Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL09 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:12 PM · 5201 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
0
Completed
0
In Progress
0
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL09.INT.SSBC.4500 RPL09.Interior.SSBC LO #07 - Install DAS (Distribution Antenna System) Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 05/05/27 05/05/27 1.2 1.2
0%
181.2
RPL09.INT.SSBC.4580 RPL09.Interior.SSBC LO #07 - Install Flooring Tiles/Resinous Flooring in specific rooms Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 05/05/27 05/07/27 3.8 3.8
0%
185.0
RPL09.INT.SSBC.4720 RPL09.Interior.SSBC LO #07 - Fire Safing / Wall Finishes Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 05/05/27 05/06/27 2.5 2.5
0%
181.2
RPL09.EY.ENDC.1930 RPL09.EY.DHD.T2 - HAC Prefab prior to install for DH A Tent 2 Not Started 05/06/27 05/19/27 12.5 12.5
0%
80.0
RPL09.INT.CTRC.1320 RPL09.Interior.Center-Corridor - BoW - Install Security Lowside OH and In-wall Balance of Walls & Overhead Not Started 05/06/27 05/14/27 8.8 8.8
0%
183.8
RPL09.INT.DHA.01093 RPL09.Interior.DHA - LV Skids and TopHat - Top Hat Busway DHA - LV Skids and TopHat Not Started 05/06/27 05/24/27 16.2 16.2
0%
140.0
RPL09.INT.DHA.01112 RPL09.Interior.DHA - MES Skids - Piping Tie-Ins & Inspections DHA - MES Skids Not Started 05/06/27 06/03/27 25.0 25.0
0%
108.8
RPL09.INT.DHB.01520 RPL09.Interior.DHB - Tie-ins - Control Fault Domain 3 (including IDF) - WBS Summary Control Fault Domain 3 Not Started 05/06/27 08/04/27 78.8 78.8
0%
175.0
RPL09.INT.DHB.02740 RPL09.Interior.DHB - Control Fault Domain 3 - Install Duct (LV Side) LV Side Tie-ins Not Started 05/06/27 05/11/27 5.0 5.0
0%
155.0
RPL09.INT.DHD.01092 RPL09.Interior.DHD - LV Skids and TopHat - Maintenance and Reserve Busways DHD - LV Skids and TopHat Not Started 05/06/27 05/21/27 15.0 15.0
0%
277.5
RPL09.INT.ENDC.1260 RPL09.Interior.End-Corridor - BoW - Install Electrical Lowside OH and In-wall and Lights (Coordinate Lights location to Balance of Walls & Overhead Not Started 05/06/27 05/19/27 12.5 12.5
0%
218.8
RPL09.INT.SBC.03400 RPL09.Interior.SSB-Corridor - BoW - Install Controls / EPMS / BMS OH and In-wall Balance of Walls & Overhead Not Started 05/06/27 05/12/27 6.2 6.2
0%
210.0
RPL09.INT.SBC.03480 RPL09.Interior.SSB-Corridor - BoW - Frame Hard Lid Balance of Walls & Overhead Not Started 05/06/27 05/12/27 6.2 6.2
0%
138.8
RPL09.INT.SSB.01270 RPL09.Interior.SSB - Loading Dock and Storage - Install Controls / EPMS / BMS Loading Dock and Storage Not Started 05/06/27 05/11/27 5.0 5.0
0%
208.8
RPL09.INT.SSB.06060 RPL09.Interior.SSB LO #16 - Hang Exterior Wall Drywall Leave Out Wall #16 (SSB - North of Loading Dock) Not Started 05/06/27 05/07/27 2.5 2.5
