Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL08 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:14 PM
· 5122 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
0
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL08.INT.DHA.02400 |
RPL08.Interior.DHA - Priority - IMP Exterior Inwall Rough-In | OverHead | Not Started | 11/24/26 | 12/02/26 | 6.2 | 6.2 |
|
117.5 |
RPL08.INT.DHB.02140 |
RPL08.Interior.DHB - Priority - Install Unistruts & Hangers (All Trades) | OverHead | Not Started | 11/24/26 | 12/02/26 | 6.2 | 6.2 |
|
107.5 |
RPL08.INT.DHB.02340 |
RPL08.Interior.DHB - Priority - Install IMP Exterior Inwall Rough-In (These walls available early) | OverHead | Not Started | 11/24/26 | 12/02/26 | 6.2 | 6.2 |
|
107.5 |
RPL08.INT.DHD.01030 |
RPL08.Interior.DHD - Priority - Install Fire Sprinkler | Early Priority OH MEPF | Not Started | 11/24/26 | 12/02/26 | 6.2 | 6.2 |
|
213.8 |
RPL08.INT.DHD.01040 |
RPL08.Interior.DHD - Priority - Install Temp Lighting | Early Priority OH MEPF | Not Started | 11/24/26 | 11/30/26 | 3.8 | 3.8 |
|
218.8 |
RPL08.MCUP.LP1.2100 |
RPL08.MCUP.Loop 1 - Install Exterior Signage | Hardscape and Landscape | Not Started | 11/24/26 | 12/09/26 | 12.5 | 12.5 |
|
505.0 |
RPL08.SKN.DHCD.01040 |
RPL08.SKIN.DHCD - Install Louvers | Glazing, Doors and Ext Devices | Not Started | 11/24/26 | 12/02/26 | 6.2 | 6.2 |
|
423.8 |
RPL08.SKN.DHCD.01100 |
RPL08.SKIN.DHCD - Install Scupper and Downspouts | Glazing, Doors and Ext Devices | Not Started | 11/24/26 | 12/02/26 | 6.2 | 6.2 |
|
435.0 |
RPL08.STR.DHAB.01260 |
RPL08.Structure.DHAB - Install SOG Sealer and Cure | F/R/P | Not Started | 11/24/26 | 11/25/26 | 2.5 | 2.5 |
|
181.2 |
ICM.B8.1865 |
[SSDCB3] Delivery of MDF GS.MDF Module (First Delivery) | Construction | Not Started | 11/25/26 | 11/25/26 | 0.0 | 0.0 |
|
171.2 |
RPL08.INT.CTRC.01020 |
RPL08.Interior.Center-Corridor - Install Priority OH, Walls, OFE and Fitout - WBS Summary | Center Corridor | Not Started | 11/25/26 | 07/09/27 | 192.5 | 192.5 |
|
158.8 |
RPL08.INT.CTRC.03460 |
RPL08.Interior.Center-Corridor - Priority - Priority - WBS Summary | Priority Walls & Overhead | Not Started | 11/25/26 | 02/12/27 | 66.2 | 66.2 |
|
185.0 |
RPL08.INT.CTRC.1020 |
RPL08.Interior.Center-Corridor - Priority - Install Priority Soffit for Wall Tie-Ins/ Rock & HoW & Draft Blanket | Priority Walls & Overhead | Not Started | 11/25/26 | 12/03/26 | 6.2 | 6.2 |
|
118.8 |
RPL08.INT.CTRC.7740 |
RPL08.Interior.Center-Corridor - Priority - Install IMP Exterior Inwall Rough-In | Priority Walls & Overhead | Not Started | 11/25/26 | 12/03/26 | 6.2 | 6.2 |
|
125.0 |
RPL08.INT.SSB.01050 |
RPL08.Interior.SSB - Priority - (P1) Frame Walls (Frame full height Walls) | Priority Wall - P1 | Not Started | 11/25/26 | 12/03/26 | 6.2 | 6.2 |
|
196.2 |
RPL08.INT.SSB.06840 |
RPL08.Interior.SSB - Priority - (P1) Frame Remaining Walls | Priority Wall - P1 | Not Started | 11/25/26 | 12/01/26 | 3.8 | 3.8 |
|
238.8 |
