Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL08 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:14 PM · 5122 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
0
Completed
0
In Progress
0
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL08.INT.DHA.02400 RPL08.Interior.DHA - Priority - IMP Exterior Inwall Rough-In OverHead Not Started 11/24/26 12/02/26 6.2 6.2
0%
117.5
RPL08.INT.DHB.02140 RPL08.Interior.DHB - Priority - Install Unistruts & Hangers (All Trades) OverHead Not Started 11/24/26 12/02/26 6.2 6.2
0%
107.5
RPL08.INT.DHB.02340 RPL08.Interior.DHB - Priority - Install IMP Exterior Inwall Rough-In (These walls available early) OverHead Not Started 11/24/26 12/02/26 6.2 6.2
0%
107.5
RPL08.INT.DHD.01030 RPL08.Interior.DHD - Priority - Install Fire Sprinkler Early Priority OH MEPF Not Started 11/24/26 12/02/26 6.2 6.2
0%
213.8
RPL08.INT.DHD.01040 RPL08.Interior.DHD - Priority - Install Temp Lighting Early Priority OH MEPF Not Started 11/24/26 11/30/26 3.8 3.8
0%
218.8
RPL08.MCUP.LP1.2100 RPL08.MCUP.Loop 1 - Install Exterior Signage Hardscape and Landscape Not Started 11/24/26 12/09/26 12.5 12.5
0%
505.0
RPL08.SKN.DHCD.01040 RPL08.SKIN.DHCD - Install Louvers Glazing, Doors and Ext Devices Not Started 11/24/26 12/02/26 6.2 6.2
0%
423.8
RPL08.SKN.DHCD.01100 RPL08.SKIN.DHCD - Install Scupper and Downspouts Glazing, Doors and Ext Devices Not Started 11/24/26 12/02/26 6.2 6.2
0%
435.0
RPL08.STR.DHAB.01260 RPL08.Structure.DHAB - Install SOG Sealer and Cure F/R/P Not Started 11/24/26 11/25/26 2.5 2.5
0%
181.2
ICM.B8.1865 [SSDCB3] Delivery of MDF GS.MDF Module (First Delivery) Construction Not Started 11/25/26 11/25/26 0.0 0.0
0%
171.2
RPL08.INT.CTRC.01020 RPL08.Interior.Center-Corridor - Install Priority OH, Walls, OFE and Fitout - WBS Summary Center Corridor Not Started 11/25/26 07/09/27 192.5 192.5
0%
158.8
RPL08.INT.CTRC.03460 RPL08.Interior.Center-Corridor - Priority - Priority - WBS Summary Priority Walls & Overhead Not Started 11/25/26 02/12/27 66.2 66.2
0%
185.0
RPL08.INT.CTRC.1020 RPL08.Interior.Center-Corridor - Priority - Install Priority Soffit for Wall Tie-Ins/ Rock & HoW & Draft Blanket Priority Walls & Overhead Not Started 11/25/26 12/03/26 6.2 6.2
0%
118.8
RPL08.INT.CTRC.7740 RPL08.Interior.Center-Corridor - Priority - Install IMP Exterior Inwall Rough-In Priority Walls & Overhead Not Started 11/25/26 12/03/26 6.2 6.2
0%
125.0
RPL08.INT.SSB.01050 RPL08.Interior.SSB - Priority - (P1) Frame Walls (Frame full height Walls) Priority Wall - P1 Not Started 11/25/26 12/03/26 6.2 6.2
0%
196.2
RPL08.INT.SSB.06840 RPL08.Interior.SSB - Priority - (P1) Frame Remaining Walls Priority Wall - P1 Not Started 11/25/26 12/01/26 3.8 3.8
0%
238.8
RPL08.MCUP.LP2.1640 RPL08.MCUP.Loop 2 - Install Early Mcup Paving Hardscape and Landscape Not Started 11/25/26 12/10/26 12.5 12.5
0%
472.5
RPL08.STR.DHCD.01140 RPL08.Structure.DHCD - SOG F/R/P #8 - Grid lines 6-25/6-28 F/R/P Not Started 11/25/26 12/03/26 6.2 6.2
0%
156.2
RPL08.INT.SSBC.01090 RPL08.Interior.SSB-Corridor - OFE - Early Equipment (1x GS.MDF piece 1 of 2) OFE/MOFE & CFCI Not Started 11/30/26 12/04/26 6.2 6.2
0%
171.2
