Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL08 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:14 PM
· 5122 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
0
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL08.INT.SSBC.3720 |
RPL08.Interior.SSBC LO #06 - Fire Safing / Wall Finishes | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 01/25/27 | 01/26/27 | 2.5 | 2.5 |
|
197.5 |
RPL08.INT.SSBC.4400 |
RPL08.Interior.SSBC LO #07 - Tape Finish Paint | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 01/25/27 | 01/29/27 | 6.2 | 6.2 |
|
191.2 |
RPL08.EY.DHB.01250 |
RPL08.EY.DHB - Install Electrical Tie-ins (include penetration detail) | Tie-ins | Not Started | 01/26/27 | 02/08/27 | 12.5 | 12.5 |
|
103.8 |
RPL08.EY.DHB.01260 |
RPL08.EY.DHB - Tie-ins - WBS Summary | Tie-ins | Not Started | 01/26/27 | 03/31/27 | 56.2 | 56.2 |
|
223.8 |
RPL08.EY.DHB.01520 |
RPL08.EY.DHB - Install Generator including Tie-ins (#1 of Qty 2) | OFE | Not Started | 01/26/27 | 02/01/27 | 6.2 | 6.2 |
|
137.5 |
RPL08.INT.DHB.01660 |
RPL08.Interior.DHB - Tie-ins - Control Fault Domain 4 - WBS Summary | Control Fault Domain 4 | Not Started | 01/26/27 | 05/07/27 | 90.0 | 90.0 |
|
183.8 |
RPL08.INT.DHB.02760 |
RPL08.Interior.DHB - Control Fault Domain 4 - Install Duct (LV Side) | LV Side Tie-ins | Not Started | 01/26/27 | 01/29/27 | 5.0 | 5.0 |
|
190.0 |
RPL08.INT.ENDC.06820 |
RPL08.Interior.End-Corridor - Final Finishes & Fixtures - MEP Rough-In | Restrooms | Not Started | 01/26/27 | 02/01/27 | 6.2 | 6.2 |
|
260.0 |
RPL08.INT.SSB.14280 |
RPL08.Interior.SSB LO #01 to #05 - QC - Backings/Walls | OH & Framing | Not Started | 01/26/27 | 02/01/27 | 6.2 | 6.2 |
|
172.5 |
RPL08.INT.SSBC.3560 |
RPL08.Interior.SSBC LO #06 - Install Remaining Lights | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 01/26/27 | 01/28/27 | 3.8 | 3.8 |
|
197.5 |
RPL08.CON.WP2.06240 |
RPL08.Conn - GSIDF/DH B2 - Install Cabling (Pull, Splice & terminate) | Cabling | Not Started | 01/27/27 | 02/03/27 | 7.5 | 7.5 |
|
423.8 |
RPL08.CON.WP2.06260 |
RPL08.Conn - GSIDF/DH B2 - Install Copper, WAPs, Security Camera & Access Control | Cabling | Not Started | 01/27/27 | 02/11/27 | 15.0 | 15.0 |
|
282.5 |
RPL08.CON.WP2.06440 |
RPL08.Conn - GSIDF/DH A2 - Install Cabling (Pull, Splice & terminate) | Cabling | Not Started | 01/27/27 | 02/03/27 | 7.5 | 7.5 |
|
423.8 |
RPL08.CON.WP2.06460 |
RPL08.Conn - GSIDF/DH A2 - Install Copper, WAPs, Security Camera & Access Control | Cabling | Not Started | 01/27/27 | 02/11/27 | 15.0 | 15.0 |
|
295.0 |
RPL08.INT.ENDC.1200 |
RPL08.Interior.End-Corr - Priority - Install Fire Safing/ Seal Penetrations through Soffit (HighS. OH space) | Priority Walls & Overhead | Not Started | 01/27/27 | 01/29/27 | 3.8 | 3.8 |
|
213.8 |
RPL08.INT.ENDC.1660 |
RPL08.Interior.End-Corr - Priority - Fixed Draft/Smoke Curtain Patching | Priority Walls & Overhead | Not Started | 01/27/27 | 01/29/27 | 3.8 | 3.8 |
|
213.8 |
RPL08.INT.SSB.01220 |
