Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL08 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:14 PM · 5122 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
0
Completed
0
In Progress
0
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL08.INT.SSBC.3720 RPL08.Interior.SSBC LO #06 - Fire Safing / Wall Finishes Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 01/25/27 01/26/27 2.5 2.5
0%
197.5
RPL08.INT.SSBC.4400 RPL08.Interior.SSBC LO #07 - Tape Finish Paint Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 01/25/27 01/29/27 6.2 6.2
0%
191.2
RPL08.EY.DHB.01250 RPL08.EY.DHB - Install Electrical Tie-ins (include penetration detail) Tie-ins Not Started 01/26/27 02/08/27 12.5 12.5
0%
103.8
RPL08.EY.DHB.01260 RPL08.EY.DHB - Tie-ins - WBS Summary Tie-ins Not Started 01/26/27 03/31/27 56.2 56.2
0%
223.8
RPL08.EY.DHB.01520 RPL08.EY.DHB - Install Generator including Tie-ins (#1 of Qty 2) OFE Not Started 01/26/27 02/01/27 6.2 6.2
0%
137.5
RPL08.INT.DHB.01660 RPL08.Interior.DHB - Tie-ins - Control Fault Domain 4 - WBS Summary Control Fault Domain 4 Not Started 01/26/27 05/07/27 90.0 90.0
0%
183.8
RPL08.INT.DHB.02760 RPL08.Interior.DHB - Control Fault Domain 4 - Install Duct (LV Side) LV Side Tie-ins Not Started 01/26/27 01/29/27 5.0 5.0
0%
190.0
RPL08.INT.ENDC.06820 RPL08.Interior.End-Corridor - Final Finishes & Fixtures - MEP Rough-In Restrooms Not Started 01/26/27 02/01/27 6.2 6.2
0%
260.0
RPL08.INT.SSB.14280 RPL08.Interior.SSB LO #01 to #05 - QC - Backings/Walls OH & Framing Not Started 01/26/27 02/01/27 6.2 6.2
0%
172.5
RPL08.INT.SSBC.3560 RPL08.Interior.SSBC LO #06 - Install Remaining Lights Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 01/26/27 01/28/27 3.8 3.8
0%
197.5
RPL08.CON.WP2.06240 RPL08.Conn - GSIDF/DH B2 - Install Cabling (Pull, Splice & terminate) Cabling Not Started 01/27/27 02/03/27 7.5 7.5
0%
423.8
RPL08.CON.WP2.06260 RPL08.Conn - GSIDF/DH B2 - Install Copper, WAPs, Security Camera & Access Control Cabling Not Started 01/27/27 02/11/27 15.0 15.0
0%
282.5
RPL08.CON.WP2.06440 RPL08.Conn - GSIDF/DH A2 - Install Cabling (Pull, Splice & terminate) Cabling Not Started 01/27/27 02/03/27 7.5 7.5
0%
423.8
RPL08.CON.WP2.06460 RPL08.Conn - GSIDF/DH A2 - Install Copper, WAPs, Security Camera & Access Control Cabling Not Started 01/27/27 02/11/27 15.0 15.0
0%
295.0
RPL08.INT.ENDC.1200 RPL08.Interior.End-Corr - Priority - Install Fire Safing/ Seal Penetrations through Soffit (HighS. OH space) Priority Walls & Overhead Not Started 01/27/27 01/29/27 3.8 3.8
0%
213.8
RPL08.INT.ENDC.1660 RPL08.Interior.End-Corr - Priority - Fixed Draft/Smoke Curtain Patching Priority Walls & Overhead Not Started 01/27/27 01/29/27 3.8 3.8
0%
213.8
RPL08.INT.SSB.01220 RPL08.Interior.SSB - BoW - Install Security Lowside OH and In-wall Balance of Walls and OverHead Not Started 01/27/27 02/04/27 8.8 8.8
0%
272.5
RPL08.INT.SSB.01240 RPL08.Interior.SSB - BoW - Install VAV's/Duct Branches Balance of Walls and OverHead Not Started 01/27/27 02/09/27 12.5 12.5
0%
260.0
RPL08.INT.SSB.01820 RPL08.Interior.SSB - BoW - Mechanical Tie-In Balance of Walls and OverHead Not Started 01/27/27 02/02/27 6.2 6.2
0%
186.2
