Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL09 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:12 PM · 5201 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
0
Completed
0
In Progress
0
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL09.INT.DHB.01800 RPL09.Interior.DHB - Tie-ins - Control Fault Domain 5 - WBS Summary Control Fault Domain 5 Not Started 05/18/27 09/03/27 96.2 96.2
0%
137.5
RPL09.INT.DHB.02500 RPL09.Interior.DHB - OFE - Control Fault Domain 2 (Mech Side Aisle) Control Fault Domain 2 Not Started 05/18/27 05/27/27 10.0 10.0
0%
106.2
RPL09.INT.DHB.02780 RPL09.Interior.DHB - Control Fault Domain 5 - Install Duct (LV Side) LV Side Tie-ins Not Started 05/18/27 05/21/27 5.0 5.0
0%
183.8
RPL09.INT.ENDC.01240 RPL09.Interior.End-Corridor - Tape Finish Paint Fit out Not Started 05/18/27 05/20/27 3.8 3.8
0%
256.2
RPL09.INT.SSB.14220 RPL09.Interior.SSB LO #01 to #05 - Fire Safing OH and In-wall Finishes Not Started 05/18/27 05/18/27 1.2 1.2
0%
168.8
RPL09.EY.DHC.01220 RPL09.EY.DHC - Install MV, RMUs & Electrical Panels (Qty 8) OFE Not Started 05/19/27 06/16/27 25.0 25.0
0%
218.8
RPL09.EY.DHC.01230 RPL09.EY.DHC - OFE - MV - WBS Summary OFE Not Started 05/19/27 11/10/27 153.8 153.8
0%
211.2
RPL09.INT.DHA.01120 RPL09.Interior.DHA - OFE - Control Fault Domain 1 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary Control Fault Domain 1 Not Started 05/19/27 06/11/27 21.2 21.2
0%
80.0
RPL09.INT.DHA.03480 RPL09.Interior.DHA - OFE - Control Fault Domain 1 (LV Side Aisle) Control Fault Domain 1 Not Started 05/19/27 05/25/27 6.2 6.2
0%
80.0
RPL09.INT.DHC.01110 RPL09.Interior.DHC - MES Skids Tie-ins (LOE) DHC - MES Skids Not Started 05/19/27 06/28/27 35.0 35.0
0%
252.5
RPL09.INT.DHC.01111 RPL09.Interior.DHC - MES Skids - Set & Anchor Interconnects DHC - MES Skids Not Started 05/19/27 06/10/27 20.0 20.0
0%
252.5
RPL09.INT.DHC.02190 RPL09.Interior.DHC - Priority - Install Controls / EPMS / BMS OverHead Not Started 05/19/27 05/21/27 3.8 3.8
0%
402.5
RPL09.INT.DHD.01114 RPL09.Interior.DHD - MES Skids - BMS Tie-Ins DHD - MES Skids Not Started 05/19/27 06/10/27 20.0 20.0
0%
265.0
RPL09.INT.SSB.01340 RPL09.Interior.SSB - BoW - Tape Finish Paint Balance of Walls and OverHead Not Started 05/19/27 05/21/27 3.8 3.8
0%
188.8
RPL09.INT.SSB.02480 RPL09.Interior.SSB - Final Finishes & Fixtures - MEP Trims Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) Not Started 05/19/27 05/27/27 8.8 8.8
0%
295.0
RPL09.INT.SSB.14400 RPL09.Interior.SSB LO #01 to #05 - Tape Finish Paint Finishes Not Started 05/19/27 05/21/27 3.8 3.8
0%
168.8
RPL09.INT.SSBC.01410 RPL09.Interior.SSB-Corridor - Battery Connection Fit out Not Started 05/19/27 05/25/27 6.2 6.2
0%
188.8
RPL09.INT.DHA.03500 RPL09.Interior.DHA - OFE - Control Fault Domain 1 (HAC) Control Fault Domain 1 Not Started 05/20/27 06/10/27 18.8 18.8
0%
80.0
RPL09.INT.DHB.01870 RPL09.Interior.DHB - Control Fault Domain 5 - Install LV Side Aisle HAC Busway LV Side Tie-ins Not Started 05/20/27 05/25/27 5.0 5.0
0%
215.0
