Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL09 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:12 PM · 5201 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
0
Completed
0
In Progress
0
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL09.INT.ENDC.1205 RPL09.Interior.End-Corridor - Balance Of Wall - (ERAD, Maintance, Network infra, Spoke, Bathroom, etc) - WBS Summary Balance of Walls & Overhead Not Started 04/22/27 12/15/27 205.0 205.0
0%
151.2
RPL09.INT.ENDC.1220 RPL09.Interior.End-Corridor - Frame Balance of Wall Balance of Walls & Overhead Not Started 04/22/27 04/28/27 6.2 6.2
0%
218.8
RPL09.INT.ENDC.6140 RPL09.Interior.End-Corridor - Early In-wall for Ancillary Skids (Room #3.6) Priority Wall Grid Line 9-27 Not Started 04/22/27 04/26/27 3.8 3.8
0%
297.5
RPL09.INT.SSB.01420 RPL09.Interior.SSB - Loading Dock and Storage - Install Dock Levelers, Pads, Exterior lights and Lock Loading Dock and Storage Not Started 04/22/27 04/30/27 8.8 8.8
0%
215.0
RPL09.INT.SSB.01900 RPL09.Interior.SSB - Final Finishes & Fixtures - Casework Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) Not Started 04/22/27 04/30/27 8.8 8.8
0%
295.0
RPL09.INT.SSB.14280 RPL09.Interior.SSB LO #01 to #05 - QC - Backings/Walls OH & Framing Not Started 04/22/27 04/28/27 6.2 6.2
0%
168.8
RPL09.INT.SSBC.4280 RPL09.Interior.SSBC LO #07 - QC - Backings/Walls Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 04/22/27 04/23/27 2.5 2.5
0%
181.2
RPL09.SKN.SSB.01150 RPL09.SKIN.SSB - Install Perm Doors Glazing, Doors and Ext Devices Not Started 04/22/27 04/23/27 2.5 2.5
0%
275.0
RPL09.INT.DHA.01090 RPL09.Interior.DHA - LV Skids and TopHat Tie-ins (LOE) DHA - LV Skids and TopHat Not Started 04/23/27 05/24/27 27.5 27.5
0%
140.0
RPL09.INT.DHA.01091 RPL09.Interior.DHA - LV Skids and TopHat - Set & Anchor Interconnects DHA - LV Skids and TopHat Not Started 04/23/27 05/12/27 17.5 17.5
0%
140.0
RPL09.INT.DHA.01100 RPL09.Interior.DHA - Tie-ins - WBS Summary Tie-Ins Not Started 04/23/27 10/05/27 143.8 143.8
0%
172.5
RPL09.INT.DHB.01183 RPL09.Interior.DHB - LV Skids and TopHat - Top Hat Busway DHB - LV Skids and TopHat Not Started 04/23/27 05/11/27 16.2 16.2
0%
140.0
RPL09.INT.DHB.01250 RPL09.Interior.DHB - Tie-ins - Control Fault Domain 1 - WBS Summary Control Fault Domain 1 Not Started 04/23/27 06/25/27 56.2 56.2
0%
102.5
RPL09.INT.DHB.02700 RPL09.Interior.DHB - Control Fault Domain 1 - Install Duct (LV Side) LV Side Tie-ins Not Started 04/23/27 04/29/27 6.2 6.2
0%
108.8
RPL09.INT.DHC.02130 RPL09.Interior.DHC - Priority - Install Mechanical Piping OverHead Not Started 04/23/27 05/10/27 15.0 15.0
0%
148.8
RPL09.INT.ENDC.01210 RPL09.Interior.End-Corridor - Install Fire Life Safety OH and In-wall Fit out Not Started 04/23/27 05/06/27 12.5 12.5
0%
256.2
RPL09.INT.ENDC.6260 RPL09.Interior.End-Corr - Priority GL9.27 - (P3) Tape Finish Paint (Both Sides) Priority Wall Grid Line 9-27 Not Started 04/23/27 04/29/27 6.2 6.2
0%
282.5
GCD.RPL09.1827 Delivery of RMU - (First Delivery) - RPL09 - DHC&D Construction Milestones Not Started 04/26/27 04/26/27 0.0 0.0
0%
222.5
RPL09.INT.DHB.01203 RPL09.Interior.DHB - MES Skids - CDU Tie-Ins DHB - MES Skids Not Started 04/26/27 05/21/27 25.0 25.0
0%
140.0
