Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL08 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:14 PM
· 5122 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
0
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL08.INT.DHB.02420 |
RPL08.Interior.DHB - OFE - Control Fault Domain 1 (HAC) | Control Fault Domain 1 | Not Started | 01/08/27 | 01/29/27 | 18.8 | 18.8 |
|
110.0 |
RPL08.INT.SSB.03060 |
RPL08.Interior.SSB - Final Finishes & Fixtures - Hang Tape Bed and Fire/Caulking | Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) | Not Started | 01/08/27 | 01/14/27 | 6.2 | 6.2 |
|
328.8 |
RPL08.INT.SSB.03080 |
RPL08.Interior.SSB - Loading Dock and Storage - Tape Finish Paint (Top Out) | Loading Dock and Storage | Not Started | 01/08/27 | 01/20/27 | 10.0 | 10.0 |
|
206.2 |
RPL08.INT.SSB.05860 |
RPL08.Interior.SSB - BoW - BoW - Install Mechanical Piping/ Refrigerant (Lowside OH space) | Balance of Walls and OverHead | Not Started | 01/08/27 | 01/14/27 | 6.2 | 6.2 |
|
186.2 |
RPL08.INT.SSB.06660 |
RPL08.Interior.SSB - Final Finishes & Fixtures - Framing RO Verification, Tile Finish & ADA Verification (Pre Drywall) | Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) | Not Started | 01/08/27 | 01/14/27 | 6.2 | 6.2 |
|
316.2 |
RPL08.INT.SSBC.3260 |
RPL08.Interior.SSBC LO #06 - Install Backing | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 01/08/27 | 01/08/27 | 1.2 | 1.2 |
|
197.5 |
RPL08.INT.DHB.01204 |
RPL08.Interior.DHB - MES Skids - BMS Tie-Ins | DHB - MES Skids | Not Started | 01/11/27 | 02/08/27 | 25.0 | 25.0 |
|
160.0 |
RPL08.INT.DHB.01320 |
RPL08.Interior.DHB - OFE - Control Fault Domain 2 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | Control Fault Domain 2 | Not Started | 01/11/27 | 02/16/27 | 31.2 | 31.2 |
|
122.5 |
RPL08.INT.DHB.01330 |
RPL08.Interior.DHB - Control Fault Domain 1 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 01/11/27 | 01/15/27 | 6.2 | 6.2 |
|
137.5 |
RPL08.INT.DHB.02460 |
RPL08.Interior.DHB - OFE - Control Fault Domain 2 (LV Side Aisle) | Control Fault Domain 2 | Not Started | 01/11/27 | 01/14/27 | 5.0 | 5.0 |
|
138.8 |
RPL08.INT.ENDC.01140 |
RPL08.Interior.End-Corridor - Install Doors Frame Hardware | Fit out | Not Started | 01/11/27 | 01/15/27 | 6.2 | 6.2 |
|
250.0 |
RPL08.INT.ENDC.01150 |
RPL08.Interior.End-Corridor - Install Electrical OH and In-wall | Fit out | Not Started | 01/11/27 | 01/20/27 | 8.8 | 8.8 |
|
247.5 |
RPL08.INT.ENDC.06940 |
RPL08.Interior.End-Corridor - Final Finishes & Fixtures - Frame/Blocking Walls & Ceilings | Restrooms | Not Started | 01/11/27 | 01/25/27 | 12.5 | 12.5 |
|
260.0 |
RPL08.INT.SSBC.3280 |
RPL08.Interior.SSBC LO #06 - QC - Backings/Walls | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 01/11/27 | 01/12/27 | 2.5 | 2.5 |
|
197.5 |
GCD.RPL08.1290 |
Interior fit-out Start RPL08 - DHC&D | Construction Milestones | Not Started | 01/12/27 | 01/12/27 | 0.0 | 0.0 |
|
440.0 |
RPL08.INT.CTRC.01070 |
