Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL09 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:12 PM · 5201 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
0
Completed
0
In Progress
9
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL09.CX.DHA.01240 RPL09.CX.DHA - L5 IST [Includes Issues Resolution, Migration & FUL] DHA DATA HALL LEVEL TESTING Not Started 03/07/28 03/16/28 10.0 10.0
0%
36.2
RPL09.CX.DHC.01110 RPL09.CX.DHC - L3/L4 - Control Fault Domain 02 Control Fault Domain 2 Not Started 03/08/28 03/29/28 20.0 20.0
0%
71.2
RPL09.CX.DHC.01210 RPL09.CX.DHC - L3/L4 - Remaining Mechanical Equipment DHC MECHANICAL Not Started 03/08/28 03/14/28 6.2 6.2
0%
128.8
RPL09.CX.ENDC.01020 RPL09.CX.END COR - L4 End Corridor Not Started 03/08/28 03/21/28 12.5 12.5
0%
121.2
GCD.RPL09.5085 L3/L4 Finish - DHD Rows 09-16 DH Not Started 03/14/28 03/14/28 0.0 0.0
0%
117.5
ICM.B9.8040.B.ET [SSDCB4] FE Area Complete (ENS Ready) [DHB] - Early Target FENW Not Started 03/14/28 03/14/28 0.0 0.0
0%
37.5
RPL09.CX.DHB.01250 RPL09.CX.DHB - Punch List Remediation, Site Acceptance, and AHJ Approval of TCO - ET DHB DATA HALL LEVEL TESTING Not Started 03/15/28 03/28/28 12.5 12.5
0%
162.5
RPL09.CX.DHD.01130 RPL09.CX.DHD - L3/L4 - Control Fault Domain 03 Control Fault Domain 3 Not Started 03/15/28 04/05/28 20.0 20.0
0%
77.5
RPL09.PR.DHD.FE.0010 RPL09.PR.DHD FENW Data Hall D - Provisioning - WBS Summary FENW Not Started 03/15/28 06/12/28 77.5 77.5
0%
85.0
RPL09.PR.DHD.FE.0015 RPL09.PR.DHD FENW PZ1 (Row 01-16) - ENS Ready for PZ1 FENW Not Started 03/15/28 03/15/28 0.0 0.0
0%
125.0
RPL09.PR.DHD.FE.0020 RPL09.PR.DHD FENW PZ1 (Row 01-16) - Provisioning, Auditing, Issue Remediation (FSW, SSW) FENW Not Started 03/15/28 04/19/28 31.2 31.2
0%
125.0
GCD.RPL09.4545 IST Finish - DHA DH Not Started 03/16/28 03/16/28 0.0 0.0
0%
36.2
DCC.B9.3235 [SSDCB4] CorpNet/Security/FacNet Ready [DHA] Connectivity Not Started 03/17/28 03/17/28 0.0 0.0
0%
118.8
RPL09.CON.WP2.08020 RPL09.Conn - GSMDF1 (South) Test Network (FIM) Network Not Started 03/17/28 03/21/28 3.8 3.8
0%
118.8
RPL09.PR.DHA.FE.0025 RPL09.PR.DHA FENW PZ1 (Row 01-08) - Remaining Provisioning with PZ2 (FSW, SSW) FENW Not Started 03/17/28 03/23/28 6.2 6.2
0%
147.5
RPL09.PR.DHA.FE.0035 RPL09.PR.DHA FENW PZ2 (Row 09-24) - ENS Ready for PZ2 FENW Not Started 03/17/28 03/17/28 0.0 0.0
0%
36.2
RPL09.PR.DHA.FE.0040 RPL09.PR.DHA FENW PZ2 (Row 09-24) - Provisioning, Auditing, Issue Remediation (FSW, SSW) FENW Not Started 03/17/28 04/21/28 31.2 31.2
0%
122.5
RPL09.WA.DHA.01000 RPL09.WA - Weather Allowance - OFE to AC - DHA Weather Allowance Not Started 03/17/28 03/29/28 16.2 16.2
0%
52.5
