Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL08 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:14 PM · 5122 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
0
Completed
0
In Progress
0
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL08.EY.SSB.02020 RPL08.EY.SSB - Install Temp Conditioning Units - CFCI Temp Conditions Not Started 08/20/26 08/26/26 6.2 6.2
0%
172.5
RPL08.LOG.1000 MCUP 500 Ton Crane Mobilization 300 Ton Crane Not Started 08/20/26 08/25/26 5.0 5.0
0%
201.2
RPL08.SKN.N.01000 RPL08.SKIN.North - Install IMP - Flashing,Panels & Caulking - Grid lines 6-01/6-07 (with temp closures for ope DBC Move 1 - Grid (6-01 / 6-07) Not Started 08/20/26 08/24/26 3.8 3.8
0%
130.0
RPL08.SKN.SSB.01000 RPL08.SKIN.SSB - Install Temp Doors Glazing, Doors and Ext Devices Not Started 08/20/26 08/21/26 2.5 2.5
0%
412.5
RPL08.SKN.SSB.01020 RPL08.SKIN.SSB - IMP, Roof, Windows, Doors, Ext Devices - WBS Summary SSB Not Started 08/20/26 02/02/27 140.0 140.0
0%
287.5
RPL08.SKN.SSB.01030 RPL08.SKIN.SSB - Install Windows, Doors, Louvers and Ext Devices - WBS Summary Glazing, Doors and Ext Devices Not Started 08/20/26 02/02/27 140.0 140.0
0%
287.5
RPL08.SKN.SSB.01050 RPL08.SKIN.SSB - Install Lighting Glazing, Doors and Ext Devices Not Started 08/20/26 08/25/26 5.0 5.0
0%
402.5
RPL08.SKN.SSB.01170 RPL08.SKIN.SSB - Install Blocking of Canopy & Backing of Exterior Wall Glazing, Doors and Ext Devices Not Started 08/20/26 08/26/26 6.2 6.2
0%
196.2
RPL08.SKN.W.01040 RPL08.SKIN.West - Secure All Exterior Mounted Boxes and Devices on Skin IMP System Not Started 08/20/26 09/02/26 12.5 12.5
0%
441.2
RPL08.MCUP.FWM.01000 RPL08.MCUP.FWM - Install PTX FWM Not Started 08/21/26 08/25/26 3.8 3.8
0%
222.5
RPL08.MCUP.FWM.01010 RPL08.MCUP.FWM - Install FWM FWM Not Started 08/21/26 08/25/26 3.8 3.8
0%
222.5
RPL08.MCUP.FWM.01030 RPL08.MCUP.FWM - Install MVS FWM Not Started 08/21/26 08/25/26 3.8 3.8
0%
222.5
RPL08.MCUP.LP1.1220 RPL08.MCUP.Loop 1 - Set mCup #1 & #2 - Dry Coolers (12) (4 per week) OFE Not Started 08/21/26 09/11/26 18.8 18.8
0%
195.0
RPL08.CFCI.5270 Campus - Fabricate / Deliver - Asphalt / Paving (CFCI) Div. 32 - Asphalt/ Conc. Paving Not Started 08/24/26 09/14/26 18.8 18.8
0%
368.8
RPL08.CFCI.5280 Campus - Submittals Review & Approval - Landscaping / Irrigation (CFCI) Div. 32 - Landscape/ Irrigation Not Started 08/24/26 09/21/26 25.0 25.0
0%
460.0
ICM.B8.1875 [SSDCB3] Delivery of mCUP (First Delivery) Construction Not Started 08/25/26 08/25/26 0.0 0.0
0%
201.2
RPL.08.D.70100.XR External Tie from RPL06 - mCup Equipment Crane Crew Flow (RPL07.MCUP.LP2.1500) Internal Milestones (XREFs) Not Started 08/25/26 08/25/26 0.0 0.0
0%
201.2
RPL.08.D.84510.XR Storm Drain Available for Roof Drain Tie-ins Receive Milestones (XREFs) Not Started 08/25/26 08/25/26 0.0 0.0
0%
132.5
