Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL08 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:14 PM · 5122 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
0
Completed
0
In Progress
0
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL08.STR.SSB.01030 RPL08.Structure.SSB - Install Storm Shelter F/R/P Deck Storm Shelter Not Started 07/01/26 07/08/26 6.2 6.2
0%
138.8
RPL08.SUB.SSB.01160 RPL08.SubStructure.SSB - Install UG Utilities - Plumbing/Testing/Backfill - Part 2 Underground Not Started 07/01/26 07/10/26 8.8 8.8
0%
126.2
RPL08.SUB.SSB.01080 RPL08.SubStructure.SSB - Strip Form Work And Apply Water Proofing System Foundations Not Started 07/06/26 07/08/26 3.8 3.8
0%
128.8
RPL08.SUB.SSB.01100 RPL08.SubStructure.SSB - Install Grounding Wire - Grid lines 6-01/6-10 Foundations Not Started 07/06/26 07/08/26 3.8 3.8
0%
128.8
RPL08.SUB.DHAB.01050 RPL08.SubStructure.DHAB - Strip Form Work And Apply Water Proofing System Foundations Not Started 07/07/26 07/08/26 2.5 2.5
0%
138.8
RPL08.SUB.DHAB.01080 RPL08.SubStructure.DHAB - Install Grounding Wire - Grid lines 6-10/6-23 Foundations Not Started 07/07/26 07/08/26 2.5 2.5
0%
138.8
RPL08.SUB.DHAB.01100 RPL08.SubStructure.DHAB - Install UG Utilities - BMS/EPMS/Testing and Pathway Verification and Backfill (new GS scope) Underground Not Started 07/07/26 07/20/26 12.5 12.5
0%
128.8
RPL08.SUB.DHAB.01150 RPL08.SubStructure.DHAB - Install UG Utilities - Plumbing/Testing/Backfill - Part 2 Underground Not Started 07/07/26 07/16/26 10.0 10.0
0%
128.8
RPL.08.D.70080.XR External Tie from RPL07 - EY MV Concrete Foundations Crew Flow (RPL07.EY.DHC.01010) Internal Milestones (XREFs) Not Started 07/08/26 07/08/26 0.0 0.0
0%
220.0
RPL08.SUB.DHCD.01050 RPL08.SubStructure.DHCD - Strip Form Work And Apply Water Proofing System Foundations Not Started 07/08/26 07/10/26 3.8 3.8
0%
172.5
RPL08.VDC.1620 T2-4 (mCUP Yard / Ext.) - GC QC BIM Model TIER 2 - 4 - mCUP Yard / Exterior Not Started 07/08/26 07/21/26 12.5 12.5
0%
203.8
RPL08.VDC.1640 T2-4 (DH A & B) - Review & Approve BIM Shop TIER 2 - 4 - DH A & B Not Started 07/08/26 08/11/26 31.2 31.2
0%
161.2
RPL08.VDC.1660 T2-4 (DH C & D) - Prepare & Submit BIM Shops TIER 2 - 4 - DH C & D Not Started 07/08/26 07/21/26 12.5 12.5
0%
247.5
RPL08.MCUP.LP1.1300 RPL08.MCUP.Loop 1 - Install UG Generator Conduit Feed Electrical UG Not Started 07/09/26 07/14/26 5.0 5.0
0%
238.8
RPL08.SUB.DHCD.01080 RPL08.SubStructure.DHCD - Install Grounding Wire - Grid lines 6-23/6-28 Foundations Not Started 07/09/26 07/10/26 2.5 2.5
0%
172.5
RPL08.SUB.DHCD.01190 RPL08.SubStructure.DHCD - Scan, Install Backfill - Grid lines 6-23/6-28 (2nd Layer Backfill) Underground Not Started 07/09/26 07/16/26 7.5 7.5
0%
156.2
RPL08.SUB.DHAB.01170 RPL08.SubStructure.DHAB - Install UG Utilities - Electrical/Testing and Pathway Verification and Backfill - Part 2 Underground Not Started 07/10/26 07/17/26 7.5 7.5
0%
128.8
RPL.08.D.70120.XR External Tie from RPL06 - Interior SSB/Corridor Crew Flow (RPL06.INT.ENDC.01120) Internal Milestones (XREFs) Not Started 07/13/26 07/13/26 0.0 0.0