RPL08.INT.SSBC.3420 RPL08.Interior.SSBC LO #06 - Electrical Trim Out Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 01/27/27 01/28/27 2.5 2.5
0%
197.5
RPL08.INT.SSBC.3440 RPL08.Interior.SSBC LO #06 - Security Trim Out Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 01/27/27 01/28/27 2.5 2.5
0%
197.5
RPL08.SKN.W.LO.01440 RPL08.SKIN.LO#16 - Install IMP Flashing & Caulking Build back Exterior Leave Out Walls #16 (SSB - North of Loading Dock) Not Started 01/27/27 02/02/27 6.2 6.2
0%
168.8
RPL08.EY.DHB.01280 RPL08.EY.DHB - Install BMS/EPMS Tie-ins Tie-ins Not Started 01/28/27 02/10/27 12.5 12.5
0%
103.8
RPL08.INT.CTRC.1260 RPL08.Interior.Center-Corridor - BoW - Install Electrical Lowside OH and In-wall and Lights (Coordinate Lights location Balance of Walls & Overhead Not Started 01/28/27 02/10/27 12.5 12.5
0%
117.5
RPL08.INT.CTRC.1400 RPL08.Interior.Center-Corridor - BoW - Install Door Frames Balance of Walls & Overhead Not Started 01/28/27 02/03/27 6.2 6.2
0%
132.5
RPL08.INT.CTRC.8980 RPL08.Interior.Center-Corr - Priority - Tape, Paint & Finish Production Entry Fiber Rooms (Room #2.7) Priority Wall Grid Line 8-16 / 8-17 Not Started 01/28/27 02/03/27 6.2 6.2
0%
185.0
RPL08.INT.DHA.01120 RPL08.Interior.DHA - OFE - Control Fault Domain 1 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary Control Fault Domain 1 Not Started 01/28/27 02/22/27 21.2 21.2
0%
105.0
RPL08.INT.DHA.02325 RPL08.Interior.DHA - Priority - Install Controls / EPMS / BMS OverHead Not Started 01/28/27 02/02/27 5.0 5.0
0%
313.8
RPL08.INT.DHA.03480 RPL08.Interior.DHA - OFE - Control Fault Domain 1 (LV Side Aisle) Control Fault Domain 1 Not Started 01/28/27 02/03/27 6.2 6.2
0%
105.0
RPL08.INT.DHB.01220 RPL08.Interior.DHB - Control Fault Domain 1 - Install Duct (MES Side) Remaining Tie-ins post Mech Side Aisle install Not Started 01/28/27 02/25/27 25.0 25.0
0%
110.0
RPL08.INT.DHB.01230 RPL08.Interior.DHB - Control Fault Domain 1 - Install Vesda / FA Remaining Tie-ins post Mech Side Aisle install Not Started 01/28/27 02/25/27 25.0 25.0
0%
122.5
RPL08.INT.DHB.01240 RPL08.Interior.DHB - Control Fault Domain 1 - Install TW Remaining Tie-ins post Mech Side Aisle install Not Started 01/28/27 02/25/27 25.0 25.0
0%
110.0
RPL08.INT.DHB.01720 RPL08.Interior.DHB - OFE - Control Fault Domain 5 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary Control Fault Domain 5 Not Started 01/28/27 04/02/27 56.2 56.2
0%
147.5
RPL08.INT.DHB.01740 RPL08.Interior.DHB - Control Fault Domain 4 - Install LV Side Aisle HAC Busway LV Side Tie-ins Not Started 01/28/27 02/02/27 5.0 5.0
0%
220.0
RPL08.INT.DHB.02120 RPL08.Interior.DHB - Control Fault Domain 1 - Install FW Remaining Tie-ins post Mech Side Aisle install Not Started 01/28/27 02/25/27 25.0 25.0
0%
110.0
RPL08.INT.DHB.02640 RPL08.Interior.DHB - OFE - Control Fault Domain 5 (LV Side Aisle) Control Fault Domain 5 Not Started 01/28/27 02/02/27 5.0 5.0
0%
186.2
RPL08.INT.DHD.01060 RPL08.Interior.DHD - OFE - LV Skids and TopHat - Set / Place / Anchor OFE/MOFE & CFCI Not Started 01/28/27 02/16/27 16.2 16.2
0%
147.5
RPL08.INT.DHD.01070 RPL08.Interior.DHD - OFE - MES Skids - Set / Place / Anchor OFE/MOFE & CFCI Not Started 01/28/27 02/16/27 16.2 16.2
0%
171.2
RPL08.INT.DHD.01080 RPL08.Interior.DHD - OFE - WBS Summary OFE/MOFE & CFCI Not Started 01/28/27 06/03/27 110.0 110.0
