Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL08 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:14 PM
· 5122 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
0
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL08.MCUP.LP2.1680 |
RPL08.MCUP.Loop 2 - Tie-in EPMS - WBS Summary | Tie-Ins EPMS | Not Started | 10/05/26 | 10/21/26 | 16.2 | 16.2 |
|
340.0 |
RPL08.MCUP.LP2.1700 |
RPL08.MCUP.Loop 2 - Tie-in EPMS #5 | Tie-Ins EPMS | Not Started | 10/05/26 | 10/14/26 | 10.0 | 10.0 |
|
346.2 |
RPL08.SKN.DHAB.01050 |
RPL08.SKIN.DHAB - Install Lighting | Glazing, Doors and Ext Devices | Not Started | 10/05/26 | 10/08/26 | 5.0 | 5.0 |
|
363.8 |
GCD.RPL08.1500 |
Start Slab-On-Grade Concrete - RPL08 | Construction Milestones | Not Started | 10/06/26 | 10/06/26 | 0.0 | 0.0 |
|
425.0 |
RPL08.EY.DHA.01130 |
RPL08.EY.DHA - Cure (High Early Mix) | Foundations | Not Started | 10/06/26 | 10/12/26 | 8.8 | 8.8 |
|
271.2 |
RPL08.EY.DHC.01010 |
RPL08.EY.DHC - Install F/R/P Equipment Pads - 1-10 (Grid 6-17/6-28) (12'' Larger For Tolerance) | Foundations | Not Started | 10/06/26 | 10/26/26 | 18.8 | 18.8 |
|
311.2 |
RPL08.EY.DHC.01020 |
RPL08.EY.DHC - Install Foundations - WBS Summary | Foundations | Not Started | 10/06/26 | 07/27/27 | 251.2 | 251.2 |
|
223.8 |
RPL08.EY.DHC.01030 |
RPL08.EY.DHC - Install Foundations, UG Utilities, OFE - WBS Summary | EY.DHC | Not Started | 10/06/26 | 08/24/27 | 276.2 | 276.2 |
|
283.8 |
RPL08.EY.ENDC.01150 |
RPL08.EY.End - Tie-ins - WBS Summary | Tie-ins | Not Started | 10/06/26 | 09/17/27 | 297.5 | 297.5 |
|
151.2 |
RPL08.EY.ENDC.01320 |
RPL08.EY.End - Install Duct/ insulation into the building Main (include penetration detail) | Tie-ins | Not Started | 10/06/26 | 10/19/26 | 12.5 | 12.5 |
|
398.8 |
RPL08.INT.1000 |
RPL08.Interior.BLDG - Install Priority OH, Walls, OFE and Fitout - WBS Summary | Interior Build-out | Not Started | 10/06/26 | 10/08/27 | 316.2 | 316.2 |
|
205.0 |
RPL08.INT.SSB.01005 |
RPL08.Interior - Priority - Install Hangers Support (SSB to Center Corr) (All Trades) | Early Priority OH MEPF | Not Started | 10/06/26 | 10/19/26 | 12.5 | 12.5 |
|
105.0 |
RPL08.SKN.DHAB.01100 |
RPL08.SKIN.DHAB - Install Roof System - DenseDeck & Flame Down | Roofing | Not Started | 10/06/26 | 10/14/26 | 8.8 | 8.8 |
|
106.2 |
RPL08.SKN.SSB.01120 |
RPL08.SKIN.SSB - Install Scupper and Downspouts | Glazing, Doors and Ext Devices | Not Started | 10/06/26 | 10/12/26 | 6.2 | 6.2 |
|
381.2 |
RPL08.SKN.SSB.01130 |
RPL08.SKIN.SSB - Install Roof System - Final Roof | Roofing | Not Started | 10/06/26 | 10/26/26 | 18.8 | 18.8 |
