Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL08 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:14 PM
· 5122 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
0
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL08.EY.ENDC.1470 |
RPL08.EY.DHD.T1 - Install Electrical Tie-ins | Tent 1 | Not Started | 10/27/26 | 10/29/26 | 3.8 | 3.8 |
|
151.2 |
RPL08.EY.ENDC.1490 |
RPL08.EY.DHD.T1 - Install Mechanical Tie-ins | Tent 1 | Not Started | 10/27/26 | 11/03/26 | 7.5 | 7.5 |
|
147.5 |
RPL08.EY.ENDC.1770 |
RPL08.EY.DHD.T2 - Install Electrical Tie-ins | Tent 2 | Not Started | 10/27/26 | 10/29/26 | 3.8 | 3.8 |
|
163.8 |
RPL08.EY.ENDC.1790 |
RPL08.EY.DHD.T2 - Install Mechanical Tie-ins | Tent 2 | Not Started | 10/27/26 | 11/03/26 | 7.5 | 7.5 |
|
160.0 |
RPL08.INT.SSB.01000 |
RPL08.Interior.SSB - Priority - WBS Summary | Priority Walls and OverHead | Not Started | 10/27/26 | 12/15/26 | 41.2 | 41.2 |
|
325.0 |
RPL08.INT.SSB.01020 |
RPL08.Interior.SSB - Install Priority OH, Walls and Fitout - WBS Summary | SSB | Not Started | 10/27/26 | 06/11/27 | 193.8 | 193.8 |
|
272.5 |
RPL08.INT.SSB.01030 |
RPL08.Interior.SSB - Priority - Install Fire Sprinkler (Highside OH space) | Early Priority OH MEPF | Not Started | 10/27/26 | 11/02/26 | 6.2 | 6.2 |
|
140.0 |
RPL08.INT.SSB.01040 |
RPL08.Interior.SSB - Priority - Install Temp Lighting (Show In Model) | Early Priority OH MEPF | Not Started | 10/27/26 | 11/02/26 | 6.2 | 6.2 |
|
140.0 |
RPL08.INT.SSB.03180 |
RPL08.Interior.SSB - Priority - Install Priority Soffit for Wall Tie-Ins/ Rock & HoW & Draft Blanket | Priority Walls and OverHead | Not Started | 10/27/26 | 11/09/26 | 12.5 | 12.5 |
|
143.8 |
RPL08.INT.SSBC.06600 |
RPL08.Interior.SSBC - Priority - Install Backing at Exterior Wall | Priority Walls & Overhead | Not Started | 10/27/26 | 10/27/26 | 1.2 | 1.2 |
|
161.2 |
RPL08.SKN.DHAB.01120 |
RPL08.SKIN.DHAB - Install Roof System - Final Roof | Roofing | Not Started | 10/27/26 | 11/12/26 | 15.0 | 15.0 |
|
206.2 |
RPL08.SKN.SSB.01140 |
RPL08.SKIN.SSB - Install Roof System - Install EJ | Roofing | Not Started | 10/27/26 | 11/02/26 | 6.2 | 6.2 |
|
140.0 |
RPL08.STR.DHAB.01180 |
RPL08.Structure.DHAB - SOG F/R/P #4 - Grid lines 6-11/6-14 | F/R/P | Not Started | 10/27/26 | 11/02/26 | 6.2 | 6.2 |
|
107.5 |
RPL08.STR.SSB.01270 |
RPL08.Structure.SSB - Install SOG Sealer and Cure | F/R/P | Not Started | 10/27/26 | 10/28/26 | 2.5 | 2.5 |
|
288.8 |
RPL08.INT.SSBC.06620 |
RPL08.Interior.SSBC - Priority - QC - Backings/Walls | Priority Walls & Overhead | Not Started | 10/28/26 | 10/29/26 | 2.5 | 2.5 |
|
161.2 |
RPL08.INT.SSBC.06720 |
RPL08.Interior.SSBC - Priority - Install Drywall at Exterior Walls for SSB Electrical Room | Priority Walls & Overhead | Not Started | 10/28/26 | 10/29/26 | 2.5 | 2.5 |
