Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL08 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:14 PM · 5122 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
0
Completed
0
In Progress
0
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
GCD.RPL08.1655 Start MES Installation - RPL08 Construction Milestones Not Started 12/17/26 12/17/26 0.0 0.0
0%
147.5
GCD.RPL08.1700 Start LV Electrical Skid Set-In-Place - RPL08 Construction Milestones Not Started 12/17/26 12/17/26 0.0 0.0
0%
351.2
RPL08.CON.WP2.07900 RPL08.Conn -MDF1<>MDF2 Install Cabling (Pull, Splice & Terminate) ISP (MDF RPL08 <> MDF RPL08) Not Started 12/17/26 12/22/26 5.0 5.0
0%
422.5
RPL08.CON.WP2.07980 RPL08.Conn - MDF1<>MDF2 Install Cabling (Pull, Splice & Terminate) ISP (MDF RPL08 <> MDF RPL08) Not Started 12/17/26 12/22/26 5.0 5.0
0%
422.5
RPL08.CON.WP2.09260 RPL08.Conn - GSMDF1 (South) - Install Copper, WAPs, Security Camera & Access Control ISP (MDF RPL08 <> MDF RPL08) Not Started 12/17/26 01/05/27 15.0 15.0
0%
327.5
RPL08.INT.DHB.01120 RPL08.Interior.DHB - Priority - Install Security OverHead Not Started 12/17/26 12/23/26 6.2 6.2
0%
115.0
RPL08.INT.DHB.01140 RPL08.Interior.DHB - OFE - LV Skids and TopHat - Set / Place / Anchor OFE/MOFE & CFCI Not Started 12/17/26 01/08/27 18.8 18.8
0%
103.8
RPL08.INT.DHB.01150 RPL08.Interior.DHB - OFE - MES Skids - Set / Place / Anchor OFE/MOFE & CFCI Not Started 12/17/26 01/08/27 18.8 18.8
0%
141.2
RPL08.INT.DHB.01160 RPL08.Interior.DHB - OFE - WBS Summary OFE/MOFE & CFCI Not Started 12/17/26 04/02/27 90.0 90.0
0%
147.5
DCC.B8.3135 [SSDCB3] GS Gear Delivered [DHA] Connectivity Not Started 12/18/26 12/18/26 0.0 0.0
0%
497.5
RPL08.INT.DHD.01000 RPL08.Interior.DHD - Priority OH - WBS Summary OverHead Not Started 12/18/26 02/10/27 45.0 45.0
0%
403.8
RPL08.INT.DHD.01020 RPL08.Interior.DHD - Install Priority OH, Walls, OFE and Tie-ins - WBS Summary DHD Not Started 12/18/26 07/26/27 187.5 187.5
0%
261.2
RPL08.INT.DHD.01980 RPL08.Interior.DHD - Priority - Install Unistruts & Hangers (All Trades) Both side of Corridor Wall OverHead Not Started 12/18/26 12/24/26 6.2 6.2
0%
156.2
RPL08.INT.DHD.02250 RPL08.Interior.DHD - Priority - Install IMP Exterior Inwall Rough-In OverHead Not Started 12/18/26 12/24/26 6.2 6.2
0%
156.2
RPL08.INT.ENDC.01020 RPL08.Interior.End-Corridor - Install Priority OH, Walls, OFE and Fitout - WBS Summary End Corridor Not Started 12/18/26 10/08/27 253.8 253.8
0%
205.0
RPL08.INT.ENDC.03480 RPL08.Interior.End-Corr - Priority - WBS Summary Priority Walls & Overhead Not Started 12/18/26 01/29/27 35.0 35.0
0%
213.8
RPL08.INT.ENDC.1020 RPL08.Interior.End-Corr - Priority - Install Priority Soffit for Wall Tie-Ins/ Rock & HoW & Draft Blanket Priority Walls & Overhead Not Started 12/18/26 12/24/26 6.2 6.2
0%
210.0
RPL08.INT.SSBC.3140 RPL08.Interior.SSBC LO #06 - Install Security Lowside OH and In-wall Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 12/18/26 12/21/26 2.5 2.5
0%
201.2
RPL08.INT.SSBC.3160 RPL08.Interior.SSBC LO #06 - Install Controls / EPMS / BMS OH and In-wall Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 12/18/26 12/21/26 2.5 2.5
0%
197.5
