Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL09 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:12 PM
· 5201 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
0
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL09.INT.ENDC.1205 |
RPL09.Interior.End-Corridor - Balance Of Wall - (ERAD, Maintance, Network infra, Spoke, Bathroom, etc) - WBS Summary | Balance of Walls & Overhead | Not Started | 04/22/27 | 12/15/27 | 205.0 | 205.0 |
|
151.2 |
RPL09.INT.ENDC.1220 |
RPL09.Interior.End-Corridor - Frame Balance of Wall | Balance of Walls & Overhead | Not Started | 04/22/27 | 04/28/27 | 6.2 | 6.2 |
|
218.8 |
RPL09.INT.ENDC.6140 |
RPL09.Interior.End-Corridor - Early In-wall for Ancillary Skids (Room #3.6) | Priority Wall Grid Line 9-27 | Not Started | 04/22/27 | 04/26/27 | 3.8 | 3.8 |
|
297.5 |
RPL09.INT.SSB.01420 |
RPL09.Interior.SSB - Loading Dock and Storage - Install Dock Levelers, Pads, Exterior lights and Lock | Loading Dock and Storage | Not Started | 04/22/27 | 04/30/27 | 8.8 | 8.8 |
|
215.0 |
RPL09.INT.SSB.01900 |
RPL09.Interior.SSB - Final Finishes & Fixtures - Casework | Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) | Not Started | 04/22/27 | 04/30/27 | 8.8 | 8.8 |
|
295.0 |
RPL09.INT.SSB.14280 |
RPL09.Interior.SSB LO #01 to #05 - QC - Backings/Walls | OH & Framing | Not Started | 04/22/27 | 04/28/27 | 6.2 | 6.2 |
|
168.8 |
RPL09.INT.SSBC.4280 |
RPL09.Interior.SSBC LO #07 - QC - Backings/Walls | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 04/22/27 | 04/23/27 | 2.5 | 2.5 |
|
181.2 |
RPL09.SKN.SSB.01150 |
RPL09.SKIN.SSB - Install Perm Doors | Glazing, Doors and Ext Devices | Not Started | 04/22/27 | 04/23/27 | 2.5 | 2.5 |
|
275.0 |
RPL09.INT.DHA.01090 |
RPL09.Interior.DHA - LV Skids and TopHat Tie-ins (LOE) | DHA - LV Skids and TopHat | Not Started | 04/23/27 | 05/24/27 | 27.5 | 27.5 |
|
140.0 |
RPL09.INT.DHA.01091 |
RPL09.Interior.DHA - LV Skids and TopHat - Set & Anchor Interconnects | DHA - LV Skids and TopHat | Not Started | 04/23/27 | 05/12/27 | 17.5 | 17.5 |
|
140.0 |
RPL09.INT.DHA.01100 |
RPL09.Interior.DHA - Tie-ins - WBS Summary | Tie-Ins | Not Started | 04/23/27 | 10/05/27 | 143.8 | 143.8 |
|
172.5 |
RPL09.INT.DHB.01183 |
RPL09.Interior.DHB - LV Skids and TopHat - Top Hat Busway | DHB - LV Skids and TopHat | Not Started | 04/23/27 | 05/11/27 | 16.2 | 16.2 |
|
140.0 |
RPL09.INT.DHB.01250 |
RPL09.Interior.DHB - Tie-ins - Control Fault Domain 1 - WBS Summary | Control Fault Domain 1 | Not Started | 04/23/27 | 06/25/27 | 56.2 | 56.2 |
|
102.5 |
RPL09.INT.DHB.02700 |
RPL09.Interior.DHB - Control Fault Domain 1 - Install Duct (LV Side) | LV Side Tie-ins | Not Started | 04/23/27 | 04/29/27 | 6.2 | 6.2 |
|
108.8 |
RPL09.INT.DHC.02130 |
RPL09.Interior.DHC - Priority - Install Mechanical Piping | OverHead | Not Started | 04/23/27 | 05/10/27 | 15.0 | 15.0 |
|
148.8 |
RPL09.INT.ENDC.01210 |
RPL09.Interior.End-Corridor - Install Fire Life Safety OH and In-wall | Fit out | Not Started | 04/23/27 | 05/06/27 | 12.5 | 12.5 |
