Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL09 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:12 PM · 5201 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
0
Completed
0
In Progress
0
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL09.INT.DHB.01590 RPL09.Interior.DHB - Control Fault Domain 3 - Install Mechanical Side Aisle Cable Tray Remaining Tie-ins post Mech Side Aisle install Not Started 06/30/27 07/28/27 25.0 25.0
0%
158.8
RPL09.INT.DHB.01620 RPL09.Interior.DHB - Control Fault Domain 3 - Install copper from GS.IDF to BMS and EPMS panels (UG from Center IDF) Remaining Tie-ins post Mech Side Aisle install Not Started 06/30/27 07/28/27 25.0 25.0
0%
120.0
RPL09.INT.DHB.01630 RPL09.Interior.DHB - Control Fault Domain 4 - Install Duct (MES Side) Remaining Tie-ins post Mech Side Aisle install Not Started 06/30/27 07/28/27 25.0 25.0
0%
127.5
RPL09.INT.DHB.01640 RPL09.Interior.DHB - Control Fault Domain 4 - Install Vesda / FA Remaining Tie-ins post Mech Side Aisle install Not Started 06/30/27 07/28/27 25.0 25.0
0%
133.8
RPL09.INT.DHB.01650 RPL09.Interior.DHB - Control Fault Domain 4 - Install FW Remaining Tie-ins post Mech Side Aisle install Not Started 06/30/27 07/28/27 25.0 25.0
0%
127.5
RPL09.INT.DHB.02260 RPL09.Interior.DHB - Control Fault Domain 4 - Install TW Remaining Tie-ins post Mech Side Aisle install Not Started 06/30/27 07/28/27 25.0 25.0
0%
127.5
RPL09.INT.SSB.01540 RPL09.Interior.SSB - Loading Dock and Storage - Fire Life Safety Trim Out / Fire Alarm Trim Out Loading Dock and Storage Not Started 06/30/27 07/09/27 8.8 8.8
0%
208.8
RPL09.INT.SSB.03140 RPL09.Interior.SSB - BoW - Install Door (verify with trades if ready to install door) Balance of Walls and OverHead Not Started 06/30/27 07/07/27 6.2 6.2
0%
188.8
RPL09.INT.SSB.06440 RPL09.Interior.SSB LO #16 - Final Paint Leave Out Wall #16 (SSB - North of Loading Dock) Not Started 06/30/27 07/09/27 8.8 8.8
0%
161.2
RPL09.WP3B.014900 RPL09.Conn EF2<>DHB.11 Splice (A-End) Pigtails (384F) P2&3 (LV) EF2<>DHB.11 Not Started 06/30/27 06/30/27 1.2 1.2
0%
223.8
RPL09.CON.WP2.02000 RPL09.Conn - GS EF2 (North) - WBS Summary GS.EF2 (North) Not Started 07/01/27 07/12/27 8.8 8.8
0%
322.5
RPL09.CON.WP2.02200 RPL09.Conn - GS EF2 (North) Set Infrastructure (Wall mounting enclousres, Tier1 Basket Tray, Waterfalls etc.) Infrastructure Not Started 07/01/27 07/06/27 3.8 3.8
0%
322.5
RPL09.CON.WP2.03000 RPL09.Conn - GS EF1 (South) - WBS Summary GS.EF1 (South) Not Started 07/01/27 07/12/27 8.8 8.8
0%
322.5
RPL09.CON.WP2.07820 RPL09.Conn - GS EF1 (South) Set Infrastructure (Wall mounting enclousres, Tier1 Basket Tray, Waterfalls etc.) Infrastructure Not Started 07/01/27 07/06/27 3.8 3.8
