Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL09 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:12 PM
· 5201 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
0
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL09.INT.SBC.03600 |
RPL09.Interior.SSB-Corridor - BoW - Electrical Trim Out (Both side of Corridor Wall) | Balance of Walls & Overhead | Not Started | 06/18/27 | 06/28/27 | 8.8 | 8.8 |
|
138.8 |
RPL09.INT.SBC.03620 |
RPL09.Interior.SSB-Corridor - BoW - Duct Drops / Trim out | Balance of Walls & Overhead | Not Started | 06/18/27 | 06/24/27 | 6.2 | 6.2 |
|
138.8 |
RPL09.INT.SBC.03700 |
RPL09.Interior.SSB-Corridor - BoW - Install Balance Of Refrigerant Line | Balance of Walls & Overhead | Not Started | 06/18/27 | 06/24/27 | 6.2 | 6.2 |
|
178.8 |
RPL09.INT.SBC.03720 |
RPL09.Interior.SSB-Corridor - BoW - Security Trim Out (Both side of Corridor Wall) | Balance of Walls & Overhead | Not Started | 06/18/27 | 06/28/27 | 8.8 | 8.8 |
|
138.8 |
RPL09.INT.SBC.03780 |
RPL09.Interior.SSB-Corridor - BoW - Install DAS (Distribution Antenna System) | Balance of Walls & Overhead | Not Started | 06/18/27 | 06/24/27 | 6.2 | 6.2 |
|
142.5 |
RPL09.INT.SSB.02380 |
RPL09.Interior.SSB - Final Finishes & Fixtures - Final Punch Walk | Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) | Not Started | 06/18/27 | 06/21/27 | 2.5 | 2.5 |
|
295.0 |
RPL09.WP4.010240 |
RPL09.Conn DHB.11 Pull Trunk (192F) [FSW<>SSW] | FSW<>SSW | Not Started | 06/18/27 | 06/18/27 | 1.2 | 1.2 |
|
237.5 |
RPL09.WP4.010560 |
RPL09.Conn DHB.11.01<>01 Pull Simplex Jumper (SC<>LC) [PON (Active, In-Row)] | Jumpers | Not Started | 06/18/27 | 06/22/27 | 3.8 | 3.8 |
|
227.5 |
RPL09.WP4.010580 |
RPL09.Conn DHB.12.05<>05 Pull Simplex Jumper (SC<>LC) [PON (Active, In-Row)] | Jumpers | Not Started | 06/18/27 | 06/22/27 | 3.8 | 3.8 |
|
227.5 |
RPL09.WP4.010600 |
RPL09.Conn DHB.11 Install Ext. Trunk (24F) [PON (Passive, In-Rack)] | In-Rack | Not Started | 06/18/27 | 06/22/27 | 3.8 | 3.8 |
|
246.2 |
RPL09.WP4.010620 |
RPL09.Conn DHB.12 Install Ext. Trunk (24F) [PON (Passive, In-Rack)] | In-Rack | Not Started | 06/18/27 | 06/22/27 | 3.8 | 3.8 |
|
246.2 |
GCD.RPL09.2001 |
Cx Power Available (Temp) | CX Milestones | Not Started | 06/21/27 | 06/21/27 | 0.0 | 0.0 |
|
76.2 |
GCD.RPL09.5805 |
RMU Loop Ready for Energization - DHA Loop | EY | Not Started | 06/21/27 | 06/21/27 | 0.0 | 0.0 |
|
88.8 |
ICM.B9.2530 |
[SSDCB4] L3/L4 Start EY | Commissioning | Not Started | 06/21/27 | 06/21/27 | 0.0 | 0.0 |
|
232.5 |
RPL09.CON.WP3B.01060 |
RPL09.Conn EF2<>DHB12 - WBS Summary | EF2<>DHB.12 | Not Started | 06/21/27 | 07/06/27 | 13.8 | 13.8 |
|
222.5 |
RPL09.CX.DHB.01000 |
RPL09.CX.DHB - L3, L4, IST - WBS Summary | DHB | Not Started | 06/21/27 | 05/10/28 | 277.5 | 277.5 |
|
125.0 |
RPL09.CX.DHB.01010 |
RPL09.CX.DHB - L3 - WBS Summary (Electrical) | DHB ELECTRICAL | Not Started | 06/21/27 | 10/07/27 | 96.2 | 96.2 |
