Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL09 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:12 PM · 5201 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
0
Completed
0
In Progress
0
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
GCD.RPL09.1700 Start LV Electrical Skid Set-In-Place - RPL09 Construction Milestones Not Started 04/07/27 04/07/27 0.0 0.0
0%
330.0
RPL09.INT.CTRC.1120 RPL09.Interior.Center-Corridor - Priority - Install Plumbing (Highside OH space) Priority Walls & Overhead Not Started 04/07/27 04/13/27 6.2 6.2
0%
117.5
RPL09.INT.CTRC.1140 RPL09.Interior.Center-Corridor - Priority - Install FA/ VESDA/ hangers & Heat Trace (Highside OH space) Priority Walls & Overhead Not Started 04/07/27 04/13/27 6.2 6.2
0%
117.5
RPL09.INT.DHB.01140 RPL09.Interior.DHB - OFE - LV Skids and TopHat - Set / Place / Anchor OFE/MOFE & CFCI Not Started 04/07/27 04/27/27 18.8 18.8
0%
80.0
RPL09.INT.DHB.01150 RPL09.Interior.DHB - OFE - MES Skids - Set / Place / Anchor OFE/MOFE & CFCI Not Started 04/07/27 04/27/27 18.8 18.8
0%
121.2
RPL09.INT.DHB.01160 RPL09.Interior.DHB - OFE - WBS Summary OFE/MOFE & CFCI Not Started 04/07/27 07/14/27 86.2 86.2
0%
131.2
RPL09.INT.DHD.02130 RPL09.Interior.DHD - Priority - Install Mechanical Piping OverHead Not Started 04/07/27 04/22/27 15.0 15.0
0%
148.8
RPL09.INT.ENDC.1140 RPL09.Interior.End-Corr - Priority - Install Plumbing (Highside OH space) Priority Walls & Overhead Not Started 04/07/27 04/13/27 6.2 6.2
0%
222.5
RPL09.INT.ENDC.1160 RPL09.Interior.End-Corr - Priority - Install FA (Highside OH space) Priority Walls & Overhead Not Started 04/07/27 04/13/27 6.2 6.2
0%
222.5
RPL09.SKN.W.LO.01390 RPL09.SKIN.LO#16 - Stemwall Water Proofing Build back Exterior Leave Out Walls #16 (SSB - North of Loading Dock) Not Started 04/07/27 04/13/27 6.2 6.2
0%
161.2
DCC.B9.3125 [SSDCB4] GS Gear Delivered [DHB] Connectivity Not Started 04/08/27 04/08/27 0.0 0.0
0%
478.8
DCC.B9.3135 [SSDCB4] GS Gear Delivered [DHA] Connectivity Not Started 04/08/27 04/08/27 0.0 0.0
0%
478.8
RPL09.EY.ENDC.1910 RPL09.EY.DHD.T1 - HAC Prefab prior to install for DH B Tent 1 Not Started 04/08/27 04/21/27 12.5 12.5
0%
102.5
RPL09.INT.CTRC.01130 RPL09.Interior.Center-Corridor - OFE - DHB (1x GS.IDF) B2 OFE/MOFE & CFCI Not Started 04/08/27 04/14/27 6.2 6.2
0%
173.8
RPL09.INT.CTRC.01200 RPL09.Interior.Center-Corridor - OFE - DHA (1x GS.IDF) A2 OFE/MOFE & CFCI Not Started 04/08/27 04/14/27 6.2 6.2
0%
173.8
RPL09.INT.ENDC.01170 RPL09.Interior.End-Corridor - Install Security OH and In-wall Fit out Not Started 04/08/27 04/16/27 8.8 8.8
0%
256.2
RPL09.INT.ENDC.01180 RPL09.Interior.End-Corridor - Install Plumbing OH and In-wall Fit out Not Started 04/08/27 04/20/27 11.2 11.2
0%
258.8
RPL09.INT.SSB.01260 RPL09.Interior.SSB - BoW - Install Fire Life Safety Lowside OH and In-wall Balance of Walls and OverHead Not Started 04/08/27 04/16/27 8.8 8.8
0%
195.0
RPL09.INT.SSB.01800 RPL09.Interior.SSB - BoW - Install Plumbing Lowside OH and In-wall Balance of Walls and OverHead Not Started 04/08/27 04/16/27 8.8 8.8
0%
188.8
RPL09.INT.SSB.06680 RPL09.Interior.SSB - Final Finishes & Fixtures - Install Cement Board/ Drywall Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) Not Started 04/08/27 04/14/27 6.2 6.2