0%
161.2
RPL09.INT.SSBC.3640 RPL09.Interior.SSBC LO #06 - Electrical L2 Checklist Completion Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 05/06/27 05/19/27 12.5 12.5
0%
187.5
RPL09.INT.SSBC.4560 RPL09.Interior.SSBC LO #07 - Install Remaining Lights Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 05/06/27 05/10/27 3.8 3.8
0%
181.2
DCC.B9.3145 [SSDCB4] GS Gear Delivered [DHC] Connectivity Not Started 05/07/27 05/07/27 0.0 0.0
0%
452.5
DCC.B9.3155 [SSDCB4] GS Gear Delivered [DHD] Connectivity Not Started 05/07/27 05/07/27 0.0 0.0
0%
452.5
RPL09.INT.CTRC.1940 RPL09.Interior.Center-Corridor - BoW - Install Vertical Tube Steel Support for Cable Tray (IFP Add) Balance of Walls & Overhead Not Started 05/07/27 05/12/27 5.0 5.0
0%
185.0
RPL09.INT.DHB.01260 RPL09.Interior.DHB - Control Fault Domain 1 - Pull BMS from panel to devices Remaining Tie-ins post Mech Side Aisle install Not Started 05/07/27 06/04/27 25.0 25.0
0%
115.0
RPL09.INT.DHB.01270 RPL09.Interior.DHB - Control Fault Domain 1 - Pull EMPS from panel to devices Remaining Tie-ins post Mech Side Aisle install Not Started 05/07/27 06/04/27 25.0 25.0
0%
115.0
RPL09.INT.DHB.01280 RPL09.Interior.DHB - Control Fault Domain 1 - Set UPS and Panel (2) Remaining Tie-ins post Mech Side Aisle install Not Started 05/07/27 06/04/27 25.0 25.0
0%
102.5
RPL09.INT.ENDC.01160 RPL09.Interior.End-Corridor - OFE - DHC (1x GS.IDF) C2 OFE/MOFE & CFCI Not Started 05/07/27 05/13/27 6.2 6.2
0%
232.5
RPL09.INT.ENDC.01220 RPL09.Interior.End-Corridor - Hang Drywall Fit out Not Started 05/07/27 05/17/27 8.8 8.8
0%
256.2
RPL09.INT.SSB.14360 RPL09.Interior.SSB LO #01 to #05 - Hang Drywall OH & Framing Not Started 05/07/27 05/17/27 8.8 8.8
0%
168.8
RPL09.INT.SSB.14500 RPL09.Interior.SSB LO #01 to #05 - Install DAS (Distribution Antenna System) Finishes Not Started 05/07/27 05/13/27 6.2 6.2
0%
182.5
RPL09.INT.SSBC.4420 RPL09.Interior.SSBC LO #07 - Electrical Trim Out Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 05/07/27 05/10/27 2.5 2.5
0%
181.2
RPL09.INT.SSBC.4440 RPL09.Interior.SSBC LO #07 - Security Trim Out Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 05/07/27 05/10/27 2.5 2.5
0%
181.2
RPL09.INT.DHA.01113 RPL09.Interior.DHA - MES Skids - CDU Tie-Ins ( 2 per day) DHA - MES Skids Not Started 05/10/27 06/07/27 25.0 25.0
0%
127.5
RPL09.INT.DHB.01580 RPL09.Interior.DHB - OFE - Control Fault Domain 4 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary Control Fault Domain 4 Not Started 05/10/27 06/25/27 42.5 42.5
0%
127.5
RPL09.INT.DHB.01600 RPL09.Interior.DHB - Control Fault Domain 3 - Install LV Side Aisle HAC Busway LV Side Tie-ins Not Started 05/10/27 05/13/27 5.0 5.0