RPL08.Interior.Center-Corridor - BoW - Early MEPF Inwall Rough-In for Ancillary Skid (Room #3.6) | Priority Wall Grid Line 8-16 / 8-17 | Not Started | 01/12/27 | 01/14/27 | 3.8 | 3.8 |
|
206.2 |
RPL08.INT.CTRC.01130 |
RPL08.Interior.Center-Corridor - OFE - DHB (1x GS.IDF) B2 | OFE/MOFE & CFCI | Not Started | 01/12/27 | 01/19/27 | 6.2 | 6.2 |
|
176.2 |
RPL08.INT.CTRC.01200 |
RPL08.Interior.Center-Corridor - OFE - DHA (1x GS.IDF) A2 | OFE/MOFE & CFCI | Not Started | 01/12/27 | 01/19/27 | 6.2 | 6.2 |
|
176.2 |
RPL08.INT.CTRC.8940 |
RPL08.Interior.Center-Corr - Priority - All MEP In-wall in Entry Fiber Rooms (Room #2.7) | Priority Wall Grid Line 8-16 / 8-17 | Not Started | 01/12/27 | 01/21/27 | 8.8 | 8.8 |
|
185.0 |
RPL08.INT.CTRC.9080 |
RPL08.Interior.Center-Corr - Priority GL8.16/8.17- (P2) Tape Finish Paint (Both Sides) | Priority Wall Grid Line 8-16 / 8-17 | Not Started | 01/12/27 | 01/19/27 | 6.2 | 6.2 |
|
118.8 |
RPL08.INT.DHC.02230 |
RPL08.Interior.DHC - Priority - Install Drywall at Exterior Walls | OverHead | Not Started | 01/12/27 | 01/19/27 | 6.2 | 6.2 |
|
158.8 |
RPL08.INT.ENDC.1080 |
RPL08.Interior.End-Corr - Priority - Tape Finish Paint Priority Soffit both sides (Top Out) & Draft Blanket | Priority Walls & Overhead | Not Started | 01/12/27 | 01/21/27 | 8.8 | 8.8 |
|
210.0 |
RPL08.INT.ENDC.1100 |
RPL08.Interior.End-Corr - Priority - Install Mechanical Piping/ Refrigerant (Highside OH space) | Priority Walls & Overhead | Not Started | 01/12/27 | 01/19/27 | 6.2 | 6.2 |
|
213.8 |
RPL08.INT.SBC.03300 |
RPL08.Interior.SSB-Corridor - BoW -Install Fire Life Safety Lowside OH and In-wall | Balance of Walls & Overhead | Not Started | 01/12/27 | 01/21/27 | 8.8 | 8.8 |
|
157.5 |
RPL08.SKN.W.LO.01395 |
RPL08.SKIN.LO#16 - Install IMP Flashing | Build back Exterior Leave Out Walls #16 (SSB - North of Loading Dock) | Not Started | 01/12/27 | 01/19/27 | 6.2 | 6.2 |
|
168.8 |
DCC.B8.3155 |
[SSDCB3] GS Gear Delivered [DHD] | Connectivity | Not Started | 01/13/27 | 01/13/27 | 0.0 | 0.0 |
|
477.5 |
RPL08.INT.CTRC.1120 |
RPL08.Interior.Center-Corridor - Priority - Install Plumbing (Highside OH space) | Priority Walls & Overhead | Not Started | 01/13/27 | 01/20/27 | 6.2 | 6.2 |
|
117.5 |
RPL08.INT.CTRC.1140 |
RPL08.Interior.Center-Corridor - Priority - Install FA/ VESDA/ hangers & Heat Trace (Highside OH space) | Priority Walls & Overhead | Not Started | 01/13/27 | 01/20/27 | 6.2 | 6.2 |
|
117.5 |
RPL08.INT.DHA.01060 |
RPL08.Interior.DHA - OFE - LV Skids and TopHat - Set / Place / Anchor | OFE/MOFE & CFCI | Not Started | 01/13/27 | 02/03/27 | 18.8 | 18.8 |
|
101.2 |
RPL08.INT.DHA.01070 |
RPL08.Interior.DHA - OFE - MES Skids - Set / Place / Anchor | OFE/MOFE & CFCI | Not Started | 01/13/27 | 02/03/27 | 18.8 | 18.8 |
|
120.0 |
RPL08.INT.DHA.01080 |
RPL08.Interior.DHA - OFE - WBS Summary | OFE/MOFE & CFCI | Not Started | 01/13/27 | 04/22/27 | 86.2 | 86.2 |
|
142.5 |
RPL08.INT.DHB.01205 |
RPL08.Interior.DHB - MES Skids - EPMS Tie-Ins | DHB - MES Skids | Not Started | 01/13/27 | 02/10/27 | 25.0 | 25.0 |
|
160.0 |