RPL09.INT.DHC.01092 RPL09.Interior.DHC - LV Skids and TopHat - Maintenance and Reserve Busways DHC - LV Skids and TopHat Not Started 05/20/27 06/07/27 15.0 15.0
0%
272.5
RPL09.INT.ENDC.07020 RPL09.Interior.Center-Corridor - Final Finishes & Fixtures - Fixture Install (Lights) Restrooms Not Started 05/20/27 05/28/27 8.8 8.8
0%
296.2
RPL09.INT.ENDC.07120 RPL09.Interior.Center-Corridor - Final Finishes & Fixtures - Framing RO Verification, Tile Finish & ADA Verification (P Restrooms Not Started 05/20/27 05/26/27 6.2 6.2
0%
268.8
RPL09.INT.ENDC.1300 RPL09.Interior.End-Corridor - BoW - Install Plumbing Lowside OH and In-wall Balance of Walls & Overhead Not Started 05/20/27 05/28/27 8.8 8.8
0%
218.8
RPL09.INT.SBC.05820 RPL09.Interior.SSB-Corridor - BoW - Install Backing (Both side of Corridor Wall) Balance of Walls & Overhead Not Started 05/20/27 05/26/27 6.2 6.2
0%
138.8
RPL09.INT.SSBC.4660 RPL09.Interior.SSBC LO #07 - Mechanical L2 Checklist Completion Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 05/20/27 06/03/27 12.5 12.5
0%
181.2
RPL09.CON.WP2.06600 RPL09.Conn - GSIDF/DH D2 - WBS Summary INT IDF OFE/MOFE - GSIDF9D2 Not Started 05/21/27 06/15/27 21.2 21.2
0%
418.8
RPL09.CON.WP2.06620 RPL09.Conn - GSIDF/DH D2 - Install Infrastructure (Racks, Waterfalls etc.) Infrastructure Not Started 05/21/27 05/27/27 6.2 6.2
0%
361.2
RPL09.CON.WP2.06840 RPL09.Conn - GSIDF/DH C2 - Install Cabling (Pull, Splice & terminate) Cabling Not Started 05/21/27 05/28/27 7.5 7.5
0%
428.8
RPL09.CON.WP2.06860 RPL09.Conn - GSIDF/DH C2 - Install Copper, WAPs, Security Camera & Access Control Cabling Not Started 05/21/27 06/08/27 15.0 15.0
0%
378.8
RPL09.INT.CTRC.01160 RPL09.Interior.Center-Corridor (N) - Install Fitout (Spoke Parts, Tech, SCR etc.) - WBS Summary Fit out (North) Not Started 05/21/27 10/27/27 138.8 138.8
0%
133.8
RPL09.INT.CTRC.01380 RPL09.Interior.Center-Corridor (N) - Install Cable Tray - North (Early) Fit out (North) Not Started 05/21/27 05/27/27 6.2 6.2
0%
223.8
RPL09.INT.CTRC.01910 RPL09.Interior.Center-Corridor (S) - Install Cable Tray- South (Early) Fit out (South) Not Started 05/21/27 05/27/27 6.2 6.2
0%
218.8
RPL09.INT.CTRC.02030 RPL09.Interior.Center-Corridor (S) - Install Fitout (Spoke Parts, Tech, SCR etc.) - WBS Summary Fit out (South) Not Started 05/21/27 10/19/27 131.2 131.2
0%
97.5
RPL09.INT.CTRC.1380 RPL09.Interior.Center-Corridor - BoW - Install Controls / EPMS / BMS OH and In-wall Balance of Walls & Overhead Not Started 05/21/27 05/27/27 6.2 6.2
0%
196.2
RPL09.INT.CTRC.1460 RPL09.Interior.Center-Corridor - BoW - Frame Hard Lid Balance of Walls & Overhead Not Started 05/21/27 05/27/27 6.2 6.2
0%
117.5
RPL09.INT.DHA.01130 RPL09.Interior.DHA - Control Fault Domain 1 - Install Duct (LV Side) LV Side Tie-ins Not Started 05/21/27 05/27/27 6.2 6.2
0%
95.0
RPL09.INT.DHA.01160 RPL09.Interior.DHA - Tie-ins - Control Fault Domain 1 - WBS Summary Control Fault Domain 1 Not Started 05/21/27 08/04/27 65.0 65.0
0%
80.0
RPL09.INT.DHB.01340 RPL09.Interior.DHB - Control Fault Domain 1 - Install copper from GS.IDF to BMS and EPMS panels Remaining Tie-ins post Mech Side Aisle install Not Started 05/21/27 06/18/27 25.0 25.0