|
256.2 |
RPL09.INT.ENDC.6260 |
RPL09.Interior.End-Corr - Priority GL9.27 - (P3) Tape Finish Paint (Both Sides) | Priority Wall Grid Line 9-27 | Not Started | 04/23/27 | 04/29/27 | 6.2 | 6.2 |
|
282.5 |
GCD.RPL09.1827 |
Delivery of RMU - (First Delivery) - RPL09 - DHC&D | Construction Milestones | Not Started | 04/26/27 | 04/26/27 | 0.0 | 0.0 |
|
222.5 |
RPL09.INT.DHB.01203 |
RPL09.Interior.DHB - MES Skids - CDU Tie-Ins | DHB - MES Skids | Not Started | 04/26/27 | 05/21/27 | 25.0 | 25.0 |
|
140.0 |
RPL09.INT.SSB.01290 |
RPL09.Interior.SSB - BoW - Frame Hard Lid | Balance of Walls and OverHead | Not Started | 04/26/27 | 04/30/27 | 6.2 | 6.2 |
|
188.8 |
RPL09.INT.SSBC.4360 |
RPL09.Interior.SSBC LO #07 - Hang Drywall | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 04/26/27 | 04/27/27 | 2.5 | 2.5 |
|
181.2 |
RPL09.INT.CTRC.1280 |
RPL09.Interior.Center-Corridor - BoW - Install Fire Life Safety Lowside OH and In-wall | Balance of Walls & Overhead | Not Started | 04/27/27 | 05/05/27 | 8.8 | 8.8 |
|
131.2 |
RPL09.INT.DHB.01310 |
RPL09.Interior.DHB - Control Fault Domain 1 - Install LV Side Aisle HAC Busway | LV Side Tie-ins | Not Started | 04/27/27 | 05/03/27 | 6.2 | 6.2 |
|
117.5 |
RPL09.INT.DHB.02440 |
RPL09.Interior.DHB - OFE - Control Fault Domain 1 (Mech Side Aisle) | Control Fault Domain 1 | Not Started | 04/27/27 | 05/13/27 | 16.2 | 16.2 |
|
102.5 |
RPL09.INT.ENDC.07060 |
RPL09.Interior.Center-Corridor - Final Finishes & Fixtures - Install Cement Board/ Drywall | Restrooms | Not Started | 04/27/27 | 05/03/27 | 6.2 | 6.2 |
|
268.8 |
RPL09.INT.ENDC.6160 |
RPL09.Interior.End-Corridor - Hang Early Drywall & DFH for Ancillary Skids (Room #3.6) | Priority Wall Grid Line 9-27 | Not Started | 04/27/27 | 04/28/27 | 2.5 | 2.5 |
|
297.5 |
RPL09.INT.SSB.01250 |
RPL09.Interior.SSB - Loading Dock and Storage - Install Security | Loading Dock and Storage | Not Started | 04/27/27 | 05/05/27 | 8.8 | 8.8 |
|
208.8 |
RPL09.INT.SSB.01470 |
RPL09.Interior.SSB - Loading Dock and Storage - Install Unit Heaters | Loading Dock and Storage | Not Started | 04/27/27 | 05/03/27 | 6.2 | 6.2 |
|
273.8 |
RPL09.INT.SSB.01760 |
RPL09.Interior.SSB - Loading Dock and Storage - Mechanical Tie-In | Loading Dock and Storage | Not Started | 04/27/27 | 05/03/27 | 6.2 | 6.2 |
|
273.8 |
RPL09.INT.SSB.01780 |
RPL09.Interior.SSB - Loading Dock and Storage - Install Split Systems/Humidifiers | Loading Dock and Storage | Not Started | 04/27/27 | 05/03/27 | 6.2 | 6.2 |
|
267.5 |
RPL09.EY.DHA.01220 |
RPL09.EY.DHA - Install MV, RMUs & Electrical Panels (Qty 10) | OFE | Not Started | 04/28/27 | 05/25/27 | 25.0 | 25.0 |
|
88.8 |
RPL09.INT.CTRC.9000 |
RPL09.Interior.Center-Corridor - Priority - MEP OH over Cable Tray | Priority Walls & Overhead | Not Started | 04/28/27 | 05/06/27 | 8.8 | 8.8 |
|
185.0 |
RPL09.INT.DHA.01110 |
RPL09.Interior.DHA - MES Skids Tie-ins (LOE) | DHA - MES Skids | Not Started | 04/28/27 | 06/11/27 | 40.0 | 40.0 |