GCD.RPL09.3727 [RPL09] TC-C Ready : All General Services [RPL09-MDFs] TC-C Ready: General Services Not Started 03/21/28 03/21/28 0.0 0.0
0%
150.0
RPL09.CX.ENDC.01030 RPL09.CX.END COR - IST End Corridor Not Started 03/22/28 04/04/28 12.5 12.5
0%
121.2
RPL09.PR.FE.0020 RPL09.PR.MDF R/S/P and Provisioning at GS.MDF 1&2 MDFs & IDFs Not Started 03/22/28 04/26/28 31.2 31.2
0%
118.8
RPL09.PR.DHA.FE.0030 RPL09.PR.DHA FENW PZ1 (Row 01-08) - Remaining Provisioning with PZ3 (FSW, SSW) FENW Not Started 03/24/28 03/30/28 6.2 6.2
0%
147.5
GCD.RPL09.5445 L3/L4 Finish - DHC Rows 09-16 DH Not Started 03/29/28 03/29/28 0.0 0.0
0%
115.0
ICM.B9.8040.A.ET [SSDCB4] FE Area Complete (ENS Ready) [DHA] - Early Target FENW Not Started 03/29/28 03/29/28 0.0 0.0
0%
36.2
RPL08.CX.DHA.01250 RPL09.CX.DHA - Punch List Remediation, Site Acceptance, and AHJ Approval of TCO - ET DHA DATA HALL LEVEL TESTING Not Started 03/30/28 04/12/28 12.5 12.5
0%
148.8
RPL09.CX.DHC.01130 RPL09.CX.DHC - L3/L4 - Control Fault Domain 03 Control Fault Domain 3 Not Started 03/30/28 04/21/28 20.0 20.0
0%
71.2
RPL09.PR.DHC.FE.0010 RPL09.PR.DHC FENW Data Hall B - Provisioning - WBS Summary FENW Not Started 03/30/28 06/27/28 77.5 77.5
0%
71.2
RPL09.PR.DHC.FE.0015 RPL09.PR.DHC FENW PZ1 (Row 01-16) - ENS Ready for PZ1 FENW Not Started 03/30/28 03/30/28 0.0 0.0
0%
111.2
RPL09.PR.DHC.FE.0020 RPL09.PR.DHC FENW PZ1 (Row 01-16) - Provisioning, Auditing, Issue Remediation (FSW, SSW) FENW Not Started 03/30/28 05/04/28 31.2 31.2
0%
111.2
GCD.RPL09.5105 L3/L4 Finish - DHD Rows 17-24 DH Not Started 04/05/28 04/05/28 0.0 0.0
0%
97.5
RPL09.CX.DHD.01150 RPL09.CX.DHD - L3/L4 - Control Fault Domain 04 Control Fault Domain 4 Not Started 04/06/28 04/28/28 20.0 20.0
0%
77.5
ICM.B9.1075.ET [SSDCB4] Partial Occupancy (FACOPS Handover) - DHA&B - Early Target Construction Not Started 04/12/28 04/12/28 0.0 0.0
0%
148.8
GCD.RPL09.5465 L3/L4 Finish - DHC Rows 17-24 DH Not Started 04/21/28 04/21/28 0.0 0.0
0%
95.0
RPL09.CX.DHC.01150 RPL09.CX.DHC - L3/L4 - Control Fault Domain 04 Control Fault Domain 5 Not Started 04/24/28 05/15/28 20.0 20.0
0%
71.2
RPL09.PR.DHA.FE.0045 RPL09.PR.DHA FENW PZ2 (Row 09-24) - Remaining Provisioning with PZ3 (FSW, SSW) FENW Not Started 04/24/28 04/28/28 6.2 6.2
0%
122.5
GCD.RPL09.3351 [RPL09] FacNet Live RPL09 - DHB - Only MDF2 TC-C Ready: FacNet Live Not Started 04/26/28 04/26/28 0.0 0.0
0%
150.0
GCD.RPL09.3353 [RPL09] FacNet Live RPL09 - DHA - Only MDF1 TC-C Ready: FacNet Live Not Started 04/26/28 04/26/28 0.0 0.0
0%
150.0
GCD.RPL09.3355 [RPL09] FacNet Live RPL09 - DHA&B TC-C Ready: FacNet Live Not Started 04/26/28 04/26/28 0.0 0.0
0%
150.0
ICM.B9.3350 [SSDCB4] CorpNet Live [GS.MDF 1/2 & MSG] Connectivity Not Started 04/26/28 04/26/28 0.0 0.0
0%
118.8
