Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL08 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:14 PM · 5122 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
0
Completed
0
In Progress
0
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL08.INT.DHA.01230 RPL08.Interior.DHA - OFE - Control Fault Domain 2 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary Control Fault Domain 2 Not Started 02/04/27 03/08/27 27.5 27.5
0%
117.5
RPL08.INT.DHA.03540 RPL08.Interior.DHA - OFE - Control Fault Domain 2 (LV Side Aisle) Control Fault Domain 2 Not Started 02/04/27 02/09/27 5.0 5.0
0%
127.5
RPL08.INT.DHB.01260 RPL08.Interior.DHB - Control Fault Domain 1 - Pull BMS from panel to devices Remaining Tie-ins post Mech Side Aisle install Not Started 02/04/27 03/04/27 25.0 25.0
0%
122.5
RPL08.INT.DHB.01270 RPL08.Interior.DHB - Control Fault Domain 1 - Pull EMPS from panel to devices Remaining Tie-ins post Mech Side Aisle install Not Started 02/04/27 03/04/27 25.0 25.0
0%
122.5
RPL08.INT.DHB.01280 RPL08.Interior.DHB - Control Fault Domain 1 - Set UPS and Panel (2) Remaining Tie-ins post Mech Side Aisle install Not Started 02/04/27 03/04/27 25.0 25.0
0%
110.0
RPL08.INT.DHB.02500 RPL08.Interior.DHB - OFE - Control Fault Domain 2 (Mech Side Aisle) Control Fault Domain 2 Not Started 02/04/27 02/16/27 10.0 10.0
0%
122.5
RPL08.INT.DHC.01050 RPL08.Interior.DHC - Priority - Install FA / Linear heat detection OverHead Not Started 02/04/27 02/10/27 6.2 6.2
0%
147.5
RPL08.INT.DHC.02150 RPL08.Interior.DHC - Priority - Install Electrical OverHead Not Started 02/04/27 02/18/27 12.5 12.5
0%
147.5
RPL08.INT.DHD.01110 RPL08.Interior.DHD - MES Skids Tie-ins (LOE) DHD - MES Skids Not Started 02/04/27 03/16/27 35.0 35.0
0%
267.5
RPL08.INT.DHD.01111 RPL08.Interior.DHD - MES Skids - Set & Anchor Interconnects DHD - MES Skids Not Started 02/04/27 02/26/27 20.0 20.0
0%
267.5
RPL08.INT.DHD.02170 RPL08.Interior.DHD - Priority - Install Security OverHead Not Started 02/04/27 02/05/27 2.5 2.5
0%
403.8
RPL08.INT.ENDC.1205 RPL08.Interior.End-Corridor - Balance Of Wall - (ERAD, Maintance, Network infra, Spoke, Bathroom, etc) - WBS Summary Balance of Walls & Overhead Not Started 02/04/27 09/01/27 182.5 182.5
0%
165.0
RPL08.INT.ENDC.1220 RPL08.Interior.End-Corridor - Frame Balance of Wall Balance of Walls & Overhead Not Started 02/04/27 02/10/27 6.2 6.2
0%
210.0
RPL08.INT.ENDC.6140 RPL08.Interior.End-Corridor - Early In-wall for Ancillary Skids (Room #3.6) Priority Wall Grid Line 8-27 Not Started 02/04/27 02/08/27 3.8 3.8
0%
282.5
RPL08.INT.SSB.01250 RPL08.Interior.SSB - Loading Dock and Storage - Install Security Loading Dock and Storage Not Started 02/04/27 02/12/27 8.8 8.8
0%
206.2