|
127.5 |
RPL09.INT.DHA.01111 |
RPL09.Interior.DHA - MES Skids - Set & Anchor Interconnects | DHA - MES Skids | Not Started | 04/28/27 | 05/25/27 | 25.0 | 25.0 |
|
108.8 |
RPL09.INT.DHB.01204 |
RPL09.Interior.DHB - MES Skids - BMS Tie-Ins | DHB - MES Skids | Not Started | 04/28/27 | 05/25/27 | 25.0 | 25.0 |
|
140.0 |
RPL09.INT.DHB.01320 |
RPL09.Interior.DHB - OFE - Control Fault Domain 2 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | Control Fault Domain 2 | Not Started | 04/28/27 | 05/27/27 | 27.5 | 27.5 |
|
106.2 |
RPL09.INT.DHB.01330 |
RPL09.Interior.DHB - Control Fault Domain 1 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 04/28/27 | 05/04/27 | 6.2 | 6.2 |
|
117.5 |
RPL09.INT.DHB.02460 |
RPL09.Interior.DHB - OFE - Control Fault Domain 2 (LV Side Aisle) | Control Fault Domain 2 | Not Started | 04/28/27 | 05/03/27 | 5.0 | 5.0 |
|
118.8 |
RPL09.INT.DHC.01050 |
RPL09.Interior.DHC - Priority - Install FA / Linear heat detection | OverHead | Not Started | 04/28/27 | 05/04/27 | 6.2 | 6.2 |
|
147.5 |
RPL09.INT.DHC.02150 |
RPL09.Interior.DHC - Priority - Install Electrical | OverHead | Not Started | 04/28/27 | 05/11/27 | 12.5 | 12.5 |
|
147.5 |
RPL09.INT.DHD.01060 |
RPL09.Interior.DHD - OFE - LV Skids and TopHat - Set / Place / Anchor | OFE/MOFE & CFCI | Not Started | 04/28/27 | 05/14/27 | 16.2 | 16.2 |
|
141.2 |
RPL09.INT.DHD.01070 |
RPL09.Interior.DHD - OFE - MES Skids - Set / Place / Anchor | OFE/MOFE & CFCI | Not Started | 04/28/27 | 05/14/27 | 16.2 | 16.2 |
|
165.0 |
RPL09.INT.DHD.01080 |
RPL09.Interior.DHD - OFE - WBS Summary | OFE/MOFE & CFCI | Not Started | 04/28/27 | 09/14/27 | 121.2 | 121.2 |
|
138.8 |
RPL09.INT.DHD.02170 |
RPL09.Interior.DHD - Priority - Install Security | OverHead | Not Started | 04/28/27 | 04/29/27 | 2.5 | 2.5 |
|
407.5 |
RPL09.INT.SSBC.3500 |
RPL09.Interior.SSBC LO #06 - Install DAS (Distribution Antenna System) | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 04/28/27 | 04/28/27 | 1.2 | 1.2 |
|
187.5 |
RPL09.INT.SSBC.3580 |
RPL09.Interior.SSBC LO #06 - Install Flooring Tiles/Resinous Flooring in specific rooms | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 04/28/27 | 04/30/27 | 3.8 | 3.8 |
|
191.2 |
RPL09.INT.SSBC.3720 |
RPL09.Interior.SSBC LO #06 - Fire Safing / Wall Finishes | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 04/28/27 | 04/29/27 | 2.5 | 2.5 |
|
187.5 |
RPL09.INT.SSBC.4400 |
RPL09.Interior.SSBC LO #07 - Tape Finish Paint | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 04/28/27 | 05/04/27 | 6.2 | 6.2 |
|
181.2 |
RPL09.SKN.W.LO.01440 |
RPL09.SKIN.LO#16 - Install IMP Flashing & Caulking | Build back Exterior Leave Out Walls #16 (SSB - North of Loading Dock) | Not Started | 04/28/27 | 05/04/27 | 6.2 | 6.2 |
|
161.2 |
RPL09.INT.DHA.01092 |
RPL09.Interior.DHA - LV Skids and TopHat - Maintenance and Reserve Busways | DHA - LV Skids and TopHat | Not Started | 04/29/27 | 05/17/27 | 16.2 | 16.2 |
|