RPL08.Interior.SSB - BoW - Install Security Lowside OH and In-wall | Balance of Walls and OverHead | Not Started | 01/27/27 | 02/04/27 | 8.8 | 8.8 |
|
272.5 |
RPL08.INT.SSB.01240 |
RPL08.Interior.SSB - BoW - Install VAV's/Duct Branches | Balance of Walls and OverHead | Not Started | 01/27/27 | 02/09/27 | 12.5 | 12.5 |
|
260.0 |
RPL08.INT.SSB.01820 |
RPL08.Interior.SSB - BoW - Mechanical Tie-In | Balance of Walls and OverHead | Not Started | 01/27/27 | 02/02/27 | 6.2 | 6.2 |
|
186.2 |
RPL08.INT.SSBC.3420 |
RPL08.Interior.SSBC LO #06 - Electrical Trim Out | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 01/27/27 | 01/28/27 | 2.5 | 2.5 |
|
197.5 |
RPL08.INT.SSBC.3440 |
RPL08.Interior.SSBC LO #06 - Security Trim Out | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 01/27/27 | 01/28/27 | 2.5 | 2.5 |
|
197.5 |
RPL08.SKN.W.LO.01440 |
RPL08.SKIN.LO#16 - Install IMP Flashing & Caulking | Build back Exterior Leave Out Walls #16 (SSB - North of Loading Dock) | Not Started | 01/27/27 | 02/02/27 | 6.2 | 6.2 |
|
168.8 |
RPL08.EY.DHB.01280 |
RPL08.EY.DHB - Install BMS/EPMS Tie-ins | Tie-ins | Not Started | 01/28/27 | 02/10/27 | 12.5 | 12.5 |
|
103.8 |
RPL08.INT.CTRC.1260 |
RPL08.Interior.Center-Corridor - BoW - Install Electrical Lowside OH and In-wall and Lights (Coordinate Lights location | Balance of Walls & Overhead | Not Started | 01/28/27 | 02/10/27 | 12.5 | 12.5 |
|
117.5 |
RPL08.INT.CTRC.1400 |
RPL08.Interior.Center-Corridor - BoW - Install Door Frames | Balance of Walls & Overhead | Not Started | 01/28/27 | 02/03/27 | 6.2 | 6.2 |
|
132.5 |
RPL08.INT.CTRC.8980 |
RPL08.Interior.Center-Corr - Priority - Tape, Paint & Finish Production Entry Fiber Rooms (Room #2.7) | Priority Wall Grid Line 8-16 / 8-17 | Not Started | 01/28/27 | 02/03/27 | 6.2 | 6.2 |
|
185.0 |
RPL08.INT.DHA.01120 |
RPL08.Interior.DHA - OFE - Control Fault Domain 1 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | Control Fault Domain 1 | Not Started | 01/28/27 | 02/22/27 | 21.2 | 21.2 |
|
105.0 |
RPL08.INT.DHA.02325 |
RPL08.Interior.DHA - Priority - Install Controls / EPMS / BMS | OverHead | Not Started | 01/28/27 | 02/02/27 | 5.0 | 5.0 |
|
313.8 |
RPL08.INT.DHA.03480 |
RPL08.Interior.DHA - OFE - Control Fault Domain 1 (LV Side Aisle) | Control Fault Domain 1 | Not Started | 01/28/27 | 02/03/27 | 6.2 | 6.2 |
|
105.0 |
RPL08.INT.DHB.01220 |
RPL08.Interior.DHB - Control Fault Domain 1 - Install Duct (MES Side) | Remaining Tie-ins post Mech Side Aisle install | Not Started | 01/28/27 | 02/25/27 | 25.0 | 25.0 |
|
110.0 |
RPL08.INT.DHB.01230 |
RPL08.Interior.DHB - Control Fault Domain 1 - Install Vesda / FA | Remaining Tie-ins post Mech Side Aisle install | Not Started | 01/28/27 | 02/25/27 | 25.0 | 25.0 |
|
122.5 |
RPL08.INT.DHB.01240 |
RPL08.Interior.DHB - Control Fault Domain 1 - Install TW | Remaining Tie-ins post Mech Side Aisle install | Not Started | 01/28/27 | 02/25/27 | 25.0 | 25.0 |
|
110.0 |
RPL08.INT.DHB.01720 |
