Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL09 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:12 PM
· 5201 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
0
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL09.INT.SSBC.01550 |
RPL09.Interior.SSB-Corridor - Remaining DHA L2 Checklist Completion | Fit out | Not Started | 08/19/27 | 08/25/27 | 6.2 | 6.2 |
|
188.8 |
RPL09.WP3B.011160 |
RPL09.Conn EF1<>DHA.04 Pull Pigtails (384F) P1&4 (LV) | EF1<>DHA.04 | Not Started | 08/19/27 | 08/19/27 | 1.2 | 1.2 |
|
177.5 |
RPL09.WP3B.012180 |
RPL09.Conn EF2<>DHB.19 Pull Pigtails (384F) P2&3 (LV) | EF2<>DHB.19 | Not Started | 08/19/27 | 08/19/27 | 1.2 | 1.2 |
|
170.0 |
RPL09.WP3B.012580 |
RPL09.Conn EF1<>DHA.03 Install (A-End) Pigtails (384F) P1&4 (LV) | EF1<>DHA.03 | Not Started | 08/19/27 | 08/19/27 | 1.2 | 1.2 |
|
183.8 |
RPL09.WP3B.013600 |
RPL09.Conn EF2<>DHB.18 Install (A-End) Pigtails (384F) P2&3 (LV) | EF2<>DHB.18 | Not Started | 08/19/27 | 08/19/27 | 1.2 | 1.2 |
|
172.5 |
RPL09.WP3B.015020 |
RPL09.Conn EF2<>DHB.17 Splice (A-End) Pigtails (384F) P2&3 (LV) | EF2<>DHB.17 | Not Started | 08/19/27 | 08/26/27 | 7.5 | 7.5 |
|
173.8 |
RPL09.WP3B.016460 |
RPL09.Conn EF2<>DHB.17 Install (Z-End) Pigtails (384F) P2&3 (LV) | EF2<>DHB.17 | Not Started | 08/19/27 | 08/19/27 | 1.2 | 1.2 |
|
173.8 |
RPL09.WP4.013640 |
RPL09.Conn DHA.03 Pull Trunk (384F) [RSW<>FSW] | Trunks | Not Started | 08/19/27 | 08/20/27 | 2.5 | 2.5 |
|
195.0 |
RPL09.WP4.013660 |
RPL09.Conn DHA.04 Pull Trunk (384F) [RSW<>FSW] | Trunks | Not Started | 08/19/27 | 08/20/27 | 2.5 | 2.5 |
|
195.0 |
RPL09.WP4.017040 |
RPL09.Conn DHB.17 Pull Trunk (384F) [RSW<>FSW] | Trunks | Not Started | 08/19/27 | 08/19/27 | 1.2 | 1.2 |
|
185.0 |
RPL09.WP4.017060 |
RPL09.Conn DHB.18 Pull Trunk (384F) [RSW<>FSW] | Trunks | Not Started | 08/19/27 | 08/19/27 | 1.2 | 1.2 |
|
185.0 |
RPL09.CON.WP3B.01380 |
RPL09.Conn EF2<>DHB.20 - WBS Summary | EF2<>DHB.20 | Not Started | 08/20/27 | 09/02/27 | 12.5 | 12.5 |
|
170.0 |
RPL09.EY.SSB.01310 |
RPL09.EY.SSB - Install Lighting | Hardscape and Landscape | Not Started | 08/20/27 | 09/10/27 | 18.8 | 18.8 |
|
161.2 |
RPL09.INT.CTRC.01480 |
RPL09.Interior.Center-Corridor (N) - Electrical L2 Checklist Completion | Fit out (North) | Not Started | 08/20/27 | 09/02/27 | 12.5 | 12.5 |
|
131.2 |
RPL09.INT.CTRC.01770 |
RPL09.Interior.Center-Corridor (S) - Electrical Trim | Fit out (South) | Not Started | 08/20/27 | 08/25/27 | 5.0 | 5.0 |
