Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL08 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:14 PM · 5122 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
0
Completed
0
In Progress
0
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL08.MR.1260 RPL08.MR - Mobilization Complete Make Ready Not Started 06/01/26 06/01/26 0.0 0.0
0%
128.8
RPL08.MR.1261 RPL08.MR - Site Checklist & Control Handoff Make Ready Not Started 06/01/26 06/02/26 2.5 2.5
0%
668.8
RPL08.SUB.1000 RPL08.SubStructure.BLDG - Install Deep/Foundations/Gradebeams/Stemwalls/UG Utilities - WBS Summary SubStructure Not Started 06/01/26 07/29/26 52.5 52.5
0%
156.2
RPL08.SUB.DHAB.01020 RPL08.SubStructure.DHAB - Install Deep/Foundations/Gradebeams/Stemwalls/UG Utilities - WBS Summary DH B & DH A Not Started 06/01/26 07/20/26 43.8 43.8
0%
128.8
RPL08.SUB.DHAB.01070 RPL08.SubStructure.DHAB - Install UG Utilities - WBS Summary Underground Not Started 06/01/26 07/20/26 43.8 43.8
0%
128.8
RPL08.SUB.DHAB.01090 RPL08.SubStructure.DHAB - Install UG Utilities - Electrical/Testing and Pathway Verification and Backfill - Part 1 Underground Not Started 06/01/26 06/18/26 17.5 17.5
0%
128.8
RPL08.SUB.SSB.01000 RPL08.SubStructure.SSB - Install Drilled Piers - Grid lines 6-01/6-10 Foundations Not Started 06/01/26 06/04/26 5.0 5.0
0%
128.8
RPL08.SUB.SSB.01010 RPL08.SubStructure.SSB - Install Deep/Foundations/Gradebeams/Stemwalls - WBS Summary Foundations Not Started 06/01/26 07/08/26 33.8 33.8
0%
128.8
RPL08.SUB.SSB.01020 RPL08.SubStructure.SSB - Install Deep/Foundations/Gradebeams/Stemwalls/UG Utilities - WBS Summary SSB Not Started 06/01/26 07/10/26 36.2 36.2
0%
126.2
RPL08.SUB.SSB.01140 RPL08.SubStructure.SSB - Piers Protection Concrete Capping Foundations Not Started 06/01/26 06/04/26 5.0 5.0
0%
133.8
RPL.08.D.82110.XG Trestle Construction Ready - SSB-1 - East side Give Milestones (XREFs) Not Started 06/02/26 06/02/26 0.0 0.0
0%
668.8
RPL.08.D.82120.XG Trestle Construction Ready - SSB-1 - South side Give Milestones (XREFs) Not Started 06/02/26 06/02/26 0.0 0.0
0%
668.8
RPL.08.D.82130.XG Trestle Construction Ready - SSB-1 - North Give Milestones (XREFs) Not Started 06/02/26 06/02/26 0.0 0.0
0%
668.8
RPL08.CFCI.4340 RPL08 - Submittals Review & Approval - Below Grade Waterproofing Waterproofing Not Started 06/02/26 06/15/26 12.5 12.5
0%
132.5
RPL08.CFCI.5190 RPL08 - Fabricate / Deliver - Vesda System (CFCI) Div. 28 - VESDA System Not Started 06/02/26 07/28/26 50.0 50.0
0%
257.5
RPL08.CFCI.5340 RPL08 - Fabricate / Deliver - Strut (CFCI) Div. 05 - Slotted Channel Framing (Strut) Not Started 06/02/26 06/29/26 25.0 25.0
0%
325.0
RPL08.VDC.1440 T2-4 (mCUP Yard / Ext.) - Review & Approve BIM Shop TIER 2 - 4 - mCUP Yard / Exterior Not Started 06/02/26 07/07/26 31.2 31.2
0%
203.8
RPL08.VDC.1460 T2-4 (EF) - BIM Model & Coordination TIER 2 - 4 - EF Not Started 06/02/26 06/29/26 25.0 25.0
