Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL08 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:14 PM · 5122 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
0
Completed
0
In Progress
0
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL08.INT.CTRC.01420 RPL08.Interior.Center-Corridor (N) - Install Battery Fit out (North) Not Started 04/14/27 04/27/27 12.5 12.5
0%
158.8
RPL08.INT.CTRC.06880 RPL08.Interior.Center-Corridor - Final Finishes & Fixtures - Water Proofing/ Tape Paint Restrooms Not Started 04/14/27 04/20/27 6.2 6.2
0%
117.5
RPL08.INT.CTRC.1240 RPL08.Interior.Center-Corridor - BoW - Install Mechanical Piping/ Refrigerant Lowside On-wall Balance of Walls & Overhead Not Started 04/14/27 04/20/27 6.2 6.2
0%
158.8
RPL08.INT.CTRC.1600 RPL08.Interior.Center-Corridor - BoW - Electrical Trim Out Balance of Walls & Overhead Not Started 04/14/27 04/22/27 8.8 8.8
0%
172.5
RPL08.INT.CTRC.1620 RPL08.Interior.Center-Corridor - BoW - Security Trim Out Balance of Walls & Overhead Not Started 04/14/27 04/22/27 8.8 8.8
0%
172.5
RPL08.INT.CTRC.1640 RPL08.Interior.Center-Corridor - BoW - Duct Drops / Trim out Balance of Walls & Overhead Not Started 04/14/27 04/20/27 6.2 6.2
0%
150.0
RPL08.INT.CTRC.1660 RPL08.Interior.Center-Corridor - BoW - Final Paint and Tube Steel Paint (IFP Add) Balance of Walls & Overhead Not Started 04/14/27 04/22/27 8.8 8.8
0%
147.5
RPL08.INT.CTRC.1680 RPL08.Interior.Center-Corridor - BoW - Install DAS (Distribution Antenna System) Balance of Walls & Overhead Not Started 04/14/27 04/20/27 6.2 6.2
0%
137.5
RPL08.INT.DHB.01810 RPL08.Interior.DHB - Control Fault Domain 5 - Pull BMS from panel to devices Remaining Tie-ins post Mech Side Aisle install Not Started 04/14/27 05/11/27 25.0 25.0
0%
155.0
RPL08.INT.DHB.01820 RPL08.Interior.DHB - Control Fault Domain 5 - Pull EMPS from panel to devices Remaining Tie-ins post Mech Side Aisle install Not Started 04/14/27 05/11/27 25.0 25.0
0%
155.0
RPL08.INT.DHB.01830 RPL08.Interior.DHB - Control Fault Domain 5 - Set UPS and Panel (2) Remaining Tie-ins post Mech Side Aisle install Not Started 04/14/27 05/11/27 25.0 25.0
0%
147.5
RPL08.INT.ENDC.1520 RPL08.Interior.End-Corridor - BoW - Install Backing at Exterior Wall Balance of Walls & Overhead Not Started 04/14/27 04/20/27 6.2 6.2
0%
210.0
RPL08.INT.SBC.03920 RPL08.Interior.SSB-Corridor - BoW - Install Asset Tags Balance of Walls & Overhead Not Started 04/14/27 04/22/27 8.8 8.8
0%
147.5
RPL08.WP3B.013520 RPL08.Conn EF2<>DHB.14 Install (A-End) Pigtails (384F) P2&3 (LV) EF2<>DHB.14 Not Started 04/14/27 04/14/27 1.2 1.2
0%
211.2