RPL08.INT.SSB.01470 RPL08.Interior.SSB - Loading Dock and Storage - Install Unit Heaters Loading Dock and Storage Not Started 02/04/27 02/10/27 6.2 6.2
0%
271.2
RPL08.INT.SSB.01760 RPL08.Interior.SSB - Loading Dock and Storage - Mechanical Tie-In Loading Dock and Storage Not Started 02/04/27 02/10/27 6.2 6.2
0%
271.2
RPL08.INT.SSB.01780 RPL08.Interior.SSB - Loading Dock and Storage - Install Split Systems/Humidifiers Loading Dock and Storage Not Started 02/04/27 02/10/27 6.2 6.2
0%
265.0
RPL08.INT.SSB.06060 RPL08.Interior.SSB LO #16 - Hang Exterior Wall Drywall Leave Out Wall #16 (SSB - North of Loading Dock) Not Started 02/04/27 02/05/27 2.5 2.5
0%
168.8
RPL08.INT.SSB.14340 RPL08.Interior.SSB LO #01 to #05 - MEPF Hard Lid Rough-In/ Close up Inspection OH & Framing Not Started 02/04/27 02/09/27 5.0 5.0
0%
172.5
RPL08.SKN.S.LO.01100 RPL08.SKIN.LO#17 - Close Exterior Leave Out #17 CC (South) WBS Summary Build back Exterior Leave Out Walls #17 (CC - South) Not Started 02/04/27 03/01/27 21.2 21.2
0%
162.5
RPL08.SKN.S.LO.03020 RPL08.SKIN.LO#17 - Pour back Stemwall Build back Exterior Leave Out Walls #17 (CC - South) Not Started 02/04/27 02/05/27 2.5 2.5
0%
162.5
RPL08.INT.DHD.01092 RPL08.Interior.DHD - LV Skids and TopHat - Maintenance and Reserve Busways DHD - LV Skids and TopHat Not Started 02/05/27 02/23/27 15.0 15.0
0%
280.0
RPL08.INT.ENDC.01160 RPL08.Interior.End-Corridor - OFE - DHC (1x GS.IDF) C2 OFE/MOFE & CFCI Not Started 02/05/27 02/11/27 6.2 6.2
0%
236.2
RPL08.INT.ENDC.01210 RPL08.Interior.End-Corridor - Install Fire Life Safety OH and In-wall Fit out Not Started 02/05/27 02/19/27 12.5 12.5
0%
247.5
RPL08.INT.ENDC.6260 RPL08.Interior.End-Corr - Priority GL8.27 - (P3) Tape Finish Paint (Both Sides) Priority Wall Grid Line 8-27 Not Started 02/05/27 02/11/27 6.2 6.2
0%
273.8
RPL08.INT.SSBC.4520 RPL08.Interior.SSBC LO #07 - Plumbing Trim Out Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 02/05/27 02/08/27 2.5 2.5
0%
191.2
RPL08.INT.SSBC.4600 RPL08.Interior.SSBC LO #07 - Install Asset Tags Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 02/05/27 02/05/27 1.2 1.2
0%
191.2
RPL08.INT.DHA.01115 RPL08.Interior.DHA - MES Skids - EPMS Tie-Ins ( 2 per day) DHA - MES Skids Not Started 02/08/27 03/08/27 25.0 25.0
0%
138.8
RPL08.INT.DHA.01300 RPL08.Interior.DHA - Tie-ins - Control Fault Domain 2 - WBS Summary Control Fault Domain 2 Not Started 02/08/27 05/06/27 77.5 77.5
0%
117.5
RPL08.INT.DHA.03800 RPL08.Interior.DHA - Control Fault Domain 2 - Install Duct (LV Side) LV Side Tie-ins Not Started 02/08/27 02/11/27 5.0 5.0
0%
145.0
RPL08.INT.DHD.02190 RPL08.Interior.DHD - Priority - Install Controls / EPMS / BMS OverHead Not Started 02/08/27 02/10/27 3.8 3.8
0%
403.8