RPL08.MCUP.LP2.1860 RPL08.MCUP.Loop 2 - Install Mcup Paving Hardscape and Landscape Not Started 12/18/26 01/04/27 12.5 12.5
0%
472.5
RPL08.STR.DHCD.01230 RPL08.Structure.DHCD - Install SOG Sealer and Cure F/R/P Not Started 12/18/26 12/19/26 2.5 2.5
0%
263.8
RPL08.INT.SSBC.4080 RPL08.Interior.SSBC LO #07 - Install Mechanical Piping Lowside OH and in-wall Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 12/21/26 12/22/26 2.5 2.5
0%
191.2
RPL08.EY.SSB.01175 RPL08.EY.SSB - Install Mechanical/refrigerantTie-ins Tie-ins Not Started 12/22/26 01/06/27 12.5 12.5
0%
133.8
RPL08.INT.DHB.01180 RPL08.Interior.DHB - LV Skids and TopHat Tie-ins (LOE) DHB - LV Skids and TopHat Not Started 12/22/26 01/25/27 27.5 27.5
0%
160.0
RPL08.INT.DHB.01181 RPL08.Interior.DHB - LV Skids and TopHat - Set & Anchor Interconnects DHB - LV Skids and TopHat Not Started 12/22/26 01/12/27 17.5 17.5
0%
160.0
RPL08.INT.DHB.01190 RPL08.Interior.DHB - Tie-ins - WBS Summary Tie-Ins Not Started 12/22/26 06/15/27 150.0 150.0
0%
186.2
RPL08.INT.ENDC.6060 RPL08.Interior.End-Corr - Priority - Install IMP Exterior Inwall Rough-In Priority Walls & Overhead Not Started 12/22/26 12/24/26 3.8 3.8
0%
216.2
RPL08.INT.SSBC.3240 RPL08.Interior.SSBC LO #06 - Install Electrical Lowside OH and In-wall Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 12/22/26 12/24/26 3.8 3.8
0%
197.5
RPL08.CON.WP2.09280 RPL08.Conn Misc P/S/T and R/S/P @ MDF2 ISP (MDF RPL08 <> MDF RPL08) Not Started 12/23/26 12/29/26 5.0 5.0
0%
422.5
RPL08.CON.WP2.09300 RPL08.Conn Misc P/S/T and R/S/P @ MDF2 ISP (MDF RPL08 <> MDF RPL08) Not Started 12/23/26 12/29/26 5.0 5.0
0%
422.5
RPL08.EY.ENDC.1910 RPL08.EY.DHD.T1 - HAC Prefab prior to install for DH B Tent 1 Not Started 12/23/26 01/07/27 12.5 12.5
0%
110.0
RPL08.INT.SBC.03420 RPL08.Interior.SSB-Corridor - BoW - Install Door Frames Balance of Walls & Overhead Not Started 12/23/26 12/30/26 6.2 6.2
0%
168.8
RPL08.INT.SBC.05800 RPL08.Interior.SSB-Corridor - BoW - Install Mechanical Piping/ Refrigerant Lowside OH and in-wall Balance of Walls & Overhead Not Started 12/23/26 01/05/27 10.0 10.0
0%
143.8
RPL08.INT.SSB.01180 RPL08.Interior.SSB - BoW - Install Door Frames Balance of Walls and OverHead Not Started 12/23/26 12/30/26 6.2 6.2
0%
207.5
RPL08.INT.SSB.01200 RPL08.Interior.SSB - Priority - Install Store Front Frames & Glass (Testing if Required) Balance of Walls and OverHead Not Started 12/23/26 01/14/27 18.8 18.8
0%
243.8
RPL08.INT.SSB.01210 RPL08.Interior.SSB - BoW - Install Electrical Lowside OH and In-wall and Lights(Coordinate Lights location to not affect Balance of Walls and OverHead Not Started 12/23/26 01/07/27 12.5 12.5
0%
186.2
RPL08.INT.SSB.02920 RPL08.Interior.SSB - Loading Dock and Storage - Install Headers and Top Out and Fire/Caulking Loading Dock and Storage Not Started 12/23/26 01/07/27 12.5 12.5
0%
206.2
RPL08.INT.SSB.14060 RPL08.Interior.SSB LO #01 to #05 - Install In-Wall Rough-in OH & Framing Not Started 12/23/26 12/24/26 2.5 2.5
0%
172.5
RPL08.INT.SSBC.4100 RPL08.Interior.SSBC LO #07 - Install Fire Life Safety Lowside OH and In-wall Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 12/23/26 12/24/26 2.5 2.5
0%
195.0