140.0 |
RPL09.INT.ENDC.1240 |
RPL09.Interior.End-Corridor - BoW - Install Mechanical Piping/ Refrigerant Lowside OH and in-wall | Balance of Walls & Overhead | Not Started | 04/29/27 | 05/05/27 | 6.2 | 6.2 |
|
218.8 |
RPL09.INT.ENDC.1400 |
RPL09.Interior.End-Corridor - BoW - Install Door Frames | Balance of Walls & Overhead | Not Started | 04/29/27 | 05/05/27 | 6.2 | 6.2 |
|
315.0 |
RPL09.INT.ENDC.6120 |
RPL09.Interior.End-Corridor - Early Tape Finish Paint for Ancillary Skids (Room #3.6) | Priority Wall Grid Line 9-27 | Not Started | 04/29/27 | 05/05/27 | 6.2 | 6.2 |
|
291.2 |
RPL09.INT.SBC.03360 |
RPL09.Interior.SSB-Corridor - BoW - Install VAV's/Duct Branches | Balance of Walls & Overhead | Not Started | 04/29/27 | 05/05/27 | 6.2 | 6.2 |
|
210.0 |
RPL09.INT.SBC.03460 |
RPL09.Interior.SSB-Corridor - BoW - Mechanical Tie-In | Balance of Walls & Overhead | Not Started | 04/29/27 | 05/05/27 | 6.2 | 6.2 |
|
138.8 |
RPL09.INT.SSB.14180 |
RPL09.Interior.SSB LO #01 to #05 - Install Door Frames | OH & Framing | Not Started | 04/29/27 | 04/30/27 | 2.5 | 2.5 |
|
168.8 |
RPL09.INT.SSBC.03380 |
RPL09.Interior.SSB-Corridor - Install Split Systems/Humidifiers | OFE/MOFE & CFCI | Not Started | 04/29/27 | 05/05/27 | 6.2 | 6.2 |
|
216.2 |
RPL09.INT.SSBC.3560 |
RPL09.Interior.SSBC LO #06 - Install Remaining Lights | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 04/29/27 | 05/03/27 | 3.8 | 3.8 |
|
187.5 |
RPL09.INT.DHB.01205 |
RPL09.Interior.DHB - MES Skids - EPMS Tie-Ins | DHB - MES Skids | Not Started | 04/30/27 | 05/27/27 | 25.0 | 25.0 |
|
140.0 |
RPL09.INT.DHB.01220 |
RPL09.Interior.DHB - Control Fault Domain 1 - Install Duct (MES Side) | Remaining Tie-ins post Mech Side Aisle install | Not Started | 04/30/27 | 05/27/27 | 25.0 | 25.0 |
|
102.5 |
RPL09.INT.DHB.01230 |
RPL09.Interior.DHB - Control Fault Domain 1 - Install Vesda / FA | Remaining Tie-ins post Mech Side Aisle install | Not Started | 04/30/27 | 05/27/27 | 25.0 | 25.0 |
|
115.0 |
RPL09.INT.DHB.01240 |
RPL09.Interior.DHB - Control Fault Domain 1 - Install TW | Remaining Tie-ins post Mech Side Aisle install | Not Started | 04/30/27 | 05/27/27 | 25.0 | 25.0 |
|
102.5 |
RPL09.INT.DHB.01380 |
RPL09.Interior.DHB - Tie-ins - Control Fault Domain 2 - WBS Summary | Control Fault Domain 2 | Not Started | 04/30/27 | 07/28/27 | 77.5 | 77.5 |
|
106.2 |
RPL09.INT.DHB.02120 |
RPL09.Interior.DHB - Control Fault Domain 1 - Install FW | Remaining Tie-ins post Mech Side Aisle install | Not Started | 04/30/27 | 05/27/27 | 25.0 | 25.0 |
|
102.5 |
RPL09.INT.DHB.02720 |
RPL09.Interior.DHB - Control Fault Domain 2 - Install Duct (LV Side) | LV Side Tie-ins | Not Started | 04/30/27 | 05/05/27 | 5.0 | 5.0 |
|
133.8 |
RPL09.INT.DHD.01090 |
RPL09.Interior.DHD - LV Skids and TopHat Tie-ins (LOE) | DHD - LV Skids and TopHat | Not Started | 04/30/27 | 05/28/27 | 26.2 | 26.2 |
|
277.5 |
RPL09.INT.DHD.01091 |
RPL09.Interior.DHD - LV Skids and TopHat - Set & Anchor Interconnects | DHD - LV Skids and TopHat | Not Started | 04/30/27 | 05/18/27 | 16.2 | 16.2 |