RPL08.MCUP.LP2.1640 |
RPL08.MCUP.Loop 2 - Install Early Mcup Paving | Hardscape and Landscape | Not Started | 11/25/26 | 12/10/26 | 12.5 | 12.5 |
|
472.5 |
RPL08.STR.DHCD.01140 |
RPL08.Structure.DHCD - SOG F/R/P #8 - Grid lines 6-25/6-28 | F/R/P | Not Started | 11/25/26 | 12/03/26 | 6.2 | 6.2 |
|
156.2 |
RPL08.INT.SSBC.01090 |
RPL08.Interior.SSB-Corridor - OFE - Early Equipment (1x GS.MDF piece 1 of 2) | OFE/MOFE & CFCI | Not Started | 11/30/26 | 12/04/26 | 6.2 | 6.2 |
|
171.2 |
RPL08.INT.SSBC.06700 |
RPL08.Interior.SSBC - Priority GL8.04 - (P0) Tape Finish Paint (Both SIdes) | Priority Wall Grid Line 8-04 | Not Started | 11/30/26 | 12/04/26 | 6.2 | 6.2 |
|
152.5 |
ICM.B8.1840 |
[SSDCB3] Delivery of DES - Data Hall Electrical Room Skid (First Delivery) | Construction | Not Started | 12/01/26 | 12/01/26 | 0.0 | 0.0 |
|
168.8 |
RPL08.EY.SSB.01160 |
RPL08.EY.SSB - Install Electrical Tie-ins (include penetration detail) | Tie-ins | Not Started | 12/01/26 | 12/29/26 | 25.0 | 25.0 |
|
140.0 |
RPL08.EY.SSB.01170 |
RPL08.EY.SSB - Install Mechanical Main (include penetration detail) | Tie-ins | Not Started | 12/01/26 | 12/21/26 | 18.8 | 18.8 |
|
133.8 |
RPL08.INT.DHA.03440 |
RPL08.Interior.DHA - Priority - Install Backing at Exterior Wall | OverHead | Not Started | 12/01/26 | 12/02/26 | 2.5 | 2.5 |
|
117.5 |
RPL08.INT.DHB.02380 |
RPL08.Interior.DHB - Priority - Install Backing at Exterior Wall | OverHead | Not Started | 12/01/26 | 12/02/26 | 2.5 | 2.5 |
|
107.5 |
RPL08.WA.OFE.01000 |
RPL08.WA - Weather Allowance - FDN to OFE | Weather Allowance | Not Started | 12/01/26 | 12/16/26 | 20.0 | 20.0 |
|
155.0 |
RPL08.CON.WP2.09200 |
RPL08.Conn - CorpNet & FacNet Available (South EY) - All IDFs | WP#02 GS | Not Started | 12/02/26 | 12/02/26 | 0.0 | 0.0 |
|
511.2 |
RPL08.Conn.MS.01100 |
RPL08.Conn Wifi Ready - South EY (Pred from RPL10 CorpNet needed?) | Connectivity Milestones | Not Started | 12/02/26 | 12/02/26 | 0.0 | 0.0 |
|
355.0 |
RPL08.INT.SSB.01660 |
RPL08.Interior.SSB - Priority - Install Plumbing (Highside OH space) | Priority Walls and OverHead | Not Started | 12/02/26 | 12/08/26 | 6.2 | 6.2 |
|
143.8 |
RPL08.INT.SSB.01680 |
RPL08.Interior.SSB - Priority - Install Mechanical Piping/ Refrigerant (Highside OH space) | Priority Walls and OverHead | Not Started | 12/02/26 | 12/08/26 | 6.2 | 6.2 |
|
143.8 |
RPL08.INT.SSB.03200 |
RPL08.Interior.SSB - Priority - Install Fire Alarm hangers & members (Highside OH space) | Priority Walls and OverHead | Not Started | 12/02/26 | 12/08/26 | 6.2 | 6.2 |
|
331.2 |
RPL08.INT.SSB.06880 |
RPL08.Interior.SSB - Priority - (P1) Install Remaining MEP In-Wall/Backing | Priority Wall - P1 | Not Started | 12/02/26 | 12/03/26 | 2.5 | 2.5 |
|
238.8 |
RPL08.INT.SSBC.01060 |
RPL08.Interior.SSB-Corridor - OFE - Early Equipment (1x SSB Elect) | OFE/MOFE & CFCI | Not Started | 12/02/26 | 12/15/26 | 12.5 | 12.5 |
|
168.8 |
GCD.RPL08.1280 |