0%
295.0
RPL09.INT.CTRC.01090 RPL09.Interior.Center-Corridor - BoW - Early Install Drywall for Ancillary Skid (Room #3.6) Priority Wall Grid Line 9-16 / 9-17 Not Started 04/09/27 04/13/27 3.8 3.8
0%
206.2
RPL09.INT.ENDC.1120 RPL09.Interior.End-Corr - Priority GL9.27 - (P3) Frame Walls (All full height Walls) Priority Wall Grid Line 9-27 Not Started 04/09/27 04/15/27 6.2 6.2
0%
218.8
RPL09.INT.SSBC.4180 RPL09.Interior.SSBC LO #07 - Install Door Frames Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 04/09/27 04/12/27 2.5 2.5
0%
181.2
GCD.RPL09.1826 Delivery of RMU - (First Delivery) - RPL09 - DHA&B Construction Milestones Not Started 04/12/27 04/12/27 0.0 0.0
0%
83.8
ICM.B9.1825 [SSDCB4] Delivery of MVS - Medium Voltage Switches (First Delivery) Construction Not Started 04/12/27 04/12/27 0.0 0.0
0%
83.8
RPL09.INT.DHB.01180 RPL09.Interior.DHB - LV Skids and TopHat Tie-ins (LOE) DHB - LV Skids and TopHat Not Started 04/12/27 05/11/27 27.5 27.5
0%
140.0
RPL09.INT.DHB.01181 RPL09.Interior.DHB - LV Skids and TopHat - Set & Anchor Interconnects DHB - LV Skids and TopHat Not Started 04/12/27 04/29/27 17.5 17.5
0%
140.0
RPL09.INT.DHB.01190 RPL09.Interior.DHB - Tie-ins - WBS Summary Tie-Ins Not Started 04/12/27 09/07/27 130.0 130.0
0%
186.2
RPL09.INT.SBC.03300 RPL09.Interior.SSB-Corridor - BoW -Install Fire Life Safety Lowside OH and In-wall Balance of Walls & Overhead Not Started 04/12/27 04/20/27 8.8 8.8
0%
152.5
RPL.09.D.70160.XR External Tie from RPL07 - Interior HAC Crew 2 Flow (RPL07.INT.DHC.02470) Internal Milestones (XREFs) Not Started 04/13/27 04/13/27 0.0 0.0
0%
112.5
RPL09.INT.DHC.02110 RPL09.Interior.DHC - Priority - Install Plumbing OverHead Not Started 04/13/27 04/19/27 6.2 6.2
0%
158.8
RPL09.INT.ENDC.06820 RPL09.Interior.Center-Corridor - Final Finishes & Fixtures - MEP Rough-In Restrooms Not Started 04/13/27 04/19/27 6.2 6.2
0%
268.8
RPL09.INT.SSB.01190 RPL09.Interior.SSB - Loading Dock and Storage - Install Electrical Rough-In Loading Dock and Storage Not Started 04/13/27 04/21/27 8.8 8.8
0%
212.5
RPL09.INT.SSB.01410 RPL09.Interior.SSB - Loading Dock and Storage - Install DAS (Distribution Antenna System) Loading Dock and Storage Not Started 04/13/27 04/19/27 6.2 6.2
0%
271.2
RPL09.INT.SSB.01510 RPL09.Interior.SSB - Loading Dock and Storage - Install Door Frames Loading Dock and Storage Not Started 04/13/27 04/19/27 6.2 6.2
0%
215.0
RPL09.INT.SSB.01740 RPL09.Interior.SSB - Loading Dock and Storage - Install VAV's/Duct Branches Loading Dock and Storage Not Started 04/13/27 04/26/27 12.5 12.5
0%
208.8
RPL09.INT.SSB.02940 RPL09.Interior.SSB - Loading Dock and Storage - Install Blocking/Steel support Assembly for Metal Canopy Loading Dock and Storage Not Started 04/13/27 04/19/27 6.2 6.2
0%
217.5
RPL09.INT.SSBC.3220 RPL09.Interior.SSBC LO #06 - Fire Safing OH and In-wall Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 04/13/27 04/13/27 1.2 1.2
0%
187.5
RPL09.INT.SSBC.4200 RPL09.Interior.SSBC LO #07 - Mechanical Tie-In Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 04/13/27 04/14/27 2.5 2.5
0%
181.2
RPL09.INT.SSBC.4300 RPL09.Interior.SSBC LO #07 - Electrical Tie-In Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 04/13/27 04/19/27 6.2 6.2
