Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL08 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:14 PM · 5122 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
0
Completed
0
In Progress
0
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL08.EY.ENDC.1470 RPL08.EY.DHD.T1 - Install Electrical Tie-ins Tent 1 Not Started 10/27/26 10/29/26 3.8 3.8
0%
151.2
RPL08.EY.ENDC.1490 RPL08.EY.DHD.T1 - Install Mechanical Tie-ins Tent 1 Not Started 10/27/26 11/03/26 7.5 7.5
0%
147.5
RPL08.EY.ENDC.1770 RPL08.EY.DHD.T2 - Install Electrical Tie-ins Tent 2 Not Started 10/27/26 10/29/26 3.8 3.8
0%
163.8
RPL08.EY.ENDC.1790 RPL08.EY.DHD.T2 - Install Mechanical Tie-ins Tent 2 Not Started 10/27/26 11/03/26 7.5 7.5
0%
160.0
RPL08.INT.SSB.01000 RPL08.Interior.SSB - Priority - WBS Summary Priority Walls and OverHead Not Started 10/27/26 12/15/26 41.2 41.2
0%
325.0
RPL08.INT.SSB.01020 RPL08.Interior.SSB - Install Priority OH, Walls and Fitout - WBS Summary SSB Not Started 10/27/26 06/11/27 193.8 193.8
0%
272.5
RPL08.INT.SSB.01030 RPL08.Interior.SSB - Priority - Install Fire Sprinkler (Highside OH space) Early Priority OH MEPF Not Started 10/27/26 11/02/26 6.2 6.2
0%
140.0
RPL08.INT.SSB.01040 RPL08.Interior.SSB - Priority - Install Temp Lighting (Show In Model) Early Priority OH MEPF Not Started 10/27/26 11/02/26 6.2 6.2
0%
140.0
RPL08.INT.SSB.03180 RPL08.Interior.SSB - Priority - Install Priority Soffit for Wall Tie-Ins/ Rock & HoW & Draft Blanket Priority Walls and OverHead Not Started 10/27/26 11/09/26 12.5 12.5
0%
143.8
RPL08.INT.SSBC.06600 RPL08.Interior.SSBC - Priority - Install Backing at Exterior Wall Priority Walls & Overhead Not Started 10/27/26 10/27/26 1.2 1.2
0%
161.2
RPL08.SKN.DHAB.01120 RPL08.SKIN.DHAB - Install Roof System - Final Roof Roofing Not Started 10/27/26 11/12/26 15.0 15.0
0%
206.2
RPL08.SKN.SSB.01140 RPL08.SKIN.SSB - Install Roof System - Install EJ Roofing Not Started 10/27/26 11/02/26 6.2 6.2
0%
140.0
RPL08.STR.DHAB.01180 RPL08.Structure.DHAB - SOG F/R/P #4 - Grid lines 6-11/6-14 F/R/P Not Started 10/27/26 11/02/26 6.2 6.2
0%
107.5
RPL08.STR.SSB.01270 RPL08.Structure.SSB - Install SOG Sealer and Cure F/R/P Not Started 10/27/26 10/28/26 2.5 2.5
0%
288.8
RPL08.INT.SSBC.06620 RPL08.Interior.SSBC - Priority - QC - Backings/Walls Priority Walls & Overhead Not Started 10/28/26 10/29/26 2.5 2.5
0%
161.2
RPL08.INT.SSBC.06720 RPL08.Interior.SSBC - Priority - Install Drywall at Exterior Walls for SSB Electrical Room Priority Walls & Overhead Not Started 10/28/26 10/29/26 2.5 2.5
0%
185.0
GCD.RPL08.2051 MCUP Ready for Energization - (MCUPs Loop 1) mCup Not Started 10/29/26 10/29/26 0.0 0.0
0%
220.0
RPL08.CX.1180 RPL08.CX.BLDG - L3, L4, IST - WBS Summary Commissioning Not Started 10/29/26 07/11/28 526.2 526.2
0%
12.5
RPL08.CX.MCUP.01000 RPL08.CX.mCup Loop 1 - L3, L4, IST - WBS Summary mCUP 1-4 Not Started 10/29/26 05/27/27 178.8 178.8
0%
212.5
