Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL08 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:14 PM
· 5122 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
0
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL08.INT.CTRC.01420 |
RPL08.Interior.Center-Corridor (N) - Install Battery | Fit out (North) | Not Started | 04/14/27 | 04/27/27 | 12.5 | 12.5 |
|
158.8 |
RPL08.INT.CTRC.06880 |
RPL08.Interior.Center-Corridor - Final Finishes & Fixtures - Water Proofing/ Tape Paint | Restrooms | Not Started | 04/14/27 | 04/20/27 | 6.2 | 6.2 |
|
117.5 |
RPL08.INT.CTRC.1240 |
RPL08.Interior.Center-Corridor - BoW - Install Mechanical Piping/ Refrigerant Lowside On-wall | Balance of Walls & Overhead | Not Started | 04/14/27 | 04/20/27 | 6.2 | 6.2 |
|
158.8 |
RPL08.INT.CTRC.1600 |
RPL08.Interior.Center-Corridor - BoW - Electrical Trim Out | Balance of Walls & Overhead | Not Started | 04/14/27 | 04/22/27 | 8.8 | 8.8 |
|
172.5 |
RPL08.INT.CTRC.1620 |
RPL08.Interior.Center-Corridor - BoW - Security Trim Out | Balance of Walls & Overhead | Not Started | 04/14/27 | 04/22/27 | 8.8 | 8.8 |
|
172.5 |
RPL08.INT.CTRC.1640 |
RPL08.Interior.Center-Corridor - BoW - Duct Drops / Trim out | Balance of Walls & Overhead | Not Started | 04/14/27 | 04/20/27 | 6.2 | 6.2 |
|
150.0 |
RPL08.INT.CTRC.1660 |
RPL08.Interior.Center-Corridor - BoW - Final Paint and Tube Steel Paint (IFP Add) | Balance of Walls & Overhead | Not Started | 04/14/27 | 04/22/27 | 8.8 | 8.8 |
|
147.5 |
RPL08.INT.CTRC.1680 |
RPL08.Interior.Center-Corridor - BoW - Install DAS (Distribution Antenna System) | Balance of Walls & Overhead | Not Started | 04/14/27 | 04/20/27 | 6.2 | 6.2 |
|
137.5 |
RPL08.INT.DHB.01810 |
RPL08.Interior.DHB - Control Fault Domain 5 - Pull BMS from panel to devices | Remaining Tie-ins post Mech Side Aisle install | Not Started | 04/14/27 | 05/11/27 | 25.0 | 25.0 |
|
155.0 |
RPL08.INT.DHB.01820 |
RPL08.Interior.DHB - Control Fault Domain 5 - Pull EMPS from panel to devices | Remaining Tie-ins post Mech Side Aisle install | Not Started | 04/14/27 | 05/11/27 | 25.0 | 25.0 |
|
155.0 |
RPL08.INT.DHB.01830 |
RPL08.Interior.DHB - Control Fault Domain 5 - Set UPS and Panel (2) | Remaining Tie-ins post Mech Side Aisle install | Not Started | 04/14/27 | 05/11/27 | 25.0 | 25.0 |
|
147.5 |
RPL08.INT.ENDC.1520 |
RPL08.Interior.End-Corridor - BoW - Install Backing at Exterior Wall | Balance of Walls & Overhead | Not Started | 04/14/27 | 04/20/27 | 6.2 | 6.2 |
|
210.0 |
RPL08.INT.SBC.03920 |
RPL08.Interior.SSB-Corridor - BoW - Install Asset Tags | Balance of Walls & Overhead | Not Started | 04/14/27 | 04/22/27 | 8.8 | 8.8 |
|
147.5 |
RPL08.WP3B.013520 |
RPL08.Conn EF2<>DHB.14 Install (A-End) Pigtails (384F) P2&3 (LV) | EF2<>DHB.14 | Not Started | 04/14/27 | 04/14/27 | 1.2 | 1.2 |
|
211.2 |
RPL08.WP3B.014000 |
RPL08.Conn EF1<>DHA.02 Splice (A-End) Pigtails (384F) P1&4 (LV) | EF1<>DHA.02 | Not Started | 04/14/27 | 04/21/27 | 7.5 | 7.5 |