RPL08.Interior.DHB - OFE - Control Fault Domain 5 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | Control Fault Domain 5 | Not Started | 01/28/27 | 04/02/27 | 56.2 | 56.2 |
|
147.5 |
RPL08.INT.DHB.01740 |
RPL08.Interior.DHB - Control Fault Domain 4 - Install LV Side Aisle HAC Busway | LV Side Tie-ins | Not Started | 01/28/27 | 02/02/27 | 5.0 | 5.0 |
|
220.0 |
RPL08.INT.DHB.02120 |
RPL08.Interior.DHB - Control Fault Domain 1 - Install FW | Remaining Tie-ins post Mech Side Aisle install | Not Started | 01/28/27 | 02/25/27 | 25.0 | 25.0 |
|
110.0 |
RPL08.INT.DHB.02640 |
RPL08.Interior.DHB - OFE - Control Fault Domain 5 (LV Side Aisle) | Control Fault Domain 5 | Not Started | 01/28/27 | 02/02/27 | 5.0 | 5.0 |
|
186.2 |
RPL08.INT.DHD.01060 |
RPL08.Interior.DHD - OFE - LV Skids and TopHat - Set / Place / Anchor | OFE/MOFE & CFCI | Not Started | 01/28/27 | 02/16/27 | 16.2 | 16.2 |
|
147.5 |
RPL08.INT.DHD.01070 |
RPL08.Interior.DHD - OFE - MES Skids - Set / Place / Anchor | OFE/MOFE & CFCI | Not Started | 01/28/27 | 02/16/27 | 16.2 | 16.2 |
|
171.2 |
RPL08.INT.DHD.01080 |
RPL08.Interior.DHD - OFE - WBS Summary | OFE/MOFE & CFCI | Not Started | 01/28/27 | 06/03/27 | 110.0 | 110.0 |
|
151.2 |
RPL08.INT.DHD.02210 |
RPL08.Interior.DHD - Priority - Install Temp Doors Frame Hardware | OverHead | Not Started | 01/28/27 | 02/01/27 | 3.8 | 3.8 |
|
406.2 |
RPL08.INT.ENDC.6220 |
RPL08.Interior.End-Corr - Priority GL8.27 - (P3) Install MEP In-Wall/Backing | Priority Wall Grid Line 8-27 | Not Started | 01/28/27 | 02/01/27 | 3.8 | 3.8 |
|
273.8 |
RPL08.SKN.SSB.01125 |
RPL08.SKIN.SSB - Install Metal Canopy | Glazing, Doors and Ext Devices | Not Started | 01/28/27 | 01/29/27 | 2.5 | 2.5 |
|
272.5 |
RPL08.INT.DHA.01093 |
RPL08.Interior.DHA - LV Skids and TopHat - Top Hat Busway | DHA - LV Skids and TopHat | Not Started | 01/29/27 | 02/17/27 | 16.2 | 16.2 |
|
152.5 |
RPL08.INT.DHA.01112 |
RPL08.Interior.DHA - MES Skids - Piping Tie-Ins & Inspections | DHA - MES Skids | Not Started | 01/29/27 | 02/26/27 | 25.0 | 25.0 |
|
120.0 |
RPL08.INT.DHA.03500 |
RPL08.Interior.DHA - OFE - Control Fault Domain 1 (HAC) | Control Fault Domain 1 | Not Started | 01/29/27 | 02/19/27 | 18.8 | 18.8 |
|
105.0 |
RPL08.INT.DHB.01750 |
RPL08.Interior.DHB - Control Fault Domain 4 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 01/29/27 | 02/03/27 | 5.0 | 5.0 |
|
265.0 |
RPL08.INT.ENDC.6200 |
RPL08.Interior.End-Corr - Priority GL8.27 - (P3) Install IMP Wall | Priority Wall Grid Line 8-27 | Not Started | 01/29/27 | 02/03/27 | 5.0 | 5.0 |
|
210.0 |
RPL08.INT.SSBC.3520 |
RPL08.Interior.SSBC LO #06 - Plumbing Trim Out | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 01/29/27 | 02/01/27 | 2.5 | 2.5 |
|
197.5 |
RPL08.INT.SSBC.3600 |
RPL08.Interior.SSBC LO #06 - Install Asset Tags | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 01/29/27 | 01/29/27 | 1.2 | 1.2 |
|
197.5 |
RPL08.INT.DHA.01160 |
