Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL09 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:12 PM
· 5201 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
0
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL09.INT.CTRC.07160 |
RPL09.Interior.Center-Corridor (N) - Install Cable Tray - North (Remaining at LO) | Fit out (North) | Not Started | 07/21/27 | 07/27/27 | 6.2 | 6.2 |
|
170.0 |
RPL09.INT.CTRC.07180 |
RPL09.Interior.Center-Corridor (S) - Install Cable Tray - South (Remaining at LO) | Fit out (South) | Not Started | 07/21/27 | 07/27/27 | 6.2 | 6.2 |
|
170.0 |
RPL09.INT.DHC.01670 |
RPL09.Interior.DHC - Control Fault Domain 4 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 07/21/27 | 07/26/27 | 5.0 | 5.0 |
|
287.5 |
RPL09.INT.SBC.03680 |
RPL09.Interior.SSB-Corridor - BoW - Install Door (Verify with Trades before installation) | Balance of Walls & Overhead | Not Started | 07/21/27 | 07/29/27 | 8.8 | 8.8 |
|
142.5 |
RPL09.WP4.011700 |
RPL09.Conn DHB.13 Pull Trunk (192F) [FSW<>SSW] | FSW<>SSW | Not Started | 07/21/27 | 07/21/27 | 1.2 | 1.2 |
|
210.0 |
RPL09.WP4.011720 |
RPL09.Conn DHB.14 Pull Trunk (192F) [FSW<>SSW] | FSW<>SSW | Not Started | 07/21/27 | 07/21/27 | 1.2 | 1.2 |
|
210.0 |
RPL09.WP4.012220 |
RPL09.Conn DHB.13.09<>09 Pull Simplex Jumper (SC<>LC) [PON (Active, In-Row)] | Jumpers | Not Started | 07/21/27 | 07/23/27 | 3.8 | 3.8 |
|
200.0 |
RPL09.WP4.012240 |
RPL09.Conn DHB.14.13<>13 Pull Simplex Jumper (SC<>LC) [PON (Active, In-Row)] | Across-Row | Not Started | 07/21/27 | 07/23/27 | 3.8 | 3.8 |
|
200.0 |
RPL09.WP4.012260 |
RPL09.Conn DHB.13 Install Ext. Trunk (24F) [PON (Passive, In-Rack)] | In-Rack | Not Started | 07/21/27 | 07/23/27 | 3.8 | 3.8 |
|
218.8 |
RPL09.WP4.012280 |
RPL09.Conn DHB.14 Install Ext. Trunk (24F) [PON (Passive, In-Rack)] | In-Rack | Not Started | 07/21/27 | 07/23/27 | 3.8 | 3.8 |
|
218.8 |
DCC.B9.3025 |
[SSDCB4] Production Gear Delivered [DHA] Front End (SSW &FSW) | Connectivity | Not Started | 07/22/27 | 07/22/27 | 0.0 | 0.0 |
|
207.5 |
RPL09.CON.WP2.08720 |
RPL09.Conn - GSIDF/DH B1 - WBS Summary | INT IDF Stick Build - GSIDF9B1 | Not Started | 07/22/27 | 08/13/27 | 21.2 | 21.2 |
|
366.2 |
RPL09.CON.WP2.08740 |
RPL09.Conn - GSIDF/DH B1 - Install Infrastructure (Racks, Waterfalls etc.) | Infrastructure | Not Started | 07/22/27 | 07/28/27 | 6.2 | 6.2 |
|
196.2 |
RPL09.CON.WP2.11020 |