0%
322.5
RPL09.INT.CC.9060 RPL09.Interior.CC Ext. LO #17 - Duct Drops / Trim out Exterior Leave Out Wall #17 (CC - South) Not Started 07/01/27 07/02/27 2.5 2.5
0%
143.8
RPL09.INT.CC.9080 RPL09.Interior.CC Ext. LO #17 - Install Remaining Refrigerant Line Exterior Leave Out Wall #17 (CC - South) Not Started 07/01/27 07/01/27 1.2 1.2
0%
172.5
RPL09.INT.CC.9100 RPL09.Interior.CC Ext. LO #17 - Install Remaining Lights Exterior Leave Out Wall #17 (CC - South) Not Started 07/01/27 07/07/27 5.0 5.0
0%
143.8
RPL09.INT.CC.9120 RPL09.Interior.CC Ext. LO #17 - Fire Safing / Wall Finishes Exterior Leave Out Wall #17 (CC - South) Not Started 07/01/27 07/06/27 3.8 3.8
0%
141.2
RPL09.INT.CC.9220 RPL09.Interior.CC Ext. LO #17 - Install Flooring Tiles/Resinous Flooring in specific rooms **?? Exterior Leave Out Wall #17 (CC - South) Not Started 07/01/27 07/06/27 3.8 3.8
0%
145.0
RPL09.INT.DHC.01350 RPL09.Interior.DHC - OFE - Control Fault Domain 3 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary Control Fault Domain 3 Not Started 07/01/27 09/28/27 77.5 77.5
0%
123.8
RPL09.INT.DHC.01370 RPL09.Interior.DHC - Control Fault Domain 2 - Install LV Side Aisle HAC Busway LV Side Tie-ins Not Started 07/01/27 07/07/27 5.0 5.0
0%
237.5
RPL09.INT.DHC.02390 RPL09.Interior.DHC - OFE - Control Fault Domain 3 (LV Side Aisle) Control Fault Domain 3 Not Started 07/01/27 07/07/27 5.0 5.0
0%
183.8
RPL09.INT.ENDC.01360 RPL09.Interior.End-Corridor - Install Lighting Fit out Not Started 07/01/27 07/12/27 8.8 8.8
0%
256.2
RPL09.INT.ENDC.07000 RPL09.Interior.Center-Corridor - Final Finishes & Fixtures - Final Clean Restrooms Not Started 07/01/27 07/07/27 5.0 5.0
0%
268.8
RPL09.INT.SBC.03640 RPL09.Interior.SSB-Corridor - BoW - Install Vertical Tube Steel Support for Cable Tray (IFP Add) Balance of Walls & Overhead Not Started 07/01/27 07/08/27 6.2 6.2
0%
138.8
RPL09.WP3B.017780 RPL09.Conn EF2<>DHB.11 Test Pigtails (384F) P2&3 (LV) EF2<>DHB.11 Not Started 07/01/27 07/02/27 2.5 2.5
0%
223.8
RPL09.WP4.010100 RPL09.Conn DHB.12 Pull Ext. Trunk (384F) [SSW<>JXSW] SSW<>JXSW Not Started 07/01/27 07/01/27 1.2 1.2
0%
225.0
RPL09.WP4.011280 RPL09.Conn DHB.11.02 Pull Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] Jumpers (AI Confirmed) Not Started 07/01/27 07/15/27 12.5 12.5
0%
198.8
RPL09.WP4.011300 RPL09.Conn DHB.12.06 Pull Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] Jumpers (AI Confirmed) Not Started 07/01/27 07/15/27 12.5 12.5
0%
198.8
GCD.RPL09.2251 L3/L4 Finish EY - DHB EY Not Started 07/02/27 07/02/27 0.0 0.0
0%
220.0
