Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL09 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:12 PM · 5201 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
0
Completed
0
In Progress
0
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL09.INT.DHA.02400 RPL09.Interior.DHA - Priority - IMP Exterior Inwall Rough-In OverHead Not Started 02/19/27 02/25/27 6.2 6.2
0%
111.2
RPL09.INT.DHB.02140 RPL09.Interior.DHB - Priority - Install Unistruts & Hangers (All Trades) OverHead Not Started 02/19/27 02/25/27 6.2 6.2
0%
98.8
RPL09.INT.DHB.02340 RPL09.Interior.DHB - Priority - Install IMP Exterior Inwall Rough-In (These walls available early) OverHead Not Started 02/19/27 02/25/27 6.2 6.2
0%
98.8
RPL09.INT.SSB.01050 RPL09.Interior.SSB - Priority - (P1) Frame Walls (Frame full height Walls) Priority Wall - P1 Not Started 02/19/27 02/25/27 6.2 6.2
0%
198.8
RPL09.INT.SSB.06840 RPL09.Interior.SSB - Priority - (P1) Frame Reamining Walls Priority Wall - P1 Not Started 02/19/27 02/23/27 3.8 3.8
0%
241.2
RPL09.INT.SSBC.06700 RPL09.Interior.SSBC - Priority GL9.04 - (P0) Tape Finish Paint (Both SIdes) Priority Wall Grid Line 9-04 Not Started 02/19/27 02/25/27 6.2 6.2
0%
155.0
RPL09.STR.DHAB.01260 RPL09.Structure.DHAB - Install SOG Sealer and Cure F/R/P Not Started 02/19/27 02/20/27 2.5 2.5
0%
171.2
RPL09.WA.OFE.01000 RPL09.WA - Weather Allowance - FDN to OFE Weather Allowance Not Started 02/20/27 03/07/27 20.0 20.0
0%
152.5
RPL09.EY.SSB.01160 RPL09.EY.SSB - Install Electrical Tie-ins (include penetration detail) Tie-ins Not Started 02/22/27 03/19/27 25.0 25.0
0%
142.5
RPL09.EY.SSB.01170 RPL09.EY.SSB - Install Mechanical Main (include penetration detail) Tie-ins Not Started 02/22/27 03/12/27 18.8 18.8
0%
136.2
RPL09.INT.CTRC.01020 RPL09.Interior.Center-Corridor - Install Priority OH, Walls, OFE and Fitout - WBS Summary Center Corridor Not Started 02/22/27 10/27/27 217.5 217.5
0%
133.8
RPL09.INT.CTRC.03460 RPL09.Interior.Center-Corridor - Priority - Priority - WBS Summary Priority Walls & Overhead Not Started 02/22/27 05/06/27 66.2 66.2
0%
185.0
RPL09.INT.CTRC.1020 RPL09.Interior.Center-Corridor - Priority - Install Priority Soffit for Wall Tie-Ins/ Rock & HoW & Draft Blanket Priority Walls & Overhead Not Started 02/22/27 02/26/27 6.2 6.2
0%
118.8
RPL09.INT.CTRC.7740 RPL09.Interior.Center-Corridor - Priority - Install IMP Exterior Inwall Rough-In Priority Walls & Overhead Not Started 02/22/27 02/26/27 6.2 6.2
0%
125.0
RPL09.STR.DHCD.01140 RPL09.Structure.DHCD - SOG F/R/P #8 - Grid lines 6-25/6-28 F/R/P Not Started 02/22/27 02/26/27 6.2 6.2
0%
157.5
GCD.RPL09.3985 MCUP Ready for Energization - (MCUPs Loop 2) mCup Not Started 02/23/27 02/23/27 0.0 0.0
0%
458.8
RPL09.CX.MCUP.01020 RPL09.CX.mCup Loop 2 - L3, L4, IST - WBS Summary mCUP 5-6 Not Started 02/23/27 10/05/27 196.2 196.2
0%
321.2
RPL09.CX.MCUP.01100 RPL09.CX.mCup Loop 2 - L3/L4 - mCUP - Flush and Fill - mCup Yard - Loop 2 (mCUPs 5-6) (Phase 3) Fill and Flush Not Started 02/23/27 03/01/27 6.2 6.2
0%
356.2
RPL09.EY.DHC.01120 RPL09.EY.DHC - Install BMS UG Underground Not Started 02/23/27 03/08/27 12.5 12.5
0%
308.8