RPL08.INT.SBC.03400 RPL08.Interior.SSB-Corridor - BoW - Install Controls / EPMS / BMS OH and In-wall Balance of Walls & Overhead Not Started 02/08/27 02/12/27 6.2 6.2
0%
215.0
RPL08.INT.SBC.03480 RPL08.Interior.SSB-Corridor - BoW - Frame Hard Lid Balance of Walls & Overhead Not Started 02/08/27 02/12/27 6.2 6.2
0%
143.8
RPL08.INT.SSB.06080 RPL08.Interior.SSB LO #16 - Tape Finish Paint Leave Out Wall #16 (SSB - North of Loading Dock) Not Started 02/08/27 02/12/27 6.2 6.2
0%
168.8
RPL08.INT.SSBC.01230 RPL08.Interior.SSB-Corridor - Install Remaining Refrigerant Line Fit out Not Started 02/08/27 02/12/27 6.2 6.2
0%
228.8
RPL08.INT.SSBC.4540 RPL08.Interior.SSBC LO #07 - Fire Life Safety Trim Out Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 02/08/27 02/08/27 1.2 1.2
0%
191.2
RPL08.INT.SSBC.4620 RPL08.Interior.SSBC LO #07 - Install Door (Verify with Trades before installation) Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 02/08/27 02/08/27 1.2 1.2
0%
191.2
RPL08.SKN.S.LO.03040 RPL08.SKIN.LO#17 - Cure Stemwall Build back Exterior Leave Out Walls #17 (CC - South) Not Started 02/08/27 02/17/27 8.8 8.8
0%
162.5
RPL08.INT.ENDC.07060 RPL08.Interior.End-Corridor - Final Finishes & Fixtures - Install Cement Board/ Drywall Restrooms Not Started 02/09/27 02/16/27 6.2 6.2
0%
260.0
RPL08.INT.ENDC.6160 RPL08.Interior.End-Corridor - Hang Early Drywall & DFH for Ancillary Skids (Room #3.6) Priority Wall Grid Line 8-27 Not Started 02/09/27 02/10/27 2.5 2.5
0%
282.5
RPL08.INT.SSBC.3660 RPL08.Interior.SSBC LO #06 - Mechanical L2 Checklist Completion Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 02/09/27 02/23/27 12.5 12.5
0%
197.5
RPL08.INT.SSBC.4640 RPL08.Interior.SSBC LO #07 - Electrical L2 Checklist Completion Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 02/09/27 02/23/27 12.5 12.5
0%
191.2
RPL08.INT.DHA.01350 RPL08.Interior.DHA - OFE - Control Fault Domain 3 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary Control Fault Domain 3 Not Started 02/10/27 03/22/27 35.0 35.0
0%
131.2
RPL08.INT.DHA.01370 RPL08.Interior.DHA - Control Fault Domain 2 - Install LV Side Aisle HAC Busway LV Side Tie-ins Not Started 02/10/27 02/16/27 5.0 5.0
0%
153.8
RPL08.INT.DHA.03600 RPL08.Interior.DHA - OFE - Control Fault Domain 3 (LV Side Aisle) Control Fault Domain 3 Not Started 02/10/27 02/16/27 5.0 5.0
0%
135.0
RPL08.INT.SSB.01230 RPL08.Interior.SSB - BoW - Install Controls / EPMS / BMS OH and In-wall Balance of Walls and OverHead Not Started 02/10/27 02/19/27 8.8 8.8
0%
260.0
RPL08.INT.SSB.01310 RPL08.Interior.SSB - BoW - MEPF Hard Lid Rough-In Balance of Walls and OverHead Not Started 02/10/27 02/17/27 6.2 6.2
0%
186.2
RPL08.INT.SSB.01530 RPL08.Interior.SSB - Loading Dock and Storage - Install OverHead Doors Loading Dock and Storage Not Started 02/10/27 02/24/27 12.5 12.5
