Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL08 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:14 PM
· 5122 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
0
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL08.EY.SSB.02020 |
RPL08.EY.SSB - Install Temp Conditioning Units - CFCI | Temp Conditions | Not Started | 08/20/26 | 08/26/26 | 6.2 | 6.2 |
|
172.5 |
RPL08.LOG.1000 |
MCUP 500 Ton Crane Mobilization | 300 Ton Crane | Not Started | 08/20/26 | 08/25/26 | 5.0 | 5.0 |
|
201.2 |
RPL08.SKN.N.01000 |
RPL08.SKIN.North - Install IMP - Flashing,Panels & Caulking - Grid lines 6-01/6-07 (with temp closures for ope | DBC Move 1 - Grid (6-01 / 6-07) | Not Started | 08/20/26 | 08/24/26 | 3.8 | 3.8 |
|
130.0 |
RPL08.SKN.SSB.01000 |
RPL08.SKIN.SSB - Install Temp Doors | Glazing, Doors and Ext Devices | Not Started | 08/20/26 | 08/21/26 | 2.5 | 2.5 |
|
412.5 |
RPL08.SKN.SSB.01020 |
RPL08.SKIN.SSB - IMP, Roof, Windows, Doors, Ext Devices - WBS Summary | SSB | Not Started | 08/20/26 | 02/02/27 | 140.0 | 140.0 |
|
287.5 |
RPL08.SKN.SSB.01030 |
RPL08.SKIN.SSB - Install Windows, Doors, Louvers and Ext Devices - WBS Summary | Glazing, Doors and Ext Devices | Not Started | 08/20/26 | 02/02/27 | 140.0 | 140.0 |
|
287.5 |
RPL08.SKN.SSB.01050 |
RPL08.SKIN.SSB - Install Lighting | Glazing, Doors and Ext Devices | Not Started | 08/20/26 | 08/25/26 | 5.0 | 5.0 |
|
402.5 |
RPL08.SKN.SSB.01170 |
RPL08.SKIN.SSB - Install Blocking of Canopy & Backing of Exterior Wall | Glazing, Doors and Ext Devices | Not Started | 08/20/26 | 08/26/26 | 6.2 | 6.2 |
|
196.2 |
RPL08.SKN.W.01040 |
RPL08.SKIN.West - Secure All Exterior Mounted Boxes and Devices on Skin | IMP System | Not Started | 08/20/26 | 09/02/26 | 12.5 | 12.5 |
|
441.2 |
RPL08.MCUP.FWM.01000 |
RPL08.MCUP.FWM - Install PTX | FWM | Not Started | 08/21/26 | 08/25/26 | 3.8 | 3.8 |
|
222.5 |
RPL08.MCUP.FWM.01010 |
RPL08.MCUP.FWM - Install FWM | FWM | Not Started | 08/21/26 | 08/25/26 | 3.8 | 3.8 |
|
222.5 |
RPL08.MCUP.FWM.01030 |
RPL08.MCUP.FWM - Install MVS | FWM | Not Started | 08/21/26 | 08/25/26 | 3.8 | 3.8 |
|
222.5 |
RPL08.MCUP.LP1.1220 |
RPL08.MCUP.Loop 1 - Set mCup #1 & #2 - Dry Coolers (12) (4 per week) | OFE | Not Started | 08/21/26 | 09/11/26 | 18.8 | 18.8 |
|
195.0 |
RPL08.CFCI.5270 |
Campus - Fabricate / Deliver - Asphalt / Paving | (CFCI) Div. 32 - Asphalt/ Conc. Paving | Not Started | 08/24/26 | 09/14/26 | 18.8 | 18.8 |
|
368.8 |
RPL08.CFCI.5280 |
Campus - Submittals Review & Approval - Landscaping / Irrigation | (CFCI) Div. 32 - Landscape/ Irrigation | Not Started | 08/24/26 | 09/21/26 | 25.0 | 25.0 |
|
460.0 |
ICM.B8.1875 |
