Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL09 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:12 PM · 5201 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
0
Completed
0
In Progress
0
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL09.INT.DHB.01410 RPL09.Interior.DHB - Control Fault Domain 2 - Set UPS and Panel (2) Remaining Tie-ins post Mech Side Aisle install Not Started 06/09/27 07/07/27 25.0 25.0
0%
106.2
RPL09.INT.DHD.01410 RPL09.Interior.DHD - Control Fault Domain 3 - Install Duct (LV Side) LV Side Tie-ins Not Started 06/09/27 06/14/27 5.0 5.0
0%
262.5
RPL09.INT.DHD.01440 RPL09.Interior.DHD - Tie-ins - Control Fault Domain 3 (including IDF) - WBS Summary Control Fault Domain 3 Not Started 06/09/27 10/19/27 116.2 116.2
0%
206.2
RPL.09.D.70200.XR External Tie from RPL07 - Interior Cx Energization Crew Flow (RPL07.CX.DHC.01140) Internal Milestones (XREFs) Not Started 06/10/27 06/10/27 0.0 0.0
0%
76.2
RPL.09.D.93310.XR Pull and Term MV Skids - RPL09 DHA Receive Milestones (XREFs) Not Started 06/10/27 06/10/27 0.0 0.0
0%
97.5
RPL.09.D.93810.XR 100MW Cx Temp Power to MV Skids RPL09 DHA Available Receive Milestones (XREFs) Not Started 06/10/27 06/10/27 0.0 0.0
0%
97.5
RPL09.INT.DHA.01540 RPL09.Interior.DHA - Control Fault Domain 4 - Install Duct (LV Side) LV Side Tie-ins Not Started 06/10/27 06/15/27 5.0 5.0
0%
156.2
RPL09.INT.DHA.01570 RPL09.Interior.DHA - Tie-ins - Control Fault Domain 4 - WBS Summary Control Fault Domain 4 Not Started 06/10/27 09/16/27 86.2 86.2
0%
156.2
RPL09.INT.SSB.01430 RPL09.Interior.SSB - Loading Dock and Storage - Electrical Trim Out Loading Dock and Storage Not Started 06/10/27 06/18/27 8.8 8.8
0%
208.8
RPL09.INT.SSB.01450 RPL09.Interior.SSB - BoW - Install DAS (Distribution Antenna System) Balance of Walls and OverHead Not Started 06/10/27 06/11/27 2.5 2.5
0%
188.8
RPL09.INT.SSB.01460 RPL09.Interior.SSB - Loading Dock and Storage - Install Lighting and Devices Loading Dock and Storage Not Started 06/10/27 06/18/27 8.8 8.8
0%
226.2
RPL09.INT.SSB.01920 RPL09.Interior.SSB - Loading Dock and Storage - Install Remaining Refrigerant Line Loading Dock and Storage Not Started 06/10/27 06/16/27 6.2 6.2
0%
235.0
RPL09.INT.SSB.02560 RPL09.Interior.SSB - BoW - ACT - Device Tiles Balance of Walls and OverHead Not Started 06/10/27 06/16/27 6.2 6.2
0%
206.2
RPL09.INT.SSB.02580 RPL09.Interior.SSB - BoW - ACT - MEP Devices Balance of Walls and OverHead Not Started 06/10/27 06/16/27 6.2 6.2
0%
206.2
RPL09.OFCI.C.4020 OFCI Delivery: FE Fiber for CFD B.1 (ROJ ) (RVCD ) Data Hall B Not Started 06/10/27 06/16/27 6.2 6.2
0%
207.5
RPL09.CX.MCUP.01010 RPL09.CX.mCup Loop 1 - L3/L4 - MV Skids mCUP 1-4 Not Started 06/11/27 06/18/27 7.5 7.5
0%
76.2
RPL09.EY.DHA.02080 RPL09.EY.DHA - Install reminder of CSUs post LO buildback (Qty1) OFE Not Started 06/11/27 06/14/27 2.5 2.5
0%
223.8
RPL09.INT.CC.9500 RPL09.Interior.CC Ext. LO #17 - Install Electrical Lowside OH and In-wall Exterior Leave Out Wall #17 (CC - South) Not Started 06/11/27 06/14/27 2.5 2.5
0%
142.5
RPL09.INT.DHA.03560 RPL09.Interior.DHA - OFE - Control Fault Domain 2 (HAC) Control Fault Domain 2 Not Started 06/11/27 06/24/27 12.5 12.5