RPL08.SKN.S.01000 RPL08.SKIN.South - Install IMP - Flashing,Panels & Caulking - Grid lines 6-01/6-07 (with temp closures for openings) DBC Move 1 - Grid (6-01 / 6-07) Not Started 08/25/26 08/27/26 3.8 3.8
0%
130.0
RPL08.STR.DHAB.01035 RPL08.Structure.DHAB - Install Decking & Detailing turnover #5 - Grid lines 6-14/6-18 Steel and Decking Not Started 08/25/26 08/27/26 3.8 3.8
0%
126.2
RPL08.STR.SSB.01100 RPL08.Structure.SSB - Adjust MEP Verts and Grounding wire Prep Not Started 08/25/26 08/31/26 6.2 6.2
0%
126.2
RPL08.STR.SSB.01110 RPL08.Structure.SSB - Install Remaining UG and Subgrade Prep - WBS Summary Prep Not Started 08/25/26 09/14/26 17.5 17.5
0%
126.2
GCD.RPL08.1182 Start mCUP Unit Set-In-Place - RPL08 Construction Milestones Not Started 08/26/26 08/26/26 0.0 0.0
0%
447.5
RPL08.EY.ENDC.01020 RPL08.EY.End - Install Foundations, UG Utilities, OFE - WBS Summary EY.EC Not Started 08/26/26 10/15/27 357.5 357.5
0%
237.5
RPL08.EY.ENDC.01300 RPL08.EY.DHD.T1 - Install Shallow Tent UG Tent 1 Not Started 08/26/26 08/28/26 3.8 3.8
0%
151.2
RPL08.LOG.1860 Steel Crane #1 Demobilzation Steel Crane 1 Not Started 08/26/26 08/26/26 0.0 0.0
0%
185.0
RPL08.LOG.1880 Steel Crane #2 Demobilization Steel Crane 2 Not Started 08/26/26 08/26/26 0.0 0.0
0%
185.0
RPL08.MCUP.LP1.1340 RPL08.MCUP.Loop 1 - Set mCUPs XXMY.MCUP.01 (1 per 5 days) OFE Not Started 08/26/26 09/01/26 6.2 6.2
0%
201.2
RPL08.SKN.SSB.01070 RPL08.SKIN.SSB - Install Security Glazing, Doors and Ext Devices Not Started 08/26/26 08/27/26 2.5 2.5
0%
402.5
RPL08.VDC.1840 T2-4 (DH C & D) - GC QC BIM Model TIER 2 - 4 - DH C & D Not Started 08/26/26 09/09/26 12.5 12.5
0%
247.5
RPL08.EY.SSB.02040 RPL08.EY.SSB - Install Temp Duct to Permanent Duct Temp Conditions Not Started 08/27/26 09/02/26 6.2 6.2
0%
172.5
RPL08.SKN.SSB.01075 RPL08.SKIN.SSB - QC Blocking Glazing, Doors and Ext Devices Not Started 08/27/26 08/28/26 2.5 2.5
0%
398.8
RPL08.MCUP.LP1.2140 RPL08.MCUP.Loop 1 - Set Facility Water Pipe Rack (mCUP2) OFE Not Started 08/28/26 09/09/26 10.0 10.0
0%
206.2
RPL08.MCUP.LP2.1180 RPL08.MCUP.Loop 2 - Cure for Pads Foundations Not Started 08/28/26 09/03/26 8.8 8.8
0%
515.0
RPL08.STR.DHCD.01015 RPL08.Structure.DHCD - Install Decking & Detailing turnover #6 - Grid lines 6-18/6-21 Steel and Decking Not Started 08/28/26 09/01/26 3.8 3.8
0%
126.2
RPL08.EY.ENDC.01360 RPL08.EY.DHD.T2 - Install Shallow Tent UG Tent 2 Not Started 08/31/26 09/02/26 3.8 3.8
0%
161.2
RPL08.EY.ENDC.1310 RPL08.EY.DHD.T1 - Install Final Grading Tent 1 Not Started 08/31/26 09/01/26 2.5 2.5
0%
151.2
RPL08.SKN.SSB.01040 RPL08.SKIN.SSB - Install Louvers Glazing, Doors and Ext Devices Not Started 08/31/26 09/04/26 6.2 6.2
0%
392.5
RPL08.STR.SSB.01120 RPL08.Structure.SSB - Install AB final grade and Vapor Barrier Prep Not Started 09/01/26 09/08/26 6.2 6.2
0%
126.2