0%
313.8
RPL08.LOG.1340 Steel Crane #1 Mobilization Steel Crane 1 Not Started 07/13/26 07/13/26 0.0 0.0
0%
225.0
RPL08.LOG.1360 Steel Crane #2 Mobilization Steel Crane 2 Not Started 07/13/26 07/13/26 0.0 0.0
0%
225.0
RPL08.STR.SSB.01050 RPL08.Structure.SSB - Erect Steel/Joist/Decking - WBS Summary Steel and Decking Not Started 07/13/26 08/10/26 26.2 26.2
0%
126.2
RPL08.STR.SSB.01210 RPL08.Structure.SSB - Crane Road Prep - Grid lines 6-01/6-10 Steel and Decking Not Started 07/13/26 07/15/26 3.8 3.8
0%
126.2
RPL08.MCUP.LP1.1020 RPL08.MCUP.Loop 1 - Install Foundations - WBS Summary Foundations Not Started 07/15/26 08/20/26 33.8 33.8
0%
195.0
RPL08.MCUP.LP1.1120 Logistics Area #XX - Chewy Ct/ Smuggler St (DPR Laydown Area) - Complete **Need Succ, Constraint, update road names Foundations Not Started 07/15/26 07/15/26 0.0 0.0
0%
195.0
RPL08.MCUP.LP1.2200 RPL08.MCUP.Loop 1 - Flow Fill & Backfill (Loop 1 & 2) Foundations Not Started 07/15/26 08/07/26 22.5 22.5
0%
195.0
RPL08.MCUP.LP2.1100 RPL08.MCUP.Loop 2 - Install Electrical UG Electrical UG Not Started 07/15/26 08/04/26 18.8 18.8
0%
232.5
RPL08.MCUP.LP2.1140 RPL08.MCUP.Loop 2 - Install Controls/EPMS/BMS UG Controls/EPMS/BMS UG Not Started 07/15/26 08/04/26 18.8 18.8
0%
237.5
RPL08.VDC.1700 T2-4 (EF) - Review & Approve BIM Shop TIER 2 - 4 - EF Not Started 07/15/26 08/18/26 31.2 31.2
0%
197.5
RPL08.CFCI.4010 RPL08 - Submittals Review & Approval - Roofing Roofing Not Started 07/16/26 07/29/26 12.5 12.5
0%
105.0
RPL08.CFCI.5700 RPL08 - Submittals Review & Approval - Glass / Frames Glass & Glazing (Alum. Entrances & Curtainwall) Not Started 07/16/26 07/29/26 12.5 12.5
0%
312.5
RPL08.CFCI.6500 Submittals Review & Approval - Roof Drain Pipes (CFCI) Div. 33 - Utilities Storm / Sanitary Manholes and Inlets - Area 2 Not Started 07/16/26 08/12/26 25.0 25.0
0%
105.0
RPL08.STR.SSB.01230 RPL08.Structure.SSB - Steel Shake out - Grid lines 6-01/6-10 Steel and Decking Not Started 07/16/26 07/22/26 6.2 6.2
0%
126.2
RPL08.MCUP.LP1.1100 RPL08.MCUP.Loop 1 - F/R/P Pads (12'' larger) Foundations Not Started 07/17/26 08/13/26 25.0 25.0
0%
195.0
RPL08.SUB.DHCD.01150 RPL08.SubStructure.DHCD - Install UG Utilities - Plumbing/Testing/Backfill - Part 2 Underground Not Started 07/17/26 07/27/26 8.8 8.8
0%
156.2
RPL08.CFCI.4450 RPL08 - Submittals - Finished Carpentry (Millwork/Countertops) Finished Carpentry (Millwork/Tops) Not Started 07/20/26 08/14/26 25.0 25.0
0%
420.0
RPL08.CFCI.4610 RPL08 - Submittals Prep & Submit for Review - Interior Painting (Spec 09 91 23) XX (CFCI) Div. 09 - Painting Not Started 07/20/26 08/14/26 25.0 25.0
0%
323.8
RPL08.CFCI.4630 RPL08 - Submittals Prep & Submit for Review - Fire Alarm (CFCI) Div. 26 - Fire Alarm Not Started 07/20/26 08/14/26 25.0 25.0
0%
360.0
RPL08.CFCI.4730 RPL08 - Submittals Review & Approval - Finished Carpentry (Millwork/Countertops) Finished Carpentry (Millwork/Tops) Not Started 07/20/26 08/14/26 25.0 25.0
0%
420.0
RPL08.CFCI.4950 Campus - Submittals Prep & Submit for Review - Landscaping / Irrigation (CFCI) Div. 32 - Landscape/ Irrigation Not Started 07/20/26 08/21/26 31.2 31.2