Interior fit-out Start RPL08 - DHA&B | Construction Milestones | Not Started | 12/03/26 | 12/03/26 | 0.0 | 0.0 |
|
363.8 |
RPL08.EY.SSB.01240 |
RPL08.EY.SSB - Install BMS/EPMS Tie-ins | Tie-ins | Not Started | 12/03/26 | 12/23/26 | 18.8 | 18.8 |
|
143.8 |
RPL08.INT.DHA.02380 |
RPL08.Interior.DHA - Priority - Install Drywall at Exterior Walls | OverHead | Not Started | 12/03/26 | 12/11/26 | 8.8 | 8.8 |
|
117.5 |
RPL08.INT.DHB.02320 |
RPL08.Interior.DHB - Priority - Install Drywall at Exterior Walls | OverHead | Not Started | 12/03/26 | 12/11/26 | 8.8 | 8.8 |
|
107.5 |
RPL08.INT.DHC.01030 |
RPL08.Interior.DHC - Priority - Install Fire Sprinkler | Early Priority OH MEPF | Not Started | 12/03/26 | 12/09/26 | 6.2 | 6.2 |
|
213.8 |
RPL08.SKN.DHCD.01050 |
RPL08.SKIN.DHCD - Install Lighting | Glazing, Doors and Ext Devices | Not Started | 12/03/26 | 12/08/26 | 5.0 | 5.0 |
|
423.8 |
RPL08.INT.CTRC.1000 |
RPL08.Interior.Center-Corridor - Priority - Install Unistruts & Hangers (All Trades) Both side of Corridor Wall | Priority Walls & Overhead | Not Started | 12/04/26 | 12/10/26 | 6.2 | 6.2 |
|
118.8 |
RPL08.INT.SSB.01170 |
RPL08.Interior.SSB - Loading Dock and Storage - WBS Summary | Loading Dock and Storage | Not Started | 12/04/26 | 05/19/27 | 142.5 | 142.5 |
|
206.2 |
RPL08.INT.SSB.02900 |
RPL08.Interior.SSB - Loading Dock and Storage - Pre Priority OH & Walls Tasks (Unistruts,Hangers,Track) | Loading Dock and Storage | Not Started | 12/04/26 | 12/10/26 | 6.2 | 6.2 |
|
206.2 |
RPL08.INT.SSB.06780 |
RPL08.Interior.SSB - Priority - (P1) Install MEP In-Wall/Backing | Priority Wall - P1 | Not Started | 12/04/26 | 12/09/26 | 5.0 | 5.0 |
|
232.5 |
RPL08.INT.SSB.06860 |
RPL08.Interior.SSB - Priority - (P1) Remaining Wall Hang Drywall (Both Sides) | Priority Wall - P1 | Not Started | 12/04/26 | 12/08/26 | 3.8 | 3.8 |
|
238.8 |
RPL08.STR.DHCD.01150 |
RPL08.Structure.DHCD - Zone SOG Cure | F/R/P | Not Started | 12/04/26 | 12/10/26 | 8.8 | 8.8 |
|
231.2 |
GCD.RPL08.1826 |
Delivery of RMU - (First Delivery) - RPL08 - DHA&B | Construction Milestones | Not Started | 12/07/26 | 12/07/26 | 0.0 | 0.0 |
|
118.8 |
ICM.B8.1825 |
[SSDCB3] Delivery of MVS - Medium Voltage Switches (First Delivery) | Construction | Not Started | 12/07/26 | 12/07/26 | 0.0 | 0.0 |
|
118.8 |
RPL08.CON.WP2.04000 |
RPL08.Conn - GSMDF2 (North) - WBS Summary | GS.MDF2 (North) | Not Started | 12/07/26 | 05/03/27 | 126.2 | 126.2 |
|
320.0 |
RPL08.CON.WP2.07880 |
RPL08.Conn - GSMDF2 (North) Set Infrastructure (Wall mounting enclosures, Tier1 Basket Tray, Waterfalls etc.) | Infrastructure | Not Started | 12/07/26 | 12/09/26 | 3.8 | 3.8 |
|
321.2 |
RPL08.INT.DHB.01050 |
RPL08.Interior.DHB - Priority - Install FA / Linear heat detection | OverHead | Not Started | 12/07/26 | 12/11/26 | 6.2 | 6.2 |
|
107.5 |
RPL08.INT.DHB.02300 |
RPL08.Interior.DHB - Priority - Install Electrical | OverHead | Not Started | 12/07/26 | 12/28/26 | 18.8 | 18.8 |
|
107.5 |
RPL08.INT.DHC.01040 |