RPL08.EY.ENDC.1330 RPL08.EY.DHD.T1 - Install F/R/P Tent1 Slab Tent 1 Not Started 09/02/26 09/09/26 6.2 6.2
0%
151.2
RPL08.MCUP.LP1.1360 RPL08.MCUP.Loop 1 - Set Electrical Skids #1 OFE Not Started 09/02/26 09/03/26 2.5 2.5
0%
216.2
RPL08.MCUP.LP1.1380 RPL08.MCUP.Loop 1 - Set mCUPs XXMY.MCUP.02 (1 per 5 days) OFE Not Started 09/02/26 09/09/26 6.2 6.2
0%
201.2
RPL08.SKN.N.01010 RPL08.SKIN.North - Install IMP Insulated Metal Panels System - WBS Summary DBC Move 2 - Grid (6-07 / 6-21) Not Started 09/02/26 09/25/26 21.2 21.2
0%
513.8
RPL08.SKN.S.01030 RPL08.SKIN.South - Install IMP - Flashing,Panels & Caulking - Grid lines 6-07/6-14 (with temp closures for openings) DBC Move 2 - Grid (6-07 / 6-21) Not Started 09/02/26 09/04/26 3.8 3.8
0%
126.2
RPL08.STR.DHCD.01025 RPL08.Structure.DHCD - Install Decking & Detailing turnover #7 - Grid lines 6-21/6-25 Steel and Decking Not Started 09/02/26 09/04/26 3.8 3.8
0%
141.2
RPL08.EY.ENDC.1610 RPL08.EY.DHD.T2 - Install Final Grading Tent 2 Not Started 09/03/26 09/04/26 2.5 2.5
0%
161.2
RPL08.EY.SSB.01040 RPL08.EY.SSB - Install Electrical UG Underground Not Started 09/03/26 09/10/26 6.2 6.2
0%
182.5
RPL08.EY.SSB.01050 RPL08.EY.SSB - Install Cure (High Early Mix) Foundations Not Started 09/03/26 09/09/26 8.8 8.8
0%
315.0
RPL08.EY.SSB.01060 RPL08.EY.SSB - Install UG Utilities - WBS Summary Underground Not Started 09/03/26 10/01/26 25.0 25.0
0%
195.0
RPL08.EY.SSB.01180 RPL08.EY.SSB - Tie-ins - WBS Summary Tie-ins Not Started 09/03/26 01/21/27 117.5 117.5
0%
133.8
RPL08.EY.SSB.01400 RPL08.EY.SSB - Install Duct/ insulation into the building Main (include penetration detail) Tie-ins Not Started 09/03/26 09/24/26 18.8 18.8
0%
188.8
RPL08.MCUP.LP1.1400 RPL08.MCUP.Loop 1 - Tie-ins - WBS Summary Tie-ins Not Started 09/04/26 10/28/26 47.5 47.5
0%
472.5
RPL08.MCUP.LP1.1440 RPL08.MCUP.Loop 1 - Tie-in Mechanical - WBS Summary Tie-Ins Mechanical Not Started 09/04/26 10/21/26 41.2 41.2
0%
195.0
RPL08.MCUP.LP1.1460 RPL08.MCUP.Loop 1 - Tie-in Mechanical #1 Tie-Ins Mechanical Not Started 09/04/26 09/25/26 18.8 18.8
0%
217.5
RPL08.CFCI.5090 RPL08 - Fabricate / Deliver - Fire Alarm (CFCI) Div. 26 - Fire Alarm Not Started 09/08/26 11/02/26 50.0 50.0
0%
360.0
RPL08.EY.DHA.01010 RPL08.EY.DHA - Install F/R/P Equipment Pads - 1-12 (Grid 6-01/6-16) (12'' Larger For Tolerance) Foundations Not Started 09/08/26 10/05/26 25.0 25.0
0%
183.8
RPL08.EY.DHA.01020 RPL08.EY.DHA - Install Foundations - WBS Summary Foundations Not Started 09/08/26 10/12/26 31.2 31.2
0%
183.8
RPL08.EY.DHA.01030 RPL08.EY.DHA - Install Foundations, UG Utilities, OFE- WBS Summary EY.DHA Not Started 09/08/26 05/11/27 210.0 210.0
0%
375.0
RPL08.EY.ENDC.1630 RPL08.EY.DHD.T2 - Install F/R/P Tent1 Slab Tent 2 Not Started 09/08/26 09/14/26 6.2 6.2
0%
161.2
RPL08.EY.SSB.01420 RPL08.EY.SSB - Install Grounding UG Underground Not Started 09/08/26 09/14/26 6.2 6.2