|
185.0 |
GCD.RPL08.2051 |
MCUP Ready for Energization - (MCUPs Loop 1) | mCup | Not Started | 10/29/26 | 10/29/26 | 0.0 | 0.0 |
|
220.0 |
RPL08.CX.1180 |
RPL08.CX.BLDG - L3, L4, IST - WBS Summary | Commissioning | Not Started | 10/29/26 | 07/11/28 | 526.2 | 526.2 |
|
12.5 |
RPL08.CX.MCUP.01000 |
RPL08.CX.mCup Loop 1 - L3, L4, IST - WBS Summary | mCUP 1-4 | Not Started | 10/29/26 | 05/27/27 | 178.8 | 178.8 |
|
212.5 |
RPL08.CX.MCUP.01350 |
RPL08.CX.mCup Loop 1 - L3/L4 - mCUP - Flush and Fill - Temp Flush Skid (PR) | Fill and Flush | Not Started | 10/29/26 | 11/04/26 | 6.2 | 6.2 |
|
218.8 |
RPL08.EY.DHD.01120 |
RPL08.EY.DHD - Cure (High Early Mix) | Foundations | Not Started | 10/29/26 | 11/04/26 | 8.8 | 8.8 |
|
425.0 |
RPL08.INT.DHA.01010 |
RPL08.Interior.DHA - Priority - Install Duct | Early Priority OH MEPF | Not Started | 10/29/26 | 11/04/26 | 6.2 | 6.2 |
|
105.0 |
RPL08.INT.DHB.01010 |
RPL08.Interior.DHB - Priority - Install Duct | Early Priority OH MEPF | Not Started | 10/29/26 | 11/04/26 | 6.2 | 6.2 |
|
105.0 |
RPL08.MCUP.LP2.1420 |
RPL08.MCUP.Loop 2 - Tie-in SD, DW | Tie-ins | Not Started | 10/29/26 | 11/19/26 | 18.8 | 18.8 |
|
472.5 |
RPL08.MCUP.LP2.2060 |
RPL08.MCUP.Loop 2 - Tie-in - Electrical L2 Checklist Completion | Tie-ins | Not Started | 10/29/26 | 11/04/26 | 6.2 | 6.2 |
|
340.0 |
RPL08.EY.ENDC.01030 |
RPL08.EY.End - Install Mechanical UG | Underground | Not Started | 10/30/26 | 11/05/26 | 6.2 | 6.2 |
|
373.8 |
RPL08.EY.SSB.01230 |
RPL08.EY.SSB - Install LD F/R/P Loading Dock Walls | Loading Dock | Not Started | 10/30/26 | 11/10/26 | 10.0 | 10.0 |
|
298.8 |
RPL08.INT.SSB.02680 |
RPL08.Interior.SSB - Priority - Install Layout, Unistruts & Hangers (All Trades) | Priority Walls and OverHead | Not Started | 10/30/26 | 11/13/26 | 12.5 | 12.5 |
|
143.8 |
RPL08.INT.SSBC.06740 |
RPL08.Interior.SSBC - Priority - Frame, Hang Drywall, Tape Finish Paint for SSB Electrical Room | Priority Walls & Overhead | Not Started | 10/30/26 | 11/09/26 | 8.8 | 8.8 |
|
185.0 |
RPL08.MCUP.LP2.1980 |
RPL08.MCUP.Loop 2 - Tie-in BMS #6 | Tie-Ins BMS | Not Started | 11/02/26 | 11/12/26 | 10.0 | 10.0 |
|
327.5 |
RPL08.EY.ENDC.01040 |
RPL08.EY.End - Install BMS UG | Underground | Not Started | 11/03/26 | 11/09/26 | 6.2 | 6.2 |
|
392.5 |
RPL08.INT.SSB.06640 |
RPL08.Interior.SSB - Priority - Install IMP Exterior Inwall Rough-In | Priority Walls and OverHead | Not Started | 11/03/26 | 11/09/26 | 6.2 | 6.2 |
|
143.8 |
RPL08.INT.SSBC.01030 |
RPL08.Interior.SSB-Corridor - Priority - Install Fire Sprinkler (Highside OH space) | Early Priority OH MEPF | Not Started | 11/03/26 | 11/03/26 | 1.2 | 1.2 |
|
140.0 |
RPL08.INT.SSBC.01040 |