RPL09.INT.SSB.01290 RPL09.Interior.SSB - BoW - Frame Hard Lid Balance of Walls and OverHead Not Started 04/26/27 04/30/27 6.2 6.2
0%
188.8
RPL09.INT.SSBC.4360 RPL09.Interior.SSBC LO #07 - Hang Drywall Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 04/26/27 04/27/27 2.5 2.5
0%
181.2
RPL09.INT.CTRC.1280 RPL09.Interior.Center-Corridor - BoW - Install Fire Life Safety Lowside OH and In-wall Balance of Walls & Overhead Not Started 04/27/27 05/05/27 8.8 8.8
0%
131.2
RPL09.INT.DHB.01310 RPL09.Interior.DHB - Control Fault Domain 1 - Install LV Side Aisle HAC Busway LV Side Tie-ins Not Started 04/27/27 05/03/27 6.2 6.2
0%
117.5
RPL09.INT.DHB.02440 RPL09.Interior.DHB - OFE - Control Fault Domain 1 (Mech Side Aisle) Control Fault Domain 1 Not Started 04/27/27 05/13/27 16.2 16.2
0%
102.5
RPL09.INT.ENDC.07060 RPL09.Interior.Center-Corridor - Final Finishes & Fixtures - Install Cement Board/ Drywall Restrooms Not Started 04/27/27 05/03/27 6.2 6.2
0%
268.8
RPL09.INT.ENDC.6160 RPL09.Interior.End-Corridor - Hang Early Drywall & DFH for Ancillary Skids (Room #3.6) Priority Wall Grid Line 9-27 Not Started 04/27/27 04/28/27 2.5 2.5
0%
297.5
RPL09.INT.SSB.01250 RPL09.Interior.SSB - Loading Dock and Storage - Install Security Loading Dock and Storage Not Started 04/27/27 05/05/27 8.8 8.8
0%
208.8
RPL09.INT.SSB.01470 RPL09.Interior.SSB - Loading Dock and Storage - Install Unit Heaters Loading Dock and Storage Not Started 04/27/27 05/03/27 6.2 6.2
0%
273.8
RPL09.INT.SSB.01760 RPL09.Interior.SSB - Loading Dock and Storage - Mechanical Tie-In Loading Dock and Storage Not Started 04/27/27 05/03/27 6.2 6.2
0%
273.8
RPL09.INT.SSB.01780 RPL09.Interior.SSB - Loading Dock and Storage - Install Split Systems/Humidifiers Loading Dock and Storage Not Started 04/27/27 05/03/27 6.2 6.2
0%
267.5
RPL09.EY.DHA.01220 RPL09.EY.DHA - Install MV, RMUs & Electrical Panels (Qty 10) OFE Not Started 04/28/27 05/25/27 25.0 25.0
0%
88.8
RPL09.INT.CTRC.9000 RPL09.Interior.Center-Corridor - Priority - MEP OH over Cable Tray Priority Walls & Overhead Not Started 04/28/27 05/06/27 8.8 8.8
0%
185.0
RPL09.INT.DHA.01110 RPL09.Interior.DHA - MES Skids Tie-ins (LOE) DHA - MES Skids Not Started 04/28/27 06/11/27 40.0 40.0
0%
127.5
RPL09.INT.DHA.01111 RPL09.Interior.DHA - MES Skids - Set & Anchor Interconnects DHA - MES Skids Not Started 04/28/27 05/25/27 25.0 25.0
0%
108.8
RPL09.INT.DHB.01204 RPL09.Interior.DHB - MES Skids - BMS Tie-Ins DHB - MES Skids Not Started 04/28/27 05/25/27 25.0 25.0
0%
140.0
RPL09.INT.DHB.01320 RPL09.Interior.DHB - OFE - Control Fault Domain 2 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary Control Fault Domain 2 Not Started 04/28/27 05/27/27 27.5 27.5
0%
106.2
RPL09.INT.DHB.01330 RPL09.Interior.DHB - Control Fault Domain 1 - Install LV Side Aisle Cable Tray LV Side Tie-ins Not Started 04/28/27 05/04/27 6.2 6.2
0%
117.5
RPL09.INT.DHB.02460 RPL09.Interior.DHB - OFE - Control Fault Domain 2 (LV Side Aisle) Control Fault Domain 2 Not Started 04/28/27 05/03/27 5.0 5.0
0%
118.8
RPL09.INT.DHC.01050 RPL09.Interior.DHC - Priority - Install FA / Linear heat detection OverHead Not Started 04/28/27 05/04/27 6.2 6.2
0%
147.5
RPL09.INT.DHC.02150 RPL09.Interior.DHC - Priority - Install Electrical OverHead Not Started 04/28/27 05/11/27 12.5 12.5