RPL08.CX.MCUP.01350 RPL08.CX.mCup Loop 1 - L3/L4 - mCUP - Flush and Fill - Temp Flush Skid (PR) Fill and Flush Not Started 10/29/26 11/04/26 6.2 6.2
0%
218.8
RPL08.EY.DHD.01120 RPL08.EY.DHD - Cure (High Early Mix) Foundations Not Started 10/29/26 11/04/26 8.8 8.8
0%
425.0
RPL08.INT.DHA.01010 RPL08.Interior.DHA - Priority - Install Duct Early Priority OH MEPF Not Started 10/29/26 11/04/26 6.2 6.2
0%
105.0
RPL08.INT.DHB.01010 RPL08.Interior.DHB - Priority - Install Duct Early Priority OH MEPF Not Started 10/29/26 11/04/26 6.2 6.2
0%
105.0
RPL08.MCUP.LP2.1420 RPL08.MCUP.Loop 2 - Tie-in SD, DW Tie-ins Not Started 10/29/26 11/19/26 18.8 18.8
0%
472.5
RPL08.MCUP.LP2.2060 RPL08.MCUP.Loop 2 - Tie-in - Electrical L2 Checklist Completion Tie-ins Not Started 10/29/26 11/04/26 6.2 6.2
0%
340.0
RPL08.EY.ENDC.01030 RPL08.EY.End - Install Mechanical UG Underground Not Started 10/30/26 11/05/26 6.2 6.2
0%
373.8
RPL08.EY.SSB.01230 RPL08.EY.SSB - Install LD F/R/P Loading Dock Walls Loading Dock Not Started 10/30/26 11/10/26 10.0 10.0
0%
298.8
RPL08.INT.SSB.02680 RPL08.Interior.SSB - Priority - Install Layout, Unistruts & Hangers (All Trades) Priority Walls and OverHead Not Started 10/30/26 11/13/26 12.5 12.5
0%
143.8
RPL08.INT.SSBC.06740 RPL08.Interior.SSBC - Priority - Frame, Hang Drywall, Tape Finish Paint for SSB Electrical Room Priority Walls & Overhead Not Started 10/30/26 11/09/26 8.8 8.8
0%
185.0
RPL08.MCUP.LP2.1980 RPL08.MCUP.Loop 2 - Tie-in BMS #6 Tie-Ins BMS Not Started 11/02/26 11/12/26 10.0 10.0
0%
327.5
RPL08.EY.ENDC.01040 RPL08.EY.End - Install BMS UG Underground Not Started 11/03/26 11/09/26 6.2 6.2
0%
392.5
RPL08.INT.SSB.06640 RPL08.Interior.SSB - Priority - Install IMP Exterior Inwall Rough-In Priority Walls and OverHead Not Started 11/03/26 11/09/26 6.2 6.2
0%
143.8
RPL08.INT.SSBC.01030 RPL08.Interior.SSB-Corridor - Priority - Install Fire Sprinkler (Highside OH space) Early Priority OH MEPF Not Started 11/03/26 11/03/26 1.2 1.2
0%
140.0
RPL08.INT.SSBC.01040 RPL08.Interior.SSB-Corridor - Priority - Install Temp Lighting (Show In Model) Early Priority OH MEPF Not Started 11/03/26 11/05/26 3.8 3.8
0%
140.0
RPL08.STR.DHAB.01100 RPL08.Structure.DHAB - SOG F/R/P #5 - Grid lines 6-14/6-18 F/R/P Not Started 11/03/26 11/09/26 6.2 6.2
0%
107.5
RPL08.EY.ENDC.1510 RPL08.EY.DHD.T1 - Temp Conditioning Startup and Available Tent 1 Not Started 11/04/26 11/05/26 2.5 2.5
0%
147.5
RPL08.EY.ENDC.1810 RPL08.EY.DHD.T2 - Temp Conditioning Startup and Available Tent 2 Not Started 11/04/26 11/05/26 2.5 2.5
0%
160.0
RPL08.INT.DHB.01030 RPL08.Interior.DHB - Priority - Install Fire Sprinkler Early Priority OH MEPF Not Started 11/04/26 11/10/26 6.2 6.2
0%
140.0
ICM.B8.1212 [SSDCB3] Start Flush & Fill of Chilled Water System Commissioning Not Started 11/05/26 11/05/26 0.0 0.0
0%
225.0
RPL08.CX.MCUP.01150 RPL08.CX.mCup Loop 1 - L3/L4 - mCUP - Flush and Fill - mCup Yard & FWM - Loop 1 (mCUPs 1-4) (Phase 1) Fill and Flush Not Started 11/05/26 11/12/26 6.2 6.2
0%
218.8