|
136.2 |
RPL09.CX.DHB.01020 |
RPL09.CX.DHB - L3/L4 - MV Skids (10) Loop | DHB ELECTRICAL | Not Started | 06/21/27 | 07/02/27 | 12.5 | 12.5 |
|
76.2 |
RPL09.CX.DHB.01090 |
RPL09.CX.DHB - L4 - WBS Summary (Mechanical) | DHB MECHANICAL | Not Started | 06/21/27 | 01/27/28 | 187.5 | 187.5 |
|
45.0 |
RPL09.CX.DHB.01260 |
RPL09.CX.DHB - L3/L4 - Control Fault Domain 01 - FW Flush and Fill | Control Fault Domain 1 | Not Started | 06/21/27 | 06/29/27 | 8.8 | 8.8 |
|
127.5 |
RPL09.CX.MCUP.01030 |
RPL09.CX.mCup Loop 2 - L3/L4 - MV Skids | mCUP 5-6 | Not Started | 06/21/27 | 06/24/27 | 5.0 | 5.0 |
|
222.5 |
RPL09.CX.MCUP.01040 |
RPL09.CX.mCup Loop 1 - L3/L4 - mCUP - FWM | mCUP 1-4 | Not Started | 06/21/27 | 07/02/27 | 12.5 | 12.5 |
|
82.5 |
RPL09.EY.DHA.01330 |
RPL09.EY.DHA - Install Early EY Paving | Hardscape and Landscape | Not Started | 06/21/27 | 06/25/27 | 6.2 | 6.2 |
|
240.0 |
RPL09.EY.DHC.01280 |
RPL09.EY.DHC - Install BMS/EPMS Tie-ins | Tie-ins | Not Started | 06/21/27 | 07/02/27 | 12.5 | 12.5 |
|
218.8 |
RPL09.EY.DHD.01300 |
RPL09.EY.DHD - Install Sleeves MEPL | Hardscape and Landscape | Not Started | 06/21/27 | 06/25/27 | 6.2 | 6.2 |
|
333.8 |
RPL09.EY.DHD.01310 |
RPL09.EY.DHD - MV Loop - L2 Checklist Completion | Tie-ins | Not Started | 06/21/27 | 07/02/27 | 12.5 | 12.5 |
|
215.0 |
RPL09.EY.DHD.01320 |
RPL09.EY.DHD - Install Hardscape and Landscape - WBS Summary | Hardscape and Landscape | Not Started | 06/21/27 | 12/03/27 | 143.8 | 143.8 |
|
271.2 |
RPL09.INT.CC.9020 |
RPL09.Interior.CC Ext. LO #17 - Hang Drywall | Exterior Leave Out Wall #17 (CC - South) | Not Started | 06/21/27 | 06/23/27 | 3.8 | 3.8 |
|
141.2 |
RPL09.INT.CTRC.06820 |
RPL09.Interior.Center-Corridor - Final Finishes & Fixtures - Hang Tape Bed Wall, Ceiling and Fire/Caulking | Restrooms | Not Started | 06/21/27 | 06/25/27 | 6.2 | 6.2 |
|
130.0 |
RPL09.INT.CTRC.06840 |
RPL09.Interior.Center-Corridor - Final Finishes & Fixtures - Framing RO Verification, Tile Finish & ADA Verification (P | Restrooms | Not Started | 06/21/27 | 06/25/27 | 6.2 | 6.2 |
|
117.5 |
RPL09.INT.CTRC.1560 |
RPL09.Interior.Center-Corridor - BoW - Hang Drywall | Balance of Walls & Overhead | Not Started | 06/21/27 | 06/29/27 | 8.8 | 8.8 |
|
143.8 |
RPL09.INT.DHA.01800 |
RPL09.Interior.DHA - Control Fault Domain 5 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 06/21/27 | 06/24/27 | 5.0 | 5.0 |
|
217.5 |
RPL09.INT.SSB.01480 |
RPL09.Interior.SSB - Loading Dock and Storage - Security Trim Out | Loading Dock and Storage | Not Started | 06/21/27 | 06/29/27 | 8.8 | 8.8 |
|
208.8 |
RPL09.INT.SSB.02960 |
RPL09.Interior.SSB - Loading Dock and Storage - Install Flooring | Loading Dock and Storage | Not Started | 06/21/27 | 06/25/27 | 6.2 | 6.2 |
|
233.8 |
RPL09.WP3B.012040 |
RPL09.Conn EF2<>DHB.12 Pull Pigtails (384F) P2&3 (LV) | EF2<>DHB.12 | Not Started | 06/21/27 | 06/22/27 | 2.5 | 2.5 |