0%
147.5
RPL09.INT.DHD.01060 RPL09.Interior.DHD - OFE - LV Skids and TopHat - Set / Place / Anchor OFE/MOFE & CFCI Not Started 04/28/27 05/14/27 16.2 16.2
0%
141.2
RPL09.INT.DHD.01070 RPL09.Interior.DHD - OFE - MES Skids - Set / Place / Anchor OFE/MOFE & CFCI Not Started 04/28/27 05/14/27 16.2 16.2
0%
165.0
RPL09.INT.DHD.01080 RPL09.Interior.DHD - OFE - WBS Summary OFE/MOFE & CFCI Not Started 04/28/27 09/14/27 121.2 121.2
0%
138.8
RPL09.INT.DHD.02170 RPL09.Interior.DHD - Priority - Install Security OverHead Not Started 04/28/27 04/29/27 2.5 2.5
0%
407.5
RPL09.INT.SSBC.3500 RPL09.Interior.SSBC LO #06 - Install DAS (Distribution Antenna System) Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 04/28/27 04/28/27 1.2 1.2
0%
187.5
RPL09.INT.SSBC.3580 RPL09.Interior.SSBC LO #06 - Install Flooring Tiles/Resinous Flooring in specific rooms Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 04/28/27 04/30/27 3.8 3.8
0%
191.2
RPL09.INT.SSBC.3720 RPL09.Interior.SSBC LO #06 - Fire Safing / Wall Finishes Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 04/28/27 04/29/27 2.5 2.5
0%
187.5
RPL09.INT.SSBC.4400 RPL09.Interior.SSBC LO #07 - Tape Finish Paint Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 04/28/27 05/04/27 6.2 6.2
0%
181.2
RPL09.SKN.W.LO.01440 RPL09.SKIN.LO#16 - Install IMP Flashing & Caulking Build back Exterior Leave Out Walls #16 (SSB - North of Loading Dock) Not Started 04/28/27 05/04/27 6.2 6.2
0%
161.2
RPL09.INT.DHA.01092 RPL09.Interior.DHA - LV Skids and TopHat - Maintenance and Reserve Busways DHA - LV Skids and TopHat Not Started 04/29/27 05/17/27 16.2 16.2
0%
140.0
RPL09.INT.ENDC.1240 RPL09.Interior.End-Corridor - BoW - Install Mechanical Piping/ Refrigerant Lowside OH and in-wall Balance of Walls & Overhead Not Started 04/29/27 05/05/27 6.2 6.2
0%
218.8
RPL09.INT.ENDC.1400 RPL09.Interior.End-Corridor - BoW - Install Door Frames Balance of Walls & Overhead Not Started 04/29/27 05/05/27 6.2 6.2
0%
315.0
RPL09.INT.ENDC.6120 RPL09.Interior.End-Corridor - Early Tape Finish Paint for Ancillary Skids (Room #3.6) Priority Wall Grid Line 9-27 Not Started 04/29/27 05/05/27 6.2 6.2
0%
291.2
RPL09.INT.SBC.03360 RPL09.Interior.SSB-Corridor - BoW - Install VAV's/Duct Branches Balance of Walls & Overhead Not Started 04/29/27 05/05/27 6.2 6.2
0%
210.0
RPL09.INT.SBC.03460 RPL09.Interior.SSB-Corridor - BoW - Mechanical Tie-In Balance of Walls & Overhead Not Started 04/29/27 05/05/27 6.2 6.2
0%
138.8
RPL09.INT.SSB.14180 RPL09.Interior.SSB LO #01 to #05 - Install Door Frames OH & Framing Not Started 04/29/27 04/30/27 2.5 2.5
0%
168.8
RPL09.INT.SSBC.03380 RPL09.Interior.SSB-Corridor - Install Split Systems/Humidifiers OFE/MOFE & CFCI Not Started 04/29/27 05/05/27 6.2 6.2
0%
216.2
RPL09.INT.SSBC.3560 RPL09.Interior.SSBC LO #06 - Install Remaining Lights Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 04/29/27 05/03/27 3.8 3.8
0%
187.5
RPL09.INT.DHB.01205 RPL09.Interior.DHB - MES Skids - EPMS Tie-Ins DHB - MES Skids Not Started 04/30/27 05/27/27 25.0 25.0
0%
140.0
RPL09.INT.DHB.01220 RPL09.Interior.DHB - Control Fault Domain 1 - Install Duct (MES Side) Remaining Tie-ins post Mech Side Aisle install Not Started 04/30/27 05/27/27 25.0 25.0
0%
102.5