RPL09.Conn - GSMDF1(South)<>DH B - CFD1 Rack #01 Pull, Install & Test PON Trunks | MDF1 <> DH B - Rack#01 MES side | Not Started | 07/22/27 | 07/26/27 | 3.8 | 3.8 |
|
196.2 |
RPL09.CON.WP2.12020 |
RPL09.Conn - GSMDF2(North)<>DH B - CFD1 Rack #50 Pull, Install & Patch PON Trunks | MDF2 <> DH B - Rack#50 LV side | Not Started | 07/22/27 | 07/28/27 | 6.2 | 6.2 |
|
183.8 |
RPL09.CON.WP3B.01040 |
RPL09.Conn WP#3B - ISP DHA - WBS Summary | DHA | Not Started | 07/22/27 | 10/29/27 | 88.8 | 88.8 |
|
131.2 |
RPL09.CON.WP3B.01140 |
RPL09.Conn EF2<>DHB14 - WBS Summary | EF2<>DHB.14 | Not Started | 07/22/27 | 08/05/27 | 13.8 | 13.8 |
|
195.0 |
RPL09.CON.WP4.03000 |
RPL09.Conn - DH A Network - WBS Summary | DH A | Not Started | 07/22/27 | 12/03/27 | 116.2 | 116.2 |
|
116.2 |
RPL09.CON.WP4.03020 |
RPL09.Conn WP4 FENW DHA CFD1 Infrastructure | Infrastructure | Not Started | 07/22/27 | 08/18/27 | 25.0 | 25.0 |
|
207.5 |
RPL09.INT.CTRC.06920 |
RPL09.Interior.Center-Corridor - Final Finishes & Fixtures - Fixture Install (Lights) | Restrooms | Not Started | 07/22/27 | 07/30/27 | 8.8 | 8.8 |
|
141.2 |
RPL09.INT.CTRC.06940 |
RPL09.Interior.Center-Corridor - Final Finishes & Fixtures - Framing RO Verification, Tile Finish & ADA Verification (P | Restrooms | Not Started | 07/22/27 | 07/28/27 | 6.2 | 6.2 |
|
117.5 |
RPL09.INT.CTRC.1760 |
RPL09.Interior.Center-Corridor - BoW - Install Flooring Tiles/Resinous Flooring in specific rooms | Balance of Walls & Overhead | Not Started | 07/22/27 | 07/30/27 | 8.8 | 8.8 |
|
141.2 |
RPL09.INT.CTRC.2720 |
RPL09.Interior.Center-Corridor LO #10 & #12 - Install Security Lowside OH | Interior Leave Out Wall #10, #12 (DHB/CC) | Not Started | 07/22/27 | 07/26/27 | 3.8 | 3.8 |
|
135.0 |
RPL09.INT.CTRC.2760 |
RPL09.Interior.Center-Corridor LO #10 & #12 - Install Controls / EPMS / BMS OH | Interior Leave Out Wall #10, #12 (DHB/CC) | Not Started | 07/22/27 | 07/26/27 | 3.8 | 3.8 |
|
130.0 |
RPL09.INT.DHA.01200 |
RPL09.Conn DHA - CFD1 - Set Passive Racks for WP#3b (16) | Infrastructure | Not Started | 07/22/27 | 07/26/27 | 3.8 | 3.8 |
|
176.2 |
RPL09.INT.DHA.01390 |
RPL09.Interior.DHA - Control Fault Domain 2 - Install Copper from GS.IDF to BMS and EPMS panels | Remaining Tie-ins post Mech Side Aisle install | Not Started | 07/22/27 | 08/18/27 | 25.0 | 25.0 |
|
92.5 |
RPL09.INT.DHA.01440 |
RPL09.Interior.DHA - Control Fault Domain 3 - Pull BMS from panel to devices | Remaining Tie-ins post Mech Side Aisle install | Not Started | 07/22/27 | 08/18/27 | 25.0 | 25.0 |
