Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL08 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:14 PM
· 5122 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
0
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL08.STR.SSB.01030 |
RPL08.Structure.SSB - Install Storm Shelter F/R/P Deck | Storm Shelter | Not Started | 07/01/26 | 07/08/26 | 6.2 | 6.2 |
|
138.8 |
RPL08.SUB.SSB.01160 |
RPL08.SubStructure.SSB - Install UG Utilities - Plumbing/Testing/Backfill - Part 2 | Underground | Not Started | 07/01/26 | 07/10/26 | 8.8 | 8.8 |
|
126.2 |
RPL08.SUB.SSB.01080 |
RPL08.SubStructure.SSB - Strip Form Work And Apply Water Proofing System | Foundations | Not Started | 07/06/26 | 07/08/26 | 3.8 | 3.8 |
|
128.8 |
RPL08.SUB.SSB.01100 |
RPL08.SubStructure.SSB - Install Grounding Wire - Grid lines 6-01/6-10 | Foundations | Not Started | 07/06/26 | 07/08/26 | 3.8 | 3.8 |
|
128.8 |
RPL08.SUB.DHAB.01050 |
RPL08.SubStructure.DHAB - Strip Form Work And Apply Water Proofing System | Foundations | Not Started | 07/07/26 | 07/08/26 | 2.5 | 2.5 |
|
138.8 |
RPL08.SUB.DHAB.01080 |
RPL08.SubStructure.DHAB - Install Grounding Wire - Grid lines 6-10/6-23 | Foundations | Not Started | 07/07/26 | 07/08/26 | 2.5 | 2.5 |
|
138.8 |
RPL08.SUB.DHAB.01100 |
RPL08.SubStructure.DHAB - Install UG Utilities - BMS/EPMS/Testing and Pathway Verification and Backfill (new GS scope) | Underground | Not Started | 07/07/26 | 07/20/26 | 12.5 | 12.5 |
|
128.8 |
RPL08.SUB.DHAB.01150 |
RPL08.SubStructure.DHAB - Install UG Utilities - Plumbing/Testing/Backfill - Part 2 | Underground | Not Started | 07/07/26 | 07/16/26 | 10.0 | 10.0 |
|
128.8 |
RPL.08.D.70080.XR |
External Tie from RPL07 - EY MV Concrete Foundations Crew Flow (RPL07.EY.DHC.01010) | Internal Milestones (XREFs) | Not Started | 07/08/26 | 07/08/26 | 0.0 | 0.0 |
|
220.0 |
RPL08.SUB.DHCD.01050 |
RPL08.SubStructure.DHCD - Strip Form Work And Apply Water Proofing System | Foundations | Not Started | 07/08/26 | 07/10/26 | 3.8 | 3.8 |
|
172.5 |
RPL08.VDC.1620 |
T2-4 (mCUP Yard / Ext.) - GC QC BIM Model | TIER 2 - 4 - mCUP Yard / Exterior | Not Started | 07/08/26 | 07/21/26 | 12.5 | 12.5 |
|
203.8 |
RPL08.VDC.1640 |
T2-4 (DH A & B) - Review & Approve BIM Shop | TIER 2 - 4 - DH A & B | Not Started | 07/08/26 | 08/11/26 | 31.2 | 31.2 |
|
161.2 |
RPL08.VDC.1660 |
T2-4 (DH C & D) - Prepare & Submit BIM Shops | TIER 2 - 4 - DH C & D | Not Started | 07/08/26 | 07/21/26 | 12.5 | 12.5 |
|
247.5 |
RPL08.MCUP.LP1.1300 |
RPL08.MCUP.Loop 1 - Install UG Generator Conduit Feed | Electrical UG | Not Started | 07/09/26 | 07/14/26 | 5.0 | 5.0 |
|
238.8 |
RPL08.SUB.DHCD.01080 |
RPL08.SubStructure.DHCD - Install Grounding Wire - Grid lines 6-23/6-28 | Foundations | Not Started | 07/09/26 | 07/10/26 | 2.5 | 2.5 |
|
172.5 |
RPL08.SUB.DHCD.01190 |