|
277.5 |
RPL09.INT.DHD.01100 |
RPL09.Interior.DHD - Tie-ins - WBS Summary | Tie-Ins | Not Started | 04/30/27 | 11/03/27 | 163.8 | 163.8 |
|
247.5 |
RPL09.INT.DHD.02190 |
RPL09.Interior.DHD - Priority - Install Controls / EPMS / BMS | OverHead | Not Started | 04/30/27 | 05/04/27 | 3.8 | 3.8 |
|
407.5 |
RPL09.INT.SBC.03440 |
RPL09.Interior.SSB-Corridor - BoW - Install Electrical - Lighitng Inverter Room (XX.S2.XX) | Balance of Walls & Overhead | Not Started | 04/30/27 | 05/10/27 | 8.8 | 8.8 |
|
172.5 |
RPL09.INT.SSBC.3420 |
RPL09.Interior.SSBC LO #06 - Electrical Trim Out | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 04/30/27 | 05/03/27 | 2.5 | 2.5 |
|
187.5 |
RPL09.INT.SSBC.3440 |
RPL09.Interior.SSBC LO #06 - Security Trim Out | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 04/30/27 | 05/03/27 | 2.5 | 2.5 |
|
187.5 |
RPL09.INT.SSB.01230 |
RPL09.Interior.SSB - BoW - Install Controls / EPMS / BMS OH and In-wall | Balance of Walls and OverHead | Not Started | 05/03/27 | 05/11/27 | 8.8 | 8.8 |
|
262.5 |
RPL09.INT.SSB.01310 |
RPL09.Interior.SSB - BoW - MEPF Hard Lid Rough-In | Balance of Walls and OverHead | Not Started | 05/03/27 | 05/07/27 | 6.2 | 6.2 |
|
188.8 |
RPL09.INT.SSB.01530 |
RPL09.Interior.SSB - Loading Dock and Storage - Install OverHead Doors | Loading Dock and Storage | Not Started | 05/03/27 | 05/14/27 | 12.5 | 12.5 |
|
215.0 |
RPL09.INT.SSB.02420 |
RPL09.Interior.SSB - Final Finishes & Fixtures - Fixture Install | Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) | Not Started | 05/03/27 | 05/11/27 | 8.8 | 8.8 |
|
322.5 |
RPL09.INT.SSB.05780 |
RPL09.Interior.SSB - BoW - QC - Walls | Balance of Walls and OverHead | Not Started | 05/03/27 | 05/07/27 | 6.2 | 6.2 |
|
188.8 |
RPL09.INT.SSB.06000 |
RPL09.Interior.SSB LO #16 - Close Exterior LO #16 (SSB - North of Loading Dock) WBS Summary | Leave Out Wall #16 (SSB - North of Loading Dock) | Not Started | 05/03/27 | 07/22/27 | 71.2 | 71.2 |
|
161.2 |
RPL09.INT.SSB.06020 |
RPL09.Interior.SSB LO #16 - IMP In Wall MEP | Leave Out Wall #16 (SSB - North of Loading Dock) | Not Started | 05/03/27 | 05/04/27 | 2.5 | 2.5 |
|
161.2 |
RPL09.INT.SSB.06740 |
RPL09.Interior.SSB - Final Finishes & Fixtures - Framing RO Verification, Tile Finish & ADA Verification (Post Drywall) | Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) | Not Started | 05/03/27 | 05/07/27 | 6.2 | 6.2 |
|
295.0 |
RPL09.INT.SSB.14340 |
RPL09.Interior.SSB LO #01 to #05 - MEPF Hard Lid Rough-In/ Close up Inspection | OH & Framing | Not Started | 05/03/27 | 05/06/27 | 5.0 | 5.0 |
|
168.8 |
RPL09.INT.DHB.01440 |
RPL09.Interior.DHB - OFE - Control Fault Domain 3 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | Control Fault Domain 3 | Not Started | 05/04/27 | 06/11/27 | 35.0 | 35.0 |
|
120.0 |
RPL09.INT.DHB.01460 |
RPL09.Interior.DHB - Control Fault Domain 2 - Install LV Side Aisle HAC Busway | LV Side Tie-ins | Not Started | 05/04/27 | 05/07/27 | 5.0 | 5.0 |