|
225.0 |
RPL08.WP3B.015440 |
RPL08.Conn EF1<>DHA.02 Install (Z-End) Pigtails (384F) P1&4 (LV) | EF1<>DHA.02 | Not Started | 04/14/27 | 04/14/27 | 1.2 | 1.2 |
|
225.0 |
RPL08.WP4.012540 |
RPL08.Conn DHB.13.11<>11 Pull Simplex Jumper (SC<>LC) [PON (Active, In-Row)] | Jumpers | Not Started | 04/14/27 | 04/16/27 | 3.8 | 3.8 |
|
216.2 |
RPL08.WP4.012560 |
RPL08.Conn DHB.14.15<>15 Pull Simplex Jumper (SC<>LC) [PON (Active, In-Row)] | Across-Row | Not Started | 04/14/27 | 04/16/27 | 3.8 | 3.8 |
|
216.2 |
RPL.GF.D.N8140.XR |
Fiber Pulls, Test & Term to Prod EF1 Complete RPL 10 to RPL08 | Receive Milestones (XREFs) | Not Started | 04/15/27 | 04/15/27 | 0.0 | 0.0 |
|
320.0 |
RPL.GF.D.N8150.XR |
Fiber Pulls, Test & Term to Prod EF2 Complete RPL 10 to RPL08 | Receive Milestones (XREFs) | Not Started | 04/15/27 | 04/15/27 | 0.0 | 0.0 |
|
320.0 |
RPL.GF.D.N8200.XR |
DAS/PS System pathways complete SSB, DH B, DH A for RPL07 | Receive Milestones (XREFs) | Not Started | 04/15/27 | 04/15/27 | 0.0 | 0.0 |
|
398.8 |
RPL.GF.D.N8210.XR |
DAS/PS System pathways complete DH D, DH C for RPL07 | Receive Milestones (XREFs) | Not Started | 04/15/27 | 04/15/27 | 0.0 | 0.0 |
|
398.8 |
RPL.GF.D.N8220.XR |
ENS complete - RPL06 DHB/A | Receive Milestones (XREFs) | Not Started | 04/15/27 | 04/15/27 | 0.0 | 0.0 |
|
398.8 |
RPL.GF.D.N8230.XR |
ENS complete - RPL06 DHD/C | Receive Milestones (XREFs) | Not Started | 04/15/27 | 04/15/27 | 0.0 | 0.0 |
|
398.8 |
RPL08.CON.WP2.02400 |
RPL08.Conn - GS EF2 (North) Install Cabling (Pull, Splice & Terminate) | Cabling | Not Started | 04/15/27 | 04/20/27 | 5.0 | 5.0 |
|
320.0 |
RPL08.CON.WP2.07840 |
RPL08.Conn - GS EF1 (South) Install Cabling (Pull, Splice & Terminate) | Cabling | Not Started | 04/15/27 | 04/20/27 | 5.0 | 5.0 |
|
320.0 |
RPL08.CON.WP3A.01000 |
RPL08.Conn - OSP - WBS Summary | WP#3A OSP | Not Started | 04/15/27 | 06/21/27 | 58.8 | 58.8 |
|
340.0 |
RPL08.CON.WP3A.01200 |
RPL08.Conn - Production EF2 (North) - WBS Summary | Prod EF2 (North) | Not Started | 04/15/27 | 06/01/27 | 41.2 | 41.2 |
|
357.5 |
RPL08.CON.WP3A.01620 |
RPL08.Conn EF2 Infrastructure 1 (Racks & Vertical Cable Manager, Ladder Racks) | Infrastructure | Not Started | 04/15/27 | 05/12/27 | 25.0 | 25.0 |
|
191.2 |
RPL08.INT.CTRC.3000 |
RPL08.Interior.Center-Corridor LO #10 & #12 - Install Electrical Lowside OH | Interior Leave Out Wall #10, #12 (DHB/CC) | Not Started | 04/15/27 | 04/20/27 | 5.0 | 5.0 |
|
147.5 |
RPL08.INT.CTRC.7940 |
RPL08.Interior.Center-Corridor LO #10 - Hard Lid Framing | Remaining of LO Wall #10 ((Spoke Parts & Spoke Tech) | Not Started | 04/15/27 | 04/19/27 | 3.8 | 3.8 |
|
150.0 |
RPL08.INT.DHD.01130 |
RPL08.Interior.DHD - Control Fault Domain 1 - Install Duct (MES Side) | Remaining Tie-ins post Mech Side Aisle install | Not Started | 04/15/27 | 05/12/27 | 25.0 | 25.0 |
|
191.2 |
RPL08.INT.DHD.01140 |
