Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL09 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:12 PM
· 5201 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
0
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL09.INT.DHD.01980 |
RPL09.Interior.DHD - Priority - Install Unistruts & Hangers (All Trades) Both side of Corridor Wall | OverHead | Not Started | 03/15/27 | 03/19/27 | 6.2 | 6.2 |
|
156.2 |
RPL09.INT.DHD.02250 |
RPL09.Interior.DHD - Priority - Install IMP Exterior Inwall Rough-In | OverHead | Not Started | 03/15/27 | 03/19/27 | 6.2 | 6.2 |
|
156.2 |
ICM.B9.1845 |
[SSDCB4] Delivery of FSHAC - Hot Aisle Containment (First Delivery) | Construction | Not Started | 03/16/27 | 03/16/27 | 0.0 | 0.0 |
|
132.5 |
RPL09.INT.ENDC.1000 |
RPL09.Interior.End-Corr - Priority - Install Unistruts & Hangers (All Trades) Both side of Corridor Wall | Priority Walls & Overhead | Not Started | 03/16/27 | 03/22/27 | 6.2 | 6.2 |
|
218.8 |
RPL09.INT.SSB.14000 |
RPL09.Interior.Center-Corridor Leave Out #01 #02 #03 #04 #5 - SSB (for Elec. Room) WBS Summary | Interior Leave Out Wall #01, #02, #03, #04, #05 SSB for Electrical Room | Not Started | 03/16/27 | 07/27/27 | 116.2 | 116.2 |
|
168.8 |
RPL09.INT.SSB.14020 |
RPL09.Interior.SSB LO #01 to #05 - Install LO Framing | OH & Framing | Not Started | 03/16/27 | 03/22/27 | 6.2 | 6.2 |
|
168.8 |
RPL09.CON.WP2.09240 |
RPL09.Conn - GSMDF2 (North) - Install Copper, WAPs, Security Camera & Access Control | ISP (MDF RPL09 <> MDF RPL09) | Not Started | 03/17/27 | 04/02/27 | 15.0 | 15.0 |
|
312.5 |
RPL09.EY.SSB.01250 |
RPL09.EY.SSB - Install Sleeves MEPL | Hardscape and Landscape | Not Started | 03/17/27 | 03/23/27 | 6.2 | 6.2 |
|
266.2 |
RPL09.EY.SSB.01270 |
RPL09.EY.SSB - Hardscape and Landscape - WBS Summary | Hardscape and Landscape | Not Started | 03/17/27 | 11/15/27 | 211.2 | 211.2 |
|
286.2 |
RPL09.INT.SBC.03240 |
RPL09.Interior.SSB-Corridor - Frame Balance of Wall | Balance of Walls & Overhead | Not Started | 03/17/27 | 03/23/27 | 6.2 | 6.2 |
|
138.8 |
RPL09.INT.SBC.03260 |
RPL09.Interior.SSB-Corridor - Balace Of Wall (ERAD, Maintance, Network infra, Spoke, Bathroom, etc) - WBS Summary | Balance of Walls & Overhead | Not Started | 03/17/27 | 09/01/27 | 147.5 | 147.5 |
|
138.8 |
RPL09.INT.SSB.01180 |
RPL09.Interior.SSB - BoW - Install Door Frames | Balance of Walls and OverHead | Not Started | 03/17/27 | 03/23/27 | 6.2 | 6.2 |
|
210.0 |
RPL09.INT.SSB.01200 |
RPL09.Interior.SSB - Priority - Install Store Front Frames & Glass (Testing if Required) | Balance of Walls and OverHead | Not Started | 03/17/27 | 04/07/27 | 18.8 | 18.8 |
|
246.2 |
RPL09.INT.SSB.01210 |
RPL09.Interior.SSB - BoW - Install Electrical Lowside OH and In-wall | Balance of Walls and OverHead | Not Started | 03/17/27 | 03/31/27 | 12.5 | 12.5 |
|
188.8 |
RPL09.INT.SSB.02920 |
RPL09.Interior.SSB - Loading Dock and Storage - Install Headers and Top Out and Fire/Caulking | Loading Dock and Storage | Not Started | 03/17/27 | 03/31/27 | 12.5 | 12.5 |
|
208.8 |
RPL09.CON.WP2.09200 |