RPL08.INT.CTRC.1180 RPL08.Interior.Center-Corridor - Priority - Install Duct (Highside OH space) Early Priority OH MEPF Not Started 11/05/26 11/16/26 8.8 8.8
0%
288.8
RPL08.INT.DHA.01020 RPL08.Interior.DHA - Install Priority OH, Walls, OFE and Tie-ins - WBS Summary DHA Not Started 11/05/26 06/16/27 188.8 188.8
0%
197.5
RPL08.INT.DHA.03380 RPL08.Interior.DHA - Temp Conditions - Drop Curtains (from Corridor to EJ) Temp Conditions Not Started 11/05/26 11/17/26 10.0 10.0
0%
105.0
RPL08.INT.DHB.01020 RPL08.Interior.DHB - Install Priority OH, Walls, OFE and Tie-ins - WBS Summary DHB Not Started 11/05/26 06/15/27 187.5 187.5
0%
186.2
RPL08.INT.DHB.01060 RPL08.Interior.DHB - Temp Conditions - Drop Curtains (from Corridor to EJ) Temp Conditions Not Started 11/05/26 11/16/26 8.8 8.8
0%
106.2
RPL08.INT.SSB.02840 RPL08.Interior.SSB - Priority - Tape Finish Paint Priority Soffit (Top Out) Priority Walls and OverHead Not Started 11/05/26 11/19/26 12.5 12.5
0%
210.0
RPL08.SKN.DHCD.01000 RPL08.SKIN.DHCD - Install Temp Doors Glazing, Doors and Ext Devices Not Started 11/05/26 11/06/26 2.5 2.5
0%
423.8
RPL08.SKN.DHCD.01020 RPL08.SKIN.DHCD - Install Windows, Doors, Louvers and Ext Devices - WBS Summary Glazing, Doors and Ext Devices Not Started 11/05/26 07/22/27 220.0 220.0
0%
236.2
RPL08.EY.DHC.01120 RPL08.EY.DHC - Install BMS UG Underground Not Started 11/06/26 11/20/26 12.5 12.5
0%
322.5
RPL08.EY.ENDC.01050 RPL08.EY.End - Install SD, DW, FW UG Underground Not Started 11/06/26 11/20/26 12.5 12.5
0%
376.2
RPL08.INT.DHB.01040 RPL08.Interior.DHB - Priority - Install Temp Lighting Early Priority OH MEPF Not Started 11/06/26 11/10/26 3.8 3.8
0%
140.0
RPL08.INT.SSB.06560 RPL08.Interior.SSB - Priority - Install Backing at Exterior Wall Priority Walls and OverHead Not Started 11/06/26 11/13/26 6.2 6.2
0%
143.8
ICM.B8.1855 [SSDCB3] Delivery of MES - Multi Trade Rack (First Delivery) Construction Not Started 11/09/26 11/09/26 0.0 0.0
0%
171.2
RPL08.MCUP.LP1.2040 RPL08.MCUP.Loop 1 - Install Mcup Paving Hardscape and Landscape Not Started 11/09/26 11/23/26 12.5 12.5
0%
505.0
RPL08.SKN.DHCD.01140 RPL08.SKIN.DHCD - Install Blocking of Canopy & Backing of Exterior Wall Glazing, Doors and Ext Devices Not Started 11/09/26 11/16/26 6.2 6.2
0%
423.8
RPL08.CFCI.5290 RPL08 - Fabricate / Deliver - Carpet Tile (CFCI) Div. 09 - Carpet Not Started 11/10/26 01/11/27 50.0 50.0
0%
298.8
RPL08.INT.SSBC.03500 RPL08.Interior.SSBC - Priority - Install Drywall at Exterior Walls Priority Walls & Overhead Not Started 11/10/26 11/13/26 3.8 3.8
0%
152.5
RPL08.STR.DHAB.01140 RPL08.Structure.DHAB - Zone SOG Cure F/R/P Not Started 11/10/26 11/16/26 8.8 8.8
0%
161.2
RPL08.STR.DHCD.01110 RPL08.Structure.DHCD - SOG F/R/P - WBS Summary F/R/P Not Started 11/10/26 12/19/26 32.5 32.5
0%
178.8
RPL08.STR.DHCD.01120 RPL08.Structure.DHCD - SOG F/R/P #6 - Grid lines 6-18/6-21 F/R/P Not Started 11/10/26 11/17/26 6.2 6.2
0%
118.8
GCD.RPL08.1020 Weather tight SSB and DHA&B Construction Milestones Not Started 11/12/26 11/12/26 0.0 0.0