RPL08.Interior.DHD - Control Fault Domain 1 - Install Vesda / FA | Remaining Tie-ins post Mech Side Aisle install | Not Started | 04/15/27 | 05/12/27 | 25.0 | 25.0 |
|
203.8 |
RPL08.INT.DHD.01150 |
RPL08.Interior.DHD - Control Fault Domain 1 - Install FW | Remaining Tie-ins post Mech Side Aisle install | Not Started | 04/15/27 | 05/12/27 | 25.0 | 25.0 |
|
191.2 |
RPL08.INT.DHD.01990 |
RPL08.Interior.DHD - Control Fault Domain 1 - Install TW | Remaining Tie-ins post Mech Side Aisle install | Not Started | 04/15/27 | 05/12/27 | 25.0 | 25.0 |
|
191.2 |
RPL08.WP3B.014960 |
RPL08.Conn EF2<>DHB.14 Splice (A-End) Pigtails (384F) P2&3 (LV) | EF2<>DHB.14 | Not Started | 04/15/27 | 04/22/27 | 7.5 | 7.5 |
|
211.2 |
RPL08.WP3B.016400 |
RPL08.Conn EF2<>DHB.14 Install (Z-End) Pigtails (384F) P2&3 (LV) | EF2<>DHB.14 | Not Started | 04/15/27 | 04/15/27 | 1.2 | 1.2 |
|
211.2 |
RPL08.WP4.012820 |
RPL08.Conn DHB.11.03 Pull Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] | Jumpers (AI Confirmed) | Not Started | 04/15/27 | 04/28/27 | 12.5 | 12.5 |
|
206.2 |
RPL08.WP4.012840 |
RPL08.Conn DHB.12.07 Pull Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] | Jumpers (AI Confirmed) | Not Started | 04/15/27 | 04/28/27 | 12.5 | 12.5 |
|
206.2 |
RPL.08.D.83340.XR |
Pull and Term MV Skids - RPL08 DHD | Receive Milestones (XREFs) | Not Started | 04/16/27 | 04/16/27 | 0.0 | 0.0 |
|
210.0 |
RPL.08.D.83840.XR |
100MW Cx Temp Power to MV Skids RPL08 DHD Available | Receive Milestones (XREFs) | Not Started | 04/16/27 | 04/16/27 | 0.0 | 0.0 |
|
210.0 |
RPL08.INT.CTRC.1700 |
RPL08.Interior.Center-Corridor - BoW - Plumbing Trim Out | Balance of Walls & Overhead | Not Started | 04/16/27 | 04/22/27 | 6.2 | 6.2 |
|
172.5 |
RPL08.INT.CTRC.1720 |
RPL08.Interior.Center-Corridor - BoW - Fire Life Safety Trim Out / Fire Alarm Trim Out | Balance of Walls & Overhead | Not Started | 04/16/27 | 04/26/27 | 8.8 | 8.8 |
|
172.5 |
RPL08.INT.CTRC.2500 |
RPL08.Interior.Center-Corridor LO #11 & #13 - Close Interior LO #11 & #13 DHA/CC (For HACs in DHA) WBS Summary | Interior Leave Out Wall #11, #13 (DHA/CC) | Not Started | 04/16/27 | 06/16/27 | 53.8 | 53.8 |
|
115.0 |
RPL08.INT.CTRC.3540 |
RPL08.Interior.Center-Corridor LO #11 & #13 - Install IMP Wall at Leave Out (DH A) | Interior Leave Out Wall #11, #13 (DHA/CC) | Not Started | 04/16/27 | 04/20/27 | 3.8 | 3.8 |
|
115.0 |
RPL08.INT.CTRC.3560 |
RPL08.Interior.Center-Corridor LO #11 & #13 - Tie In MEPF with IMP Wall buildback | Interior Leave Out Wall #11, #13 (DHA/CC) | Not Started | 04/16/27 | 04/21/27 | 5.0 | 5.0 |
|
115.0 |
RPL08.INT.DHA.01580 |
RPL08.Interior.DHA - Control Fault Domain 4 - Pull BMS from panel to devices | Remaining Tie-ins post Mech Side Aisle install | Not Started | 04/16/27 | 05/13/27 | 25.0 | 25.0 |
|
145.0 |
RPL08.INT.DHA.01590 |
RPL08.Interior.DHA - Control Fault Domain 4 - Pull EMPS from panel to devices | Remaining Tie-ins post Mech Side Aisle install | Not Started | 04/16/27 | 05/13/27 | 25.0 | 25.0 |