RPL08.WP3B.014000 RPL08.Conn EF1<>DHA.02 Splice (A-End) Pigtails (384F) P1&4 (LV) EF1<>DHA.02 Not Started 04/14/27 04/21/27 7.5 7.5
0%
225.0
RPL08.WP3B.015440 RPL08.Conn EF1<>DHA.02 Install (Z-End) Pigtails (384F) P1&4 (LV) EF1<>DHA.02 Not Started 04/14/27 04/14/27 1.2 1.2
0%
225.0
RPL08.WP4.012540 RPL08.Conn DHB.13.11<>11 Pull Simplex Jumper (SC<>LC) [PON (Active, In-Row)] Jumpers Not Started 04/14/27 04/16/27 3.8 3.8
0%
216.2
RPL08.WP4.012560 RPL08.Conn DHB.14.15<>15 Pull Simplex Jumper (SC<>LC) [PON (Active, In-Row)] Across-Row Not Started 04/14/27 04/16/27 3.8 3.8
0%
216.2
RPL.GF.D.N8140.XR Fiber Pulls, Test & Term to Prod EF1 Complete RPL 10 to RPL08 Receive Milestones (XREFs) Not Started 04/15/27 04/15/27 0.0 0.0
0%
320.0
RPL.GF.D.N8150.XR Fiber Pulls, Test & Term to Prod EF2 Complete RPL 10 to RPL08 Receive Milestones (XREFs) Not Started 04/15/27 04/15/27 0.0 0.0
0%
320.0
RPL.GF.D.N8200.XR DAS/PS System pathways complete SSB, DH B, DH A for RPL07 Receive Milestones (XREFs) Not Started 04/15/27 04/15/27 0.0 0.0
0%
398.8
RPL.GF.D.N8210.XR DAS/PS System pathways complete DH D, DH C for RPL07 Receive Milestones (XREFs) Not Started 04/15/27 04/15/27 0.0 0.0
0%
398.8
RPL.GF.D.N8220.XR ENS complete - RPL06 DHB/A Receive Milestones (XREFs) Not Started 04/15/27 04/15/27 0.0 0.0
0%
398.8
RPL.GF.D.N8230.XR ENS complete - RPL06 DHD/C Receive Milestones (XREFs) Not Started 04/15/27 04/15/27 0.0 0.0
0%
398.8
RPL08.CON.WP2.02400 RPL08.Conn - GS EF2 (North) Install Cabling (Pull, Splice & Terminate) Cabling Not Started 04/15/27 04/20/27 5.0 5.0
0%
320.0
RPL08.CON.WP2.07840 RPL08.Conn - GS EF1 (South) Install Cabling (Pull, Splice & Terminate) Cabling Not Started 04/15/27 04/20/27 5.0 5.0
0%
320.0
RPL08.CON.WP3A.01000 RPL08.Conn - OSP - WBS Summary WP#3A OSP Not Started 04/15/27 06/21/27 58.8 58.8
0%
340.0
RPL08.CON.WP3A.01200 RPL08.Conn - Production EF2 (North) - WBS Summary Prod EF2 (North) Not Started 04/15/27 06/01/27 41.2 41.2
0%
357.5
RPL08.CON.WP3A.01620 RPL08.Conn EF2 Infrastructure 1 (Racks & Vertical Cable Manager, Ladder Racks) Infrastructure Not Started 04/15/27 05/12/27 25.0 25.0
0%
191.2
RPL08.INT.CTRC.3000 RPL08.Interior.Center-Corridor LO #10 & #12 - Install Electrical Lowside OH Interior Leave Out Wall #10, #12 (DHB/CC) Not Started 04/15/27 04/20/27 5.0 5.0
0%
147.5
RPL08.INT.CTRC.7940 RPL08.Interior.Center-Corridor LO #10 - Hard Lid Framing Remaining of LO Wall #10 ((Spoke Parts & Spoke Tech) Not Started 04/15/27 04/19/27 3.8 3.8
0%
150.0
RPL08.INT.DHD.01130 RPL08.Interior.DHD - Control Fault Domain 1 - Install Duct (MES Side) Remaining Tie-ins post Mech Side Aisle install Not Started 04/15/27 05/12/27 25.0 25.0