[SSDCB3] Delivery of mCUP (First Delivery) | Construction | Not Started | 08/25/26 | 08/25/26 | 0.0 | 0.0 |
|
201.2 |
RPL.08.D.70100.XR |
External Tie from RPL06 - mCup Equipment Crane Crew Flow (RPL07.MCUP.LP2.1500) | Internal Milestones (XREFs) | Not Started | 08/25/26 | 08/25/26 | 0.0 | 0.0 |
|
201.2 |
RPL.08.D.84510.XR |
Storm Drain Available for Roof Drain Tie-ins | Receive Milestones (XREFs) | Not Started | 08/25/26 | 08/25/26 | 0.0 | 0.0 |
|
132.5 |
RPL08.SKN.S.01000 |
RPL08.SKIN.South - Install IMP - Flashing,Panels & Caulking - Grid lines 6-01/6-07 (with temp closures for openings) | DBC Move 1 - Grid (6-01 / 6-07) | Not Started | 08/25/26 | 08/27/26 | 3.8 | 3.8 |
|
130.0 |
RPL08.STR.DHAB.01035 |
RPL08.Structure.DHAB - Install Decking & Detailing turnover #5 - Grid lines 6-14/6-18 | Steel and Decking | Not Started | 08/25/26 | 08/27/26 | 3.8 | 3.8 |
|
126.2 |
RPL08.STR.SSB.01100 |
RPL08.Structure.SSB - Adjust MEP Verts and Grounding wire | Prep | Not Started | 08/25/26 | 08/31/26 | 6.2 | 6.2 |
|
126.2 |
RPL08.STR.SSB.01110 |
RPL08.Structure.SSB - Install Remaining UG and Subgrade Prep - WBS Summary | Prep | Not Started | 08/25/26 | 09/14/26 | 17.5 | 17.5 |
|
126.2 |
GCD.RPL08.1182 |
Start mCUP Unit Set-In-Place - RPL08 | Construction Milestones | Not Started | 08/26/26 | 08/26/26 | 0.0 | 0.0 |
|
447.5 |
RPL08.EY.ENDC.01020 |
RPL08.EY.End - Install Foundations, UG Utilities, OFE - WBS Summary | EY.EC | Not Started | 08/26/26 | 10/15/27 | 357.5 | 357.5 |
|
237.5 |
RPL08.EY.ENDC.01300 |
RPL08.EY.DHD.T1 - Install Shallow Tent UG | Tent 1 | Not Started | 08/26/26 | 08/28/26 | 3.8 | 3.8 |
|
151.2 |
RPL08.LOG.1860 |
Steel Crane #1 Demobilzation | Steel Crane 1 | Not Started | 08/26/26 | 08/26/26 | 0.0 | 0.0 |
|
185.0 |
RPL08.LOG.1880 |
Steel Crane #2 Demobilization | Steel Crane 2 | Not Started | 08/26/26 | 08/26/26 | 0.0 | 0.0 |
|
185.0 |
RPL08.MCUP.LP1.1340 |
RPL08.MCUP.Loop 1 - Set mCUPs XXMY.MCUP.01 (1 per 5 days) | OFE | Not Started | 08/26/26 | 09/01/26 | 6.2 | 6.2 |
|
201.2 |
RPL08.SKN.SSB.01070 |
RPL08.SKIN.SSB - Install Security | Glazing, Doors and Ext Devices | Not Started | 08/26/26 | 08/27/26 | 2.5 | 2.5 |
|
402.5 |
RPL08.VDC.1840 |
T2-4 (DH C & D) - GC QC BIM Model | TIER 2 - 4 - DH C & D | Not Started | 08/26/26 | 09/09/26 | 12.5 | 12.5 |
|
247.5 |
RPL08.EY.SSB.02040 |
RPL08.EY.SSB - Install Temp Duct to Permanent Duct | Temp Conditions | Not Started | 08/27/26 | 09/02/26 | 6.2 | 6.2 |
|
172.5 |
RPL08.SKN.SSB.01075 |
RPL08.SKIN.SSB - QC Blocking | Glazing, Doors and Ext Devices | Not Started | 08/27/26 | 08/28/26 | 2.5 | 2.5 |
|
398.8 |
RPL08.MCUP.LP1.2140 |