0%
151.2
RPL08.INT.DHD.02210 RPL08.Interior.DHD - Priority - Install Temp Doors Frame Hardware OverHead Not Started 01/28/27 02/01/27 3.8 3.8
0%
406.2
RPL08.INT.ENDC.6220 RPL08.Interior.End-Corr - Priority GL8.27 - (P3) Install MEP In-Wall/Backing Priority Wall Grid Line 8-27 Not Started 01/28/27 02/01/27 3.8 3.8
0%
273.8
RPL08.SKN.SSB.01125 RPL08.SKIN.SSB - Install Metal Canopy Glazing, Doors and Ext Devices Not Started 01/28/27 01/29/27 2.5 2.5
0%
272.5
RPL08.INT.DHA.01093 RPL08.Interior.DHA - LV Skids and TopHat - Top Hat Busway DHA - LV Skids and TopHat Not Started 01/29/27 02/17/27 16.2 16.2
0%
152.5
RPL08.INT.DHA.01112 RPL08.Interior.DHA - MES Skids - Piping Tie-Ins & Inspections DHA - MES Skids Not Started 01/29/27 02/26/27 25.0 25.0
0%
120.0
RPL08.INT.DHA.03500 RPL08.Interior.DHA - OFE - Control Fault Domain 1 (HAC) Control Fault Domain 1 Not Started 01/29/27 02/19/27 18.8 18.8
0%
105.0
RPL08.INT.DHB.01750 RPL08.Interior.DHB - Control Fault Domain 4 - Install LV Side Aisle Cable Tray LV Side Tie-ins Not Started 01/29/27 02/03/27 5.0 5.0
0%
265.0
RPL08.INT.ENDC.6200 RPL08.Interior.End-Corr - Priority GL8.27 - (P3) Install IMP Wall Priority Wall Grid Line 8-27 Not Started 01/29/27 02/03/27 5.0 5.0
0%
210.0
RPL08.INT.SSBC.3520 RPL08.Interior.SSBC LO #06 - Plumbing Trim Out Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 01/29/27 02/01/27 2.5 2.5
0%
197.5
RPL08.INT.SSBC.3600 RPL08.Interior.SSBC LO #06 - Install Asset Tags Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 01/29/27 01/29/27 1.2 1.2
0%
197.5
RPL08.INT.DHA.01160 RPL08.Interior.DHA - Tie-ins - Control Fault Domain 1 - WBS Summary Control Fault Domain 1 Not Started 02/01/27 04/15/27 65.0 65.0
0%
105.0
RPL08.INT.DHA.03780 RPL08.Interior.DHA - Control Fault Domain 1 - Install Duct (LV Side) LV Side Tie-ins Not Started 02/01/27 02/05/27 6.2 6.2
0%
120.0
RPL08.INT.DHB.01800 RPL08.Interior.DHB - Tie-ins - Control Fault Domain 5 - WBS Summary Control Fault Domain 5 Not Started 02/01/27 05/25/27 100.0 100.0
0%
153.8
RPL08.INT.DHB.01870 RPL08.Interior.DHB - Control Fault Domain 5 - Install LV Side Aisle HAC Busway LV Side Tie-ins Not Started 02/01/27 02/04/27 5.0 5.0
0%
237.5
RPL08.INT.DHB.02480 RPL08.Interior.DHB - OFE - Control Fault Domain 2 (HAC) Control Fault Domain 2 Not Started 02/01/27 02/12/27 12.5 12.5
0%
122.5
RPL08.INT.DHB.02780 RPL08.Interior.DHB - Control Fault Domain 5 - Install Duct (LV Side) LV Side Tie-ins Not Started 02/01/27 02/04/27 5.0 5.0
0%
203.8
RPL08.INT.DHC.02130 RPL08.Interior.DHC - Priority - Install Mechanical Piping OverHead Not Started 02/01/27 02/17/27 15.0 15.0
0%
148.8
RPL08.INT.DHD.01090 RPL08.Interior.DHD - LV Skids and TopHat Tie-ins (LOE) DHD - LV Skids and TopHat Not Started 02/01/27 03/02/27 26.2 26.2
0%
280.0
RPL08.INT.DHD.01091 RPL08.Interior.DHD - LV Skids and TopHat - Set & Anchor Interconnects DHD - LV Skids and TopHat Not Started 02/01/27 02/18/27 16.2 16.2
0%
280.0
RPL08.INT.DHD.01100 RPL08.Interior.DHD - Tie-ins - WBS Summary Tie-Ins Not Started 02/01/27 07/26/27 152.5 152.5
0%
261.2
RPL08.INT.ENDC.01200 RPL08.Interior.End-Corridor - Install Controls / EPMS / BMS Fit out Not Started 02/01/27 02/04/27 5.0 5.0
0%
247.5
