Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL08 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:14 PM · 5122 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
0
Completed
0
In Progress
0
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL08.MCUP.LP2.1680 RPL08.MCUP.Loop 2 - Tie-in EPMS - WBS Summary Tie-Ins EPMS Not Started 10/05/26 10/21/26 16.2 16.2
0%
340.0
RPL08.MCUP.LP2.1700 RPL08.MCUP.Loop 2 - Tie-in EPMS #5 Tie-Ins EPMS Not Started 10/05/26 10/14/26 10.0 10.0
0%
346.2
RPL08.SKN.DHAB.01050 RPL08.SKIN.DHAB - Install Lighting Glazing, Doors and Ext Devices Not Started 10/05/26 10/08/26 5.0 5.0
0%
363.8
GCD.RPL08.1500 Start Slab-On-Grade Concrete - RPL08 Construction Milestones Not Started 10/06/26 10/06/26 0.0 0.0
0%
425.0
RPL08.EY.DHA.01130 RPL08.EY.DHA - Cure (High Early Mix) Foundations Not Started 10/06/26 10/12/26 8.8 8.8
0%
271.2
RPL08.EY.DHC.01010 RPL08.EY.DHC - Install F/R/P Equipment Pads - 1-10 (Grid 6-17/6-28) (12'' Larger For Tolerance) Foundations Not Started 10/06/26 10/26/26 18.8 18.8
0%
311.2
RPL08.EY.DHC.01020 RPL08.EY.DHC - Install Foundations - WBS Summary Foundations Not Started 10/06/26 07/27/27 251.2 251.2
0%
223.8
RPL08.EY.DHC.01030 RPL08.EY.DHC - Install Foundations, UG Utilities, OFE - WBS Summary EY.DHC Not Started 10/06/26 08/24/27 276.2 276.2
0%
283.8
RPL08.EY.ENDC.01150 RPL08.EY.End - Tie-ins - WBS Summary Tie-ins Not Started 10/06/26 09/17/27 297.5 297.5
0%
151.2
RPL08.EY.ENDC.01320 RPL08.EY.End - Install Duct/ insulation into the building Main (include penetration detail) Tie-ins Not Started 10/06/26 10/19/26 12.5 12.5
0%
398.8
RPL08.INT.1000 RPL08.Interior.BLDG - Install Priority OH, Walls, OFE and Fitout - WBS Summary Interior Build-out Not Started 10/06/26 10/08/27 316.2 316.2
0%
205.0
RPL08.INT.SSB.01005 RPL08.Interior - Priority - Install Hangers Support (SSB to Center Corr) (All Trades) Early Priority OH MEPF Not Started 10/06/26 10/19/26 12.5 12.5
0%
105.0
RPL08.SKN.DHAB.01100 RPL08.SKIN.DHAB - Install Roof System - DenseDeck & Flame Down Roofing Not Started 10/06/26 10/14/26 8.8 8.8
0%
106.2
RPL08.SKN.SSB.01120 RPL08.SKIN.SSB - Install Scupper and Downspouts Glazing, Doors and Ext Devices Not Started 10/06/26 10/12/26 6.2 6.2
0%
381.2
RPL08.SKN.SSB.01130 RPL08.SKIN.SSB - Install Roof System - Final Roof Roofing Not Started 10/06/26 10/26/26 18.8 18.8
0%
140.0
RPL08.STR.SSB.01140 RPL08.Structure.SSB - SOG F/R/P #1 - Grid lines 6-01/6-04 F/R/P Not Started 10/06/26 10/12/26 6.2 6.2
0%
107.5
RPL08.STR.SSB.01150 RPL08.Structure.SSB - SOG F/R/P - WBS Summary F/R/P Not Started 10/06/26 10/28/26 21.2 21.2
0%
195.0
RPL.08.D.84160.XG Ready for MV Cable Pull mCUP - Loop#2 (Qty 2)* Give Milestones (XREFs) Not Started 10/07/26 10/07/26 0.0 0.0
0%
557.5