RPL08.Interior.SSB-Corridor - Priority - Install Temp Lighting (Show In Model) | Early Priority OH MEPF | Not Started | 11/03/26 | 11/05/26 | 3.8 | 3.8 |
|
140.0 |
RPL08.STR.DHAB.01100 |
RPL08.Structure.DHAB - SOG F/R/P #5 - Grid lines 6-14/6-18 | F/R/P | Not Started | 11/03/26 | 11/09/26 | 6.2 | 6.2 |
|
107.5 |
RPL08.EY.ENDC.1510 |
RPL08.EY.DHD.T1 - Temp Conditioning Startup and Available | Tent 1 | Not Started | 11/04/26 | 11/05/26 | 2.5 | 2.5 |
|
147.5 |
RPL08.EY.ENDC.1810 |
RPL08.EY.DHD.T2 - Temp Conditioning Startup and Available | Tent 2 | Not Started | 11/04/26 | 11/05/26 | 2.5 | 2.5 |
|
160.0 |
RPL08.INT.DHB.01030 |
RPL08.Interior.DHB - Priority - Install Fire Sprinkler | Early Priority OH MEPF | Not Started | 11/04/26 | 11/10/26 | 6.2 | 6.2 |
|
140.0 |
ICM.B8.1212 |
[SSDCB3] Start Flush & Fill of Chilled Water System | Commissioning | Not Started | 11/05/26 | 11/05/26 | 0.0 | 0.0 |
|
225.0 |
RPL08.CX.MCUP.01150 |
RPL08.CX.mCup Loop 1 - L3/L4 - mCUP - Flush and Fill - mCup Yard & FWM - Loop 1 (mCUPs 1-4) (Phase 1) | Fill and Flush | Not Started | 11/05/26 | 11/12/26 | 6.2 | 6.2 |
|
218.8 |
RPL08.INT.CTRC.1180 |
RPL08.Interior.Center-Corridor - Priority - Install Duct (Highside OH space) | Early Priority OH MEPF | Not Started | 11/05/26 | 11/16/26 | 8.8 | 8.8 |
|
288.8 |
RPL08.INT.DHA.01020 |
RPL08.Interior.DHA - Install Priority OH, Walls, OFE and Tie-ins - WBS Summary | DHA | Not Started | 11/05/26 | 06/16/27 | 188.8 | 188.8 |
|
197.5 |
RPL08.INT.DHA.03380 |
RPL08.Interior.DHA - Temp Conditions - Drop Curtains (from Corridor to EJ) | Temp Conditions | Not Started | 11/05/26 | 11/17/26 | 10.0 | 10.0 |
|
105.0 |
RPL08.INT.DHB.01020 |
RPL08.Interior.DHB - Install Priority OH, Walls, OFE and Tie-ins - WBS Summary | DHB | Not Started | 11/05/26 | 06/15/27 | 187.5 | 187.5 |
|
186.2 |
RPL08.INT.DHB.01060 |
RPL08.Interior.DHB - Temp Conditions - Drop Curtains (from Corridor to EJ) | Temp Conditions | Not Started | 11/05/26 | 11/16/26 | 8.8 | 8.8 |
|
106.2 |
RPL08.INT.SSB.02840 |
RPL08.Interior.SSB - Priority - Tape Finish Paint Priority Soffit (Top Out) | Priority Walls and OverHead | Not Started | 11/05/26 | 11/19/26 | 12.5 | 12.5 |
|
210.0 |
RPL08.SKN.DHCD.01000 |
RPL08.SKIN.DHCD - Install Temp Doors | Glazing, Doors and Ext Devices | Not Started | 11/05/26 | 11/06/26 | 2.5 | 2.5 |
|
423.8 |
RPL08.SKN.DHCD.01020 |
RPL08.SKIN.DHCD - Install Windows, Doors, Louvers and Ext Devices - WBS Summary | Glazing, Doors and Ext Devices | Not Started | 11/05/26 | 07/22/27 | 220.0 | 220.0 |
|
236.2 |
RPL08.EY.DHC.01120 |
RPL08.EY.DHC - Install BMS UG | Underground | Not Started | 11/06/26 | 11/20/26 | 12.5 | 12.5 |
|
322.5 |
RPL08.EY.ENDC.01050 |
RPL08.EY.End - Install SD, DW, FW UG | Underground | Not Started | 11/06/26 | 11/20/26 | 12.5 | 12.5 |
|
376.2 |
