Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL08 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:14 PM
· 5122 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
0
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL08.INT.ENDC.01330 |
RPL08.Interior.End-Corridor - Electrical Trim | Fit out | Not Started | 03/30/27 | 04/02/27 | 5.0 | 5.0 |
|
247.5 |
RPL08.INT.ENDC.01340 |
RPL08.Interior.End-Corridor - Install Grounding | Fit out | Not Started | 03/30/27 | 04/12/27 | 12.5 | 12.5 |
|
247.5 |
RPL08.WP4.011220 |
RPL08.Conn DHB.12.07<>07 Pull Simplex Jumper (SC<>LC) [PON (Active, In-Row)] | Jumpers | Not Started | 03/30/27 | 04/01/27 | 3.8 | 3.8 |
|
235.0 |
GCD.RPL08.1735 |
Start FSHAC set in place - RPL08 - DHC&D | Construction Milestones | Not Started | 03/31/27 | 03/31/27 | 0.0 | 0.0 |
|
373.8 |
RPL08.EY.DHC.01290 |
RPL08.EY.DHC - MV Loop - L2 Checklist Completion | Tie-ins | Not Started | 03/31/27 | 04/13/27 | 12.5 | 12.5 |
|
222.5 |
RPL08.INT.CTRC.06820 |
RPL08.Interior.Center-Corridor - Final Finishes & Fixtures - Hang Tape Bed Wall, Ceiling and Fire/Caulking | Restrooms | Not Started | 03/31/27 | 04/06/27 | 6.2 | 6.2 |
|
130.0 |
RPL08.INT.CTRC.06840 |
RPL08.Interior.Center-Corridor - Final Finishes & Fixtures - Framing RO Verification, Tile Finish & ADA Verification (P | Restrooms | Not Started | 03/31/27 | 04/06/27 | 6.2 | 6.2 |
|
117.5 |
RPL08.INT.CTRC.1560 |
RPL08.Interior.Center-Corridor - BoW - Hang Drywall | Balance of Walls & Overhead | Not Started | 03/31/27 | 04/08/27 | 8.8 | 8.8 |
|
137.5 |
RPL08.INT.DHD.02290 |
RPL08.Interior.DHD - OFE - Control Fault Domain 1 (HAC) | Control Fault Domain 1 | Not Started | 03/31/27 | 04/20/27 | 18.8 | 18.8 |
|
151.2 |
RPL08.INT.ENDC.1460 |
RPL08.Interior.End-Corridor - BoW - Frame Hard Lid | Balance of Walls & Overhead | Not Started | 03/31/27 | 04/06/27 | 6.2 | 6.2 |
|
210.0 |
RPL08.INT.SBC.03840 |
RPL08.Interior.SSB-Corridor - BoW - Install Remaining Lights | Balance of Walls & Overhead | Not Started | 03/31/27 | 04/13/27 | 12.5 | 12.5 |
|
147.5 |
RPL08.INT.SSB.02380 |
RPL08.Interior.SSB - Final Finishes & Fixtures - Final Punch Walk | Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) | Not Started | 03/31/27 | 04/01/27 | 2.5 | 2.5 |
|
316.2 |
RPL08.WP3B.014900 |
RPL08.Conn EF2<>DHB.11 Splice (A-End) Pigtails (384F) P2&3 (LV) | EF2<>DHB.11 | Not Started | 03/31/27 | 03/31/27 | 1.2 | 1.2 |
|
231.2 |
RPL08.CX.MCUP.01370 |
RPL08.CX.mCup Loop 2 - L3/L4 - mCUP - Flush and Fill - DHD & DHC - Loop 2 (Phase 4) | Fill and Flush | Not Started | 04/01/27 | 04/07/27 | 6.2 | 6.2 |
|
255.0 |
RPL08.INT.SSB.01480 |
RPL08.Interior.SSB - Loading Dock and Storage - Security Trim Out | Loading Dock and Storage | Not Started | 04/01/27 | 04/09/27 | 8.8 | 8.8 |
|
206.2 |
RPL08.INT.SSB.02960 |
RPL08.Interior.SSB - Loading Dock and Storage - Install Flooring | Loading Dock and Storage | Not Started | 04/01/27 | 04/07/27 | 6.2 | 6.2 |