RPL08.SubStructure.DHCD - Scan, Install Backfill - Grid lines 6-23/6-28 (2nd Layer Backfill) | Underground | Not Started | 07/09/26 | 07/16/26 | 7.5 | 7.5 |
|
156.2 |
RPL08.SUB.DHAB.01170 |
RPL08.SubStructure.DHAB - Install UG Utilities - Electrical/Testing and Pathway Verification and Backfill - Part 2 | Underground | Not Started | 07/10/26 | 07/17/26 | 7.5 | 7.5 |
|
128.8 |
RPL.08.D.70120.XR |
External Tie from RPL06 - Interior SSB/Corridor Crew Flow (RPL06.INT.ENDC.01120) | Internal Milestones (XREFs) | Not Started | 07/13/26 | 07/13/26 | 0.0 | 0.0 |
|
313.8 |
RPL08.LOG.1340 |
Steel Crane #1 Mobilization | Steel Crane 1 | Not Started | 07/13/26 | 07/13/26 | 0.0 | 0.0 |
|
225.0 |
RPL08.LOG.1360 |
Steel Crane #2 Mobilization | Steel Crane 2 | Not Started | 07/13/26 | 07/13/26 | 0.0 | 0.0 |
|
225.0 |
RPL08.STR.SSB.01050 |
RPL08.Structure.SSB - Erect Steel/Joist/Decking - WBS Summary | Steel and Decking | Not Started | 07/13/26 | 08/10/26 | 26.2 | 26.2 |
|
126.2 |
RPL08.STR.SSB.01210 |
RPL08.Structure.SSB - Crane Road Prep - Grid lines 6-01/6-10 | Steel and Decking | Not Started | 07/13/26 | 07/15/26 | 3.8 | 3.8 |
|
126.2 |
RPL08.MCUP.LP1.1020 |
RPL08.MCUP.Loop 1 - Install Foundations - WBS Summary | Foundations | Not Started | 07/15/26 | 08/20/26 | 33.8 | 33.8 |
|
195.0 |
RPL08.MCUP.LP1.1120 |
Logistics Area #XX - Chewy Ct/ Smuggler St (DPR Laydown Area) - Complete **Need Succ, Constraint, update road names | Foundations | Not Started | 07/15/26 | 07/15/26 | 0.0 | 0.0 |
|
195.0 |
RPL08.MCUP.LP1.2200 |
RPL08.MCUP.Loop 1 - Flow Fill & Backfill (Loop 1 & 2) | Foundations | Not Started | 07/15/26 | 08/07/26 | 22.5 | 22.5 |
|
195.0 |
RPL08.MCUP.LP2.1100 |
RPL08.MCUP.Loop 2 - Install Electrical UG | Electrical UG | Not Started | 07/15/26 | 08/04/26 | 18.8 | 18.8 |
|
232.5 |
RPL08.MCUP.LP2.1140 |
RPL08.MCUP.Loop 2 - Install Controls/EPMS/BMS UG | Controls/EPMS/BMS UG | Not Started | 07/15/26 | 08/04/26 | 18.8 | 18.8 |
|
237.5 |
RPL08.VDC.1700 |
T2-4 (EF) - Review & Approve BIM Shop | TIER 2 - 4 - EF | Not Started | 07/15/26 | 08/18/26 | 31.2 | 31.2 |
|
197.5 |
RPL08.CFCI.4010 |
RPL08 - Submittals Review & Approval - Roofing | Roofing | Not Started | 07/16/26 | 07/29/26 | 12.5 | 12.5 |
|
105.0 |
RPL08.CFCI.5700 |
RPL08 - Submittals Review & Approval - Glass / Frames | Glass & Glazing (Alum. Entrances & Curtainwall) | Not Started | 07/16/26 | 07/29/26 | 12.5 | 12.5 |
|
312.5 |
RPL08.CFCI.6500 |
Submittals Review & Approval - Roof Drain Pipes | (CFCI) Div. 33 - Utilities Storm / Sanitary Manholes and Inlets - Area 2 | Not Started | 07/16/26 | 08/12/26 | 25.0 | 25.0 |
|
105.0 |
RPL08.STR.SSB.01230 |
RPL08.Structure.SSB - Steel Shake out - Grid lines 6-01/6-10 | Steel and Decking | Not Started | 07/16/26 | 07/22/26 | 6.2 | 6.2 |
|
126.2 |
RPL08.MCUP.LP1.1100 |
RPL08.MCUP.Loop 1 - F/R/P Pads (12'' larger) | Foundations | Not Started | 07/17/26 | 08/13/26 | 25.0 | 25.0 |