RPL08.Interior.DHC - Priority - Install Temp Lighting | Early Priority OH MEPF | Not Started | 12/07/26 | 12/09/26 | 3.8 | 3.8 |
|
213.8 |
RPL08.INT.SSBC.01140 |
RPL08.Interior.SSB-Corridor - OFE - Early Equipment (1x GS.MDF piece 2 of 2) | OFE/MOFE & CFCI | Not Started | 12/07/26 | 12/11/26 | 6.2 | 6.2 |
|
171.2 |
RPL08.INT.SSBC.3000 |
RPL08.Interior.SSBC LO #06 - Close Interior Leave Out #06 SSB/SSBC (For MDF2) WBS Summary | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 12/07/26 | 02/23/27 | 66.2 | 66.2 |
|
197.5 |
RPL08.INT.SSBC.3020 |
RPL08.Interior.SSBC LO #06 - Install Framing at LO | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 12/07/26 | 12/11/26 | 6.2 | 6.2 |
|
197.5 |
RPL08.INT.DHC.01010 |
RPL08.Interior.DHC - Priority - Install Duct | Early Priority OH MEPF | Not Started | 12/08/26 | 12/11/26 | 5.0 | 5.0 |
|
272.5 |
RPL08.INT.DHD.01010 |
RPL08.Interior.DHD - Priority - Install Duct | Early Priority OH MEPF | Not Started | 12/08/26 | 12/14/26 | 5.0 | 5.0 |
|
272.5 |
RPL08.INT.SSB.03220 |
RPL08.Interior.SSB - Priority - Install Fire Safing/ Seal all Penetrations through Soffit (Highside OH space) | Priority Walls and OverHead | Not Started | 12/09/26 | 12/15/26 | 6.2 | 6.2 |
|
186.2 |
RPL08.INT.SSB.06900 |
RPL08.Interior.SSB - Priority - (P1) Remaining Wall Tape Finish Paint (Both Sides) | Priority Wall - P1 | Not Started | 12/09/26 | 12/15/26 | 6.2 | 6.2 |
|
238.8 |
RPL08.INT.SSBC.02180 |
RPL08.Interior.SSBC - Priority - Install Plumbing (Highside OH space) | Priority Walls & Overhead | Not Started | 12/09/26 | 12/15/26 | 6.2 | 6.2 |
|
143.8 |
RPL08.INT.SSBC.02200 |
RPL08.Interior.SSBC - Priority - Install Mechanical Piping/ Refrigerant (Highside OH space) | Priority Walls & Overhead | Not Started | 12/09/26 | 12/15/26 | 6.2 | 6.2 |
|
143.8 |
RPL08.INT.SSBC.03300 |
RPL08.Interior.SSBC - Priority - Install FA/ VESDA/ hangers & Heat Trace (Highside OH space) | Priority Walls & Overhead | Not Started | 12/09/26 | 12/15/26 | 6.2 | 6.2 |
|
143.8 |
RPL08.SKN.DHCD.01060 |
RPL08.SKIN.DHCD - Install Security | Glazing, Doors and Ext Devices | Not Started | 12/09/26 | 12/10/26 | 2.5 | 2.5 |
|
423.8 |
RPL08.CON.WP2.09240 |
RPL08.Conn - GSMDF2 (North) - Install Copper, WAPs, Security Camera & Access Control | ISP (MDF RPL08 <> MDF RPL08) | Not Started | 12/10/26 | 12/28/26 | 15.0 | 15.0 |
|
321.2 |
RPL08.INT.ENDC.1040 |
RPL08.Interior.End-Corridor - Priority - Install Fire Sprinkler (Highside OH space) | Early Priority OH MEPF | Not Started | 12/10/26 | 12/14/26 | 3.8 | 3.8 |
|
213.8 |
RPL08.INT.ENDC.1060 |
RPL08.Interior.End-Corridor - Priority - Install Temp Lighting (Show In Model) | Early Priority OH MEPF | Not Started | 12/10/26 | 12/14/26 | 3.8 | 3.8 |
|
213.8 |
RPL08.INT.SSB.06800 |
RPL08.Interior.SSB - Priority - (P1) Hang Drywall (Both Sides) | Priority Wall - P1 | Not Started | 12/10/26 | 12/15/26 | 5.0 | 5.0 |
|
232.5 |
RPL08.INT.CTRC.1920 |