0%
205.0
RPL08.SKN.N.01030 RPL08.SKIN.North - Install IMP - Flashing,Panels & Caulking - Grid lines 6-07/6-14 (with temp closures for openings) DBC Move 2 - Grid (6-07 / 6-21) Not Started 09/08/26 09/09/26 2.5 2.5
0%
126.2
RPL08.SKN.S.01010 RPL08.SKIN.South - Install IMP Insulated Metal Panels System - WBS Summary DBC Move 3 - Grid (6-21 / 6-28) Not Started 09/08/26 09/30/26 21.2 21.2
0%
510.0
RPL08.SKN.S.01040 RPL08.SKIN.South - Install IMP EJ - Grid lines 6-09/6-10 DBC Move 2 - Grid (6-07 / 6-21) Not Started 09/08/26 09/14/26 6.2 6.2
0%
145.0
RPL08.SKN.S.01140 RPL08.SKIN.South - Install Stair Tower (DH A) DBC Move 3 - Grid (6-21 / 6-28) Not Started 09/08/26 09/09/26 2.5 2.5
0%
247.5
RPL08.SKN.SSB.01060 RPL08.SKIN.SSB - Install Awning over Doors Glazing, Doors and Ext Devices Not Started 09/08/26 09/14/26 6.2 6.2
0%
400.0
RPL08.STR.DHAB.01060 RPL08.Structure.DHAB - Adjust MEP Verts and Grounding wire Prep Not Started 09/08/26 09/14/26 6.2 6.2
0%
141.2
RPL08.STR.DHAB.01070 RPL08.Structure.DHAB - Install Remaining UG and Subgrade Prep - WBS Summary Prep Not Started 09/08/26 09/24/26 16.2 16.2
0%
141.2
RPL08.STR.DHCD.01035 RPL08.Structure.DHCD - Install Decking & Detailing turnover #8 - Grid lines 6-25/6-28 Steel and Decking Not Started 09/08/26 09/10/26 3.8 3.8
0%
143.8
RPL08.LOG.1020 MCUP 500 Ton Crane Movement 1 300 Ton Crane Not Started 09/09/26 09/09/26 0.0 0.0
0%
201.2
RPL08.STR.SSB.01130 RPL08.Structure.SSB - Asphalt Emulsion and Wrap Steel Columns Prep Not Started 09/09/26 09/14/26 5.0 5.0
0%
126.2
GCD.RPL08.1320 Steel Complete - RPL08 Construction Milestones Not Started 09/10/26 09/10/26 0.0 0.0
0%
171.2
GCD.RPL08.1456 Start RPL08 EY RMU Equipment Pad Placement - RPL08 Construction Milestones Not Started 09/10/26 09/10/26 0.0 0.0
0%
447.5
RPL08.EY.DHB.01010 RPL08.EY.DHB - Install F/R/P Equipment Pads - 1-12(Grid 6-01/6-16) (12'' Larger For Tolerance) Foundations Not Started 09/10/26 10/07/26 25.0 25.0
0%
162.5
RPL08.EY.DHB.01020 RPL08.EY.DHB - Install Foundations - WBS Summary Foundations Not Started 09/10/26 10/14/26 31.2 31.2
0%
162.5
RPL08.EY.DHB.01030 RPL08.EY.DHB - Install Foundations, UG Utilities, OFE - WBS Summary EY.DHB Not Started 09/10/26 04/16/27 186.2 186.2
0%
396.2
RPL08.EY.ENDC.1350 RPL08.EY.DHD.T1 - Install Saw Cut and Cure Tent 1 Not Started 09/10/26 09/16/26 8.8 8.8
0%
225.0
RPL08.MCUP.LP1.1240 RPL08.MCUP.Loop 1 - Set GS.IDF Hut (1x GS.IDF) XX01 OFE Not Started 09/10/26 09/16/26 6.2 6.2
0%
201.2
RPL08.MCUP.LP1.1500 RPL08.MCUP.Loop 1 - Set mCUPs XXMY.MCUP.03 (1 per 5 days) OFE Not Started 09/10/26 09/16/26 6.2 6.2
0%
201.2
RPL08.MCUP.LP1.1520 RPL08.MCUP.Loop 1 - Set Electrical Skids #2 OFE Not Started 09/10/26 09/11/26 2.5 2.5
0%
212.5
RPL08.MCUP.LP1.2160 RPL08.MCUP.Loop 1 - Set Facility Water Pipe Rack (mCUP3) OFE Not Started 09/10/26 09/21/26 10.0 10.0