RPL08.MCUP.Loop 1 - Set Facility Water Pipe Rack (mCUP2) | OFE | Not Started | 08/28/26 | 09/09/26 | 10.0 | 10.0 |
|
206.2 |
RPL08.MCUP.LP2.1180 |
RPL08.MCUP.Loop 2 - Cure for Pads | Foundations | Not Started | 08/28/26 | 09/03/26 | 8.8 | 8.8 |
|
515.0 |
RPL08.STR.DHCD.01015 |
RPL08.Structure.DHCD - Install Decking & Detailing turnover #6 - Grid lines 6-18/6-21 | Steel and Decking | Not Started | 08/28/26 | 09/01/26 | 3.8 | 3.8 |
|
126.2 |
RPL08.EY.ENDC.01360 |
RPL08.EY.DHD.T2 - Install Shallow Tent UG | Tent 2 | Not Started | 08/31/26 | 09/02/26 | 3.8 | 3.8 |
|
161.2 |
RPL08.EY.ENDC.1310 |
RPL08.EY.DHD.T1 - Install Final Grading | Tent 1 | Not Started | 08/31/26 | 09/01/26 | 2.5 | 2.5 |
|
151.2 |
RPL08.SKN.SSB.01040 |
RPL08.SKIN.SSB - Install Louvers | Glazing, Doors and Ext Devices | Not Started | 08/31/26 | 09/04/26 | 6.2 | 6.2 |
|
392.5 |
RPL08.STR.SSB.01120 |
RPL08.Structure.SSB - Install AB final grade and Vapor Barrier | Prep | Not Started | 09/01/26 | 09/08/26 | 6.2 | 6.2 |
|
126.2 |
RPL08.EY.ENDC.1330 |
RPL08.EY.DHD.T1 - Install F/R/P Tent1 Slab | Tent 1 | Not Started | 09/02/26 | 09/09/26 | 6.2 | 6.2 |
|
151.2 |
RPL08.MCUP.LP1.1360 |
RPL08.MCUP.Loop 1 - Set Electrical Skids #1 | OFE | Not Started | 09/02/26 | 09/03/26 | 2.5 | 2.5 |
|
216.2 |
RPL08.MCUP.LP1.1380 |
RPL08.MCUP.Loop 1 - Set mCUPs XXMY.MCUP.02 (1 per 5 days) | OFE | Not Started | 09/02/26 | 09/09/26 | 6.2 | 6.2 |
|
201.2 |
RPL08.SKN.N.01010 |
RPL08.SKIN.North - Install IMP Insulated Metal Panels System - WBS Summary | DBC Move 2 - Grid (6-07 / 6-21) | Not Started | 09/02/26 | 09/25/26 | 21.2 | 21.2 |
|
513.8 |
RPL08.SKN.S.01030 |
RPL08.SKIN.South - Install IMP - Flashing,Panels & Caulking - Grid lines 6-07/6-14 (with temp closures for openings) | DBC Move 2 - Grid (6-07 / 6-21) | Not Started | 09/02/26 | 09/04/26 | 3.8 | 3.8 |
|
126.2 |
RPL08.STR.DHCD.01025 |
RPL08.Structure.DHCD - Install Decking & Detailing turnover #7 - Grid lines 6-21/6-25 | Steel and Decking | Not Started | 09/02/26 | 09/04/26 | 3.8 | 3.8 |
|
141.2 |
RPL08.EY.ENDC.1610 |
RPL08.EY.DHD.T2 - Install Final Grading | Tent 2 | Not Started | 09/03/26 | 09/04/26 | 2.5 | 2.5 |
|
161.2 |
RPL08.EY.SSB.01040 |
RPL08.EY.SSB - Install Electrical UG | Underground | Not Started | 09/03/26 | 09/10/26 | 6.2 | 6.2 |
|
182.5 |
RPL08.EY.SSB.01050 |
RPL08.EY.SSB - Install Cure (High Early Mix) | Foundations | Not Started | 09/03/26 | 09/09/26 | 8.8 | 8.8 |
|
315.0 |
RPL08.EY.SSB.01060 |
RPL08.EY.SSB - Install UG Utilities - WBS Summary | Underground | Not Started | 09/03/26 | 10/01/26 | 25.0 | 25.0 |
|
195.0 |
RPL08.EY.SSB.01180 |
