8 |
RPL09.INT.SSB.06860 |
RPL09.Interior.SSB - Priority - (P1) Reamining Wall Hang Drywall (Both Sides) | Priority Wall - P1 | Not Started | 03/01/27 | 03/02/27 | 2.5 | 2.5 |
|
241.2 |
RPL09.INT.DHB.01050 |
RPL09.Interior.DHB - Priority - Install FA / Linear heat detection | OverHead | Not Started | 03/02/27 | 03/08/27 | 6.2 | 6.2 |
|
105.0 |
RPL09.INT.DHB.02300 |
RPL09.Interior.DHB - Priority - Install Electrical | OverHead | Not Started | 03/02/27 | 03/22/27 | 18.8 | 18.8 |
|
98.8 |
RPL09.INT.DHC.01010 |
RPL09.Interior.DHC - Priority - Install Duct | Early Priority OH MEPF | Not Started | 03/02/27 | 03/05/27 | 5.0 | 5.0 |
|
277.5 |
RPL09.INT.DHD.01010 |
RPL09.Interior.DHD - Priority - Install Duct | Early Priority OH MEPF | Not Started | 03/02/27 | 03/08/27 | 5.0 | 5.0 |
|
277.5 |
RPL09.INT.SSBC.01060 |
RPL09.Interior.SSB-Corridor - OFE - Early Equipment (1x SSB Elect) | OFE/MOFE & CFCI | Not Started | 03/02/27 | 03/15/27 | 12.5 | 12.5 |
|
165.0 |
RPL09.CON.WP2.08560 |
RPL09.Conn - Ext. GSIDF9X04 - Install Copper, WAPs, Security Camera & Access Control (EY-DH C) | Cabling | Not Started | 03/03/27 | 03/18/27 | 15.0 | 15.0 |
|
336.2 |
RPL09.INT.SSB.03220 |
RPL09.Interior.SSB - Priority - Install Fire Safing/ Seal all Penetrations through Soffit (Highside OH space) | Priority Walls and OverHead | Not Started | 03/03/27 | 03/09/27 | 6.2 | 6.2 |
|
188.8 |
RPL09.INT.SSB.06900 |
RPL09.Interior.SSB - Priority - (P1) Reamining Wall Tape Finish Paint (Both Sides) | Priority Wall - P1 | Not Started | 03/03/27 | 03/09/27 | 6.2 | 6.2 |
|
241.2 |
RPL09.INT.SSBC.02200 |
RPL09.Interior.SSB-Corridor - Priority - Install Mechanical Piping/ Refrigerant (Highside OH space) | Priority Walls & Overhead | Not Started | 03/03/27 | 03/09/27 | 6.2 | 6.2 |
|
138.8 |
ICM.B9.1865 |
[SSDCB4] Delivery of MDF GS.MDF Module (First Delivery) | Construction | Not Started | 03/04/27 | 03/04/27 | 0.0 | 0.0 |
|
161.2 |
RPL09.INT.ENDC.1040 |
RPL09.Interior.End-Corridor - Priority - Install Fire Sprinkler (Highside OH space) | Early Priority OH MEPF | Not Started | 03/04/27 | 03/08/27 | 3.8 | 3.8 |
|
218.8 |
RPL09.INT.ENDC.1060 |
RPL09.Interior.End-Corridor - Priority - Install Temp Lighting (Show In Model) | Early Priority OH MEPF | Not Started | 03/04/27 | 03/08/27 | 3.8 | 3.8 |
|
218.8 |
RPL09.INT.SSB.06800 |
RPL09.Interior.SSB - Priority - (P1) Hang Drywall (Both Sides) | Priority Wall - P1 | Not Started | 03/04/27 | 03/09/27 | 5.0 | 5.0 |
|
235.0 |
RPL09.INT.SSB.01140 |
RPL09.Interior.SSB - Loading Dock and Storage - Frame Walls | Loading Dock and Storage | Not Started | 03/05/27 | 03/16/27 | 10.0 | 10.0 |
|
208.8 |
RPL09.INT.SSBC.01090 |
RPL09.Interior.SSB-Corridor - OFE - Early Equipment (1x GS.MDF piece 1 of 2) | OFE/MOFE & CFCI | Not Started | 03/05/27 | 03/11/27 | 6.2 | 6.2 |
|
161.2 |
RPL09.SKN.DHCD.01030 |
RPL09.SKIN.DHCD - Install Awning over Doors | Glazing, Doors and Ext Devices | Not Started | 03/05/27 | 03/11/27 | 6.2 | 6.2 |