|
140.0 |
RPL08.STR.SSB.01140 |
RPL08.Structure.SSB - SOG F/R/P #1 - Grid lines 6-01/6-04 | F/R/P | Not Started | 10/06/26 | 10/12/26 | 6.2 | 6.2 |
|
107.5 |
RPL08.STR.SSB.01150 |
RPL08.Structure.SSB - SOG F/R/P - WBS Summary | F/R/P | Not Started | 10/06/26 | 10/28/26 | 21.2 | 21.2 |
|
195.0 |
RPL.08.D.84160.XG |
Ready for MV Cable Pull mCUP - Loop#2 (Qty 2)* | Give Milestones (XREFs) | Not Started | 10/07/26 | 10/07/26 | 0.0 | 0.0 |
|
557.5 |
RPL08.CON.WP2.08520 |
RPL08.Conn - Ext. GSIDF8X03 - Install Copper, WAPs, Security Camera & Access Control | Cabling | Not Started | 10/08/26 | 10/23/26 | 15.0 | 15.0 |
|
373.8 |
RPL08.EY.DHB.01130 |
RPL08.EY.DHB - Cure (High Early Mix) | Foundations | Not Started | 10/08/26 | 10/14/26 | 8.8 | 8.8 |
|
242.5 |
RPL08.EY.DHD.01010 |
RPL08.EY.DHD - Install F/R/P Equipment Pads - 1-10 (Grid 6-17/6-28) (12'' Larger For Tolerance) | Foundations | Not Started | 10/08/26 | 10/28/26 | 18.8 | 18.8 |
|
288.8 |
RPL08.EY.DHD.01020 |
RPL08.EY.DHD - Install Foundations - WBS Summary | Foundations | Not Started | 10/08/26 | 07/23/27 | 246.2 | 246.2 |
|
216.2 |
RPL08.EY.SSB.01190 |
RPL08.EY.SSB - Set LD Grade and Prep | Loading Dock | Not Started | 10/08/26 | 10/13/26 | 5.0 | 5.0 |
|
298.8 |
RPL08.INT.SSB.01010 |
RPL08.Interior.SSB - Priority - Install Duct (Highside OH space) | Early Priority OH MEPF | Not Started | 10/08/26 | 10/21/26 | 12.5 | 12.5 |
|
105.0 |
RPL08.LOG.1100 |
MCUP 500 Ton Crane Demobilization | 300 Ton Crane | Not Started | 10/08/26 | 10/13/26 | 5.0 | 5.0 |
|
552.5 |
RPL08.MCUP.LP1.2060 |
RPL08.MCUP.Loop 1 - Tie-in - Electrical L2 Checklist Completion | Tie-ins | Not Started | 10/08/26 | 10/21/26 | 12.5 | 12.5 |
|
201.2 |
RPL08.MCUP.LP2.1500 |
RPL08.MCUP.Loop 2 - Set Electrical Skids #6 | OFE | Not Started | 10/08/26 | 10/09/26 | 2.5 | 2.5 |
|
343.8 |
RPL08.MCUP.LP2.2000 |
RPL08.MCUP.Loop 2 - Tie-in Electrical #6 | Tie-Ins Electrical | Not Started | 10/08/26 | 10/21/26 | 12.5 | 12.5 |
|
340.0 |
RPL.08.D.83760.XG |
RMUs Set - mCUP Loop 2 | Give Milestones (XREFs) | Not Started | 10/09/26 | 10/09/26 | 0.0 | 0.0 |
|
555.0 |
RPL08.EY.DHA.01120 |
RPL08.EY.DHA - Install BMS UG | Underground | Not Started | 10/09/26 | 10/22/26 | 12.5 | 12.5 |
|
201.2 |
RPL08.EY.DHA.01230 |
RPL08.EY.DHA - OFE - MV - WBS Summary | OFE | Not Started | 10/09/26 | 03/29/27 | 142.5 | 142.5 |
|
221.2 |
RPL08.EY.DHA.01540 |
RPL08.EY.DHA - Install AHUs (Qty 1) | OFE | Not Started | 10/09/26 | 10/20/26 | 10.0 | 10.0 |
|
352.5 |
RPL08.EY.DHB.01120 |
RPL08.EY.DHB - Install BMS/EPMS UG | Underground | Not Started | 10/09/26 | 10/22/26 | 12.5 | 12.5 |