RPL08.INT.DHB.01040 |
RPL08.Interior.DHB - Priority - Install Temp Lighting | Early Priority OH MEPF | Not Started | 11/06/26 | 11/10/26 | 3.8 | 3.8 |
|
140.0 |
RPL08.INT.SSB.06560 |
RPL08.Interior.SSB - Priority - Install Backing at Exterior Wall | Priority Walls and OverHead | Not Started | 11/06/26 | 11/13/26 | 6.2 | 6.2 |
|
143.8 |
ICM.B8.1855 |
[SSDCB3] Delivery of MES - Multi Trade Rack (First Delivery) | Construction | Not Started | 11/09/26 | 11/09/26 | 0.0 | 0.0 |
|
171.2 |
RPL08.MCUP.LP1.2040 |
RPL08.MCUP.Loop 1 - Install Mcup Paving | Hardscape and Landscape | Not Started | 11/09/26 | 11/23/26 | 12.5 | 12.5 |
|
505.0 |
RPL08.SKN.DHCD.01140 |
RPL08.SKIN.DHCD - Install Blocking of Canopy & Backing of Exterior Wall | Glazing, Doors and Ext Devices | Not Started | 11/09/26 | 11/16/26 | 6.2 | 6.2 |
|
423.8 |
RPL08.CFCI.5290 |
RPL08 - Fabricate / Deliver - Carpet Tile | (CFCI) Div. 09 - Carpet | Not Started | 11/10/26 | 01/11/27 | 50.0 | 50.0 |
|
298.8 |
RPL08.INT.SSBC.03500 |
RPL08.Interior.SSBC - Priority - Install Drywall at Exterior Walls | Priority Walls & Overhead | Not Started | 11/10/26 | 11/13/26 | 3.8 | 3.8 |
|
152.5 |
RPL08.STR.DHAB.01140 |
RPL08.Structure.DHAB - Zone SOG Cure | F/R/P | Not Started | 11/10/26 | 11/16/26 | 8.8 | 8.8 |
|
161.2 |
RPL08.STR.DHCD.01110 |
RPL08.Structure.DHCD - SOG F/R/P - WBS Summary | F/R/P | Not Started | 11/10/26 | 12/19/26 | 32.5 | 32.5 |
|
178.8 |
RPL08.STR.DHCD.01120 |
RPL08.Structure.DHCD - SOG F/R/P #6 - Grid lines 6-18/6-21 | F/R/P | Not Started | 11/10/26 | 11/17/26 | 6.2 | 6.2 |
|
118.8 |
GCD.RPL08.1020 |
Weather tight SSB and DHA&B | Construction Milestones | Not Started | 11/12/26 | 11/12/26 | 0.0 | 0.0 |
|
378.8 |
RPL08.INT.DHA.01030 |
RPL08.Interior.DHA - Priority - Install Fire Sprinkler | Early Priority OH MEPF | Not Started | 11/12/26 | 11/18/26 | 6.2 | 6.2 |
|
213.8 |
RPL08.INT.DHA.01040 |
RPL08.Interior.DHA - Priority - Install Temp Lighting | Early Priority OH MEPF | Not Started | 11/12/26 | 11/16/26 | 3.8 | 3.8 |
|
221.2 |
DCC.B8.3125 |
[SSDCB3] GS Gear Delivered [DHB] | Connectivity | Not Started | 11/13/26 | 11/13/26 | 0.0 | 0.0 |
|
526.2 |
RPL08.CON.WP2.08560 |
RPL08.Conn - Ext. GSIDF8X04 - Install Copper, WAPs, Security Camera & Access Control (EY-DH C) | Cabling | Not Started | 11/13/26 | 12/02/26 | 15.0 | 15.0 |
|
355.0 |
RPL08.CX.MCUP.01190 |
RPL08.CX.mCup Loop 1 - L3/L4 - mCUP - Flush and Fill - mCup1 and Dry Coolers | Fill and Flush | Not Started | 11/13/26 | 11/20/26 | 7.5 | 7.5 |
|
218.8 |
RPL08.CX.MCUP.01210 |
RPL08.CX.mCup Loop 1 - L3/L4 - mCUP - Flush and Fill - mCup2 and Dry Coolers | Fill and Flush | Not Started | 11/13/26 | 11/20/26 | 7.5 | 7.5 |
|
218.8 |
RPL08.INT.DHB.01090 |