|
231.2 |
RPL08.INT.SSB.06440 |
RPL08.Interior.SSB LO #16 - Final Paint | Leave Out Wall #16 (SSB - North of Loading Dock) | Not Started | 04/01/27 | 04/09/27 | 8.8 | 8.8 |
|
168.8 |
RPL08.WP3B.017780 |
RPL08.Conn EF2<>DHB.11 Test Pigtails (384F) P2&3 (LV) | EF2<>DHB.11 | Not Started | 04/01/27 | 04/02/27 | 2.5 | 2.5 |
|
231.2 |
RPL08.WP4.011280 |
RPL08.Conn DHB.11.02 Pull Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] | Jumpers (AI Confirmed) | Not Started | 04/01/27 | 04/14/27 | 12.5 | 12.5 |
|
206.2 |
RPL08.WP4.011300 |
RPL08.Conn DHB.12.06 Pull Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] | Jumpers (AI Confirmed) | Not Started | 04/01/27 | 04/14/27 | 12.5 | 12.5 |
|
206.2 |
DCC.B8.3025 |
[SSDCB3] Production Gear Delivered [DHA] Front End (SSW &FSW) | Connectivity | Not Started | 04/02/27 | 04/02/27 | 0.0 | 0.0 |
|
232.5 |
RPL.08.D.83310.XR |
Pull and Term MV Skids - RPL08 DHA | Receive Milestones (XREFs) | Not Started | 04/02/27 | 04/02/27 | 0.0 | 0.0 |
|
86.2 |
RPL.08.D.83810.XR |
100MW Cx Temp Power to MV Skids RPL08 DHA Available | Receive Milestones (XREFs) | Not Started | 04/02/27 | 04/02/27 | 0.0 | 0.0 |
|
86.2 |
RPL08.CON.WP3B.01040 |
RPL08.Conn WP#3B - ISP DHA - WBS Summary | DH A | Not Started | 04/02/27 | 07/13/27 | 88.8 | 88.8 |
|
156.2 |
RPL08.CON.WP4.03000 |
RPL08.Conn - DH A Network - WBS Summary | DH A | Not Started | 04/02/27 | 08/12/27 | 116.2 | 116.2 |
|
141.2 |
RPL08.CON.WP4.03020 |
RPL08.Conn WP4 FENW DHA CFD1 Infrastructure | Infrastructure | Not Started | 04/02/27 | 04/29/27 | 25.0 | 25.0 |
|
232.5 |
RPL08.INT.CTRC.1900 |
RPL08.Interior.Center-Corridor - BoW - F/R/P Pads | Balance of Walls & Overhead | Not Started | 04/02/27 | 04/08/27 | 6.2 | 6.2 |
|
137.5 |
RPL08.INT.CTRC.2560 |
RPL08.Interior.Center-Corridor LO #10 - Install Vertical Tube Steel Support for Cable Tray (IFP Add) | Remaining of LO Wall #10 ((Spoke Parts & Spoke Tech) | Not Started | 04/02/27 | 04/05/27 | 2.5 | 2.5 |
|
175.0 |
RPL08.INT.CTRC.2660 |
RPL08.Interior.Center-Corridor LO #10 & #12 - Install Mechanical Piping Lowside OH | Interior Leave Out Wall #10, #12 (DHB/CC) | Not Started | 04/02/27 | 04/06/27 | 3.8 | 3.8 |
|
147.5 |
RPL08.INT.CTRC.7760 |
RPL08.Interior.Center-Corridor LO #10 - Frame Out All Walls | Remaining of LO Wall #10 ((Spoke Parts & Spoke Tech) | Not Started | 04/02/27 | 04/06/27 | 3.8 | 3.8 |
|
148.8 |
RPL08.INT.DHA.01200 |
RPL08.Conn DHA - CFD1 - Set Passive Racks for WP#3b (16) | Infrastructure | Not Started | 04/02/27 | 04/06/27 | 3.8 | 3.8 |
|
201.2 |
RPL08.INT.DHA.01390 |
RPL08.Interior.DHA - Control Fault Domain 2 - Install Copper from GS.IDF to BMS and EPMS panels | Remaining Tie-ins post Mech Side Aisle install | Not Started | 04/02/27 | 04/29/27 | 25.0 | 25.0 |
|
117.5 |
RPL08.INT.DHA.01440 |
RPL08.Interior.DHA - Control Fault Domain 3 - Pull BMS from panel to devices | Remaining Tie-ins post Mech Side Aisle install | Not Started | 04/02/27 | 04/29/27 | 25.0 | 25.0 |