RPL09.EY.ENDC.01050 RPL09.EY.End - Install SD, DW, FW UG Underground Not Started 02/23/27 03/08/27 12.5 12.5
0%
363.8
RPL09.EY.ENDC.1510 RPL09.EY.DHD.T1 - Temp Conditioning Startup and Available Tent 1 Not Started 02/23/27 02/24/27 2.5 2.5
0%
138.8
RPL09.EY.ENDC.1810 RPL09.EY.DHD.T2 - Temp Conditioning Startup and Available Tent 2 Not Started 02/23/27 02/24/27 2.5 2.5
0%
141.2
RPL09.MCUP.LP2.1520 RPL09.MCUP.Loop 2 - Install Hardscape and Landscape - WBS Summary Hardscape and Landscape Not Started 02/23/27 04/16/27 47.5 47.5
0%
470.0
RPL09.MCUP.LP2.1540 RPL09.MCUP.Loop 2 - Install Sleeves MEPL Hardscape and Landscape Not Started 02/23/27 02/25/27 3.8 3.8
0%
470.0
RPL09.EY.SSB.01240 RPL09.EY.SSB - Install BMS/EPMS Tie-ins Tie-ins Not Started 02/24/27 03/16/27 18.8 18.8
0%
146.2
RPL09.INT.DHA.03440 RPL09.Interior.DHA - Priority - Install Backing at Exterior Wall OverHead Not Started 02/24/27 02/25/27 2.5 2.5
0%
111.2
RPL09.INT.DHB.02380 RPL09.Interior.DHB - Priority - Install Backing at Exterior Wall OverHead Not Started 02/24/27 02/25/27 2.5 2.5
0%
98.8
RPL09.INT.SSB.01660 RPL09.Interior.SSB - Priority - Install Plumbing (Highside OH space) Priority Walls and OverHead Not Started 02/24/27 03/02/27 6.2 6.2
0%
145.0
RPL09.INT.SSB.01680 RPL09.Interior.SSB - Priority - Install Mechanical Piping/ Refrigerant (Highside OH space) Priority Walls and OverHead Not Started 02/24/27 03/02/27 6.2 6.2
0%
138.8
RPL09.INT.SSB.03200 RPL09.Interior.SSB - Priority - Install Fire Alarm hangers & members (Highside OH space) Priority Walls and OverHead Not Started 02/24/27 03/02/27 6.2 6.2
0%
333.8
RPL09.INT.SSB.06880 RPL09.Interior.SSB - Priority - (P1) Install Reamining MEP In-Wall/Backing Priority Wall - P1 Not Started 02/24/27 02/26/27 3.8 3.8
0%
241.2
RPL09.MCUP.LP1.2040 RPL09.MCUP.Loop 1 - Install Mcup Paving Hardscape and Landscape Not Started 02/24/27 03/09/27 12.5 12.5
0%
491.2
RPL09.SKN.DHCD.01000 RPL09.SKIN.DHCD - Install Temp Doors Glazing, Doors and Ext Devices Not Started 02/24/27 02/25/27 2.5 2.5
0%
408.8
RPL09.SKN.DHCD.01020 RPL09.SKIN.DHCD - Install Windows, Doors, Louvers and Ext Devices - WBS Summary Glazing, Doors and Ext Devices Not Started 02/24/27 11/01/27 218.8 218.8
0%
222.5
RPL09.CX.MCUP.01230 RPL09.CX.mCup Loop 1 - L3/L4 - mCUP - Flush and Fill - mCup3 and Dry Coolers Fill and Flush Not Started 02/25/27 03/04/27 7.5 7.5
0%
213.8
RPL09.CX.MCUP.01250 RPL09.CX.mCup Loop 1 - L3/L4 - mCUP - Flush and Fill - mCup4 and Dry Coolers Fill and Flush Not Started 02/25/27 03/04/27 7.5 7.5
0%
216.2
RPL09.INT.DHC.01030 RPL09.Interior.DHC - Priority - Install Fire Sprinkler Early Priority OH MEPF Not Started 02/25/27 03/03/27 6.2 6.2
0%
218.8
GCD.RPL09.1280 Interior fit-out Start RPL09 - DHA&B Construction Milestones Not Started 02/26/27 02/26/27 0.0 0.0
0%
363.8
RPL09.INT.DHA.02380 RPL09.Interior.DHA - Priority - Install Drywall at Exterior Walls OverHead Not Started 02/26/27 03/08/27 8.8 8.8
0%
111.2
RPL09.INT.DHB.02320 RPL09.Interior.DHB - Priority - Install Drywall at Exterior Walls OverHead Not Started 02/26/27 03/08/27 8.8 8.8
0%
98.8
RPL09.INT.SSB.01170 RPL09.Interior.SSB - Loading Dock and Storage - WBS Summary Loading Dock and Storage Not Started 02/26/27 08/09/27 142.5 142.5