|
182.5 |
RPL08.EY.DHC.01050 |
RPL08.EY.DHC - Install Electrical UG | Underground | Not Started | 10/09/26 | 10/22/26 | 12.5 | 12.5 |
|
322.5 |
RPL08.EY.DHC.01060 |
RPL08.EY.DHC - Install UG Utilities - WBS Summary | Underground | Not Started | 10/09/26 | 07/13/27 | 235.0 | 235.0 |
|
225.0 |
RPL08.EY.DHD.01100 |
RPL08.EY.DHD - Install Mechanical UG | Underground | Not Started | 10/09/26 | 10/22/26 | 12.5 | 12.5 |
|
331.2 |
RPL08.EY.DHD.01110 |
RPL08.EY.DHD - Install SD, DW, FW UG | Underground | Not Started | 10/09/26 | 10/22/26 | 12.5 | 12.5 |
|
328.8 |
RPL08.SKN.DHAB.01060 |
RPL08.SKIN.DHAB - Install Security | Glazing, Doors and Ext Devices | Not Started | 10/09/26 | 10/12/26 | 2.5 | 2.5 |
|
363.8 |
RPL08.MCUP.LP1.1920 |
RPL08.MCUP.Loop 1 - Install Early Mcup Paving | Hardscape and Landscape | Not Started | 10/12/26 | 10/23/26 | 12.5 | 12.5 |
|
505.0 |
RPL08.MCUP.LP1.1940 |
RPL08.MCUP.Loop 1 - Tie-in BMS #4 | Tie-Ins BMS | Not Started | 10/12/26 | 10/21/26 | 10.0 | 10.0 |
|
195.0 |
RPL08.MCUP.LP2.1940 |
RPL08.MCUP.Loop 2 - Tie-in EPMS #6 | Tie-Ins EPMS | Not Started | 10/12/26 | 10/21/26 | 10.0 | 10.0 |
|
340.0 |
RPL.08.D.84210.XR |
FW Water Available for mCUP Flush/Fill - Utility connections | Receive Milestones (XREFs) | Not Started | 10/13/26 | 10/13/26 | 0.0 | 0.0 |
|
233.8 |
RPL.08.D.84410.XR |
Discharge Available for Fill/Flush Cx - Utility connections | Receive Milestones (XREFs) | Not Started | 10/13/26 | 10/13/26 | 0.0 | 0.0 |
|
233.8 |
RPL08.CFCI.5110 |
RPL08 - Submittals Review & Approval - Carpet | (CFCI) Div. 09 - Carpet | Not Started | 10/13/26 | 11/09/26 | 25.0 | 25.0 |
|
298.8 |
RPL08.CFCI.5140 |
RPL08 - Fabricate / Deliver -Epoxy Flooring (Spec 09 67 23) XX | (CFCI) Div. 09 - Epoxy Flooring | Not Started | 10/13/26 | 11/02/26 | 18.8 | 18.8 |
|
355.0 |
RPL08.CFCI.5260 |
RPL08 - Fabricate / Deliver - Specialities | (CFCI) Div. 10 - Specialities | Not Started | 10/13/26 | 11/24/26 | 37.5 | 37.5 |
|
285.0 |
RPL08.EY.DHA.01530 |
RPL08.EY.DHA - Set GS.IDF Hut (1x GS.IDF) XX04 | OFE | Not Started | 10/13/26 | 10/19/26 | 6.2 | 6.2 |
|
355.0 |
RPL08.EY.DHC.01530 |
RPL08.EY.DHC - Install Grounding UG | Underground | Not Started | 10/13/26 | 10/26/26 | 12.5 | 12.5 |
|
332.5 |
RPL08.SKN.DHAB.01140 |
RPL08.SKIN.DHAB - Install Perm Doors | Glazing, Doors and Ext Devices | Not Started | 10/13/26 | 10/14/26 | 2.5 | 2.5 |
|
363.8 |
RPL08.STR.DHAB.01110 |
RPL08.Structure.DHAB - SOG F/R/P - Grid Lines 6-11/6-23 - WBS Summary | F/R/P | Not Started | 10/13/26 | 11/25/26 | 38.8 | 38.8 |
|
120.0 |