0%
212.5
RPL08.INT.SSB.02420 RPL08.Interior.SSB - Final Finishes & Fixtures - Fixture Install (Lights) Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) Not Started 02/10/27 02/19/27 8.8 8.8
0%
343.8
RPL08.INT.SSB.05780 RPL08.Interior.SSB - BoW - QC - Walls Balance of Walls and OverHead Not Started 02/10/27 02/17/27 6.2 6.2
0%
186.2
RPL08.INT.SSB.06740 RPL08.Interior.SSB - Final Finishes & Fixtures - Framing RO Verification, Tile Finish & ADA Verification (Post Drywall) Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) Not Started 02/10/27 02/17/27 6.2 6.2
0%
316.2
RPL08.INT.SSB.14360 RPL08.Interior.SSB LO #01 to #05 - Hang Drywall OH & Framing Not Started 02/10/27 02/19/27 8.8 8.8
0%
172.5
RPL08.INT.SSB.14500 RPL08.Interior.SSB LO #01 to #05 - Install DAS (Distribution Antenna System) Finishes Not Started 02/10/27 02/17/27 6.2 6.2
0%
186.2
RPL08.EY.DHB.01290 RPL08.EY.DHB - Install Sleeves MEPL Hardscape and Landscape Not Started 02/11/27 02/18/27 6.2 6.2
0%
261.2
RPL08.EY.DHB.01300 RPL08.EY.DHB - MV Loop - L2 Checklist Completion Tie-ins Not Started 02/11/27 02/25/27 12.5 12.5
0%
103.8
RPL08.EY.DHB.01320 RPL08.EY.DHB - Install Hardscape and Landscape - WBS Summary Hardscape and Landscape Not Started 02/11/27 04/16/27 56.2 56.2
0%
396.2
RPL08.INT.CTRC.1300 RPL08.Interior.Center-Corridor - BoW - Install Plumbing Lowside OH and In-wall Balance of Walls & Overhead Not Started 02/11/27 02/22/27 8.8 8.8
0%
117.5
RPL08.INT.DHA.01380 RPL08.Interior.DHA - Control Fault Domain 2 - Install LV Side Aisle Cable Tray LV Side Tie-ins Not Started 02/11/27 02/17/27 5.0 5.0
0%
153.8
RPL08.INT.DHB.01300 RPL08.Interior.DHB - Control Fault Domain 1 - Install Mechanical Side Aisle Cable Tray Remaining Tie-ins post Mech Side Aisle install Not Started 02/11/27 03/11/27 25.0 25.0
0%
110.0
RPL08.INT.DHC.01060 RPL08.Interior.DHC - OFE - LV Skids and TopHat - Set / Place / Anchor OFE/MOFE & CFCI Not Started 02/11/27 03/02/27 16.2 16.2
0%
147.5
RPL08.INT.DHC.01070 RPL08.Interior.DHC - OFE - MES Skids - Set / Place / Anchor OFE/MOFE & CFCI Not Started 02/11/27 03/02/27 16.2 16.2
0%
147.5
RPL08.INT.DHC.01080 RPL08.Interior.DHC - OFE - WBS Summary OFE/MOFE & CFCI Not Started 02/11/27 06/23/27 115.0 115.0
0%
142.5
RPL08.INT.DHD.01120 RPL08.Interior.DHD - OFE - Control Fault Domain 1 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary Control Fault Domain 1 Not Started 02/11/27 04/21/27 60.0 60.0
0%
158.8
RPL08.INT.DHD.02270 RPL08.Interior.DHD - OFE - Control Fault Domain 1 (LV Side Aisle) Control Fault Domain 1 Not Started 02/11/27 02/18/27 6.2 6.2
0%
190.0