|
112.5 |
RPL09.INT.DHA.01450 |
RPL09.Interior.DHA - Control Fault Domain 3 - Pull EMPS from panel to devices | Remaining Tie-ins post Mech Side Aisle install | Not Started | 07/22/27 | 08/18/27 | 25.0 | 25.0 |
|
112.5 |
RPL09.INT.DHA.01460 |
RPL09.Interior.DHA - Control Fault Domain 3 - Set UPS and Panel (2) and GS.IDF B1 (Stick Build) | Remaining Tie-ins post Mech Side Aisle install | Not Started | 07/22/27 | 08/18/27 | 25.0 | 25.0 |
|
106.2 |
RPL09.INT.DHA.03880 |
RPL09.Conn DHA - CFD1 - Set Passive Racks for PON (16) | Infrastructure | Not Started | 07/22/27 | 07/26/27 | 3.8 | 3.8 |
|
191.2 |
RPL09.INT.DHB.01850 |
RPL09.Interior.DHB - Control Fault Domain 4 - L2 Checklist Completion | Remaining Tie-ins post Mech Side Aisle install | Not Started | 07/22/27 | 08/18/27 | 25.0 | 25.0 |
|
127.5 |
RPL09.INT.SSB.03160 |
RPL09.Interior.SSB - BoW - Final Paint | Balance of Walls and OverHead | Not Started | 07/22/27 | 07/28/27 | 6.2 | 6.2 |
|
188.8 |
RPL09.INT.SSBC.01300 |
RPL09.Interior.SSB-Corridor - Install DAS (Distribution Antenna System) | Fit out | Not Started | 07/22/27 | 07/28/27 | 6.2 | 6.2 |
|
142.5 |
RPL09.INT.SSBC.01310 |
RPL09.Interior.SSB-Corridor - Install Lighting | Fit out | Not Started | 07/22/27 | 07/30/27 | 8.8 | 8.8 |
|
142.5 |
RPL09.WP3B.012080 |
RPL09.Conn EF2<>DHB.14 Pull Pigtails (384F) P2&3 (LV) | EF2<>DHB.14 | Not Started | 07/22/27 | 07/23/27 | 2.5 | 2.5 |
|
185.0 |
RPL09.WP3B.013500 |
RPL09.Conn EF2<>DHB.13 Install (A-End) Pigtails (384F) P2&3 (LV) | EF2<>DHB.13 | Not Started | 07/22/27 | 07/22/27 | 1.2 | 1.2 |
|
197.5 |
RPL09.WP4.011980 |
RPL09.Conn DHB.13 Pull Trunk (384F) [RSW<>FSW] | Trunks | Not Started | 07/22/27 | 07/22/27 | 1.2 | 1.2 |
|
210.0 |
RPL09.WP4.012000 |
RPL09.Conn DHB.14 Pull Trunk (384F) [RSW<>FSW] | Trunks | Not Started | 07/22/27 | 07/22/27 | 1.2 | 1.2 |
|
210.0 |
RPL09.CON.WP2.08500 |
RPL09.Conn - Ext. GSIDF9X04 - Install & Test Network (FIM) | Network | Not Started | 07/23/27 | 07/27/27 | 3.8 | 3.8 |
|
382.5 |
RPL09.EY.SSB.01280 |
RPL09.EY.SSB - Install Curb and Gutter | Hardscape and Landscape | Not Started | 07/23/27 | 08/05/27 | 12.5 | 12.5 |
|
161.2 |
RPL09.INT.CTRC.01430 |
RPL09.Interior.Center-Corridor (N) - Electrical Trim | Fit out (North) | Not Started | 07/23/27 | 07/28/27 | 5.0 | 5.0 |
|
131.2 |
RPL09.INT.ENDC.1580 |
RPL09.Interior.End-Corridor - BoW - Tape Finish Paint | Balance of Walls & Overhead | Not Started | 07/23/27 | 07/27/27 | 3.8 | 3.8 |