|
207.5 |
RPL09.WP3B.013460 |
RPL09.Conn EF2<>DHB.11 Install (A-End) Pigtails (384F) P2&3 (LV) | EF2<>DHB.11 | Not Started | 06/21/27 | 06/21/27 | 1.2 | 1.2 |
|
223.8 |
RPL09.WP4.010400 |
RPL09.Conn DHB.11 Pull Trunk (384F) [RSW<>FSW] | Trunks | Not Started | 06/21/27 | 06/21/27 | 1.2 | 1.2 |
|
237.5 |
RPL09.INT.DHC.01130 |
RPL09.Interior.DHC - Control Fault Domain 1 - Install Duct (LV Side) | LV Side Tie-ins | Not Started | 06/22/27 | 06/28/27 | 6.2 | 6.2 |
|
215.0 |
RPL09.INT.DHC.01160 |
RPL09.Interior.DHC - Tie-ins - Control Fault Domain 1 - WBS Summary | Control Fault Domain 1 | Not Started | 06/22/27 | 10/19/27 | 105.0 | 105.0 |
|
160.0 |
RPL09.INT.ENDC.06780 |
RPL09.Interior.Center-Corridor - Final Finishes & Fixtures - Final Paint | Restrooms | Not Started | 06/22/27 | 06/30/27 | 8.8 | 8.8 |
|
268.8 |
RPL09.INT.ENDC.1480 |
RPL09.Interior.End-Corridor - BoW - MEPF Hard Lid Rough-In/ Close of Inspection | Balance of Walls & Overhead | Not Started | 06/22/27 | 06/30/27 | 8.8 | 8.8 |
|
228.8 |
RPL09.INT.ENDC.1500 |
RPL09.Interior.End-Corridor - BoW - Install Blocking/Steel support Assembly for Metal Canopy | Balance of Walls & Overhead | Not Started | 06/22/27 | 06/28/27 | 6.2 | 6.2 |
|
218.8 |
RPL09.INT.SBC.03740 |
RPL09.Interior.SSB-Corridor - BoW - Plumbing Trim Out | Balance of Walls & Overhead | Not Started | 06/22/27 | 06/28/27 | 6.2 | 6.2 |
|
138.8 |
RPL09.INT.SBC.03760 |
RPL09.Interior.SSB-Corridor - BoW - Fire Life Safety Trim Out / Fire Alarm Trim Out | Balance of Walls & Overhead | Not Started | 06/22/27 | 06/30/27 | 8.8 | 8.8 |
|
138.8 |
RPL09.INT.SSB.02180 |
RPL09.Interior.SSB - Final Finishes & Fixtures - Electrical L2 Checklist Completion | Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) | Not Started | 06/22/27 | 07/06/27 | 12.5 | 12.5 |
|
295.0 |
RPL09.WP3B.016340 |
RPL09.Conn EF2<>DHB.11 Install (Z-End) Pigtails (384F) P2&3 (LV) | EF2<>DHB.11 | Not Started | 06/22/27 | 06/29/27 | 7.5 | 7.5 |
|
223.8 |
RPL09.INT.CTRC.1900 |
RPL09.Interior.Center-Corridor - BoW - F/R/P Pads | Balance of Walls & Overhead | Not Started | 06/23/27 | 06/29/27 | 6.2 | 6.2 |
|
143.8 |
RPL09.INT.DHA.01240 |
RPL09.Interior.DHA - Control Fault Domain 1 - Install Mechanical Side Aisle Cable Tray | Remaining Tie-ins post Mech Side Aisle install | Not Started | 06/23/27 | 07/21/27 | 25.0 | 25.0 |
|
80.0 |
RPL09.INT.DHB.01480 |
RPL09.Interior.DHB - Control Fault Domain 2 - Install copper from GS.IDF to BMS and EPMS panels | Remaining Tie-ins post Mech Side Aisle install | Not Started | 06/23/27 | 07/21/27 | 25.0 | 25.0 |
|
106.2 |
RPL09.INT.DHB.01530 |
RPL09.Interior.DHB - Control Fault Domain 3 - Pull BMS from panel to devices | Remaining Tie-ins post Mech Side Aisle install | Not Started | 06/23/27 | 07/21/27 | 25.0 | 25.0 |
|
126.2 |
RPL09.INT.DHB.01540 |