RPL09.INT.DHB.02680 RPL09.Interior.DHB - OFE - Control Fault Domain 5 (Mech Side Aisle) Control Fault Domain 5 Not Started 07/02/27 07/14/27 10.0 10.0
0%
131.2
RPL09.INT.DHC.01390 RPL09.Interior.DHC - Control Fault Domain 2 - Install LV Side Aisle Cable Tray LV Side Tie-ins Not Started 07/02/27 07/08/27 5.0 5.0
0%
237.5
RPL09.WP3B.017800 RPL09.Conn EF2<>DHB.12 Test Pigtails (384F) P2&3 (LV) EF2<>DHB.12 Not Started 07/02/27 07/06/27 2.5 2.5
0%
222.5
RPL09.WP4.010260 RPL09.Conn DHB.12 Pull Trunk (192F) [FSW<>SSW] FSW<>SSW Not Started 07/02/27 07/02/27 1.2 1.2
0%
225.0
RPL09.WP4.011900 RPL09.Conn DHB.11.04<>03 Pull Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] Across-Row Not Started 07/02/27 07/08/27 5.0 5.0
0%
227.5
RPL09.WP4.011920 RPL09.Conn DHB.12.08<>07 Pull Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] Across-Row Not Started 07/02/27 07/08/27 5.0 5.0
0%
227.5
GCD.RPL09.4605 L3/L4 Start EY - DHA EY Not Started 07/06/27 07/06/27 0.0 0.0
0%
231.2
GCD.RPL09.5845 RMU Loop Ready for Energization - DHD Loop EY Not Started 07/06/27 07/06/27 0.0 0.0
0%
215.0
ICM.B9.2510.B [SSDCB4] L3/4 Start - DHB Commissioning Not Started 07/06/27 07/06/27 0.0 0.0
0%
220.0
ICM.B9.2550 [SSDCB4] L3/L4 Start mCUP [1-4] - RPL09 Commissioning Not Started 07/06/27 07/06/27 0.0 0.0
0%
402.5
RPL09.CX.DHA.01000 RPL09.CX.DHA - L3, L4, IST - WBS Summary DHA Not Started 07/06/27 05/24/28 277.5 277.5
0%
112.5
RPL09.CX.DHA.01010 RPL09.CX.DHA - L3 - WBS Summary (Electrical) DHA ELECTRICAL Not Started 07/06/27 10/22/27 97.5 97.5
0%
133.8
RPL09.CX.DHA.01020 RPL09.CX.DHA - L3/L4 - MV Skids (10) Loop DHA ELECTRICAL Not Started 07/06/27 07/19/27 12.5 12.5
0%
76.2
RPL09.CX.DHB.01030 RPL09.CX.DHB - L3/L4 - House Power (for electrical) DHB HOUSE POWER Not Started 07/06/27 07/19/27 12.5 12.5
0%
77.5
RPL09.CX.MCUP.01050 RPL09.CX.mCup Loop 1 - L3/L4 - mCUP mCUP 1-4 Not Started 07/06/27 08/12/27 35.0 35.0
0%
82.5
RPL09.EY.DHB.01430 RPL09.EY.DHB - Install Irrigation Hardscape and Landscape Not Started 07/06/27 07/19/27 12.5 12.5
0%
377.5
RPL09.EY.DHB.01440 RPL09.EY.DHB - Install Exterior Signage Hardscape and Landscape Not Started 07/06/27 07/19/27 12.5 12.5
0%
240.0
RPL09.EY.DHC.01300 RPL09.EY.DHC - Install Sleeves MEPL Hardscape and Landscape Not Started 07/06/27 07/12/27 6.2 6.2
0%
333.8
RPL09.EY.DHC.01320 RPL09.EY.DHC - Install Hardscape and Landscape - WBS Summary Hardscape and Landscape Not Started 07/06/27 12/07/27 133.8 133.8
0%
268.8
RPL09.EY.DHD.01340 RPL09.EY.DHD - Install Lighting Hardscape and Landscape Not Started 07/06/27 07/19/27 12.5 12.5
0%
333.8
RPL09.INT.CTRC.06880 RPL09.Interior.Center-Corridor - Final Finishes & Fixtures - Water Proofing/ Tape Paint Restrooms Not Started 07/06/27 07/12/27 6.2 6.2