RPL08.INT.SSBC.4120 RPL08.Interior.SSBC LO #07 - Install Plumbing Lowside OH and In-wall Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 12/23/26 12/24/26 2.5 2.5
0%
191.2
RPL08.SKN.W.LO.01385 RPL08.SKIN.LO#16 - Cure Stemwall Build back Exterior Leave Out Walls #16 (SSB - North of Loading Dock) Not Started 12/23/26 01/04/27 8.8 8.8
0%
168.8
RPL08.EY.DHB.01220 RPL08.EY.DHB - Install MV, RMUs & Electrical Panels (Qty 10) OFE Not Started 12/24/26 01/25/27 25.0 25.0
0%
103.8
RPL08.EY.DHB.01230 RPL08.EY.DHB - OFE - MV - WBS Summary OFE Not Started 12/24/26 03/09/27 62.5 62.5
0%
223.8
RPL08.EY.SSB.01250 RPL08.EY.SSB - Install Sleeves MEPL Hardscape and Landscape Not Started 12/24/26 12/31/26 6.2 6.2
0%
263.8
RPL08.EY.SSB.01270 RPL08.EY.SSB - Hardscape and Landscape - WBS Summary Hardscape and Landscape Not Started 12/24/26 08/16/27 201.2 201.2
0%
291.2
RPL08.INT.CTRC.1160 RPL08.Interior.Center-Corr - Priority GL8.16/8.17 - (P2) Frame Walls (Incl. Entry Fiber Rooms #3.7, Ancillary Room #3.6) Priority Wall Grid Line 8-16 / 8-17 Not Started 12/24/26 01/05/27 8.8 8.8
0%
118.8
RPL08.INT.DHB.01130 RPL08.Interior.DHB - Priority - Install Controls / EPMS / BMS OverHead Not Started 12/24/26 12/30/26 5.0 5.0
0%
115.0
RPL08.INT.DHB.01200 RPL08.Interior.DHB - MES Skids Tie-ins (LOE) DHB - MES Skids Not Started 12/24/26 02/10/27 40.0 40.0
0%
160.0
RPL08.INT.DHB.01201 RPL08.Interior.DHB - MES Skids - Set & Anchor Interconnects DHB - MES Skids Not Started 12/24/26 01/25/27 25.0 25.0
0%
141.2
RPL08.INT.DHD.02230 RPL08.Interior.DHD - Priority - Install Drywall at Exterior Walls OverHead Not Started 12/28/26 01/04/27 6.2 6.2
0%
156.2
RPL08.INT.ENDC.1000 RPL08.Interior.End-Corr - Priority - Install Unistruts & Hangers (All Trades) Both side of Corridor Wall Priority Walls & Overhead Not Started 12/28/26 01/04/27 6.2 6.2
0%
210.0
RPL08.INT.SSB.14080 RPL08.Interior.SSB LO #01 to #05 - Install Mechanical Piping & Refrigerant Lowside OH and in-wall OH & Framing Not Started 12/28/26 12/30/26 3.8 3.8
0%
172.5
RPL08.INT.SSBC.3180 RPL08.Interior.SSBC LO #06 - Install Door Frames Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 12/28/26 12/29/26 2.5 2.5
0%
197.5
RPL08.INT.SSBC.4140 RPL08.Interior.SSBC LO #07 - Install Security Lowside OH and In-wall Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 12/28/26 12/29/26 2.5 2.5
0%
195.0
RPL08.INT.SSBC.4160 RPL08.Interior.SSBC LO #07 - Install Controls / EPMS / BMS OH and In-wall Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 12/28/26 12/29/26 2.5 2.5
0%
191.2
RPL08.INT.DHA.01050 RPL08.Interior.DHA - Priority - Install FA / Linear heat detection OverHead Not Started 12/29/26 01/05/27 6.2 6.2
0%
107.5
RPL08.INT.DHA.02320 RPL08.Interior.DHA - Priority - Install Electrical OverHead Not Started 12/29/26 01/20/27 18.8 18.8
0%
107.5
RPL08.INT.DHB.01182 RPL08.Interior.DHB - LV Skids and TopHat - Maintenance and Reserve Busways DHB - LV Skids and TopHat Not Started 12/29/26 01/15/27 16.2 16.2
0%
160.0
DCC.B8.3225 [SSDCB3] CorpNet/Security/FacNet Ready [DHB] Connectivity Not Started 12/30/26 12/30/26 0.0 0.0
0%
422.5
RPL08.INT.SSBC.3200 RPL08.Interior.SSBC LO #06 - Mechanical Tie-In Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 12/30/26 12/31/26 2.5 2.5
0%