RPL09.Conn - CorpNet & FacNet Available (South EY) - All IDFs | WP#02 GS | Not Started | 03/18/27 | 03/18/27 | 0.0 | 0.0 |
|
495.0 |
RPL09.Conn.MS.01100 |
RPL09.Conn Wifi Ready - South EY (Pred from RPL10 CorpNet needed?) | Connectivity Milestones | Not Started | 03/18/27 | 03/18/27 | 0.0 | 0.0 |
|
336.2 |
RPL09.CON.WP2.05000 |
RPL09.Conn - GSMDF1 (South) - WBS Summary | GS.MDF1 (South) | Not Started | 03/19/27 | 03/21/28 | 313.8 | 313.8 |
|
118.8 |
RPL09.CON.WP2.07960 |
RPL09.Conn - GSMDF1 (South) Set Infrastructure (Wall mounting enclosures, Tier1 Basket Tray, Waterfalls etc.) | Infrastructure | Not Started | 03/19/27 | 03/23/27 | 3.8 | 3.8 |
|
317.5 |
RPL09.CON.WP4.00010 |
RPL09.Conn - Network - WBS Summary | WP#4 Network | Not Started | 03/19/27 | 02/17/28 | 286.2 | 286.2 |
|
208.8 |
RPL09.INT.CTRC.1160 |
RPL09.Interior.Center-Corr - Priority GL9.16/9.17 - (P2) Frame Walls (Incl. Entry Fiber Rooms #3.7, Ancillary Room #3.6) | Priority Wall Grid Line 9-16 / 9-17 | Not Started | 03/19/27 | 03/30/27 | 8.8 | 8.8 |
|
118.8 |
RPL09.INT.DHB.01130 |
RPL09.Interior.DHB - Priority - Install Controls / EPMS / BMS | OverHead | Not Started | 03/19/27 | 03/24/27 | 5.0 | 5.0 |
|
125.0 |
RPL09.INT.SSBC.3080 |
RPL09.Interior.SSBC LO #06 - Install Mechanical Piping Lowside OH and in-wall | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 03/19/27 | 03/22/27 | 2.5 | 2.5 |
|
187.5 |
RPL09.INT.SSBC.4000 |
RPL09.Interior.SSBC LO #07 - Close Interior LO #07 SSB/SSBC (For MDF1) WBS Summary | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 03/19/27 | 06/03/27 | 66.2 | 66.2 |
|
181.2 |
RPL09.INT.SSBC.4020 |
RPL09.Interior.SSBC LO #07 - Install Framing at LO | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 03/19/27 | 03/25/27 | 6.2 | 6.2 |
|
181.2 |
RPL09.MCUP.LP2.1860 |
RPL09.MCUP.Loop 2 - Install Mcup Paving | Hardscape and Landscape | Not Started | 03/19/27 | 04/02/27 | 12.5 | 12.5 |
|
470.0 |
RPL09.SKN.DHCD.01050 |
RPL09.SKIN.DHCD - Install Lighting | Glazing, Doors and Ext Devices | Not Started | 03/19/27 | 03/24/27 | 5.0 | 5.0 |
|
408.8 |
RPL09.SKN.W.LO.01120 |
RPL09.SKIN.LO#16 - Close Exterior Leave Out #16 SSB (North of Loading Dock) WBS Summary | Build back Exterior Leave Out Walls #16 (SSB - North of Loading Dock) | Not Started | 03/19/27 | 05/04/27 | 40.0 | 40.0 |
|
161.2 |
RPL09.SKN.W.LO.01380 |
RPL09.SKIN.LO#16 - Pour back Stemwall | Build back Exterior Leave Out Walls #16 (SSB - North of Loading Dock) | Not Started | 03/19/27 | 03/25/27 | 6.2 | 6.2 |
|
161.2 |
RPL09.WP4.010000 |
RPL09.Conn GSMDF1 Pull Fanout (5F) [PON (Active, In-Row)] | GSMDF1 | Not Started | 03/19/27 | 03/19/27 | 1.2 | 1.2 |
|
293.8 |
RPL09.INT.DHD.02230 |
RPL09.Interior.DHD - Priority - Install Drywall at Exterior Walls | OverHead | Not Started | 03/22/27 | 03/29/27 | 6.2 | 6.2 |
|
156.2 |
RPL09.WP4.010020 |
RPL09.Conn GSMDF2 Pull Fanout (5F) [PON (Active, In-Row)] | GSMDF2 | Not Started | 03/22/27 | 03/22/27 | 1.2 | 1.2 |
|
293.8 |
RPL09.WP4.010040 |
RPL09.Conn GSMDF1 Install Fanout (5F) [PON (Active, In-Row)] | GSMDF1 | Not Started | 03/22/27 | 04/06/27 | 13.8 | 13.8 |