|
137.5 |
RPL08.INT.DHA.01450 |
RPL08.Interior.DHA - Control Fault Domain 3 - Pull EMPS from panel to devices | Remaining Tie-ins post Mech Side Aisle install | Not Started | 04/02/27 | 04/29/27 | 25.0 | 25.0 |
|
137.5 |
RPL08.INT.DHA.01460 |
RPL08.Interior.DHA - Control Fault Domain 3 - Set UPS and Panel (2) and GS.IDF B1 (Stick Build) | Remaining Tie-ins post Mech Side Aisle install | Not Started | 04/02/27 | 04/29/27 | 25.0 | 25.0 |
|
131.2 |
RPL08.INT.DHA.03880 |
RPL08.Conn DHA - CFD1 - Set Passive Racks for PON (16) | Infrastructure | Not Started | 04/02/27 | 04/06/27 | 3.8 | 3.8 |
|
216.2 |
RPL08.INT.ENDC.06840 |
RPL08.Interior.End-Corridor - Final Finishes & Fixtures - Install Acoustical Ceiling | Restrooms | Not Started | 04/02/27 | 04/06/27 | 3.8 | 3.8 |
|
260.0 |
RPL08.INT.SSB.02180 |
RPL08.Interior.SSB - Final Finishes & Fixtures - Electrical L2 Checklist Completion | Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) | Not Started | 04/02/27 | 04/15/27 | 12.5 | 12.5 |
|
316.2 |
RPL08.INT.SSB.14640 |
RPL08.Interior.SSB LO #01 to #05 - Electrical L2 Checklist Completion | Finishes | Not Started | 04/02/27 | 04/15/27 | 12.5 | 12.5 |
|
172.5 |
RPL08.WP3B.017800 |
RPL08.Conn EF2<>DHB.12 Test Pigtails (384F) P2&3 (LV) | EF2<>DHB.12 | Not Started | 04/02/27 | 04/05/27 | 2.5 | 2.5 |
|
230.0 |
RPL08.WP4.011900 |
RPL08.Conn DHB.11.04<>03 Pull Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] | Across-Row | Not Started | 04/02/27 | 04/07/27 | 5.0 | 5.0 |
|
235.0 |
RPL08.WP4.011920 |
RPL08.Conn DHB.12.08<>07 Pull Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] | Across-Row | Not Started | 04/02/27 | 04/07/27 | 5.0 | 5.0 |
|
235.0 |
GCD.RPL08.2251 |
L3/L4 Finish EY - DHB | EY | Not Started | 04/05/27 | 04/05/27 | 0.0 | 0.0 |
|
226.2 |
RPL08.CON.WP4.01200 |
RPL08.Conn WP4 FENW DHB CFD2 Infrastructure | Infrastructure | Not Started | 04/05/27 | 04/30/27 | 25.0 | 25.0 |
|
218.8 |
RPL08.EY.DHB.01480 |
RPL08.EY.DHB - Install Landscaping | Hardscape and Landscape | Not Started | 04/05/27 | 04/16/27 | 12.5 | 12.5 |
|
396.2 |
RPL08.EY.DHD.01330 |
RPL08.EY.DHD - Install Early EY Paving | Hardscape and Landscape | Not Started | 04/05/27 | 04/09/27 | 6.2 | 6.2 |
|
332.5 |
RPL08.INT.CC.9060 |
RPL08.Interior.CC Ext. LO #17 - Duct Drops / Trim out | Exterior Leave Out Wall #17 (CC - South) | Not Started | 04/05/27 | 04/06/27 | 2.5 | 2.5 |
|
150.0 |
RPL08.INT.CC.9080 |
RPL08.Interior.CC Ext. LO #17 - Install Remaining Refrigerant Line | Exterior Leave Out Wall #17 (CC - South) | Not Started | 04/05/27 | 04/05/27 | 1.2 | 1.2 |
|
178.8 |
RPL08.INT.CC.9100 |
RPL08.Interior.CC Ext. LO #17 - Install Remaining Lights | Exterior Leave Out Wall #17 (CC - South) | Not Started | 04/05/27 | 04/08/27 | 5.0 | 5.0 |
|
150.0 |
RPL08.INT.CC.9120 |