RPL09.INT.DHB.01230 RPL09.Interior.DHB - Control Fault Domain 1 - Install Vesda / FA Remaining Tie-ins post Mech Side Aisle install Not Started 04/30/27 05/27/27 25.0 25.0
0%
115.0
RPL09.INT.DHB.01240 RPL09.Interior.DHB - Control Fault Domain 1 - Install TW Remaining Tie-ins post Mech Side Aisle install Not Started 04/30/27 05/27/27 25.0 25.0
0%
102.5
RPL09.INT.DHB.01380 RPL09.Interior.DHB - Tie-ins - Control Fault Domain 2 - WBS Summary Control Fault Domain 2 Not Started 04/30/27 07/28/27 77.5 77.5
0%
106.2
RPL09.INT.DHB.02120 RPL09.Interior.DHB - Control Fault Domain 1 - Install FW Remaining Tie-ins post Mech Side Aisle install Not Started 04/30/27 05/27/27 25.0 25.0
0%
102.5
RPL09.INT.DHB.02720 RPL09.Interior.DHB - Control Fault Domain 2 - Install Duct (LV Side) LV Side Tie-ins Not Started 04/30/27 05/05/27 5.0 5.0
0%
133.8
RPL09.INT.DHD.01090 RPL09.Interior.DHD - LV Skids and TopHat Tie-ins (LOE) DHD - LV Skids and TopHat Not Started 04/30/27 05/28/27 26.2 26.2
0%
277.5
RPL09.INT.DHD.01091 RPL09.Interior.DHD - LV Skids and TopHat - Set & Anchor Interconnects DHD - LV Skids and TopHat Not Started 04/30/27 05/18/27 16.2 16.2
0%
277.5
RPL09.INT.DHD.01100 RPL09.Interior.DHD - Tie-ins - WBS Summary Tie-Ins Not Started 04/30/27 11/03/27 163.8 163.8
0%
247.5
RPL09.INT.DHD.02190 RPL09.Interior.DHD - Priority - Install Controls / EPMS / BMS OverHead Not Started 04/30/27 05/04/27 3.8 3.8
0%
407.5
RPL09.INT.SBC.03440 RPL09.Interior.SSB-Corridor - BoW - Install Electrical - Lighitng Inverter Room (XX.S2.XX) Balance of Walls & Overhead Not Started 04/30/27 05/10/27 8.8 8.8
0%
172.5
RPL09.INT.SSBC.3420 RPL09.Interior.SSBC LO #06 - Electrical Trim Out Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 04/30/27 05/03/27 2.5 2.5
0%
187.5
RPL09.INT.SSBC.3440 RPL09.Interior.SSBC LO #06 - Security Trim Out Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 04/30/27 05/03/27 2.5 2.5
0%
187.5
RPL09.INT.SSB.01230 RPL09.Interior.SSB - BoW - Install Controls / EPMS / BMS OH and In-wall Balance of Walls and OverHead Not Started 05/03/27 05/11/27 8.8 8.8
0%
262.5
RPL09.INT.SSB.01310 RPL09.Interior.SSB - BoW - MEPF Hard Lid Rough-In Balance of Walls and OverHead Not Started 05/03/27 05/07/27 6.2 6.2
0%
188.8
RPL09.INT.SSB.01530 RPL09.Interior.SSB - Loading Dock and Storage - Install OverHead Doors Loading Dock and Storage Not Started 05/03/27 05/14/27 12.5 12.5
0%
215.0
RPL09.INT.SSB.02420 RPL09.Interior.SSB - Final Finishes & Fixtures - Fixture Install Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) Not Started 05/03/27 05/11/27 8.8 8.8
0%
322.5
RPL09.INT.SSB.05780 RPL09.Interior.SSB - BoW - QC - Walls Balance of Walls and OverHead Not Started 05/03/27 05/07/27 6.2 6.2
0%
188.8
RPL09.INT.SSB.06000 RPL09.Interior.SSB LO #16 - Close Exterior LO #16 (SSB - North of Loading Dock) WBS Summary Leave Out Wall #16 (SSB - North of Loading Dock) Not Started 05/03/27 07/22/27 71.2 71.2
0%
161.2
RPL09.INT.SSB.06020 RPL09.Interior.SSB LO #16 - IMP In Wall MEP Leave Out Wall #16 (SSB - North of Loading Dock) Not Started 05/03/27 05/04/27 2.5 2.5
0%
161.2
RPL09.INT.SSB.06740 RPL09.Interior.SSB - Final Finishes & Fixtures - Framing RO Verification, Tile Finish & ADA Verification (Post Drywall) Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) Not Started 05/03/27 05/07/27 6.2 6.2