197.5
RPL08.INT.SSBC.3300 RPL08.Interior.SSBC LO #06 - Electrical Tie-In Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 12/30/26 01/06/27 6.2 6.2
0%
197.5
RPL08.INT.SSBC.4240 RPL08.Interior.SSBC LO #07 - Install Electrical Lowside OH and In-wall Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 12/30/26 01/04/27 3.8 3.8
0%
191.2
RPL08.INT.SSB.02860 RPL08.Interior.SSB - Final Finishes & Fixtures - MEP Rough-In Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) Not Started 12/31/26 01/07/27 6.2 6.2
0%
316.2
RPL08.INT.SSB.14100 RPL08.Interior.SSB LO #01 to #05 - Install Fire Life Safety Lowside OH and In-wall OH & Framing Not Started 12/31/26 12/31/26 1.2 1.2
0%
195.0
RPL08.INT.SSB.14120 RPL08.Interior.SSB LO #01 to #05 - Install Plumbing Lowside OH and In-wall OH & Framing Not Started 12/31/26 01/04/27 2.5 2.5
0%
172.5
RPL08.EY.SSB.01290 RPL08.EY.SSB - Install Trash Enclosure (CMU) Hardscape and Landscape Not Started 01/04/27 02/01/27 25.0 25.0
0%
288.8
RPL08.INT.CTRC.9040 RPL08.Interior.Center-Corr - Priority GL8.16/8.17- (P2) Install MEP In-Wall/Backing Priority Wall Grid Line 8-16 / 8-17 Not Started 01/04/27 01/07/27 5.0 5.0
0%
118.8
RPL08.INT.DHB.01210 RPL08.Interior.DHB - OFE - Control Fault Domain 1 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary Control Fault Domain 1 Not Started 01/04/27 02/01/27 25.0 25.0
0%
110.0
RPL08.INT.DHB.02400 RPL08.Interior.DHB - OFE - Control Fault Domain 1 (LV Side Aisle) Control Fault Domain 1 Not Started 01/04/27 01/08/27 6.2 6.2
0%
113.8
RPL08.INT.SSB.14140 RPL08.Interior.SSB LO #01 to #05 - Install Security Lowside OH and In-wall OH & Framing Not Started 01/04/27 01/05/27 2.5 2.5
0%
195.0
RPL08.INT.DHB.01202 RPL08.Interior.DHB - MES Skids - Piping Tie-Ins & Inspections DHB - MES Skids Not Started 01/05/27 02/02/27 25.0 25.0
0%
141.2
RPL08.INT.DHC.01000 RPL08.Interior.DHC - Priority OH - WBS Summary OverHead Not Started 01/05/27 03/02/27 48.8 48.8
0%
397.5
RPL08.INT.DHC.01020 RPL08.Interior.DHC - Install Priority OH, Walls, OFE and Tie-ins - WBS Summary DHC Not Started 01/05/27 08/13/27 192.5 192.5
0%
253.8
RPL08.INT.DHC.01980 RPL08.Interior.DHC - Priority - Install Unistruts & Hangers (All Trades) Both side of Corridor Wall OverHead Not Started 01/05/27 01/11/27 6.2 6.2
0%
158.8
RPL08.INT.DHC.02250 RPL08.Interior.DHC - Priority - Install IMP Exterior Inwall Rough-In OverHead Not Started 01/05/27 01/11/27 6.2 6.2
0%
158.8
RPL08.INT.ENDC.01120 RPL08.Interior.End-Corridor - Frame Remaining Walls Fit out Not Started 01/05/27 01/08/27 5.0 5.0
0%
247.5
RPL08.INT.ENDC.01130 RPL08.Interior.End-Corridor - Install Fitout (Restroom, Janitor, Fire Riser, Humidifier) - WBS Summary Fit out Not Started 01/05/27 09/28/27 231.2 231.2
0%
215.0
RPL08.INT.ENDC.1920 RPL08.Interior.End-Corr - Priority - Install Drywall at Exterior Walls Priority Walls & Overhead Not Started 01/05/27 01/11/27 6.2 6.2
0%
210.0
RPL08.INT.SSB.14160 RPL08.Interior.SSB LO #01 to #05 - Install Controls / EPMS / BMS OH and In-wall OH & Framing Not Started 01/05/27 01/06/27 2.5 2.5
0%
172.5
RPL08.INT.SSBC.4180 RPL08.Interior.SSBC LO #07 - Install Door Frames Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 01/05/27 01/06/27 2.5 2.5