RPL08.Interior.DHB - Temp Conditions - Install Early Temp Conditions | Temp Conditions | Not Started | 11/13/26 | 11/16/26 | 2.5 | 2.5 |
|
106.2 |
RPL08.INT.SSBC.03280 |
RPL08.Interior.SSBC - Priority GL8.04 - (P0) Frame Walls (All full height Walls) | Priority Wall Grid Line 8-04 | Not Started | 11/13/26 | 11/19/26 | 6.2 | 6.2 |
|
152.5 |
RPL08.MCUP.LP2.2080 |
RPL08.MCUP.Loop 2 - Tie-in - Mechanical L2 Checklist Completion | Tie-ins | Not Started | 11/13/26 | 11/19/26 | 6.2 | 6.2 |
|
327.5 |
RPL08.SKN.DHAB.01130 |
RPL08.SKIN.DHAB - Install Roof System - Install EJ | Roofing | Not Started | 11/13/26 | 11/16/26 | 2.5 | 2.5 |
|
206.2 |
RPL08.SKN.DHCD.01110 |
RPL08.SKIN.DHCD - Install Roof System - Final Roof | Roofing | Not Started | 11/13/26 | 12/02/26 | 15.0 | 15.0 |
|
472.5 |
RPL08.INT.DHA.03400 |
RPL08.Interior.DHA - Temp Conditions - Install Early Temp Conditions | Temp Conditions | Not Started | 11/16/26 | 11/17/26 | 2.5 | 2.5 |
|
105.0 |
RPL08.INT.SSB.06580 |
RPL08.Interior.SSB - Priority - QC - Backings/Walls | Priority Walls and OverHead | Not Started | 11/16/26 | 11/20/26 | 6.2 | 6.2 |
|
143.8 |
RPL08.INT.SSBC.03260 |
RPL08.Interior.SSBC - Priority - Tape Finish Paint Priority Soffit both sides (Top Out) | Priority Walls & Overhead | Not Started | 11/16/26 | 11/20/26 | 6.2 | 6.2 |
|
175.0 |
ICM.B8.1845 |
[SSDCB3] Delivery of FSHAC - Hot Aisle Containment (First Delivery) | Construction | Not Started | 11/17/26 | 11/17/26 | 0.0 | 0.0 |
|
150.0 |
RPL08.INT.DHB.02360 |
RPL08.Interior.DHB - Temp Conditions - CC West Duct Work Complete for Temp Conditioning (LVs) | Temp Conditions | Not Started | 11/17/26 | 11/18/26 | 2.5 | 2.5 |
|
106.2 |
RPL08.SKN.DHCD.01030 |
RPL08.SKIN.DHCD - Install Awning over Doors | Glazing, Doors and Ext Devices | Not Started | 11/17/26 | 11/23/26 | 6.2 | 6.2 |
|
423.8 |
RPL08.STR.DHAB.01240 |
RPL08.Structure.DHAB - Moisture requirements for floor Sealer | F/R/P | Not Started | 11/17/26 | 11/23/26 | 8.8 | 8.8 |
|
161.2 |
RPL08.INT.DHA.03420 |
RPL08.Interior.DHA - Temp Conditions - CC West Duct Work Complete for Temp Conditioning (LVs) | Temp Conditions | Not Started | 11/18/26 | 11/19/26 | 2.5 | 2.5 |
|
105.0 |
RPL08.INT.DHB.01000 |
RPL08.Interior.DHB - Priority OH - WBS Summary | OverHead | Not Started | 11/18/26 | 12/30/26 | 35.0 | 35.0 |
|
115.0 |
RPL08.INT.DHB.02100 |
RPL08.Interior.DHB - Priority - Install Mechanical Piping | OverHead | Not Started | 11/18/26 | 12/10/26 | 18.8 | 18.8 |
|
118.8 |
RPL08.INT.SSBC.06660 |
RPL08.Interior.SSBC - Priority GL8.04 - (P0) Install MEP In-Wall/Backing | Priority Wall Grid Line 8-04 | Not Started | 11/18/26 | 11/23/26 | 5.0 | 5.0 |
|
152.5 |
RPL08.STR.DHCD.01130 |
RPL08.Structure.DHCD - SOG F/R/P #7 - Grid lines 6-21/6-25 | F/R/P | Not Started | 11/18/26 | 11/24/26 | 6.2 | 6.2 |