RPL09.Interior.DHB - Control Fault Domain 3 - Pull EMPS from panel to devices | Remaining Tie-ins post Mech Side Aisle install | Not Started | 06/23/27 | 07/21/27 | 25.0 | 25.0 |
|
126.2 |
RPL09.INT.DHB.01550 |
RPL09.Interior.DHB - Control Fault Domain 3 - Set UPS and Panel (2) and GS.IDF B1 (Stick Build) | Remaining Tie-ins post Mech Side Aisle install | Not Started | 06/23/27 | 07/21/27 | 25.0 | 25.0 |
|
120.0 |
RPL09.WP3B.013480 |
RPL09.Conn EF2<>DHB.12 Install (A-End) Pigtails (384F) P2&3 (LV) | EF2<>DHB.12 | Not Started | 06/23/27 | 06/23/27 | 1.2 | 1.2 |
|
222.5 |
RPL09.WP4.010720 |
RPL09.Conn DHB.11.03<>03 Pull Simplex Jumper (SC<>LC) [PON (Active, In-Row)] | Jumpers | Not Started | 06/23/27 | 06/25/27 | 3.8 | 3.8 |
|
227.5 |
RPL09.WP4.010740 |
RPL09.Conn DHB.12.06<>05 Pull Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] | Across-Row | Not Started | 06/23/27 | 06/28/27 | 5.0 | 5.0 |
|
227.5 |
RPL.09.D.93340.XR |
Pull and Term MV Skids - RPL09 DHD | Receive Milestones (XREFs) | Not Started | 06/24/27 | 06/24/27 | 0.0 | 0.0 |
|
223.8 |
RPL.09.D.93840.XR |
100MW Cx Temp Power to MV Skids RPL09 DHD Available | Receive Milestones (XREFs) | Not Started | 06/24/27 | 06/24/27 | 0.0 | 0.0 |
|
223.8 |
RPL09.INT.CC.9040 |
RPL09.Interior.CC Ext. LO #17 - Tape Finish Paint | Exterior Leave Out Wall #17 (CC - South) | Not Started | 06/24/27 | 06/30/27 | 6.2 | 6.2 |
|
141.2 |
RPL09.INT.DHC.01230 |
RPL09.Interior.DHC - Control Fault Domain 1 - Install LV Side Aisle HAC Busway | LV Side Tie-ins | Not Started | 06/24/27 | 06/30/27 | 6.2 | 6.2 |
|
223.8 |
RPL09.INT.ENDC.01300 |
RPL09.Interior.End-Corridor - DAS (Distribution Antenna System) | Fit out | Not Started | 06/24/27 | 06/30/27 | 6.2 | 6.2 |
|
256.2 |
RPL09.WP3B.014920 |
RPL09.Conn EF2<>DHB.12 Splice (A-End) Pigtails (384F) P2&3 (LV) | EF2<>DHB.12 | Not Started | 06/24/27 | 07/01/27 | 7.5 | 7.5 |
|
222.5 |
RPL09.WP3B.016360 |
RPL09.Conn EF2<>DHB.12 Install (Z-End) Pigtails (384F) P2&3 (LV) | EF2<>DHB.12 | Not Started | 06/24/27 | 06/24/27 | 1.2 | 1.2 |
|
222.5 |
RPL09.EY.ENDC.1950 |
RPL09.EY.DHD.T1 - HAC Prefab prior to install for DH D | Tent 1 | Not Started | 06/25/27 | 07/09/27 | 12.5 | 12.5 |
|
138.8 |
RPL09.INT.DHA.03620 |
RPL09.Interior.DHA - OFE - Control Fault Domain 3 (HAC) | Control Fault Domain 3 | Not Started | 06/25/27 | 07/09/27 | 12.5 | 12.5 |
|
90.0 |
RPL09.INT.DHB.02660 |
RPL09.Interior.DHB - OFE - Control Fault Domain 5 (HAC) | Control Fault Domain 5 | Not Started | 06/25/27 | 07/09/27 | 12.5 | 12.5 |
|
130.0 |
RPL09.INT.DHC.01210 |
RPL09.Interior.DHC - OFE - Control Fault Domain 2 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | Control Fault Domain 2 | Not Started | 06/25/27 | 09/14/27 | 70.0 | 70.0 |
|
126.2 |
RPL09.INT.DHC.01250 |
RPL09.Interior.DHC - Control Fault Domain 1 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 06/25/27 | 07/01/27 | 6.2 | 6.2 |
|
223.8 |
RPL09.INT.DHC.02330 |