|
195.0 |
RPL08.SUB.DHCD.01150 |
RPL08.SubStructure.DHCD - Install UG Utilities - Plumbing/Testing/Backfill - Part 2 | Underground | Not Started | 07/17/26 | 07/27/26 | 8.8 | 8.8 |
|
156.2 |
RPL08.CFCI.4450 |
RPL08 - Submittals - Finished Carpentry (Millwork/Countertops) | Finished Carpentry (Millwork/Tops) | Not Started | 07/20/26 | 08/14/26 | 25.0 | 25.0 |
|
420.0 |
RPL08.CFCI.4610 |
RPL08 - Submittals Prep & Submit for Review - Interior Painting (Spec 09 91 23) XX | (CFCI) Div. 09 - Painting | Not Started | 07/20/26 | 08/14/26 | 25.0 | 25.0 |
|
323.8 |
RPL08.CFCI.4630 |
RPL08 - Submittals Prep & Submit for Review - Fire Alarm | (CFCI) Div. 26 - Fire Alarm | Not Started | 07/20/26 | 08/14/26 | 25.0 | 25.0 |
|
360.0 |
RPL08.CFCI.4730 |
RPL08 - Submittals Review & Approval - Finished Carpentry (Millwork/Countertops) | Finished Carpentry (Millwork/Tops) | Not Started | 07/20/26 | 08/14/26 | 25.0 | 25.0 |
|
420.0 |
RPL08.CFCI.4950 |
Campus - Submittals Prep & Submit for Review - Landscaping / Irrigation | (CFCI) Div. 32 - Landscape/ Irrigation | Not Started | 07/20/26 | 08/21/26 | 31.2 | 31.2 |
|
460.0 |
RPL08.SUB.DHCD.01100 |
RPL08.SubStructure.DHCD - Install UG Utilities - BMS/EPMS/Testing and Pathway Verification and Backfill (new GS Scope) | Underground | Not Started | 07/20/26 | 07/29/26 | 10.0 | 10.0 |
|
156.2 |
RPL.08.D.70060.XR |
External Tie from RPL07 - Roofing DenseDeck & Flame Down Crew Flow (RPL07.SKN.DHCD.01090) | Internal Milestones (XREFs) | Not Started | 07/21/26 | 07/21/26 | 0.0 | 0.0 |
|
162.5 |
RPL08.STR.DHAB.01010 |
RPL08.Structure.DHAB - Erect Steel/Joist/Decking - WBS Summary | Steel and Decking | Not Started | 07/21/26 | 08/27/26 | 35.0 | 35.0 |
|
126.2 |
RPL08.STR.DHAB.01020 |
RPL08.Structure.DHAB - Erect Steel/Joist/Decking, Remaining UG/SOG - WBS Summary | DH B & DH A | Not Started | 07/21/26 | 11/25/26 | 112.5 | 112.5 |
|
120.0 |
RPL08.STR.DHAB.01200 |
RPL08.Structure.DHAB - Crane Road Prep - Grid Lines 6-11/6-23 | Steel and Decking | Not Started | 07/21/26 | 07/23/26 | 3.8 | 3.8 |
|
137.5 |
RPL08.SUB.DHCD.01170 |
RPL08.SubStructure.DHCD - Install UG Utilities - Electrical/Testing and Pathway Verification and Backfill - Part 2 | Underground | Not Started | 07/21/26 | 07/28/26 | 7.5 | 7.5 |
|
156.2 |
RPL08.VDC.1720 |
T2-4 (DH C & D) - Review & Approve BIM Shop | TIER 2 - 4 - DH C & D | Not Started | 07/22/26 | 08/25/26 | 31.2 | 31.2 |
|
247.5 |
RPL08.VDC.1740 |
T2-4 (mCUP Yard / Ext.) - Procurement Equipments | TIER 2 - 4 - mCUP Yard / Exterior | Not Started | 07/22/26 | 08/11/26 | 18.8 | 18.8 |
|
203.8 |
GCD.RPL08.1360 |
Steel Erection Start - RPL08 | Construction Milestones | Not Started | 07/23/26 | 07/23/26 | 0.0 | 0.0 |
|
490.0 |
RPL08.STR.SSB.01040 |
RPL08.Structure.SSB - Install Erect Steel Columns and Beams, Erect Joist - Grid lines 6-01/6-10 | Steel and Decking | Not Started | 07/23/26 | 08/04/26 | 11.2 | 11.2 |