RPL08.INT.SBC.03360 RPL08.Interior.SSB-Corridor - BoW - Install VAV's/Duct Branches Balance of Walls & Overhead Not Started 02/01/27 02/05/27 6.2 6.2
0%
215.0
RPL08.INT.SBC.03460 RPL08.Interior.SSB-Corridor - BoW - Mechanical Tie-In Balance of Walls & Overhead Not Started 02/01/27 02/05/27 6.2 6.2
0%
143.8
RPL08.INT.SSB.01420 RPL08.Interior.SSB - Loading Dock and Storage - Install Dock Levelers, Pads, Exterior lights and Lock Loading Dock and Storage Not Started 02/01/27 02/09/27 8.8 8.8
0%
212.5
RPL08.INT.SSB.01900 RPL08.Interior.SSB - Final Finishes & Fixtures - Casework Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) Not Started 02/01/27 02/09/27 8.8 8.8
0%
316.2
RPL08.INT.SSB.06000 RPL08.Interior.SSB LO #16 - Close Exterior LO #16 (SSB - North of Loading Dock) WBS Summary Leave Out Wall #16 (SSB - North of Loading Dock) Not Started 02/01/27 04/22/27 71.2 71.2
0%
168.8
RPL08.INT.SSB.06020 RPL08.Interior.SSB LO #16 - IMP In Wall MEP Leave Out Wall #16 (SSB - North of Loading Dock) Not Started 02/01/27 02/02/27 2.5 2.5
0%
168.8
RPL08.INT.SSBC.01180 RPL08.Interior.SSB-Corridor - Install Fitout (GS.MDF Mech & Elec2x, Riser Room, GS Fiber Entry Room, Carrier MDF) - WBS Fit out Not Started 02/01/27 06/09/27 112.5 112.5
0%
188.8
RPL08.INT.SSBC.01210 RPL08.Interior.SSB-Corridor - Install Split Systems/Humidifiers Fit out Not Started 02/01/27 02/05/27 6.2 6.2
0%
228.8
RPL08.INT.SSBC.01390 RPL08.Interior.SSB-Corridor - Install Battery **?? Fit out Not Started 02/01/27 02/12/27 12.5 12.5
0%
198.8
RPL08.INT.SSBC.01590 RPL08.Interior.SSB-Corridor - Install Mechanical Tie-Ins (needs to micro plan) Fit out Not Started 02/01/27 02/05/27 6.2 6.2
0%
235.0
RPL08.INT.SSBC.03380 RPL08.Interior.SSB-Corridor - Install Split Systems/Humidifiers OFE/MOFE & CFCI Not Started 02/01/27 02/05/27 6.2 6.2
0%
221.2
RPL08.INT.SSBC.3540 RPL08.Interior.SSBC LO #06 - Fire Life Safety Trim Out Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 02/01/27 02/01/27 1.2 1.2
0%
197.5
RPL08.INT.SSBC.3620 RPL08.Interior.SSBC LO #06 - Install Door (Verify with Trades before installation) Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 02/01/27 02/01/27 1.2 1.2
0%
197.5
RPL08.INT.SSBC.4500 RPL08.Interior.SSBC LO #07 - Install DAS (Distribution Antenna System) Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 02/01/27 02/01/27 1.2 1.2
0%
191.2
RPL08.INT.SSBC.4580 RPL08.Interior.SSBC LO #07 - Install Flooring Tiles/Resinous Flooring in specific rooms Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 02/01/27 02/03/27 3.8 3.8
0%
195.0
RPL08.INT.SSBC.4720 RPL08.Interior.SSBC LO #07 - Fire Safing / Wall Finishes Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 02/01/27 02/02/27 2.5 2.5
0%
191.2
RPL08.SKN.SSB.01150 RPL08.SKIN.SSB - Install Perm Doors Glazing, Doors and Ext Devices Not Started 02/01/27 02/02/27 2.5 2.5
0%
272.5
ICM.B8.1805 [SSDCB3] Delivery of Substation MSG Alpha (First Delivery) NOT DPR SCOPE Construction Not Started 02/02/27 02/02/27 0.0 0.0
0%
460.0
RPL08.INT.DHA.01113 RPL08.Interior.DHA - MES Skids - CDU Tie-Ins ( 2 per day) DHA - MES Skids Not Started 02/02/27 03/02/27 25.0 25.0
0%
138.8
RPL08.INT.DHB.01890 RPL08.Interior.DHB - Control Fault Domain 5 - Install LV Side Aisle Cable Tray LV Side Tie-ins Not Started 02/02/27 02/05/27 5.0 5.0