RPL08.Interior.DHA - Tie-ins - Control Fault Domain 1 - WBS Summary | Control Fault Domain 1 | Not Started | 02/01/27 | 04/15/27 | 65.0 | 65.0 |
|
105.0 |
RPL08.INT.DHA.03780 |
RPL08.Interior.DHA - Control Fault Domain 1 - Install Duct (LV Side) | LV Side Tie-ins | Not Started | 02/01/27 | 02/05/27 | 6.2 | 6.2 |
|
120.0 |
RPL08.INT.DHB.01800 |
RPL08.Interior.DHB - Tie-ins - Control Fault Domain 5 - WBS Summary | Control Fault Domain 5 | Not Started | 02/01/27 | 05/25/27 | 100.0 | 100.0 |
|
153.8 |
RPL08.INT.DHB.01870 |
RPL08.Interior.DHB - Control Fault Domain 5 - Install LV Side Aisle HAC Busway | LV Side Tie-ins | Not Started | 02/01/27 | 02/04/27 | 5.0 | 5.0 |
|
237.5 |
RPL08.INT.DHB.02480 |
RPL08.Interior.DHB - OFE - Control Fault Domain 2 (HAC) | Control Fault Domain 2 | Not Started | 02/01/27 | 02/12/27 | 12.5 | 12.5 |
|
122.5 |
RPL08.INT.DHB.02780 |
RPL08.Interior.DHB - Control Fault Domain 5 - Install Duct (LV Side) | LV Side Tie-ins | Not Started | 02/01/27 | 02/04/27 | 5.0 | 5.0 |
|
203.8 |
RPL08.INT.DHC.02130 |
RPL08.Interior.DHC - Priority - Install Mechanical Piping | OverHead | Not Started | 02/01/27 | 02/17/27 | 15.0 | 15.0 |
|
148.8 |
RPL08.INT.DHD.01090 |
RPL08.Interior.DHD - LV Skids and TopHat Tie-ins (LOE) | DHD - LV Skids and TopHat | Not Started | 02/01/27 | 03/02/27 | 26.2 | 26.2 |
|
280.0 |
RPL08.INT.DHD.01091 |
RPL08.Interior.DHD - LV Skids and TopHat - Set & Anchor Interconnects | DHD - LV Skids and TopHat | Not Started | 02/01/27 | 02/18/27 | 16.2 | 16.2 |
|
280.0 |
RPL08.INT.DHD.01100 |
RPL08.Interior.DHD - Tie-ins - WBS Summary | Tie-Ins | Not Started | 02/01/27 | 07/26/27 | 152.5 | 152.5 |
|
261.2 |
RPL08.INT.ENDC.01200 |
RPL08.Interior.End-Corridor - Install Controls / EPMS / BMS | Fit out | Not Started | 02/01/27 | 02/04/27 | 5.0 | 5.0 |
|
247.5 |
RPL08.INT.SBC.03360 |
RPL08.Interior.SSB-Corridor - BoW - Install VAV's/Duct Branches | Balance of Walls & Overhead | Not Started | 02/01/27 | 02/05/27 | 6.2 | 6.2 |
|
215.0 |
RPL08.INT.SBC.03460 |
RPL08.Interior.SSB-Corridor - BoW - Mechanical Tie-In | Balance of Walls & Overhead | Not Started | 02/01/27 | 02/05/27 | 6.2 | 6.2 |
|
143.8 |
RPL08.INT.SSB.01420 |
RPL08.Interior.SSB - Loading Dock and Storage - Install Dock Levelers, Pads, Exterior lights and Lock | Loading Dock and Storage | Not Started | 02/01/27 | 02/09/27 | 8.8 | 8.8 |
|
212.5 |
RPL08.INT.SSB.01900 |
RPL08.Interior.SSB - Final Finishes & Fixtures - Casework | Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) | Not Started | 02/01/27 | 02/09/27 | 8.8 | 8.8 |
|
316.2 |
RPL08.INT.SSB.06000 |
RPL08.Interior.SSB LO #16 - Close Exterior LO #16 (SSB - North of Loading Dock) WBS Summary | Leave Out Wall #16 (SSB - North of Loading Dock) | Not Started | 02/01/27 | 04/22/27 | 71.2 | 71.2 |
|
168.8 |
RPL08.INT.SSB.06020 |
RPL08.Interior.SSB LO #16 - IMP In Wall MEP | Leave Out Wall #16 (SSB - North of Loading Dock) | Not Started | 02/01/27 | 02/02/27 | 2.5 | 2.5 |
|
168.8 |
RPL08.INT.SSBC.01180 |