0%
102.5
RPL09.INT.DHB.01890 RPL09.Interior.DHB - Control Fault Domain 5 - Install LV Side Aisle Cable Tray LV Side Tie-ins Not Started 05/21/27 05/26/27 5.0 5.0
0%
225.0
RPL09.INT.DHD.01115 RPL09.Interior.DHD - MES Skids - EPMS Tie-In DHD - MES Skids Not Started 05/21/27 06/14/27 20.0 20.0
0%
265.0
RPL09.INT.ENDC.01250 RPL09.Interior.End-Corridor - Set Equipment / Interior ?? Fit out Not Started 05/21/27 05/27/27 6.2 6.2
0%
256.2
RPL09.INT.ENDC.01270 RPL09.Interior.End-Corridor - Install Tile Fit out Not Started 05/21/27 06/01/27 8.8 8.8
0%
262.5
RPL09.INT.ENDC.01420 RPL09.Interior.End-Corridor - Install Remaining Refrigerant Line Fit out Not Started 05/21/27 05/27/27 6.2 6.2
0%
311.2
RPL09.INT.ENDC.1320 RPL09.Interior.End-Corridor - BoW - Install Security Lowside OH and In-wall Balance of Walls & Overhead Not Started 05/21/27 06/01/27 8.8 8.8
0%
301.2
RPL09.INT.SSB.01330 RPL09.Interior.SSB - Loading Dock and Storage - Hang Drywall Loading Dock and Storage Not Started 05/21/27 06/04/27 12.5 12.5
0%
208.8
RPL09.INT.SSBC.01400 RPL09.Interior.SSB-Corridor - Install Grounding Fit out Not Started 05/21/27 05/25/27 3.8 3.8
0%
195.0
RPL09.INT.DHD.01120 RPL09.Interior.DHD - OFE - Control Fault Domain 1 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary Control Fault Domain 1 Not Started 05/24/27 08/02/27 61.2 61.2
0%
146.2
RPL09.INT.DHD.02270 RPL09.Interior.DHD - OFE - Control Fault Domain 1 (LV Side Aisle) Control Fault Domain 1 Not Started 05/24/27 05/28/27 6.2 6.2
0%
178.8
RPL09.INT.SSB.01280 RPL09.Interior.SSB - BoW - Duct Drops / Trim out Balance of Walls and OverHead Not Started 05/24/27 05/28/27 6.2 6.2
0%
252.5
RPL09.INT.SSB.01360 RPL09.Interior.SSB - BoW - Electrical Trim Out Balance of Walls and OverHead Not Started 05/24/27 06/02/27 8.8 8.8
0%
257.5
RPL09.INT.SSB.01380 RPL09.Interior.SSB - BoW - Security Trim Out Balance of Walls and OverHead Not Started 05/24/27 06/02/27 8.8 8.8
0%
257.5
RPL09.INT.SSB.01840 RPL09.Interior.SSB - Install Split Systems/Humidifiers OFE/MOFE & CFCI Not Started 05/24/27 05/28/27 6.2 6.2
0%
246.2
RPL09.INT.SSB.01860 RPL09.Interior.SSB - Final Finishes & Fixtures - Flooring Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) Not Started 05/24/27 06/02/27 8.8 8.8
0%
303.8
RPL09.INT.SSB.02520 RPL09.Interior.SSB - BoW - ACT - Set Wall Angle & Shoot Ceiling Wire Balance of Walls and OverHead Not Started 05/24/27 06/02/27 8.8 8.8
0%
188.8
RPL09.INT.SSB.14460 RPL09.Interior.SSB LO #01 to #05 - Mechanical Trim out Finishes Not Started 05/24/27 05/28/27 6.2 6.2
0%
183.8
RPL09.INT.SSB.14480 RPL09.Interior.SSB LO #01 to #05 - Final Paint Finishes Not Started 05/24/27 06/02/27 8.8 8.8
0%
208.8
RPL09.INT.SSB.14560 RPL09.Interior.SSB LO #01 to #05 - Install Remaining Lights Finishes Not Started 05/24/27 06/07/27 12.5 12.5
0%
168.8
RPL09.INT.SSB.14580 RPL09.Interior.SSB LO #01 to #05 - Install Flooring Tiles/Resinous Flooring in specific rooms Finishes Not Started 05/24/27 06/02/27 8.8 8.8
0%
190.0
RPL09.INT.SSB.14720 RPL09.Interior.SSB LO #01 to #05 - Fire Safing / Wall Finishes Finishes Not Started 05/24/27 05/28/27 6.2 6.2