ICM.B9.3355 [SSDCB4] FacNet Live [GS.MDF 1/2 & MSG] Connectivity Not Started 04/26/28 04/26/28 0.0 0.0
0%
118.8
ICM.B9.8040.B [SSDCB4] FE Area Complete (ENS Ready) [DHB] - Incentivised (04/26/28) FENW Not Started 04/26/28 04/26/28 0.0 0.0
0%
125.0
RPL09.CX.DHB.01600 RPL09.CX.DHB - Punch List Remediation, Site Acceptance, and AHJ Approval of TCO - Contractual DHB DATA HALL LEVEL TESTING Not Started 04/27/28 05/10/28 12.5 12.5
0%
125.0
GCD.RPL09.5125 L3/L4 Finish - DHD Rows 25-32 DH Not Started 04/28/28 04/28/28 0.0 0.0
0%
77.5
ICM.B9.1070 [SSDCB4] FE Network Complete (ENS Handover) [DHA,B] - Contractual FENW Not Started 04/28/28 04/28/28 0.0 0.0
0%
122.5
ICM.B9.1070.ET [SSDCB4] FE Network Complete (ENS Handover) [DHA,B] - Early Target FENW Not Started 04/28/28 04/28/28 0.0 0.0
0%
122.5
RPL09.CX.DHD.01220 RPL09.CX.DHD - L4 - Data Hall Level Testing DHD DATA HALL LEVEL TESTING Not Started 05/01/28 05/12/28 12.5 12.5
0%
77.5
RPL09.PR.DHBA.ACT.20 RPL09.PR.DHB&A Activation - DH B & A DH B&A - Activation, Undraining Not Started 05/01/28 05/12/28 12.5 12.5
0%
122.5
RPL09.PR.DHD.FE.0030 RPL09.PR.DHD FENW PZ1 (Row 01-16) - Remaining Provisioning with PZ2 (FSW, SSW) FENW Not Started 05/01/28 05/05/28 6.2 6.2
0%
116.2
RPL09.PR.DHD.FE.0035 RPL09.PR.DHD FENW PZ2 (Row 17-32) - ENS Ready for PZ2 FENW Not Started 05/01/28 05/01/28 0.0 0.0
0%
85.0
RPL09.PR.DHD.FE.0040 RPL09.PR.DHD FENW PZ2 (Row 17-32) - Provisioning, Auditing, Issue Remediation (FSW, SSW) FENW Not Started 05/01/28 06/12/28 37.5 37.5
0%
85.0
RPL09.PR.DHC.FE.0030 RPL09.PR.DHC FENW PZ1 (Row 01-16) - Remaining Provisioning with PZ2 (FSW, SSW) FENW Not Started 05/05/28 05/11/28 6.2 6.2
0%
111.2
ICM.B9.8040.A [SSDCB4] FE Area Complete (ENS Ready) [DHA] - Incentivised (05/10/28) FENW Not Started 05/10/28 05/10/28 0.0 0.0
0%
112.5
RPL08.CX.DHA.01270 RPL09.CX.DHA - Punch List Remediation, Site Acceptance, and AHJ Approval of TCO - Contractual DHA DATA HALL LEVEL TESTING Not Started 05/11/28 05/24/28 12.5 12.5
0%
112.5
GCD.RPL09.5485 L3/L4 Finish - DHC Rows 25-32 DH Not Started 05/15/28 05/15/28 0.0 0.0
0%
75.0
RPL09.CX.DHD.01230 RPL09.CX.DHD - L5 IST [Includes Issues Resolution, Migration & FUL] DHD DATA HALL LEVEL TESTING Not Started 05/15/28 05/24/28 10.0 10.0
0%
77.5
RPL09.PR.DHBA.ACT.40 RPL09.PR.DHB&A Undraining - DH B & A DH B&A - Activation, Undraining Not Started 05/15/28 05/26/28 12.5 12.5
0%
122.5
RPL09.CX.DHC.01230 RPL09.CX.DHC - L4 - Data Hall Level Testing DHC DATA HALL LEVEL TESTING Not Started 05/16/28 05/30/28 12.5 12.5
0%
75.0
RPL09.PR.DHC.FE.0035 RPL09.PR.DHC FENW PZ2 (Row 17-32) - ENS Ready for PZ2 FENW Not Started 05/16/28 05/16/28 0.0 0.0
0%
71.2
RPL09.PR.DHC.FE.0040 RPL09.PR.DHC FENW PZ2 (Row 17-32) - Provisioning, Auditing, Issue Remediation (FSW, SSW) FENW Not Started 05/16/28 06/27/28 37.5 37.5
