Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL09 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:12 PM · 5201 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
0
Completed
0
In Progress
0
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL09.INT.SBC.03600 RPL09.Interior.SSB-Corridor - BoW - Electrical Trim Out (Both side of Corridor Wall) Balance of Walls & Overhead Not Started 06/18/27 06/28/27 8.8 8.8
0%
138.8
RPL09.INT.SBC.03620 RPL09.Interior.SSB-Corridor - BoW - Duct Drops / Trim out Balance of Walls & Overhead Not Started 06/18/27 06/24/27 6.2 6.2
0%
138.8
RPL09.INT.SBC.03700 RPL09.Interior.SSB-Corridor - BoW - Install Balance Of Refrigerant Line Balance of Walls & Overhead Not Started 06/18/27 06/24/27 6.2 6.2
0%
178.8
RPL09.INT.SBC.03720 RPL09.Interior.SSB-Corridor - BoW - Security Trim Out (Both side of Corridor Wall) Balance of Walls & Overhead Not Started 06/18/27 06/28/27 8.8 8.8
0%
138.8
RPL09.INT.SBC.03780 RPL09.Interior.SSB-Corridor - BoW - Install DAS (Distribution Antenna System) Balance of Walls & Overhead Not Started 06/18/27 06/24/27 6.2 6.2
0%
142.5
RPL09.INT.SSB.02380 RPL09.Interior.SSB - Final Finishes & Fixtures - Final Punch Walk Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) Not Started 06/18/27 06/21/27 2.5 2.5
0%
295.0
RPL09.WP4.010240 RPL09.Conn DHB.11 Pull Trunk (192F) [FSW<>SSW] FSW<>SSW Not Started 06/18/27 06/18/27 1.2 1.2
0%
237.5
RPL09.WP4.010560 RPL09.Conn DHB.11.01<>01 Pull Simplex Jumper (SC<>LC) [PON (Active, In-Row)] Jumpers Not Started 06/18/27 06/22/27 3.8 3.8
0%
227.5
RPL09.WP4.010580 RPL09.Conn DHB.12.05<>05 Pull Simplex Jumper (SC<>LC) [PON (Active, In-Row)] Jumpers Not Started 06/18/27 06/22/27 3.8 3.8
0%
227.5
RPL09.WP4.010600 RPL09.Conn DHB.11 Install Ext. Trunk (24F) [PON (Passive, In-Rack)] In-Rack Not Started 06/18/27 06/22/27 3.8 3.8
0%
246.2
RPL09.WP4.010620 RPL09.Conn DHB.12 Install Ext. Trunk (24F) [PON (Passive, In-Rack)] In-Rack Not Started 06/18/27 06/22/27 3.8 3.8
0%
246.2
GCD.RPL09.2001 Cx Power Available (Temp) CX Milestones Not Started 06/21/27 06/21/27 0.0 0.0
0%
76.2
GCD.RPL09.5805 RMU Loop Ready for Energization - DHA Loop EY Not Started 06/21/27 06/21/27 0.0 0.0
0%
88.8
ICM.B9.2530 [SSDCB4] L3/L4 Start EY Commissioning Not Started 06/21/27 06/21/27 0.0 0.0
0%
232.5
RPL09.CON.WP3B.01060 RPL09.Conn EF2<>DHB12 - WBS Summary EF2<>DHB.12 Not Started 06/21/27 07/06/27 13.8 13.8
0%
222.5
RPL09.CX.DHB.01000 RPL09.CX.DHB - L3, L4, IST - WBS Summary DHB Not Started 06/21/27 05/10/28 277.5 277.5
0%
125.0
RPL09.CX.DHB.01010 RPL09.CX.DHB - L3 - WBS Summary (Electrical) DHB ELECTRICAL Not Started 06/21/27 10/07/27 96.2 96.2