|
408.8 |
RPL09.STR.DHCD.01210 |
RPL09.Structure.DHCD - Moisture requirements for floor Sealer | F/R/P | Not Started | 03/06/27 | 03/12/27 | 8.8 | 8.8 |
|
226.2 |
RPL09.INT.CTRC.1920 |
RPL09.Interior.Center-Corridor - Priority - Install Drywall at Exterior Walls | Priority Walls & Overhead | Not Started | 03/08/27 | 03/12/27 | 6.2 | 6.2 |
|
118.8 |
RPL09.INT.ENDC.1180 |
RPL09.Interior.End-Corridor - Priority - Install Duct (Highside OH space) | Early Priority OH MEPF | Not Started | 03/08/27 | 03/16/27 | 8.8 | 8.8 |
|
277.5 |
RPL09.INT.DHA.02140 |
RPL09.Interior.DHA - Priority - Install Plumbing | OverHead | Not Started | 03/09/27 | 03/15/27 | 6.2 | 6.2 |
|
111.2 |
RPL09.INT.DHA.02160 |
RPL09.Interior.DHA - Priority - Install Mechanical Piping | OverHead | Not Started | 03/09/27 | 03/30/27 | 18.8 | 18.8 |
|
111.2 |
RPL09.INT.DHB.01100 |
RPL09.Interior.DHB - Priority - Install Temp Doors Frame Hardware | OverHead | Not Started | 03/09/27 | 03/11/27 | 3.8 | 3.8 |
|
125.0 |
RPL09.INT.ENDC.01020 |
RPL09.Interior.End-Corridor - Install Priority OH, Walls, OFE and Fitout - WBS Summary | End Corridor | Not Started | 03/09/27 | 02/03/28 | 283.8 | 283.8 |
|
185.0 |
RPL09.INT.ENDC.03480 |
RPL09.Interior.End-Corr - Priority - WBS Summary | Priority Walls & Overhead | Not Started | 03/09/27 | 04/16/27 | 35.0 | 35.0 |
|
222.5 |
RPL09.INT.ENDC.1020 |
RPL09.Interior.End-Corr - Priority - Install Priority Soffit for Wall Tie-Ins/ Rock & HoW & Draft Blanket | Priority Walls & Overhead | Not Started | 03/09/27 | 03/15/27 | 6.2 | 6.2 |
|
218.8 |
RPL09.INT.CTRC.1100 |
RPL09.Interior.Center-Corridor - Priority - Tape Finish Paint Priority Soffit both sides (Top Out) | Priority Walls & Overhead | Not Started | 03/10/27 | 03/18/27 | 8.8 | 8.8 |
|
118.8 |
RPL09.INT.SSB.01150 |
RPL09.Interior.SSB - BoW - BoW - Framing Balance of Wall | Balance of Walls and OverHead | Not Started | 03/10/27 | 03/16/27 | 6.2 | 6.2 |
|
188.8 |
RPL09.INT.SSB.01160 |
RPL09.Interior.SSB - BoW - Balace Of Wall (ERAD, Maintance, Network infra, Spoke, Bathroom, etc) - WBS Summary | Balance of Walls and OverHead | Not Started | 03/10/27 | 08/31/27 | 152.5 | 152.5 |
|
188.8 |
RPL09.INT.SSB.01880 |
RPL09.Interior.SSB - Final Finishes & Fixtures - Frame/Blocking Walls & Ceilings | Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) | Not Started | 03/10/27 | 03/23/27 | 12.5 | 12.5 |
|
295.0 |
RPL09.INT.SSB.06820 |
RPL09.Interior.SSB - Priority - (P1) Tape Finish Paint (Both Sides) | Priority Wall - P1 | Not Started | 03/10/27 | 03/16/27 | 6.2 | 6.2 |
|
235.0 |
RPL09.INT.SSBC.02180 |
RPL09.Interior.SSB-Corridor - Priority - Install Plumbing (Highside OH space) | Priority Walls & Overhead | Not Started | 03/10/27 | 03/16/27 | 6.2 | 6.2 |
|
138.8 |
RPL09.INT.SSBC.03300 |
RPL09.Interior.SSB-Corridor - Priority - Install FA/ VESDA/ hangers & Heat Trace (Highside OH space) | Priority Walls & Overhead | Not Started | 03/10/27 | 03/16/27 | 6.2 | 6.2 |
