Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL08 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:14 PM · 5122 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
0
Completed
0
In Progress
0
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL08.INT.DHC.01490 RPL08.Interior.DHC - OFE - Control Fault Domain 4 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary Control Fault Domain 4 Not Started 03/18/27 06/23/27 85.0 85.0
0%
142.5
RPL08.INT.DHC.01510 RPL08.Interior.DHC - Control Fault Domain 3 - Install LV Side Aisle HAC Busway LV Side Tie-ins Not Started 03/18/27 03/23/27 5.0 5.0
0%
302.5
RPL08.INT.DHC.02450 RPL08.Interior.DHC - OFE - Control Fault Domain 4 (LV Side Aisle) Control Fault Domain 4 Not Started 03/18/27 03/23/27 5.0 5.0
0%
212.5
RPL08.INT.SBC.03580 RPL08.Interior.SSB-Corridor - BoW - Tape Finish Paint (Both side of Corridor Wall) Balance of Walls & Overhead Not Started 03/18/27 03/22/27 3.8 3.8
0%
143.8
RPL08.WP4.010240 RPL08.Conn DHB.11 Pull Trunk (192F) [FSW<>SSW] FSW<>SSW Not Started 03/18/27 03/18/27 1.2 1.2
0%
245.0
RPL08.WP4.010260 RPL08.Conn DHB.12 Pull Trunk (192F) [FSW<>SSW] FSW<>SSW Not Started 03/18/27 03/18/27 1.2 1.2
0%
245.0
RPL08.WP4.010560 RPL08.Conn DHB.11.01<>01 Pull Simplex Jumper (SC<>LC) [PON (Active, In-Row)] Jumpers Not Started 03/18/27 03/22/27 3.8 3.8
0%
235.0
RPL08.WP4.010580 RPL08.Conn DHB.12.05<>05 Pull Simplex Jumper (SC<>LC) [PON (Active, In-Row)] Jumpers Not Started 03/18/27 03/22/27 3.8 3.8
0%
235.0
RPL08.WP4.010600 RPL08.Conn DHB.11 Install Ext. Trunk (24F) [PON (Passive, In-Rack)] In-Rack Not Started 03/18/27 03/22/27 3.8 3.8
0%
253.8
RPL08.WP4.010620 RPL08.Conn DHB.12 Install Ext. Trunk (24F) [PON (Passive, In-Rack)] In-Rack Not Started 03/18/27 03/22/27 3.8 3.8
0%
253.8
RPL08.CON.WP3B.01060 RPL08.Conn EF2<>DHB.12 - WBS Summary EF2<>DHB.12 Not Started 03/19/27 04/05/27 13.8 13.8
0%
230.0
RPL08.EY.DHB.01430 RPL08.EY.DHB - Install Irrigation Hardscape and Landscape Not Started 03/19/27 04/02/27 12.5 12.5
0%
396.2
RPL08.EY.DHB.01440 RPL08.EY.DHB - Install Exterior Signage Hardscape and Landscape Not Started 03/19/27 04/02/27 12.5 12.5
0%
261.2
RPL08.EY.DHC.01250 RPL08.EY.DHC - Install Electrical Tie-ins (include penetration detail) Tie-ins Not Started 03/19/27 04/02/27 12.5 12.5
0%
222.5
RPL08.EY.DHC.01260 RPL08.EY.DHC - Tie-ins - WBS Summary Tie-ins Not Started 03/19/27 08/16/27 130.0 130.0
0%
223.8
RPL08.INT.DHB.01570 RPL08.Interior.DHB - Control Fault Domain 2 - L2 Checklist Completion Remaining Tie-ins post Mech Side Aisle install Not Started 03/19/27 04/16/27 25.0 25.0
0%
122.5