0%
200.0
RPL09.INT.SSB.14740 RPL09.Interior.SSB LO #01 to #05 - Install Split Systems Finishes Not Started 05/24/27 05/26/27 3.8 3.8
0%
188.8
RPL.09.D.93710.XG RMUs/MV Skids Set (Ready for Longhorn Pulls) - DHA Give Milestones (XREFs) Not Started 05/25/27 05/25/27 0.0 0.0
0%
436.2
RPL.09.D.94000.XG Ready for MV Cable Pull DH A (MVs - Qty 10)* Give Milestones (XREFs) Not Started 05/25/27 05/25/27 0.0 0.0
0%
436.2
RPL09.INT.DHA.01220 RPL09.Interior.DHA - Control Fault Domain 1 - Install LV Side Aisle HAC Busway LV Side Tie-ins Not Started 05/25/27 06/01/27 6.2 6.2
0%
103.8
RPL09.INT.DHA.03520 RPL09.Interior.DHA - OFE - Control Fault Domain 1 (Mech Side Aisle) Control Fault Domain 1 Not Started 05/25/27 06/11/27 16.2 16.2
0%
80.0
RPL09.SKN.S.LO.03060 RPL09.SKIN.LO#17 - Stemwall Water Proofing Build back Exterior Leave Out Walls #17 (CC - South) Not Started 05/25/27 05/26/27 2.5 2.5
0%
150.0
RPL.09.D.93210.XR 500kva Temp Power Skids Energized (First 10 MW or Gen) Receive Milestones (XREFs) Not Started 05/26/27 05/26/27 0.0 0.0
0%
97.5
RPL.09.D.93320.XR Pull and Term MV Skids - RPL09 DHB Receive Milestones (XREFs) Not Started 05/26/27 05/26/27 0.0 0.0
0%
97.5
RPL.09.D.93410.XR SS Power to RPL09 MSG 1B Numeric (Cx Temp) Receive Milestones (XREFs) Not Started 05/26/27 05/26/27 0.0 0.0
0%
97.5
RPL.09.D.93510.XR Substation Perm Power Cutover - RPL09 DH & mCUPs Receive Milestones (XREFs) Not Started 05/26/27 05/26/27 0.0 0.0
0%
97.5
RPL.09.D.93820.XR 100MW Cx Temp Power to MV Skids RPL09 DHB Available Receive Milestones (XREFs) Not Started 05/26/27 05/26/27 0.0 0.0
0%
97.5
RPL09.EY.DHA.01250 RPL09.EY.DHA - Install Electrical Tie-ins (include penetration detail) Tie-ins Not Started 05/26/27 06/09/27 12.5 12.5
0%
88.8
RPL09.EY.DHA.01260 RPL09.EY.DHA - Tie-ins - WBS Summary Tie-ins Not Started 05/26/27 08/03/27 60.0 60.0
0%
198.8
RPL09.INT.CTRC.8860 RPL09.Interior.Center-Corridor - BoW - Electrical Tie-In Balance of Walls & Overhead Not Started 05/26/27 06/02/27 6.2 6.2
0%
192.5
RPL09.INT.DHA.01210 RPL09.Interior.DHA - Control Fault Domain 1 - Install LV Side Aisle Cable Tray LV Side Tie-ins Not Started 05/26/27 06/02/27 6.2 6.2
0%
103.8
RPL09.INT.DHA.01230 RPL09.Interior.DHA - OFE - Control Fault Domain 2 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary Control Fault Domain 2 Not Started 05/26/27 06/25/27 27.5 27.5
0%
92.5
RPL09.INT.DHA.03540 RPL09.Interior.DHA - OFE - Control Fault Domain 2 (LV Side Aisle) Control Fault Domain 2 Not Started 05/26/27 06/01/27 5.0 5.0
0%
102.5
RPL09.INT.DHD.01130 RPL09.Interior.DHD - Control Fault Domain 1 - Install Duct (LV Side) LV Side Tie-ins Not Started 05/26/27 06/02/27 6.2 6.2
0%
230.0
RPL09.INT.DHD.01160 RPL09.Interior.DHD - Tie-ins - Control Fault Domain 1 - WBS Summary Control Fault Domain 1 Not Started 05/26/27 09/21/27 102.5 102.5
0%
177.5
RPL09.INT.SSB.01390 RPL09.Interior.SSB - BoW - Plumbing Trim Out Balance of Walls and OverHead Not Started 05/26/27 06/04/27 8.8 8.8
0%
257.5