0%
181.2
RPL09.EY.DHB.01220 RPL09.EY.DHB - Install MV, RMUs & Electrical Panels (Qty 10) OFE Not Started 04/14/27 05/11/27 25.0 25.0
0%
82.5
RPL09.EY.DHB.01230 RPL09.EY.DHB - OFE - MV - WBS Summary OFE Not Started 04/14/27 06/14/27 53.8 53.8
0%
212.5
RPL09.INT.CTRC.01110 RPL09.Interior.Center-Corridor - BoW - Early Tape Finish Paint for Ancillary Skid (Room #3.6) Priority Wall Grid Line 9-16 / 9-17 Not Started 04/14/27 04/20/27 6.2 6.2
0%
206.2
RPL09.INT.CTRC.1200 RPL09.Interior.Center-Corridor - Priority - Install Fire Safing/ Seal Penetrations through Soffit (Highside OH space) Priority Walls & Overhead Not Started 04/14/27 04/16/27 3.8 3.8
0%
117.5
RPL09.INT.CTRC.1220 RPL09.Interior.Center-Corridor - BoW - Frame Balance of Wall Balance of Walls & Overhead Not Started 04/14/27 04/20/27 6.2 6.2
0%
117.5
RPL09.INT.CTRC.1230 RPL09.Interior.Center-Corridor - BoW - Balance Of Wall (ERAD, Maintance, Network infra, Spoke, Bathroom, etc) - WBS Summ Balance of Walls & Overhead Not Started 04/14/27 10/05/27 152.5 152.5
0%
110.0
RPL09.INT.CTRC.2020 RPL09.Interior.Center-Corridor - Priority - Fixed Draft/Smoke Curtain Patching Priority Walls & Overhead Not Started 04/14/27 04/16/27 3.8 3.8
0%
117.5
RPL09.INT.DHA.02340 RPL09.Interior.DHA - Priority - Install Security OverHead Not Started 04/14/27 04/20/27 6.2 6.2
0%
313.8
RPL09.INT.DHB.01200 RPL09.Interior.DHB - MES Skids Tie-ins (LOE) DHB - MES Skids Not Started 04/14/27 05/27/27 40.0 40.0
0%
140.0
RPL09.INT.DHB.01201 RPL09.Interior.DHB - MES Skids - Set & Anchor Interconnects DHB - MES Skids Not Started 04/14/27 05/11/27 25.0 25.0
0%
121.2
RPL09.INT.DHD.01050 RPL09.Interior.DHD - Priority - Install FA / Linear heat detection OverHead Not Started 04/14/27 04/20/27 6.2 6.2
0%
147.5
RPL09.INT.DHD.02150 RPL09.Interior.DHD - Priority - Install Electrical OverHead Not Started 04/14/27 04/27/27 12.5 12.5
0%
147.5
RPL09.INT.ENDC.1200 RPL09.Interior.End-Corr - Priority - Install Fire Safing/ Seal Penetrations through Soffit (HighS. OH space) Priority Walls & Overhead Not Started 04/14/27 04/16/27 3.8 3.8
0%
222.5
RPL09.INT.ENDC.1660 RPL09.Interior.End-Corr - Priority - Fixed Draft/Smoke Curtain Patching Priority Walls & Overhead Not Started 04/14/27 04/16/27 3.8 3.8
0%
222.5
RPL09.INT.SSBC.3260 RPL09.Interior.SSBC LO #06 - Install Backing Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 04/14/27 04/14/27 1.2 1.2
0%
187.5
RPL09.SKN.W.LO.01395 RPL09.SKIN.LO#16 - Install IMP Flashing Build back Exterior Leave Out Walls #16 (SSB - North of Loading Dock) Not Started 04/14/27 04/20/27 6.2 6.2
0%
161.2
RPL09.CON.WP2.06000 RPL09.Conn - Interior GSIDFs - WBS Summary GS.IDF (Interior) Not Started 04/15/27 06/14/28 365.0 365.0
0%
107.5
RPL09.CON.WP2.06200 RPL09.Conn - GSIDF/DH B2 - WBS Summary INT IDF OFE/MOFE - GSIDF9B2 Not Started 04/15/27 05/30/28 351.2 351.2
0%
90.0
RPL09.CON.WP2.06220 RPL09.Conn - GSIDF/DH B2 - Install Infrastructure (Racks, Waterfalls etc.) Infrastructure Not Started 04/15/27 04/21/27 6.2 6.2
0%
281.2
RPL09.CON.WP2.06400 RPL09.Conn - GSIDF/DH A2 - WBS Summary INT IDF OFE/MOFE - GSIDF9A2 Not Started 04/15/27 06/14/28 365.0 365.0
0%
76.2