|
97.5 |
RPL09.INT.CTRC.8120 |
RPL09.Interior.Center-Corridor LO #10 - Install Asset Tags | Remaining of LO Wall #10 (Spoke Parts & Spoke Tech) | Not Started | 08/20/27 | 08/23/27 | 2.5 | 2.5 |
|
140.0 |
RPL09.INT.ENDC.1780 |
RPL09.Interior.End-Corridor - BoW - Install Asset Tags | Balance of Walls & Overhead | Not Started | 08/20/27 | 08/23/27 | 2.5 | 2.5 |
|
228.8 |
RPL09.WP3B.012200 |
RPL09.Conn EF2<>DHB.20 Pull Pigtails (384F) P2&3 (LV) | EF2<>DHB.20 | Not Started | 08/20/27 | 08/20/27 | 1.2 | 1.2 |
|
170.0 |
RPL09.WP3B.012600 |
RPL09.Conn EF1<>DHA.04 Install (A-End) Pigtails (384F) P1&4 (LV) | EF1<>DHA.04 | Not Started | 08/20/27 | 08/20/27 | 1.2 | 1.2 |
|
182.5 |
RPL09.WP3B.013620 |
RPL09.Conn EF2<>DHB.19 Install (A-End) Pigtails (384F) P2&3 (LV) | EF2<>DHB.19 | Not Started | 08/20/27 | 08/20/27 | 1.2 | 1.2 |
|
171.2 |
RPL09.WP3B.014020 |
RPL09.Conn EF1<>DHA.03 Splice (A-End) Pigtails (384F) P1&4 (LV) | EF1<>DHA.03 | Not Started | 08/20/27 | 08/27/27 | 7.5 | 7.5 |
|
183.8 |
RPL09.WP3B.015040 |
RPL09.Conn EF2<>DHB.18 Splice (A-End) Pigtails (384F) P2&3 (LV) | EF2<>DHB.18 | Not Started | 08/20/27 | 08/27/27 | 7.5 | 7.5 |
|
172.5 |
RPL09.WP3B.015460 |
RPL09.Conn EF1<>DHA.03 Install (Z-End) Pigtails (384F) P1&4 (LV) | EF1<>DHA.03 | Not Started | 08/20/27 | 08/20/27 | 1.2 | 1.2 |
|
183.8 |
RPL09.WP3B.016480 |
RPL09.Conn EF2<>DHB.18 Install (Z-End) Pigtails (384F) P2&3 (LV) | EF2<>DHB.18 | Not Started | 08/20/27 | 08/20/27 | 1.2 | 1.2 |
|
172.5 |
RPL09.CX.DHA.01400 |
RPL09.CX.DHA - L3/L4 - Control Fault Domain 03 - TW Flush and Fill | Control Fault Domain 3 | Not Started | 08/23/27 | 09/01/27 | 10.0 | 10.0 |
|
132.5 |
RPL09.INT.CTRC.01990 |
RPL09.Interior.Center-Corridor (S) - Install Battery | Fit out (South) | Not Started | 08/23/27 | 09/03/27 | 12.5 | 12.5 |
|
108.8 |
RPL09.INT.CTRC.1860 |
RPL09.Interior.Center-Corridor - BoW - Final Clean | Balance of Walls & Overhead | Not Started | 08/23/27 | 08/26/27 | 5.0 | 5.0 |
|
141.2 |
RPL09.INT.DHA.01720 |
RPL09.Interior.DHA - Control Fault Domain 5 - Pull BMS from panel to devices | Remaining Tie-ins post Mech Side Aisle install | Not Started | 08/23/27 | 09/20/27 | 25.0 | 25.0 |
|
125.0 |
RPL09.INT.DHA.01730 |
RPL09.Interior.DHA - Control Fault Domain 5 - Pull EMPS from panel to devices | Remaining Tie-ins post Mech Side Aisle install | Not Started | 08/23/27 | 09/20/27 | 25.0 | 25.0 |
|
125.0 |
RPL09.INT.DHA.01740 |