RPL08.CON.WP2.08520 RPL08.Conn - Ext. GSIDF8X03 - Install Copper, WAPs, Security Camera & Access Control Cabling Not Started 10/08/26 10/23/26 15.0 15.0
0%
373.8
RPL08.EY.DHB.01130 RPL08.EY.DHB - Cure (High Early Mix) Foundations Not Started 10/08/26 10/14/26 8.8 8.8
0%
242.5
RPL08.EY.DHD.01010 RPL08.EY.DHD - Install F/R/P Equipment Pads - 1-10 (Grid 6-17/6-28) (12'' Larger For Tolerance) Foundations Not Started 10/08/26 10/28/26 18.8 18.8
0%
288.8
RPL08.EY.DHD.01020 RPL08.EY.DHD - Install Foundations - WBS Summary Foundations Not Started 10/08/26 07/23/27 246.2 246.2
0%
216.2
RPL08.EY.SSB.01190 RPL08.EY.SSB - Set LD Grade and Prep Loading Dock Not Started 10/08/26 10/13/26 5.0 5.0
0%
298.8
RPL08.INT.SSB.01010 RPL08.Interior.SSB - Priority - Install Duct (Highside OH space) Early Priority OH MEPF Not Started 10/08/26 10/21/26 12.5 12.5
0%
105.0
RPL08.LOG.1100 MCUP 500 Ton Crane Demobilization 300 Ton Crane Not Started 10/08/26 10/13/26 5.0 5.0
0%
552.5
RPL08.MCUP.LP1.2060 RPL08.MCUP.Loop 1 - Tie-in - Electrical L2 Checklist Completion Tie-ins Not Started 10/08/26 10/21/26 12.5 12.5
0%
201.2
RPL08.MCUP.LP2.1500 RPL08.MCUP.Loop 2 - Set Electrical Skids #6 OFE Not Started 10/08/26 10/09/26 2.5 2.5
0%
343.8
RPL08.MCUP.LP2.2000 RPL08.MCUP.Loop 2 - Tie-in Electrical #6 Tie-Ins Electrical Not Started 10/08/26 10/21/26 12.5 12.5
0%
340.0
RPL.08.D.83760.XG RMUs Set - mCUP Loop 2 Give Milestones (XREFs) Not Started 10/09/26 10/09/26 0.0 0.0
0%
555.0
RPL08.EY.DHA.01120 RPL08.EY.DHA - Install BMS UG Underground Not Started 10/09/26 10/22/26 12.5 12.5
0%
201.2
RPL08.EY.DHA.01230 RPL08.EY.DHA - OFE - MV - WBS Summary OFE Not Started 10/09/26 03/29/27 142.5 142.5
0%
221.2
RPL08.EY.DHA.01540 RPL08.EY.DHA - Install AHUs (Qty 1) OFE Not Started 10/09/26 10/20/26 10.0 10.0
0%
352.5
RPL08.EY.DHB.01120 RPL08.EY.DHB - Install BMS/EPMS UG Underground Not Started 10/09/26 10/22/26 12.5 12.5
0%
182.5
RPL08.EY.DHC.01050 RPL08.EY.DHC - Install Electrical UG Underground Not Started 10/09/26 10/22/26 12.5 12.5
0%
322.5
RPL08.EY.DHC.01060 RPL08.EY.DHC - Install UG Utilities - WBS Summary Underground Not Started 10/09/26 07/13/27 235.0 235.0
0%
225.0
RPL08.EY.DHD.01100 RPL08.EY.DHD - Install Mechanical UG Underground Not Started 10/09/26 10/22/26 12.5 12.5
0%
331.2
RPL08.EY.DHD.01110 RPL08.EY.DHD - Install SD, DW, FW UG Underground Not Started 10/09/26 10/22/26 12.5 12.5
0%
328.8
RPL08.SKN.DHAB.01060 RPL08.SKIN.DHAB - Install Security Glazing, Doors and Ext Devices Not Started 10/09/26 10/12/26 2.5 2.5
0%
363.8
RPL08.MCUP.LP1.1920 RPL08.MCUP.Loop 1 - Install Early Mcup Paving Hardscape and Landscape Not Started 10/12/26 10/23/26 12.5 12.5
0%
505.0
RPL08.MCUP.LP1.1940 RPL08.MCUP.Loop 1 - Tie-in BMS #4 Tie-Ins BMS Not Started 10/12/26 10/21/26 10.0 10.0