0%
117.5
RPL09.INT.CTRC.1240 RPL09.Interior.Center-Corridor - BoW - Install Mechanical Piping/ Refrigerant Lowside On-wall Balance of Walls & Overhead Not Started 07/06/27 07/12/27 6.2 6.2
0%
158.8
RPL09.INT.CTRC.1600 RPL09.Interior.Center-Corridor - BoW - Electrical Trim Out Balance of Walls & Overhead Not Started 07/06/27 07/14/27 8.8 8.8
0%
172.5
RPL09.INT.CTRC.1620 RPL09.Interior.Center-Corridor - BoW - Security Trim Out Balance of Walls & Overhead Not Started 07/06/27 07/14/27 8.8 8.8
0%
172.5
RPL09.INT.CTRC.1640 RPL09.Interior.Center-Corridor - BoW - Duct Drops / Trim out Balance of Walls & Overhead Not Started 07/06/27 07/12/27 6.2 6.2
0%
150.0
RPL09.INT.CTRC.1680 RPL09.Interior.Center-Corridor - BoW - Install DAS (Distribution Antenna System) Balance of Walls & Overhead Not Started 07/06/27 07/12/27 6.2 6.2
0%
143.8
RPL09.INT.CTRC.1740 RPL09.Interior.Center-Corridor - BoW - Install Remaining Lights Balance of Walls & Overhead Not Started 07/06/27 07/19/27 12.5 12.5
0%
143.8
RPL09.INT.DHC.01410 RPL09.Interior.DHC - Control Fault Domain 3 - Install Duct (LV Side) LV Side Tie-ins Not Started 07/06/27 07/09/27 5.0 5.0
0%
240.0
RPL09.INT.DHC.01440 RPL09.Interior.DHC - Tie-ins - Control Fault Domain 3 (including IDF) - WBS Summary Control Fault Domain 3 Not Started 07/06/27 11/17/27 118.8 118.8
0%
185.0
RPL09.INT.SSB.14660 RPL09.Interior.SSB LO #01 to #05 - Mechanical L2 Checklist Completion Finishes Not Started 07/06/27 07/19/27 12.5 12.5
0%
168.8
RPL09.WP4.010420 RPL09.Conn DHB.12 Pull Trunk (384F) [RSW<>FSW] Trunks Not Started 07/06/27 07/06/27 1.2 1.2
0%
225.0
DCC.B9.3300 [SSDCB4] Cabling Start : OSP Pathways - Primary GS Connectivity Not Started 07/07/27 07/07/27 0.0 0.0
0%
401.2
DCC.B9.3707 [SSDCB4] Cabling Start : General Services (GS) Connectivity Not Started 07/07/27 07/07/27 0.0 0.0
0%
401.2
RPL.09.D.93330.XR Pull and Term MV Skids - RPL09 DHC Receive Milestones (XREFs) Not Started 07/07/27 07/07/27 0.0 0.0
0%
223.8
RPL.09.D.93830.XR 100MW Cx Temp Power to MV Skids RPL09 DHC Available Receive Milestones (XREFs) Not Started 07/07/27 07/07/27 0.0 0.0
0%
223.8
RPL.GF.D.N9140.XR Fiber Pulls, Test & Term to Prod EF1 Complete RPL 10 to RPL09 Receive Milestones (XREFs) Not Started 07/07/27 07/07/27 0.0 0.0
0%
322.5
RPL.GF.D.N9150.XR Fiber Pulls, Test & Term to Prod EF2 Complete RPL 10 to RPL09 Receive Milestones (XREFs) Not Started 07/07/27 07/07/27 0.0 0.0
0%
322.5
RPL09.CON.WP2.02400 RPL09.Conn - GS EF2 (North) Install Cabling (Pull, Splice & Terminate) Cabling Not Started 07/07/27 07/12/27 5.0 5.0
0%
322.5
RPL09.CON.WP2.07240 RPL09.Conn - Ext. GSIDF9X01 - Install Cabling (Pull, Splice & terminate) Cabling Not Started 07/07/27 07/14/27 7.5 7.5