0%
206.2
RPL08.SKN.DHAB.01000 RPL08.SKIN.DHAB - Install Temp Doors Glazing, Doors and Ext Devices Not Started 09/10/26 09/11/26 2.5 2.5
0%
152.5
RPL08.SKN.DHAB.01010 RPL08.SKIN.DHAB - IMP, Roof, Windows, Doors, Ext Devices - WBS Summary DH A & DH B Not Started 09/10/26 11/16/26 58.8 58.8
0%
357.5
RPL08.SKN.DHAB.01020 RPL08.SKIN.DHAB - Install Windows, Doors, Louvers and Ext Devices - WBS Summary Glazing, Doors and Ext Devices Not Started 09/10/26 10/21/26 37.5 37.5
0%
378.8
RPL08.SKN.N.01040 RPL08.SKIN.North - Install IMP EJ - Grid lines 6-09/6-10 DBC Move 2 - Grid (6-07 / 6-21) Not Started 09/10/26 09/16/26 6.2 6.2
0%
140.0
RPL08.SKN.N.01080 RPL08.SKIN.North - Install IMP - Flashing,Panels & Caulking - Grid lines 6-14/6-21 (with temp closures for openings) DBC Move 2 - Grid (6-07 / 6-21) Not Started 09/10/26 09/11/26 2.5 2.5
0%
140.0
RPL08.SKN.N.01120 RPL08.SKIN.North - Install Stair Tower (DH B) DBC Move 2 - Grid (6-07 / 6-21) Not Started 09/10/26 09/11/26 2.5 2.5
0%
245.0
RPL08.VDC.1860 T2-4 (SSB) - Procurement Materials TIER 2 - 4 - SSB Not Started 09/10/26 09/30/26 18.8 18.8
0%
111.2
RPL08.EY.DHA.01060 RPL08.EY.DHA - Install Electrical UG Underground Not Started 09/11/26 09/24/26 12.5 12.5
0%
201.2
RPL08.EY.DHA.01070 RPL08.EY.DHA - Install UG Utilities - WBS Summary Underground Not Started 09/11/26 10/22/26 37.5 37.5
0%
201.2
RPL08.EY.DHB.01060 RPL08.EY.DHB - Install Electrical UG Underground Not Started 09/11/26 09/24/26 12.5 12.5
0%
182.5
RPL08.EY.DHB.01070 RPL08.EY.DHB - Install UG Utilities - WBS Summary Underground Not Started 09/11/26 10/22/26 37.5 37.5
0%
182.5
RPL08.EY.SSB.01070 RPL08.EY.SSB - Install Mechanical UG Underground Not Started 09/11/26 09/17/26 6.2 6.2
0%
188.8
RPL08.LOG.1140 Dry Cooler 230 Ton Crane Movement 01 100 Ton Crane Not Started 09/11/26 09/11/26 0.0 0.0
0%
195.0
RPL08.STR.DHCD.01060 RPL08.Structure.DHCD - Adjust MEP Verts and Grounding wire Prep Not Started 09/11/26 09/17/26 6.2 6.2
0%
155.0
RPL08.STR.DHCD.01070 RPL08.Structure.DHCD - Install Remaining UG and Subgrade Prep - WBS Summary Prep Not Started 09/11/26 09/29/26 16.2 16.2
0%
155.0
RPL08.MCUP.LP1.1280 RPL08.MCUP.Loop 1 - Set MTRs (4 per day) OFE Not Started 09/14/26 09/18/26 6.2 6.2
0%
195.0
RPL08.MCUP.LP1.1320 RPL08.MCUP.Loop 1 - Set mCup #3 & #4 - Dry Coolers (12) (4 per week) OFE Not Started 09/14/26 10/02/26 18.8 18.8
0%
195.0
RPL08.MCUP.LP1.1660 RPL08.MCUP.Loop 1 - Tie-in SD, DW Tie-ins Not Started 09/14/26 10/02/26 18.8 18.8
0%
495.0
RPL08.MCUP.LP1.1760 RPL08.MCUP.Loop 1 - Tie-in Mechanical #2 Tie-Ins Mechanical Not Started 09/14/26 10/02/26 18.8 18.8
0%
211.2
RPL08.SKN.DHAB.01160 RPL08.SKIN.DHAB - Install Blocking of Canopy & Backing of Exterior Wall Glazing, Doors and Ext Devices Not Started 09/14/26 09/18/26 6.2 6.2
0%
152.5