RPL08.EY.SSB - Tie-ins - WBS Summary | Tie-ins | Not Started | 09/03/26 | 01/21/27 | 117.5 | 117.5 |
|
133.8 |
RPL08.EY.SSB.01400 |
RPL08.EY.SSB - Install Duct/ insulation into the building Main (include penetration detail) | Tie-ins | Not Started | 09/03/26 | 09/24/26 | 18.8 | 18.8 |
|
188.8 |
RPL08.MCUP.LP1.1400 |
RPL08.MCUP.Loop 1 - Tie-ins - WBS Summary | Tie-ins | Not Started | 09/04/26 | 10/28/26 | 47.5 | 47.5 |
|
472.5 |
RPL08.MCUP.LP1.1440 |
RPL08.MCUP.Loop 1 - Tie-in Mechanical - WBS Summary | Tie-Ins Mechanical | Not Started | 09/04/26 | 10/21/26 | 41.2 | 41.2 |
|
195.0 |
RPL08.MCUP.LP1.1460 |
RPL08.MCUP.Loop 1 - Tie-in Mechanical #1 | Tie-Ins Mechanical | Not Started | 09/04/26 | 09/25/26 | 18.8 | 18.8 |
|
217.5 |
RPL08.CFCI.5090 |
RPL08 - Fabricate / Deliver - Fire Alarm | (CFCI) Div. 26 - Fire Alarm | Not Started | 09/08/26 | 11/02/26 | 50.0 | 50.0 |
|
360.0 |
RPL08.EY.DHA.01010 |
RPL08.EY.DHA - Install F/R/P Equipment Pads - 1-12 (Grid 6-01/6-16) (12'' Larger For Tolerance) | Foundations | Not Started | 09/08/26 | 10/05/26 | 25.0 | 25.0 |
|
183.8 |
RPL08.EY.DHA.01020 |
RPL08.EY.DHA - Install Foundations - WBS Summary | Foundations | Not Started | 09/08/26 | 10/12/26 | 31.2 | 31.2 |
|
183.8 |
RPL08.EY.DHA.01030 |
RPL08.EY.DHA - Install Foundations, UG Utilities, OFE- WBS Summary | EY.DHA | Not Started | 09/08/26 | 05/11/27 | 210.0 | 210.0 |
|
375.0 |
RPL08.EY.ENDC.1630 |
RPL08.EY.DHD.T2 - Install F/R/P Tent1 Slab | Tent 2 | Not Started | 09/08/26 | 09/14/26 | 6.2 | 6.2 |
|
161.2 |
RPL08.EY.SSB.01420 |
RPL08.EY.SSB - Install Grounding UG | Underground | Not Started | 09/08/26 | 09/14/26 | 6.2 | 6.2 |
|
205.0 |
RPL08.SKN.N.01030 |
RPL08.SKIN.North - Install IMP - Flashing,Panels & Caulking - Grid lines 6-07/6-14 (with temp closures for openings) | DBC Move 2 - Grid (6-07 / 6-21) | Not Started | 09/08/26 | 09/09/26 | 2.5 | 2.5 |
|
126.2 |
RPL08.SKN.S.01010 |
RPL08.SKIN.South - Install IMP Insulated Metal Panels System - WBS Summary | DBC Move 3 - Grid (6-21 / 6-28) | Not Started | 09/08/26 | 09/30/26 | 21.2 | 21.2 |
|
510.0 |
RPL08.SKN.S.01040 |
RPL08.SKIN.South - Install IMP EJ - Grid lines 6-09/6-10 | DBC Move 2 - Grid (6-07 / 6-21) | Not Started | 09/08/26 | 09/14/26 | 6.2 | 6.2 |
|
145.0 |
RPL08.SKN.S.01140 |
RPL08.SKIN.South - Install Stair Tower (DH A) | DBC Move 3 - Grid (6-21 / 6-28) | Not Started | 09/08/26 | 09/09/26 | 2.5 | 2.5 |
|
247.5 |
RPL08.SKN.SSB.01060 |
RPL08.SKIN.SSB - Install Awning over Doors | Glazing, Doors and Ext Devices | Not Started | 09/08/26 | 09/14/26 | 6.2 | 6.2 |
|
400.0 |
RPL08.STR.DHAB.01060 |
RPL08.Structure.DHAB - Adjust MEP Verts and Grounding wire | Prep | Not Started | 09/08/26 | 09/14/26 | 6.2 | 6.2 |