|
295.0 |
RPL09.INT.DHA.01050 |
RPL09.Interior.DHA - Priority - Install FA / Linear heat detection | OverHead | Not Started | 03/23/27 | 03/30/27 | 6.2 | 6.2 |
|
98.8 |
RPL09.INT.DHA.02320 |
RPL09.Interior.DHA - Priority - Install Electrical | OverHead | Not Started | 03/23/27 | 04/13/27 | 18.8 | 18.8 |
|
98.8 |
RPL09.INT.ENDC.01120 |
RPL09.Interior.End-Corridor - Frame Remaining Walls | Fit out | Not Started | 03/23/27 | 03/29/27 | 5.0 | 5.0 |
|
256.2 |
RPL09.INT.ENDC.01130 |
RPL09.Interior.End-Corridor - Install Fitout (Restroom, Janitor, Fire Riser, Humidifier) - WBS Summary | Fit out | Not Started | 03/23/27 | 01/24/28 | 261.2 | 261.2 |
|
195.0 |
RPL09.INT.ENDC.1920 |
RPL09.Interior.End-Corr - Priority - Install Drywall at Exterior Walls | Priority Walls & Overhead | Not Started | 03/23/27 | 03/30/27 | 6.2 | 6.2 |
|
218.8 |
RPL09.INT.SSB.14060 |
RPL09.Interior.SSB LO #01 to #05 - Install In-Wall Rough-in | OH & Framing | Not Started | 03/23/27 | 03/24/27 | 2.5 | 2.5 |
|
168.8 |
RPL09.INT.SSBC.3100 |
RPL09.Interior.SSBC LO #06 - Install Fire Life Safety Lowside OH and In-wall | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 03/23/27 | 03/24/27 | 2.5 | 2.5 |
|
191.2 |
RPL09.INT.SSBC.3120 |
RPL09.Interior.SSBC LO #06 - Install Plumbing Lowside OH and In-wall | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 03/23/27 | 03/24/27 | 2.5 | 2.5 |
|
187.5 |
RPL09.WP4.010060 |
RPL09.Conn GSMDF2 Install Fanout (5F) [PON (Active, In-Row)] | GSMDF2 | Not Started | 03/23/27 | 04/07/27 | 13.8 | 13.8 |
|
293.8 |
RPL09.CON.WP2.07900 |
RPL09.Conn -MDF1<>MDF2 Install Cabling (Pull, Splice & Terminate) | ISP (MDF RPL09 <> MDF RPL09) | Not Started | 03/24/27 | 03/30/27 | 5.0 | 5.0 |
|
415.0 |
RPL09.CON.WP2.07980 |
RPL09.Conn - MDF1<>MDF2 Install Cabling (Pull, Splice & Terminate) | ISP (MDF RPL09 <> MDF RPL09) | Not Started | 03/24/27 | 03/30/27 | 5.0 | 5.0 |
|
415.0 |
RPL09.CON.WP2.09260 |
RPL09.Conn - GSMDF1 (South) - Install Copper, WAPs, Security Camera & Access Control | ISP (MDF RPL09 <> MDF RPL09) | Not Started | 03/24/27 | 04/09/27 | 15.0 | 15.0 |
|
317.5 |
RPL09.EY.SSB.01290 |
RPL09.EY.SSB - Install Trash Enclosure (CMU) | Hardscape and Landscape | Not Started | 03/24/27 | 04/21/27 | 25.0 | 25.0 |
|
291.2 |
RPL09.INT.SBC.03420 |
RPL09.Interior.SSB-Corridor - BoW - Install Door Frames | Balance of Walls & Overhead | Not Started | 03/24/27 | 03/31/27 | 6.2 | 6.2 |
|
163.8 |
RPL09.INT.SBC.05800 |
RPL09.Interior.SSB-Corridor - BoW - Install Mechanical Piping/ Refrigerant Lowside OH and in-wall | Balance of Walls & Overhead | Not Started | 03/24/27 | 04/05/27 | 10.0 | 10.0 |
|
138.8 |
RPL09.INT.SSB.02860 |
RPL09.Interior.SSB - Final Finishes & Fixtures - MEP Rough-In | Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) | Not Started | 03/24/27 | 03/31/27 | 6.2 | 6.2 |
|
295.0 |
RPL09.INT.SSB.14080 |
RPL09.Interior.SSB LO #01 to #05 - Install Mechanical Piping & Refrigerant Lowside OH and in-wall | OH & Framing | Not Started | 03/25/27 | 03/30/27 | 3.8 | 3.8 |