0%
390.0
RPL09.CON.WP2.07440 RPL09.Conn - Ext. GSIDF9X02 - Install Cabling (Pull, Splice & terminate) Cabling Not Started 07/07/27 07/14/27 7.5 7.5
0%
390.0
RPL09.CON.WP2.07840 RPL09.Conn - GS EF1 (South) Install Cabling (Pull, Splice & Terminate) Cabling Not Started 07/07/27 07/12/27 5.0 5.0
0%
322.5
RPL09.CON.WP2.08420 RPL09.Conn - Ext. GSIDF9X03 - Install Cabling (Pull, Splice & terminate) Cabling Not Started 07/07/27 07/14/27 7.5 7.5
0%
390.0
RPL09.CON.WP2.08480 RPL09.Conn - Ext. GSIDF9X04 - Install Cabling (Pull, Splice & terminate) Cabling Not Started 07/07/27 07/22/27 15.0 15.0
0%
382.5
RPL09.CX.MCUP.01270 RPL09.CX.mCup Loop 2 - L3/L4 - mCUP - Flush and Fill - mCup5 and Dry Coolers Fill and Flush Not Started 07/07/27 07/14/27 7.5 7.5
0%
362.5
RPL09.CX.MCUP.01330 RPL09.CX.mCup Loop 2 - L3/L4 - mCUP - Flush and Fill - mCup6 and Dry Coolers Fill and Flush Not Started 07/07/27 07/14/27 7.5 7.5
0%
362.5
RPL09.EY.DHA.01610 RPL09.EY.DHC - Install Electrical Tie-ins Build back Exterior Leave Out #17 (South) Not Started 07/07/27 07/13/27 6.2 6.2
0%
198.8
RPL09.INT.CC.9140 RPL09.Interior.CC Ext. LO #17 - Electrical Trim Out Exterior Leave Out Wall #17 (CC - South) Not Started 07/07/27 07/07/27 1.2 1.2
0%
141.2
RPL09.INT.CC.9160 RPL09.Interior.CC Ext. LO #17 - Security Trim Out Exterior Leave Out Wall #17 (CC - South) Not Started 07/07/27 07/07/27 1.2 1.2
0%
141.2
RPL09.INT.ENDC.1540 RPL09.Interior.End-Corridor - BoW - QC - Backings/Walls Balance of Walls & Overhead Not Started 07/07/27 07/13/27 6.2 6.2
0%
218.8
RPL09.CX.DHA.01090 RPL09.CX.DHA - L4 - WBS Summary (Mechanical) DHA MECHANICAL Not Started 07/08/27 02/11/28 186.2 186.2
0%
42.5
RPL09.CX.DHA.01260 RPL09.CX.DHA - L3/L4 - Control Fault Domain 01 - FW Flush and Fill Control Fault Domain 1 Not Started 07/08/27 07/16/27 8.8 8.8
0%
123.8
RPL09.INT.CTRC.1700 RPL09.Interior.Center-Corridor - BoW - Plumbing Trim Out Balance of Walls & Overhead Not Started 07/08/27 07/14/27 6.2 6.2
0%
172.5
RPL09.INT.CTRC.1720 RPL09.Interior.Center-Corridor - BoW - Fire Life Safety Trim Out / Fire Alarm Trim Out Balance of Walls & Overhead Not Started 07/08/27 07/16/27 8.8 8.8
0%
172.5
RPL09.INT.CTRC.2000 RPL09.Interior.Center-Corridor LO #10 & #12 - Close Interior Leave Out #10 DHB/CC (For HACs in DHB) WBS Summary Interior Leave Out Wall #10, #12 (DHB/CC) Not Started 07/08/27 08/19/27 38.8 38.8
0%
130.0
RPL09.INT.CTRC.2520 RPL09.Interior.Center-Corridor LO #10 & #12 - Install IMP Wall at Leave Out (DH B) Interior Leave Out Wall #10, #12 (DHB/CC) Not Started 07/08/27 07/12/27 3.8 3.8
0%
130.0