RPL08.Interior.Center-Corridor - Priority - Install Drywall at Exterior Walls | Priority Walls & Overhead | Not Started | 12/11/26 | 12/17/26 | 6.2 | 6.2 |
|
118.8 |
RPL08.INT.SSB.01140 |
RPL08.Interior.SSB - Loading Dock and Storage - Frame Walls | Loading Dock and Storage | Not Started | 12/11/26 | 12/22/26 | 10.0 | 10.0 |
|
206.2 |
RPL08.MCUP.LP2.1760 |
RPL08.MCUP.Loop 2 - Install Lighting | Hardscape and Landscape | Not Started | 12/11/26 | 12/17/26 | 6.2 | 6.2 |
|
472.5 |
RPL08.STR.DHCD.01210 |
RPL08.Structure.DHCD - Moisture requirements for floor Sealer | F/R/P | Not Started | 12/11/26 | 12/17/26 | 8.8 | 8.8 |
|
231.2 |
RPL08.CON.WP2.05000 |
RPL08.Conn - GSMDF1 (South) - WBS Summary | GS.MDF1 (South) | Not Started | 12/14/26 | 05/03/27 | 120.0 | 120.0 |
|
320.0 |
RPL08.CON.WP2.07960 |
RPL08.Conn - GSMDF1 (South) Set Infrastructure (Wall mounting enclosures, Tier1 Basket Tray, Waterfalls etc.) | Infrastructure | Not Started | 12/14/26 | 12/16/26 | 3.8 | 3.8 |
|
327.5 |
RPL08.CON.WP4.00010 |
RPL08.Conn - Network - WBS Summary | WP#4 Network | Not Started | 12/14/26 | 10/22/27 | 271.2 | 271.2 |
|
231.2 |
RPL08.INT.DHA.02140 |
RPL08.Interior.DHA - Priority - Install Plumbing | OverHead | Not Started | 12/14/26 | 12/18/26 | 6.2 | 6.2 |
|
117.5 |
RPL08.INT.DHA.02160 |
RPL08.Interior.DHA - Priority - Install Mechanical Piping | OverHead | Not Started | 12/14/26 | 01/05/27 | 18.8 | 18.8 |
|
117.5 |
RPL08.INT.DHB.01100 |
RPL08.Interior.DHB - Priority - Install Temp Doors Frame Hardware | OverHead | Not Started | 12/14/26 | 12/16/26 | 3.8 | 3.8 |
|
115.0 |
RPL08.INT.ENDC.1180 |
RPL08.Interior.End-Corridor - Priority - Install Duct (Highside OH space) | Early Priority OH MEPF | Not Started | 12/14/26 | 12/22/26 | 8.8 | 8.8 |
|
272.5 |
RPL08.INT.SSBC.3080 |
RPL08.Interior.SSBC LO #06 - Install Mechanical Piping Lowside OH and in-wall | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 12/14/26 | 12/15/26 | 2.5 | 2.5 |
|
197.5 |
RPL08.INT.SSBC.4000 |
RPL08.Interior.SSBC LO #07 - Close Interior LO #07 SSB/SSBC (For MDF1) WBS Summary | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 12/14/26 | 03/02/27 | 66.2 | 66.2 |
|
191.2 |
RPL08.INT.SSBC.4020 |
RPL08.Interior.SSBC LO #07 - Install Framing at LO | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 12/14/26 | 12/18/26 | 6.2 | 6.2 |
|
191.2 |
RPL08.WP4.010000 |
RPL08.Conn GSMDF1 Pull Fanout (5F) [PON (Active, In-Row)] | GSMDF1 | Not Started | 12/14/26 | 12/14/26 | 1.2 | 1.2 |
|
321.2 |
RPL08.INT.CTRC.1100 |
RPL08.Interior.Center-Corridor - Priority - Tape Finish Paint Priority Soffit both sides (Top Out) | Priority Walls & Overhead | Not Started | 12/15/26 | 12/23/26 | 8.8 | 8.8 |
|
118.8 |
RPL08.WP4.010020 |
RPL08.Conn GSMDF2 Pull Fanout (5F) [PON (Active, In-Row)] | GSMDF2 | Not Started | 12/15/26 | 12/15/26 | 1.2 | 1.2 |
|
321.2 |
RPL08.WP4.010040 |
RPL08.Conn GSMDF1 Install Fanout (5F) [PON (Active, In-Row)] | GSMDF1 | Not Started | 12/15/26 | 12/30/26 | 13.8 | 13.8 |
|
322.5 |
RPL08.INT.SBC.03240 |