0%
197.5
RPL08.SUB.SSB.01050 RPL08.SubStructure.SSB - Install UG Utilities - Plumbing/Testing/Backfill - Part 1 Underground Not Started 06/03/26 06/15/26 11.2 11.2
0%
131.2
RPL08.SUB.SSB.01060 RPL08.SubStructure.SSB - Install UG Utilities - WBS Summary Underground Not Started 06/03/26 07/10/26 33.8 33.8
0%
126.2
RPL08.CFCI.6240 RPL08 - Fabricate / Deliver - AHUs (EY.SSBC, EY.DHA) (CFCI) Div. 23 - Air Handler Units (AHUs) Not Started 06/04/26 09/15/26 90.0 90.0
0%
210.0
RPL08.CFCI.6920 RPL08 - Fabricate / Deliver - AHUs (EYEC) (CFCI) Div. 23 - Air Handler Units (AHUs) Not Started 06/04/26 06/23/27 330.0 330.0
0%
180.0
PRE.TPA.1160 Roofing - Award and Issue Subcontract DPR issue Trade Parter Agreements Not Started 06/05/26 06/16/26 10.0 10.0
0%
105.0
PRE.TPA.1240 Glass / Metal Panel / Glazing - Award and Issue Subcontract DPR issue Trade Parter Agreements Not Started 06/05/26 06/16/26 10.0 10.0
0%
312.5
PRE.TPA.1280 Kitchen Equipment - Award and Issue Subcontract DPR issue Trade Parter Agreements Not Started 06/05/26 06/16/26 10.0 10.0
0%
546.2
RPL08.CFCI.3900 RPL08 - Fabricate / Deliver - HVAC Materials and Equipment (CFCI) Div. 23 - HVAC Materials and Equip. Not Started 06/05/26 06/11/26 6.2 6.2
0%
207.5
RPL08.CFCI.4120 RPL08 - Fabricate / Deliver - Exterior Louvers Fixed Louvers Not Started 06/05/26 08/28/26 75.0 75.0
0%
392.5
RPL08.CFCI.4190 RPL08 - Fabricate / Deliver - Fire Suppression (CFCI) Div. 21 - Fire Suppression Not Started 06/05/26 07/02/26 25.0 25.0
0%
240.0
RPL08.CFCI.5130 RPL08 - Fabricate / Deliver - Interior Expansion Joints (Spec 07 95 13.13) XX Building Expansion Joints (Spec 07 95 13.13) Not Started 06/05/26 08/14/26 62.5 62.5
0%
202.5
RPL08.SUB.DHAB.01000 RPL08.SubStructure.DHAB - Install Drilled Piers - Grid lines 6-10/6-23 Foundations Not Started 06/05/26 06/11/26 6.2 6.2
0%
128.8
RPL08.SUB.DHAB.01010 RPL08.SubStructure.DHAB - Install Deep/Foundations/Gradebeams/Stemwalls - WBS Summary Foundations Not Started 06/05/26 07/08/26 28.8 28.8
0%
138.8
RPL08.SUB.DHAB.01130 RPL08.SubStructure.DHAB - Piers Protection Concrete Capping Foundations Not Started 06/05/26 06/11/26 6.2 6.2
0%
146.2
RPL08.SUB.SSB.01030 RPL08.SubStructure.SSB - Foundation For Storm Shelter Rebar CMU Foundations Not Started 06/05/26 06/11/26 6.2 6.2
0%
138.8
RPL.08.D.70180.XR External Tie from RPL06 - Interior mCup Crew Flow (RPL06.MCUP.LP2.2000) Internal Milestones (XREFs) Not Started 06/08/26 06/08/26 0.0 0.0
0%
291.2
RPL08.CFCI.4700 RPL08 - Submittals Review & Approval - Security System (CFCI) Div. 28 - Security Syst. Not Started 06/08/26 07/06/26 25.0 25.0
0%
413.8
PRE.MIR.1260 Balance of Trades SA - Meta Review / Authorization Meta Internal Review of Trade Partner Bids Not Started 06/09/26 06/18/26 10.0 10.0
0%
186.2
RPL08.SUB.DHAB.01060 RPL08.SubStructure.DHAB - Install UG Utilities - Plumbing/Testing/Backfill - Part 1 Underground Not Started 06/09/26 06/18/26 10.0 10.0