|
145.0 |
RPL08.INT.DHA.01600 |
RPL08.Interior.DHA - Control Fault Domain 4 - Set UPS and Panel (2) | Remaining Tie-ins post Mech Side Aisle install | Not Started | 04/16/27 | 05/13/27 | 25.0 | 25.0 |
|
138.8 |
RPL08.INT.DHA.01620 |
RPL08.Interior.DHA - Control Fault Domain 3 - L2 Checklist Completion | Remaining Tie-ins post Mech Side Aisle install | Not Started | 04/16/27 | 05/13/27 | 25.0 | 25.0 |
|
131.2 |
RPL08.INT.ENDC.01360 |
RPL08.Interior.End-Corridor - Install Lighting | Fit out | Not Started | 04/16/27 | 04/26/27 | 8.8 | 8.8 |
|
247.5 |
RPL08.INT.ENDC.07000 |
RPL08.Interior.End-Corridor - Final Finishes & Fixtures - Final Clean | Restrooms | Not Started | 04/16/27 | 04/21/27 | 5.0 | 5.0 |
|
260.0 |
RPL08.INT.SSB.06485 |
RPL08.Interior.SSB LO #16 - Final Punch Walk | Leave Out Wall #16 (SSB - North of Loading Dock) | Not Started | 04/16/27 | 04/22/27 | 6.2 | 6.2 |
|
168.8 |
RPL08.WP4.012580 |
RPL08.Conn DHA.01.02<>01 Pull Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] | Jumpers | Not Started | 04/16/27 | 04/21/27 | 5.0 | 5.0 |
|
230.0 |
RPL08.WP4.012600 |
RPL08.Conn DHA.02.06<>05 Pull Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] | Across-Row | Not Started | 04/16/27 | 04/21/27 | 5.0 | 5.0 |
|
230.0 |
GCD.RPL08.4565 |
L3/L4 Finish EY - DHA | EY | Not Started | 04/19/27 | 04/19/27 | 0.0 | 0.0 |
|
226.2 |
RPL08.CON.WP2.07280 |
RPL08.Conn - Ext. GSIDF8X01- Install & Test Network (FIM) | Network | Not Started | 04/19/27 | 04/21/27 | 3.8 | 3.8 |
|
392.5 |
RPL08.CON.WP2.07480 |
RPL08.Conn - Ext. GSIDF8X02 - Install & Test Network (FIM) | Network | Not Started | 04/19/27 | 04/21/27 | 3.8 | 3.8 |
|
392.5 |
RPL08.CON.WP2.08440 |
RPL08.Conn - Ext. GSIDF8X03 - Install & Test Network (FIM) | Network | Not Started | 04/19/27 | 04/21/27 | 3.8 | 3.8 |
|
392.5 |
RPL08.CON.WP2.08760 |
RPL08.Conn - GSIDF/DH B1 - Install Cabling (Pull, Splice & terminate) | Cabling | Not Started | 04/19/27 | 04/26/27 | 7.5 | 7.5 |
|
385.0 |
RPL08.CON.WP2.08800 |
RPL08.Conn - GSIDF/DH B1 - Install Copper, WAPs, Security Camera & Access Control | Cabling | Not Started | 04/19/27 | 05/04/27 | 15.0 | 15.0 |
|
212.5 |
RPL08.CON.WP4.01400 |
RPL08.Conn WP4 FENW DHB CFD3 Infrastructure | Infrastructure | Not Started | 04/19/27 | 05/14/27 | 25.0 | 25.0 |
|
206.2 |
RPL08.CX.DHB.01400 |
RPL08.CX.DHB - L3/L4 - Control Fault Domain 03 - TW Flush and Fill | Control Fault Domain 3 | Not Started | 04/19/27 | 04/28/27 | 10.0 | 10.0 |
|
158.8 |
RPL08.CX.DHB.01560 |
RPL08.CX.DHB - L3/L4 - Control Fault Domain 04 - FW Flush and Fill | Control Fault Domain 4 | Not Started | 04/19/27 | 04/27/27 | 8.8 | 8.8 |
|
170.0 |
RPL08.INT.CTRC.01440 |
RPL08.Interior.Center-Corridor (N) - Plumbing Trim | Fit out (North) | Not Started | 04/19/27 | 04/22/27 | 5.0 | 5.0 |
|
148.8 |
RPL08.INT.CTRC.8900 |