RPL08.INT.DHB.01380 |
RPL08.Interior.DHB - Tie-ins - Control Fault Domain 2 - WBS Summary | Control Fault Domain 2 | Not Started | 01/13/27 | 04/16/27 | 81.2 | 81.2 |
|
122.5 |
RPL08.INT.DHB.02440 |
RPL08.Interior.DHB - OFE - Control Fault Domain 1 (Mech Side Aisle) | Control Fault Domain 1 | Not Started | 01/13/27 | 02/01/27 | 16.2 | 16.2 |
|
110.0 |
RPL08.INT.DHB.02720 |
RPL08.Interior.DHB - Control Fault Domain 2 - Install Duct (LV Side) | LV Side Tie-ins | Not Started | 01/13/27 | 01/19/27 | 5.0 | 5.0 |
|
153.8 |
RPL08.INT.DHD.02130 |
RPL08.Interior.DHD - Priority - Install Mechanical Piping | OverHead | Not Started | 01/13/27 | 01/29/27 | 15.0 | 15.0 |
|
148.8 |
RPL08.INT.SSBC.3360 |
RPL08.Interior.SSBC LO #06 - Hang Drywall | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 01/13/27 | 01/14/27 | 2.5 | 2.5 |
|
197.5 |
RPL08.EY.ENDC.1930 |
RPL08.EY.DHD.T1 - HAC Prefab prior to install for DH A | Tent 2 | Not Started | 01/14/27 | 01/28/27 | 12.5 | 12.5 |
|
105.0 |
RPL08.INT.SSBC.4220 |
RPL08.Interior.SSBC LO #07 - Fire Safing OH and In-wall | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 01/14/27 | 01/14/27 | 1.2 | 1.2 |
|
191.2 |
RPL08.INT.CTRC.01090 |
RPL08.Interior.Center-Corridor - BoW - Early Install Drywall for Ancillary Skid (Room #3.6) | Priority Wall Grid Line 8-16 / 8-17 | Not Started | 01/15/27 | 01/20/27 | 3.8 | 3.8 |
|
206.2 |
RPL08.INT.DHA.01090 |
RPL08.Interior.DHA - LV Skids and TopHat Tie-ins (LOE) | DHA - LV Skids and TopHat | Not Started | 01/15/27 | 02/17/27 | 27.5 | 27.5 |
|
152.5 |
RPL08.INT.DHA.01091 |
RPL08.Interior.DHA - LV Skids and TopHat - Set & Anchor Interconnects | DHA - LV Skids and TopHat | Not Started | 01/15/27 | 02/04/27 | 17.5 | 17.5 |
|
152.5 |
RPL08.INT.DHA.01100 |
RPL08.Interior.DHA - Tie-ins - WBS Summary | Tie-Ins | Not Started | 01/15/27 | 06/16/27 | 131.2 | 131.2 |
|
197.5 |
RPL08.INT.DHB.01440 |
RPL08.Interior.DHB - OFE - Control Fault Domain 3 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | Control Fault Domain 3 | Not Started | 01/15/27 | 03/02/27 | 38.8 | 38.8 |
|
136.2 |
RPL08.INT.DHB.01460 |
RPL08.Interior.DHB - Control Fault Domain 2 - Install LV Side Aisle HAC Busway | LV Side Tie-ins | Not Started | 01/15/27 | 01/21/27 | 5.0 | 5.0 |
|
162.5 |
RPL08.INT.DHB.02520 |
RPL08.Interior.DHB - OFE - Control Fault Domain 3 (LV Side Aisle) | Control Fault Domain 3 | Not Started | 01/15/27 | 01/21/27 | 5.0 | 5.0 |
|
160.0 |
RPL08.INT.SSB.01260 |
RPL08.Interior.SSB - BoW - Install Fire Life Safety Lowside OH and In-wall | Balance of Walls and OverHead | Not Started | 01/15/27 | 01/26/27 | 8.8 | 8.8 |
|
192.5 |
RPL08.INT.SSB.01800 |
RPL08.Interior.SSB - BoW - Install Plumbing Lowside OH and In-wall | Balance of Walls and OverHead | Not Started | 01/15/27 | 01/26/27 | 8.8 | 8.8 |
|
186.2 |
RPL08.INT.SSB.06680 |
RPL08.Interior.SSB - Final Finishes & Fixtures - Install Cement Board/ Drywall | Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) | Not Started | 01/15/27 | 01/22/27 | 6.2 | 6.2 |
|
316.2 |