|
138.8 |
RPL09.INT.SSBC.03320 |
RPL09.Interior.SSB-Corridor - Priority - Install Fire Safing/ Seal Penetrations through Soffit (Highside OH space) | Priority Walls & Overhead | Not Started | 03/10/27 | 03/12/27 | 3.8 | 3.8 |
|
141.2 |
RPL09.INT.SSBC.03340 |
RPL09.Interior.SSB-Corridor - Priority - Fixed Draft/Smoke Curtain Patching | Priority Walls & Overhead | Not Started | 03/10/27 | 03/12/27 | 3.8 | 3.8 |
|
141.2 |
RPL09.MCUP.LP1.2100 |
RPL09.MCUP.Loop 1 - Install Exterior Signage | Hardscape and Landscape | Not Started | 03/10/27 | 03/23/27 | 12.5 | 12.5 |
|
491.2 |
RPL09.INT.ENDC.6060 |
RPL09.Interior.End-Corr - Priority - Install IMP Exterior Inwall Rough-In | Priority Walls & Overhead | Not Started | 03/11/27 | 03/15/27 | 3.8 | 3.8 |
|
225.0 |
RPL09.CON.WP2.04000 |
RPL09.Conn - GSMDF2 (North) - WBS Summary | GS.MDF2 (North) | Not Started | 03/12/27 | 07/23/27 | 116.2 | 116.2 |
|
322.5 |
RPL09.CON.WP2.07880 |
RPL09.Conn - GSMDF2 (North) Set Infrastructure (Wall mounting enclosures, Tier1 Basket Tray, Waterfalls etc.) | Infrastructure | Not Started | 03/12/27 | 03/16/27 | 3.8 | 3.8 |
|
312.5 |
RPL09.INT.DHB.01120 |
RPL09.Interior.DHB - Priority - Install Security | OverHead | Not Started | 03/12/27 | 03/18/27 | 6.2 | 6.2 |
|
125.0 |
RPL09.INT.SSBC.01140 |
RPL09.Interior.SSB-Corridor - OFE - Early Equipment (1x GS.MDF piece 2 of 2) | OFE/MOFE & CFCI | Not Started | 03/12/27 | 03/18/27 | 6.2 | 6.2 |
|
161.2 |
RPL09.INT.SSBC.3000 |
RPL09.Interior.SSBC LO #06 - Close Interior Leave Out #06 SSB/SSBC (For MDF2) WBS Summary | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 03/12/27 | 05/26/27 | 66.2 | 66.2 |
|
187.5 |
RPL09.INT.SSBC.3020 |
RPL09.Interior.SSBC LO #06 - Install Framing at LO | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 03/12/27 | 03/18/27 | 6.2 | 6.2 |
|
187.5 |
RPL09.MCUP.LP2.1760 |
RPL09.MCUP.Loop 2 - Install Lighting | Hardscape and Landscape | Not Started | 03/12/27 | 03/18/27 | 6.2 | 6.2 |
|
470.0 |
RPL09.SKN.DHCD.01040 |
RPL09.SKIN.DHCD - Install Louvers | Glazing, Doors and Ext Devices | Not Started | 03/12/27 | 03/18/27 | 6.2 | 6.2 |
|
408.8 |
RPL09.SKN.DHCD.01100 |
RPL09.SKIN.DHCD - Install Scupper and Downspouts | Glazing, Doors and Ext Devices | Not Started | 03/12/27 | 03/18/27 | 6.2 | 6.2 |
|
420.0 |
RPL09.STR.DHCD.01230 |
RPL09.Structure.DHCD - Install SOG Sealer and Cure | F/R/P | Not Started | 03/13/27 | 03/14/27 | 2.5 | 2.5 |
|
257.5 |
RPL09.EY.SSB.01175 |
RPL09.EY.SSB - Install Mechanical/refrigerantTie-ins | Tie-ins | Not Started | 03/15/27 | 03/29/27 | 12.5 | 12.5 |
|
136.2 |
RPL09.INT.DHD.01000 |
RPL09.Interior.DHD - Priority OH - WBS Summary | OverHead | Not Started | 03/15/27 | 05/04/27 | 45.0 | 45.0 |
|
407.5 |
RPL09.INT.DHD.01020 |
RPL09.Interior.DHD - Install Priority OH, Walls, OFE and Tie-ins - WBS Summary | DHD | Not Started | 03/15/27 | 11/03/27 | 205.0 | 205.0 |
|
247.5 |