|
141.2 |
RPL08.STR.DHAB.01070 |
RPL08.Structure.DHAB - Install Remaining UG and Subgrade Prep - WBS Summary | Prep | Not Started | 09/08/26 | 09/24/26 | 16.2 | 16.2 |
|
141.2 |
RPL08.STR.DHCD.01035 |
RPL08.Structure.DHCD - Install Decking & Detailing turnover #8 - Grid lines 6-25/6-28 | Steel and Decking | Not Started | 09/08/26 | 09/10/26 | 3.8 | 3.8 |
|
143.8 |
RPL08.LOG.1020 |
MCUP 500 Ton Crane Movement 1 | 300 Ton Crane | Not Started | 09/09/26 | 09/09/26 | 0.0 | 0.0 |
|
201.2 |
RPL08.STR.SSB.01130 |
RPL08.Structure.SSB - Asphalt Emulsion and Wrap Steel Columns | Prep | Not Started | 09/09/26 | 09/14/26 | 5.0 | 5.0 |
|
126.2 |
GCD.RPL08.1320 |
Steel Complete - RPL08 | Construction Milestones | Not Started | 09/10/26 | 09/10/26 | 0.0 | 0.0 |
|
171.2 |
GCD.RPL08.1456 |
Start RPL08 EY RMU Equipment Pad Placement - RPL08 | Construction Milestones | Not Started | 09/10/26 | 09/10/26 | 0.0 | 0.0 |
|
447.5 |
RPL08.EY.DHB.01010 |
RPL08.EY.DHB - Install F/R/P Equipment Pads - 1-12(Grid 6-01/6-16) (12'' Larger For Tolerance) | Foundations | Not Started | 09/10/26 | 10/07/26 | 25.0 | 25.0 |
|
162.5 |
RPL08.EY.DHB.01020 |
RPL08.EY.DHB - Install Foundations - WBS Summary | Foundations | Not Started | 09/10/26 | 10/14/26 | 31.2 | 31.2 |
|
162.5 |
RPL08.EY.DHB.01030 |
RPL08.EY.DHB - Install Foundations, UG Utilities, OFE - WBS Summary | EY.DHB | Not Started | 09/10/26 | 04/16/27 | 186.2 | 186.2 |
|
396.2 |
RPL08.EY.ENDC.1350 |
RPL08.EY.DHD.T1 - Install Saw Cut and Cure | Tent 1 | Not Started | 09/10/26 | 09/16/26 | 8.8 | 8.8 |
|
225.0 |
RPL08.MCUP.LP1.1240 |
RPL08.MCUP.Loop 1 - Set GS.IDF Hut (1x GS.IDF) XX01 | OFE | Not Started | 09/10/26 | 09/16/26 | 6.2 | 6.2 |
|
201.2 |
RPL08.MCUP.LP1.1500 |
RPL08.MCUP.Loop 1 - Set mCUPs XXMY.MCUP.03 (1 per 5 days) | OFE | Not Started | 09/10/26 | 09/16/26 | 6.2 | 6.2 |
|
201.2 |
RPL08.MCUP.LP1.1520 |
RPL08.MCUP.Loop 1 - Set Electrical Skids #2 | OFE | Not Started | 09/10/26 | 09/11/26 | 2.5 | 2.5 |
|
212.5 |
RPL08.MCUP.LP1.2160 |
RPL08.MCUP.Loop 1 - Set Facility Water Pipe Rack (mCUP3) | OFE | Not Started | 09/10/26 | 09/21/26 | 10.0 | 10.0 |
|
206.2 |
RPL08.SKN.DHAB.01000 |
RPL08.SKIN.DHAB - Install Temp Doors | Glazing, Doors and Ext Devices | Not Started | 09/10/26 | 09/11/26 | 2.5 | 2.5 |
|
152.5 |
RPL08.SKN.DHAB.01010 |
RPL08.SKIN.DHAB - IMP, Roof, Windows, Doors, Ext Devices - WBS Summary | DH A & DH B | Not Started | 09/10/26 | 11/16/26 | 58.8 | 58.8 |
|
357.5 |
RPL08.SKN.DHAB.01020 |
RPL08.SKIN.DHAB - Install Windows, Doors, Louvers and Ext Devices - WBS Summary | Glazing, Doors and Ext Devices | Not Started | 09/10/26 | 10/21/26 | 37.5 | 37.5 |