RPL08.INT.SSBC.3400 |
RPL08.Interior.SSBC LO #06 - Tape Finish Paint | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 01/15/27 | 01/22/27 | 6.2 | 6.2 |
|
197.5 |
RPL08.INT.SSBC.4260 |
RPL08.Interior.SSBC LO #07 - Install Backing | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 01/15/27 | 01/15/27 | 1.2 | 1.2 |
|
191.2 |
RPL08.INT.DHB.01470 |
RPL08.Interior.DHB - Control Fault Domain 2 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 01/19/27 | 01/22/27 | 5.0 | 5.0 |
|
162.5 |
RPL08.INT.SSB.14260 |
RPL08.Interior.SSB LO #01 to #05 - Install Backing | OH & Framing | Not Started | 01/19/27 | 01/25/27 | 6.2 | 6.2 |
|
172.5 |
RPL08.INT.SSBC.4280 |
RPL08.Interior.SSBC LO #07 - QC - Backings/Walls | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 01/19/27 | 01/20/27 | 2.5 | 2.5 |
|
191.2 |
RPL08.CON.WP2.06000 |
RPL08.Conn - Interior GSIDFs - WBS Summary | GS.IDF (Interior) | Not Started | 01/20/27 | 08/09/27 | 175.0 | 175.0 |
|
297.5 |
RPL08.CON.WP2.06200 |
RPL08.Conn - GSIDF/DH B2 - WBS Summary | Int. IDF OFE/MOFE - GSIDF8B2 | Not Started | 01/20/27 | 02/17/27 | 25.0 | 25.0 |
|
416.2 |
RPL08.CON.WP2.06220 |
RPL08.Conn - GSIDF/DH B2 - Install Infrastructure (Racks, Waterfalls etc.) | Infrastructure | Not Started | 01/20/27 | 01/26/27 | 6.2 | 6.2 |
|
282.5 |
RPL08.CON.WP2.06400 |
RPL08.Conn - GSIDF/DH A2 - WBS Summary | Int. IDF OFE/MOFE - GSIDF8A2 | Not Started | 01/20/27 | 02/17/27 | 25.0 | 25.0 |
|
416.2 |
RPL08.CON.WP2.06420 |
RPL08.Conn - GSIDF/DH A2 - Install Infrastructure (Racks, Waterfalls etc.) | Infrastructure | Not Started | 01/20/27 | 01/26/27 | 6.2 | 6.2 |
|
295.0 |
RPL08.INT.DHB.01520 |
RPL08.Interior.DHB - Tie-ins - Control Fault Domain 3 (including IDF) - WBS Summary | Control Fault Domain 3 | Not Started | 01/20/27 | 04/23/27 | 82.5 | 82.5 |
|
191.2 |
RPL08.INT.DHB.02740 |
RPL08.Interior.DHB - Control Fault Domain 3 - Install Duct (LV Side) | LV Side Tie-ins | Not Started | 01/20/27 | 01/25/27 | 5.0 | 5.0 |
|
175.0 |
RPL08.INT.DHC.02110 |
RPL08.Interior.DHC - Priority - Install Plumbing | OverHead | Not Started | 01/20/27 | 01/26/27 | 6.2 | 6.2 |
|
158.8 |
RPL08.INT.ENDC.1140 |
RPL08.Interior.End-Corr - Priority - Install Plumbing (Highside OH space) | Priority Walls & Overhead | Not Started | 01/20/27 | 01/26/27 | 6.2 | 6.2 |
|
213.8 |
RPL08.INT.ENDC.1160 |
RPL08.Interior.End-Corr - Priority - Install FA (Highside OH space) | Priority Walls & Overhead | Not Started | 01/20/27 | 01/26/27 | 6.2 | 6.2 |
|
213.8 |
RPL08.SKN.W.LO.01420 |
RPL08.SKIN.LO#16 - Install IMP Insulated Metal Panels | Build back Exterior Leave Out Walls #16 (SSB - North of Loading Dock) | Not Started | 01/20/27 | 01/26/27 | 6.2 | 6.2 |
|
168.8 |
RPL08.EY.DHA.01220 |
RPL08.EY.DHA - Install MV, RMUs & Electrical Panels (Qty 10) | OFE | Not Started | 01/21/27 | 02/18/27 | 25.0 | 25.0 |
|
101.2 |
RPL08.INT.CTRC.01110 |
RPL08.Interior.Center-Corridor - BoW - Early Tape Finish Paint for Ancillary Skid (Room #3.6) | Priority Wall Grid Line 8-16 / 8-17 | Not Started | 01/21/27 | 01/27/27 | 6.2 | 6.2 |