0%
208.8
RPL09.INT.SSB.02900 RPL09.Interior.SSB - Loading Dock and Storage - Pre Priority OH & Walls Tasks (Unistruts,Hangers,Track) Loading Dock and Storage Not Started 02/26/27 03/04/27 6.2 6.2
0%
208.8
RPL09.INT.SSB.06780 RPL09.Interior.SSB - Priority - (P1) Install MEP In-Wall/Backing Priority Wall - P1 Not Started 02/26/27 03/03/27 5.0 5.0
0%
235.0
RPL09.MCUP.LP2.1640 RPL09.MCUP.Loop 2 - Install Early Mcup Paving Hardscape and Landscape Not Started 02/26/27 03/11/27 12.5 12.5
0%
470.0
RPL09.SKN.DHCD.01140 RPL09.SKIN.DHCD - Install Blocking of Canopy & Backing of Exterior Wall Glazing, Doors and Ext Devices Not Started 02/26/27 03/04/27 6.2 6.2
0%
408.8
RPL09.STR.DHCD.01150 RPL09.Structure.DHCD - Zone SOG Cure F/R/P Not Started 02/27/27 03/05/27 8.8 8.8
0%
226.2
ICM.B9.1840 [SSDCB4] Delivery of DES - Data Hall Electrical Room Skid (First Delivery) Construction Not Started 03/01/27 03/01/27 0.0 0.0
0%
165.0
ICM.B9.1855 [SSDCB4] Delivery of MES - Multi Trade Rack (First Delivery) Construction Not Started 03/01/27 03/01/27 0.0 0.0
0%
152.5
RPL09.INT.CTRC.1000 RPL09.Interior.Center-Corridor - Priority - Install Unistruts & Hangers (All Trades) Both side of Corridor Wall Priority Walls & Overhead Not Started 03/01/27 03/05/27 6.2 6.2
0%
118.8
RPL09.INT.DHC.01040 RPL09.Interior.DHC - Priority - Install Temp Lighting Early Priority OH MEPF Not Started 03/01/27 03/03/27 3.8 3.8
0%
218.8
RPL09.INT.SSB.06860 RPL09.Interior.SSB - Priority - (P1) Reamining Wall Hang Drywall (Both Sides) Priority Wall - P1 Not Started 03/01/27 03/02/27 2.5 2.5
0%
241.2
RPL09.INT.DHB.01050 RPL09.Interior.DHB - Priority - Install FA / Linear heat detection OverHead Not Started 03/02/27 03/08/27 6.2 6.2
0%
105.0
RPL09.INT.DHB.02300 RPL09.Interior.DHB - Priority - Install Electrical OverHead Not Started 03/02/27 03/22/27 18.8 18.8
0%
98.8
RPL09.INT.DHC.01010 RPL09.Interior.DHC - Priority - Install Duct Early Priority OH MEPF Not Started 03/02/27 03/05/27 5.0 5.0
0%
277.5
RPL09.INT.DHD.01010 RPL09.Interior.DHD - Priority - Install Duct Early Priority OH MEPF Not Started 03/02/27 03/08/27 5.0 5.0
0%
277.5
RPL09.INT.SSBC.01060 RPL09.Interior.SSB-Corridor - OFE - Early Equipment (1x SSB Elect) OFE/MOFE & CFCI Not Started 03/02/27 03/15/27 12.5 12.5
0%
165.0
RPL09.CON.WP2.08560 RPL09.Conn - Ext. GSIDF9X04 - Install Copper, WAPs, Security Camera & Access Control (EY-DH C) Cabling Not Started 03/03/27 03/18/27 15.0 15.0
0%
336.2
RPL09.INT.SSB.03220 RPL09.Interior.SSB - Priority - Install Fire Safing/ Seal all Penetrations through Soffit (Highside OH space) Priority Walls and OverHead Not Started 03/03/27 03/09/27 6.2 6.2
0%
188.8
RPL09.INT.SSB.06900 RPL09.Interior.SSB - Priority - (P1) Reamining Wall Tape Finish Paint (Both Sides) Priority Wall - P1 Not Started 03/03/27 03/09/27 6.2 6.2
0%
241.2
RPL09.INT.SSBC.02200 RPL09.Interior.SSB-Corridor - Priority - Install Mechanical Piping/ Refrigerant (Highside OH space) Priority Walls & Overhead Not Started 03/03/27 03/09/27 6.2 6.2
0%
138.8
ICM.B9.1865 [SSDCB4] Delivery of MDF GS.MDF Module (First Delivery) Construction Not Started 03/04/27 03/04/27 0.0 0.0