|
168.8 |
RPL09.INT.SSBC.3140 |
RPL09.Interior.SSBC LO #06 - Install Security Lowside OH and In-wall | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 03/25/27 | 03/29/27 | 2.5 | 2.5 |
|
191.2 |
RPL09.INT.SSBC.3160 |
RPL09.Interior.SSBC LO #06 - Install Controls / EPMS / BMS OH and In-wall | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 03/25/27 | 03/29/27 | 2.5 | 2.5 |
|
187.5 |
RPL09.SKN.DHCD.01060 |
RPL09.SKIN.DHCD - Install Security | Glazing, Doors and Ext Devices | Not Started | 03/25/27 | 03/29/27 | 2.5 | 2.5 |
|
408.8 |
RPL09.INT.CTRC.9040 |
RPL09.Interior.Center-Corr - Priority GL9.16/9.17 - (P2) Install MEP In-Wall/Backing | Priority Wall Grid Line 9-16 / 9-17 | Not Started | 03/29/27 | 04/01/27 | 5.0 | 5.0 |
|
118.8 |
RPL09.INT.SSBC.4080 |
RPL09.Interior.SSBC LO #07 - Install Mechanical Piping Lowside OH and in-wall | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 03/29/27 | 03/30/27 | 2.5 | 2.5 |
|
181.2 |
RPL09.SKN.W.LO.01385 |
RPL09.SKIN.LO#16 - Cure Stemwall | Build back Exterior Leave Out Walls #16 (SSB - North of Loading Dock) | Not Started | 03/29/27 | 04/06/27 | 8.8 | 8.8 |
|
161.2 |
RPL.09.D.70140.XR |
External Tie from RPL07 - Interior HAC Crew 1 Flow (RPL07.INT.DHD.02470) | Internal Milestones (XREFs) | Not Started | 03/30/27 | 03/30/27 | 0.0 | 0.0 |
|
122.5 |
RPL09.EY.SSB.01260 |
RPL09.EY.SSB - L2 Checklist Completion | Tie-ins | Not Started | 03/30/27 | 04/12/27 | 12.5 | 12.5 |
|
136.2 |
RPL09.INT.DHC.01000 |
RPL09.Interior.DHC - Priority OH - WBS Summary | OverHead | Not Started | 03/30/27 | 05/21/27 | 48.8 | 48.8 |
|
402.5 |
RPL09.INT.DHC.01020 |
RPL09.Interior.DHC - Install Priority OH, Walls, OFE and Tie-ins - WBS Summary | DHC | Not Started | 03/30/27 | 12/06/27 | 217.5 | 217.5 |
|
233.8 |
RPL09.INT.DHC.01980 |
RPL09.Interior.DHC - Priority - Install Unistruts & Hangers (All Trades) Both side of Corridor Wall | OverHead | Not Started | 03/30/27 | 04/05/27 | 6.2 | 6.2 |
|
158.8 |
RPL09.INT.DHC.02250 |
RPL09.Interior.DHC - Priority - Install IMP Exterior Inwall Rough-In | OverHead | Not Started | 03/30/27 | 04/05/27 | 6.2 | 6.2 |
|
158.8 |
RPL09.INT.ENDC.01140 |
RPL09.Interior.End-Corridor - Install Doors Frame Hardware | Fit out | Not Started | 03/30/27 | 04/05/27 | 6.2 | 6.2 |
|
258.8 |
RPL09.INT.ENDC.01150 |
RPL09.Interior.End-Corridor - Install Electrical OH and In-wall | Fit out | Not Started | 03/30/27 | 04/07/27 | 8.8 | 8.8 |
|
256.2 |
RPL09.INT.ENDC.06940 |
RPL09.Interior.Center-Corridor - Final Finishes & Fixtures - Frame/Blocking Walls & Ceilings | Restrooms | Not Started | 03/30/27 | 04/12/27 | 12.5 | 12.5 |
|
268.8 |
RPL09.INT.SSBC.3240 |
RPL09.Interior.SSBC LO #06 - Install Electrical Lowside OH and In-wall | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 03/30/27 | 04/01/27 | 3.8 | 3.8 |
|
187.5 |
RPL09.CON.WP2.09280 |
RPL09.Conn Misc P/S/T and R/S/P @ MDF2 | ISP (MDF RPL09 <> MDF RPL09) | Not Started | 03/31/27 | 04/05/27 | 5.0 | 5.0 |
|
415.0 |
RPL09.CON.WP2.09300 |