0%
191.2
RPL08.MCUP.LP2.1960 RPL08.MCUP.Loop 2 - Install Exterior Signage Hardscape and Landscape Not Started 01/05/27 01/19/27 12.5 12.5
0%
472.5
RPL08.SKN.W.LO.01390 RPL08.SKIN.LO#16 - Stemwall Water Proofing Build back Exterior Leave Out Walls #16 (SSB - North of Loading Dock) Not Started 01/05/27 01/11/27 6.2 6.2
0%
168.8
DCC.B8.3235 [SSDCB3] CorpNet/Security/FacNet Ready [DHA] Connectivity Not Started 01/06/27 01/06/27 0.0 0.0
0%
417.5
RPL08.INT.CTRC.1080 RPL08.Interior.Center-Corridor - Priority - Install Mechanical Piping/ Refrigerant (Highside OH space) Priority Walls & Overhead Not Started 01/06/27 01/12/27 6.2 6.2
0%
117.5
RPL08.INT.CTRC.9020 RPL08.Interior.Center-Corr - Priority GL8.16/8.17 - (P2) Install IMP Wall Priority Wall Grid Line 8-16 / 8-17 Not Started 01/06/27 01/11/27 5.0 5.0
0%
125.0
RPL08.INT.CTRC.9060 RPL08.Interior.Center-Corr - Priority GL8.16/8.17- (P2) Hang Drywall (Both Sides) Priority Wall Grid Line 8-16 / 8-17 Not Started 01/06/27 01/11/27 5.0 5.0
0%
118.8
RPL08.INT.DHA.02360 RPL08.Interior.DHA - Priority - Install Temp Doors Frame Hardware OverHead Not Started 01/06/27 01/08/27 3.8 3.8
0%
322.5
RPL08.INT.DHB.01183 RPL08.Interior.DHB - LV Skids and TopHat - Top Hat Busway DHB - LV Skids and TopHat Not Started 01/06/27 01/25/27 16.2 16.2
0%
160.0
RPL08.INT.DHB.01250 RPL08.Interior.DHB - Tie-ins - Control Fault Domain 1 - WBS Summary Control Fault Domain 1 Not Started 01/06/27 03/25/27 68.8 68.8
0%
110.0
RPL08.INT.DHB.02700 RPL08.Interior.DHB - Control Fault Domain 1 - Install Duct (LV Side) LV Side Tie-ins Not Started 01/06/27 01/12/27 6.2 6.2
0%
128.8
RPL08.INT.SBC.03280 RPL08.Interior.SSB-Corridor - BoW -Install Electrical Lowside OH and In-wall and Lights (Coordinate Lights location to n Balance of Walls & Overhead Not Started 01/06/27 01/20/27 12.5 12.5
0%
143.8
RPL.08.D.70140.XR External Tie from RPL06 - Interior HAC Crew 1 Flow (RPL06.INT.DHD.02470) (1/19/27) Internal Milestones (XREFs) Not Started 01/07/27 01/07/27 0.0 0.0
0%
110.0
RPL08.EY.SSB.01260 RPL08.EY.SSB - L2 Checklist Completion Tie-ins Not Started 01/07/27 01/21/27 12.5 12.5
0%
133.8
RPL08.INT.DHB.01203 RPL08.Interior.DHB - MES Skids - CDU Tie-Ins DHB - MES Skids Not Started 01/07/27 02/04/27 25.0 25.0
0%
160.0
RPL08.INT.SSB.14240 RPL08.Interior.SSB LO #01 to #05 - Install Electrical Lowside OH and In-wall OH & Framing Not Started 01/07/27 01/15/27 8.8 8.8
0%
172.5
RPL08.INT.SSBC.3220 RPL08.Interior.SSBC LO #06 - Fire Safing OH and In-wall Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 01/07/27 01/07/27 1.2 1.2
0%
197.5
RPL08.INT.SSBC.4200 RPL08.Interior.SSBC LO #07 - Mechanical Tie-In Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 01/07/27 01/08/27 2.5 2.5
0%
191.2
RPL08.INT.SSBC.4300 RPL08.Interior.SSBC LO #07 - Electrical Tie-In Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 01/07/27 01/13/27 6.2 6.2
0%
191.2
GCD.RPL08.1725 Start FSHAC set in place - RPL08 - DHA&B Construction Milestones Not Started 01/08/27 01/08/27 0.0 0.0
0%
333.8
RPL08.INT.DHB.01310 RPL08.Interior.DHB - Control Fault Domain 1 - Install LV Side Aisle HAC Busway LV Side Tie-ins Not Started 01/08/27 01/14/27 6.2 6.2
0%
137.5