0%
90.0
RPL09.INT.DHB.02600 RPL09.Interior.DHB - OFE - Control Fault Domain 4 (HAC) Control Fault Domain 4 Not Started 06/11/27 06/24/27 12.5 12.5
0%
127.5
RPL09.INT.DHD.01490 RPL09.Interior.DHD - OFE - Control Fault Domain 4 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary Control Fault Domain 4 Not Started 06/11/27 09/14/27 82.5 82.5
0%
138.8
RPL09.INT.DHD.01510 RPL09.Interior.DHD - Control Fault Domain 3 - Install LV Side Aisle HAC Busway LV Side Tie-ins Not Started 06/11/27 06/16/27 5.0 5.0
0%
295.0
RPL09.INT.DHD.02450 RPL09.Interior.DHD - OFE - Control Fault Domain 4 (LV Side Aisle) Control Fault Domain 4 Not Started 06/11/27 06/16/27 5.0 5.0
0%
206.2
RPL09.INT.ENDC.06920 RPL09.Interior.Center-Corridor - Final Finishes & Fixtures - Flooring Restrooms Not Started 06/11/27 06/21/27 8.8 8.8
0%
277.5
RPL09.INT.SSB.06380 RPL09.Interior.SSB LO #16 - Install Flooring Tiles/Resinous Flooring in specific rooms Leave Out Wall #16 (SSB - North of Loading Dock) Not Started 06/11/27 06/15/27 3.8 3.8
0%
161.2
RPL09.INT.SSBC.01420 RPL09.Interior.SSB-Corridor - Final Clean Fit out Not Started 06/11/27 06/16/27 5.0 5.0
0%
181.2
GCD.RPL09.1116 RPL09 EY Ready for Energization Construction Milestones Not Started 06/14/27 06/14/27 0.0 0.0
0%
271.2
GCD.RPL09.5765 RMU Loop Ready for Energization - DHB Loop EY Not Started 06/14/27 06/14/27 0.0 0.0
0%
82.5
RPL09.CON.WP3B.01000 RPL09.Conn WP#3B - ISP - WBS Summary WP#3B ISP - Updated Not Started 06/14/27 12/20/27 163.8 163.8
0%
176.2
RPL09.CON.WP3B.01020 RPL09.Conn WP#3B - ISP DHB - WBS Summary DHB Not Started 06/14/27 10/06/27 101.2 101.2
0%
143.8
RPL09.CON.WP4.01000 RPL09.Conn - DH B Network - WBS Summary DH B Not Started 06/14/27 11/29/27 145.0 145.0
0%
110.0
RPL09.CON.WP4.01020 RPL09.Conn WP4 FENW DHB CFD1 Infrastructure Infrastructure Not Started 06/14/27 07/12/27 25.0 25.0
0%
230.0
RPL09.CX.MCUP.01070 RPL09.CX.mCup Loop 1 - L3/L4 - mCUP - Flush and Fill - DHB & DHA (Phase2) Fill and Flush Not Started 06/14/27 06/18/27 6.2 6.2
0%
127.5
RPL09.EY.DHA.01300 RPL09.EY.DHA - Install Sleeves MEPL Hardscape and Landscape Not Started 06/14/27 06/18/27 6.2 6.2
0%
240.0
RPL09.EY.DHA.01320 RPL09.EY.DHA - Install Hardscape and Landscape - WBS Summary Hardscape and Landscape Not Started 06/14/27 08/16/27 56.2 56.2
0%
365.0
RPL09.EY.DHB.01340 RPL09.EY.DHB - Install Lighting Hardscape and Landscape Not Started 06/14/27 06/25/27 12.5 12.5
0%
240.0
RPL09.INT.CC.9480 RPL09.Interior.CC Ext. LO #17 - Fire Safing OH and In-wall Exterior Leave Out Wall #17 (CC - South) Not Started 06/14/27 06/15/27 2.5 2.5
0%
141.2
RPL09.INT.CTRC.06800 RPL09.Interior.Center-Corridor - Final Finishes & Fixtures - MEP Rough-In Restrooms Not Started 06/14/27 06/18/27 6.2 6.2
0%
117.5
RPL09.INT.CTRC.1540 RPL09.Interior.Center-Corridor - BoW - QC - Backings/Walls Balance of Walls & Overhead Not Started 06/14/27 06/18/27 6.2 6.2
0%
143.8
RPL09.INT.DHA.01630 RPL09.Interior.DHA - OFE - Control Fault Domain 5 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary Control Fault Domain 5 Not Started 06/14/27 08/11/27 52.5 52.5
0%