|
218.8 |
RPL09.WP3B.014940 |
RPL09.Conn EF2<>DHB.13 Splice (A-End) Pigtails (384F) P2&3 (LV) | EF2<>DHB.13 | Not Started | 07/23/27 | 07/30/27 | 7.5 | 7.5 |
|
197.5 |
RPL09.WP3B.016380 |
RPL09.Conn EF2<>DHB.13 Install (Z-End) Pigtails (384F) P2&3 (LV) | EF2<>DHB.13 | Not Started | 07/23/27 | 07/23/27 | 1.2 | 1.2 |
|
197.5 |
RPL09.CX.DHB.01400 |
RPL09.CX.DHB - L3/L4 - Control Fault Domain 03 - TW Flush and Fill | Control Fault Domain 3 | Not Started | 07/26/27 | 08/04/27 | 10.0 | 10.0 |
|
146.2 |
RPL09.EY.ENDC.1970 |
RPL09.EY.DHD.T2 - HAC Prefab prior to install for DH C | Tent 2 | Not Started | 07/26/27 | 08/06/27 | 12.5 | 12.5 |
|
121.2 |
RPL09.INT.CTRC.01420 |
RPL09.Interior.Center-Corridor (N) - Install Battery | Fit out (North) | Not Started | 07/26/27 | 08/06/27 | 12.5 | 12.5 |
|
141.2 |
RPL09.INT.DHA.03740 |
RPL09.Interior.DHA - OFE - Control Fault Domain 5 (HAC) | Control Fault Domain 5 | Not Started | 07/26/27 | 08/06/27 | 12.5 | 12.5 |
|
90.0 |
RPL09.INT.DHB.01810 |
RPL09.Interior.DHB - Control Fault Domain 5 - Pull BMS from panel to devices | Remaining Tie-ins post Mech Side Aisle install | Not Started | 07/26/27 | 08/20/27 | 25.0 | 25.0 |
|
138.8 |
RPL09.INT.DHB.01820 |
RPL09.Interior.DHB - Control Fault Domain 5 - Pull EMPS from panel to devices | Remaining Tie-ins post Mech Side Aisle install | Not Started | 07/26/27 | 08/20/27 | 25.0 | 25.0 |
|
138.8 |
RPL09.INT.DHB.01830 |
RPL09.Interior.DHB - Control Fault Domain 5 - Set UPS and Panel (2) | Remaining Tie-ins post Mech Side Aisle install | Not Started | 07/26/27 | 08/20/27 | 25.0 | 25.0 |
|
131.2 |
RPL09.INT.SBC.03980 |
RPL09.Interior.SSB-Corridor - BoW - Install Flooring Tiles/Resinous Flooring in specific rooms | Balance of Walls & Overhead | Not Started | 07/26/27 | 08/03/27 | 8.8 | 8.8 |
|
138.8 |
RPL09.INT.SBC.06500 |
RPL09.Interior.SSB-Corridor - BoW - QC | Balance of Walls & Overhead | Not Started | 07/26/27 | 07/30/27 | 6.2 | 6.2 |
|
141.2 |
RPL09.INT.SSB.14700 |
RPL09.Interior.SSB LO #01 to #05 - Final Punch Walk | Finishes | Not Started | 07/26/27 | 07/27/27 | 2.5 | 2.5 |
|
168.8 |
RPL09.WP3B.013520 |
RPL09.Conn EF2<>DHB.14 Install (A-End) Pigtails (384F) P2&3 (LV) | EF2<>DHB.14 | Not Started | 07/26/27 | 07/26/27 | 1.2 | 1.2 |
|
195.0 |
RPL09.WP4.012540 |
RPL09.Conn DHB.13.11<>11 Pull Simplex Jumper (SC<>LC) [PON (Active, In-Row)] | Jumpers | Not Started | 07/26/27 | 07/28/27 | 3.8 | 3.8 |
|
200.0 |
RPL09.WP4.012560 |