0%
136.2
RPL09.CX.DHB.01020 RPL09.CX.DHB - L3/L4 - MV Skids (10) Loop DHB ELECTRICAL Not Started 06/21/27 07/02/27 12.5 12.5
0%
76.2
RPL09.CX.DHB.01090 RPL09.CX.DHB - L4 - WBS Summary (Mechanical) DHB MECHANICAL Not Started 06/21/27 01/27/28 187.5 187.5
0%
45.0
RPL09.CX.DHB.01260 RPL09.CX.DHB - L3/L4 - Control Fault Domain 01 - FW Flush and Fill Control Fault Domain 1 Not Started 06/21/27 06/29/27 8.8 8.8
0%
127.5
RPL09.CX.MCUP.01030 RPL09.CX.mCup Loop 2 - L3/L4 - MV Skids mCUP 5-6 Not Started 06/21/27 06/24/27 5.0 5.0
0%
222.5
RPL09.CX.MCUP.01040 RPL09.CX.mCup Loop 1 - L3/L4 - mCUP - FWM mCUP 1-4 Not Started 06/21/27 07/02/27 12.5 12.5
0%
82.5
RPL09.EY.DHA.01330 RPL09.EY.DHA - Install Early EY Paving Hardscape and Landscape Not Started 06/21/27 06/25/27 6.2 6.2
0%
240.0
RPL09.EY.DHC.01280 RPL09.EY.DHC - Install BMS/EPMS Tie-ins Tie-ins Not Started 06/21/27 07/02/27 12.5 12.5
0%
218.8
RPL09.EY.DHD.01300 RPL09.EY.DHD - Install Sleeves MEPL Hardscape and Landscape Not Started 06/21/27 06/25/27 6.2 6.2
0%
333.8
RPL09.EY.DHD.01310 RPL09.EY.DHD - MV Loop - L2 Checklist Completion Tie-ins Not Started 06/21/27 07/02/27 12.5 12.5
0%
215.0
RPL09.EY.DHD.01320 RPL09.EY.DHD - Install Hardscape and Landscape - WBS Summary Hardscape and Landscape Not Started 06/21/27 12/03/27 143.8 143.8
0%
271.2
RPL09.INT.CC.9020 RPL09.Interior.CC Ext. LO #17 - Hang Drywall Exterior Leave Out Wall #17 (CC - South) Not Started 06/21/27 06/23/27 3.8 3.8
0%
141.2
RPL09.INT.CTRC.06820 RPL09.Interior.Center-Corridor - Final Finishes & Fixtures - Hang Tape Bed Wall, Ceiling and Fire/Caulking Restrooms Not Started 06/21/27 06/25/27 6.2 6.2
0%
130.0
RPL09.INT.CTRC.06840 RPL09.Interior.Center-Corridor - Final Finishes & Fixtures - Framing RO Verification, Tile Finish & ADA Verification (P Restrooms Not Started 06/21/27 06/25/27 6.2 6.2
0%
117.5
RPL09.INT.CTRC.1560 RPL09.Interior.Center-Corridor - BoW - Hang Drywall Balance of Walls & Overhead Not Started 06/21/27 06/29/27 8.8 8.8
0%
143.8
RPL09.INT.DHA.01800 RPL09.Interior.DHA - Control Fault Domain 5 - Install LV Side Aisle Cable Tray LV Side Tie-ins Not Started 06/21/27 06/24/27 5.0 5.0
0%
217.5
RPL09.INT.SSB.01480 RPL09.Interior.SSB - Loading Dock and Storage - Security Trim Out Loading Dock and Storage Not Started 06/21/27 06/29/27 8.8 8.8
0%
208.8
RPL09.INT.SSB.02960 RPL09.Interior.SSB - Loading Dock and Storage - Install Flooring Loading Dock and Storage Not Started 06/21/27 06/25/27 6.2 6.2
0%
233.8
RPL09.WP3B.012040 RPL09.Conn EF2<>DHB.12 Pull Pigtails (384F) P2&3 (LV) EF2<>DHB.12 Not Started 06/21/27 06/22/27 2.5 2.5