0%
161.2
RPL09.INT.ENDC.1040 RPL09.Interior.End-Corridor - Priority - Install Fire Sprinkler (Highside OH space) Early Priority OH MEPF Not Started 03/04/27 03/08/27 3.8 3.8
0%
218.8
RPL09.INT.ENDC.1060 RPL09.Interior.End-Corridor - Priority - Install Temp Lighting (Show In Model) Early Priority OH MEPF Not Started 03/04/27 03/08/27 3.8 3.8
0%
218.8
RPL09.INT.SSB.06800 RPL09.Interior.SSB - Priority - (P1) Hang Drywall (Both Sides) Priority Wall - P1 Not Started 03/04/27 03/09/27 5.0 5.0
0%
235.0
RPL09.INT.SSB.01140 RPL09.Interior.SSB - Loading Dock and Storage - Frame Walls Loading Dock and Storage Not Started 03/05/27 03/16/27 10.0 10.0
0%
208.8
RPL09.INT.SSBC.01090 RPL09.Interior.SSB-Corridor - OFE - Early Equipment (1x GS.MDF piece 1 of 2) OFE/MOFE & CFCI Not Started 03/05/27 03/11/27 6.2 6.2
0%
161.2
RPL09.SKN.DHCD.01030 RPL09.SKIN.DHCD - Install Awning over Doors Glazing, Doors and Ext Devices Not Started 03/05/27 03/11/27 6.2 6.2
0%
408.8
RPL09.STR.DHCD.01210 RPL09.Structure.DHCD - Moisture requirements for floor Sealer F/R/P Not Started 03/06/27 03/12/27 8.8 8.8
0%
226.2
RPL09.INT.CTRC.1920 RPL09.Interior.Center-Corridor - Priority - Install Drywall at Exterior Walls Priority Walls & Overhead Not Started 03/08/27 03/12/27 6.2 6.2
0%
118.8
RPL09.INT.ENDC.1180 RPL09.Interior.End-Corridor - Priority - Install Duct (Highside OH space) Early Priority OH MEPF Not Started 03/08/27 03/16/27 8.8 8.8
0%
277.5
RPL09.INT.DHA.02140 RPL09.Interior.DHA - Priority - Install Plumbing OverHead Not Started 03/09/27 03/15/27 6.2 6.2
0%
111.2
RPL09.INT.DHA.02160 RPL09.Interior.DHA - Priority - Install Mechanical Piping OverHead Not Started 03/09/27 03/30/27 18.8 18.8
0%
111.2
RPL09.INT.DHB.01100 RPL09.Interior.DHB - Priority - Install Temp Doors Frame Hardware OverHead Not Started 03/09/27 03/11/27 3.8 3.8
0%
125.0
RPL09.INT.ENDC.01020 RPL09.Interior.End-Corridor - Install Priority OH, Walls, OFE and Fitout - WBS Summary End Corridor Not Started 03/09/27 02/03/28 283.8 283.8
0%
185.0
RPL09.INT.ENDC.03480 RPL09.Interior.End-Corr - Priority - WBS Summary Priority Walls & Overhead Not Started 03/09/27 04/16/27 35.0 35.0
0%
222.5
RPL09.INT.ENDC.1020 RPL09.Interior.End-Corr - Priority - Install Priority Soffit for Wall Tie-Ins/ Rock & HoW & Draft Blanket Priority Walls & Overhead Not Started 03/09/27 03/15/27 6.2 6.2
0%
218.8
RPL09.INT.CTRC.1100 RPL09.Interior.Center-Corridor - Priority - Tape Finish Paint Priority Soffit both sides (Top Out) Priority Walls & Overhead Not Started 03/10/27 03/18/27 8.8 8.8
0%
118.8
RPL09.INT.SSB.01150 RPL09.Interior.SSB - BoW - BoW - Framing Balance of Wall Balance of Walls and OverHead Not Started 03/10/27 03/16/27 6.2 6.2
0%
188.8
RPL09.INT.SSB.01160 RPL09.Interior.SSB - BoW - Balace Of Wall (ERAD, Maintance, Network infra, Spoke, Bathroom, etc) - WBS Summary Balance of Walls and OverHead Not Started 03/10/27 08/31/27 152.5 152.5
0%
188.8
RPL09.INT.SSB.01880 RPL09.Interior.SSB - Final Finishes & Fixtures - Frame/Blocking Walls & Ceilings Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) Not Started 03/10/27 03/23/27 12.5 12.5