0%
185.0
RPL09.INT.DHB.02580 RPL09.Interior.DHB - OFE - Control Fault Domain 4 (LV Side Aisle) Control Fault Domain 4 Not Started 05/10/27 05/13/27 5.0 5.0
0%
155.0
RPL09.INT.SSB.01320 RPL09.Interior.SSB - BoW - Hang Drywall Balance of Walls and OverHead Not Started 05/10/27 05/18/27 8.8 8.8
0%
188.8
RPL09.INT.SSB.06080 RPL09.Interior.SSB LO #16 - Tape Finish Paint Leave Out Wall #16 (SSB - North of Loading Dock) Not Started 05/10/27 05/14/27 6.2 6.2
0%
161.2
RPL09.INT.SSB.06720 RPL09.Interior.SSB - Final Finishes & Fixtures - Install Tile/ Grout Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) Not Started 05/10/27 05/21/27 12.5 12.5
0%
303.8
RPL09.INT.SSB.06760 RPL09.Interior.SSB - Final Finishes & Fixtures - Install Fixtures, Partitions & Accessories Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) Not Started 05/10/27 05/18/27 8.8 8.8
0%
295.0
RPL.09.D.93720.XG RMUs/MV Skids Set (Ready for Longhorn Pulls) - DHB Give Milestones (XREFs) Not Started 05/11/27 05/11/27 0.0 0.0
0%
448.8
RPL.09.D.93960.XG Ready for MV Cable Pull DH B (MVs - Qty 10)* Give Milestones (XREFs) Not Started 05/11/27 05/11/27 0.0 0.0
0%
448.8
RPL09.INT.DHB.01610 RPL09.Interior.DHB - Control Fault Domain 3 - Install LV Side Aisle Cable Tray LV Side Tie-ins Not Started 05/11/27 05/14/27 5.0 5.0
0%
245.0
RPL09.INT.ENDC.06960 RPL09.Interior.Center-Corridor - Final Finishes & Fixtures - Casework Restrooms Not Started 05/11/27 05/19/27 8.8 8.8
0%
268.8
RPL09.INT.SSBC.4520 RPL09.Interior.SSBC LO #07 - Plumbing Trim Out Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 05/11/27 05/12/27 2.5 2.5
0%
181.2
RPL09.INT.SSBC.4600 RPL09.Interior.SSBC LO #07 - Install Asset Tags Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 05/11/27 05/11/27 1.2 1.2
0%
181.2
RPL09.EY.DHB.01250 RPL09.EY.DHB - Install Electrical Tie-ins (include penetration detail) Tie-ins Not Started 05/12/27 05/25/27 12.5 12.5
0%
82.5
RPL09.EY.DHB.01260 RPL09.EY.DHB - Tie-ins - WBS Summary Tie-ins Not Started 05/12/27 07/06/27 47.5 47.5
0%
212.5
RPL09.EY.DHB.01520 RPL09.EY.DHB - Install Generator including Tie-ins (#1 of Qty 2) OFE Not Started 05/12/27 05/18/27 6.2 6.2
0%
117.5
RPL09.INT.DHA.01114 RPL09.Interior.DHA - MES Skids - BMS Tie-Ins ( 2 per day) DHA - MES Skids Not Started 05/12/27 06/09/27 25.0 25.0
0%
127.5
RPL09.INT.DHB.01660 RPL09.Interior.DHB - Tie-ins - Control Fault Domain 4 - WBS Summary Control Fault Domain 4 Not Started 05/12/27 08/18/27 86.2 86.2
0%
167.5
RPL09.INT.DHB.02760 RPL09.Interior.DHB - Control Fault Domain 4 - Install Duct (LV Side) LV Side Tie-ins Not Started 05/12/27 05/17/27 5.0 5.0
0%
170.0