RPL08.INT.DHB.01590 RPL08.Interior.DHB - Control Fault Domain 3 - Install Mechanical Side Aisle Cable Tray Remaining Tie-ins post Mech Side Aisle install Not Started 03/19/27 04/16/27 25.0 25.0
0%
175.0
RPL08.INT.DHB.01620 RPL08.Interior.DHB - Control Fault Domain 3 - Install copper from GS.IDF to BMS and EPMS panels (UG from Center IDF) Remaining Tie-ins post Mech Side Aisle install Not Started 03/19/27 04/16/27 25.0 25.0
0%
136.2
RPL08.INT.DHB.01630 RPL08.Interior.DHB - Control Fault Domain 4 - Install Duct (MES Side) Remaining Tie-ins post Mech Side Aisle install Not Started 03/19/27 04/16/27 25.0 25.0
0%
143.8
RPL08.INT.DHB.01640 RPL08.Interior.DHB - Control Fault Domain 4 - Install Vesda / FA Remaining Tie-ins post Mech Side Aisle install Not Started 03/19/27 04/16/27 25.0 25.0
0%
150.0
RPL08.INT.DHB.01650 RPL08.Interior.DHB - Control Fault Domain 4 - Install FW Remaining Tie-ins post Mech Side Aisle install Not Started 03/19/27 04/16/27 25.0 25.0
0%
143.8
RPL08.INT.DHB.02260 RPL08.Interior.DHB - Control Fault Domain 4 - Install TW Remaining Tie-ins post Mech Side Aisle install Not Started 03/19/27 04/16/27 25.0 25.0
0%
143.8
RPL08.INT.DHC.01530 RPL08.Interior.DHC - Control Fault Domain 3 - Install LV Side Aisle Cable Tray LV Side Tie-ins Not Started 03/19/27 03/24/27 5.0 5.0
0%
317.5
RPL08.WP3B.012040 RPL08.Conn EF2<>DHB.12 Pull Pigtails (384F) P2&3 (LV) EF2<>DHB.12 Not Started 03/19/27 03/22/27 2.5 2.5
0%
215.0
RPL08.WP3B.013460 RPL08.Conn EF2<>DHB.11 Install (A-End) Pigtails (384F) P2&3 (LV) EF2<>DHB.11 Not Started 03/19/27 03/19/27 1.2 1.2
0%
231.2
RPL08.WP4.010400 RPL08.Conn DHB.11 Pull Trunk (384F) [RSW<>FSW] Trunks Not Started 03/19/27 03/19/27 1.2 1.2
0%
245.0
RPL08.WP4.010420 RPL08.Conn DHB.12 Pull Trunk (384F) [RSW<>FSW] Trunks Not Started 03/19/27 03/19/27 1.2 1.2
0%
245.0
GCD.RPL08.2001 Cx Power Available (Temp) CX Milestones Not Started 03/22/27 03/22/27 0.0 0.0
0%
83.8
ICM.B8.2530 [SSDCB3] L3/L4 Start EY Commissioning Not Started 03/22/27 03/22/27 0.0 0.0
0%
238.8
RPL08.CX.DHB.01010 RPL08.CX.DHB - L3 - WBS Summary (Electrical) DHB ELECTRICAL Not Started 03/22/27 08/05/27 120.0 120.0
0%
118.8
RPL08.CX.DHB.01020 RPL08.CX.DHB - L3/L4 - MV Skids (10) Loop DHB ELECTRICAL Not Started 03/22/27 04/05/27 12.5 12.5
0%
83.8
RPL08.CX.MCUP.01030 RPL08.CX.mCup Loop 2 - L3/L4 - MV Skids mCUP 5-6 Not Started 03/22/27 03/25/27 5.0 5.0
0%
227.5
RPL08.CX.MCUP.01040 RPL08.CX.mCup Loop 1 - L3/L4 - mCUP - FWM mCUP 1-4 Not Started 03/22/27 04/05/27 12.5 12.5
0%
88.8
RPL08.INT.CC.9540 RPL08.Interior.CC Ext. LO #17 - QC - Backings/Walls Exterior Leave Out Wall #17 (CC - South) Not Started 03/22/27 03/22/27 1.2 1.2
0%
147.5