0%
460.0
RPL08.SUB.DHCD.01100 RPL08.SubStructure.DHCD - Install UG Utilities - BMS/EPMS/Testing and Pathway Verification and Backfill (new GS Scope) Underground Not Started 07/20/26 07/29/26 10.0 10.0
0%
156.2
RPL.08.D.70060.XR External Tie from RPL07 - Roofing DenseDeck & Flame Down Crew Flow (RPL07.SKN.DHCD.01090) Internal Milestones (XREFs) Not Started 07/21/26 07/21/26 0.0 0.0
0%
162.5
RPL08.STR.DHAB.01010 RPL08.Structure.DHAB - Erect Steel/Joist/Decking - WBS Summary Steel and Decking Not Started 07/21/26 08/27/26 35.0 35.0
0%
126.2
RPL08.STR.DHAB.01020 RPL08.Structure.DHAB - Erect Steel/Joist/Decking, Remaining UG/SOG - WBS Summary DH B & DH A Not Started 07/21/26 11/25/26 112.5 112.5
0%
120.0
RPL08.STR.DHAB.01200 RPL08.Structure.DHAB - Crane Road Prep - Grid Lines 6-11/6-23 Steel and Decking Not Started 07/21/26 07/23/26 3.8 3.8
0%
137.5
RPL08.SUB.DHCD.01170 RPL08.SubStructure.DHCD - Install UG Utilities - Electrical/Testing and Pathway Verification and Backfill - Part 2 Underground Not Started 07/21/26 07/28/26 7.5 7.5
0%
156.2
RPL08.VDC.1720 T2-4 (DH C & D) - Review & Approve BIM Shop TIER 2 - 4 - DH C & D Not Started 07/22/26 08/25/26 31.2 31.2
0%
247.5
RPL08.VDC.1740 T2-4 (mCUP Yard / Ext.) - Procurement Equipments TIER 2 - 4 - mCUP Yard / Exterior Not Started 07/22/26 08/11/26 18.8 18.8
0%
203.8
GCD.RPL08.1360 Steel Erection Start - RPL08 Construction Milestones Not Started 07/23/26 07/23/26 0.0 0.0
0%
490.0
RPL08.STR.SSB.01040 RPL08.Structure.SSB - Install Erect Steel Columns and Beams, Erect Joist - Grid lines 6-01/6-10 Steel and Decking Not Started 07/23/26 08/04/26 11.2 11.2
0%
126.2
RPL08.STR.DHAB.01220 RPL08.Structure.DHAB - Steel Shake out - Grid Lines 6-11/6-23 Steel and Decking Not Started 07/24/26 07/30/26 6.2 6.2
0%
137.5
RPL08.CFCI.5100 Campus - Submittal Review & Approval - Asphalt / Paving (CFCI) Div. 32 - Asphalt/ Conc. Paving Not Started 07/27/26 08/21/26 25.0 25.0
0%
368.8
RPL08.MCUP.LP2.1120 RPL08.MCUP.Loop 2 - Install Grounding Wire, Grounding Rod, Exothermic Weld & Backfill Grounding UG Not Started 07/29/26 08/04/26 6.2 6.2
0%
232.5
RPL08.CFCI.4300 RPL08 - Fabricate / Deliver - Roofing Roofing Not Started 07/30/26 09/17/26 43.8 43.8
0%
105.0
RPL08.CFCI.5690 RPL08 - Fabricate / Deliver - Glass / Frames Glass & Glazing (Alum. Entrances & Curtainwall) Not Started 07/30/26 10/01/26 56.2 56.2
0%
312.5
RPL08.MCUP.LP2.1260 RPL08.MCUP.Loop 2 - Install UG Generator Conduit Feed Electrical UG Not Started 07/30/26 08/04/26 5.0 5.0
0%
383.8
RPL08.STR.DHCD.01010 RPL08.Structure.DHCD - Erect Steel/Joist/Decking - WBS Summary Steel and Decking Not Started 07/30/26 09/10/26 37.5 37.5
0%
143.8
RPL08.STR.DHCD.01020 RPL08.Structure.DHCD - Erect Steel/Joist/Decking, Remaining UG/SOG - WBS Summary DH D & DH C Not Started 07/30/26 12/19/26 122.5 122.5
0%
178.8
RPL08.STR.DHCD.01170 RPL08.Structure.DHCD - Crane Road Prep - Grid Lines 6-23/6-28 Steel and Decking Not Started 07/30/26 08/03/26 3.8 3.8
0%
156.2
RPL08.CFCI.4820 Campus - Submittals Prep & Submit for Review - Asphalt / Paving (CFCI) Div. 32 - Asphalt/ Conc. Paving Not Started 08/03/26 08/21/26 18.8 18.8