RPL08.INT.SSBC.06700 RPL08.Interior.SSBC - Priority GL8.04 - (P0) Tape Finish Paint (Both SIdes) Priority Wall Grid Line 8-04 Not Started 11/30/26 12/04/26 6.2 6.2
0%
152.5
ICM.B8.1840 [SSDCB3] Delivery of DES - Data Hall Electrical Room Skid (First Delivery) Construction Not Started 12/01/26 12/01/26 0.0 0.0
0%
168.8
RPL08.EY.SSB.01160 RPL08.EY.SSB - Install Electrical Tie-ins (include penetration detail) Tie-ins Not Started 12/01/26 12/29/26 25.0 25.0
0%
140.0
RPL08.EY.SSB.01170 RPL08.EY.SSB - Install Mechanical Main (include penetration detail) Tie-ins Not Started 12/01/26 12/21/26 18.8 18.8
0%
133.8
RPL08.INT.DHA.03440 RPL08.Interior.DHA - Priority - Install Backing at Exterior Wall OverHead Not Started 12/01/26 12/02/26 2.5 2.5
0%
117.5
RPL08.INT.DHB.02380 RPL08.Interior.DHB - Priority - Install Backing at Exterior Wall OverHead Not Started 12/01/26 12/02/26 2.5 2.5
0%
107.5
RPL08.WA.OFE.01000 RPL08.WA - Weather Allowance - FDN to OFE Weather Allowance Not Started 12/01/26 12/16/26 20.0 20.0
0%
155.0
RPL08.CON.WP2.09200 RPL08.Conn - CorpNet & FacNet Available (South EY) - All IDFs WP#02 GS Not Started 12/02/26 12/02/26 0.0 0.0
0%
511.2
RPL08.Conn.MS.01100 RPL08.Conn Wifi Ready - South EY (Pred from RPL10 CorpNet needed?) Connectivity Milestones Not Started 12/02/26 12/02/26 0.0 0.0
0%
355.0
RPL08.INT.SSB.01660 RPL08.Interior.SSB - Priority - Install Plumbing (Highside OH space) Priority Walls and OverHead Not Started 12/02/26 12/08/26 6.2 6.2
0%
143.8
RPL08.INT.SSB.01680 RPL08.Interior.SSB - Priority - Install Mechanical Piping/ Refrigerant (Highside OH space) Priority Walls and OverHead Not Started 12/02/26 12/08/26 6.2 6.2
0%
143.8
RPL08.INT.SSB.03200 RPL08.Interior.SSB - Priority - Install Fire Alarm hangers & members (Highside OH space) Priority Walls and OverHead Not Started 12/02/26 12/08/26 6.2 6.2
0%
331.2
RPL08.INT.SSB.06880 RPL08.Interior.SSB - Priority - (P1) Install Remaining MEP In-Wall/Backing Priority Wall - P1 Not Started 12/02/26 12/03/26 2.5 2.5
0%
238.8
RPL08.INT.SSBC.01060 RPL08.Interior.SSB-Corridor - OFE - Early Equipment (1x SSB Elect) OFE/MOFE & CFCI Not Started 12/02/26 12/15/26 12.5 12.5
0%
168.8
GCD.RPL08.1280 Interior fit-out Start RPL08 - DHA&B Construction Milestones Not Started 12/03/26 12/03/26 0.0 0.0
0%
363.8
RPL08.EY.SSB.01240 RPL08.EY.SSB - Install BMS/EPMS Tie-ins Tie-ins Not Started 12/03/26 12/23/26 18.8 18.8
0%
143.8
RPL08.INT.DHA.02380 RPL08.Interior.DHA - Priority - Install Drywall at Exterior Walls OverHead Not Started 12/03/26 12/11/26 8.8 8.8
0%
117.5
RPL08.INT.DHB.02320 RPL08.Interior.DHB - Priority - Install Drywall at Exterior Walls OverHead Not Started 12/03/26 12/11/26 8.8 8.8
0%
107.5
RPL08.INT.DHC.01030 RPL08.Interior.DHC - Priority - Install Fire Sprinkler Early Priority OH MEPF Not Started 12/03/26 12/09/26 6.2 6.2
0%
213.8
RPL08.SKN.DHCD.01050 RPL08.SKIN.DHCD - Install Lighting Glazing, Doors and Ext Devices Not Started 12/03/26 12/08/26 5.0 5.0
0%
423.8
RPL08.INT.CTRC.1000 RPL08.Interior.Center-Corridor - Priority - Install Unistruts & Hangers (All Trades) Both side of Corridor Wall Priority Walls & Overhead Not Started 12/04/26 12/10/26 6.2 6.2
0%
118.8
RPL08.INT.SSB.01170 RPL08.Interior.SSB - Loading Dock and Storage - WBS Summary Loading Dock and Storage Not Started 12/04/26 05/19/27 142.5 142.5