0%
191.2
RPL08.INT.DHD.01140 RPL08.Interior.DHD - Control Fault Domain 1 - Install Vesda / FA Remaining Tie-ins post Mech Side Aisle install Not Started 04/15/27 05/12/27 25.0 25.0
0%
203.8
RPL08.INT.DHD.01150 RPL08.Interior.DHD - Control Fault Domain 1 - Install FW Remaining Tie-ins post Mech Side Aisle install Not Started 04/15/27 05/12/27 25.0 25.0
0%
191.2
RPL08.INT.DHD.01990 RPL08.Interior.DHD - Control Fault Domain 1 - Install TW Remaining Tie-ins post Mech Side Aisle install Not Started 04/15/27 05/12/27 25.0 25.0
0%
191.2
RPL08.WP3B.014960 RPL08.Conn EF2<>DHB.14 Splice (A-End) Pigtails (384F) P2&3 (LV) EF2<>DHB.14 Not Started 04/15/27 04/22/27 7.5 7.5
0%
211.2
RPL08.WP3B.016400 RPL08.Conn EF2<>DHB.14 Install (Z-End) Pigtails (384F) P2&3 (LV) EF2<>DHB.14 Not Started 04/15/27 04/15/27 1.2 1.2
0%
211.2
RPL08.WP4.012820 RPL08.Conn DHB.11.03 Pull Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] Jumpers (AI Confirmed) Not Started 04/15/27 04/28/27 12.5 12.5
0%
206.2
RPL08.WP4.012840 RPL08.Conn DHB.12.07 Pull Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] Jumpers (AI Confirmed) Not Started 04/15/27 04/28/27 12.5 12.5
0%
206.2
RPL.08.D.83340.XR Pull and Term MV Skids - RPL08 DHD Receive Milestones (XREFs) Not Started 04/16/27 04/16/27 0.0 0.0
0%
210.0
RPL.08.D.83840.XR 100MW Cx Temp Power to MV Skids RPL08 DHD Available Receive Milestones (XREFs) Not Started 04/16/27 04/16/27 0.0 0.0
0%
210.0
RPL08.INT.CTRC.1700 RPL08.Interior.Center-Corridor - BoW - Plumbing Trim Out Balance of Walls & Overhead Not Started 04/16/27 04/22/27 6.2 6.2
0%
172.5
RPL08.INT.CTRC.1720 RPL08.Interior.Center-Corridor - BoW - Fire Life Safety Trim Out / Fire Alarm Trim Out Balance of Walls & Overhead Not Started 04/16/27 04/26/27 8.8 8.8
0%
172.5
RPL08.INT.CTRC.2500 RPL08.Interior.Center-Corridor LO #11 & #13 - Close Interior LO #11 & #13 DHA/CC (For HACs in DHA) WBS Summary Interior Leave Out Wall #11, #13 (DHA/CC) Not Started 04/16/27 06/16/27 53.8 53.8
0%
115.0
RPL08.INT.CTRC.3540 RPL08.Interior.Center-Corridor LO #11 & #13 - Install IMP Wall at Leave Out (DH A) Interior Leave Out Wall #11, #13 (DHA/CC) Not Started 04/16/27 04/20/27 3.8 3.8
0%
115.0
RPL08.INT.CTRC.3560 RPL08.Interior.Center-Corridor LO #11 & #13 - Tie In MEPF with IMP Wall buildback Interior Leave Out Wall #11, #13 (DHA/CC) Not Started 04/16/27 04/21/27 5.0 5.0
0%
115.0
RPL08.INT.DHA.01580 RPL08.Interior.DHA - Control Fault Domain 4 - Pull BMS from panel to devices Remaining Tie-ins post Mech Side Aisle install Not Started 04/16/27 05/13/27 25.0 25.0
0%
145.0