0%
295.0
RPL09.INT.SSB.06820 RPL09.Interior.SSB - Priority - (P1) Tape Finish Paint (Both Sides) Priority Wall - P1 Not Started 03/10/27 03/16/27 6.2 6.2
0%
235.0
RPL09.INT.SSBC.02180 RPL09.Interior.SSB-Corridor - Priority - Install Plumbing (Highside OH space) Priority Walls & Overhead Not Started 03/10/27 03/16/27 6.2 6.2
0%
138.8
RPL09.INT.SSBC.03300 RPL09.Interior.SSB-Corridor - Priority - Install FA/ VESDA/ hangers & Heat Trace (Highside OH space) Priority Walls & Overhead Not Started 03/10/27 03/16/27 6.2 6.2
0%
138.8
RPL09.INT.SSBC.03320 RPL09.Interior.SSB-Corridor - Priority - Install Fire Safing/ Seal Penetrations through Soffit (Highside OH space) Priority Walls & Overhead Not Started 03/10/27 03/12/27 3.8 3.8
0%
141.2
RPL09.INT.SSBC.03340 RPL09.Interior.SSB-Corridor - Priority - Fixed Draft/Smoke Curtain Patching Priority Walls & Overhead Not Started 03/10/27 03/12/27 3.8 3.8
0%
141.2
RPL09.MCUP.LP1.2100 RPL09.MCUP.Loop 1 - Install Exterior Signage Hardscape and Landscape Not Started 03/10/27 03/23/27 12.5 12.5
0%
491.2
RPL09.INT.ENDC.6060 RPL09.Interior.End-Corr - Priority - Install IMP Exterior Inwall Rough-In Priority Walls & Overhead Not Started 03/11/27 03/15/27 3.8 3.8
0%
225.0
RPL09.CON.WP2.04000 RPL09.Conn - GSMDF2 (North) - WBS Summary GS.MDF2 (North) Not Started 03/12/27 07/23/27 116.2 116.2
0%
322.5
RPL09.CON.WP2.07880 RPL09.Conn - GSMDF2 (North) Set Infrastructure (Wall mounting enclosures, Tier1 Basket Tray, Waterfalls etc.) Infrastructure Not Started 03/12/27 03/16/27 3.8 3.8
0%
312.5
RPL09.INT.DHB.01120 RPL09.Interior.DHB - Priority - Install Security OverHead Not Started 03/12/27 03/18/27 6.2 6.2
0%
125.0
RPL09.INT.SSBC.01140 RPL09.Interior.SSB-Corridor - OFE - Early Equipment (1x GS.MDF piece 2 of 2) OFE/MOFE & CFCI Not Started 03/12/27 03/18/27 6.2 6.2
0%
161.2
RPL09.INT.SSBC.3000 RPL09.Interior.SSBC LO #06 - Close Interior Leave Out #06 SSB/SSBC (For MDF2) WBS Summary Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 03/12/27 05/26/27 66.2 66.2
0%
187.5
RPL09.INT.SSBC.3020 RPL09.Interior.SSBC LO #06 - Install Framing at LO Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 03/12/27 03/18/27 6.2 6.2
0%
187.5
RPL09.MCUP.LP2.1760 RPL09.MCUP.Loop 2 - Install Lighting Hardscape and Landscape Not Started 03/12/27 03/18/27 6.2 6.2
0%
470.0
RPL09.SKN.DHCD.01040 RPL09.SKIN.DHCD - Install Louvers Glazing, Doors and Ext Devices Not Started 03/12/27 03/18/27 6.2 6.2
0%
408.8
RPL09.SKN.DHCD.01100 RPL09.SKIN.DHCD - Install Scupper and Downspouts Glazing, Doors and Ext Devices Not Started 03/12/27 03/18/27 6.2 6.2
0%
420.0
RPL09.STR.DHCD.01230 RPL09.Structure.DHCD - Install SOG Sealer and Cure F/R/P Not Started 03/13/27 03/14/27 2.5 2.5
0%
257.5
RPL09.EY.SSB.01175 RPL09.EY.SSB - Install Mechanical/refrigerantTie-ins Tie-ins Not Started 03/15/27 03/29/27 12.5 12.5
0%
136.2
RPL09.INT.DHD.01000 RPL09.Interior.DHD - Priority OH - WBS Summary OverHead Not Started 03/15/27 05/04/27 45.0 45.0
0%
407.5
RPL09.INT.DHD.01020 RPL09.Interior.DHD - Install Priority OH, Walls, OFE and Tie-ins - WBS Summary DHD Not Started 03/15/27 11/03/27 205.0 205.0
0%
247.5