0%
368.8
RPL08.CFCI.6040 Submittals Review & Approval - Technical Water (Assume HDPE Pipe) (CFCI) Div. 33 - Utilities Technical Water (Assume HDPE) Not Started 08/03/26 08/21/26 18.8 18.8
0%
186.2
ICM.B8.1830 [SSDCB3] Delivery of PTX - Pad Mounted Transformers (First Delivery) Construction Not Started 08/04/26 08/04/26 0.0 0.0
0%
237.5
ICM.B8.1835 [SSDCB3] Delivery of FCA - Fan Coil Assembly (First Delivery) Construction Not Started 08/04/26 08/04/26 0.0 0.0
0%
210.0
ICM.B8.1860 [SSDCB3] Delivery of Dry Cooling Towers (First Delivery) Construction Not Started 08/04/26 08/04/26 0.0 0.0
0%
210.0
RPL08.STR.DHCD.01190 RPL08.Structure.DHCD - Steel Shake out - Grid Lines 6-23/6-28 Steel and Decking Not Started 08/04/26 08/10/26 6.2 6.2
0%
156.2
RPL08.STR.DHAB.01000 RPL08.Structure.DHAB - Install Erect Steel Columns and Beams, Erect Joist Grid Lines 6-11/6-23 Steel and Decking Not Started 08/05/26 08/14/26 10.0 10.0
0%
133.8
RPL08.STR.SSB.01060 RPL08.Structure.SSB - Install Decking & Detailing turnover #1 - Grid lines 6-01/6-04 Steel and Decking Not Started 08/05/26 08/10/26 5.0 5.0
0%
126.2
RPL08.VDC.1760 T2-4 (SSB) - GC QC BIM Model TIER 2 - 4 - SSB Not Started 08/05/26 08/18/26 12.5 12.5
0%
111.2
RPL08.CFCI.6050 Submittals Review & Approval - Technical Water (Assume HDPE Pipe) (CFCI) Div. 33 - Utilities Technical Water (Assume HDPE) Not Started 08/10/26 08/21/26 12.5 12.5
0%
186.2
RPL08.CFCI.6060 Fabricate / Deliver - Technical Water (Assume HDPE Pipe) (CFCI) Div. 33 - Utilities Technical Water (Assume HDPE) Not Started 08/11/26 10/06/26 50.0 50.0
0%
186.2
RPL08.STR.DHAB.01015 RPL08.Structure.DHAB - Install Decking & Detailing turnover #2 - Grid lines 6-04/6-07 Steel and Decking Not Started 08/11/26 08/13/26 3.8 3.8
0%
126.2
RPL08.VDC.1780 T2-4 (DH A & B) - GC QC BIM Model TIER 2 - 4 - DH A & B Not Started 08/12/26 08/25/26 12.5 12.5
0%
161.2
RPL08.CFCI.6510 Fabricate / Deliver - Roof Drain Pipes (CFCI) Div. 33 - Utilities Storm / Sanitary Manholes and Inlets - Area 2 Not Started 08/13/26 09/17/26 31.2 31.2
0%
105.0
PRE.FA.1300 Non-Critical Trade Buyout - Final Agreement Trade Partner Final Agreement Not Started 08/14/26 08/14/26 0.0 0.0
0%
186.2
RPL08.MCUP.LP1.1180 RPL08.MCUP.Loop 1 - Cure for Pads Foundations Not Started 08/14/26 08/20/26 8.8 8.8
0%
288.8
RPL08.MCUP.LP1.1200 RPL08.MCUP.Loop 1 - OFE - WBS Summary OFE Not Started 08/14/26 10/02/26 43.8 43.8
0%
205.0
RPL08.MCUP.LP1.2120 RPL08.MCUP.Loop 1 - Set Facility Water Pipe Rack (mCUP1) OFE Not Started 08/14/26 08/27/26 12.5 12.5
0%
206.2
RPL08.MCUP.LP2.1020 RPL08.MCUP.Loop 2 - Install Foundations - WBS Summary Foundations Not Started 08/14/26 09/03/26 18.8 18.8
0%
352.5
RPL08.MCUP.LP2.1160 RPL08.MCUP.Loop 2 - F/R/P Pads (12'' larger) Foundations Not Started 08/14/26 08/27/26 12.5 12.5
0%
352.5
RPL08.SKIN.01000 RPL08.SKIN.BLDG - Install Insulated Metal Panels (IMP), Roof, Windows, Doors, Louvers - WBS Summary Skin Not Started 08/14/26 07/22/27 292.5 292.5
0%
273.8