RPL08.INT.DHA.01590 RPL08.Interior.DHA - Control Fault Domain 4 - Pull EMPS from panel to devices Remaining Tie-ins post Mech Side Aisle install Not Started 04/16/27 05/13/27 25.0 25.0
0%
145.0
RPL08.INT.DHA.01600 RPL08.Interior.DHA - Control Fault Domain 4 - Set UPS and Panel (2) Remaining Tie-ins post Mech Side Aisle install Not Started 04/16/27 05/13/27 25.0 25.0
0%
138.8
RPL08.INT.DHA.01620 RPL08.Interior.DHA - Control Fault Domain 3 - L2 Checklist Completion Remaining Tie-ins post Mech Side Aisle install Not Started 04/16/27 05/13/27 25.0 25.0
0%
131.2
RPL08.INT.ENDC.01360 RPL08.Interior.End-Corridor - Install Lighting Fit out Not Started 04/16/27 04/26/27 8.8 8.8
0%
247.5
RPL08.INT.ENDC.07000 RPL08.Interior.End-Corridor - Final Finishes & Fixtures - Final Clean Restrooms Not Started 04/16/27 04/21/27 5.0 5.0
0%
260.0
RPL08.INT.SSB.06485 RPL08.Interior.SSB LO #16 - Final Punch Walk Leave Out Wall #16 (SSB - North of Loading Dock) Not Started 04/16/27 04/22/27 6.2 6.2
0%
168.8
RPL08.WP4.012580 RPL08.Conn DHA.01.02<>01 Pull Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] Jumpers Not Started 04/16/27 04/21/27 5.0 5.0
0%
230.0
RPL08.WP4.012600 RPL08.Conn DHA.02.06<>05 Pull Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] Across-Row Not Started 04/16/27 04/21/27 5.0 5.0
0%
230.0
GCD.RPL08.4565 L3/L4 Finish EY - DHA EY Not Started 04/19/27 04/19/27 0.0 0.0
0%
226.2
RPL08.CON.WP2.07280 RPL08.Conn - Ext. GSIDF8X01- Install & Test Network (FIM) Network Not Started 04/19/27 04/21/27 3.8 3.8
0%
392.5
RPL08.CON.WP2.07480 RPL08.Conn - Ext. GSIDF8X02 - Install & Test Network (FIM) Network Not Started 04/19/27 04/21/27 3.8 3.8
0%
392.5
RPL08.CON.WP2.08440 RPL08.Conn - Ext. GSIDF8X03 - Install & Test Network (FIM) Network Not Started 04/19/27 04/21/27 3.8 3.8
0%
392.5
RPL08.CON.WP2.08760 RPL08.Conn - GSIDF/DH B1 - Install Cabling (Pull, Splice & terminate) Cabling Not Started 04/19/27 04/26/27 7.5 7.5
0%
385.0
RPL08.CON.WP2.08800 RPL08.Conn - GSIDF/DH B1 - Install Copper, WAPs, Security Camera & Access Control Cabling Not Started 04/19/27 05/04/27 15.0 15.0
0%
212.5
RPL08.CON.WP4.01400 RPL08.Conn WP4 FENW DHB CFD3 Infrastructure Infrastructure Not Started 04/19/27 05/14/27 25.0 25.0
0%
206.2
RPL08.CX.DHB.01400 RPL08.CX.DHB - L3/L4 - Control Fault Domain 03 - TW Flush and Fill Control Fault Domain 3 Not Started 04/19/27 04/28/27 10.0 10.0
0%
158.8
RPL08.CX.DHB.01560 RPL08.CX.DHB - L3/L4 - Control Fault Domain 04 - FW Flush and Fill Control Fault Domain 4 Not Started 04/19/27 04/27/27 8.8 8.8
0%
170.0
RPL08.INT.CTRC.01440 RPL08.Interior.Center-Corridor (N) - Plumbing Trim Fit out (North) Not Started 04/19/27 04/22/27 5.0 5.0
0%