RPL09.Interior.DHA - Control Fault Domain 5 - Set UPS and Panel (2) | Remaining Tie-ins post Mech Side Aisle install | Not Started | 08/23/27 | 09/20/27 | 25.0 | 25.0 |
|
117.5 |
RPL09.WP3B.013640 |
RPL09.Conn EF2<>DHB.20 Install (A-End) Pigtails (384F) P2&3 (LV) | EF2<>DHB.20 | Not Started | 08/23/27 | 08/23/27 | 1.2 | 1.2 |
|
170.0 |
RPL09.WP3B.014040 |
RPL09.Conn EF1<>DHA.04 Splice (A-End) Pigtails (384F) P1&4 (LV) | EF1<>DHA.04 | Not Started | 08/23/27 | 08/30/27 | 7.5 | 7.5 |
|
182.5 |
RPL09.WP3B.015060 |
RPL09.Conn EF2<>DHB.19 Splice (A-End) Pigtails (384F) P2&3 (LV) | EF2<>DHB.19 | Not Started | 08/23/27 | 08/30/27 | 7.5 | 7.5 |
|
171.2 |
RPL09.WP3B.015480 |
RPL09.Conn EF1<>DHA.04 Install (Z-End) Pigtails (384F) P1&4 (LV) | EF1<>DHA.04 | Not Started | 08/23/27 | 08/23/27 | 1.2 | 1.2 |
|
182.5 |
RPL09.WP3B.016500 |
RPL09.Conn EF2<>DHB.19 Install (Z-End) Pigtails (384F) P2&3 (LV) | EF2<>DHB.19 | Not Started | 08/23/27 | 08/23/27 | 1.2 | 1.2 |
|
171.2 |
RPL09.WP4.014760 |
RPL09.Conn DHA.03.11<>11 Pull Simplex Jumper (SC<>LC) [PON (Active, In-Row)] | Jumpers | Not Started | 08/23/27 | 08/25/27 | 3.8 | 3.8 |
|
186.2 |
RPL09.WP4.014780 |
RPL09.Conn DHA.04.15<>15 Pull Simplex Jumper (SC<>LC) [PON (Active, In-Row)] | Jumpers | Not Started | 08/23/27 | 08/25/27 | 3.8 | 3.8 |
|
186.2 |
RPL09.WP4.018140 |
RPL09.Conn DHB.17.27<>27 Pull Simplex Jumper (SC<>LC) [PON (Active, In-Row)] | Jumpers | Not Started | 08/23/27 | 08/25/27 | 3.8 | 3.8 |
|
175.0 |
RPL09.CON.WP3A.01600 |
RPL09.Conn - Production EF1 (South) - WBS Summary | Prod EF1 (South) | Not Started | 08/24/27 | 10/08/27 | 41.2 | 41.2 |
|
317.5 |
RPL09.CON.WP3A.01740 |
RPL09.Conn EF1 Infrastructure 1 (Racks & Vertical Cable Manager, Ladder Racks) | Infrastructure | Not Started | 08/24/27 | 09/21/27 | 25.0 | 25.0 |
|
143.8 |
RPL09.CX.DHD.01080 |
RPL09.CX.DHD - L4 - WBS Summary (Mechanical) | DHD MECHANICAL | Not Started | 08/24/27 | 04/28/28 | 211.2 | 211.2 |
|
77.5 |
RPL09.CX.DHD.01260 |
RPL09.CX.DHD - L3/L4 - Control Fault Domain 01 - FW Flush and Fill | Control Fault Domain 1 | Not Started | 08/24/27 | 09/01/27 | 8.8 | 8.8 |
|
210.0 |
RPL09.CX.SSB.01000 |
RPL09.CX.SSB - L3, L4, IST - WBS Summary | SSB | Not Started | 08/24/27 | 11/17/27 | 75.0 | 75.0 |
|
258.8 |
RPL09.CX.SSB.01010 |
RPL09.CX.SSB - L3 | SSB | Not Started | 08/24/27 | 10/12/27 | 43.8 | 43.8 |
|
258.8 |
RPL09.CX.SSB.01620 |
RPL09.CX.SSB - L3/L4 - FW to SSB Heat Pumps Flush and Fill | SSB | Not Started | 08/24/27 | 10/05/27 | 37.5 | 37.5 |