|
206.2 |
RPL08.INT.CTRC.1200 |
RPL08.Interior.Center-Corridor - Priority - Install Fire Safing/ Seal Penetrations through Soffit (Highside OH space) | Priority Walls & Overhead | Not Started | 01/21/27 | 01/25/27 | 3.8 | 3.8 |
|
117.5 |
RPL08.INT.CTRC.1220 |
RPL08.Interior.Center-Corridor - BoW - Frame Balance of Wall | Balance of Walls & Overhead | Not Started | 01/21/27 | 01/27/27 | 6.2 | 6.2 |
|
117.5 |
RPL08.INT.CTRC.1230 |
RPL08.Interior.Center-Corridor - BoW - Balance Of Wall (ERAD, Maintance, Network infra, Spoke, Bathroom, etc) - WBS Summ | Balance of Walls & Overhead | Not Started | 01/21/27 | 07/07/27 | 145.0 | 145.0 |
|
117.5 |
RPL08.INT.CTRC.2020 |
RPL08.Interior.Center-Corridor - Priority - Fixed Draft/Smoke Curtain Patching | Priority Walls & Overhead | Not Started | 01/21/27 | 01/25/27 | 3.8 | 3.8 |
|
117.5 |
RPL08.INT.DHA.01110 |
RPL08.Interior.DHA - MES Skids Tie-ins (LOE) | DHA - MES Skids | Not Started | 01/21/27 | 03/08/27 | 40.0 | 40.0 |
|
138.8 |
RPL08.INT.DHA.01111 |
RPL08.Interior.DHA - MES Skids - Set & Anchor Interconnects | DHA - MES Skids | Not Started | 01/21/27 | 02/18/27 | 25.0 | 25.0 |
|
120.0 |
RPL08.INT.DHA.02340 |
RPL08.Interior.DHA - Priority - Install Security | OverHead | Not Started | 01/21/27 | 01/27/27 | 6.2 | 6.2 |
|
313.8 |
RPL08.INT.DHD.01050 |
RPL08.Interior.DHD - Priority - Install FA / Linear heat detection | OverHead | Not Started | 01/21/27 | 01/27/27 | 6.2 | 6.2 |
|
147.5 |
RPL08.INT.DHD.02150 |
RPL08.Interior.DHD - Priority - Install Electrical | OverHead | Not Started | 01/21/27 | 02/03/27 | 12.5 | 12.5 |
|
147.5 |
RPL08.INT.ENDC.01170 |
RPL08.Interior.End-Corridor - Install Security OH and In-wall | Fit out | Not Started | 01/21/27 | 01/29/27 | 8.8 | 8.8 |
|
247.5 |
RPL08.INT.ENDC.01180 |
RPL08.Interior.End-Corridor - Install Plumbing OH and In-wall | Fit out | Not Started | 01/21/27 | 02/02/27 | 11.2 | 11.2 |
|
250.0 |
RPL08.INT.SBC.03320 |
RPL08.Interior.SSB-Corridor - BoW - Install Plumbing Lowside OH and In-wall | Balance of Walls & Overhead | Not Started | 01/21/27 | 01/29/27 | 8.8 | 8.8 |
|
143.8 |
RPL08.INT.SSB.01190 |
RPL08.Interior.SSB - Loading Dock and Storage - Install Electrical Rough-In | Loading Dock and Storage | Not Started | 01/21/27 | 01/29/27 | 8.8 | 8.8 |
|
210.0 |
RPL08.INT.SSB.01410 |
RPL08.Interior.SSB - Loading Dock and Storage - Install DAS (Distribution Antenna System) | Loading Dock and Storage | Not Started | 01/21/27 | 01/27/27 | 6.2 | 6.2 |
|
268.8 |
RPL08.INT.SSB.01510 |
RPL08.Interior.SSB - Loading Dock and Storage - Install Door Frames | Loading Dock and Storage | Not Started | 01/21/27 | 01/27/27 | 6.2 | 6.2 |
|
212.5 |
RPL08.INT.SSB.01740 |
RPL08.Interior.SSB - Loading Dock and Storage - Install VAV's/Duct Branches | Loading Dock and Storage | Not Started | 01/21/27 | 02/03/27 | 12.5 | 12.5 |
|
206.2 |
RPL08.INT.SSB.02940 |
RPL08.Interior.SSB - Loading Dock and Storage - Install Blocking/Steel support Assembly for Metal Canopy | Loading Dock and Storage | Not Started | 01/21/27 | 01/27/27 | 6.2 | 6.2 |