148.8
RPL08.INT.CTRC.8900 RPL08.Interior.Center-Corridor LO #11 & #13 - Install IMP Wall at Leave Out (DH C) Interior Leave Out Wall #11, #13 (DHA/CC) Not Started 04/19/27 04/21/27 3.8 3.8
0%
115.0
RPL08.INT.DHB.01560 RPL08.Conn DHB - CFD3 - Set Passive Racks for WP#3b (16) Infrastructure Not Started 04/19/27 04/21/27 3.8 3.8
0%
175.0
RPL08.INT.DHB.02840 RPL08.Conn DHB - CFD3 - Set Passive Racks for PON (16) Infrastructure Not Started 04/19/27 04/21/27 3.8 3.8
0%
202.5
RPL08.INT.SBC.03960 RPL08.Interior.SSB-Corridor - BoW - Final Paint and Tube Steel Paint (IFP Add) Balance of Walls & Overhead Not Started 04/19/27 04/27/27 8.8 8.8
0%
143.8
RPL08.INT.SSB.02600 RPL08.Interior.SSB - BoW - ACT - Close Up Inspection Balance of Walls and OverHead Not Started 04/19/27 04/23/27 6.2 6.2
0%
186.2
RPL08.INT.SSBC.01290 RPL08.Interior.SSB-Corridor - Install Cable Tray Fit out Not Started 04/19/27 04/23/27 6.2 6.2
0%
147.5
RPL08.WP4.012940 RPL08.Conn DHB.13.10<>09 Pull Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] Across-Row Not Started 04/19/27 04/22/27 5.0 5.0
0%
216.2
RPL08.WP4.012960 RPL08.Conn DHB.14.14<>13 Pull Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] Jumpers Not Started 04/19/27 04/22/27 5.0 5.0
0%
216.2
GCD.RPL08.4965 L3/L4 Start EY - DHD EY Not Started 04/20/27 04/20/27 0.0 0.0
0%
323.8
ICM.B8.2510.A [SSDCB3] L3/4 Start - DHA Commissioning Not Started 04/20/27 04/20/27 0.0 0.0
0%
226.2
RPL.GF.D.N8100.XG Both GSEF Room Complete RPL 8 Give Milestones (XREFs) Not Started 04/20/27 04/20/27 0.0 0.0
0%
393.8
RPL08.CX.DHA.01030 RPL08.CX.DHA - L3/L4 - House Power (for electrical) DHA HOUSE POWER Not Started 04/20/27 05/03/27 12.5 12.5
0%
83.8
RPL08.CX.DHA.01340 RPL08.CX.DHA - L3/L4 - Control Fault Domain 02 - TW Flush and Fill Control Fault Domain 2 Not Started 04/20/27 04/29/27 10.0 10.0
0%
150.0
RPL08.CX.DHB.01070 RPL08.CX.DHB - L3/L4 - House Power (for mechainical) DHB HOUSE POWER Not Started 04/20/27 05/03/27 12.5 12.5
0%
83.8
RPL08.CX.DHD.00000 RPL08.CX.DHD - L3, L4, IST - WBS Summary DHD Not Started 04/20/27 06/23/28 370.0 370.0
0%
12.5
RPL08.CX.DHD.01000 RPL08.CX.DHD - L3 - WBS Summary (Electrical) DHD ELECTRICAL Not Started 04/20/27 08/27/27 115.0 115.0
0%
208.8
RPL08.CX.DHD.01010 RPL08.CX.DHD - L3/L4 - MV Skids (8) Loop DHD ELECTRICAL Not Started 04/20/27 04/29/27 10.0 10.0
0%
207.5
RPL08.INT.CTRC.7920 RPL08.Interior.Center-Corridor LO #10 - Hard Lid Rough-In Remaining of LO Wall #10 ((Spoke Parts & Spoke Tech) Not Started 04/20/27 04/23/27 5.0 5.0
0%
150.0
RPL08.INT.DHC.02290 RPL08.Interior.DHC - OFE - Control Fault Domain 1 (HAC) Control Fault Domain 1 Not Started 04/20/27 05/10/27 18.8 18.8