RPL08.INT.DHA.03680 RPL08.Interior.DHA - OFE - Control Fault Domain 4 (HAC) Control Fault Domain 4 Not Started 03/22/27 04/05/27 12.5 12.5
0%
115.0
RPL08.INT.DHC.01580 RPL08.Interior.DHC - Tie-ins - Control Fault Domain 4 - WBS Summary Control Fault Domain 4 Not Started 03/22/27 08/12/27 126.2 126.2
0%
205.0
RPL08.INT.DHC.02570 RPL08.Interior.DHC - Control Fault Domain 4 - Install Duct (LV Side) LV Side Tie-ins Not Started 03/22/27 03/25/27 5.0 5.0
0%
257.5
RPL08.INT.SSB.01430 RPL08.Interior.SSB - Loading Dock and Storage - Electrical Trim Out Loading Dock and Storage Not Started 03/22/27 03/31/27 8.8 8.8
0%
206.2
RPL08.INT.SSB.01450 RPL08.Interior.SSB - BoW - Install DAS (Distribution Antenna System) Balance of Walls and OverHead Not Started 03/22/27 03/23/27 2.5 2.5
0%
186.2
RPL08.INT.SSB.01460 RPL08.Interior.SSB - Loading Dock and Storage - Install Lighting and Devices Loading Dock and Storage Not Started 03/22/27 03/31/27 8.8 8.8
0%
223.8
RPL08.INT.SSB.01920 RPL08.Interior.SSB - Loading Dock and Storage - Install Remaining Refrigerant Line Loading Dock and Storage Not Started 03/22/27 03/29/27 6.2 6.2
0%
232.5
RPL08.INT.SSB.02560 RPL08.Interior.SSB - BoW - ACT - Device Tiles Balance of Walls and OverHead Not Started 03/22/27 03/29/27 6.2 6.2
0%
203.8
RPL08.INT.SSB.02580 RPL08.Interior.SSB - BoW - ACT - MEP Devices Balance of Walls and OverHead Not Started 03/22/27 03/29/27 6.2 6.2
0%
203.8
RPL08.WP3B.016340 RPL08.Conn EF2<>DHB.11 Install (Z-End) Pigtails (384F) P2&3 (LV) EF2<>DHB.11 Not Started 03/22/27 03/30/27 7.5 7.5
0%
231.2
RPL08.EY.DHA.01340 RPL08.EY.DHA - Install Lighting Hardscape and Landscape Not Started 03/23/27 04/06/27 12.5 12.5
0%
252.5
RPL08.EY.DHC.01280 RPL08.EY.DHC - Install BMS/EPMS Tie-ins Tie-ins Not Started 03/23/27 04/06/27 12.5 12.5
0%
222.5
RPL08.INT.CC.9020 RPL08.Interior.CC Ext. LO #17 - Hang Drywall Exterior Leave Out Wall #17 (CC - South) Not Started 03/23/27 03/25/27 3.8 3.8
0%
147.5
RPL08.INT.CTRC.06800 RPL08.Interior.Center-Corridor - Final Finishes & Fixtures - MEP Rough-In Restrooms Not Started 03/23/27 03/30/27 6.2 6.2
0%
117.5
RPL08.INT.CTRC.1540 RPL08.Interior.Center-Corridor - BoW - QC - Backings/Walls Balance of Walls & Overhead Not Started 03/23/27 03/30/27 6.2 6.2
0%
137.5
RPL08.INT.DHB.02680 RPL08.Interior.DHB - OFE - Control Fault Domain 5 (Mech Side Aisle) Control Fault Domain 5 Not Started 03/23/27 04/02/27 10.0 10.0
0%
147.5
RPL08.INT.ENDC.01310 RPL08.Interior.End-Corridor - Fire Life Safe Trim Fit out Not Started 03/23/27 03/29/27 5.0 5.0
0%
247.5
RPL08.INT.ENDC.01430 RPL08.Interior.End-Corridor - MOFE - Ancillary Skids Qty2 (DH D) OFE/MOFE & CFCI Not Started 03/23/27 04/06/27 12.5 12.5
0%
268.8