RPL08.INT.ENDC.1240 RPL08.Interior.End-Corridor - BoW - Install Mechanical Piping/ Refrigerant Lowside OH and in-wall Balance of Walls & Overhead Not Started 02/11/27 02/18/27 6.2 6.2
0%
210.0
RPL08.INT.ENDC.1400 RPL08.Interior.End-Corridor - BoW - Install Door Frames Balance of Walls & Overhead Not Started 02/11/27 02/18/27 6.2 6.2
0%
293.8
RPL08.INT.ENDC.6180 RPL08.Interior.End-Corridor - Early Tape Finish Paint for Ancillary Skids (Room #3.6) Priority Wall Grid Line 8-27 Not Started 02/11/27 02/18/27 6.2 6.2
0%
282.5
DCC.B8.3245 [SSDCB3] CorpNet/Security/FacNet Ready [DHC] Connectivity Not Started 02/12/27 02/12/27 0.0 0.0
0%
416.2
DCC.B8.3255 [SSDCB3] CorpNet/Security/FacNet Ready [DHD] Connectivity Not Started 02/12/27 02/12/27 0.0 0.0
0%
416.2
RPL08.CON.WP2.06280 RPL08.Conn - GSIDF/DH B2 - Install & Test Network (FIM) Network Not Started 02/12/27 02/17/27 3.8 3.8
0%
416.2
RPL08.CON.WP2.06480 RPL08.Conn - GSIDF/DH A2 - Install & Test Network (FIM) Network Not Started 02/12/27 02/17/27 3.8 3.8
0%
416.2
RPL08.CON.WP2.06800 RPL08.Conn - GSIDF/DH C2 - WBS Summary Int. IDF OFE/MOFE - GSIDF8C2 Not Started 02/12/27 03/09/27 21.2 21.2
0%
430.0
RPL08.CON.WP2.06820 RPL08.Conn - GSIDF/DH C2 - Install Infrastructure (Racks, Waterfalls etc.) Infrastructure Not Started 02/12/27 02/19/27 6.2 6.2
0%
381.2
RPL08.INT.CTRC.1320 RPL08.Interior.Center-Corridor - BoW - Install Security Lowside OH and In-wall Balance of Walls & Overhead Not Started 02/12/27 02/23/27 8.8 8.8
0%
183.8
RPL08.INT.DHA.01430 RPL08.Interior.DHA - Tie-ins - Control Fault Domain 3 (including IDF) - WBS Summary Control Fault Domain 3 Not Started 02/12/27 05/13/27 78.8 78.8
0%
191.2
RPL08.INT.DHA.03820 RPL08.Interior.DHA - Control Fault Domain 3 - Install Duct (LV Side) LV Side Tie-ins Not Started 02/12/27 02/18/27 5.0 5.0
0%
166.2
RPL08.INT.DHD.01093 RPL08.Interior.DHD - LV Skids and TopHat - Top Hat Busway DHD - LV Skids and TopHat Not Started 02/12/27 03/02/27 15.0 15.0
0%
280.0
RPL08.INT.DHD.01112 RPL08.Interior.DHD - MES Skids - Piping Tie-Ins & Inspections DHD - MES Skids Not Started 02/12/27 03/08/27 20.0 20.0
0%
267.5
RPL08.INT.ENDC.01190 RPL08.Interior.End-Corridor - OFE - DHD (1x GS.IDF) D2 OFE/MOFE & CFCI Not Started 02/12/27 02/19/27 6.2 6.2
0%
236.2
RPL08.INT.CTRC.1940 RPL08.Interior.Center-Corridor - BoW - Install Vertical Tube Steel Support for Cable Tray (IFP Add) Balance of Walls & Overhead Not Started 02/16/27 02/19/27 5.0 5.0
0%
185.0
RPL08.INT.DHB.02540 RPL08.Interior.DHB - OFE - Control Fault Domain 3 (HAC) Control Fault Domain 3 Not Started 02/16/27 03/01/27 12.5 12.5
0%
136.2
RPL08.INT.DHC.01090 RPL08.Interior.DHC - LV Skids and TopHat Tie-ins (LOE) DHC - LV Skids and TopHat Not Started 02/16/27 03/16/27 26.2 26.2
0%
276.2