RPL09.CON.WP2.06420 RPL09.Conn - GSIDF/DH A2 - Install Infrastructure (Racks, Waterfalls etc.) Infrastructure Not Started 04/15/27 04/21/27 6.2 6.2
0%
292.5
RPL09.INT.CTRC.8960 RPL09.Interior.Center-Corr - Priority - Hang Drywall Rock all Production Entry Fiber Rooms (Room #2.7) Priority Wall Grid Line 9-16 / 9-17 Not Started 04/15/27 04/20/27 5.0 5.0
0%
185.0
RPL09.INT.ENDC.6220 RPL09.Interior.End-Corr - Priority GL9.27 - (P3) Install MEP In-Wall/Backing Priority Wall Grid Line 9-27 Not Started 04/15/27 04/19/27 3.8 3.8
0%
282.5
RPL09.INT.SSB.06700 RPL09.Interior.SSB - Final Finishes & Fixtures - Water Proofing/ Tape Paint Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) Not Started 04/15/27 04/21/27 6.2 6.2
0%
295.0
RPL09.INT.SSB.14260 RPL09.Interior.SSB LO #01 to #05 - Install Backing OH & Framing Not Started 04/15/27 04/21/27 6.2 6.2
0%
168.8
RPL09.INT.SSBC.3280 RPL09.Interior.SSBC LO #06 - QC - Backings/Walls Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 04/15/27 04/16/27 2.5 2.5
0%
187.5
RPL09.INT.DHB.01182 RPL09.Interior.DHB - LV Skids and TopHat - Maintenance and Reserve Busways DHB - LV Skids and TopHat Not Started 04/16/27 05/04/27 16.2 16.2
0%
140.0
RPL09.INT.ENDC.6200 RPL09.Interior.End-Corr - Priority GL9.27 - (P3) Install IMP Wall Priority Wall Grid Line 9-27 Not Started 04/16/27 04/21/27 5.0 5.0
0%
218.8
RPL09.INT.ENDC.01200 RPL09.Interior.End-Corridor - Install Controls / EPMS / BMS Fit out Not Started 04/19/27 04/22/27 5.0 5.0
0%
256.2
RPL09.INT.SSB.01220 RPL09.Interior.SSB - BoW - Install Security Lowside OH and In-wall Balance of Walls and OverHead Not Started 04/19/27 04/27/27 8.8 8.8
0%
275.0
RPL09.INT.SSB.01240 RPL09.Interior.SSB - BoW - Install VAV's/Duct Branches Balance of Walls and OverHead Not Started 04/19/27 04/30/27 12.5 12.5
0%
262.5
RPL09.INT.SSB.01820 RPL09.Interior.SSB - BoW - Mechanical Tie-In Balance of Walls and OverHead Not Started 04/19/27 04/23/27 6.2 6.2
0%
188.8
RPL09.INT.SSBC.3360 RPL09.Interior.SSBC LO #06 - Hang Drywall Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 04/19/27 04/20/27 2.5 2.5
0%
187.5
RPL09.INT.ENDC.06860 RPL09.Interior.Center-Corridor - Final Finishes & Fixtures - Hang Tape Bed and Fire/Caulking Restrooms Not Started 04/20/27 04/26/27 6.2 6.2
0%
281.2
RPL09.INT.ENDC.07040 RPL09.Interior.Center-Corridor - Final Finishes & Fixtures - Framing RO Verification, Tile Finish & ADA Verification (P Restrooms Not Started 04/20/27 04/26/27 6.2 6.2
0%
268.8
RPL09.INT.ENDC.6240 RPL09.Interior.End-Corr - Priority GL9.27 - (P3) Hang Drywall (Both Sides) Priority Wall Grid Line 9-27 Not Started 04/20/27 04/22/27 3.8 3.8
0%
282.5
RPL09.INT.SBC.03320 RPL09.Interior.SSB-Corridor - BoW - Install Plumbing Lowside OH and In-wall Balance of Walls & Overhead Not Started 04/20/27 04/28/27 8.8 8.8
0%
138.8
RPL09.INT.SSBC.4220 RPL09.Interior.SSBC LO #07 - Fire Safing OH and In-wall Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 04/20/27 04/20/27 1.2 1.2
0%
181.2
RPL09.SKN.SSB.01125 RPL09.SKIN.SSB - Install Metal Canopy Glazing, Doors and Ext Devices Not Started 04/20/27 04/21/27 2.5 2.5
0%
275.0
RPL09.INT.CTRC.1260 RPL09.Interior.Center-Corridor - BoW - Install Electrical Lowside OH and In-wall and Lights (Coordinate Lights location Balance of Walls & Overhead Not Started 04/21/27 05/04/27 12.5 12.5