|
283.8 |
RPL09.INT.CTRC.3760 |
RPL09.Interior.Center-Corridor LO #11 & #13 - Install Electrical Lowside OH | Interior Leave Out Wall #11, #13 (DHA/CC) | Not Started | 08/24/27 | 08/27/27 | 5.0 | 5.0 |
|
90.0 |
RPL09.INT.CTRC.8140 |
RPL09.Interior.Center-Corridor LO #10 - Install Door (Verify with Trades before installation) | Remaining of LO Wall #10 (Spoke Parts & Spoke Tech) | Not Started | 08/24/27 | 08/25/27 | 2.5 | 2.5 |
|
140.0 |
RPL09.INT.CTRC.8500 |
RPL09.Interior.Center-Corridor LO #11 - Hard Lid Framing | Remaining of LO Wall #11 (Spoke Parts) | Not Started | 08/24/27 | 08/26/27 | 3.8 | 3.8 |
|
110.0 |
RPL09.INT.DHC.01140 |
RPL09.Interior.DHC - Control Fault Domain 1 - Install Vesda / FA | Remaining Tie-ins post Mech Side Aisle install | Not Started | 08/24/27 | 09/21/27 | 25.0 | 25.0 |
|
172.5 |
RPL09.INT.DHC.01150 |
RPL09.Interior.DHC - Control Fault Domain 1 - Install FW | Remaining Tie-ins post Mech Side Aisle install | Not Started | 08/24/27 | 09/21/27 | 25.0 | 25.0 |
|
160.0 |
RPL09.INT.DHC.01990 |
RPL09.Interior.DHC - Control Fault Domain 1 - Install TW | Remaining Tie-ins post Mech Side Aisle install | Not Started | 08/24/27 | 09/21/27 | 25.0 | 25.0 |
|
160.0 |
RPL09.INT.DHC.02570 |
RPL09.Interior.DHC - Control Fault Domain 1 - Install Duct (MES Side) | Remaining Tie-ins post Mech Side Aisle install | Not Started | 08/24/27 | 09/21/27 | 25.0 | 25.0 |
|
160.0 |
RPL09.INT.DHD.01260 |
RPL09.Interior.DHD - Control Fault Domain 1 - L2 Checklist Completion | Remaining Tie-ins post Mech Side Aisle install | Not Started | 08/24/27 | 09/21/27 | 25.0 | 25.0 |
|
177.5 |
RPL09.INT.DHD.01310 |
RPL09.Interior.DHD - Control Fault Domain 2 - Pull BMS from panel to devices | Remaining Tie-ins post Mech Side Aisle install | Not Started | 08/24/27 | 09/21/27 | 25.0 | 25.0 |
|
191.2 |
RPL09.INT.DHD.01320 |
RPL09.Interior.DHD - Control Fault Domain 2 - Pull EMPS from panel to devices | Remaining Tie-ins post Mech Side Aisle install | Not Started | 08/24/27 | 09/21/27 | 25.0 | 25.0 |
|
191.2 |
RPL09.INT.DHD.01330 |
RPL09.Interior.DHD - Control Fault Domain 2 - Set UPS and Panel (2) | Remaining Tie-ins post Mech Side Aisle install | Not Started | 08/24/27 | 09/21/27 | 25.0 | 25.0 |
|
178.8 |
RPL09.INT.SSB.01580 |
RPL09.Interior.SSB - BoW - Final Clean | Balance of Walls and OverHead | Not Started | 08/24/27 | 08/27/27 | 5.0 | 5.0 |
|
188.8 |
RPL09.OFCI.C.4160 |