0%
128.8
RPL08.SUB.SSB.01040 RPL08.SubStructure.SSB - Install Foundations/Anchor Bolts and Gradebeams - Grid lines 6-01/6-10 Foundations Not Started 06/09/26 06/29/26 18.8 18.8
0%
126.2
RPL08.SUB.SSB.01090 RPL08.SubStructure.SSB - Install UG Utilities - Electrical/Testing and Pathway Verification and Backfill - Part 1 Underground Not Started 06/09/26 06/19/26 11.2 11.2
0%
126.2
RPL08.VDC.1480 T2-4 (DH C & D) - BIM Model & Coordination TIER 2 - 4 - DH C & D Not Started 06/09/26 07/07/26 25.0 25.0
0%
247.5
RPL08.VDC.1520 T1 (SSB to Center EF) - GC QC BIM Model TIER 1 - SSB to Center of EF Not Started 06/09/26 06/10/26 2.5 2.5
0%
138.8
RPL08.VDC.1560 T1 (Center EF to End Corridor) - GC QC BIM Model TIER 1 - Center of EF to End Corridor Not Started 06/09/26 06/22/26 12.5 12.5
0%
152.5
RPL08.VDC.1680 T1 (SSB to Center EF) - Procure IMP Walls TIER 1 - SSB to Center of EF Not Started 06/11/26 08/06/26 50.0 50.0
0%
138.8
RPL08.STR.1000 RPL08.Structure.BLDG - Erect Steel/Joist/Decking, Remaining UG/SOG - WBS Summary Structure Not Started 06/12/26 12/19/26 163.8 163.8
0%
178.8
RPL08.STR.SSB.01000 RPL08.Structure.SSB - Install Storm Shelter Rebar, CMU Storm Shelter Not Started 06/12/26 06/23/26 10.0 10.0
0%
138.8
RPL08.STR.SSB.01010 RPL08.Structure.SSB - Erect Steel/Joist/Decking, Remaining UG/SOG - WBS Summary SSB Not Started 06/12/26 10/28/26 121.2 121.2
0%
195.0
RPL08.SUB.DHCD.01000 RPL08.SubStructure.DHCD - Install Drilled Piers - Grid lines 6-23/6-28 Foundations Not Started 06/12/26 06/17/26 5.0 5.0
0%
146.2
RPL08.SUB.DHCD.01010 RPL08.SubStructure.DHCD - Install Deep/Foundations/Gradebeams/Stemwalls - WBS Summary Foundations Not Started 06/12/26 07/10/26 25.0 25.0
0%
172.5
RPL08.SUB.DHCD.01020 RPL08.SubStructure.DHCD - Install Deep/Foundations/Gradebeams/Stemwalls/UG Utilities - WBS Summary DH D & DH C Not Started 06/12/26 07/29/26 41.2 41.2
0%
156.2
RPL08.SUB.DHCD.01130 RPL08.SubStructure.DHCD - Piers Protection Concrete Capping Foundations Not Started 06/12/26 06/17/26 5.0 5.0
0%
147.5
RPL08.CFCI.4320 RPL08 - Fabricate / Deliver - Lighting (CFCI) Div. 26 - Lighting Not Started 06/15/26 02/03/27 200.0 200.0
0%
227.5
RPL08.SUB.DHAB.01030 RPL08.SubStructure.DHAB - Install Foundations/Anchor Bolts and Gradebeams - Grid lines 6-10/6-23 Foundations Not Started 06/15/26 06/30/26 15.0 15.0
0%
138.8
PRE.FA.1140 Roofing - Final Agreement Trade Partner Final Agreement Not Started 06/16/26 06/16/26 0.0 0.0
0%
105.0
PRE.FA.1200 Glass / Glazing - Final Agreement Trade Partner Final Agreement Not Started 06/16/26 06/16/26 0.0 0.0
0%
337.5
PRE.FA.1260 Kitchen Equipment - Final Agreement Trade Partner Final Agreement Not Started 06/16/26 06/16/26 0.0 0.0
0%
546.2
RPL08.CFCI.4490 RPL08 - (SPW - Div 07) Fabricate / Deliver - Below Grade Waterproofing Waterproofing Not Started 06/16/26 06/29/26 12.5 12.5
0%
132.5