0%
295.0
RPL09.INT.SSB.14340 RPL09.Interior.SSB LO #01 to #05 - MEPF Hard Lid Rough-In/ Close up Inspection OH & Framing Not Started 05/03/27 05/06/27 5.0 5.0
0%
168.8
RPL09.INT.DHB.01440 RPL09.Interior.DHB - OFE - Control Fault Domain 3 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary Control Fault Domain 3 Not Started 05/04/27 06/11/27 35.0 35.0
0%
120.0
RPL09.INT.DHB.01460 RPL09.Interior.DHB - Control Fault Domain 2 - Install LV Side Aisle HAC Busway LV Side Tie-ins Not Started 05/04/27 05/07/27 5.0 5.0
0%
142.5
RPL09.INT.DHB.02520 RPL09.Interior.DHB - OFE - Control Fault Domain 3 (LV Side Aisle) Control Fault Domain 3 Not Started 05/04/27 05/07/27 5.0 5.0
0%
140.0
RPL09.INT.ENDC.07080 RPL09.Interior.Center-Corridor - Final Finishes & Fixtures - Water Proofing/ Tape Paint Restrooms Not Started 05/04/27 05/10/27 6.2 6.2
0%
268.8
RPL09.INT.SSBC.3520 RPL09.Interior.SSBC LO #06 - Plumbing Trim Out Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 05/04/27 05/05/27 2.5 2.5
0%
187.5
RPL09.INT.SSBC.3600 RPL09.Interior.SSBC LO #06 - Install Asset Tags Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 05/04/27 05/04/27 1.2 1.2
0%
187.5
RPL09.EY.DHD.01220 RPL09.EY.DHD - Install MV, RMUs & Electrical Panels (Qty 8) OFE Not Started 05/05/27 06/02/27 25.0 25.0
0%
215.0
RPL09.EY.DHD.01230 RPL09.EY.DHD - OFE - MV - WBS Summary OFE Not Started 05/05/27 11/08/27 163.8 163.8
0%
202.5
RPL09.INT.CTRC.1300 RPL09.Interior.Center-Corridor - BoW - Install Plumbing Lowside OH and In-wall Balance of Walls & Overhead Not Started 05/05/27 05/13/27 8.8 8.8
0%
117.5
RPL09.INT.DHB.01470 RPL09.Interior.DHB - Control Fault Domain 2 - Install LV Side Aisle Cable Tray LV Side Tie-ins Not Started 05/05/27 05/10/27 5.0 5.0
0%
142.5
RPL09.INT.DHD.01110 RPL09.Interior.DHD - MES Skids Tie-ins (LOE) DHD - MES Skids Not Started 05/05/27 06/14/27 35.0 35.0
0%
265.0
RPL09.INT.DHD.01111 RPL09.Interior.DHD - MES Skids - Set & Anchor Interconnects DHD - MES Skids Not Started 05/05/27 05/26/27 20.0 20.0
0%
265.0
RPL09.INT.SSB.06040 RPL09.Interior.SSB LO #16 - QC - Backings/Walls Leave Out Wall #16 (SSB - North of Loading Dock) Not Started 05/05/27 05/05/27 1.2 1.2
0%
161.2
RPL09.INT.SSBC.01180 RPL09.Interior.SSB-Corridor - Install Fitout (GS.MDF Mech & Elec2x, Riser Room, GS Fiber Entry Room, Carrier MDF) - WBS Fit out Not Started 05/05/27 09/03/27 107.5 107.5
0%
185.0
RPL09.INT.SSBC.01210 RPL09.Interior.SSB-Corridor - Install Split Systems/Humidifiers Fit out Not Started 05/05/27 05/11/27 6.2 6.2
0%
218.8
RPL09.INT.SSBC.01390 RPL09.Interior.SSB-Corridor - Install Battery **?? Fit out Not Started 05/05/27 05/18/27 12.5 12.5
0%
188.8
RPL09.INT.SSBC.01590 RPL09.Interior.SSB-Corridor - Install Mechanical Tie-Ins (needs to micro plan) Fit out Not Started 05/05/27 05/11/27 6.2 6.2
0%
225.0
RPL09.INT.SSBC.3540 RPL09.Interior.SSBC LO #06 - Fire Life Safety Trim Out Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 05/05/27 05/05/27 1.2 1.2
0%
187.5
RPL09.INT.SSBC.3620 RPL09.Interior.SSBC LO #06 - Install Door (Verify with Trades before installation) Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 05/05/27 05/05/27 1.2 1.2
0%
187.5