0%
207.5
RPL09.WP3B.013460 RPL09.Conn EF2<>DHB.11 Install (A-End) Pigtails (384F) P2&3 (LV) EF2<>DHB.11 Not Started 06/21/27 06/21/27 1.2 1.2
0%
223.8
RPL09.WP4.010400 RPL09.Conn DHB.11 Pull Trunk (384F) [RSW<>FSW] Trunks Not Started 06/21/27 06/21/27 1.2 1.2
0%
237.5
RPL09.INT.DHC.01130 RPL09.Interior.DHC - Control Fault Domain 1 - Install Duct (LV Side) LV Side Tie-ins Not Started 06/22/27 06/28/27 6.2 6.2
0%
215.0
RPL09.INT.DHC.01160 RPL09.Interior.DHC - Tie-ins - Control Fault Domain 1 - WBS Summary Control Fault Domain 1 Not Started 06/22/27 10/19/27 105.0 105.0
0%
160.0
RPL09.INT.ENDC.06780 RPL09.Interior.Center-Corridor - Final Finishes & Fixtures - Final Paint Restrooms Not Started 06/22/27 06/30/27 8.8 8.8
0%
268.8
RPL09.INT.ENDC.1480 RPL09.Interior.End-Corridor - BoW - MEPF Hard Lid Rough-In/ Close of Inspection Balance of Walls & Overhead Not Started 06/22/27 06/30/27 8.8 8.8
0%
228.8
RPL09.INT.ENDC.1500 RPL09.Interior.End-Corridor - BoW - Install Blocking/Steel support Assembly for Metal Canopy Balance of Walls & Overhead Not Started 06/22/27 06/28/27 6.2 6.2
0%
218.8
RPL09.INT.SBC.03740 RPL09.Interior.SSB-Corridor - BoW - Plumbing Trim Out Balance of Walls & Overhead Not Started 06/22/27 06/28/27 6.2 6.2
0%
138.8
RPL09.INT.SBC.03760 RPL09.Interior.SSB-Corridor - BoW - Fire Life Safety Trim Out / Fire Alarm Trim Out Balance of Walls & Overhead Not Started 06/22/27 06/30/27 8.8 8.8
0%
138.8
RPL09.INT.SSB.02180 RPL09.Interior.SSB - Final Finishes & Fixtures - Electrical L2 Checklist Completion Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) Not Started 06/22/27 07/06/27 12.5 12.5
0%
295.0
RPL09.WP3B.016340 RPL09.Conn EF2<>DHB.11 Install (Z-End) Pigtails (384F) P2&3 (LV) EF2<>DHB.11 Not Started 06/22/27 06/29/27 7.5 7.5
0%
223.8
RPL09.INT.CTRC.1900 RPL09.Interior.Center-Corridor - BoW - F/R/P Pads Balance of Walls & Overhead Not Started 06/23/27 06/29/27 6.2 6.2
0%
143.8
RPL09.INT.DHA.01240 RPL09.Interior.DHA - Control Fault Domain 1 - Install Mechanical Side Aisle Cable Tray Remaining Tie-ins post Mech Side Aisle install Not Started 06/23/27 07/21/27 25.0 25.0
0%
80.0
RPL09.INT.DHB.01480 RPL09.Interior.DHB - Control Fault Domain 2 - Install copper from GS.IDF to BMS and EPMS panels Remaining Tie-ins post Mech Side Aisle install Not Started 06/23/27 07/21/27 25.0 25.0
0%
106.2
RPL09.INT.DHB.01530 RPL09.Interior.DHB - Control Fault Domain 3 - Pull BMS from panel to devices Remaining Tie-ins post Mech Side Aisle install Not Started 06/23/27 07/21/27 25.0 25.0
0%
126.2