|
118.8 |
RPL08.INT.CTRC.1040 |
RPL08.Interior.Center-Corridor - Priority - Install Fire Sprinkler (Highside OH space) | Early Priority OH MEPF | Not Started | 11/19/26 | 11/23/26 | 3.8 | 3.8 |
|
213.8 |
RPL08.INT.CTRC.1060 |
RPL08.Interior.Center-Corridor - Priority - Install Temp Lighting (Show In Model) | Early Priority OH MEPF | Not Started | 11/19/26 | 11/23/26 | 3.8 | 3.8 |
|
218.8 |
GCD.RPL08.3985 |
MCUP Ready for Energization - (MCUPs Loop 2) | mCup | Not Started | 11/20/26 | 11/20/26 | 0.0 | 0.0 |
|
435.0 |
ICM.B8.1750 |
[SSDCB3] Room Ready for GS.MDF Module Placement | Construction | Not Started | 11/20/26 | 11/20/26 | 0.0 | 0.0 |
|
175.0 |
RPL08.CX.MCUP.01020 |
RPL08.CX.mCup Loop 2 - L3, L4, IST - WBS Summary | mCUP 5-6 | Not Started | 11/20/26 | 07/07/27 | 193.8 | 193.8 |
|
287.5 |
RPL08.CX.MCUP.01100 |
RPL08.CX.mCup Loop 2 - L3/L4 - mCUP - Flush and Fill - mCup Yard - Loop 2 (mCUPs 5-6) (Phase 3) | Fill and Flush | Not Started | 11/20/26 | 11/30/26 | 6.2 | 6.2 |
|
357.5 |
RPL08.INT.DHA.03460 |
RPL08.Interior.DHA - Temp Conditions - Temp Conditioning Achieved & Acclimated for West of CC (SSB/DHB/DHA) | Temp Conditions | Not Started | 11/20/26 | 11/30/26 | 6.2 | 6.2 |
|
105.0 |
RPL08.INT.SSBC.06640 |
RPL08.Interior.SSBC - Priority GL8.04 - (P0) Install IMP Wall | Priority Wall Grid Line 8-04 | Not Started | 11/20/26 | 11/25/26 | 5.0 | 5.0 |
|
171.2 |
RPL08.INT.SSBC.06680 |
RPL08.Interior.SSBC - Priority GL8.04 - (P0) Hang Drywall (Both SIdes) | Priority Wall Grid Line 8-04 | Not Started | 11/20/26 | 11/25/26 | 5.0 | 5.0 |
|
152.5 |
RPL08.MCUP.LP2.1520 |
RPL08.MCUP.Loop 2 - Install Hardscape and Landscape - WBS Summary | Hardscape and Landscape | Not Started | 11/20/26 | 01/19/27 | 47.5 | 47.5 |
|
472.5 |
RPL08.MCUP.LP2.1540 |
RPL08.MCUP.Loop 2 - Install Sleeves MEPL | Hardscape and Landscape | Not Started | 11/20/26 | 11/24/26 | 3.8 | 3.8 |
|
472.5 |
RPL08.CX.MCUP.01230 |
RPL08.CX.mCup Loop 1 - L3/L4 - mCUP - Flush and Fill - mCup3 and Dry Coolers | Fill and Flush | Not Started | 11/23/26 | 12/02/26 | 7.5 | 7.5 |
|
218.8 |
RPL08.CX.MCUP.01250 |
RPL08.CX.mCup Loop 1 - L3/L4 - mCUP - Flush and Fill - mCup4 and Dry Coolers | Fill and Flush | Not Started | 11/23/26 | 12/02/26 | 7.5 | 7.5 |
|
221.2 |
RPL08.INT.SSB.06540 |
RPL08.Interior.SSB - Priority - Install Drywall at Exterior Walls | Priority Walls and OverHead | Not Started | 11/23/26 | 12/08/26 | 12.5 | 12.5 |
|
143.8 |
RPL08.INT.DHA.01000 |
RPL08.Interior.DHA - Priority OH - WBS Summary | OverHead | Not Started | 11/24/26 | 02/02/27 | 57.5 | 57.5 |
|
313.8 |
RPL08.INT.DHA.01980 |
RPL08.Interior.DHA - Priority - Install Unistruts & Hangers (All Trades) | OverHead | Not Started | 11/24/26 | 12/02/26 | 6.2 | 6.2 |
|
117.5 |