RPL09.Conn DHB.14.15<>15 Pull Simplex Jumper (SC<>LC) [PON (Active, In-Row)] | Across-Row | Not Started | 07/26/27 | 07/28/27 | 3.8 | 3.8 |
|
200.0 |
DCC.B9.3537 |
[SSDCB4] Cabling Start : Front End Production Cabling [DHA] | Connectivity | Not Started | 07/27/27 | 07/27/27 | 0.0 | 0.0 |
|
225.0 |
GCD.RPL09.4065 |
[RPL09] TC-C Ready : Production Cabling Start [DHA Rows 01-08] | TC-C Ready: Production Cabling - DHA | Not Started | 07/27/27 | 07/27/27 | 0.0 | 0.0 |
|
225.0 |
GCD.RPL09.5605 |
[RPL09] FacNet Live RPL09 - All Exterior IDF huts | TC-C Ready: FacNet Live | Not Started | 07/27/27 | 07/27/27 | 0.0 | 0.0 |
|
382.5 |
GCD.RPL09.5745 |
[RPL09] TC-C Ready : All General Services [RPL09-Exterior IDFs] | TC-C Ready: General Services | Not Started | 07/27/27 | 07/27/27 | 0.0 | 0.0 |
|
382.5 |
RPL09.CON.WP2.11040 |
RPL09.Conn - GSMDF1(South)<>DH B - CFD2 Rack #01 Pull, Install & Test PON Trunks | MDF1 <> DH B - Rack#01 MES side | Not Started | 07/27/27 | 07/29/27 | 3.8 | 3.8 |
|
196.2 |
RPL09.CON.WP2.13020 |
RPL09.Conn - GSMDF1(South)<>DH A - CFD1 Rack #50 Pull, Install & Patch PON Trunks | MDF1 <> DH A - Rack#50 LV side | Not Started | 07/27/27 | 08/02/27 | 6.2 | 6.2 |
|
191.2 |
RPL09.CON.WP2.14020 |
RPL09.Conn - GSMDF2(North)<>DH A - CFD1 Rack #01 Pull, Install & Test PON Trunks | MDF2 <> DH A - Rack#01 MES side | Not Started | 07/27/27 | 07/29/27 | 3.8 | 3.8 |
|
203.8 |
RPL09.CON.WP3A.01000 |
RPL09.Conn - OSP - WBS Summary | WP#3A OSP | Not Started | 07/27/27 | 10/08/27 | 66.2 | 66.2 |
|
317.5 |
RPL09.CON.WP3A.01200 |
RPL09.Conn - Production EF2 (North) - WBS Summary | Prod EF2 (North) | Not Started | 07/27/27 | 09/10/27 | 41.2 | 41.2 |
|
342.5 |
RPL09.CON.WP3A.01620 |
RPL09.Conn EF2 Infrastructure 1 (Racks & Vertical Cable Manager, Ladder Racks) | Infrastructure | Not Started | 07/27/27 | 08/23/27 | 25.0 | 25.0 |
|
168.8 |
RPL09.CON.WP3B.01900 |
RPL09.Conn EF1<>DHA.01 - WBS Summary | EF1<>DHA.01 | Not Started | 07/27/27 | 08/10/27 | 13.8 | 13.8 |
|
202.5 |
RPL09.INT.CTRC.3000 |
RPL09.Interior.Center-Corridor LO #10 & #12 - Install Electrical Lowside OH | Interior Leave Out Wall #10, #12 (DHB/CC) | Not Started | 07/27/27 | 07/30/27 | 5.0 | 5.0 |
|
130.0 |
RPL09.INT.CTRC.7940 |
RPL09.Interior.Center-Corridor LO #10 - Hard Lid Framing | Remaining of LO Wall #10 (Spoke Parts & Spoke Tech) | Not Started | 07/27/27 | 07/29/27 | 3.8 | 3.8 |
|
132.5 |
RPL09.INT.DHD.01140 |