RPL08.Interior.Center-Corridor LO #11 & #13 - Install IMP Wall at Leave Out (DH C) | Interior Leave Out Wall #11, #13 (DHA/CC) | Not Started | 04/19/27 | 04/21/27 | 3.8 | 3.8 |
|
115.0 |
RPL08.INT.DHB.01560 |
RPL08.Conn DHB - CFD3 - Set Passive Racks for WP#3b (16) | Infrastructure | Not Started | 04/19/27 | 04/21/27 | 3.8 | 3.8 |
|
175.0 |
RPL08.INT.DHB.02840 |
RPL08.Conn DHB - CFD3 - Set Passive Racks for PON (16) | Infrastructure | Not Started | 04/19/27 | 04/21/27 | 3.8 | 3.8 |
|
202.5 |
RPL08.INT.SBC.03960 |
RPL08.Interior.SSB-Corridor - BoW - Final Paint and Tube Steel Paint (IFP Add) | Balance of Walls & Overhead | Not Started | 04/19/27 | 04/27/27 | 8.8 | 8.8 |
|
143.8 |
RPL08.INT.SSB.02600 |
RPL08.Interior.SSB - BoW - ACT - Close Up Inspection | Balance of Walls and OverHead | Not Started | 04/19/27 | 04/23/27 | 6.2 | 6.2 |
|
186.2 |
RPL08.INT.SSBC.01290 |
RPL08.Interior.SSB-Corridor - Install Cable Tray | Fit out | Not Started | 04/19/27 | 04/23/27 | 6.2 | 6.2 |
|
147.5 |
RPL08.WP4.012940 |
RPL08.Conn DHB.13.10<>09 Pull Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] | Across-Row | Not Started | 04/19/27 | 04/22/27 | 5.0 | 5.0 |
|
216.2 |
RPL08.WP4.012960 |
RPL08.Conn DHB.14.14<>13 Pull Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] | Jumpers | Not Started | 04/19/27 | 04/22/27 | 5.0 | 5.0 |
|
216.2 |
GCD.RPL08.4965 |
L3/L4 Start EY - DHD | EY | Not Started | 04/20/27 | 04/20/27 | 0.0 | 0.0 |
|
323.8 |
ICM.B8.2510.A |
[SSDCB3] L3/4 Start - DHA | Commissioning | Not Started | 04/20/27 | 04/20/27 | 0.0 | 0.0 |
|
226.2 |
RPL.GF.D.N8100.XG |
Both GSEF Room Complete RPL 8 | Give Milestones (XREFs) | Not Started | 04/20/27 | 04/20/27 | 0.0 | 0.0 |
|
393.8 |
RPL08.CX.DHA.01030 |
RPL08.CX.DHA - L3/L4 - House Power (for electrical) | DHA HOUSE POWER | Not Started | 04/20/27 | 05/03/27 | 12.5 | 12.5 |
|
83.8 |
RPL08.CX.DHA.01340 |
RPL08.CX.DHA - L3/L4 - Control Fault Domain 02 - TW Flush and Fill | Control Fault Domain 2 | Not Started | 04/20/27 | 04/29/27 | 10.0 | 10.0 |
|
150.0 |
RPL08.CX.DHB.01070 |
RPL08.CX.DHB - L3/L4 - House Power (for mechainical) | DHB HOUSE POWER | Not Started | 04/20/27 | 05/03/27 | 12.5 | 12.5 |
|
83.8 |
RPL08.CX.DHD.00000 |
RPL08.CX.DHD - L3, L4, IST - WBS Summary | DHD | Not Started | 04/20/27 | 06/23/28 | 370.0 | 370.0 |
|
12.5 |
RPL08.CX.DHD.01000 |
RPL08.CX.DHD - L3 - WBS Summary (Electrical) | DHD ELECTRICAL | Not Started | 04/20/27 | 08/27/27 | 115.0 | 115.0 |
|
208.8 |
RPL08.CX.DHD.01010 |
RPL08.CX.DHD - L3/L4 - MV Skids (8) Loop | DHD ELECTRICAL | Not Started | 04/20/27 | 04/29/27 | 10.0 | 10.0 |
|
207.5 |
RPL08.INT.CTRC.7920 |
RPL08.Interior.Center-Corridor LO #10 - Hard Lid Rough-In | Remaining of LO Wall #10 ((Spoke Parts & Spoke Tech) | Not Started | 04/20/27 | 04/23/27 | 5.0 | 5.0 |
|
150.0 |
RPL08.INT.DHC.02290 |
RPL08.Interior.DHC - OFE - Control Fault Domain 1 (HAC) | Control Fault Domain 1 | Not Started | 04/20/27 | 05/10/27 | 18.8 | 18.8 |