|
142.5 |
RPL09.INT.DHB.02520 |
RPL09.Interior.DHB - OFE - Control Fault Domain 3 (LV Side Aisle) | Control Fault Domain 3 | Not Started | 05/04/27 | 05/07/27 | 5.0 | 5.0 |
|
140.0 |
RPL09.INT.ENDC.07080 |
RPL09.Interior.Center-Corridor - Final Finishes & Fixtures - Water Proofing/ Tape Paint | Restrooms | Not Started | 05/04/27 | 05/10/27 | 6.2 | 6.2 |
|
268.8 |
RPL09.INT.SSBC.3520 |
RPL09.Interior.SSBC LO #06 - Plumbing Trim Out | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 05/04/27 | 05/05/27 | 2.5 | 2.5 |
|
187.5 |
RPL09.INT.SSBC.3600 |
RPL09.Interior.SSBC LO #06 - Install Asset Tags | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 05/04/27 | 05/04/27 | 1.2 | 1.2 |
|
187.5 |
RPL09.EY.DHD.01220 |
RPL09.EY.DHD - Install MV, RMUs & Electrical Panels (Qty 8) | OFE | Not Started | 05/05/27 | 06/02/27 | 25.0 | 25.0 |
|
215.0 |
RPL09.EY.DHD.01230 |
RPL09.EY.DHD - OFE - MV - WBS Summary | OFE | Not Started | 05/05/27 | 11/08/27 | 163.8 | 163.8 |
|
202.5 |
RPL09.INT.CTRC.1300 |
RPL09.Interior.Center-Corridor - BoW - Install Plumbing Lowside OH and In-wall | Balance of Walls & Overhead | Not Started | 05/05/27 | 05/13/27 | 8.8 | 8.8 |
|
117.5 |
RPL09.INT.DHB.01470 |
RPL09.Interior.DHB - Control Fault Domain 2 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 05/05/27 | 05/10/27 | 5.0 | 5.0 |
|
142.5 |
RPL09.INT.DHD.01110 |
RPL09.Interior.DHD - MES Skids Tie-ins (LOE) | DHD - MES Skids | Not Started | 05/05/27 | 06/14/27 | 35.0 | 35.0 |
|
265.0 |
RPL09.INT.DHD.01111 |
RPL09.Interior.DHD - MES Skids - Set & Anchor Interconnects | DHD - MES Skids | Not Started | 05/05/27 | 05/26/27 | 20.0 | 20.0 |
|
265.0 |
RPL09.INT.SSB.06040 |
RPL09.Interior.SSB LO #16 - QC - Backings/Walls | Leave Out Wall #16 (SSB - North of Loading Dock) | Not Started | 05/05/27 | 05/05/27 | 1.2 | 1.2 |
|
161.2 |
RPL09.INT.SSBC.01180 |
RPL09.Interior.SSB-Corridor - Install Fitout (GS.MDF Mech & Elec2x, Riser Room, GS Fiber Entry Room, Carrier MDF) - WBS | Fit out | Not Started | 05/05/27 | 09/03/27 | 107.5 | 107.5 |
|
185.0 |
RPL09.INT.SSBC.01210 |
RPL09.Interior.SSB-Corridor - Install Split Systems/Humidifiers | Fit out | Not Started | 05/05/27 | 05/11/27 | 6.2 | 6.2 |
|
218.8 |
RPL09.INT.SSBC.01390 |
RPL09.Interior.SSB-Corridor - Install Battery **?? | Fit out | Not Started | 05/05/27 | 05/18/27 | 12.5 | 12.5 |
|
188.8 |
RPL09.INT.SSBC.01590 |
RPL09.Interior.SSB-Corridor - Install Mechanical Tie-Ins (needs to micro plan) | Fit out | Not Started | 05/05/27 | 05/11/27 | 6.2 | 6.2 |
|
225.0 |
RPL09.INT.SSBC.3540 |
RPL09.Interior.SSBC LO #06 - Fire Life Safety Trim Out | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 05/05/27 | 05/05/27 | 1.2 | 1.2 |
|
187.5 |
RPL09.INT.SSBC.3620 |
RPL09.Interior.SSBC LO #06 - Install Door (Verify with Trades before installation) | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 05/05/27 | 05/05/27 | 1.2 | 1.2 |
|
187.5 |