OFCI Delivery: FE Fiber for CFD A.3 (ROJ ) (RVCD ) | Data Hall A | Not Started | 08/24/27 | 08/30/27 | 6.2 | 6.2 |
|
168.8 |
RPL09.OFCI.C.4380 |
OFCI Delivery: BE Fiber for CFD B.1 (ROJ ) (RVCD ) | Data Hall B | Not Started | 08/24/27 | 08/30/27 | 6.2 | 6.2 |
|
225.0 |
RPL09.WP3B.015080 |
RPL09.Conn EF2<>DHB.20 Splice (A-End) Pigtails (384F) P2&3 (LV) | EF2<>DHB.20 | Not Started | 08/24/27 | 08/31/27 | 7.5 | 7.5 |
|
170.0 |
RPL09.WP3B.016520 |
RPL09.Conn EF2<>DHB.20 Install (Z-End) Pigtails (384F) P2&3 (LV) | EF2<>DHB.20 | Not Started | 08/24/27 | 08/24/27 | 1.2 | 1.2 |
|
170.0 |
RPL09.WP4.014600 |
RPL09.Conn DHA.01.03 Pull Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] | Jumpers (AI Confirmed) | Not Started | 08/24/27 | 09/07/27 | 12.5 | 12.5 |
|
176.2 |
RPL09.WP4.014620 |
RPL09.Conn DHA.02.07 Pull Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] | Jumpers (AI Confirmed) | Not Started | 08/24/27 | 09/07/27 | 12.5 | 12.5 |
|
176.2 |
RPL09.WP4.014640 |
RPL09.Conn DHA.03.09<>09 Install (A-End) Simplex Jumper (SC<>LC) [PON (Active, In-Row)] | Jumpers | Not Started | 08/24/27 | 08/24/27 | 1.2 | 1.2 |
|
200.0 |
RPL09.WP4.014660 |
RPL09.Conn DHA.04.13<>13 Install (A-End) Simplex Jumper (SC<>LC) [PON (Active, In-Row)] | Jumpers | Not Started | 08/24/27 | 08/24/27 | 1.2 | 1.2 |
|
200.0 |
RPL09.WP4.017520 |
RPL09.Conn DHB.15.20<>19 Install (A-End) Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] | Across-Row | Not Started | 08/24/27 | 08/24/27 | 1.2 | 1.2 |
|
187.5 |
RPL09.WP4.017540 |
RPL09.Conn DHB.16.24<>23 Install (A-End) Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] | Across-Row | Not Started | 08/24/27 | 08/24/27 | 1.2 | 1.2 |
|
187.5 |
RPL09.WP4.018080 |
RPL09.Conn DHB.17.25<>25 Install (A-End) Simplex Jumper (SC<>LC) [PON (Active, In-Row)] | Jumpers | Not Started | 08/24/27 | 08/24/27 | 1.2 | 1.2 |
|
188.8 |
RPL09.WP4.018200 |
RPL09.Conn DHB.18.30<>29 Install (A-End) Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] | Across-Row | Not Started | 08/24/27 | 08/24/27 | 1.2 | 1.2 |
|
188.8 |
RPL09.WP4.018260 |
RPL09.Conn DHB.18.32<>31 Pull Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] | Across-Row | Not Started | 08/24/27 | 08/27/27 | 5.0 | 5.0 |
|
177.5 |
RPL09.CX.DHB.01520 |
RPL09.CX.DHB - L3/L4 - Control Fault Domain 05 - TW Flush and Fill | Control Fault Domain 5 | Not Started | 08/25/27 | 09/03/27 | 10.0 | 10.0 |
|
158.8 |
RPL09.CX.DHC.01060 |