0%
206.2
RPL08.INT.SSB.02900 RPL08.Interior.SSB - Loading Dock and Storage - Pre Priority OH & Walls Tasks (Unistruts,Hangers,Track) Loading Dock and Storage Not Started 12/04/26 12/10/26 6.2 6.2
0%
206.2
RPL08.INT.SSB.06780 RPL08.Interior.SSB - Priority - (P1) Install MEP In-Wall/Backing Priority Wall - P1 Not Started 12/04/26 12/09/26 5.0 5.0
0%
232.5
RPL08.INT.SSB.06860 RPL08.Interior.SSB - Priority - (P1) Remaining Wall Hang Drywall (Both Sides) Priority Wall - P1 Not Started 12/04/26 12/08/26 3.8 3.8
0%
238.8
RPL08.STR.DHCD.01150 RPL08.Structure.DHCD - Zone SOG Cure F/R/P Not Started 12/04/26 12/10/26 8.8 8.8
0%
231.2
GCD.RPL08.1826 Delivery of RMU - (First Delivery) - RPL08 - DHA&B Construction Milestones Not Started 12/07/26 12/07/26 0.0 0.0
0%
118.8
ICM.B8.1825 [SSDCB3] Delivery of MVS - Medium Voltage Switches (First Delivery) Construction Not Started 12/07/26 12/07/26 0.0 0.0
0%
118.8
RPL08.CON.WP2.04000 RPL08.Conn - GSMDF2 (North) - WBS Summary GS.MDF2 (North) Not Started 12/07/26 05/03/27 126.2 126.2
0%
320.0
RPL08.CON.WP2.07880 RPL08.Conn - GSMDF2 (North) Set Infrastructure (Wall mounting enclosures, Tier1 Basket Tray, Waterfalls etc.) Infrastructure Not Started 12/07/26 12/09/26 3.8 3.8
0%
321.2
RPL08.INT.DHB.01050 RPL08.Interior.DHB - Priority - Install FA / Linear heat detection OverHead Not Started 12/07/26 12/11/26 6.2 6.2
0%
107.5
RPL08.INT.DHB.02300 RPL08.Interior.DHB - Priority - Install Electrical OverHead Not Started 12/07/26 12/28/26 18.8 18.8
0%
107.5
RPL08.INT.DHC.01040 RPL08.Interior.DHC - Priority - Install Temp Lighting Early Priority OH MEPF Not Started 12/07/26 12/09/26 3.8 3.8
0%
213.8
RPL08.INT.SSBC.01140 RPL08.Interior.SSB-Corridor - OFE - Early Equipment (1x GS.MDF piece 2 of 2) OFE/MOFE & CFCI Not Started 12/07/26 12/11/26 6.2 6.2
0%
171.2
RPL08.INT.SSBC.3000 RPL08.Interior.SSBC LO #06 - Close Interior Leave Out #06 SSB/SSBC (For MDF2) WBS Summary Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 12/07/26 02/23/27 66.2 66.2
0%
197.5
RPL08.INT.SSBC.3020 RPL08.Interior.SSBC LO #06 - Install Framing at LO Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 12/07/26 12/11/26 6.2 6.2
0%
197.5
RPL08.INT.DHC.01010 RPL08.Interior.DHC - Priority - Install Duct Early Priority OH MEPF Not Started 12/08/26 12/11/26 5.0 5.0
0%
272.5
RPL08.INT.DHD.01010 RPL08.Interior.DHD - Priority - Install Duct Early Priority OH MEPF Not Started 12/08/26 12/14/26 5.0 5.0
0%
272.5
RPL08.INT.SSB.03220 RPL08.Interior.SSB - Priority - Install Fire Safing/ Seal all Penetrations through Soffit (Highside OH space) Priority Walls and OverHead Not Started 12/09/26 12/15/26 6.2 6.2
0%
186.2
RPL08.INT.SSB.06900 RPL08.Interior.SSB - Priority - (P1) Remaining Wall Tape Finish Paint (Both Sides) Priority Wall - P1 Not Started 12/09/26 12/15/26 6.2 6.2
0%
238.8
RPL08.INT.SSBC.02180 RPL08.Interior.SSBC - Priority - Install Plumbing (Highside OH space) Priority Walls & Overhead Not Started 12/09/26 12/15/26 6.2 6.2
0%
143.8
RPL08.INT.SSBC.02200 RPL08.Interior.SSBC - Priority - Install Mechanical Piping/ Refrigerant (Highside OH space) Priority Walls & Overhead Not Started 12/09/26 12/15/26 6.2 6.2
0%
143.8