RPL08.Interior.CC Ext. LO #17 - Fire Safing / Wall Finishes | Exterior Leave Out Wall #17 (CC - South) | Not Started | 04/05/27 | 04/07/27 | 3.8 | 3.8 |
|
147.5 |
RPL08.INT.CC.9220 |
RPL08.Interior.CC Ext. LO #17 - Install Flooring Tiles/Resinous Flooring in specific rooms **?? | Exterior Leave Out Wall #17 (CC - South) | Not Started | 04/05/27 | 04/07/27 | 3.8 | 3.8 |
|
151.2 |
RPL08.INT.DHB.01420 |
RPL08.Conn DHB - CFD2 - Set Passive Racks for WP#3b (16) | Infrastructure | Not Started | 04/05/27 | 04/07/27 | 3.8 | 3.8 |
|
187.5 |
RPL08.INT.DHB.01730 |
RPL08.Interior.DHB - Control Fault Domain 4 - Install Mechanical Side Aisle Cable Tray | Remaining Tie-ins post Mech Side Aisle install | Not Started | 04/05/27 | 04/30/27 | 25.0 | 25.0 |
|
162.5 |
RPL08.INT.DHB.01760 |
RPL08.Interior.DHB - Control Fault Domain 4 - Install copper from GS.IDF to BMS and EPMS panels (UG from Center IDF) | Remaining Tie-ins post Mech Side Aisle install | Not Started | 04/05/27 | 04/30/27 | 25.0 | 25.0 |
|
143.8 |
RPL08.INT.DHB.02820 |
RPL08.Conn DHB - CFD2 - Set Passive Racks for PON (16) | Infrastructure | Not Started | 04/05/27 | 04/07/27 | 3.8 | 3.8 |
|
208.8 |
RPL08.INT.DHD.02310 |
RPL08.Interior.DHD - OFE - Control Fault Domain 1 (Mech Side Aisle) | Control Fault Domain 1 | Not Started | 04/05/27 | 04/21/27 | 16.2 | 16.2 |
|
158.8 |
RPL08.INT.ENDC.01350 |
RPL08.Interior.End-Corridor - Plumbing Trim | Fit out | Not Started | 04/05/27 | 04/08/27 | 5.0 | 5.0 |
|
247.5 |
RPL08.INT.SSBC.01490 |
RPL08.Interior.SSB-Corridor - Remaining Mechanical DHB OFE TIe Ins | Fit out | Not Started | 04/05/27 | 04/09/27 | 6.2 | 6.2 |
|
231.2 |
RPL08.INT.SSBC.01500 |
RPL08.Interior.SSB-Corridor - Remaining Electrical DHB OFE TIe Ins | Fit out | Not Started | 04/05/27 | 04/09/27 | 6.2 | 6.2 |
|
231.2 |
DCC.B8.3165 |
[SSDCB3] PortMaps Delivered : GS | Connectivity | Not Started | 04/06/27 | 04/06/27 | 0.0 | 0.0 |
|
407.5 |
DCC.B8.3170 |
[SSDCB3] PortMaps Delivered : Elevations & Cabling | Connectivity | Not Started | 04/06/27 | 04/06/27 | 0.0 | 0.0 |
|
407.5 |
DCC.B8.3175 |
[SSDCB3] PortMaps Delivered : Backbone | Connectivity | Not Started | 04/06/27 | 04/06/27 | 0.0 | 0.0 |
|
407.5 |
DCC.B8.3180 |
[SSDCB3] PortMaps Delivered : Front End | Connectivity | Not Started | 04/06/27 | 04/06/27 | 0.0 | 0.0 |
|
407.5 |
DCC.B8.3460 |
[SSDCB3] Production Dark Fiber Path 1 - Circuit Delivered **Pred?? only for RPL10?? | Connectivity | Not Started | 04/06/27 | 04/06/27 | 0.0 | 0.0 |
|
407.5 |
GCD.RPL08.4605 |
L3/L4 Start EY - DHA | EY | Not Started | 04/06/27 | 04/06/27 | 0.0 | 0.0 |
|
238.8 |
ICM.B8.2510.B |
[SSDCB3] L3/4 Start - DHB | Commissioning | Not Started | 04/06/27 | 04/06/27 | 0.0 | 0.0 |
|
226.2 |
ICM.B8.2550 |
[SSDCB3] L3/L4 Start mCUP [1-4] - RPL08 | Commissioning | Not Started | 04/06/27 | 04/06/27 | 0.0 | 0.0 |
|
260.0 |
RPL08.CON.WP2.02000 |
RPL08.Conn - GS EF2 (North) - WBS Summary | GS.EF2 (North) | Not Started | 04/06/27 | 04/20/27 | 13.8 | 13.8 |