RPL09.INT.DHB.01540 RPL09.Interior.DHB - Control Fault Domain 3 - Pull EMPS from panel to devices Remaining Tie-ins post Mech Side Aisle install Not Started 06/23/27 07/21/27 25.0 25.0
0%
126.2
RPL09.INT.DHB.01550 RPL09.Interior.DHB - Control Fault Domain 3 - Set UPS and Panel (2) and GS.IDF B1 (Stick Build) Remaining Tie-ins post Mech Side Aisle install Not Started 06/23/27 07/21/27 25.0 25.0
0%
120.0
RPL09.WP3B.013480 RPL09.Conn EF2<>DHB.12 Install (A-End) Pigtails (384F) P2&3 (LV) EF2<>DHB.12 Not Started 06/23/27 06/23/27 1.2 1.2
0%
222.5
RPL09.WP4.010720 RPL09.Conn DHB.11.03<>03 Pull Simplex Jumper (SC<>LC) [PON (Active, In-Row)] Jumpers Not Started 06/23/27 06/25/27 3.8 3.8
0%
227.5
RPL09.WP4.010740 RPL09.Conn DHB.12.06<>05 Pull Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] Across-Row Not Started 06/23/27 06/28/27 5.0 5.0
0%
227.5
RPL.09.D.93340.XR Pull and Term MV Skids - RPL09 DHD Receive Milestones (XREFs) Not Started 06/24/27 06/24/27 0.0 0.0
0%
223.8
RPL.09.D.93840.XR 100MW Cx Temp Power to MV Skids RPL09 DHD Available Receive Milestones (XREFs) Not Started 06/24/27 06/24/27 0.0 0.0
0%
223.8
RPL09.INT.CC.9040 RPL09.Interior.CC Ext. LO #17 - Tape Finish Paint Exterior Leave Out Wall #17 (CC - South) Not Started 06/24/27 06/30/27 6.2 6.2
0%
141.2
RPL09.INT.DHC.01230 RPL09.Interior.DHC - Control Fault Domain 1 - Install LV Side Aisle HAC Busway LV Side Tie-ins Not Started 06/24/27 06/30/27 6.2 6.2
0%
223.8
RPL09.INT.ENDC.01300 RPL09.Interior.End-Corridor - DAS (Distribution Antenna System) Fit out Not Started 06/24/27 06/30/27 6.2 6.2
0%
256.2
RPL09.WP3B.014920 RPL09.Conn EF2<>DHB.12 Splice (A-End) Pigtails (384F) P2&3 (LV) EF2<>DHB.12 Not Started 06/24/27 07/01/27 7.5 7.5
0%
222.5
RPL09.WP3B.016360 RPL09.Conn EF2<>DHB.12 Install (Z-End) Pigtails (384F) P2&3 (LV) EF2<>DHB.12 Not Started 06/24/27 06/24/27 1.2 1.2
0%
222.5
RPL09.EY.ENDC.1950 RPL09.EY.DHD.T1 - HAC Prefab prior to install for DH D Tent 1 Not Started 06/25/27 07/09/27 12.5 12.5
0%
138.8
RPL09.INT.DHA.03620 RPL09.Interior.DHA - OFE - Control Fault Domain 3 (HAC) Control Fault Domain 3 Not Started 06/25/27 07/09/27 12.5 12.5
0%
90.0
RPL09.INT.DHB.02660 RPL09.Interior.DHB - OFE - Control Fault Domain 5 (HAC) Control Fault Domain 5 Not Started 06/25/27 07/09/27 12.5 12.5
0%
130.0
RPL09.INT.DHC.01210 RPL09.Interior.DHC - OFE - Control Fault Domain 2 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary Control Fault Domain 2 Not Started 06/25/27 09/14/27 70.0 70.0
0%
126.2
RPL09.INT.DHC.01250 RPL09.Interior.DHC - Control Fault Domain 1 - Install LV Side Aisle Cable Tray LV Side Tie-ins Not Started 06/25/27 07/01/27 6.2 6.2
0%
223.8