RPL08.INT.SSBC.03300 RPL08.Interior.SSBC - Priority - Install FA/ VESDA/ hangers & Heat Trace (Highside OH space) Priority Walls & Overhead Not Started 12/09/26 12/15/26 6.2 6.2
0%
143.8
RPL08.SKN.DHCD.01060 RPL08.SKIN.DHCD - Install Security Glazing, Doors and Ext Devices Not Started 12/09/26 12/10/26 2.5 2.5
0%
423.8
RPL08.CON.WP2.09240 RPL08.Conn - GSMDF2 (North) - Install Copper, WAPs, Security Camera & Access Control ISP (MDF RPL08 <> MDF RPL08) Not Started 12/10/26 12/28/26 15.0 15.0
0%
321.2
RPL08.INT.ENDC.1040 RPL08.Interior.End-Corridor - Priority - Install Fire Sprinkler (Highside OH space) Early Priority OH MEPF Not Started 12/10/26 12/14/26 3.8 3.8
0%
213.8
RPL08.INT.ENDC.1060 RPL08.Interior.End-Corridor - Priority - Install Temp Lighting (Show In Model) Early Priority OH MEPF Not Started 12/10/26 12/14/26 3.8 3.8
0%
213.8
RPL08.INT.SSB.06800 RPL08.Interior.SSB - Priority - (P1) Hang Drywall (Both Sides) Priority Wall - P1 Not Started 12/10/26 12/15/26 5.0 5.0
0%
232.5
RPL08.INT.CTRC.1920 RPL08.Interior.Center-Corridor - Priority - Install Drywall at Exterior Walls Priority Walls & Overhead Not Started 12/11/26 12/17/26 6.2 6.2
0%
118.8
RPL08.INT.SSB.01140 RPL08.Interior.SSB - Loading Dock and Storage - Frame Walls Loading Dock and Storage Not Started 12/11/26 12/22/26 10.0 10.0
0%
206.2
RPL08.MCUP.LP2.1760 RPL08.MCUP.Loop 2 - Install Lighting Hardscape and Landscape Not Started 12/11/26 12/17/26 6.2 6.2
0%
472.5
RPL08.STR.DHCD.01210 RPL08.Structure.DHCD - Moisture requirements for floor Sealer F/R/P Not Started 12/11/26 12/17/26 8.8 8.8
0%
231.2
RPL08.CON.WP2.05000 RPL08.Conn - GSMDF1 (South) - WBS Summary GS.MDF1 (South) Not Started 12/14/26 05/03/27 120.0 120.0
0%
320.0
RPL08.CON.WP2.07960 RPL08.Conn - GSMDF1 (South) Set Infrastructure (Wall mounting enclosures, Tier1 Basket Tray, Waterfalls etc.) Infrastructure Not Started 12/14/26 12/16/26 3.8 3.8
0%
327.5
RPL08.CON.WP4.00010 RPL08.Conn - Network - WBS Summary WP#4 Network Not Started 12/14/26 10/22/27 271.2 271.2
0%
231.2
RPL08.INT.DHA.02140 RPL08.Interior.DHA - Priority - Install Plumbing OverHead Not Started 12/14/26 12/18/26 6.2 6.2
0%
117.5
RPL08.INT.DHA.02160 RPL08.Interior.DHA - Priority - Install Mechanical Piping OverHead Not Started 12/14/26 01/05/27 18.8 18.8
0%
117.5
RPL08.INT.DHB.01100 RPL08.Interior.DHB - Priority - Install Temp Doors Frame Hardware OverHead Not Started 12/14/26 12/16/26 3.8 3.8
0%
115.0
RPL08.INT.ENDC.1180 RPL08.Interior.End-Corridor - Priority - Install Duct (Highside OH space) Early Priority OH MEPF Not Started 12/14/26 12/22/26 8.8 8.8
0%
272.5
RPL08.INT.SSBC.3080 RPL08.Interior.SSBC LO #06 - Install Mechanical Piping Lowside OH and in-wall Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 12/14/26 12/15/26 2.5 2.5
0%
197.5
RPL08.INT.SSBC.4000 RPL08.Interior.SSBC LO #07 - Close Interior LO #07 SSB/SSBC (For MDF1) WBS Summary Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 12/14/26 03/02/27 66.2 66.2
0%
191.2
RPL08.INT.SSBC.4020 RPL08.Interior.SSBC LO #07 - Install Framing at LO Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 12/14/26 12/18/26 6.2 6.2
0%
191.2
RPL08.WP4.010000 RPL08.Conn GSMDF1 Pull Fanout (5F) [PON (Active, In-Row)] GSMDF1 Not Started 12/14/26 12/14/26 1.2 1.2