RPL09.Interior.DHD - Control Fault Domain 1 - Install Vesda / FA | Remaining Tie-ins post Mech Side Aisle install | Not Started | 07/27/27 | 08/23/27 | 25.0 | 25.0 |
|
190.0 |
RPL09.INT.DHD.01150 |
RPL09.Interior.DHD - Control Fault Domain 1 - Install FW | Remaining Tie-ins post Mech Side Aisle install | Not Started | 07/27/27 | 08/23/27 | 25.0 | 25.0 |
|
177.5 |
RPL09.INT.DHD.01990 |
RPL09.Interior.DHD - Control Fault Domain 1 - Install TW | Remaining Tie-ins post Mech Side Aisle install | Not Started | 07/27/27 | 08/23/27 | 25.0 | 25.0 |
|
177.5 |
RPL09.INT.DHD.02550 |
RPL09.Interior.DHD - Control Fault Domain 1 - Install Duct (MES Side) | Remaining Tie-ins post Mech Side Aisle install | Not Started | 07/27/27 | 08/23/27 | 25.0 | 25.0 |
|
177.5 |
RPL09.OFCI.C.4060 |
OFCI Delivery: FE Fiber for CFD B.3 (ROJ ) (RVCD ) | Data Hall B | Not Started | 07/27/27 | 08/02/27 | 6.2 | 6.2 |
|
177.5 |
RPL09.WP3B.011100 |
RPL09.Conn EF1<>DHA.01 Pull Pigtails (384F) P1&4 (LV) | EF1<>DHA.01 | Not Started | 07/27/27 | 07/28/27 | 2.5 | 2.5 |
|
191.2 |
RPL09.WP3B.014960 |
RPL09.Conn EF2<>DHB.14 Splice (A-End) Pigtails (384F) P2&3 (LV) | EF2<>DHB.14 | Not Started | 07/27/27 | 08/03/27 | 7.5 | 7.5 |
|
195.0 |
RPL09.WP3B.016400 |
RPL09.Conn EF2<>DHB.14 Install (Z-End) Pigtails (384F) P2&3 (LV) | EF2<>DHB.14 | Not Started | 07/27/27 | 07/27/27 | 1.2 | 1.2 |
|
195.0 |
RPL09.WP4.010760 |
RPL09.Conn DHA.01 Pull Ext. Trunk (384F) [SSW<>JXSW] | SSW<>JXSW | Not Started | 07/27/27 | 07/27/27 | 1.2 | 1.2 |
|
213.8 |
RPL09.WP4.010780 |
RPL09.Conn DHA.02 Pull Ext. Trunk (384F) [SSW<>JXSW] | SSW<>JXSW | Not Started | 07/27/27 | 07/27/27 | 1.2 | 1.2 |
|
213.8 |
RPL09.WP4.011000 |
RPL09.Conn DHA.01.01 Pull Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] | Jumpers (AI Confirmed) | Not Started | 07/27/27 | 08/09/27 | 12.5 | 12.5 |
|
176.2 |
RPL09.WP4.011020 |
RPL09.Conn DHA.02.05 Pull Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] | Jumpers (AI Confirmed) | Not Started | 07/27/27 | 08/09/27 | 12.5 | 12.5 |
|
176.2 |
RPL09.WP4.011320 |
RPL09.Conn DHA.01 Pull Ext. Trunk (24F) [PON (Passive, In-Rack)] | In-Rack | Not Started | 07/27/27 | 07/27/27 | 1.2 | 1.2 |
|
205.0 |
RPL09.WP4.011340 |
RPL09.Conn DHA.02 Pull Ext. Trunk (24F) [PON (Passive, In-Rack)] | In-Rack | Not Started | 07/27/27 | 07/27/27 | 1.2 | 1.2 |
|
205.0 |
RPL09.EY.DHA.01470 |
RPL09.EY.DHA - Remaining L2 Checklist Completion | Tie-ins | Not Started | 07/28/27 | 08/03/27 | 6.2 | 6.2 |
|