0%
195.0
RPL08.MCUP.LP2.1940 RPL08.MCUP.Loop 2 - Tie-in EPMS #6 Tie-Ins EPMS Not Started 10/12/26 10/21/26 10.0 10.0
0%
340.0
RPL.08.D.84210.XR FW Water Available for mCUP Flush/Fill - Utility connections Receive Milestones (XREFs) Not Started 10/13/26 10/13/26 0.0 0.0
0%
233.8
RPL.08.D.84410.XR Discharge Available for Fill/Flush Cx - Utility connections Receive Milestones (XREFs) Not Started 10/13/26 10/13/26 0.0 0.0
0%
233.8
RPL08.CFCI.5110 RPL08 - Submittals Review & Approval - Carpet (CFCI) Div. 09 - Carpet Not Started 10/13/26 11/09/26 25.0 25.0
0%
298.8
RPL08.CFCI.5140 RPL08 - Fabricate / Deliver -Epoxy Flooring (Spec 09 67 23) XX (CFCI) Div. 09 - Epoxy Flooring Not Started 10/13/26 11/02/26 18.8 18.8
0%
355.0
RPL08.CFCI.5260 RPL08 - Fabricate / Deliver - Specialities (CFCI) Div. 10 - Specialities Not Started 10/13/26 11/24/26 37.5 37.5
0%
285.0
RPL08.EY.DHA.01530 RPL08.EY.DHA - Set GS.IDF Hut (1x GS.IDF) XX04 OFE Not Started 10/13/26 10/19/26 6.2 6.2
0%
355.0
RPL08.EY.DHC.01530 RPL08.EY.DHC - Install Grounding UG Underground Not Started 10/13/26 10/26/26 12.5 12.5
0%
332.5
RPL08.SKN.DHAB.01140 RPL08.SKIN.DHAB - Install Perm Doors Glazing, Doors and Ext Devices Not Started 10/13/26 10/14/26 2.5 2.5
0%
363.8
RPL08.STR.DHAB.01110 RPL08.Structure.DHAB - SOG F/R/P - Grid Lines 6-11/6-23 - WBS Summary F/R/P Not Started 10/13/26 11/25/26 38.8 38.8
0%
120.0
RPL08.STR.DHAB.01160 RPL08.Structure.DHAB - SOG F/R/P #2 - Grid lines 6-04/6-07 F/R/P Not Started 10/13/26 10/19/26 6.2 6.2
0%
107.5
RPL08.STR.SSB.01190 RPL08.Structure.SSB - Zone SOG Cure F/R/P Not Started 10/13/26 10/19/26 8.8 8.8
0%
181.2
RPL08.EY.SSB.01200 RPL08.EY.SSB - Install LD F/R/P Loading Dock Ramp Loading Dock Not Started 10/14/26 10/23/26 10.0 10.0
0%
298.8
RPL08.MCUP.LP2.2120 RPL08.MCUP.Loop 2 - Set Facility Water Pipe Rack (mCUP6) OFE Not Started 10/14/26 10/27/26 12.5 12.5
0%
335.0
RPL08.INT.DHB.02160 RPL08.Interior.DHBADC - Priority - Install Fixed Draft/Smoke Curtain (#5) Early Priority OH MEPF Not Started 10/15/26 10/27/26 11.2 11.2
0%
145.0
RPL08.MCUP.LP1.2080 RPL08.MCUP.Loop 1 - Tie-in - Mechanical L2 Checklist Completion Tie-ins Not Started 10/15/26 10/28/26 12.5 12.5
0%
195.0
RPL08.SKN.DHAB.01110 RPL08.SKIN.DHAB - Install Scupper and Downspouts Glazing, Doors and Ext Devices Not Started 10/15/26 10/21/26 6.2 6.2
0%
378.8
RPL08.SKN.DHCD.01090 RPL08.SKIN.DHCD - Install Roof System - DenseDeck & Flame Down Roofing Not Started 10/15/26 10/23/26 8.8 8.8
0%
132.5
RPL08.MCUP.LP2.1580 RPL08.MCUP.Loop 2 - Tie-in Mechanical - WBS Summary Tie-Ins Mechanical Not Started 10/16/26 11/12/26 23.8 23.8
0%
327.5
RPL08.MCUP.LP2.1600 RPL08.MCUP.Loop 1 - Tie-in Mechanical #5 Tie-Ins Mechanical Not Started 10/16/26 11/03/26 16.2 16.2
0%
335.0