RPL09.INT.DHC.01060 RPL09.Interior.DHC - OFE - LV Skids and TopHat - Set / Place / Anchor OFE/MOFE & CFCI Not Started 05/12/27 05/28/27 16.2 16.2
0%
141.2
RPL09.INT.DHC.01070 RPL09.Interior.DHC - OFE - MES Skids - Set / Place / Anchor OFE/MOFE & CFCI Not Started 05/12/27 05/28/27 16.2 16.2
0%
141.2
RPL09.INT.DHC.01080 RPL09.Interior.DHC - OFE - WBS Summary OFE/MOFE & CFCI Not Started 05/12/27 10/12/27 133.8 133.8
0%
121.2
RPL09.INT.DHC.02210 RPL09.Interior.DHC - Priority - Install Temp Doors Frame Hardware OverHead Not Started 05/12/27 05/14/27 3.8 3.8
0%
402.5
RPL09.INT.ENDC.1280 RPL09.Interior.End-Corridor - BoW - Install Fire Life Safety Lowside OH and In-wall Balance of Walls & Overhead Not Started 05/12/27 05/20/27 8.8 8.8
0%
238.8
RPL09.INT.SSB.01300 RPL09.Interior.SSB - Loading Dock and Storage - Install Fire Life Safety Loading Dock and Storage Not Started 05/12/27 05/20/27 8.8 8.8
0%
208.8
RPL09.INT.SSBC.01230 RPL09.Interior.SSB-Corridor - Install Remaining Refrigerant Line Fit out Not Started 05/12/27 05/18/27 6.2 6.2
0%
218.8
RPL09.INT.SSBC.4540 RPL09.Interior.SSBC LO #07 - Fire Life Safety Trim Out Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 05/12/27 05/12/27 1.2 1.2
0%
181.2
RPL09.INT.SSBC.4620 RPL09.Interior.SSBC LO #07 - Install Door (Verify with Trades before installation) Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 05/12/27 05/12/27 1.2 1.2
0%
181.2
RPL09.SKN.S.LO.01100 RPL09.SKIN.LO#17 - Close Exterior Leave Out #17 CC (South) WBS Summary Build back Exterior Leave Out Walls #17 (CC - South) Not Started 05/12/27 06/04/27 21.2 21.2
0%
150.0
RPL09.SKN.S.LO.03020 RPL09.SKIN.LO#17 - Pour back Stemwall Build back Exterior Leave Out Walls #17 (CC - South) Not Started 05/12/27 05/13/27 2.5 2.5
0%
150.0
RPL09.INT.CTRC.01670 RPL09.Interior.Center-Corridor - MOFE - Ancillary Skids Qty2 (DH A) OFE/MOFE & CFCI Not Started 05/13/27 05/26/27 12.5 12.5
0%
186.2
RPL09.INT.CTRC.01690 RPL09.Interior.Center-Corridor - MOFE - Ancillary Skids Qty2 (DH B) OFE/MOFE & CFCI Not Started 05/13/27 05/26/27 12.5 12.5
0%
195.0
RPL09.INT.CTRC.1960 RPL09.Interior.Center-Corridor - BoW - Install Horizontal Steel Supports for Cable Tray (IFP Add) Balance of Walls & Overhead Not Started 05/13/27 05/20/27 7.5 7.5
0%
185.0
RPL09.INT.DHB.02480 RPL09.Interior.DHB - OFE - Control Fault Domain 2 (HAC) Control Fault Domain 2 Not Started 05/13/27 05/26/27 12.5 12.5
0%
106.2
RPL09.INT.DHD.01093 RPL09.Interior.DHD - LV Skids and TopHat - Top Hat Busway DHD - LV Skids and TopHat Not Started 05/13/27 05/28/27 15.0 15.0
0%
277.5
RPL09.INT.DHD.01112 RPL09.Interior.DHD - MES Skids - Piping Tie-Ins & Inspections DHD - MES Skids Not Started 05/13/27 06/04/27 20.0 20.0
0%
265.0