|
215.0 |
RPL08.INT.SSBC.4360 |
RPL08.Interior.SSBC LO #07 - Hang Drywall | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 01/21/27 | 01/22/27 | 2.5 | 2.5 |
|
191.2 |
DCC.B8.3145 |
[SSDCB3] GS Gear Delivered [DHC] | Connectivity | Not Started | 01/22/27 | 01/22/27 | 0.0 | 0.0 |
|
470.0 |
RPL.08.D.70160.XR |
External Tie from RPL06 - Interior HAC Crew 2 Flow (RPL06.INT.DHC.02470) (2/2/27) | Internal Milestones (XREFs) | Not Started | 01/22/27 | 01/22/27 | 0.0 | 0.0 |
|
110.0 |
RPL08.INT.CTRC.8960 |
RPL08.Interior.Center-Corr - Priority - Hang Drywall Rock all Entry Fiber Rooms (Room #2.7) | Priority Wall Grid Line 8-16 / 8-17 | Not Started | 01/22/27 | 01/27/27 | 5.0 | 5.0 |
|
185.0 |
RPL08.INT.DHA.01092 |
RPL08.Interior.DHA - LV Skids and TopHat - Maintenance and Reserve Busways | DHA - LV Skids and TopHat | Not Started | 01/22/27 | 02/09/27 | 16.2 | 16.2 |
|
152.5 |
RPL08.INT.DHB.01580 |
RPL08.Interior.DHB - OFE - Control Fault Domain 4 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | Control Fault Domain 4 | Not Started | 01/22/27 | 03/16/27 | 46.2 | 46.2 |
|
143.8 |
RPL08.INT.DHB.01600 |
RPL08.Interior.DHB - Control Fault Domain 3 - Install LV Side Aisle HAC Busway | LV Side Tie-ins | Not Started | 01/22/27 | 01/27/27 | 5.0 | 5.0 |
|
205.0 |
RPL08.INT.DHB.02580 |
RPL08.Interior.DHB - OFE - Control Fault Domain 4 (LV Side Aisle) | Control Fault Domain 4 | Not Started | 01/22/27 | 01/27/27 | 5.0 | 5.0 |
|
175.0 |
RPL08.INT.ENDC.1120 |
RPL08.Interior.End-Corr - Priority GL8.27 - (P3) Frame Walls (Incl. Ancillary Room #3.6) | Priority Wall Grid Line 8-27 | Not Started | 01/22/27 | 01/28/27 | 6.2 | 6.2 |
|
210.0 |
RPL08.INT.SBC.03340 |
RPL08.Interior.SSB-Corridor - BoW - Install Security Lowside OH and In-wall | Balance of Walls & Overhead | Not Started | 01/22/27 | 02/01/27 | 8.8 | 8.8 |
|
177.5 |
RPL.08.D.83720.XG |
RMUs/MV Skids Set (Ready for Longhorn Pulls) - DHB | Give Milestones (XREFs) | Not Started | 01/25/27 | 01/25/27 | 0.0 | 0.0 |
|
467.5 |
RPL.08.D.83960.XG |
Ready for MV Cable Pull DH B (MVs - Qty 10)* | Give Milestones (XREFs) | Not Started | 01/25/27 | 01/25/27 | 0.0 | 0.0 |
|
467.5 |
RPL08.INT.DHB.01610 |
RPL08.Interior.DHB - Control Fault Domain 3 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 01/25/27 | 01/28/27 | 5.0 | 5.0 |
|
265.0 |
RPL08.INT.SSB.06700 |
RPL08.Interior.SSB - Final Finishes & Fixtures - Water Proofing/ Tape Paint | Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) | Not Started | 01/25/27 | 01/29/27 | 6.2 | 6.2 |
|
316.2 |
RPL08.INT.SSBC.3500 |
RPL08.Interior.SSBC LO #06 - Install DAS (Distribution Antenna System) | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 01/25/27 | 01/25/27 | 1.2 | 1.2 |
|
197.5 |
RPL08.INT.SSBC.3580 |
RPL08.Interior.SSBC LO #06 - Install Flooring Tiles/Resinous Flooring in specific rooms | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 01/25/27 | 01/27/27 | 3.8 | 3.8 |
|
201.2 |