RPL.GF.D.N8170.XR Natural Gas Available for Fill/Flush Cx - Utility connections Receive Milestones (XREFs) Not Started 10/20/26 10/20/26 0.0 0.0
0%
233.8
RPL08.CON.WP2.07800 RPL08.Conn - Ext. GSIDF8X04 (South Elec Yard) - WBS Summary Ext. IDF Hut - GSIDF8X04 Not Started 10/20/26 04/29/27 162.5 162.5
0%
385.0
RPL08.CON.WP2.08460 RPL08.Conn - Ext. GSIDF8X04 - Install Infrastructure (Racks, Waterfalls etc.) ??pred?? Infrastructure Not Started 10/20/26 10/26/26 6.2 6.2
0%
355.0
RPL08.EY.ENDC.1390 RPL08.EY.DHD.T1 - Install Panels Tent 1 Not Started 10/20/26 10/26/26 6.2 6.2
0%
151.2
RPL08.EY.ENDC.1410 RPL08.EY.DHD.T1 - Install Heating and Cooling Equipment Tent 1 Not Started 10/20/26 10/26/26 6.2 6.2
0%
147.5
RPL08.EY.ENDC.1430 RPL08.EY.DHD.T1 - Install Overhead Doors Tent 1 Not Started 10/20/26 10/26/26 6.2 6.2
0%
155.0
RPL08.EY.ENDC.1450 RPL08.EY.DHD.T1 - Install Tent Fit-out Tent 1 Not Started 10/20/26 11/02/26 12.5 12.5
0%
148.8
RPL08.EY.ENDC.1690 RPL08.EY.DHD.T2 - Install Panels Tent 2 Not Started 10/20/26 10/26/26 6.2 6.2
0%
163.8
RPL08.EY.ENDC.1710 RPL08.EY.DHD.T2 - Install Heating and Cooling Equipment Tent 2 Not Started 10/20/26 10/26/26 6.2 6.2
0%
160.0
RPL08.EY.ENDC.1730 RPL08.EY.DHD.T2 - Install Overhead Doors Tent 2 Not Started 10/20/26 10/26/26 6.2 6.2
0%
167.5
RPL08.EY.ENDC.1750 RPL08.EY.DHD.T2 - Install Tent Fit-out Tent 2 Not Started 10/20/26 11/02/26 12.5 12.5
0%
161.2
RPL08.INT.SSB.01006 RPL08.Interior - Priority - Install Hangers Support (Center Corr to End Corr) (All Trades) Early Priority OH MEPF Not Started 10/20/26 11/02/26 12.5 12.5
0%
240.0
RPL08.INT.SSBC.01000 RPL08.Interior.SSBC - Priority - WBS Summary Priority Walls & Overhead Not Started 10/20/26 12/18/26 51.2 51.2
0%
152.5
RPL08.INT.SSBC.01020 RPL08.Interior.SSB-Corridor - Install Priority OH, Walls, OFE and Fitout - WBS Summary SSB Corridor Not Started 10/20/26 06/09/27 197.5 197.5
0%
188.8
RPL08.INT.SSBC.01080 RPL08.Interior.SSBC - Priority GL8.04 - (P0) Apply Intumescent Paint to Deck Priority Wall Grid Line 8-04 Not Started 10/20/26 11/09/26 18.8 18.8
0%
116.2
RPL08.INT.SSBC.02400 RPL08.Interior.SSBC - Priority - Install Layout, Unistruts & Hangers (All Trades) Both side of Corridor Wall Priority Walls & Overhead Not Started 10/20/26 10/23/26 5.0 5.0
0%
117.5
RPL08.STR.DHAB.01170 RPL08.Structure.DHAB - SOG F/R/P #3 - Grid lines 6-07/6-11 F/R/P Not Started 10/20/26 10/26/26 6.2 6.2
0%
107.5
RPL08.STR.SSB.01250 RPL08.Structure.SSB - Moisture requirements for floor Sealer F/R/P Not Started 10/20/26 10/26/26 8.8 8.8
0%
210.0
RPL08.INT.SSBC.01011 RPL08.Interior.SSB-Corridor - Priority - Install Duct (Highside OH space) Early Priority OH MEPF Not Started 10/22/26 10/28/26 6.2 6.2
0%
105.0