117.5
RPL09.INT.DHA.01650 RPL09.Interior.DHA - Control Fault Domain 4 - Install LV Side Aisle HAC Busway LV Side Tie-ins Not Started 06/14/27 06/17/27 5.0 5.0
0%
186.2
RPL09.INT.DHA.03720 RPL09.Interior.DHA - OFE - Control Fault Domain 5 (LV Side Aisle) Control Fault Domain 5 Not Started 06/14/27 06/17/27 5.0 5.0
0%
125.0
RPL09.INT.DHB.01290 RPL09.Conn DHB - CFD1 - Set Passive Racks for WP#3b (16) Infrastructure Not Started 06/14/27 06/16/27 3.8 3.8
0%
198.8
RPL09.INT.DHB.02800 RPL09.Conn DHB - CFD1 - Set Passive Racks for PON (16) Infrastructure Not Started 06/14/27 06/16/27 3.8 3.8
0%
213.8
RPL09.INT.DHD.01530 RPL09.Interior.DHD - Control Fault Domain 3 - Install LV Side Aisle Cable Tray LV Side Tie-ins Not Started 06/14/27 06/17/27 5.0 5.0
0%
313.8
RPL09.INT.ENDC.01330 RPL09.Interior.End-Corridor - Electrical Trim Fit out Not Started 06/14/27 06/17/27 5.0 5.0
0%
256.2
RPL09.INT.ENDC.01340 RPL09.Interior.End-Corridor - Install Grounding Fit out Not Started 06/14/27 06/25/27 12.5 12.5
0%
256.2
RPL09.INT.SSB.01490 RPL09.Interior.SSB - BoW - Install Lights (**Work with FTI to coordinate flow map light Install & duration) Balance of Walls and OverHead Not Started 06/14/27 06/25/27 12.5 12.5
0%
188.8
RPL09.INT.SSB.01500 RPL09.Interior.SSB - BoW - Install Bathroom Fixtures Balance of Walls and OverHead Not Started 06/14/27 06/22/27 8.8 8.8
0%
188.8
RPL09.INT.SSB.02400 RPL09.Interior.SSB - Final Finishes & Fixtures - Final Clean Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) Not Started 06/14/27 06/17/27 5.0 5.0
0%
295.0
RPL09.EY.DHA.01450 RPL09.EY.DHA - Install Remaining Electrical Tie-ins Tie-ins Not Started 06/15/27 06/24/27 10.0 10.0
0%
226.2
RPL09.EY.DHB.01450 RPL09.EY.DHB - Install Remaining Remaining Electrical Tie-ins Tie-ins Not Started 06/15/27 06/24/27 10.0 10.0
0%
215.0
RPL09.EY.DHB.01460 RPL09.EY.DHB - Install Remaining Mechanical/refrigerantTie-ins Tie-ins Not Started 06/15/27 06/28/27 12.5 12.5
0%
212.5
RPL09.INT.CC.9580 RPL09.Interior.CC Ext. LO #17 - Install Door Frame Hardware Exterior Leave Out Wall #17 (CC - South) Not Started 06/15/27 06/18/27 5.0 5.0
0%
155.0
RPL09.INT.DHA.01660 RPL09.Interior.DHA - Control Fault Domain 4 - Install LV Side Aisle Cable Tray LV Side Tie-ins Not Started 06/15/27 06/18/27 5.0 5.0
0%
233.8
RPL09.INT.DHD.01550 RPL09.Interior.DHD - Control Fault Domain 4 - Install Duct (LV Side) LV Side Tie-ins Not Started 06/15/27 06/18/27 5.0 5.0
0%
257.5
RPL09.INT.DHD.01580 RPL09.Interior.DHD - Tie-ins - Control Fault Domain 4 - WBS Summary Control Fault Domain 4 Not Started 06/15/27 11/02/27 123.8 123.8
0%
200.0
RPL09.INT.ENDC.01430 RPL09.Interior.End-Corridor - MOFE - Ancillary Skids Qty2 (DH D) OFE/MOFE & CFCI Not Started 06/15/27 06/28/27 12.5 12.5
0%
271.2
RPL09.INT.ENDC.01450 RPL09.Interior.End-Corridor - MOFE - Ancillary Skids Qty2 (DH C) OFE/MOFE & CFCI Not Started 06/15/27 06/28/27 12.5 12.5
0%
271.2
RPL09.INT.ENDC.1460 RPL09.Interior.End-Corridor - BoW - Frame Hard Lid Balance of Walls & Overhead Not Started 06/15/27 06/21/27 6.2 6.2
0%
218.8
RPL09.INT.SBC.03580 RPL09.Interior.SSB-Corridor - BoW - Tape Finish Paint (Both side of Corridor Wall) Balance of Walls & Overhead Not Started 06/15/27 06/17/27 3.8 3.8