RPL09.INT.SBC.03500 RPL09.Interior.SSB-Corridor - BoW - MEPF Hard Lid Rough-In/ Close of Inspection Balance of Walls & Overhead Not Started 05/13/27 05/21/27 8.8 8.8
0%
148.8
RPL09.INT.SBC.03520 RPL09.Interior.SSB-Corridor - BoW - Install Blocking/Steel support Assembly for Metal Canopy Balance of Walls & Overhead Not Started 05/13/27 05/19/27 6.2 6.2
0%
138.8
RPL09.INT.SSBC.3660 RPL09.Interior.SSBC LO #06 - Mechanical L2 Checklist Completion Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 05/13/27 05/26/27 12.5 12.5
0%
187.5
RPL09.INT.SSBC.4640 RPL09.Interior.SSBC LO #07 - Electrical L2 Checklist Completion Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 05/13/27 05/26/27 12.5 12.5
0%
181.2
RPL09.CON.WP2.06800 RPL09.Conn - GSIDF/DH C2 - WBS Summary INT IDF OFE/MOFE - GSIDF9C2 Not Started 05/14/27 06/08/27 21.2 21.2
0%
425.0
RPL09.CON.WP2.06820 RPL09.Conn - GSIDF/DH C2 - Install Infrastructure (Racks, Waterfalls etc.) Infrastructure Not Started 05/14/27 05/20/27 6.2 6.2
0%
378.8
RPL09.EY.DHB.01280 RPL09.EY.DHB - Install BMS/EPMS Tie-ins Tie-ins Not Started 05/14/27 05/27/27 12.5 12.5
0%
82.5
RPL09.INT.CTRC.1340 RPL09.Interior.Center-Corridor - BoW - Install VAV's/Duct Branches Balance of Walls & Overhead Not Started 05/14/27 05/20/27 6.2 6.2
0%
196.2
RPL09.INT.CTRC.1440 RPL09.Interior.Center-Corridor - BoW - Mechanical Tie-In Balance of Walls & Overhead Not Started 05/14/27 05/20/27 6.2 6.2
0%
117.5
RPL09.INT.DHA.01115 RPL09.Interior.DHA - MES Skids - EPMS Tie-Ins ( 2 per day) DHA - MES Skids Not Started 05/14/27 06/11/27 25.0 25.0
0%
127.5
RPL09.INT.DHB.01300 RPL09.Interior.DHB - Control Fault Domain 1 - Install Mechanical Side Aisle Cable Tray Remaining Tie-ins post Mech Side Aisle install Not Started 05/14/27 06/11/27 25.0 25.0
0%
102.5
RPL09.INT.DHB.01720 RPL09.Interior.DHB - OFE - Control Fault Domain 5 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary Control Fault Domain 5 Not Started 05/14/27 07/14/27 52.5 52.5
0%
131.2
RPL09.INT.DHB.01740 RPL09.Interior.DHB - Control Fault Domain 4 - Install LV Side Aisle HAC Busway LV Side Tie-ins Not Started 05/14/27 05/19/27 5.0 5.0
0%
200.0
RPL09.INT.DHB.02640 RPL09.Interior.DHB - OFE - Control Fault Domain 5 (LV Side Aisle) Control Fault Domain 5 Not Started 05/14/27 05/19/27 5.0 5.0
0%
165.0
RPL09.INT.DHC.01090 RPL09.Interior.DHC - LV Skids and TopHat Tie-ins (LOE) DHC - LV Skids and TopHat Not Started 05/14/27 06/14/27 26.2 26.2
0%
272.5
RPL09.INT.DHC.01091 RPL09.Interior.DHC - LV Skids and TopHat - Set & Anchor Interconnects DHC - LV Skids and TopHat Not Started 05/14/27 06/02/27 16.2 16.2
0%
272.5
RPL09.INT.DHC.01100 RPL09.Interior.DHC - Tie-ins - WBS Summary Tie-Ins Not Started 05/14/27 12/06/27 176.2 176.2
0%
233.8