|
142.5 |
RPL08.WP3B.016860 |
RPL08.Conn EF1<>DHA.01 Test Pigtails (384F) P1&4 (LV) | EF1<>DHA.01 | Not Started | 04/20/27 | 04/21/27 | 2.5 | 2.5 |
|
227.5 |
RPL08.CON.WP2.07920 |
RPL08.Conn - EF2<>MDF2 Install Cabling (Pull, Splice & Terminate) | OSP (MDF RPL10 <> MDF RPL08) | Not Started | 04/21/27 | 04/28/27 | 7.5 | 7.5 |
|
320.0 |
RPL08.CON.WP2.08000 |
RPL08.Conn - EF1<>MDF1 Install Cabling (Pull, Splice & Terminate) | OSP (MDF RPL10 <> MDF RPL08) | Not Started | 04/21/27 | 04/28/27 | 7.5 | 7.5 |
|
320.0 |
RPL08.Conn.MS.01220 |
CorpNet FacNet Available (mCUP) | Connectivity Milestones | Not Started | 04/21/27 | 04/21/27 | 0.0 | 0.0 |
|
392.5 |
RPL08.EY.DHC.01340 |
RPL08.EY.DHC - Install Lighting | Hardscape and Landscape | Not Started | 04/21/27 | 05/04/27 | 12.5 | 12.5 |
|
335.0 |
RPL08.INT.CTRC.06900 |
RPL08.Interior.Center-Corridor - Final Finishes & Fixtures - Casework | Restrooms | Not Started | 04/21/27 | 04/29/27 | 8.8 | 8.8 |
|
117.5 |
RPL08.INT.CTRC.1360 |
RPL08.Interior.Center-Corridor - BoW - Install Split Systems/Humidifiers | Balance of Walls & Overhead | Not Started | 04/21/27 | 04/27/27 | 6.2 | 6.2 |
|
158.8 |
RPL08.INT.CTRC.1740 |
RPL08.Interior.Center-Corridor - BoW - Install Remaining Lights | Balance of Walls & Overhead | Not Started | 04/21/27 | 05/04/27 | 12.5 | 12.5 |
|
137.5 |
RPL08.INT.CTRC.1800 |
RPL08.Interior.Center-Corridor - BoW - Install Door (Verify with Trades before installation) | Balance of Walls & Overhead | Not Started | 04/21/27 | 04/29/27 | 8.8 | 8.8 |
|
150.0 |
RPL08.INT.CTRC.2780 |
RPL08.Interior.Center-Corridor LO #10 & #12 - Install Door Frames | Interior Leave Out Wall #10, #12 (DHB/CC) | Not Started | 04/21/27 | 04/22/27 | 2.5 | 2.5 |
|
147.5 |
RPL08.INT.DHB.01860 |
RPL08.Interior.DHB - Control Fault Domain 5 - Install Mechanical Side Aisle Cable Tray | Remaining Tie-ins post Mech Side Aisle install | Not Started | 04/21/27 | 05/18/27 | 25.0 | 25.0 |
|
147.5 |
RPL08.INT.DHB.01900 |
RPL08.Interior.DHB - Control Fault Domain 5 - Install copper from GS.IDF to BMS and EPMS panels (UG from Corr IDF) | Remaining Tie-ins post Mech Side Aisle install | Not Started | 04/21/27 | 05/18/27 | 25.0 | 25.0 |
|
148.8 |
RPL08.INT.DHD.02350 |
RPL08.Interior.DHD - OFE - Control Fault Domain 2 (HAC) | Control Fault Domain 2 | Not Started | 04/21/27 | 05/04/27 | 12.5 | 12.5 |
|
151.2 |
RPL08.INT.ENDC.1540 |
RPL08.Interior.End-Corridor - BoW - QC - Backings/Walls | Balance of Walls & Overhead | Not Started | 04/21/27 | 04/27/27 | 6.2 | 6.2 |
|
210.0 |
RPL08.INT.SSB.01570 |
RPL08.Interior.SSB - Loading Dock and Storage - Electrical L2 Checklist Completion | Loading Dock and Storage | Not Started | 04/21/27 | 05/04/27 | 12.5 | 12.5 |
|
206.2 |
RPL08.WP3B.017820 |
RPL08.Conn EF2<>DHB.13 Test Pigtails (384F) P2&3 (LV) | EF2<>DHB.13 | Not Started | 04/21/27 | 04/22/27 | 2.5 | 2.5 |
|
213.8 |