RPL08.Interior.SSB-Corridor - Frame Balance of Wall | Balance of Walls & Overhead | Not Started | 12/16/26 | 12/22/26 | 6.2 | 6.2 |
|
143.8 |
RPL08.INT.SBC.03260 |
RPL08.Interior.SSB-Corridor - Balace Of Wall (ERAD, Maintance, Network infra, Spoke, Bathroom, etc) - WBS Summary | Balance of Walls & Overhead | Not Started | 12/16/26 | 06/07/27 | 147.5 | 147.5 |
|
143.8 |
RPL08.INT.SSB.01150 |
RPL08.Interior.SSB - BoW - BoW - Framing Balance of Wall | Balance of Walls and OverHead | Not Started | 12/16/26 | 12/22/26 | 6.2 | 6.2 |
|
186.2 |
RPL08.INT.SSB.01160 |
RPL08.Interior.SSB - BoW - Balace Of Wall (ERAD, Maintance, Network infra, Spoke, Bathroom, etc) - WBS Summary | Balance of Walls and OverHead | Not Started | 12/16/26 | 06/11/27 | 152.5 | 152.5 |
|
186.2 |
RPL08.INT.SSB.01880 |
RPL08.Interior.SSB - Final Finishes & Fixtures - Frame/Blocking Walls & Ceilings | Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) | Not Started | 12/16/26 | 12/30/26 | 12.5 | 12.5 |
|
316.2 |
RPL08.INT.SSB.06820 |
RPL08.Interior.SSB - Priority - (P1) Tape Finish Paint (Both Sides) | Priority Wall - P1 | Not Started | 12/16/26 | 12/22/26 | 6.2 | 6.2 |
|
232.5 |
RPL08.INT.SSB.14000 |
RPL08.Interior.Center-Corridor Leave Out #01 #02 #03 #04 #5 - SSB (for Elec. Room) WBS Summary | Interior Leave Out Wall #01, #02, #03, #04, #05 SSB for Electrical Room | Not Started | 12/16/26 | 04/30/27 | 116.2 | 116.2 |
|
172.5 |
RPL08.INT.SSB.14020 |
RPL08.Interior.SSB LO #01 to #05 - Install LO Framing | OH & Framing | Not Started | 12/16/26 | 12/22/26 | 6.2 | 6.2 |
|
172.5 |
RPL08.INT.SSBC.03320 |
RPL08.Interior.SSBC - Priority - Install Fire Safing/ Seal Penetrations through Soffit (Highside OH space) | Priority Walls & Overhead | Not Started | 12/16/26 | 12/18/26 | 3.8 | 3.8 |
|
143.8 |
RPL08.INT.SSBC.03340 |
RPL08.Interior.SSBC - Priority - Fixed Draft/Smoke Curtain Patching | Priority Walls & Overhead | Not Started | 12/16/26 | 12/18/26 | 3.8 | 3.8 |
|
143.8 |
RPL08.INT.SSBC.3100 |
RPL08.Interior.SSBC LO #06 - Install Fire Life Safety Lowside OH and In-wall | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 12/16/26 | 12/17/26 | 2.5 | 2.5 |
|
201.2 |
RPL08.INT.SSBC.3120 |
RPL08.Interior.SSBC LO #06 - Install Plumbing Lowside OH and In-wall | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 12/16/26 | 12/17/26 | 2.5 | 2.5 |
|
197.5 |
RPL08.SKN.W.LO.01120 |
RPL08.SKIN.LO#16 - Close Exterior Leave Out #16 SSB (North of Loading Dock) WBS Summary | Build back Exterior Leave Out Walls #16 (SSB - North of Loading Dock) | Not Started | 12/16/26 | 02/02/27 | 40.0 | 40.0 |
|
168.8 |
RPL08.SKN.W.LO.01380 |
RPL08.SKIN.LO#16 - Pour back Stemwall | Build back Exterior Leave Out Walls #16 (SSB - North of Loading Dock) | Not Started | 12/16/26 | 12/22/26 | 6.2 | 6.2 |
|
168.8 |
RPL08.WP4.010060 |
RPL08.Conn GSMDF2 Install Fanout (5F) [PON (Active, In-Row)] | GSMDF2 | Not Started | 12/16/26 | 12/31/26 | 13.8 | 13.8 |
|
321.2 |