RPL08.CFCI.4760 RPL08 - Fabricate / Deliver - FSC Rough Carpentry (In Wall Backing / Blocking) Rough Carpentry - FSC Wood Not Started 06/16/26 06/29/26 12.5 12.5
0%
325.0
RPL08.CFCI.4920 RPL08 - Fabricate / Deliver - Security System (CFCI) Div. 28 - Security Syst. Not Started 06/16/26 08/11/26 50.0 50.0
0%
413.8
RPL08.CFCI.5180 RPL08 - (SPW-Div 10) Fabricate / Deliver - Finished Carpentry (FRP) FRP [Hallways] Not Started 06/16/26 07/28/26 37.5 37.5
0%
300.0
RPL08.MCUP.LP1.1000 RPL08.MCUP.Loop 1 - Install Foundations, UG Utilities, OFE - WBS Summary mCup Loop 1 Not Started 06/16/26 12/09/26 152.5 152.5
0%
505.0
RPL08.MCUP.LP1.1040 RPL08.MCUP.Loop 1 - Install UG Utilities - WBS Summary Underground Not Started 06/16/26 07/14/26 25.0 25.0
0%
238.8
RPL08.MCUP.LP1.1060 RPL08.MCUP.Loop 1 - Install Mechanical UG Mechanical UG Not Started 06/16/26 06/29/26 12.5 12.5
0%
195.0
RPL08.MCUP.LP1.1080 RPL08.MCUP.Loop 1 - Install Electrical UG Electrical UG Not Started 06/16/26 07/14/26 25.0 25.0
0%
195.0
RPL08.MCUP.LP1.1140 RPL08.MCUP.Loop 1 - Install Controls/EPMS/BMS UG Controls/EPMS/BMS UG Not Started 06/16/26 07/14/26 25.0 25.0
0%
237.5
RPL08.MCUP.LP1.1160 RPL08.MCUP.Loop 1 - Install Grounding Wire, Grounding Rod, Exothermic Weld & Backfill Grounding UG Not Started 06/16/26 06/29/26 12.5 12.5
0%
241.2
RPL08.SUB.DHCD.01060 RPL08.SubStructure.DHCD - Install UG Utilities - Plumbing/Testing/Backfill - Part 1 Underground Not Started 06/16/26 06/25/26 10.0 10.0
0%
158.8
RPL08.SUB.DHCD.01070 RPL08.SubStructure.DHCD - Install UG Utilities - WBS Summary Underground Not Started 06/16/26 07/29/26 38.8 38.8
0%
156.2
RPL08.VDC.1500 T2-4 (SSB) - Prepare & Submit BIM Shops TIER 2 - 4 - SSB Not Started 06/16/26 06/29/26 12.5 12.5
0%
111.2
RPL08.mCUP.1060 RPL08.MCUP.BLDG - Install Foundations, UG Utilities, OFE 1-6 - WBS Summary mCUP Yard Not Started 06/16/26 01/19/27 185.0 185.0
0%
472.5
RPL08.CFCI.3710 RPL08 - Submittals Prep & Submit for Review - Roofing Roofing Not Started 06/17/26 07/15/26 25.0 25.0
0%
105.0
RPL08.CFCI.5680 RPL08 - Submittals Prep & Submit for Review - Glass / Frames Glass & Glazing (Alum. Entrances & Curtainwall) Not Started 06/17/26 07/15/26 25.0 25.0
0%
312.5
RPL08.CFCI.6490 Submittals Prep & Submit for Review - Roof Drain Pipes (CFCI) Div. 33 - Utilities Storm / Sanitary Manholes and Inlets - Area 2 Not Started 06/17/26 07/15/26 25.0 25.0
0%
105.0
RPL.08.D.70040.XR External Tie from RPL07 - Exterior IMP Crew Flow (RPL07.SKN.N.01050) Internal Milestones (XREFs) Not Started 06/18/26 06/18/26 0.0 0.0
0%
178.8
RPL08.SUB.DHAB.01110 RPL08.SubStructure.DHAB - Scan, Install Backfill - Grid lines 6-10/6-23 (1st Layer Backfill) Underground Not Started 06/18/26 06/25/26 7.5 7.5
0%
128.8
RPL08.SUB.SSB.01120 RPL08.SubStructure.SSB - Scan, Install Backfill - Grid lines 6-01/6-10 (1st Layer Backfill) Underground Not Started 06/18/26 06/24/26 6.2 6.2
0%
126.2