RPL08.INT.DHC.01091 RPL08.Interior.DHC - LV Skids and TopHat - Set & Anchor Interconnects DHC - LV Skids and TopHat Not Started 02/16/27 03/04/27 16.2 16.2
0%
276.2
RPL08.INT.DHC.01100 RPL08.Interior.DHC - Tie-ins - WBS Summary Tie-Ins Not Started 02/16/27 08/13/27 157.5 157.5
0%
253.8
RPL08.INT.DHD.01160 RPL08.Interior.DHD - Tie-ins - Control Fault Domain 1 - WBS Summary Control Fault Domain 1 Not Started 02/16/27 06/10/27 101.2 101.2
0%
191.2
RPL08.INT.DHD.02510 RPL08.Interior.DHD - Control Fault Domain 1 - Install Duct (LV Side) LV Side Tie-ins Not Started 02/16/27 02/22/27 6.2 6.2
0%
242.5
RPL08.INT.SBC.03500 RPL08.Interior.SSB-Corridor - BoW - MEPF Hard Lid Rough-In/ Close of Inspection Balance of Walls & Overhead Not Started 02/16/27 02/24/27 8.8 8.8
0%
153.8
RPL08.INT.SBC.03520 RPL08.Interior.SSB-Corridor - BoW - Install Blocking/Steel support Assembly for Metal Canopy Balance of Walls & Overhead Not Started 02/16/27 02/22/27 6.2 6.2
0%
143.8
RPL08.INT.SSB.01270 RPL08.Interior.SSB - Loading Dock and Storage - Install Controls / EPMS / BMS Loading Dock and Storage Not Started 02/16/27 02/19/27 5.0 5.0
0%
206.2
RPL08.INT.SSB.06100 RPL08.Interior.SSB LO #16 - Install Mechanical Piping/ Refrigerant Lowside OH Leave Out Wall #16 (SSB - North of Loading Dock) Not Started 02/16/27 02/22/27 6.2 6.2
0%
171.2
RPL08.INT.SSB.06120 RPL08.Interior.SSB LO #16 - Install Electrical Lowside OH Leave Out Wall #16 (SSB - North of Loading Dock) Not Started 02/16/27 02/24/27 8.8 8.8
0%
172.5
RPL08.INT.SSB.06140 RPL08.Interior.SSB LO #16 - Install Plumbing Lowside OH Leave Out Wall #16 (SSB - North of Loading Dock) Not Started 02/16/27 02/24/27 8.8 8.8
0%
168.8
RPL08.INT.SSB.06160 RPL08.Interior.SSB LO #16 - Install Fire Life Safety Lowside OH Leave Out Wall #16 (SSB - North of Loading Dock) Not Started 02/16/27 02/18/27 3.8 3.8
0%
173.8
RPL08.INT.SSB.06180 RPL08.Interior.SSB LO #16 - Install Security Lowside OH Leave Out Wall #16 (SSB - North of Loading Dock) Not Started 02/16/27 02/19/27 5.0 5.0
0%
172.5
RPL08.INT.SSB.06200 RPL08.Interior.SSB LO #16 - Install Controls / EPMS / BMS OH Leave Out Wall #16 (SSB - North of Loading Dock) Not Started 02/16/27 02/18/27 3.8 3.8
0%
173.8
RPL08.INT.SSB.06220 RPL08.Interior.SSB LO #16 - Fire Safing OH Leave Out Wall #16 (SSB - North of Loading Dock) Not Started 02/16/27 02/22/27 6.2 6.2
0%
171.2
RPL08.INT.SSBC.01410 RPL08.Interior.SSB-Corridor - Battery Connection Fit out Not Started 02/16/27 02/22/27 6.2 6.2
0%
198.8
RPL08.INT.CTRC.01670 RPL08.Interior.Center-Corridor - MOFE - Ancillary Skids Qty2 (DH A) OFE/MOFE & CFCI Not Started 02/17/27 03/02/27 12.5 12.5
0%
190.0
RPL08.INT.CTRC.01690 RPL08.Interior.Center-Corridor - MOFE - Ancillary Skids Qty2 (DH B) OFE/MOFE & CFCI Not Started 02/17/27 03/02/27 12.5 12.5
0%
198.8