198.8 |
RPL09.INT.ENDC.1600 |
RPL09.Interior.End-Corridor - BoW - Electrical Trim Out | Balance of Walls & Overhead | Not Started | 07/28/27 | 08/05/27 | 8.8 | 8.8 |
|
218.8 |
RPL09.INT.ENDC.1620 |
RPL09.Interior.End-Corridor - BoW - Security Trim Out | Balance of Walls & Overhead | Not Started | 07/28/27 | 08/05/27 | 8.8 | 8.8 |
|
218.8 |
RPL09.INT.ENDC.1640 |
RPL09.Interior.End-Corridor - BoW - Duct Drops / Trim out | Balance of Walls & Overhead | Not Started | 07/28/27 | 08/03/27 | 6.2 | 6.2 |
|
218.8 |
RPL09.INT.ENDC.1680 |
RPL09.Interior.End-Corridor - BoW - Install DAS (Distribution Antenna System) | Balance of Walls & Overhead | Not Started | 07/28/27 | 08/03/27 | 6.2 | 6.2 |
|
223.8 |
RPL09.INT.ENDC.1980 |
RPL09.Interior.End-Corridor - BoW - Install Balance Of Refrigerant Line | Balance of Walls & Overhead | Not Started | 07/28/27 | 08/02/27 | 5.0 | 5.0 |
|
247.5 |
RPL09.WP4.011040 |
RPL09.Conn DHA.01 Pull Trunk (192F) [FSW<>SSW] | FSW<>SSW | Not Started | 07/28/27 | 07/28/27 | 1.2 | 1.2 |
|
213.8 |
RPL09.WP4.011060 |
RPL09.Conn DHA.02 Pull Trunk (192F) [FSW<>SSW] | FSW<>SSW | Not Started | 07/28/27 | 07/28/27 | 1.2 | 1.2 |
|
213.8 |
RPL09.WP4.011560 |
RPL09.Conn DHA.01.01<>01 Pull Simplex Jumper (SC<>LC) [PON (Active, In-Row)] | Across-Row | Not Started | 07/28/27 | 07/30/27 | 3.8 | 3.8 |
|
205.0 |
RPL09.WP4.011580 |
RPL09.Conn DHA.02.05<>05 Pull Simplex Jumper (SC<>LC) [PON (Active, In-Row)] | Jumpers | Not Started | 07/28/27 | 07/30/27 | 3.8 | 3.8 |
|
205.0 |
RPL09.WP4.011600 |
RPL09.Conn DHA.01 Install Ext. Trunk (24F) [PON (Passive, In-Rack)] | In-Rack | Not Started | 07/28/27 | 07/30/27 | 3.8 | 3.8 |
|
223.8 |
RPL09.WP4.011620 |
RPL09.Conn DHA.02 Install Ext. Trunk (24F) [PON (Passive, In-Rack)] | In-Rack | Not Started | 07/28/27 | 07/30/27 | 3.8 | 3.8 |
|
223.8 |
GCD.RPL09.4925 |
L3/L4 Finish EY - DHD | EY | Not Started | 07/29/27 | 07/29/27 | 0.0 | 0.0 |
|
310.0 |
RPL09.CON.WP2.08760 |
RPL09.Conn - GSIDF/DH B1 - Install Cabling (Pull, Splice & terminate) | Cabling | Not Started | 07/29/27 | 08/05/27 | 7.5 | 7.5 |
|
370.0 |
RPL09.CON.WP2.08800 |
RPL09.Conn - GSIDF/DH B1 - Install Copper, WAPs, Security Camera & Access Control | Cabling | Not Started | 07/29/27 | 08/13/27 | 15.0 | 15.0 |
|
196.2 |
RPL09.CON.WP2.12040 |
RPL09.Conn - GSMDF2(North)<>DH B - CFD2 Rack #50 Pull, Install & Patch PON Trunks | MDF2 <> DH B - Rack#50 LV side | Not Started | 07/29/27 | 08/04/27 | 6.2 | 6.2 |
|
183.8 |