0%
378.8
RPL08.INT.DHA.01030 RPL08.Interior.DHA - Priority - Install Fire Sprinkler Early Priority OH MEPF Not Started 11/12/26 11/18/26 6.2 6.2
0%
213.8
RPL08.INT.DHA.01040 RPL08.Interior.DHA - Priority - Install Temp Lighting Early Priority OH MEPF Not Started 11/12/26 11/16/26 3.8 3.8
0%
221.2
DCC.B8.3125 [SSDCB3] GS Gear Delivered [DHB] Connectivity Not Started 11/13/26 11/13/26 0.0 0.0
0%
526.2
RPL08.CON.WP2.08560 RPL08.Conn - Ext. GSIDF8X04 - Install Copper, WAPs, Security Camera & Access Control (EY-DH C) Cabling Not Started 11/13/26 12/02/26 15.0 15.0
0%
355.0
RPL08.CX.MCUP.01190 RPL08.CX.mCup Loop 1 - L3/L4 - mCUP - Flush and Fill - mCup1 and Dry Coolers Fill and Flush Not Started 11/13/26 11/20/26 7.5 7.5
0%
218.8
RPL08.CX.MCUP.01210 RPL08.CX.mCup Loop 1 - L3/L4 - mCUP - Flush and Fill - mCup2 and Dry Coolers Fill and Flush Not Started 11/13/26 11/20/26 7.5 7.5
0%
218.8
RPL08.INT.DHB.01090 RPL08.Interior.DHB - Temp Conditions - Install Early Temp Conditions Temp Conditions Not Started 11/13/26 11/16/26 2.5 2.5
0%
106.2
RPL08.INT.SSBC.03280 RPL08.Interior.SSBC - Priority GL8.04 - (P0) Frame Walls (All full height Walls) Priority Wall Grid Line 8-04 Not Started 11/13/26 11/19/26 6.2 6.2
0%
152.5
RPL08.MCUP.LP2.2080 RPL08.MCUP.Loop 2 - Tie-in - Mechanical L2 Checklist Completion Tie-ins Not Started 11/13/26 11/19/26 6.2 6.2
0%
327.5
RPL08.SKN.DHAB.01130 RPL08.SKIN.DHAB - Install Roof System - Install EJ Roofing Not Started 11/13/26 11/16/26 2.5 2.5
0%
206.2
RPL08.SKN.DHCD.01110 RPL08.SKIN.DHCD - Install Roof System - Final Roof Roofing Not Started 11/13/26 12/02/26 15.0 15.0
0%
472.5
RPL08.INT.DHA.03400 RPL08.Interior.DHA - Temp Conditions - Install Early Temp Conditions Temp Conditions Not Started 11/16/26 11/17/26 2.5 2.5
0%
105.0
RPL08.INT.SSB.06580 RPL08.Interior.SSB - Priority - QC - Backings/Walls Priority Walls and OverHead Not Started 11/16/26 11/20/26 6.2 6.2
0%
143.8
RPL08.INT.SSBC.03260 RPL08.Interior.SSBC - Priority - Tape Finish Paint Priority Soffit both sides (Top Out) Priority Walls & Overhead Not Started 11/16/26 11/20/26 6.2 6.2
0%
175.0
ICM.B8.1845 [SSDCB3] Delivery of FSHAC - Hot Aisle Containment (First Delivery) Construction Not Started 11/17/26 11/17/26 0.0 0.0
0%
150.0
RPL08.INT.DHB.02360 RPL08.Interior.DHB - Temp Conditions - CC West Duct Work Complete for Temp Conditioning (LVs) Temp Conditions Not Started 11/17/26 11/18/26 2.5 2.5
0%
106.2
RPL08.SKN.DHCD.01030 RPL08.SKIN.DHCD - Install Awning over Doors Glazing, Doors and Ext Devices Not Started 11/17/26 11/23/26 6.2 6.2
0%
423.8
RPL08.STR.DHAB.01240 RPL08.Structure.DHAB - Moisture requirements for floor Sealer F/R/P Not Started 11/17/26 11/23/26 8.8 8.8
0%
161.2
RPL08.INT.DHA.03420 RPL08.Interior.DHA - Temp Conditions - CC West Duct Work Complete for Temp Conditioning (LVs) Temp Conditions Not Started 11/18/26 11/19/26 2.5 2.5
0%
105.0