0%
71.2
ICM.B9.1075 [SSDCB4] Partial Occupancy (FACOPS Handover) - DHA&B - Contractual Contractual Not Started 05/24/28 05/24/28 0.0 0.0
0%
112.5
DCC.B9.3255 [SSDCB4] CorpNet/Security/FacNet Ready [DHD] Connectivity Not Started 05/25/28 05/25/28 0.0 0.0
0%
90.0
GCD.RPL09.4905 IST Finish - DHD DH Not Started 05/25/28 05/25/28 0.0 0.0
0%
77.5
ICM.B9.2710.D [SSDCB4] IST Start - DHD Commissioning Not Started 05/25/28 05/25/28 0.0 0.0
0%
77.5
RPL09.CON.WP2.06280 RPL09.Conn - GSIDF/DH B2 - Install & Test Network (FIM) Network Not Started 05/25/28 05/30/28 3.8 3.8
0%
90.0
RPL09.WA.DHD.01000 RPL09.WA - Weather Allowance - OFE to AC - DHD Weather Allowance Not Started 05/25/28 06/06/28 16.2 16.2
0%
113.8
ICM.B9.2710.C [SSDCB4] IST Start - DHC Commissioning Not Started 05/31/28 05/31/28 0.0 0.0
0%
85.0
RPL09.CX.DHC.01240 RPL09.CX.DHC - L5 IST [Includes Issues Resolution, Migration & FUL] DHC DATA HALL LEVEL TESTING Not Started 05/31/28 06/09/28 10.0 10.0
0%
75.0
RPL09.PR.FE.0040 RPL09.PR.IDFB2 R/S/P and Provisioning at GS.IDF B2 MDFs & IDFs Not Started 05/31/28 07/06/28 31.2 31.2
0%
90.0
ICM.B9.8040.D.ET [SSDCB4] FE Area Complete (ENS Ready) [DHD] - Early Target FENW Not Started 06/06/28 06/06/28 0.0 0.0
0%
77.5
RPL09.CX.DHD.01250 RPL09.CX.DHC - Punch List Remediation, Site Acceptance, and AHJ Approval of TCO - ET DHD DATA HALL LEVEL TESTING Not Started 06/07/28 06/20/28 12.5 12.5
0%
90.0
GCD.RPL09.5265 IST Finish - DHC DH Not Started 06/09/28 06/09/28 0.0 0.0
0%
75.0
RPL09.WA.DHC.01000 RPL09.WA - Weather Allowance - OFE to AC - DHC Weather Allowance Not Started 06/10/28 06/22/28 16.2 16.2
0%
111.2
DCC.B9.3245 [SSDCB4] CorpNet/Security/FacNet Ready [DHC] Connectivity Not Started 06/12/28 06/12/28 0.0 0.0
0%
76.2
RPL09.CON.WP2.06480 RPL09.Conn - GSIDF/DH A2 - Install & Test Network (FIM) Network Not Started 06/12/28 06/14/28 3.8 3.8
0%
76.2
GCD.RPL09.3717 [RPL09] TC-C Ready : All General Services [RPL09-Interior IDFs] **Removed pred** TC-C Ready: General Services Not Started 06/14/28 06/14/28 0.0 0.0
0%
107.5
RPL09.PR.FE.0060 RPL09.PR.IDFA2 R/S/P and Provisioning at GS.IDF A2 MDFs & IDFs Not Started 06/15/28 07/21/28 31.2 31.2
0%
76.2
ICM.B9.8040.C.ET [SSDCB4] FE Area Complete (ENS Ready) [DHC] - Early Target FENW Not Started 06/22/28 06/22/28 0.0 0.0
0%
75.0
RPL08.CX.DHC.01250 RPL09.CX.DHC - Punch List Remediation, Site Acceptance, and AHJ Approval of TCO - ET DHC DATA HALL LEVEL TESTING Not Started 06/23/28 07/10/28 12.5 12.5
0%
75.0
ICM.B9.1080 [SSDCB4] FE Network Complete (ENS Handover) [DHC,D] - Contractual FENW Not Started 06/27/28 06/27/28 0.0 0.0
0%
71.2
ICM.B9.1080.ET [SSDCB4] FE Network Complete (ENS Handover) [DHC,D] - Early Target FENW Not Started 06/27/28 06/27/28 0.0 0.0