|
378.8 |
RPL08.SKN.N.01040 |
RPL08.SKIN.North - Install IMP EJ - Grid lines 6-09/6-10 | DBC Move 2 - Grid (6-07 / 6-21) | Not Started | 09/10/26 | 09/16/26 | 6.2 | 6.2 |
|
140.0 |
RPL08.SKN.N.01080 |
RPL08.SKIN.North - Install IMP - Flashing,Panels & Caulking - Grid lines 6-14/6-21 (with temp closures for openings) | DBC Move 2 - Grid (6-07 / 6-21) | Not Started | 09/10/26 | 09/11/26 | 2.5 | 2.5 |
|
140.0 |
RPL08.SKN.N.01120 |
RPL08.SKIN.North - Install Stair Tower (DH B) | DBC Move 2 - Grid (6-07 / 6-21) | Not Started | 09/10/26 | 09/11/26 | 2.5 | 2.5 |
|
245.0 |
RPL08.VDC.1860 |
T2-4 (SSB) - Procurement Materials | TIER 2 - 4 - SSB | Not Started | 09/10/26 | 09/30/26 | 18.8 | 18.8 |
|
111.2 |
RPL08.EY.DHA.01060 |
RPL08.EY.DHA - Install Electrical UG | Underground | Not Started | 09/11/26 | 09/24/26 | 12.5 | 12.5 |
|
201.2 |
RPL08.EY.DHA.01070 |
RPL08.EY.DHA - Install UG Utilities - WBS Summary | Underground | Not Started | 09/11/26 | 10/22/26 | 37.5 | 37.5 |
|
201.2 |
RPL08.EY.DHB.01060 |
RPL08.EY.DHB - Install Electrical UG | Underground | Not Started | 09/11/26 | 09/24/26 | 12.5 | 12.5 |
|
182.5 |
RPL08.EY.DHB.01070 |
RPL08.EY.DHB - Install UG Utilities - WBS Summary | Underground | Not Started | 09/11/26 | 10/22/26 | 37.5 | 37.5 |
|
182.5 |
RPL08.EY.SSB.01070 |
RPL08.EY.SSB - Install Mechanical UG | Underground | Not Started | 09/11/26 | 09/17/26 | 6.2 | 6.2 |
|
188.8 |
RPL08.LOG.1140 |
Dry Cooler 230 Ton Crane Movement 01 | 100 Ton Crane | Not Started | 09/11/26 | 09/11/26 | 0.0 | 0.0 |
|
195.0 |
RPL08.STR.DHCD.01060 |
RPL08.Structure.DHCD - Adjust MEP Verts and Grounding wire | Prep | Not Started | 09/11/26 | 09/17/26 | 6.2 | 6.2 |
|
155.0 |
RPL08.STR.DHCD.01070 |
RPL08.Structure.DHCD - Install Remaining UG and Subgrade Prep - WBS Summary | Prep | Not Started | 09/11/26 | 09/29/26 | 16.2 | 16.2 |
|
155.0 |
RPL08.MCUP.LP1.1280 |
RPL08.MCUP.Loop 1 - Set MTRs (4 per day) | OFE | Not Started | 09/14/26 | 09/18/26 | 6.2 | 6.2 |
|
195.0 |
RPL08.MCUP.LP1.1320 |
RPL08.MCUP.Loop 1 - Set mCup #3 & #4 - Dry Coolers (12) (4 per week) | OFE | Not Started | 09/14/26 | 10/02/26 | 18.8 | 18.8 |
|
195.0 |
RPL08.MCUP.LP1.1660 |
RPL08.MCUP.Loop 1 - Tie-in SD, DW | Tie-ins | Not Started | 09/14/26 | 10/02/26 | 18.8 | 18.8 |
|
495.0 |
RPL08.MCUP.LP1.1760 |
RPL08.MCUP.Loop 1 - Tie-in Mechanical #2 | Tie-Ins Mechanical | Not Started | 09/14/26 | 10/02/26 | 18.8 | 18.8 |
|
211.2 |
RPL08.SKN.DHAB.01160 |
RPL08.SKIN.DHAB - Install Blocking of Canopy & Backing of Exterior Wall | Glazing, Doors and Ext Devices | Not Started | 09/14/26 | 09/18/26 | 6.2 | 6.2 |
|
152.5 |