RPL08.Interior.SSB-Corridor - Install Fitout (GS.MDF Mech & Elec2x, Riser Room, GS Fiber Entry Room, Carrier MDF) - WBS | Fit out | Not Started | 02/01/27 | 06/09/27 | 112.5 | 112.5 |
|
188.8 |
RPL08.INT.SSBC.01210 |
RPL08.Interior.SSB-Corridor - Install Split Systems/Humidifiers | Fit out | Not Started | 02/01/27 | 02/05/27 | 6.2 | 6.2 |
|
228.8 |
RPL08.INT.SSBC.01390 |
RPL08.Interior.SSB-Corridor - Install Battery **?? | Fit out | Not Started | 02/01/27 | 02/12/27 | 12.5 | 12.5 |
|
198.8 |
RPL08.INT.SSBC.01590 |
RPL08.Interior.SSB-Corridor - Install Mechanical Tie-Ins (needs to micro plan) | Fit out | Not Started | 02/01/27 | 02/05/27 | 6.2 | 6.2 |
|
235.0 |
RPL08.INT.SSBC.03380 |
RPL08.Interior.SSB-Corridor - Install Split Systems/Humidifiers | OFE/MOFE & CFCI | Not Started | 02/01/27 | 02/05/27 | 6.2 | 6.2 |
|
221.2 |
RPL08.INT.SSBC.3540 |
RPL08.Interior.SSBC LO #06 - Fire Life Safety Trim Out | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 02/01/27 | 02/01/27 | 1.2 | 1.2 |
|
197.5 |
RPL08.INT.SSBC.3620 |
RPL08.Interior.SSBC LO #06 - Install Door (Verify with Trades before installation) | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 02/01/27 | 02/01/27 | 1.2 | 1.2 |
|
197.5 |
RPL08.INT.SSBC.4500 |
RPL08.Interior.SSBC LO #07 - Install DAS (Distribution Antenna System) | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 02/01/27 | 02/01/27 | 1.2 | 1.2 |
|
191.2 |
RPL08.INT.SSBC.4580 |
RPL08.Interior.SSBC LO #07 - Install Flooring Tiles/Resinous Flooring in specific rooms | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 02/01/27 | 02/03/27 | 3.8 | 3.8 |
|
195.0 |
RPL08.INT.SSBC.4720 |
RPL08.Interior.SSBC LO #07 - Fire Safing / Wall Finishes | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 02/01/27 | 02/02/27 | 2.5 | 2.5 |
|
191.2 |
RPL08.SKN.SSB.01150 |
RPL08.SKIN.SSB - Install Perm Doors | Glazing, Doors and Ext Devices | Not Started | 02/01/27 | 02/02/27 | 2.5 | 2.5 |
|
272.5 |
ICM.B8.1805 |
[SSDCB3] Delivery of Substation MSG Alpha (First Delivery) NOT DPR SCOPE | Construction | Not Started | 02/02/27 | 02/02/27 | 0.0 | 0.0 |
|
460.0 |
RPL08.INT.DHA.01113 |
RPL08.Interior.DHA - MES Skids - CDU Tie-Ins ( 2 per day) | DHA - MES Skids | Not Started | 02/02/27 | 03/02/27 | 25.0 | 25.0 |
|
138.8 |
RPL08.INT.DHB.01890 |
RPL08.Interior.DHB - Control Fault Domain 5 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 02/02/27 | 02/05/27 | 5.0 | 5.0 |
|
247.5 |
RPL08.INT.ENDC.06860 |
RPL08.Interior.End-Corridor - Final Finishes & Fixtures - Hang Tape Bed and Fire/Caulking | Restrooms | Not Started | 02/02/27 | 02/08/27 | 6.2 | 6.2 |
|
272.5 |
RPL08.INT.ENDC.07040 |
RPL08.Interior.End-Corridor - Final Finishes & Fixtures - Framing RO Verification, Tile Finish & ADA Verification (Pre | Restrooms | Not Started | 02/02/27 | 02/08/27 | 6.2 | 6.2 |
|
260.0 |
RPL08.INT.ENDC.6240 |
RPL08.Interior.End-Corr - Priority GL8.27 - (P3) Hang Drywall (Both Sides) | Priority Wall Grid Line 8-27 | Not Started | 02/02/27 | 02/04/27 | 3.8 | 3.8 |