RPL08.STR.DHAB.01160 |
RPL08.Structure.DHAB - SOG F/R/P #2 - Grid lines 6-04/6-07 | F/R/P | Not Started | 10/13/26 | 10/19/26 | 6.2 | 6.2 |
|
107.5 |
RPL08.STR.SSB.01190 |
RPL08.Structure.SSB - Zone SOG Cure | F/R/P | Not Started | 10/13/26 | 10/19/26 | 8.8 | 8.8 |
|
181.2 |
RPL08.EY.SSB.01200 |
RPL08.EY.SSB - Install LD F/R/P Loading Dock Ramp | Loading Dock | Not Started | 10/14/26 | 10/23/26 | 10.0 | 10.0 |
|
298.8 |
RPL08.MCUP.LP2.2120 |
RPL08.MCUP.Loop 2 - Set Facility Water Pipe Rack (mCUP6) | OFE | Not Started | 10/14/26 | 10/27/26 | 12.5 | 12.5 |
|
335.0 |
RPL08.INT.DHB.02160 |
RPL08.Interior.DHBADC - Priority - Install Fixed Draft/Smoke Curtain (#5) | Early Priority OH MEPF | Not Started | 10/15/26 | 10/27/26 | 11.2 | 11.2 |
|
145.0 |
RPL08.MCUP.LP1.2080 |
RPL08.MCUP.Loop 1 - Tie-in - Mechanical L2 Checklist Completion | Tie-ins | Not Started | 10/15/26 | 10/28/26 | 12.5 | 12.5 |
|
195.0 |
RPL08.SKN.DHAB.01110 |
RPL08.SKIN.DHAB - Install Scupper and Downspouts | Glazing, Doors and Ext Devices | Not Started | 10/15/26 | 10/21/26 | 6.2 | 6.2 |
|
378.8 |
RPL08.SKN.DHCD.01090 |
RPL08.SKIN.DHCD - Install Roof System - DenseDeck & Flame Down | Roofing | Not Started | 10/15/26 | 10/23/26 | 8.8 | 8.8 |
|
132.5 |
RPL08.MCUP.LP2.1580 |
RPL08.MCUP.Loop 2 - Tie-in Mechanical - WBS Summary | Tie-Ins Mechanical | Not Started | 10/16/26 | 11/12/26 | 23.8 | 23.8 |
|
327.5 |
RPL08.MCUP.LP2.1600 |
RPL08.MCUP.Loop 1 - Tie-in Mechanical #5 | Tie-Ins Mechanical | Not Started | 10/16/26 | 11/03/26 | 16.2 | 16.2 |
|
335.0 |
RPL.GF.D.N8170.XR |
Natural Gas Available for Fill/Flush Cx - Utility connections | Receive Milestones (XREFs) | Not Started | 10/20/26 | 10/20/26 | 0.0 | 0.0 |
|
233.8 |
RPL08.CON.WP2.07800 |
RPL08.Conn - Ext. GSIDF8X04 (South Elec Yard) - WBS Summary | Ext. IDF Hut - GSIDF8X04 | Not Started | 10/20/26 | 04/29/27 | 162.5 | 162.5 |
|
385.0 |
RPL08.CON.WP2.08460 |
RPL08.Conn - Ext. GSIDF8X04 - Install Infrastructure (Racks, Waterfalls etc.) ??pred?? | Infrastructure | Not Started | 10/20/26 | 10/26/26 | 6.2 | 6.2 |
|
355.0 |
RPL08.EY.ENDC.1390 |
RPL08.EY.DHD.T1 - Install Panels | Tent 1 | Not Started | 10/20/26 | 10/26/26 | 6.2 | 6.2 |
|
151.2 |
RPL08.EY.ENDC.1410 |
RPL08.EY.DHD.T1 - Install Heating and Cooling Equipment | Tent 1 | Not Started | 10/20/26 | 10/26/26 | 6.2 | 6.2 |
|
147.5 |
RPL08.EY.ENDC.1430 |
RPL08.EY.DHD.T1 - Install Overhead Doors | Tent 1 | Not Started | 10/20/26 | 10/26/26 | 6.2 | 6.2 |
|
155.0 |
RPL08.EY.ENDC.1450 |
RPL08.EY.DHD.T1 - Install Tent Fit-out | Tent 1 | Not Started | 10/20/26 | 11/02/26 | 12.5 | 12.5 |