RPL08.INT.DHB.01000 RPL08.Interior.DHB - Priority OH - WBS Summary OverHead Not Started 11/18/26 12/30/26 35.0 35.0
0%
115.0
RPL08.INT.DHB.02100 RPL08.Interior.DHB - Priority - Install Mechanical Piping OverHead Not Started 11/18/26 12/10/26 18.8 18.8
0%
118.8
RPL08.INT.SSBC.06660 RPL08.Interior.SSBC - Priority GL8.04 - (P0) Install MEP In-Wall/Backing Priority Wall Grid Line 8-04 Not Started 11/18/26 11/23/26 5.0 5.0
0%
152.5
RPL08.STR.DHCD.01130 RPL08.Structure.DHCD - SOG F/R/P #7 - Grid lines 6-21/6-25 F/R/P Not Started 11/18/26 11/24/26 6.2 6.2
0%
118.8
RPL08.INT.CTRC.1040 RPL08.Interior.Center-Corridor - Priority - Install Fire Sprinkler (Highside OH space) Early Priority OH MEPF Not Started 11/19/26 11/23/26 3.8 3.8
0%
213.8
RPL08.INT.CTRC.1060 RPL08.Interior.Center-Corridor - Priority - Install Temp Lighting (Show In Model) Early Priority OH MEPF Not Started 11/19/26 11/23/26 3.8 3.8
0%
218.8
GCD.RPL08.3985 MCUP Ready for Energization - (MCUPs Loop 2) mCup Not Started 11/20/26 11/20/26 0.0 0.0
0%
435.0
ICM.B8.1750 [SSDCB3] Room Ready for GS.MDF Module Placement Construction Not Started 11/20/26 11/20/26 0.0 0.0
0%
175.0
RPL08.CX.MCUP.01020 RPL08.CX.mCup Loop 2 - L3, L4, IST - WBS Summary mCUP 5-6 Not Started 11/20/26 07/07/27 193.8 193.8
0%
287.5
RPL08.CX.MCUP.01100 RPL08.CX.mCup Loop 2 - L3/L4 - mCUP - Flush and Fill - mCup Yard - Loop 2 (mCUPs 5-6) (Phase 3) Fill and Flush Not Started 11/20/26 11/30/26 6.2 6.2
0%
357.5
RPL08.INT.DHA.03460 RPL08.Interior.DHA - Temp Conditions - Temp Conditioning Achieved & Acclimated for West of CC (SSB/DHB/DHA) Temp Conditions Not Started 11/20/26 11/30/26 6.2 6.2
0%
105.0
RPL08.INT.SSBC.06640 RPL08.Interior.SSBC - Priority GL8.04 - (P0) Install IMP Wall Priority Wall Grid Line 8-04 Not Started 11/20/26 11/25/26 5.0 5.0
0%
171.2
RPL08.INT.SSBC.06680 RPL08.Interior.SSBC - Priority GL8.04 - (P0) Hang Drywall (Both SIdes) Priority Wall Grid Line 8-04 Not Started 11/20/26 11/25/26 5.0 5.0
0%
152.5
RPL08.MCUP.LP2.1520 RPL08.MCUP.Loop 2 - Install Hardscape and Landscape - WBS Summary Hardscape and Landscape Not Started 11/20/26 01/19/27 47.5 47.5
0%
472.5
RPL08.MCUP.LP2.1540 RPL08.MCUP.Loop 2 - Install Sleeves MEPL Hardscape and Landscape Not Started 11/20/26 11/24/26 3.8 3.8
0%
472.5
RPL08.CX.MCUP.01230 RPL08.CX.mCup Loop 1 - L3/L4 - mCUP - Flush and Fill - mCup3 and Dry Coolers Fill and Flush Not Started 11/23/26 12/02/26 7.5 7.5
0%
218.8
RPL08.CX.MCUP.01250 RPL08.CX.mCup Loop 1 - L3/L4 - mCUP - Flush and Fill - mCup4 and Dry Coolers Fill and Flush Not Started 11/23/26 12/02/26 7.5 7.5
0%
221.2
RPL08.INT.SSB.06540 RPL08.Interior.SSB - Priority - Install Drywall at Exterior Walls Priority Walls and OverHead Not Started 11/23/26 12/08/26 12.5 12.5
0%
143.8
RPL08.INT.DHA.01000 RPL08.Interior.DHA - Priority OH - WBS Summary OverHead Not Started 11/24/26 02/02/27 57.5 57.5
0%
313.8
RPL08.INT.DHA.01980 RPL08.Interior.DHA - Priority - Install Unistruts & Hangers (All Trades) OverHead Not Started 11/24/26 12/02/26 6.2 6.2
0%
117.5