RPL09.CX.DHC - L3/L4 - House Power (for mechainical) | DHC HOUSE POWER | Not Started | 08/25/27 | 09/08/27 | 12.5 | 12.5 |
|
202.5 |
RPL09.INT.CTRC.8040 |
RPL09.Interior.Center-Corridor LO #10 - Electrical Trim Out | Remaining of LO Wall #10 (Spoke Parts & Spoke Tech) | Not Started | 08/25/27 | 08/27/27 | 3.8 | 3.8 |
|
135.0 |
RPL09.INT.CTRC.8060 |
RPL09.Interior.Center-Corridor LO #10 - Security Trim Out | Remaining of LO Wall #10 (Spoke Parts & Spoke Tech) | Not Started | 08/25/27 | 08/27/27 | 3.8 | 3.8 |
|
135.0 |
RPL09.INT.CTRC.8160 |
RPL09.Interior.Center-Corridor LO #10 - Install Remaining Refrigerant Line | Remaining of LO Wall #10 (Spoke Parts & Spoke Tech) | Not Started | 08/25/27 | 08/27/27 | 3.8 | 3.8 |
|
138.8 |
RPL09.INT.SBC.04040 |
RPL09.Interior.SSB-Corridor - BoW - Final Clean | Balance of Walls & Overhead | Not Started | 08/25/27 | 08/30/27 | 5.0 | 5.0 |
|
138.8 |
RPL09.CON.WP2.08860 |
RPL09.Conn - GSIDF/DH A1 - Install Cabling (Pull, Splice & terminate) | Cabling | Not Started | 08/26/27 | 09/02/27 | 7.5 | 7.5 |
|
345.0 |
RPL09.CON.WP2.08900 |
RPL09.Conn - GSIDF/DH A1 - Install Copper, WAPs, Security Camera & Access Control | Cabling | Not Started | 08/26/27 | 09/13/27 | 15.0 | 15.0 |
|
182.5 |
RPL09.CON.WP4.03400 |
RPL09.Conn WP4 FENW DHA CFD3 Infrastructure | Infrastructure | Not Started | 08/26/27 | 09/23/27 | 25.0 | 25.0 |
|
176.2 |
RPL09.CX.DHA.01560 |
RPL09.CX.DHA - L3/L4 - Control Fault Domain 04 - FW Flush and Fill | Control Fault Domain 4 | Not Started | 08/26/27 | 09/03/27 | 8.8 | 8.8 |
|
140.0 |
RPL09.INT.CTRC.01790 |
RPL09.Interior.Center-Corridor (S) - Plumbing Trim | Fit out (South) | Not Started | 08/26/27 | 08/31/27 | 5.0 | 5.0 |
|
97.5 |
RPL09.INT.DHA.01470 |
RPL09.Conn DHA - CFD3 - Set Passive Racks for WP#3b (16) | Infrastructure | Not Started | 08/26/27 | 08/30/27 | 3.8 | 3.8 |
|
145.0 |
RPL09.INT.DHA.03920 |
RPL09.Conn DHA - CFD3 - Set Passive Racks for PON (16) | Infrastructure | Not Started | 08/26/27 | 08/30/27 | 3.8 | 3.8 |
|
172.5 |
RPL09.WP4.015080 |
RPL09.Conn DHA.03.11<>11 Install (A-End) Simplex Jumper (SC<>LC) [PON (Active, In-Row)] | Jumpers | Not Started | 08/26/27 | 08/26/27 | 1.2 | 1.2 |
|
198.8 |
RPL09.WP4.015100 |
RPL09.Conn DHA.04.15<>15 Install (A-End) Simplex Jumper (SC<>LC) [PON (Active, In-Row)] | Jumpers | Not Started | 08/26/27 | 08/26/27 | 1.2 | 1.2 |
|
198.8 |
RPL09.WP4.015240 |