|
148.8 |
RPL08.EY.ENDC.1690 |
RPL08.EY.DHD.T2 - Install Panels | Tent 2 | Not Started | 10/20/26 | 10/26/26 | 6.2 | 6.2 |
|
163.8 |
RPL08.EY.ENDC.1710 |
RPL08.EY.DHD.T2 - Install Heating and Cooling Equipment | Tent 2 | Not Started | 10/20/26 | 10/26/26 | 6.2 | 6.2 |
|
160.0 |
RPL08.EY.ENDC.1730 |
RPL08.EY.DHD.T2 - Install Overhead Doors | Tent 2 | Not Started | 10/20/26 | 10/26/26 | 6.2 | 6.2 |
|
167.5 |
RPL08.EY.ENDC.1750 |
RPL08.EY.DHD.T2 - Install Tent Fit-out | Tent 2 | Not Started | 10/20/26 | 11/02/26 | 12.5 | 12.5 |
|
161.2 |
RPL08.INT.SSB.01006 |
RPL08.Interior - Priority - Install Hangers Support (Center Corr to End Corr) (All Trades) | Early Priority OH MEPF | Not Started | 10/20/26 | 11/02/26 | 12.5 | 12.5 |
|
240.0 |
RPL08.INT.SSBC.01000 |
RPL08.Interior.SSBC - Priority - WBS Summary | Priority Walls & Overhead | Not Started | 10/20/26 | 12/18/26 | 51.2 | 51.2 |
|
152.5 |
RPL08.INT.SSBC.01020 |
RPL08.Interior.SSB-Corridor - Install Priority OH, Walls, OFE and Fitout - WBS Summary | SSB Corridor | Not Started | 10/20/26 | 06/09/27 | 197.5 | 197.5 |
|
188.8 |
RPL08.INT.SSBC.01080 |
RPL08.Interior.SSBC - Priority GL8.04 - (P0) Apply Intumescent Paint to Deck | Priority Wall Grid Line 8-04 | Not Started | 10/20/26 | 11/09/26 | 18.8 | 18.8 |
|
116.2 |
RPL08.INT.SSBC.02400 |
RPL08.Interior.SSBC - Priority - Install Layout, Unistruts & Hangers (All Trades) Both side of Corridor Wall | Priority Walls & Overhead | Not Started | 10/20/26 | 10/23/26 | 5.0 | 5.0 |
|
117.5 |
RPL08.STR.DHAB.01170 |
RPL08.Structure.DHAB - SOG F/R/P #3 - Grid lines 6-07/6-11 | F/R/P | Not Started | 10/20/26 | 10/26/26 | 6.2 | 6.2 |
|
107.5 |
RPL08.STR.SSB.01250 |
RPL08.Structure.SSB - Moisture requirements for floor Sealer | F/R/P | Not Started | 10/20/26 | 10/26/26 | 8.8 | 8.8 |
|
210.0 |
RPL08.INT.SSBC.01011 |
RPL08.Interior.SSB-Corridor - Priority - Install Duct (Highside OH space) | Early Priority OH MEPF | Not Started | 10/22/26 | 10/28/26 | 6.2 | 6.2 |
|
105.0 |
RPL08.MCUP.LP2.2040 |
RPL08.MCUP.Loop 2 - Tie-in - MV Loop 2 L2 Checklist Completion | Tie-ins | Not Started | 10/22/26 | 10/28/26 | 6.2 | 6.2 |
|
340.0 |
RPL08.SKN.E.01040 |
RPL08.SKIN.East - Secure All Exterior Mounted Boxes and Devices on Skin | IMP System | Not Started | 10/22/26 | 11/04/26 | 12.5 | 12.5 |
|
423.8 |
RPL08.CON.WP2.09180 |
RPL08.Conn - CorpNet & FacNet Available (mCUP) - All IDFs | WP#02 GS | Not Started | 10/23/26 | 10/23/26 | 0.0 | 0.0 |
|
542.5 |
RPL08.Conn.MS.01080 |
RPL08.Conn Wifi Ready - mCUP Yard (Pred from RPL10 CorpNet needed?) | Connectivity Milestones | Not Started | 10/23/26 | 10/23/26 | 0.0 | 0.0 |