RPL08.MCUP.LP2.2040 RPL08.MCUP.Loop 2 - Tie-in - MV Loop 2 L2 Checklist Completion Tie-ins Not Started 10/22/26 10/28/26 6.2 6.2
0%
340.0
RPL08.SKN.E.01040 RPL08.SKIN.East - Secure All Exterior Mounted Boxes and Devices on Skin IMP System Not Started 10/22/26 11/04/26 12.5 12.5
0%
423.8
RPL08.CON.WP2.09180 RPL08.Conn - CorpNet & FacNet Available (mCUP) - All IDFs WP#02 GS Not Started 10/23/26 10/23/26 0.0 0.0
0%
542.5
RPL08.Conn.MS.01080 RPL08.Conn Wifi Ready - mCUP Yard (Pred from RPL10 CorpNet needed?) Connectivity Milestones Not Started 10/23/26 10/23/26 0.0 0.0
0%
373.8
RPL08.EY.DHC.01090 RPL08.EY.DHC - Install Mechanical UG Underground Not Started 10/23/26 11/05/26 12.5 12.5
0%
322.5
RPL08.EY.DHC.01100 RPL08.EY.DHC - Install SD, DW, FW UG Underground Not Started 10/23/26 11/05/26 12.5 12.5
0%
332.5
RPL08.EY.ENDC.01000 RPL08.EY.End - Install Electrical UG Underground Not Started 10/23/26 10/29/26 6.2 6.2
0%
373.8
RPL08.EY.ENDC.01010 RPL08.EY.End - Install UG Utilities - WBS Summary Underground Not Started 10/23/26 11/20/26 25.0 25.0
0%
382.5
RPL08.INT.SSBC.03240 RPL08.Interior.SSBC - Priority - Install Priority Soffit for Wall Tie-Ins/ Rock & HoW & Draft Blanket Priority Walls & Overhead Not Started 10/23/26 10/29/26 6.2 6.2
0%
116.2
RPL08.INT.SSBC.03520 RPL08.Interior.SSBC - Priority - Install IMP Exterior Inwall Rough-In Priority Walls & Overhead Not Started 10/23/26 10/27/26 3.8 3.8
0%
161.2
RPL08.MCUP.LP2.1660 RPL08.MCUP.Loop 2 - Tie-in BMS - WBS Summary Tie-Ins BMS Not Started 10/23/26 11/12/26 17.5 17.5
0%
327.5
RPL08.MCUP.LP2.1720 RPL08.MCUP.Loop 2 - Tie-in BMS #5 Tie-Ins BMS Not Started 10/23/26 11/03/26 10.0 10.0
0%
335.0
RPL08.EY.SSB.01210 RPL08.EY.SSB - Install LD Electrical In walls Loading Dock Not Started 10/26/26 10/29/26 5.0 5.0
0%
298.8
RPL08.EY.SSB.01220 RPL08.EY.SSB - Install LD French Drain (Not Designed) Loading Dock Not Started 10/26/26 10/29/26 5.0 5.0
0%
308.8
RPL08.LOG.1300 Dry Cooler 230 Ton Crane Demobilization 100 Ton Crane Not Started 10/26/26 10/28/26 3.8 3.8
0%
472.5
RPL08.MCUP.LP1.2000 RPL08.MCUP.Loop 1 - Install Lighting Hardscape and Landscape Not Started 10/26/26 11/06/26 12.5 12.5
0%
505.0
RPL08.MCUP.LP2.1240 RPL08.MCUP.Loop 2 - Set MTRs (4 per day) OFE Not Started 10/26/26 10/27/26 2.5 2.5
0%
335.0
RPL08.MCUP.LP2.2020 RPL08.MCUP.Loop 1 - Tie-in Mechanical #6 Tie-Ins Mechanical Not Started 10/26/26 11/12/26 16.2 16.2
0%
327.5
RPL08.CON.WP2.08540 RPL08.Conn - Ext. GSIDF8X04 - Install Copper, WAPs, Security Camera & Access Control (EY-DH A) Cabling Not Started 10/27/26 11/12/26 15.0 15.0
0%
355.0
RPL08.EY.DHC.01130 RPL08.EY.DHC - Cure (High Early Mix) Foundations Not Started 10/27/26 11/02/26 8.8 8.8
0%
455.0
RPL08.EY.ENDC.01340 RPL08.EY.End - Install Grounding UG Underground Not Started 10/27/26 11/02/26 6.2 6.2
0%
392.5