RPL09.INT.CTRC.2540 RPL09.Interior.Center-Corridor LO #10 & #12 - Tie In MEPF with IMP Wall buildback Interior Leave Out Wall #10, #12 (DHB/CC) Not Started 07/08/27 07/13/27 5.0 5.0
0%
130.0
RPL09.INT.DHA.01290 RPL09.Interior.DHA - Control Fault Domain 1 - L2 Checklist Completion Remaining Tie-ins post Mech Side Aisle install Not Started 07/08/27 08/04/27 25.0 25.0
0%
80.0
RPL09.INT.DHA.01310 RPL09.Interior.DHA - Control Fault Domain 2 - Pull BMS from panel to devices Remaining Tie-ins post Mech Side Aisle install Not Started 07/08/27 08/04/27 25.0 25.0
0%
105.0
RPL09.INT.DHA.01320 RPL09.Interior.DHA - Control Fault Domain 2 - Pull EMPS from panel to devices Remaining Tie-ins post Mech Side Aisle install Not Started 07/08/27 08/04/27 25.0 25.0
0%
105.0
RPL09.INT.DHA.01330 RPL09.Interior.DHA - Control Fault Domain 2 - Set UPS and Panel (2) Remaining Tie-ins post Mech Side Aisle install Not Started 07/08/27 08/04/27 25.0 25.0
0%
92.5
RPL09.INT.DHB.01670 RPL09.Interior.DHB - Control Fault Domain 4 - Pull BMS from panel to devices Remaining Tie-ins post Mech Side Aisle install Not Started 07/08/27 08/04/27 25.0 25.0
0%
133.8
RPL09.INT.DHB.01680 RPL09.Interior.DHB - Control Fault Domain 4 - Pull EMPS from panel to devices Remaining Tie-ins post Mech Side Aisle install Not Started 07/08/27 08/04/27 25.0 25.0
0%
133.8
RPL09.INT.DHB.01690 RPL09.Interior.DHB - Control Fault Domain 4 - Set UPS and Panel (2) Remaining Tie-ins post Mech Side Aisle install Not Started 07/08/27 08/04/27 25.0 25.0
0%
127.5
RPL09.INT.DHB.01710 RPL09.Interior.DHB - Control Fault Domain 3 - L2 Checklist Completion Remaining Tie-ins post Mech Side Aisle install Not Started 07/08/27 08/04/27 25.0 25.0
0%
120.0
RPL09.INT.DHC.01490 RPL09.Interior.DHC - OFE - Control Fault Domain 4 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary Control Fault Domain 4 Not Started 07/08/27 10/12/27 85.0 85.0
0%
121.2
RPL09.INT.DHC.01510 RPL09.Interior.DHC - Control Fault Domain 3 - Install LV Side Aisle HAC Busway LV Side Tie-ins Not Started 07/08/27 07/13/27 5.0 5.0
0%
280.0
RPL09.INT.DHC.02450 RPL09.Interior.DHC - OFE - Control Fault Domain 4 (LV Side Aisle) Control Fault Domain 4 Not Started 07/08/27 07/13/27 5.0 5.0
0%
191.2
RPL09.INT.ENDC.06980 RPL09.Interior.Center-Corridor - Final Finishes & Fixtures - Final Punch Walk Restrooms Not Started 07/08/27 07/09/27 2.5 2.5
0%
268.8
RPL09.INT.SSB.02600 RPL09.Interior.SSB - BoW - ACT - Close Up Inspection Balance of Walls and OverHead Not Started 07/08/27 07/14/27 6.2 6.2
0%
188.8
RPL09.INT.CC.9180 RPL09.Interior.CC Ext. LO #17 - Plumbing Trim Out Exterior Leave Out Wall #17 (CC - South) Not Started 07/09/27 07/09/27 1.2 1.2
0%
141.2