RPL09.INT.DHC.02330 RPL09.Interior.DHC - OFE - Control Fault Domain 2 (LV Side Aisle) Control Fault Domain 2 Not Started 06/25/27 06/30/27 5.0 5.0
0%
176.2
RPL09.INT.SBC.03840 RPL09.Interior.SSB-Corridor - BoW - Install Remaining Lights Balance of Walls & Overhead Not Started 06/25/27 07/09/27 12.5 12.5
0%
142.5
RPL09.EY.DHA.01340 RPL09.EY.DHA - Install Lighting Hardscape and Landscape Not Started 06/28/27 07/12/27 12.5 12.5
0%
240.0
RPL09.EY.DHB.01390 RPL09.EY.DHB - Install Remaining EY Paving Hardscape and Landscape Not Started 06/28/27 07/02/27 6.2 6.2
0%
240.0
RPL09.EY.DHC.01290 RPL09.EY.DHC - MV Loop - L2 Checklist Completion Tie-ins Not Started 06/28/27 07/12/27 12.5 12.5
0%
218.8
RPL09.EY.DHD.01330 RPL09.EY.DHD - Install Early EY Paving Hardscape and Landscape Not Started 06/28/27 07/02/27 6.2 6.2
0%
333.8
RPL09.INT.CTRC.06860 RPL09.Interior.Center-Corridor - Final Finishes & Fixtures - Install Cement Board/ Drywall Restrooms Not Started 06/28/27 07/02/27 6.2 6.2
0%
117.5
RPL09.INT.ENDC.01370 RPL09.Interior.End-Corridor - Asset Tagging Fit out Not Started 06/28/27 07/12/27 12.5 12.5
0%
256.2
RPL09.INT.SSB.01520 RPL09.Interior.SSB - Loading Dock and Storage - Install Shelving Loading Dock and Storage Not Started 06/28/27 07/01/27 5.0 5.0
0%
233.8
RPL09.INT.SSB.01550 RPL09.Interior.SSB - BoW - Install TVs and Conf Sound Balance of Walls and OverHead Not Started 06/28/27 07/02/27 6.2 6.2
0%
232.5
RPL09.INT.SSB.01560 RPL09.Interior.SSB - BoW - Install & QC Asset Tags Balance of Walls and OverHead Not Started 06/28/27 06/29/27 2.5 2.5
0%
188.8
RPL09.INT.SSB.14640 RPL09.Interior.SSB LO #01 to #05 - Electrical L2 Checklist Completion Finishes Not Started 06/28/27 07/12/27 12.5 12.5
0%
168.8
RPL09.WP4.010900 RPL09.Conn DHB.11.02<>01 Pull Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] Across-Row Not Started 06/28/27 07/01/27 5.0 5.0
0%
227.5
RPL09.CX.MCUP.01370 RPL09.CX.mCup Loop 2 - L3/L4 - mCUP - Flush and Fill - DHD & DHC - Loop 2 (Phase 4) Fill and Flush Not Started 06/29/27 07/06/27 6.2 6.2
0%
252.5
RPL09.EY.DHA.01590 RPL09.EY.DHC - Install Mechanical/ refrigerantTie-ins Build back Exterior Leave Out #17 (South) Not Started 06/29/27 07/06/27 6.2 6.2
0%
198.8
RPL09.EY.DHA.02000 RPL09.EY.DHA - Exterior Leave Out #17 (CC - South) WBS Summary Build back Exterior Leave Out #17 (South) Not Started 06/29/27 07/27/27 25.0 25.0
0%
198.8
RPL09.EY.DHB.01470 RPL09.EY.DHB - Remaining L2 Checklist Completion Tie-ins Not Started 06/29/27 07/06/27 6.2 6.2
0%
212.5
RPL09.INT.DHC.01270 RPL09.Interior.DHC - Control Fault Domain 2 - Install Duct (LV Side) LV Side Tie-ins Not Started 06/29/27 07/02/27 5.0 5.0