|
273.8 |
RPL08.INT.SBC.03440 |
RPL08.Interior.SSB-Corridor - BoW - Install Electrical - Lighitng Inverter Room (XX.S2.XX) | Balance of Walls & Overhead | Not Started | 02/02/27 | 02/10/27 | 8.8 | 8.8 |
|
177.5 |
RPL08.INT.SSB.14180 |
RPL08.Interior.SSB LO #01 to #05 - Install Door Frames | OH & Framing | Not Started | 02/02/27 | 02/03/27 | 2.5 | 2.5 |
|
172.5 |
RPL08.INT.SSBC.3640 |
RPL08.Interior.SSBC LO #06 - Electrical L2 Checklist Completion | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 02/02/27 | 02/16/27 | 12.5 | 12.5 |
|
197.5 |
RPL08.INT.SSBC.4560 |
RPL08.Interior.SSBC LO #07 - Install Remaining Lights | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 02/02/27 | 02/04/27 | 3.8 | 3.8 |
|
191.2 |
GCD.RPL08.1827 |
Delivery of RMU - (First Delivery) - RPL08 - DHC&D | Construction Milestones | Not Started | 02/03/27 | 02/03/27 | 0.0 | 0.0 |
|
215.0 |
RPL08.INT.CTRC.1280 |
RPL08.Interior.Center-Corridor - BoW - Install Fire Life Safety Lowside OH and In-wall | Balance of Walls & Overhead | Not Started | 02/03/27 | 02/11/27 | 8.8 | 8.8 |
|
131.2 |
RPL08.INT.DHA.01220 |
RPL08.Interior.DHA - Control Fault Domain 1 - Install LV Side Aisle HAC Busway | LV Side Tie-ins | Not Started | 02/03/27 | 02/09/27 | 6.2 | 6.2 |
|
128.8 |
RPL08.INT.DHA.03520 |
RPL08.Interior.DHA - OFE - Control Fault Domain 1 (Mech Side Aisle) | Control Fault Domain 1 | Not Started | 02/03/27 | 02/22/27 | 16.2 | 16.2 |
|
105.0 |
RPL08.INT.SSB.01290 |
RPL08.Interior.SSB - BoW - Frame Hard Lid | Balance of Walls and OverHead | Not Started | 02/03/27 | 02/09/27 | 6.2 | 6.2 |
|
186.2 |
RPL08.INT.SSB.06040 |
RPL08.Interior.SSB LO #16 - QC - Backings/Walls | Leave Out Wall #16 (SSB - North of Loading Dock) | Not Started | 02/03/27 | 02/03/27 | 1.2 | 1.2 |
|
168.8 |
RPL08.INT.SSBC.4420 |
RPL08.Interior.SSBC LO #07 - Electrical Trim Out | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 02/03/27 | 02/04/27 | 2.5 | 2.5 |
|
191.2 |
RPL08.INT.SSBC.4440 |
RPL08.Interior.SSBC LO #07 - Security Trim Out | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 02/03/27 | 02/04/27 | 2.5 | 2.5 |
|
191.2 |
RPL08.EY.DHD.01220 |
RPL08.EY.DHD - Install MV, RMUs & Electrical Panels (Qty 8) | OFE | Not Started | 02/04/27 | 03/04/27 | 25.0 | 25.0 |
|
215.0 |
RPL08.EY.DHD.01230 |
RPL08.EY.DHD - OFE - MV - WBS Summary | OFE | Not Started | 02/04/27 | 07/29/27 | 152.5 | 152.5 |
|
216.2 |
RPL08.INT.CTRC.9000 |
RPL08.Interior.Center-Corridor - Priority - MEP OH over Cable Tray | Priority Walls & Overhead | Not Started | 02/04/27 | 02/12/27 | 8.8 | 8.8 |
|
185.0 |
RPL08.INT.DHA.01114 |
RPL08.Interior.DHA - MES Skids - BMS Tie-Ins ( 2 per day) | DHA - MES Skids | Not Started | 02/04/27 | 03/04/27 | 25.0 | 25.0 |
|
138.8 |
RPL08.INT.DHA.01210 |
RPL08.Interior.DHA - Control Fault Domain 1 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 02/04/27 | 02/10/27 | 6.2 | 6.2 |
|
128.8 |