0%
117.5
RPL09.INT.CTRC.1400 RPL09.Interior.Center-Corridor - BoW - Install Door Frames Balance of Walls & Overhead Not Started 04/21/27 04/27/27 6.2 6.2
0%
132.5
RPL09.INT.CTRC.8980 RPL09.Interior.Center-Corr - Priority - Tape, Paint & Finish Production Entry Fiber Rooms (Room #2.7) Priority Wall Grid Line 9-16 / 9-17 Not Started 04/21/27 04/27/27 6.2 6.2
0%
185.0
RPL09.INT.DHA.01060 RPL09.Interior.DHA - OFE - LV Skids and TopHat - Set / Place / Anchor OFE/MOFE & CFCI Not Started 04/21/27 05/11/27 18.8 18.8
0%
80.0
RPL09.INT.DHA.01070 RPL09.Interior.DHA - OFE - MES Skids - Set / Place / Anchor OFE/MOFE & CFCI Not Started 04/21/27 05/11/27 18.8 18.8
0%
108.8
RPL09.INT.DHA.01080 RPL09.Interior.DHA - OFE - WBS Summary OFE/MOFE & CFCI Not Started 04/21/27 08/11/27 98.8 98.8
0%
117.5
RPL09.INT.DHA.02325 RPL09.Interior.DHA - Priority - Install Controls / EPMS / BMS OverHead Not Started 04/21/27 04/26/27 5.0 5.0
0%
313.8
RPL09.INT.DHB.01210 RPL09.Interior.DHB - OFE - Control Fault Domain 1 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary Control Fault Domain 1 Not Started 04/21/27 05/13/27 21.2 21.2
0%
102.5
RPL09.INT.DHB.02400 RPL09.Interior.DHB - OFE - Control Fault Domain 1 (LV Side Aisle) Control Fault Domain 1 Not Started 04/21/27 04/27/27 6.2 6.2
0%
102.5
RPL09.INT.DHD.02210 RPL09.Interior.DHD - Priority - Install Temp Doors Frame Hardware OverHead Not Started 04/21/27 04/23/27 3.8 3.8
0%
410.0
RPL09.INT.SBC.03340 RPL09.Interior.SSB-Corridor - BoW - Install Security Lowside OH and In-wall Balance of Walls & Overhead Not Started 04/21/27 04/29/27 8.8 8.8
0%
172.5
RPL09.INT.SSBC.3400 RPL09.Interior.SSBC LO #06 - Tape Finish Paint Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 04/21/27 04/27/27 6.2 6.2
0%
187.5
RPL09.INT.SSBC.4260 RPL09.Interior.SSBC LO #07 - Install Backing Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 04/21/27 04/21/27 1.2 1.2
0%
181.2
RPL09.SKN.W.LO.01420 RPL09.SKIN.LO#16 - Install IMP Insulated Metal Panels Build back Exterior Leave Out Walls #16 (SSB - North of Loading Dock) Not Started 04/21/27 04/27/27 6.2 6.2
0%
161.2
GCD.RPL09.1725 Start FSHAC set in place - RPL09 - DHA&B Construction Milestones Not Started 04/22/27 04/22/27 0.0 0.0
0%
316.2
RPL09.CON.WP2.06240 RPL09.Conn - GSIDF/DH B2 - Install Cabling (Pull, Splice & terminate) Cabling Not Started 04/22/27 04/29/27 7.5 7.5
0%
423.8
RPL09.CON.WP2.06260 RPL09.Conn - GSIDF/DH B2 - Install Copper, WAPs, Security Camera & Access Control Cabling Not Started 04/22/27 05/07/27 15.0 15.0
0%
281.2
RPL09.CON.WP2.06440 RPL09.Conn - GSIDF/DH A2 - Install Cabling (Pull, Splice & terminate) Cabling Not Started 04/22/27 04/29/27 7.5 7.5
0%
423.8
RPL09.CON.WP2.06460 RPL09.Conn - GSIDF/DH A2 - Install Copper, WAPs, Security Camera & Access Control Cabling Not Started 04/22/27 05/07/27 15.0 15.0
0%
292.5
RPL09.INT.DHB.01202 RPL09.Interior.DHB - MES Skids - Piping Tie-Ins & Inspections DHB - MES Skids Not Started 04/22/27 05/19/27 25.0 25.0
0%
121.2
RPL09.INT.DHB.02420 RPL09.Interior.DHB - OFE - Control Fault Domain 1 (HAC) Control Fault Domain 1 Not Started 04/22/27 05/12/27 18.8 18.8
0%
102.5