RPL09.Conn Misc P/S/T and R/S/P @ MDF1 | ISP (MDF RPL09 <> MDF RPL09) | Not Started | 03/31/27 | 04/05/27 | 5.0 | 5.0 |
|
415.0 |
RPL09.INT.CTRC.1080 |
RPL09.Interior.Center-Corridor - Priority - Install Mechanical Piping/ Refrigerant (Highside OH space) | Priority Walls & Overhead | Not Started | 03/31/27 | 04/06/27 | 6.2 | 6.2 |
|
117.5 |
RPL09.INT.CTRC.9020 |
RPL09.Interior.Center-Corr - Priority GL9.16/9.17 - (P2) Install IMP Wall | Priority Wall Grid Line 9-16 / 9-17 | Not Started | 03/31/27 | 04/05/27 | 5.0 | 5.0 |
|
125.0 |
RPL09.INT.CTRC.9060 |
RPL09.Interior.Center-Corr - Priority GL9.16/9.17 - (P2) Hang Drywall (Both Sides) | Priority Wall Grid Line 9-16 / 9-17 | Not Started | 03/31/27 | 04/05/27 | 5.0 | 5.0 |
|
118.8 |
RPL09.INT.DHA.02360 |
RPL09.Interior.DHA - Priority - Install Temp Doors Frame Hardware | OverHead | Not Started | 03/31/27 | 04/02/27 | 3.8 | 3.8 |
|
322.5 |
RPL09.INT.ENDC.1080 |
RPL09.Interior.End-Corr - Priority - Tape Finish Paint Priority Soffit both sides (Top Out) & Draft Blanket | Priority Walls & Overhead | Not Started | 03/31/27 | 04/08/27 | 8.8 | 8.8 |
|
218.8 |
RPL09.INT.ENDC.1100 |
RPL09.Interior.End-Corr - Priority - Install Mechanical Piping/ Refrigerant (Highside OH space) | Priority Walls & Overhead | Not Started | 03/31/27 | 04/06/27 | 6.2 | 6.2 |
|
222.5 |
RPL09.INT.SSB.14100 |
RPL09.Interior.SSB LO #01 to #05 - Install Fire Life Safety Lowside OH and In-wall | OH & Framing | Not Started | 03/31/27 | 03/31/27 | 1.2 | 1.2 |
|
191.2 |
RPL09.INT.SSB.14120 |
RPL09.Interior.SSB LO #01 to #05 - Install Plumbing Lowside OH and In-wall | OH & Framing | Not Started | 03/31/27 | 04/01/27 | 2.5 | 2.5 |
|
168.8 |
RPL09.INT.SSBC.4100 |
RPL09.Interior.SSBC LO #07 - Install Fire Life Safety Lowside OH and In-wall | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 03/31/27 | 04/01/27 | 2.5 | 2.5 |
|
185.0 |
RPL09.INT.SSBC.4120 |
RPL09.Interior.SSBC LO #07 - Install Plumbing Lowside OH and In-wall | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 03/31/27 | 04/01/27 | 2.5 | 2.5 |
|
181.2 |
RPL09.INT.SSB.03060 |
RPL09.Interior.SSB - Final Finishes & Fixtures - Hang Tape Bed and Fire/Caulking | Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) | Not Started | 04/01/27 | 04/07/27 | 6.2 | 6.2 |
|
307.5 |
RPL09.INT.SSB.03080 |
RPL09.Interior.SSB - Loading Dock and Storage - Tape Finish Paint (Top Out) | Loading Dock and Storage | Not Started | 04/01/27 | 04/12/27 | 10.0 | 10.0 |
|
208.8 |
RPL09.INT.SSB.05860 |
RPL09.Interior.SSB - BoW - BoW - Install Mechanical Piping/ Refrigerant (Lowside OH space) | Balance of Walls and OverHead | Not Started | 04/01/27 | 04/07/27 | 6.2 | 6.2 |
|
188.8 |
RPL09.INT.SSB.06660 |
RPL09.Interior.SSB - Final Finishes & Fixtures - Framing RO Verification, Tile Finish & ADA Verification (Pre Drywall) | Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) | Not Started | 04/01/27 | 04/07/27 | 6.2 | 6.2 |
|
295.0 |
RPL09.INT.SSB.14140 |
RPL09.Interior.SSB LO #01 to #05 - Install Security Lowside OH and In-wall | OH & Framing | Not Started | 04/01/27 | 04/02/27 | 2.5 | 2.5 |