RPL08.INT.ENDC.01450 RPL08.Interior.End-Corridor - MOFE - Ancillary Skids Qty2 (DH C) OFE/MOFE & CFCI Not Started 03/23/27 04/06/27 12.5 12.5
0%
268.8
RPL08.INT.ENDC.06800 RPL08.Interior.End-Corridor - Final Finishes & Fixtures - MEP Trims Restrooms Not Started 03/23/27 04/01/27 8.8 8.8
0%
260.0
RPL08.INT.ENDC.1380 RPL08.Interior.End-Corridor - BoW - Install Controls / EPMS / BMS OH and In-wall Balance of Walls & Overhead Not Started 03/23/27 03/30/27 6.2 6.2
0%
281.2
RPL08.INT.ENDC.1440 RPL08.Interior.End-Corridor - BoW - Mechanical Tie-In Balance of Walls & Overhead Not Started 03/23/27 03/30/27 6.2 6.2
0%
210.0
RPL08.INT.SBC.03600 RPL08.Interior.SSB-Corridor - BoW - Electrical Trim Out (Both side of Corridor Wall) Balance of Walls & Overhead Not Started 03/23/27 04/01/27 8.8 8.8
0%
143.8
RPL08.INT.SBC.03620 RPL08.Interior.SSB-Corridor - BoW - Duct Drops / Trim out Balance of Walls & Overhead Not Started 03/23/27 03/30/27 6.2 6.2
0%
143.8
RPL08.INT.SBC.03700 RPL08.Interior.SSB-Corridor - BoW - Install Balance of Refrigerant Line Balance of Walls & Overhead Not Started 03/23/27 03/30/27 6.2 6.2
0%
183.8
RPL08.INT.SBC.03720 RPL08.Interior.SSB-Corridor - BoW - Security Trim Out (Both side of Corridor Wall) Balance of Walls & Overhead Not Started 03/23/27 04/01/27 8.8 8.8
0%
143.8
RPL08.INT.SBC.03780 RPL08.Interior.SSB-Corridor - BoW - Install DAS (Distribution Antenna System) Balance of Walls & Overhead Not Started 03/23/27 03/30/27 6.2 6.2
0%
147.5
RPL08.INT.SSB.14620 RPL08.Interior.SSB LO #01 to #05 - Install Door (Verify with Trades before installation) Finishes Not Started 03/23/27 04/01/27 8.8 8.8
0%
172.5
RPL08.WP3B.013480 RPL08.Conn EF2<>DHB.12 Install (A-End) Pigtails (384F) P2&3 (LV) EF2<>DHB.12 Not Started 03/23/27 03/23/27 1.2 1.2
0%
230.0
RPL08.WP4.010720 RPL08.Conn DHB.11.03<>03 Pull Simplex Jumper (SC<>LC) [PON (Active, In-Row)] Jumpers Not Started 03/23/27 03/25/27 3.8 3.8
0%
235.0
RPL08.WP4.010740 RPL08.Conn DHB.12.06<>05 Pull Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] Across-Row Not Started 03/23/27 03/29/27 5.0 5.0
0%
235.0
RPL08.EY.DHB.01470 RPL08.EY.DHB - Remaining L2 Checklist Completion Tie-ins Not Started 03/24/27 03/31/27 6.2 6.2
0%
223.8
RPL08.INT.DHC.01650 RPL08.Interior.DHC - Control Fault Domain 4 - Install LV Side Aisle HAC Busway LV Side Tie-ins Not Started 03/24/27 03/30/27 5.0 5.0
0%
315.0
RPL08.INT.SSB.01490 RPL08.Interior.SSB - BoW - Install Remaining Lights (**Work with FTI to coordinate flow map light Install & duration) Balance of Walls and OverHead Not Started 03/24/27 04/07/27 12.5 12.5
0%
186.2
RPL08.INT.SSB.01500 RPL08.Interior.SSB - BoW - Install Bathroom Fixtures Balance of Walls and OverHead Not Started 03/24/27 04/02/27 8.8 8.8