0%
228.8
RPL09.INT.DHC.01300 RPL09.Interior.DHC - Tie-ins - Control Fault Domain 2 - WBS Summary Control Fault Domain 2 Not Started 06/29/27 11/09/27 117.5 117.5
0%
161.2
RPL09.INT.ENDC.1520 RPL09.Interior.End-Corridor - BoW - Install Backing at Exterior Wall Balance of Walls & Overhead Not Started 06/29/27 07/06/27 6.2 6.2
0%
218.8
RPL09.INT.ENDC.6180 RPL09.Interior.End-Corridor - BoW - Electrical Tie-In Balance of Walls & Overhead Not Started 06/29/27 07/06/27 6.2 6.2
0%
271.2
RPL09.INT.SSB.02200 RPL09.Interior.SSB - Final Finishes & Fixtures - Mechanical L2 Checklist Completion Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) Not Started 06/29/27 07/13/27 12.5 12.5
0%
295.0
RPL09.WP4.011220 RPL09.Conn DHB.12.07<>07 Pull Simplex Jumper (SC<>LC) [PON (Active, In-Row)] Jumpers Not Started 06/29/27 07/01/27 3.8 3.8
0%
227.5
RPL09.CX.DHB.01280 RPL09.CX.DHB - L3/L4 - Control Fault Domain 01 - TW Flush and Fill Control Fault Domain 1 Not Started 06/30/27 07/12/27 10.0 10.0
0%
127.5
RPL09.CX.DHB.01320 RPL09.CX.DHB - L3/L4 - Control Fault Domain 02 - FW Flush and Fill Control Fault Domain 2 Not Started 06/30/27 07/09/27 8.8 8.8
0%
138.8
RPL09.INT.CTRC.1580 RPL09.Interior.Center-Corridor - BoW - Tape Finish Paint Balance of Walls & Overhead Not Started 06/30/27 07/02/27 3.8 3.8
0%
143.8
RPL09.INT.DHA.01250 RPL09.Interior.DHA - Control Fault Domain 1 - Install Copper from GS.IDF to BMS and EPMS panels Remaining Tie-ins post Mech Side Aisle install Not Started 06/30/27 07/28/27 25.0 25.0
0%
80.0
RPL09.INT.DHA.01270 RPL09.Interior.DHA - Control Fault Domain 2 - Install Vesda / FA Remaining Tie-ins post Mech Side Aisle install Not Started 06/30/27 07/28/27 25.0 25.0
0%
105.0
RPL09.INT.DHA.01280 RPL09.Interior.DHA - Control Fault Domain 2 - Install FW Remaining Tie-ins post Mech Side Aisle install Not Started 06/30/27 07/28/27 25.0 25.0
0%
92.5
RPL09.INT.DHA.02200 RPL09.Interior.DHA - Control Fault Domain 2 - Install TW Remaining Tie-ins post Mech Side Aisle install Not Started 06/30/27 07/28/27 25.0 25.0
0%
92.5
RPL09.INT.DHA.03640 RPL09.Interior.DHA - OFE - Control Fault Domain 3 (Mech Side Aisle) Control Fault Domain 3 Not Started 06/30/27 07/12/27 10.0 10.0
0%
106.2
RPL09.INT.DHA.03820 RPL09.Interior.DHA - Control Fault Domain 2 - Install Duct (MES Side) Remaining Tie-ins post Mech Side Aisle install Not Started 06/30/27 07/28/27 25.0 25.0
0%
92.5
RPL09.INT.DHB.01570 RPL09.Interior.DHB - Control Fault Domain 2 - L2 Checklist Completion Remaining Tie-ins post Mech Side Aisle install Not Started 06/30/27 07/28/27 25.0 25.0
0%
106.2