RPL09.INT.ENDC.01190 RPL09.Interior.End-Corridor - OFE - DHD (1x GS.IDF) D2 OFE/MOFE & CFCI Not Started 05/14/27 05/20/27 6.2 6.2
0%
232.5
RPL09.SKN.S.LO.03040 RPL09.SKIN.LO#17 - Cure Stemwall Build back Exterior Leave Out Walls #17 (CC - South) Not Started 05/14/27 05/24/27 8.8 8.8
0%
150.0
RPL09.INT.CTRC.1420 RPL09.Interior.Center-Corridor - BoW - Install Electrical - Lighitng Inverter Room (XX.S2.XX) Balance of Walls & Overhead Not Started 05/17/27 05/25/27 8.8 8.8
0%
183.8
RPL09.INT.DHB.01750 RPL09.Interior.DHB - Control Fault Domain 4 - Install LV Side Aisle Cable Tray LV Side Tie-ins Not Started 05/17/27 05/20/27 5.0 5.0
0%
245.0
RPL09.INT.DHC.02170 RPL09.Interior.DHC - Priority - Install Security OverHead Not Started 05/17/27 05/18/27 2.5 2.5
0%
402.5
RPL09.INT.DHD.01113 RPL09.Interior.DHD - MES Skids - CDU Tie-Ins DHD - MES Skids Not Started 05/17/27 06/08/27 20.0 20.0
0%
265.0
RPL09.INT.SSB.01440 RPL09.Interior.SSB - Loading Dock and Storage - Install Store Front Frames Loading Dock and Storage Not Started 05/17/27 05/25/27 8.8 8.8
0%
215.0
RPL09.INT.SSB.06100 RPL09.Interior.SSB LO #16 - Install Mechanical Piping/ Refrigerant Lowside OH Leave Out Wall #16 (SSB - North of Loading Dock) Not Started 05/17/27 05/21/27 6.2 6.2
0%
163.8
RPL09.INT.SSB.06120 RPL09.Interior.SSB LO #16 - Install Electrical Lowside OH Leave Out Wall #16 (SSB - North of Loading Dock) Not Started 05/17/27 05/25/27 8.8 8.8
0%
165.0
RPL09.INT.SSB.06140 RPL09.Interior.SSB LO #16 - Install Plumbing Lowside OH Leave Out Wall #16 (SSB - North of Loading Dock) Not Started 05/17/27 05/25/27 8.8 8.8
0%
161.2
RPL09.INT.SSB.06160 RPL09.Interior.SSB LO #16 - Install Fire Life Safety Lowside OH Leave Out Wall #16 (SSB - North of Loading Dock) Not Started 05/17/27 05/19/27 3.8 3.8
0%
166.2
RPL09.INT.SSB.06180 RPL09.Interior.SSB LO #16 - Install Security Lowside OH Leave Out Wall #16 (SSB - North of Loading Dock) Not Started 05/17/27 05/20/27 5.0 5.0
0%
165.0
RPL09.INT.SSB.06200 RPL09.Interior.SSB LO #16 - Install Controls / EPMS / BMS OH Leave Out Wall #16 (SSB - North of Loading Dock) Not Started 05/17/27 05/19/27 3.8 3.8
0%
166.2
RPL09.INT.SSB.06220 RPL09.Interior.SSB LO #16 - Fire Safing OH Leave Out Wall #16 (SSB - North of Loading Dock) Not Started 05/17/27 05/21/27 6.2 6.2
0%
163.8
ICM.B9.1805 [SSDCB4] Delivery of Substation MSG Alpha (First Delivery) NOT DPR SCOPE Construction Not Started 05/18/27 05/18/27 0.0 0.0
0%
442.5
RPL.09.D.93350.XR Pull and Term mCUP Skids - RPL09 Receive Milestones (XREFs) Not Started 05/18/27 05/18/27 0.0 0.0
0%
97.5
RPL.09.D.93850.XR 100MW Cx Temp Power to MV Skids RPL09 mCUPs Available Receive Milestones (XREFs) Not Started 05/18/27 05/18/27 0.0 0.0
0%
97.5