0%
138.8
RPL.09.D.93730.XG RMUs/MV Skids Set (Ready for Longhorn Pulls) - DHC Give Milestones (XREFs) Not Started 06/16/27 06/16/27 0.0 0.0
0%
417.5
RPL.09.D.94080.XG Ready for MV Cable Pull DH C (MVs - Qty 8)* Give Milestones (XREFs) Not Started 06/16/27 06/16/27 0.0 0.0
0%
417.5
RPL09.INT.CC.9520 RPL09.Interior.CC Ext. LO #17 - Install Backing Exterior Leave Out Wall #17 (CC - South) Not Started 06/16/27 06/17/27 2.5 2.5
0%
141.2
RPL09.INT.DHA.01170 RPL09.Interior.DHA - Control Fault Domain 1 - Pull BMS from panel to devices Remaining Tie-ins post Mech Side Aisle install Not Started 06/16/27 07/14/27 25.0 25.0
0%
92.5
RPL09.INT.DHA.01180 RPL09.Interior.DHA - Control Fault Domain 1 - Pull EMPS from panel to devices Remaining Tie-ins post Mech Side Aisle install Not Started 06/16/27 07/14/27 25.0 25.0
0%
92.5
RPL09.INT.DHA.01190 RPL09.Interior.DHA - Control Fault Domain 1 - Set UPS and Panel (2) Remaining Tie-ins post Mech Side Aisle install Not Started 06/16/27 07/14/27 25.0 25.0
0%
80.0
RPL09.INT.DHA.01680 RPL09.Interior.DHA - Control Fault Domain 5 - Install Duct (LV Side) LV Side Tie-ins Not Started 06/16/27 06/21/27 5.0 5.0
0%
170.0
RPL09.INT.DHA.01710 RPL09.Interior.DHA - Tie-ins - Control Fault Domain 5 - WBS Summary Control Fault Domain 5 Not Started 06/16/27 10/04/27 96.2 96.2
0%
130.0
RPL09.INT.DHA.03580 RPL09.Interior.DHA - OFE - Control Fault Domain 2 (Mech Side Aisle) Control Fault Domain 2 Not Started 06/16/27 06/25/27 10.0 10.0
0%
92.5
RPL09.INT.DHB.01450 RPL09.Interior.DHB - Control Fault Domain 2 - Install Mechanical Side Aisle Cable Tray Remaining Tie-ins post Mech Side Aisle install Not Started 06/16/27 07/14/27 25.0 25.0
0%
106.2
RPL09.INT.DHB.01490 RPL09.Interior.DHB - Control Fault Domain 3 - Install Duct (MES Side) Remaining Tie-ins post Mech Side Aisle install Not Started 06/16/27 07/14/27 25.0 25.0
0%
120.0
RPL09.INT.DHB.01500 RPL09.Interior.DHB - Control Fault Domain 3 - Install Vesda / FA Remaining Tie-ins post Mech Side Aisle install Not Started 06/16/27 07/14/27 25.0 25.0
0%
126.2
RPL09.INT.DHB.01510 RPL09.Interior.DHB - Control Fault Domain 3 - Install FW Remaining Tie-ins post Mech Side Aisle install Not Started 06/16/27 07/14/27 25.0 25.0
0%
120.0
RPL09.INT.DHB.02240 RPL09.Interior.DHB - Control Fault Domain 3 - Install TW Remaining Tie-ins post Mech Side Aisle install Not Started 06/16/27 07/14/27 25.0 25.0
0%
120.0
RPL09.INT.DHB.02620 RPL09.Interior.DHB - OFE - Control Fault Domain 4 (Mech Side Aisle) Control Fault Domain 4 Not Started 06/16/27 06/25/27 10.0 10.0
0%
127.5
RPL09.INT.SSB.06400 RPL09.Interior.SSB LO #16 - Electrical L2 Checklist Completion Leave Out Wall #16 (SSB - North of Loading Dock) Not Started 06/16/27 06/29/27 12.5 12.5
0%
161.2
RPL09.INT.SSB.06420 RPL09.Interior.SSB LO #16 - Mechanical L2 Checklist Completion Leave Out Wall #16 (SSB - North of Loading Dock) Not Started 06/16/27 06/29/27 12.5 12.5
0%
161.2
DCC.B9.3527 [SSDCB4] Cabling Start : Front End Production Cabling [DHB] Connectivity Not Started 06/17/27 06/17/27 0.0 0.0
0%
417.5