0%
186.2
RPL08.INT.SSB.02400 RPL08.Interior.SSB - Final Finishes & Fixtures - Final Clean Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) Not Started 03/24/27 03/30/27 5.0 5.0
0%
316.2
RPL08.WP3B.014920 RPL08.Conn EF2<>DHB.12 Splice (A-End) Pigtails (384F) P2&3 (LV) EF2<>DHB.12 Not Started 03/24/27 04/01/27 7.5 7.5
0%
230.0
RPL08.WP3B.016360 RPL08.Conn EF2<>DHB.12 Install (Z-End) Pigtails (384F) P2&3 (LV) EF2<>DHB.12 Not Started 03/24/27 03/24/27 1.2 1.2
0%
230.0
RPL08.CX.DHB.01280 RPL08.CX.DHB - L3/L4 - Control Fault Domain 01 - TW Flush and Fill Control Fault Domain 1 Not Started 03/25/27 04/06/27 10.0 10.0
0%
138.8
RPL08.CX.DHB.01320 RPL08.CX.DHB - L3/L4 - Control Fault Domain 02 - FW Flush and Fill Control Fault Domain 2 Not Started 03/25/27 04/05/27 8.8 8.8
0%
150.0
RPL08.INT.DHA.01360 RPL08.Interior.DHA - Control Fault Domain 2 - Install Mechanical Side Aisle Cable Tray Remaining Tie-ins post Mech Side Aisle install Not Started 03/25/27 04/22/27 25.0 25.0
0%
117.5
RPL08.INT.DHA.01400 RPL08.Interior.DHA - Control Fault Domain 3 - Install Duct (MES Side) Remaining Tie-ins post Mech Side Aisle install Not Started 03/25/27 04/22/27 25.0 25.0
0%
131.2
RPL08.INT.DHA.01410 RPL08.Interior.DHA - Control Fault Domain 3 - Install Vesda / FA Remaining Tie-ins post Mech Side Aisle install Not Started 03/25/27 04/22/27 25.0 25.0
0%
137.5
RPL08.INT.DHA.01420 RPL08.Interior.DHA - Control Fault Domain 3 - Install FW Remaining Tie-ins post Mech Side Aisle install Not Started 03/25/27 04/22/27 25.0 25.0
0%
131.2
RPL08.INT.DHA.02220 RPL08.Interior.DHA - Control Fault Domain 3 - Install TW Remaining Tie-ins post Mech Side Aisle install Not Started 03/25/27 04/22/27 25.0 25.0
0%
131.2
RPL08.INT.DHA.03700 RPL08.Interior.DHA - OFE - Control Fault Domain 4 (Mech Side Aisle) Control Fault Domain 4 Not Started 03/25/27 04/06/27 10.0 10.0
0%
138.8
RPL08.INT.DHC.01670 RPL08.Interior.DHC - Control Fault Domain 4 - Install LV Side Aisle Cable Tray LV Side Tie-ins Not Started 03/25/27 03/31/27 5.0 5.0
0%
315.0
RPL08.INT.SBC.03740 RPL08.Interior.SSB-Corridor - BoW - Plumbing Trim Out Balance of Walls & Overhead Not Started 03/25/27 04/01/27 6.2 6.2
0%
143.8
RPL08.INT.SBC.03760 RPL08.Interior.SSB-Corridor - BoW - Fire Life Safety Trim Out / Fire Alarm Trim Out Balance of Walls & Overhead Not Started 03/25/27 04/05/27 8.8 8.8
0%
143.8
RPL08.EY.DHD.01300 RPL08.EY.DHD - Install Sleeves MEPL Hardscape and Landscape Not Started 03/29/27 04/02/27 6.2 6.2
0%
332.5
RPL08.EY.DHD.01310 RPL08.EY.DHD - MV Loop - L2 Checklist Completion Tie-ins Not Started 03/29/27 04/09/27 12.5 12.5
0%
215.0