|
126.2 |
RPL08.STR.DHAB.01220 |
RPL08.Structure.DHAB - Steel Shake out - Grid Lines 6-11/6-23 | Steel and Decking | Not Started | 07/24/26 | 07/30/26 | 6.2 | 6.2 |
|
137.5 |
RPL08.CFCI.5100 |
Campus - Submittal Review & Approval - Asphalt / Paving | (CFCI) Div. 32 - Asphalt/ Conc. Paving | Not Started | 07/27/26 | 08/21/26 | 25.0 | 25.0 |
|
368.8 |
RPL08.MCUP.LP2.1120 |
RPL08.MCUP.Loop 2 - Install Grounding Wire, Grounding Rod, Exothermic Weld & Backfill | Grounding UG | Not Started | 07/29/26 | 08/04/26 | 6.2 | 6.2 |
|
232.5 |
RPL08.CFCI.4300 |
RPL08 - Fabricate / Deliver - Roofing | Roofing | Not Started | 07/30/26 | 09/17/26 | 43.8 | 43.8 |
|
105.0 |
RPL08.CFCI.5690 |
RPL08 - Fabricate / Deliver - Glass / Frames | Glass & Glazing (Alum. Entrances & Curtainwall) | Not Started | 07/30/26 | 10/01/26 | 56.2 | 56.2 |
|
312.5 |
RPL08.MCUP.LP2.1260 |
RPL08.MCUP.Loop 2 - Install UG Generator Conduit Feed | Electrical UG | Not Started | 07/30/26 | 08/04/26 | 5.0 | 5.0 |
|
383.8 |
RPL08.STR.DHCD.01010 |
RPL08.Structure.DHCD - Erect Steel/Joist/Decking - WBS Summary | Steel and Decking | Not Started | 07/30/26 | 09/10/26 | 37.5 | 37.5 |
|
143.8 |
RPL08.STR.DHCD.01020 |
RPL08.Structure.DHCD - Erect Steel/Joist/Decking, Remaining UG/SOG - WBS Summary | DH D & DH C | Not Started | 07/30/26 | 12/19/26 | 122.5 | 122.5 |
|
178.8 |
RPL08.STR.DHCD.01170 |
RPL08.Structure.DHCD - Crane Road Prep - Grid Lines 6-23/6-28 | Steel and Decking | Not Started | 07/30/26 | 08/03/26 | 3.8 | 3.8 |
|
156.2 |
RPL08.CFCI.4820 |
Campus - Submittals Prep & Submit for Review - Asphalt / Paving | (CFCI) Div. 32 - Asphalt/ Conc. Paving | Not Started | 08/03/26 | 08/21/26 | 18.8 | 18.8 |
|
368.8 |
RPL08.CFCI.6040 |
Submittals Review & Approval - Technical Water (Assume HDPE Pipe) | (CFCI) Div. 33 - Utilities Technical Water (Assume HDPE) | Not Started | 08/03/26 | 08/21/26 | 18.8 | 18.8 |
|
186.2 |
ICM.B8.1830 |
[SSDCB3] Delivery of PTX - Pad Mounted Transformers (First Delivery) | Construction | Not Started | 08/04/26 | 08/04/26 | 0.0 | 0.0 |
|
237.5 |
ICM.B8.1835 |
[SSDCB3] Delivery of FCA - Fan Coil Assembly (First Delivery) | Construction | Not Started | 08/04/26 | 08/04/26 | 0.0 | 0.0 |
|
210.0 |
ICM.B8.1860 |
[SSDCB3] Delivery of Dry Cooling Towers (First Delivery) | Construction | Not Started | 08/04/26 | 08/04/26 | 0.0 | 0.0 |
|
210.0 |
RPL08.STR.DHCD.01190 |
RPL08.Structure.DHCD - Steel Shake out - Grid Lines 6-23/6-28 | Steel and Decking | Not Started | 08/04/26 | 08/10/26 | 6.2 | 6.2 |
|
156.2 |
RPL08.STR.DHAB.01000 |
RPL08.Structure.DHAB - Install Erect Steel Columns and Beams, Erect Joist Grid Lines 6-11/6-23 | Steel and Decking | Not Started | 08/05/26 | 08/14/26 | 10.0 | 10.0 |
|
133.8 |
RPL08.STR.SSB.01060 |