|
191.2 |
RPL09.INT.SSB.14160 |
RPL09.Interior.SSB LO #01 to #05 - Install Controls / EPMS / BMS OH and In-wall | OH & Framing | Not Started | 04/02/27 | 04/05/27 | 2.5 | 2.5 |
|
168.8 |
RPL09.INT.SSBC.3180 |
RPL09.Interior.SSBC LO #06 - Install Door Frames | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 04/02/27 | 04/05/27 | 2.5 | 2.5 |
|
187.5 |
RPL09.INT.SSBC.4140 |
RPL09.Interior.SSBC LO #07 - Install Security Lowside OH and In-wall | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 04/02/27 | 04/05/27 | 2.5 | 2.5 |
|
185.0 |
RPL09.INT.SSBC.4160 |
RPL09.Interior.SSBC LO #07 - Install Controls / EPMS / BMS OH and In-wall | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 04/02/27 | 04/05/27 | 2.5 | 2.5 |
|
181.2 |
RPL09.MCUP.LP2.1960 |
RPL09.MCUP.Loop 2 - Install Exterior Signage | Hardscape and Landscape | Not Started | 04/05/27 | 04/16/27 | 12.5 | 12.5 |
|
470.0 |
DCC.B9.3225 |
[SSDCB4] CorpNet/Security/FacNet Ready [DHB] | Connectivity | Not Started | 04/06/27 | 04/06/27 | 0.0 | 0.0 |
|
415.0 |
GCD.RPL09.1290 |
Interior fit-out Start RPL09 - DHC&D | Construction Milestones | Not Started | 04/06/27 | 04/06/27 | 0.0 | 0.0 |
|
443.8 |
RPL09.INT.CTRC.01070 |
RPL09.Interior.Center-Corridor - BoW - Early MEPF Inwall Rough-In for Ancillary Skid (Room #3.6) | Priority Wall Grid Line 9-16 / 9-17 | Not Started | 04/06/27 | 04/08/27 | 3.8 | 3.8 |
|
206.2 |
RPL09.INT.CTRC.8940 |
RPL09.Interior.Center-Corr - Priority - All MEP In-wall in Production Entry Fiber Rooms (Room #2.7) | Priority Wall Grid Line 9-16 / 9-17 | Not Started | 04/06/27 | 04/14/27 | 8.8 | 8.8 |
|
185.0 |
RPL09.INT.CTRC.9080 |
RPL09.Interior.Center-Corr - Priority GL9.16/9.17 - (P2) Tape Finish Paint (Both Sides) | Priority Wall Grid Line 9-16 / 9-17 | Not Started | 04/06/27 | 04/12/27 | 6.2 | 6.2 |
|
118.8 |
RPL09.INT.DHC.02230 |
RPL09.Interior.DHC - Priority - Install Drywall at Exterior Walls | OverHead | Not Started | 04/06/27 | 04/12/27 | 6.2 | 6.2 |
|
158.8 |
RPL09.INT.SBC.03280 |
RPL09.Interior.SSB-Corridor - BoW -Install Electrical Lowside OH and In-wall and Lights (Coordinate Lights location to n | Balance of Walls & Overhead | Not Started | 04/06/27 | 04/19/27 | 12.5 | 12.5 |
|
138.8 |
RPL09.INT.SSB.14240 |
RPL09.Interior.SSB LO #01 to #05 - Install Electrical Lowside OH and In-wall | OH & Framing | Not Started | 04/06/27 | 04/14/27 | 8.8 | 8.8 |
|
168.8 |
RPL09.INT.SSBC.3200 |
RPL09.Interior.SSBC LO #06 - Mechanical Tie-In | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 04/06/27 | 04/07/27 | 2.5 | 2.5 |
|
187.5 |
RPL09.INT.SSBC.3300 |
RPL09.Interior.SSBC LO #06 - Electrical Tie-In | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 04/06/27 | 04/12/27 | 6.2 | 6.2 |
|
187.5 |
RPL09.INT.SSBC.4240 |
RPL09.Interior.SSBC LO #07 - Install Electrical Lowside OH and In-wall | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 04/06/27 | 04/08/27 | 3.8 | 3.8 |
|
181.2 |
GCD.RPL09.1655 |
Start MES Installation - RPL09 | Construction Milestones | Not Started | 04/07/27 | 04/07/27 | 0.0 | 0.0 |
|
127.5 |