RPL08.EY.DHD.01320 RPL08.EY.DHD - Install Hardscape and Landscape - WBS Summary Hardscape and Landscape Not Started 03/29/27 08/20/27 128.8 128.8
0%
286.2
RPL08.INT.CC.9040 RPL08.Interior.CC Ext. LO #17 - Tape Finish Paint Exterior Leave Out Wall #17 (CC - South) Not Started 03/29/27 04/02/27 6.2 6.2
0%
147.5
RPL08.INT.CTRC.2000 RPL08.Interior.Center-Corridor LO #10 & #12 - Close Interior Leave Out #10 DHB/CC (For HACs in DHB) WBS Summary Interior Leave Out Wall #10, #12 (DHB/CC) Not Started 03/29/27 05/10/27 38.8 38.8
0%
147.5
RPL08.INT.CTRC.2520 RPL08.Interior.Center-Corridor LO #10 & #12 - Install IMP Wall at Leave Out (DH B) Interior Leave Out Wall #10, #12 (DHB/CC) Not Started 03/29/27 03/31/27 3.8 3.8
0%
147.5
RPL08.INT.CTRC.2540 RPL08.Interior.Center-Corridor LO #10 & #12 - Tie In MEPF with IMP Wall buildback Interior Leave Out Wall #10, #12 (DHB/CC) Not Started 03/29/27 04/01/27 5.0 5.0
0%
147.5
RPL08.INT.DHB.01670 RPL08.Interior.DHB - Control Fault Domain 4 - Pull BMS from panel to devices Remaining Tie-ins post Mech Side Aisle install Not Started 03/29/27 04/23/27 25.0 25.0
0%
150.0
RPL08.INT.DHB.01680 RPL08.Interior.DHB - Control Fault Domain 4 - Pull EMPS from panel to devices Remaining Tie-ins post Mech Side Aisle install Not Started 03/29/27 04/23/27 25.0 25.0
0%
150.0
RPL08.INT.DHB.01690 RPL08.Interior.DHB - Control Fault Domain 4 - Set UPS and Panel (2) Remaining Tie-ins post Mech Side Aisle install Not Started 03/29/27 04/23/27 25.0 25.0
0%
143.8
RPL08.INT.DHB.01710 RPL08.Interior.DHB - Control Fault Domain 3 - L2 Checklist Completion Remaining Tie-ins post Mech Side Aisle install Not Started 03/29/27 04/23/27 25.0 25.0
0%
136.2
RPL08.INT.ENDC.06920 RPL08.Interior.End-Corridor - Final Finishes & Fixtures - Flooring Restrooms Not Started 03/29/27 04/06/27 8.8 8.8
0%
268.8
RPL08.WP4.010900 RPL08.Conn DHB.11.02<>01 Pull Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] Across-Row Not Started 03/29/27 04/01/27 5.0 5.0
0%
235.0
RPL08.CX.DHA.01280 RPL08.CX.DHA - L3/L4 - Control Fault Domain 01 - TW Flush and Fill Control Fault Domain 1 Not Started 03/30/27 04/08/27 10.0 10.0
0%
148.8
RPL08.EY.DHA.01590 RPL08.EY.DHC - Install Mechanical/ refrigerantTie-ins Build back Exterior Leave Out #17 (South) Not Started 03/30/27 04/05/27 6.2 6.2
0%
207.5
RPL08.EY.DHA.02000 RPL08.EY.DHA - Exterior Leave Out #17 (CC - South) WBS Summary Build back Exterior Leave Out #17 (South) Not Started 03/30/27 04/26/27 25.0 25.0
0%
207.5
RPL08.INT.CTRC.8920 RPL08.Interior.Center-Corridor LO #10 & #12 - Install IMP Wall at Leave Out (DH D) Interior Leave Out Wall #10, #12 (DHB/CC) Not Started 03/30/27 04/01/27 3.8 3.8
0%
147.5