Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL08 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:14 PM · 5122 activities
Experimental Auto-populate checklist dates from schedule:
Clear
22
Activities Shown
0
Completed
0
In Progress
7
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL08.CX.DHD.01250 RPL08.CX.DHD - Punch List Remediation, Site Acceptance, and AHJ Approval of TCO - ET DHD DATA HALL LEVEL TESTING Not Started 04/05/28 04/19/28 12.5 12.5
0%
67.5
GCD.RPL08.5265 IST Finish - DHC DH Not Started 04/06/28 04/06/28 0.0 0.0
0%
53.8
RPL08.WA.DHC.01000 RPL08.WA - Weather Allowance - OFE to AC - DHC Weather Allowance Not Started 04/07/28 04/19/28 16.2 16.2
0%
78.8
ICM.B8.8040.C.ET [SSDCB3] FE Area Complete (ENS Ready) [DHC] - Early Target FENW Not Started 04/19/28 04/19/28 0.0 0.0
0%
55.0
RPL08.CX.DHC.01250 RPL08.CX.DHC - Punch List Remediation, Site Acceptance, and AHJ Approval of TCO - ET DHC DATA HALL LEVEL TESTING Not Started 04/20/28 05/03/28 12.5 12.5
0%
55.0
ICM.B8.1080 [SSDCB3] FE Network Complete (ENS Handover) [DHC,D] - Contractual FENW Not Started 04/25/28 04/25/28 0.0 0.0
0%
52.5
ICM.B8.1080.ET [SSDCB3] FE Network Complete (ENS Handover) [DHC,D] - Early Target FENW Not Started 04/25/28 04/25/28 0.0 0.0
0%
52.5
RPL08.PR.DHDC.ACT.20 RPL08.PR.DHD&C Activation - DH D & C DH C & D - Activation, Undraining Not Started 04/26/28 05/09/28 12.5 12.5
0%
52.5
ICM.B8.1110.ET [SSDCB3] Partial Occupancy (FACOPS Handover) - DHC&D - Early Target Construction Not Started 05/03/28 05/03/28 0.0 0.0
0%
55.0
RPL08.SC.020020 RPL07 Punch List for SC - Early Target Punch List Not Started 05/04/28 05/17/28 12.5 12.5
0%
57.5
RPL08.PR.DHDC.ACT.40 RPL08.PR.DHD&C Undraining - DH D & C DH C & D - Activation, Undraining Not Started 05/10/28 05/23/28 12.5 12.5
0%
52.5
ICM.G.9000.2.ET RPL08 Substantial Completion - Early Target IMS P0 Milestones Not Started 05/17/28 05/17/28 0.0 0.0
0%
57.5
RPL.08.D.N6240.XG RPL08 Activation Complete for 2nd GW Internal Milestones (XREFs) Not Started 05/23/28 05/23/28 0.0 0.0
0%
52.5
ICM.B8.8040.D [SSDCB3] FE Area Complete (ENS Ready) [DHD] - Incentivised (06/09/28) FENW Not Started 06/09/28 06/09/28 0.0 0.0
0%
12.5
RPL08.CX.DHD.01600 RPL08.CX.DHD - Punch List Remediation, Site Acceptance, and AHJ Approval of TCO - Contractual DHD DATA HALL LEVEL TESTING Not Started 06/12/28 06/23/28 12.5 12.5
0%
12.5
ICM.B8.8040.C [SSDCB3] FE Area Complete (ENS Ready) [DHC] - Incentivised (06/23/28) FENW Not Started 06/23/28 06/23/28 0.0 0.0
0%
0.0
RPL08.CX.DHC.01600 RPL08.CX.DHC - Punch List Remediation, Site Acceptance, and AHJ Approval of TCO - Contractual DHC DATA HALL LEVEL TESTING Not Started 06/26/28 07/11/28 12.5 12.5
0%
0.0
ICM.B8.1110 [SSDCB3] Partial Occupancy (FACOPS Handover) - DHC&D - Contractual Contractual Not Started 07/11/28 07/11/28 0.0 0.0
0%
0.0
RPL08.SC.020040 RPL07 Punch List for SC - Contractual Punch List Not Started 07/12/28 07/25/28 12.5 12.5
0%
0.0
ICM.G.9000.2 RPL08 Substantial Completion - Contractual IMS P0 Milestones Not Started 07/25/28 07/25/28 0.0 0.0
0%
0.0
RPL08.SUCC SUCC Obsolete Not Started 07/25/28 07/25/28 0.0 0.0
0%
0.0
RPL.GF.D.N8160.XR Both Fiber Pulls Complete Substation 8X1 RPL 8 Receive Milestones (XREFs) Not Started 07/26/28 07/26/28 0.0 0.0
0%
0.0