Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL08 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:14 PM
· 5122 activities
Experimental
Auto-populate checklist dates from schedule:
22
Activities Shown
0
Completed
0
In Progress
7
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL08.CX.DHD.01250 |
RPL08.CX.DHD - Punch List Remediation, Site Acceptance, and AHJ Approval of TCO - ET | DHD DATA HALL LEVEL TESTING | Not Started | 04/05/28 | 04/19/28 | 12.5 | 12.5 |
|
67.5 |
GCD.RPL08.5265 |
IST Finish - DHC | DH | Not Started | 04/06/28 | 04/06/28 | 0.0 | 0.0 |
|
53.8 |
RPL08.WA.DHC.01000 |
RPL08.WA - Weather Allowance - OFE to AC - DHC | Weather Allowance | Not Started | 04/07/28 | 04/19/28 | 16.2 | 16.2 |
|
78.8 |
ICM.B8.8040.C.ET |
[SSDCB3] FE Area Complete (ENS Ready) [DHC] - Early Target | FENW | Not Started | 04/19/28 | 04/19/28 | 0.0 | 0.0 |
|
55.0 |
RPL08.CX.DHC.01250 |
RPL08.CX.DHC - Punch List Remediation, Site Acceptance, and AHJ Approval of TCO - ET | DHC DATA HALL LEVEL TESTING | Not Started | 04/20/28 | 05/03/28 | 12.5 | 12.5 |
|
55.0 |
ICM.B8.1080 |
[SSDCB3] FE Network Complete (ENS Handover) [DHC,D] - Contractual | FENW | Not Started | 04/25/28 | 04/25/28 | 0.0 | 0.0 |
|
52.5 |
ICM.B8.1080.ET |
[SSDCB3] FE Network Complete (ENS Handover) [DHC,D] - Early Target | FENW | Not Started | 04/25/28 | 04/25/28 | 0.0 | 0.0 |
|
52.5 |
RPL08.PR.DHDC.ACT.20 |
RPL08.PR.DHD&C Activation - DH D & C | DH C & D - Activation, Undraining | Not Started | 04/26/28 | 05/09/28 | 12.5 | 12.5 |
|
52.5 |
ICM.B8.1110.ET |
[SSDCB3] Partial Occupancy (FACOPS Handover) - DHC&D - Early Target | Construction | Not Started | 05/03/28 | 05/03/28 | 0.0 | 0.0 |
|
55.0 |
RPL08.SC.020020 |
RPL07 Punch List for SC - Early Target | Punch List | Not Started | 05/04/28 | 05/17/28 | 12.5 | 12.5 |
|
57.5 |
RPL08.PR.DHDC.ACT.40 |
RPL08.PR.DHD&C Undraining - DH D & C | DH C & D - Activation, Undraining | Not Started | 05/10/28 | 05/23/28 | 12.5 | 12.5 |
|
52.5 |
ICM.G.9000.2.ET |
RPL08 Substantial Completion - Early Target | IMS P0 Milestones | Not Started | 05/17/28 | 05/17/28 | 0.0 | 0.0 |
|
57.5 |
RPL.08.D.N6240.XG |
RPL08 Activation Complete for 2nd GW | Internal Milestones (XREFs) | Not Started | 05/23/28 | 05/23/28 | 0.0 | 0.0 |
|
52.5 |
ICM.B8.8040.D |
[SSDCB3] FE Area Complete (ENS Ready) [DHD] - Incentivised (06/09/28) | FENW | Not Started | 06/09/28 | 06/09/28 | 0.0 | 0.0 |
|
12.5 |
RPL08.CX.DHD.01600 |
RPL08.CX.DHD - Punch List Remediation, Site Acceptance, and AHJ Approval of TCO - Contractual | DHD DATA HALL LEVEL TESTING | Not Started | 06/12/28 | 06/23/28 | 12.5 | 12.5 |
|
12.5 |
ICM.B8.8040.C |
[SSDCB3] FE Area Complete (ENS Ready) [DHC] - Incentivised (06/23/28) | FENW | Not Started | 06/23/28 | 06/23/28 | 0.0 | 0.0 |
|
0.0 |
RPL08.CX.DHC.01600 |
RPL08.CX.DHC - Punch List Remediation, Site Acceptance, and AHJ Approval of TCO - Contractual | DHC DATA HALL LEVEL TESTING | Not Started | 06/26/28 | 07/11/28 | 12.5 | 12.5 |
|
0.0 |
ICM.B8.1110 |
[SSDCB3] Partial Occupancy (FACOPS Handover) - DHC&D - Contractual | Contractual | Not Started | 07/11/28 | 07/11/28 | 0.0 | 0.0 |
|
0.0 |
RPL08.SC.020040 |
RPL07 Punch List for SC - Contractual | Punch List | Not Started | 07/12/28 | 07/25/28 | 12.5 | 12.5 |
|
0.0 |
ICM.G.9000.2 |
RPL08 Substantial Completion - Contractual | IMS P0 Milestones | Not Started | 07/25/28 | 07/25/28 | 0.0 | 0.0 |
|
0.0 |
RPL08.SUCC |
SUCC | Obsolete | Not Started | 07/25/28 | 07/25/28 | 0.0 | 0.0 |
|
0.0 |
RPL.GF.D.N8160.XR |
Both Fiber Pulls Complete Substation 8X1 RPL 8 | Receive Milestones (XREFs) | Not Started | 07/26/28 | 07/26/28 | 0.0 | 0.0 |
|
0.0 |