0%
321.2
RPL08.INT.CTRC.1100 RPL08.Interior.Center-Corridor - Priority - Tape Finish Paint Priority Soffit both sides (Top Out) Priority Walls & Overhead Not Started 12/15/26 12/23/26 8.8 8.8
0%
118.8
RPL08.WP4.010020 RPL08.Conn GSMDF2 Pull Fanout (5F) [PON (Active, In-Row)] GSMDF2 Not Started 12/15/26 12/15/26 1.2 1.2
0%
321.2
RPL08.WP4.010040 RPL08.Conn GSMDF1 Install Fanout (5F) [PON (Active, In-Row)] GSMDF1 Not Started 12/15/26 12/30/26 13.8 13.8
0%
322.5
RPL08.INT.SBC.03240 RPL08.Interior.SSB-Corridor - Frame Balance of Wall Balance of Walls & Overhead Not Started 12/16/26 12/22/26 6.2 6.2
0%
143.8
RPL08.INT.SBC.03260 RPL08.Interior.SSB-Corridor - Balace Of Wall (ERAD, Maintance, Network infra, Spoke, Bathroom, etc) - WBS Summary Balance of Walls & Overhead Not Started 12/16/26 06/07/27 147.5 147.5
0%
143.8
RPL08.INT.SSB.01150 RPL08.Interior.SSB - BoW - BoW - Framing Balance of Wall Balance of Walls and OverHead Not Started 12/16/26 12/22/26 6.2 6.2
0%
186.2
RPL08.INT.SSB.01160 RPL08.Interior.SSB - BoW - Balace Of Wall (ERAD, Maintance, Network infra, Spoke, Bathroom, etc) - WBS Summary Balance of Walls and OverHead Not Started 12/16/26 06/11/27 152.5 152.5
0%
186.2
RPL08.INT.SSB.01880 RPL08.Interior.SSB - Final Finishes & Fixtures - Frame/Blocking Walls & Ceilings Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) Not Started 12/16/26 12/30/26 12.5 12.5
0%
316.2
RPL08.INT.SSB.06820 RPL08.Interior.SSB - Priority - (P1) Tape Finish Paint (Both Sides) Priority Wall - P1 Not Started 12/16/26 12/22/26 6.2 6.2
0%
232.5
RPL08.INT.SSB.14000 RPL08.Interior.Center-Corridor Leave Out #01 #02 #03 #04 #5 - SSB (for Elec. Room) WBS Summary Interior Leave Out Wall #01, #02, #03, #04, #05 SSB for Electrical Room Not Started 12/16/26 04/30/27 116.2 116.2
0%
172.5
RPL08.INT.SSB.14020 RPL08.Interior.SSB LO #01 to #05 - Install LO Framing OH & Framing Not Started 12/16/26 12/22/26 6.2 6.2
0%
172.5
RPL08.INT.SSBC.03320 RPL08.Interior.SSBC - Priority - Install Fire Safing/ Seal Penetrations through Soffit (Highside OH space) Priority Walls & Overhead Not Started 12/16/26 12/18/26 3.8 3.8
0%
143.8
RPL08.INT.SSBC.03340 RPL08.Interior.SSBC - Priority - Fixed Draft/Smoke Curtain Patching Priority Walls & Overhead Not Started 12/16/26 12/18/26 3.8 3.8
0%
143.8
RPL08.INT.SSBC.3100 RPL08.Interior.SSBC LO #06 - Install Fire Life Safety Lowside OH and In-wall Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 12/16/26 12/17/26 2.5 2.5
0%
201.2
RPL08.INT.SSBC.3120 RPL08.Interior.SSBC LO #06 - Install Plumbing Lowside OH and In-wall Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 12/16/26 12/17/26 2.5 2.5
0%
197.5
RPL08.SKN.W.LO.01120 RPL08.SKIN.LO#16 - Close Exterior Leave Out #16 SSB (North of Loading Dock) WBS Summary Build back Exterior Leave Out Walls #16 (SSB - North of Loading Dock) Not Started 12/16/26 02/02/27 40.0 40.0
0%
168.8
RPL08.SKN.W.LO.01380 RPL08.SKIN.LO#16 - Pour back Stemwall Build back Exterior Leave Out Walls #16 (SSB - North of Loading Dock) Not Started 12/16/26 12/22/26 6.2 6.2
0%
168.8
RPL08.WP4.010060 RPL08.Conn GSMDF2 Install Fanout (5F) [PON (Active, In-Row)] GSMDF2 Not Started 12/16/26 12/31/26 13.8 13.8
0%
321.2