|
320.0 |
RPL08.CON.WP2.02200 |
RPL08.Conn - GS EF2 (North) Set Infrastructure (Wall mounting enclousres, Tier1 Basket Tray, Waterfalls etc.) | Infrastructure | Not Started | 04/06/27 | 04/08/27 | 3.8 | 3.8 |
|
325.0 |
RPL08.CON.WP2.03000 |
RPL08.Conn - GS EF1 (South) - WBS Summary | GS.EF1 (South) | Not Started | 04/06/27 | 04/20/27 | 13.8 | 13.8 |
|
320.0 |
RPL08.CON.WP2.07820 |
RPL08.Conn - GS EF1 (South) Set Infrastructure (Wall mounting enclousres, Tier1 Basket Tray, Waterfalls etc.) | Infrastructure | Not Started | 04/06/27 | 04/08/27 | 3.8 | 3.8 |
|
325.0 |
RPL08.CX.DHA.01010 |
RPL08.CX.DHA - L3 - WBS Summary (Electrical) | DHA ELECTRICAL | Not Started | 04/06/27 | 08/20/27 | 121.2 | 121.2 |
|
117.5 |
RPL08.CX.DHA.01020 |
RPL08.CX.DHA - L3/L4 - MV Skids (10) Loop | DHA ELECTRICAL | Not Started | 04/06/27 | 04/19/27 | 12.5 | 12.5 |
|
83.8 |
RPL08.CX.DHB.01030 |
RPL08.CX.DHB - L3/L4 - House Power (for electrical) | DHB HOUSE POWER | Not Started | 04/06/27 | 04/19/27 | 12.5 | 12.5 |
|
83.8 |
RPL08.CX.DHB.01380 |
RPL08.CX.DHB - L3/L4 - Control Fault Domain 03 - FW Flush and Fill | Control Fault Domain 3 | Not Started | 04/06/27 | 04/14/27 | 8.8 | 8.8 |
|
161.2 |
RPL08.CX.MCUP.01050 |
RPL08.CX.mCup Loop 1 - L3/L4 - mCUP | mCUP 1-4 | Not Started | 04/06/27 | 05/13/27 | 35.0 | 35.0 |
|
88.8 |
RPL08.EY.DHA.01610 |
RPL08.EY.DHC - Install Electrical Tie-ins | Build back Exterior Leave Out #17 (South) | Not Started | 04/06/27 | 04/12/27 | 6.2 | 6.2 |
|
207.5 |
RPL08.EY.ENDC.1970 |
RPL08.EY.DHD.T1 - HAC Prefab prior to install for DH C | Tent 2 | Not Started | 04/06/27 | 04/19/27 | 12.5 | 12.5 |
|
142.5 |
RPL08.INT.CTRC.2580 |
RPL08.Interior.Center-Corridor LO #10 - Install Horizontal Steel Supports for Cable Tray (IFP Add) | Remaining of LO Wall #10 ((Spoke Parts & Spoke Tech) | Not Started | 04/06/27 | 04/08/27 | 3.8 | 3.8 |
|
175.0 |
RPL08.INT.DHA.03740 |
RPL08.Interior.DHA - OFE - Control Fault Domain 5 (HAC) | Control Fault Domain 5 | Not Started | 04/06/27 | 04/19/27 | 12.5 | 12.5 |
|
115.0 |
RPL08.INT.SBC.03640 |
RPL08.Interior.SSB-Corridor - BoW - Install Vertical Tube Steel Support for Cable Tray (IFP Add) | Balance of Walls & Overhead | Not Started | 04/06/27 | 04/12/27 | 6.2 | 6.2 |
|
143.8 |
DCC.B8.3537 |
[SSDCB3] Cabling Start : Front End Production Cabling [DHA] | Connectivity | Not Started | 04/07/27 | 04/07/27 | 0.0 | 0.0 |
|
250.0 |
GCD.RPL08.4065 |
[RPL08] TC-C Ready : Production Cabling Start [DHA Rows 01-08] | TC-C Ready: Production Cabling - DHA | Not Started | 04/07/27 | 04/07/27 | 0.0 | 0.0 |
|
250.0 |
RPL08.CON.WP3B.01920 |
RPL08.Conn EF1<>DHA.01 - WBS Summary | EF1<>DHA.01 | Not Started | 04/07/27 | 04/21/27 | 13.8 | 13.8 |
|
227.5 |
RPL08.CX.DHB.01340 |
RPL08.CX.DHB - L3/L4 - Control Fault Domain 02 - TW Flush and Fill | Control Fault Domain 2 | Not Started | 04/07/27 | 04/16/27 | 10.0 | 10.0 |
|