GCD.RPL09.3527 [RPL09] TC-C Ready : Production Cabling Start [DHB Rows 01-08] TC-C Ready: Production Cabling - DHB Not Started 06/17/27 06/17/27 0.0 0.0
0%
417.5
RPL09.CON.WP3B.01080 RPL09.Conn EF2<>DHB11 - WBS Summary EF2<>DHB.11 Not Started 06/17/27 07/02/27 15.0 15.0
0%
223.8
RPL09.EY.DHA.01460 RPL09.EY.DHA - Install Remaining Mechanical Tie-ins Tie-ins Not Started 06/17/27 06/30/27 12.5 12.5
0%
221.2
RPL09.EY.DHA.01520 RPL09.EY.DHA - Install Floor Mounted Outdoor Split AC Units (Qty 4) OFE Not Started 06/17/27 06/28/27 10.0 10.0
0%
198.8
RPL09.EY.DHC.01250 RPL09.EY.DHC - Install Electrical Tie-ins (include penetration detail) Tie-ins Not Started 06/17/27 06/30/27 12.5 12.5
0%
218.8
RPL09.EY.DHC.01260 RPL09.EY.DHC - Tie-ins - WBS Summary Tie-ins Not Started 06/17/27 11/29/27 141.2 141.2
0%
211.2
RPL09.INT.DHD.01650 RPL09.Interior.DHD - Control Fault Domain 4 - Install LV Side Aisle HAC Busway LV Side Tie-ins Not Started 06/17/27 06/22/27 5.0 5.0
0%
310.0
RPL09.INT.ENDC.06840 RPL09.Interior.Center-Corridor - Final Finishes & Fixtures - Install Acoustical Ceiling Restrooms Not Started 06/17/27 06/21/27 3.8 3.8
0%
268.8
RPL09.INT.SSB.14620 RPL09.Interior.SSB LO #01 to #05 - Install Door (Verify with Trades before installation) Finishes Not Started 06/17/27 06/25/27 8.8 8.8
0%
168.8
RPL09.WP3B.012020 RPL09.Conn EF2<>DHB.11 Pull Pigtails (384F) P2&3 (LV) EF2<>DHB.11 Not Started 06/17/27 06/18/27 2.5 2.5
0%
207.5
RPL09.WP4.010080 RPL09.Conn DHB.11 Pull Ext. Trunk (384F) [SSW<>JXSW] SSW<>JXSW Not Started 06/17/27 06/17/27 1.2 1.2
0%
237.5
RPL09.WP4.010200 RPL09.Conn DHB.11.01 Pull Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] Jumpers (AI Confirmed) Not Started 06/17/27 06/30/27 12.5 12.5
0%
198.8
RPL09.WP4.010220 RPL09.Conn DHB.12.05 Pull Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] Jumpers (AI Confirmed) Not Started 06/17/27 06/30/27 12.5 12.5
0%
198.8
RPL09.WP4.010440 RPL09.Conn DHB.11 Pull Ext. Trunk (24F) [PON (Passive, In-Rack)] In-Rack Not Started 06/17/27 06/17/27 1.2 1.2
0%
227.5
RPL09.WP4.010460 RPL09.Conn DHB.12 Pull Ext. Trunk (24F) [PON (Passive, In-Rack)] In-Rack Not Started 06/17/27 06/17/27 1.2 1.2
0%
227.5
RPL09.INT.CC.9540 RPL09.Interior.CC Ext. LO #17 - QC - Backings/Walls Exterior Leave Out Wall #17 (CC - South) Not Started 06/18/27 06/18/27 1.2 1.2
0%
141.2
RPL09.INT.DHA.01780 RPL09.Interior.DHA - Control Fault Domain 5 - Install LV Side Aisle HAC Busway LV Side Tie-ins Not Started 06/18/27 06/23/27 5.0 5.0
0%
201.2
RPL09.INT.DHC.01120 RPL09.Interior.DHC - OFE - Control Fault Domain 1 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary Control Fault Domain 1 Not Started 06/18/27 08/30/27 63.8 63.8
0%
128.8
RPL09.INT.DHC.02270 RPL09.Interior.DHC - OFE - Control Fault Domain 1 (LV Side Aisle) Control Fault Domain 1 Not Started 06/18/27 06/24/27 6.2 6.2
0%
163.8
RPL09.INT.DHD.01670 RPL09.Interior.DHD - Control Fault Domain 4 - Install LV Side Aisle Cable Tray LV Side Tie-ins Not Started 06/18/27 06/23/27 5.0 5.0
0%
313.8
RPL09.INT.ENDC.01350 RPL09.Interior.End-Corridor - Plumbing Trim Fit out Not Started 06/18/27 06/23/27 5.0 5.0
0%
256.2