RPL08.Structure.SSB - Install Decking & Detailing turnover #1 - Grid lines 6-01/6-04 | Steel and Decking | Not Started | 08/05/26 | 08/10/26 | 5.0 | 5.0 |
|
126.2 |
RPL08.VDC.1760 |
T2-4 (SSB) - GC QC BIM Model | TIER 2 - 4 - SSB | Not Started | 08/05/26 | 08/18/26 | 12.5 | 12.5 |
|
111.2 |
RPL08.CFCI.6050 |
Submittals Review & Approval - Technical Water (Assume HDPE Pipe) | (CFCI) Div. 33 - Utilities Technical Water (Assume HDPE) | Not Started | 08/10/26 | 08/21/26 | 12.5 | 12.5 |
|
186.2 |
RPL08.CFCI.6060 |
Fabricate / Deliver - Technical Water (Assume HDPE Pipe) | (CFCI) Div. 33 - Utilities Technical Water (Assume HDPE) | Not Started | 08/11/26 | 10/06/26 | 50.0 | 50.0 |
|
186.2 |
RPL08.STR.DHAB.01015 |
RPL08.Structure.DHAB - Install Decking & Detailing turnover #2 - Grid lines 6-04/6-07 | Steel and Decking | Not Started | 08/11/26 | 08/13/26 | 3.8 | 3.8 |
|
126.2 |
RPL08.VDC.1780 |
T2-4 (DH A & B) - GC QC BIM Model | TIER 2 - 4 - DH A & B | Not Started | 08/12/26 | 08/25/26 | 12.5 | 12.5 |
|
161.2 |
RPL08.CFCI.6510 |
Fabricate / Deliver - Roof Drain Pipes | (CFCI) Div. 33 - Utilities Storm / Sanitary Manholes and Inlets - Area 2 | Not Started | 08/13/26 | 09/17/26 | 31.2 | 31.2 |
|
105.0 |
PRE.FA.1300 |
Non-Critical Trade Buyout - Final Agreement | Trade Partner Final Agreement | Not Started | 08/14/26 | 08/14/26 | 0.0 | 0.0 |
|
186.2 |
RPL08.MCUP.LP1.1180 |
RPL08.MCUP.Loop 1 - Cure for Pads | Foundations | Not Started | 08/14/26 | 08/20/26 | 8.8 | 8.8 |
|
288.8 |
RPL08.MCUP.LP1.1200 |
RPL08.MCUP.Loop 1 - OFE - WBS Summary | OFE | Not Started | 08/14/26 | 10/02/26 | 43.8 | 43.8 |
|
205.0 |
RPL08.MCUP.LP1.2120 |
RPL08.MCUP.Loop 1 - Set Facility Water Pipe Rack (mCUP1) | OFE | Not Started | 08/14/26 | 08/27/26 | 12.5 | 12.5 |
|
206.2 |
RPL08.MCUP.LP2.1020 |
RPL08.MCUP.Loop 2 - Install Foundations - WBS Summary | Foundations | Not Started | 08/14/26 | 09/03/26 | 18.8 | 18.8 |
|
352.5 |
RPL08.MCUP.LP2.1160 |
RPL08.MCUP.Loop 2 - F/R/P Pads (12'' larger) | Foundations | Not Started | 08/14/26 | 08/27/26 | 12.5 | 12.5 |
|
352.5 |
RPL08.SKIN.01000 |
RPL08.SKIN.BLDG - Install Insulated Metal Panels (IMP), Roof, Windows, Doors, Louvers - WBS Summary | Skin | Not Started | 08/14/26 | 07/22/27 | 292.5 | 292.5 |
|
273.8 |
RPL08.SKN.W.01000 |
RPL08.SKIN.West - Install Metal Panel Sealant & Starter Flashing - West North South East | IMP System | Not Started | 08/14/26 | 08/27/26 | 12.5 | 12.5 |
|
130.0 |
RPL08.STR.DHAB.01025 |
RPL08.Structure.DHAB - Install Decking & Detailing turnover #3 - Grid lines 6-07/6-10 | Steel and Decking | Not Started | 08/14/26 | 08/18/26 | 3.8 | 3.8 |
|
126.2 |
RPL08.CFCI.4620 |
RPL08 - Submittals Prep & Submit for Review -Epoxy Flooring (Spec 09 67 23) XX | (CFCI) Div. 09 - Epoxy Flooring | Not Started | 08/17/26 | 09/14/26 | 25.0 | 25.0 |
|
298.8 |
RPL08.CFCI.4810 |