0%
247.5
RPL08.INT.ENDC.06860 RPL08.Interior.End-Corridor - Final Finishes & Fixtures - Hang Tape Bed and Fire/Caulking Restrooms Not Started 02/02/27 02/08/27 6.2 6.2
0%
272.5
RPL08.INT.ENDC.07040 RPL08.Interior.End-Corridor - Final Finishes & Fixtures - Framing RO Verification, Tile Finish & ADA Verification (Pre Restrooms Not Started 02/02/27 02/08/27 6.2 6.2
0%
260.0
RPL08.INT.ENDC.6240 RPL08.Interior.End-Corr - Priority GL8.27 - (P3) Hang Drywall (Both Sides) Priority Wall Grid Line 8-27 Not Started 02/02/27 02/04/27 3.8 3.8
0%
273.8
RPL08.INT.SBC.03440 RPL08.Interior.SSB-Corridor - BoW - Install Electrical - Lighitng Inverter Room (XX.S2.XX) Balance of Walls & Overhead Not Started 02/02/27 02/10/27 8.8 8.8
0%
177.5
RPL08.INT.SSB.14180 RPL08.Interior.SSB LO #01 to #05 - Install Door Frames OH & Framing Not Started 02/02/27 02/03/27 2.5 2.5
0%
172.5
RPL08.INT.SSBC.3640 RPL08.Interior.SSBC LO #06 - Electrical L2 Checklist Completion Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 02/02/27 02/16/27 12.5 12.5
0%
197.5
RPL08.INT.SSBC.4560 RPL08.Interior.SSBC LO #07 - Install Remaining Lights Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 02/02/27 02/04/27 3.8 3.8
0%
191.2
GCD.RPL08.1827 Delivery of RMU - (First Delivery) - RPL08 - DHC&D Construction Milestones Not Started 02/03/27 02/03/27 0.0 0.0
0%
215.0
RPL08.INT.CTRC.1280 RPL08.Interior.Center-Corridor - BoW - Install Fire Life Safety Lowside OH and In-wall Balance of Walls & Overhead Not Started 02/03/27 02/11/27 8.8 8.8
0%
131.2
RPL08.INT.DHA.01220 RPL08.Interior.DHA - Control Fault Domain 1 - Install LV Side Aisle HAC Busway LV Side Tie-ins Not Started 02/03/27 02/09/27 6.2 6.2
0%
128.8
RPL08.INT.DHA.03520 RPL08.Interior.DHA - OFE - Control Fault Domain 1 (Mech Side Aisle) Control Fault Domain 1 Not Started 02/03/27 02/22/27 16.2 16.2
0%
105.0
RPL08.INT.SSB.01290 RPL08.Interior.SSB - BoW - Frame Hard Lid Balance of Walls and OverHead Not Started 02/03/27 02/09/27 6.2 6.2
0%
186.2
RPL08.INT.SSB.06040 RPL08.Interior.SSB LO #16 - QC - Backings/Walls Leave Out Wall #16 (SSB - North of Loading Dock) Not Started 02/03/27 02/03/27 1.2 1.2
0%
168.8
RPL08.INT.SSBC.4420 RPL08.Interior.SSBC LO #07 - Electrical Trim Out Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 02/03/27 02/04/27 2.5 2.5
0%
191.2
RPL08.INT.SSBC.4440 RPL08.Interior.SSBC LO #07 - Security Trim Out Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 02/03/27 02/04/27 2.5 2.5
0%
191.2
RPL08.EY.DHD.01220 RPL08.EY.DHD - Install MV, RMUs & Electrical Panels (Qty 8) OFE Not Started 02/04/27 03/04/27 25.0 25.0
0%
215.0
RPL08.EY.DHD.01230 RPL08.EY.DHD - OFE - MV - WBS Summary OFE Not Started 02/04/27 07/29/27 152.5 152.5
0%
216.2
RPL08.INT.CTRC.9000 RPL08.Interior.Center-Corridor - Priority - MEP OH over Cable Tray Priority Walls & Overhead Not Started 02/04/27 02/12/27 8.8 8.8
0%
185.0
RPL08.INT.DHA.01114 RPL08.Interior.DHA - MES Skids - BMS Tie-Ins ( 2 per day) DHA - MES Skids Not Started 02/04/27 03/04/27 25.0 25.0
0%
138.8
RPL08.INT.DHA.01210 RPL08.Interior.DHA - Control Fault Domain 1 - Install LV Side Aisle Cable Tray LV Side Tie-ins Not Started 02/04/27 02/10/27 6.2 6.2
0%
128.8