RPL08.SKN.W.01000 RPL08.SKIN.West - Install Metal Panel Sealant & Starter Flashing - West North South East IMP System Not Started 08/14/26 08/27/26 12.5 12.5
0%
130.0
RPL08.STR.DHAB.01025 RPL08.Structure.DHAB - Install Decking & Detailing turnover #3 - Grid lines 6-07/6-10 Steel and Decking Not Started 08/14/26 08/18/26 3.8 3.8
0%
126.2
RPL08.CFCI.4620 RPL08 - Submittals Prep & Submit for Review -Epoxy Flooring (Spec 09 67 23) XX (CFCI) Div. 09 - Epoxy Flooring Not Started 08/17/26 09/14/26 25.0 25.0
0%
298.8
RPL08.CFCI.4810 RPL08 - Submittals Prep & Submit for Review - Specialities (CFCI) Div. 10 - Specialities Not Started 08/17/26 09/14/26 25.0 25.0
0%
285.0
RPL08.CFCI.4870 RPL08 - Submittals Review & Approval - Interior Painting (Spec 09 91 23) XX (CFCI) Div. 09 - Painting Not Started 08/17/26 09/14/26 25.0 25.0
0%
336.2
RPL08.CFCI.4890 RPL08 - Submittals Review & Approval - Fire Alarm (CFCI) Div. 26 - Fire Alarm Not Started 08/17/26 09/04/26 18.8 18.8
0%
360.0
RPL08.CFCI.4960 RPL08 - Fabricate / Deliver - Finished Carpentry (Millwork/Countertops) Finished Carpentry (Millwork/Tops) Not Started 08/17/26 09/28/26 37.5 37.5
0%
420.0
RPL08.STR.DHCD.01000 RPL08.Structure.DHCD - Install Erect Steel Columns and Beams, Erect Joist - Grid Lines 6-23/6-28 Steel and Decking Not Started 08/17/26 08/25/26 8.8 8.8
0%
151.2
GCD.RPL08.1380 IMP Start - RPL08 Construction Milestones Not Started 08/18/26 08/18/26 0.0 0.0
0%
467.5
RPL08.LOG.1120 Dry Cooler 230 Ton Crane Mobilization 100 Ton Crane Not Started 08/18/26 08/20/26 3.8 3.8
0%
195.0
RPL08.SKN.W.01005 RPL08.SKIN.West - Install IMP - Flashing,Panels & Caulking - Gird lines 6A/6F (with temp closures for openings) DBC Move 1 - Grid (6-01 / 6-07) Not Started 08/18/26 08/19/26 2.5 2.5
0%
130.0
RPL08.SKN.W.01010 RPL08.SKIN.West - Install IMP Insulated Metal Panels System - WBS Summary DBC Move 1 - Grid (6-01 / 6-07) Not Started 08/18/26 08/27/26 10.0 10.0
0%
130.0
RPL08.STR.DHAB.01030 RPL08.Structure.DHAB - Install Decking & Detailing turnover #4 - Grid lines 6-10/6-14 Steel and Decking Not Started 08/19/26 08/24/26 5.0 5.0
0%
126.2
RPL08.VDC.1800 T2-4 (EF) - GC QC BIM Model TIER 2 - 4 - EF Not Started 08/19/26 09/01/26 12.5 12.5
0%
197.5
RPL08.VDC.1820 T2-4 (SSB) - Create Spool Sheet for Fab TIER 2 - 4 - SSB Not Started 08/19/26 09/09/26 18.8 18.8
0%
111.2
RPL08.EY.SSB.01000 RPL08.EY.SSB - Install F/R/P Equipment Pads Foundations Not Started 08/20/26 09/02/26 12.5 12.5
0%
182.5
RPL08.EY.SSB.01010 RPL08.EY.SSB - Install Foundations - WBS Summary Foundations Not Started 08/20/26 09/09/26 17.5 17.5
0%
215.0
RPL08.EY.SSB.01020 RPL08.EY.SSB - Install Foundations, UG Utilities, OFE - WBS Summary EY.SSB Not Started 08/20/26 08/16/27 308.8 308.8
0%
291.2
RPL08.EY.SSB.01030 RPL08.EY.BLDG - Install Foundations, UG Utilities, OFE- WBS Summary Electrical Yard Not Started 08/20/26 10/15/27 362.5 362.5
0%
237.5
RPL08.EY.SSB.01100 RPL08.EY.SSB - OFE - WBS Summary OFE Not Started 08/20/26 09/28/26 33.8 33.8
0%
207.5
RPL08.EY.SSB.01380 RPL08.EY.SSB - Install Wall Mounted AC units (5) - CFCI OFE Not Started 08/20/26 08/28/26 8.8 8.8
0%
230.0