|
373.8 |
RPL08.EY.DHC.01090 |
RPL08.EY.DHC - Install Mechanical UG | Underground | Not Started | 10/23/26 | 11/05/26 | 12.5 | 12.5 |
|
322.5 |
RPL08.EY.DHC.01100 |
RPL08.EY.DHC - Install SD, DW, FW UG | Underground | Not Started | 10/23/26 | 11/05/26 | 12.5 | 12.5 |
|
332.5 |
RPL08.EY.ENDC.01000 |
RPL08.EY.End - Install Electrical UG | Underground | Not Started | 10/23/26 | 10/29/26 | 6.2 | 6.2 |
|
373.8 |
RPL08.EY.ENDC.01010 |
RPL08.EY.End - Install UG Utilities - WBS Summary | Underground | Not Started | 10/23/26 | 11/20/26 | 25.0 | 25.0 |
|
382.5 |
RPL08.INT.SSBC.03240 |
RPL08.Interior.SSBC - Priority - Install Priority Soffit for Wall Tie-Ins/ Rock & HoW & Draft Blanket | Priority Walls & Overhead | Not Started | 10/23/26 | 10/29/26 | 6.2 | 6.2 |
|
116.2 |
RPL08.INT.SSBC.03520 |
RPL08.Interior.SSBC - Priority - Install IMP Exterior Inwall Rough-In | Priority Walls & Overhead | Not Started | 10/23/26 | 10/27/26 | 3.8 | 3.8 |
|
161.2 |
RPL08.MCUP.LP2.1660 |
RPL08.MCUP.Loop 2 - Tie-in BMS - WBS Summary | Tie-Ins BMS | Not Started | 10/23/26 | 11/12/26 | 17.5 | 17.5 |
|
327.5 |
RPL08.MCUP.LP2.1720 |
RPL08.MCUP.Loop 2 - Tie-in BMS #5 | Tie-Ins BMS | Not Started | 10/23/26 | 11/03/26 | 10.0 | 10.0 |
|
335.0 |
RPL08.EY.SSB.01210 |
RPL08.EY.SSB - Install LD Electrical In walls | Loading Dock | Not Started | 10/26/26 | 10/29/26 | 5.0 | 5.0 |
|
298.8 |
RPL08.EY.SSB.01220 |
RPL08.EY.SSB - Install LD French Drain (Not Designed) | Loading Dock | Not Started | 10/26/26 | 10/29/26 | 5.0 | 5.0 |
|
308.8 |
RPL08.LOG.1300 |
Dry Cooler 230 Ton Crane Demobilization | 100 Ton Crane | Not Started | 10/26/26 | 10/28/26 | 3.8 | 3.8 |
|
472.5 |
RPL08.MCUP.LP1.2000 |
RPL08.MCUP.Loop 1 - Install Lighting | Hardscape and Landscape | Not Started | 10/26/26 | 11/06/26 | 12.5 | 12.5 |
|
505.0 |
RPL08.MCUP.LP2.1240 |
RPL08.MCUP.Loop 2 - Set MTRs (4 per day) | OFE | Not Started | 10/26/26 | 10/27/26 | 2.5 | 2.5 |
|
335.0 |
RPL08.MCUP.LP2.2020 |
RPL08.MCUP.Loop 1 - Tie-in Mechanical #6 | Tie-Ins Mechanical | Not Started | 10/26/26 | 11/12/26 | 16.2 | 16.2 |
|
327.5 |
RPL08.CON.WP2.08540 |
RPL08.Conn - Ext. GSIDF8X04 - Install Copper, WAPs, Security Camera & Access Control (EY-DH A) | Cabling | Not Started | 10/27/26 | 11/12/26 | 15.0 | 15.0 |
|
355.0 |
RPL08.EY.DHC.01130 |
RPL08.EY.DHC - Cure (High Early Mix) | Foundations | Not Started | 10/27/26 | 11/02/26 | 8.8 | 8.8 |
|
455.0 |
RPL08.EY.ENDC.01340 |
RPL08.EY.End - Install Grounding UG | Underground | Not Started | 10/27/26 | 11/02/26 | 6.2 | 6.2 |
|
392.5 |