0%
71.2
RPL09.PR.DHDC.ACT.20 RPL09.PR.DHD&C Activation - DH D & C DH C&D - Activation, Undraining Not Started 06/28/28 07/13/28 12.5 12.5
0%
71.2
GCD.RPL09.3357 [RPL09] FacNet Live RPL09 - DHD - Only IDFB2 TC-C Ready: FacNet Live Not Started 07/06/28 07/06/28 0.0 0.0
0%
90.0
ICM.B9.1110.ET [SSDCB4] Partial Occupancy (FACOPS Handover) - DHC&D - Early Target Construction Not Started 07/10/28 07/10/28 0.0 0.0
0%
75.0
RPL09.SC.020020 RPL07 Punch List for SC - Early Target Punch List Not Started 07/11/28 07/24/28 12.5 12.5
0%
75.0
RPL09.PR.DHDC.ACT.40 RPL09.PR.DHD&C Undraining - DH D & C DH C&D - Activation, Undraining Not Started 07/14/28 07/27/28 12.5 12.5
0%
71.2
GCD.RPL09.3359 [RPL09] FacNet Live RPL09 - DHC - Only IDFA2 TC-C Ready: FacNet Live Not Started 07/21/28 07/21/28 0.0 0.0
0%
76.2
GCD.RPL09.3360 [RPL09] FacNet Live RPL09 - DHC&D TC-C Ready: FacNet Live Not Started 07/21/28 07/21/28 0.0 0.0
0%
76.2
RPL.09.D.N6240.XG RPL09 Activation Complete for 2nd GW Internal Milestones (XREFs) Not Started 07/27/28 07/27/28 0.0 0.0
0%
71.2
ICM.B9.8040.D [SSDCB4] FE Area Complete (ENS Ready) [DHD] - Incentivised (09/05/28) FENW Not Started 09/05/28 09/05/28 0.0 0.0
0%
12.5
RPL09.CX.DHD.01600 RPL09.CX.DHC - Punch List Remediation, Site Acceptance, and AHJ Approval of TCO - Contractual DHD DATA HALL LEVEL TESTING Not Started 09/06/28 09/19/28 12.5 12.5
0%
12.5
ICM.B9.8040.C [SSDCB4] FE Area Complete (ENS Ready) [DHC] - Incentivised (09/19/28) FENW Not Started 09/19/28 09/19/28 0.0 0.0
0%
0.0
RPL08.CX.DHC.01270 RPL09.CX.DHC - Punch List Remediation, Site Acceptance, and AHJ Approval of TCO - Contractual DHC DATA HALL LEVEL TESTING Not Started 09/20/28 10/03/28 12.5 12.5
0%
0.0
ICM.B9.1110 [SSDCB4] Partial Occupancy (FACOPS Handover) - DHC&D - Contractual Contractual Not Started 10/03/28 10/03/28 0.0 0.0
0%
0.0
ICM.G.9000.2.ET RPL09 Substantial Completion - Early Target IMS P0 Milestones Not Started 10/03/28 10/03/28 0.0 0.0
0%
12.5
RPL09.SC.020040 RPL07 Punch List for SC - Contractual Punch List Not Started 10/04/28 10/17/28 12.5 12.5
0%
0.0
ICM.G.9000.2 RPL09 Substantial Completion - Contractual IMS P0 Milestones Not Started 10/17/28 10/17/28 0.0 0.0
0%
0.0
RPL09.SUCC SUCC Obsolete Not Started 10/17/28 10/17/28 0.0 0.0
0%
0.0
RPL.GF.D.N9200.XR DAS/PS System pathways complete SSB, DH B, DH A for RPL09 Receive Milestones (XREFs) Not Started 10/18/28 10/18/28 0.0 0.0
0%
0.0
RPL.GF.D.N9210.XR DAS/PS System pathways complete DH D, DH C for RPL09 Receive Milestones (XREFs) Not Started 10/18/28 10/18/28 0.0 0.0
0%
0.0
RPL.GF.D.N9220.XR ENS complete - RPL09 DHB/A Receive Milestones (XREFs) Not Started 10/18/28 10/18/28 0.0 0.0
0%
0.0