0%
142.5
RPL08.WP3B.016860 RPL08.Conn EF1<>DHA.01 Test Pigtails (384F) P1&4 (LV) EF1<>DHA.01 Not Started 04/20/27 04/21/27 2.5 2.5
0%
227.5
RPL08.CON.WP2.07920 RPL08.Conn - EF2<>MDF2 Install Cabling (Pull, Splice & Terminate) OSP (MDF RPL10 <> MDF RPL08) Not Started 04/21/27 04/28/27 7.5 7.5
0%
320.0
RPL08.CON.WP2.08000 RPL08.Conn - EF1<>MDF1 Install Cabling (Pull, Splice & Terminate) OSP (MDF RPL10 <> MDF RPL08) Not Started 04/21/27 04/28/27 7.5 7.5
0%
320.0
RPL08.Conn.MS.01220 CorpNet FacNet Available (mCUP) Connectivity Milestones Not Started 04/21/27 04/21/27 0.0 0.0
0%
392.5
RPL08.EY.DHC.01340 RPL08.EY.DHC - Install Lighting Hardscape and Landscape Not Started 04/21/27 05/04/27 12.5 12.5
0%
335.0
RPL08.INT.CTRC.06900 RPL08.Interior.Center-Corridor - Final Finishes & Fixtures - Casework Restrooms Not Started 04/21/27 04/29/27 8.8 8.8
0%
117.5
RPL08.INT.CTRC.1360 RPL08.Interior.Center-Corridor - BoW - Install Split Systems/Humidifiers Balance of Walls & Overhead Not Started 04/21/27 04/27/27 6.2 6.2
0%
158.8
RPL08.INT.CTRC.1740 RPL08.Interior.Center-Corridor - BoW - Install Remaining Lights Balance of Walls & Overhead Not Started 04/21/27 05/04/27 12.5 12.5
0%
137.5
RPL08.INT.CTRC.1800 RPL08.Interior.Center-Corridor - BoW - Install Door (Verify with Trades before installation) Balance of Walls & Overhead Not Started 04/21/27 04/29/27 8.8 8.8
0%
150.0
RPL08.INT.CTRC.2780 RPL08.Interior.Center-Corridor LO #10 & #12 - Install Door Frames Interior Leave Out Wall #10, #12 (DHB/CC) Not Started 04/21/27 04/22/27 2.5 2.5
0%
147.5
RPL08.INT.DHB.01860 RPL08.Interior.DHB - Control Fault Domain 5 - Install Mechanical Side Aisle Cable Tray Remaining Tie-ins post Mech Side Aisle install Not Started 04/21/27 05/18/27 25.0 25.0
0%
147.5
RPL08.INT.DHB.01900 RPL08.Interior.DHB - Control Fault Domain 5 - Install copper from GS.IDF to BMS and EPMS panels (UG from Corr IDF) Remaining Tie-ins post Mech Side Aisle install Not Started 04/21/27 05/18/27 25.0 25.0
0%
148.8
RPL08.INT.DHD.02350 RPL08.Interior.DHD - OFE - Control Fault Domain 2 (HAC) Control Fault Domain 2 Not Started 04/21/27 05/04/27 12.5 12.5
0%
151.2
RPL08.INT.ENDC.1540 RPL08.Interior.End-Corridor - BoW - QC - Backings/Walls Balance of Walls & Overhead Not Started 04/21/27 04/27/27 6.2 6.2
0%
210.0
RPL08.INT.SSB.01570 RPL08.Interior.SSB - Loading Dock and Storage - Electrical L2 Checklist Completion Loading Dock and Storage Not Started 04/21/27 05/04/27 12.5 12.5
0%
206.2
RPL08.WP3B.017820 RPL08.Conn EF2<>DHB.13 Test Pigtails (384F) P2&3 (LV) EF2<>DHB.13 Not Started 04/21/27 04/22/27 2.5 2.5
0%
213.8