RPL09.INT.SSB.03120 RPL09.Interior.SSB - Loading Dock and Storage - Install Store Front Glazing Loading Dock and Storage Not Started 05/26/27 05/27/27 2.5 2.5
0%
215.0
RPL09.INT.SSB.06240 RPL09.Interior.SSB LO #16 - Install Remaining Lights Leave Out Wall #16 (SSB - North of Loading Dock) Not Started 05/26/27 06/04/27 8.8 8.8
0%
161.2
RPL09.INT.CTRC.01260 RPL09.Interior.Center-Corridor (N) - Remaining Electrical OFE Tie In Fit out (North) Not Started 05/27/27 06/03/27 6.2 6.2
0%
195.0
RPL09.INT.CTRC.01850 RPL09.Interior.Center-Corridor (S) - Remaining Electrical OFE Tie In Fit out (South) Not Started 05/27/27 06/03/27 6.2 6.2
0%
186.2
RPL09.INT.DHB.02540 RPL09.Interior.DHB - OFE - Control Fault Domain 3 (HAC) Control Fault Domain 3 Not Started 05/27/27 06/10/27 12.5 12.5
0%
120.0
RPL09.INT.DHC.01093 RPL09.Interior.DHC - LV Skids and TopHat - Top Hat Busway DHC - LV Skids and TopHat Not Started 05/27/27 06/14/27 15.0 15.0
0%
272.5
RPL09.INT.DHC.01112 RPL09.Interior.DHC - MES Skids - Piping Tie-Ins & Inspections DHC - MES Skids Not Started 05/27/27 06/18/27 20.0 20.0
0%
252.5
RPL09.INT.ENDC.07100 RPL09.Interior.Center-Corridor - Final Finishes & Fixtures - Install Tile/ Grout Restrooms Not Started 05/27/27 06/10/27 12.5 12.5
0%
277.5
RPL09.INT.ENDC.07140 RPL09.Interior.Center-Corridor - Final Finishes & Fixtures - Install Fixtures, Partitions & Accessories Restrooms Not Started 05/27/27 06/07/27 8.8 8.8
0%
268.8
RPL09.INT.SBC.05840 RPL09.Interior.SSB-Corridor - BoW - QC - Backings/Walls (Both side of Corridor Wall) Balance of Walls & Overhead Not Started 05/27/27 06/03/27 6.2 6.2
0%
138.8
RPL09.INT.SSB.14200 RPL09.Interior.SSB LO #01 to #05 - Mechanical Tie-In Finishes Not Started 05/27/27 05/27/27 1.2 1.2
0%
188.8
RPL09.INT.SSB.14300 RPL09.Interior.SSB LO #01 to #05 - Electrical Tie-In Finishes Not Started 05/27/27 06/03/27 6.2 6.2
0%
188.8
RPL09.INT.SSB.14760 RPL09.Interior.SSB LO #01 to #05 - Install Remaining Refrigerant Line Finishes Not Started 05/27/27 06/03/27 6.2 6.2
0%
195.0
RPL09.SKN.S.LO.03080 RPL09.SKIN.LO#17 - Install IMP Flashing Build back Exterior Leave Out Walls #17 (CC - South) Not Started 05/27/27 05/28/27 2.5 2.5
0%
150.0
DCC.B9.3035 [SSDCB4] Production Gear Delivered [DHB] Front End (SSW &FSW) Connectivity Not Started 05/28/27 05/28/27 0.0 0.0
0%
242.5
RPL07.CON.WP3B.0900 RPL09.Conn WP3B Pull/Install/Test Universal Fabric EF1(South)<>EF2 (North) EF1 <> EF2 Not Started 05/28/27 06/04/27 6.2 6.2
0%
248.8
RPL09.CON.WP2.06640 RPL09.Conn - GSIDF/DH D2 - Install Cabling (Pull, Splice & terminate) Cabling Not Started 05/28/27 06/07/27 7.5 7.5
0%
422.5
RPL09.CON.WP2.06660 RPL09.Conn - GSIDF/DH D2 - Install Copper, WAPs, Security Camera & Access Control Cabling Not Started 05/28/27 06/15/27 15.0 15.0
0%
361.2
RPL09.EY.DHA.01280 RPL09.EY.DHA - Install BMS/EPMS Tie-ins Tie-ins Not Started 05/28/27 06/11/27 12.5 12.5
0%
88.8
RPL09.EY.DHB.01290 RPL09.EY.DHB - Install Sleeves MEPL Hardscape and Landscape Not Started 05/28/27 06/04/27 6.2 6.2
0%
240.0
RPL09.EY.DHB.01300 RPL09.EY.DHB - MV Loop - L2 Checklist Completion Tie-ins Not Started 05/28/27 06/11/27 12.5 12.5
0%
82.5