RPL08 - Submittals Prep & Submit for Review - Specialities | (CFCI) Div. 10 - Specialities | Not Started | 08/17/26 | 09/14/26 | 25.0 | 25.0 |
|
285.0 |
RPL08.CFCI.4870 |
RPL08 - Submittals Review & Approval - Interior Painting (Spec 09 91 23) XX | (CFCI) Div. 09 - Painting | Not Started | 08/17/26 | 09/14/26 | 25.0 | 25.0 |
|
336.2 |
RPL08.CFCI.4890 |
RPL08 - Submittals Review & Approval - Fire Alarm | (CFCI) Div. 26 - Fire Alarm | Not Started | 08/17/26 | 09/04/26 | 18.8 | 18.8 |
|
360.0 |
RPL08.CFCI.4960 |
RPL08 - Fabricate / Deliver - Finished Carpentry (Millwork/Countertops) | Finished Carpentry (Millwork/Tops) | Not Started | 08/17/26 | 09/28/26 | 37.5 | 37.5 |
|
420.0 |
RPL08.STR.DHCD.01000 |
RPL08.Structure.DHCD - Install Erect Steel Columns and Beams, Erect Joist - Grid Lines 6-23/6-28 | Steel and Decking | Not Started | 08/17/26 | 08/25/26 | 8.8 | 8.8 |
|
151.2 |
GCD.RPL08.1380 |
IMP Start - RPL08 | Construction Milestones | Not Started | 08/18/26 | 08/18/26 | 0.0 | 0.0 |
|
467.5 |
RPL08.LOG.1120 |
Dry Cooler 230 Ton Crane Mobilization | 100 Ton Crane | Not Started | 08/18/26 | 08/20/26 | 3.8 | 3.8 |
|
195.0 |
RPL08.SKN.W.01005 |
RPL08.SKIN.West - Install IMP - Flashing,Panels & Caulking - Gird lines 6A/6F (with temp closures for openings) | DBC Move 1 - Grid (6-01 / 6-07) | Not Started | 08/18/26 | 08/19/26 | 2.5 | 2.5 |
|
130.0 |
RPL08.SKN.W.01010 |
RPL08.SKIN.West - Install IMP Insulated Metal Panels System - WBS Summary | DBC Move 1 - Grid (6-01 / 6-07) | Not Started | 08/18/26 | 08/27/26 | 10.0 | 10.0 |
|
130.0 |
RPL08.STR.DHAB.01030 |
RPL08.Structure.DHAB - Install Decking & Detailing turnover #4 - Grid lines 6-10/6-14 | Steel and Decking | Not Started | 08/19/26 | 08/24/26 | 5.0 | 5.0 |
|
126.2 |
RPL08.VDC.1800 |
T2-4 (EF) - GC QC BIM Model | TIER 2 - 4 - EF | Not Started | 08/19/26 | 09/01/26 | 12.5 | 12.5 |
|
197.5 |
RPL08.VDC.1820 |
T2-4 (SSB) - Create Spool Sheet for Fab | TIER 2 - 4 - SSB | Not Started | 08/19/26 | 09/09/26 | 18.8 | 18.8 |
|
111.2 |
RPL08.EY.SSB.01000 |
RPL08.EY.SSB - Install F/R/P Equipment Pads | Foundations | Not Started | 08/20/26 | 09/02/26 | 12.5 | 12.5 |
|
182.5 |
RPL08.EY.SSB.01010 |
RPL08.EY.SSB - Install Foundations - WBS Summary | Foundations | Not Started | 08/20/26 | 09/09/26 | 17.5 | 17.5 |
|
215.0 |
RPL08.EY.SSB.01020 |
RPL08.EY.SSB - Install Foundations, UG Utilities, OFE - WBS Summary | EY.SSB | Not Started | 08/20/26 | 08/16/27 | 308.8 | 308.8 |
|
291.2 |
RPL08.EY.SSB.01030 |
RPL08.EY.BLDG - Install Foundations, UG Utilities, OFE- WBS Summary | Electrical Yard | Not Started | 08/20/26 | 10/15/27 | 362.5 | 362.5 |
|
237.5 |
RPL08.EY.SSB.01100 |
RPL08.EY.SSB - OFE - WBS Summary | OFE | Not Started | 08/20/26 | 09/28/26 | 33.8 | 33.8 |
|
207.5 |
RPL08.EY.SSB.01380 |
RPL08.EY.SSB - Install Wall Mounted AC units (5) - CFCI | OFE | Not Started | 08/20/26 | 08/28/26 | 8.8 | 8.8 |
|
230.0 |