RPL09.Interior.DHC - OFE - Control Fault Domain 2 (LV Side Aisle) | Control Fault Domain 2 | Not Started | 06/25/27 | 06/30/27 | 5.0 | 5.0 |
|
176.2 |
RPL09.INT.SBC.03840 |
RPL09.Interior.SSB-Corridor - BoW - Install Remaining Lights | Balance of Walls & Overhead | Not Started | 06/25/27 | 07/09/27 | 12.5 | 12.5 |
|
142.5 |
RPL09.EY.DHA.01340 |
RPL09.EY.DHA - Install Lighting | Hardscape and Landscape | Not Started | 06/28/27 | 07/12/27 | 12.5 | 12.5 |
|
240.0 |
RPL09.EY.DHB.01390 |
RPL09.EY.DHB - Install Remaining EY Paving | Hardscape and Landscape | Not Started | 06/28/27 | 07/02/27 | 6.2 | 6.2 |
|
240.0 |
RPL09.EY.DHC.01290 |
RPL09.EY.DHC - MV Loop - L2 Checklist Completion | Tie-ins | Not Started | 06/28/27 | 07/12/27 | 12.5 | 12.5 |
|
218.8 |
RPL09.EY.DHD.01330 |
RPL09.EY.DHD - Install Early EY Paving | Hardscape and Landscape | Not Started | 06/28/27 | 07/02/27 | 6.2 | 6.2 |
|
333.8 |
RPL09.INT.CTRC.06860 |
RPL09.Interior.Center-Corridor - Final Finishes & Fixtures - Install Cement Board/ Drywall | Restrooms | Not Started | 06/28/27 | 07/02/27 | 6.2 | 6.2 |
|
117.5 |
RPL09.INT.ENDC.01370 |
RPL09.Interior.End-Corridor - Asset Tagging | Fit out | Not Started | 06/28/27 | 07/12/27 | 12.5 | 12.5 |
|
256.2 |
RPL09.INT.SSB.01520 |
RPL09.Interior.SSB - Loading Dock and Storage - Install Shelving | Loading Dock and Storage | Not Started | 06/28/27 | 07/01/27 | 5.0 | 5.0 |
|
233.8 |
RPL09.INT.SSB.01550 |
RPL09.Interior.SSB - BoW - Install TVs and Conf Sound | Balance of Walls and OverHead | Not Started | 06/28/27 | 07/02/27 | 6.2 | 6.2 |
|
232.5 |
RPL09.INT.SSB.01560 |
RPL09.Interior.SSB - BoW - Install & QC Asset Tags | Balance of Walls and OverHead | Not Started | 06/28/27 | 06/29/27 | 2.5 | 2.5 |
|
188.8 |
RPL09.INT.SSB.14640 |
RPL09.Interior.SSB LO #01 to #05 - Electrical L2 Checklist Completion | Finishes | Not Started | 06/28/27 | 07/12/27 | 12.5 | 12.5 |
|
168.8 |
RPL09.WP4.010900 |
RPL09.Conn DHB.11.02<>01 Pull Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] | Across-Row | Not Started | 06/28/27 | 07/01/27 | 5.0 | 5.0 |
|
227.5 |
RPL09.CX.MCUP.01370 |
RPL09.CX.mCup Loop 2 - L3/L4 - mCUP - Flush and Fill - DHD & DHC - Loop 2 (Phase 4) | Fill and Flush | Not Started | 06/29/27 | 07/06/27 | 6.2 | 6.2 |
|
252.5 |
RPL09.EY.DHA.01590 |
RPL09.EY.DHC - Install Mechanical/ refrigerantTie-ins | Build back Exterior Leave Out #17 (South) | Not Started | 06/29/27 | 07/06/27 | 6.2 | 6.2 |
|
198.8 |
RPL09.EY.DHA.02000 |
RPL09.EY.DHA - Exterior Leave Out #17 (CC - South) WBS Summary | Build back Exterior Leave Out #17 (South) | Not Started | 06/29/27 | 07/27/27 | 25.0 | 25.0 |
|
198.8 |
RPL09.EY.DHB.01470 |
RPL09.EY.DHB - Remaining L2 Checklist Completion | Tie-ins | Not Started | 06/29/27 | 07/06/27 | 6.2 | 6.2 |
|
212.5 |
RPL09.INT.DHC.01270 |
RPL09.Interior.DHC - Control Fault Domain 2 - Install Duct (LV Side) | LV Side Tie-ins | Not Started | 06/29/27 | 07/02/27 | 5.0 | 5.0 |