RPL09.Conn DHA.03.10<>09 Pull Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] | Across-Row | Not Started | 08/26/27 | 08/31/27 | 5.0 | 5.0 |
|
186.2 |
RPL09.WP4.015260 |
RPL09.Conn DHA.04.14<>13 Pull Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] | Across-Row | Not Started | 08/26/27 | 08/31/27 | 5.0 | 5.0 |
|
186.2 |
RPL09.WP4.018700 |
RPL09.Conn DHB.17.27<>27 Install (A-End) Simplex Jumper (SC<>LC) [PON (Active, In-Row)] | Jumpers | Not Started | 08/26/27 | 08/26/27 | 1.2 | 1.2 |
|
187.5 |
RPL09.WP4.018860 |
RPL09.Conn DHB.17.26<>25 Pull Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] | Across-Row | Not Started | 08/26/27 | 08/31/27 | 5.0 | 5.0 |
|
175.0 |
GCD.RPL09.3507 |
[RPL09] TC-C Ready : EF Pathways complete [DHB] | TC-C Ready: Production Cabling - DHB | Not Started | 08/27/27 | 08/27/27 | 0.0 | 0.0 |
|
353.8 |
GCD.RPL09.3825 |
[RPL09] TC-C Ready : Overhead cable tray complete [DHB] | TC-C Ready: Production Cabling - DHB | Not Started | 08/27/27 | 08/27/27 | 0.0 | 0.0 |
|
353.8 |
RPL09.INT.CTRC.01500 |
RPL09.Interior.Center-Corridor (N) - Mechanical L2 Checklist Completion | Fit out (North) | Not Started | 08/27/27 | 09/10/27 | 12.5 | 12.5 |
|
131.2 |
RPL09.INT.CTRC.07080 |
RPL09.Interior.Center-Corridor - Final Finishes & Fixtures - Final Clean | Restrooms | Not Started | 08/27/27 | 09/01/27 | 5.0 | 5.0 |
|
117.5 |
RPL09.INT.CTRC.8080 |
RPL09.Interior.Center-Corridor LO #10 - Plumbing Trim Out | Remaining of LO Wall #10 (Spoke Parts & Spoke Tech) | Not Started | 08/27/27 | 08/31/27 | 3.8 | 3.8 |
|
135.0 |
RPL09.INT.CTRC.8100 |
RPL09.Interior.Center-Corridor LO #10 - Fire Life Safety Trim Out | Remaining of LO Wall #10 (Spoke Parts & Spoke Tech) | Not Started | 08/27/27 | 08/31/27 | 3.8 | 3.8 |
|
135.0 |
RPL09.INT.CTRC.8480 |
RPL09.Interior.Center-Corridor LO #11 - Hard Lid Rough-In | Remaining of LO Wall #11 (Spoke Parts) | Not Started | 08/27/27 | 09/01/27 | 5.0 | 5.0 |
|
110.0 |
RPL09.OFCI.C.4400 |
OFCI Delivery: BE Fiber for CFD B.2 (ROJ ) (RVCD ) | Data Hall B | Not Started | 08/27/27 | 09/02/27 | 6.2 | 6.2 |
|
225.0 |
RPL09.WP3B.017900 |
RPL09.Conn EF2<>DHB.17 Test Pigtails (384F) P2&3 (LV) | EF2<>DHB.17 | Not Started | 08/27/27 | 08/30/27 | 2.5 | 2.5 |
|
173.8 |
RPL09.CON.WP3B.01120 |
RPL09.Conn EF1<>DHB11 - WBS Summary | EF1<>DHB.11 | Not Started | 08/30/27 | 09/14/27 | 13.8 | 13.8 |
|
161.2 |
RPL09.CON.WP4.01800 |
RPL09.Conn WP4 FENW DHB CFD5 Infrastructure | Infrastructure | Not Started | 08/30/27 | 09/27/27 | 25.0 | 25.0 |
|
162.5 |