148.8 |
RPL08.EY.DHA.01390 |
RPL08.EY.DHA - Install Remaining EY Paving | Hardscape and Landscape | Not Started | 04/07/27 | 04/13/27 | 6.2 | 6.2 |
|
252.5 |
RPL08.EY.DHC.01300 |
RPL08.EY.DHC - Install Sleeves MEPL | Hardscape and Landscape | Not Started | 04/07/27 | 04/13/27 | 6.2 | 6.2 |
|
335.0 |
RPL08.EY.DHC.01320 |
RPL08.EY.DHC - Install Hardscape and Landscape - WBS Summary | Hardscape and Landscape | Not Started | 04/07/27 | 08/24/27 | 122.5 | 122.5 |
|
283.8 |
RPL08.INT.CTRC.01390 |
RPL08.Interior.Center-Corridor (N) - Set Equipment / Interior | Fit out (North) | Not Started | 04/07/27 | 04/13/27 | 6.2 | 6.2 |
|
158.8 |
RPL08.INT.CTRC.01410 |
RPL08.Interior.Center-Corridor (N) - Fire Life Safe Trim | Fit out (North) | Not Started | 04/07/27 | 04/12/27 | 5.0 | 5.0 |
|
148.8 |
RPL08.INT.CTRC.06860 |
RPL08.Interior.Center-Corridor - Final Finishes & Fixtures - Install Cement Board/ Drywall | Restrooms | Not Started | 04/07/27 | 04/13/27 | 6.2 | 6.2 |
|
117.5 |
RPL08.INT.CTRC.2680 |
RPL08.Interior.Center-Corridor LO #10 & #12 - Install Fire Life Safety Lowside OH | Interior Leave Out Wall #10, #12 (DHB/CC) | Not Started | 04/07/27 | 04/09/27 | 3.8 | 3.8 |
|
152.5 |
RPL08.INT.CTRC.2700 |
RPL08.Interior.Center-Corridor LO #10 & #12 - Install Plumbing Lowside OH | Interior Leave Out Wall #10, #12 (DHB/CC) | Not Started | 04/07/27 | 04/09/27 | 3.8 | 3.8 |
|
147.5 |
RPL08.INT.CTRC.7800 |
RPL08.Interior.Center-Corridor LO #10 - Install Mechanical Piping Lowside OH & In Wall | Remaining of LO Wall #10 ((Spoke Parts & Spoke Tech) | Not Started | 04/07/27 | 04/09/27 | 3.8 | 3.8 |
|
153.8 |
RPL08.INT.CTRC.7820 |
RPL08.Interior.Center-Corridor LO #10 - Install Fire Life Safety Lowside OH & In Wall | Remaining of LO Wall #10 ((Spoke Parts & Spoke Tech) | Not Started | 04/07/27 | 04/09/27 | 3.8 | 3.8 |
|
153.8 |
RPL08.INT.CTRC.7840 |
RPL08.Interior.Center-Corridor LO #10 - Install Plumbing Lowside OH & In Wall | Remaining of LO Wall #10 ((Spoke Parts & Spoke Tech) | Not Started | 04/07/27 | 04/09/27 | 3.8 | 3.8 |
|
153.8 |
RPL08.INT.CTRC.7860 |
RPL08.Interior.Center-Corridor LO #10 - Install Security Lowside OH & In Wall | Remaining of LO Wall #10 ((Spoke Parts & Spoke Tech) | Not Started | 04/07/27 | 04/09/27 | 3.8 | 3.8 |
|
153.8 |
RPL08.INT.CTRC.7880 |
RPL08.Interior.Center-Corridor LO #10 - Install Controls / EPMS / BMS OH & In Wall | Remaining of LO Wall #10 ((Spoke Parts & Spoke Tech) | Not Started | 04/07/27 | 04/09/27 | 3.8 | 3.8 |
|
153.8 |
RPL08.INT.CTRC.7900 |
RPL08.Interior.Center-Corridor LO #10 - Install Electrical Lowside OH & In Wall | Remaining of LO Wall #10 ((Spoke Parts & Spoke Tech) | Not Started | 04/07/27 | 04/14/27 | 7.5 | 7.5 |
|
150.0 |
RPL08.INT.DHB.01770 |
RPL08.Interior.DHB - Control Fault Domain 5 - Install Duct (MES Side) | Remaining Tie-ins post Mech Side Aisle install | Not Started | 04/07/27 | 05/04/27 | 25.0 | 25.0 |
|
147.5 |