|
228.8 |
RPL09.INT.DHC.01300 |
RPL09.Interior.DHC - Tie-ins - Control Fault Domain 2 - WBS Summary | Control Fault Domain 2 | Not Started | 06/29/27 | 11/09/27 | 117.5 | 117.5 |
|
161.2 |
RPL09.INT.ENDC.1520 |
RPL09.Interior.End-Corridor - BoW - Install Backing at Exterior Wall | Balance of Walls & Overhead | Not Started | 06/29/27 | 07/06/27 | 6.2 | 6.2 |
|
218.8 |
RPL09.INT.ENDC.6180 |
RPL09.Interior.End-Corridor - BoW - Electrical Tie-In | Balance of Walls & Overhead | Not Started | 06/29/27 | 07/06/27 | 6.2 | 6.2 |
|
271.2 |
RPL09.INT.SSB.02200 |
RPL09.Interior.SSB - Final Finishes & Fixtures - Mechanical L2 Checklist Completion | Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) | Not Started | 06/29/27 | 07/13/27 | 12.5 | 12.5 |
|
295.0 |
RPL09.WP4.011220 |
RPL09.Conn DHB.12.07<>07 Pull Simplex Jumper (SC<>LC) [PON (Active, In-Row)] | Jumpers | Not Started | 06/29/27 | 07/01/27 | 3.8 | 3.8 |
|
227.5 |
RPL09.CX.DHB.01280 |
RPL09.CX.DHB - L3/L4 - Control Fault Domain 01 - TW Flush and Fill | Control Fault Domain 1 | Not Started | 06/30/27 | 07/12/27 | 10.0 | 10.0 |
|
127.5 |
RPL09.CX.DHB.01320 |
RPL09.CX.DHB - L3/L4 - Control Fault Domain 02 - FW Flush and Fill | Control Fault Domain 2 | Not Started | 06/30/27 | 07/09/27 | 8.8 | 8.8 |
|
138.8 |
RPL09.INT.CTRC.1580 |
RPL09.Interior.Center-Corridor - BoW - Tape Finish Paint | Balance of Walls & Overhead | Not Started | 06/30/27 | 07/02/27 | 3.8 | 3.8 |
|
143.8 |
RPL09.INT.DHA.01250 |
RPL09.Interior.DHA - Control Fault Domain 1 - Install Copper from GS.IDF to BMS and EPMS panels | Remaining Tie-ins post Mech Side Aisle install | Not Started | 06/30/27 | 07/28/27 | 25.0 | 25.0 |
|
80.0 |
RPL09.INT.DHA.01270 |
RPL09.Interior.DHA - Control Fault Domain 2 - Install Vesda / FA | Remaining Tie-ins post Mech Side Aisle install | Not Started | 06/30/27 | 07/28/27 | 25.0 | 25.0 |
|
105.0 |
RPL09.INT.DHA.01280 |
RPL09.Interior.DHA - Control Fault Domain 2 - Install FW | Remaining Tie-ins post Mech Side Aisle install | Not Started | 06/30/27 | 07/28/27 | 25.0 | 25.0 |
|
92.5 |
RPL09.INT.DHA.02200 |
RPL09.Interior.DHA - Control Fault Domain 2 - Install TW | Remaining Tie-ins post Mech Side Aisle install | Not Started | 06/30/27 | 07/28/27 | 25.0 | 25.0 |
|
92.5 |
RPL09.INT.DHA.03640 |
RPL09.Interior.DHA - OFE - Control Fault Domain 3 (Mech Side Aisle) | Control Fault Domain 3 | Not Started | 06/30/27 | 07/12/27 | 10.0 | 10.0 |
|
106.2 |
RPL09.INT.DHA.03820 |
RPL09.Interior.DHA - Control Fault Domain 2 - Install Duct (MES Side) | Remaining Tie-ins post Mech Side Aisle install | Not Started | 06/30/27 | 07/28/27 | 25.0 | 25.0 |
|
92.5 |
RPL09.INT.DHB.01570 |
RPL09.Interior.DHB - Control Fault Domain 2 - L2 Checklist Completion | Remaining Tie-ins post Mech Side Aisle install | Not Started | 06/30/27 | 07/28/27 | 25.0 | 25.0 |
|
106.2 |