PRE.TPA.1300 Architectural/Security Fencing - Award and Issue Subcontract DPR issue Trade Parter Agreements Not Started 06/19/26 06/30/26 10.0 10.0
0%
625.0
PRE.TPA.1320 Non-Critical Trade Buyout - Award and Issue Subcontract DPR issue Trade Parter Agreements Not Started 06/19/26 08/14/26 50.0 50.0
0%
186.2
RPL08.CFCI.3890 RPL08 - Fabricate / Deliver - Plumbing (OH Piping) (Prefab) (CFCI) Div. 22 - Plumbing Not Started 06/19/26 06/25/26 6.2 6.2
0%
441.2
RPL08.CFCI.3910 RPL08 - Fabricate / Deliver - HVAC Insulation (CFCI) Div. 23 - HVAC Insulation Not Started 06/19/26 06/25/26 6.2 6.2
0%
195.0
RPL08.CFCI.5040 RPL08 - Fabricate / Deliver - Joint Sealants Joint Sealants Not Started 06/19/26 07/02/26 12.5 12.5
0%
171.2
RPL08.CFCI.4990 RPL08 - Submittals Review & Approval - Vesda System (CFCI) Div. 28 - VESDA System Not Started 06/22/26 07/06/26 12.5 12.5
0%
257.5
RPL08.SUB.DHCD.01030 RPL08.SubStructure.DHCD - Install Foundations/Anchor Bolts and Gradebeams - Grid lines 6-23/6-28 Foundations Not Started 06/22/26 07/01/26 10.0 10.0
0%
140.0
RPL08.SUB.DHCD.01090 RPL08.SubStructure.DHCD - Install UG Utilities - Electrical/Testing and Pathway Verification and Backfill - Part 1 Underground Not Started 06/22/26 06/29/26 7.5 7.5
0%
156.2
RPL08.VDC.1540 T2-4 (DH A & B) - Prepare & Submit BIM Shops TIER 2 - 4 - DH A & B Not Started 06/23/26 07/07/26 12.5 12.5
0%
161.2
RPL08.STR.SSB.01020 RPL08.Structure.SSB - Install Storm Shelter Steel and Decking Storm Shelter Not Started 06/24/26 06/30/26 6.2 6.2
0%
138.8
RPL08.SUB.SSB.01070 RPL08.SubStructure.SSB - Install Stem Walls - Grid lines 6-01/6-10 Foundations Not Started 06/25/26 07/02/26 7.5 7.5
0%
128.8
RPL08.SUB.SSB.01200 RPL08.SubStructure.SSB - Scan, Install Backfill - Grid lines 6-01/6-10 (2nd Layer Backfill) Underground Not Started 06/25/26 06/30/26 5.0 5.0
0%
126.2
RPL08.SUB.DHAB.01040 RPL08.SubStructure.DHAB - Install Stem Walls - Grid lines 6-10/6-23 Foundations Not Started 06/26/26 07/06/26 7.5 7.5
0%
138.8
RPL08.SUB.DHAB.01190 RPL08.SubStructure.DHAB - Scan, Install Backfill - Grid lines 6-10/6-23 (2nd Layer Backfill) Underground Not Started 06/26/26 07/06/26 7.5 7.5
0%
128.8
RPL08.SUB.SSB.01110 RPL08.SubStructure.SSB - Install UG Utilities - BMS/EPMS/Testing and Pathway Verification and Backfill Underground Not Started 06/26/26 07/10/26 12.5 12.5
0%
126.2
RPL08.SUB.DHCD.01040 RPL08.SubStructure.DHCD - Install Stem walls - Grid lines 6-23/6-28 Foundations Not Started 06/29/26 07/07/26 7.5 7.5
0%
140.0
PRE.FA.1280 Architectural/Security Fencing - Final Agreement Trade Partner Final Agreement Not Started 06/30/26 06/30/26 0.0 0.0
0%
625.0
RPL08.MCUP.LP1.2220 RPL08.MCUP.Loop 1 - Install Mechanical Pipe Hydro Testing Mechanical UG Not Started 06/30/26 07/09/26 8.8 8.8
0%
198.8
RPL08.MCUP.LP2.1000 RPL08.MCUP.Loop 2 - Install Foundations, UG Utilities, OFE - WBS Summary mCup Loop 2 Not Started 06/30/26 01/19/27 172.5 172.5
0%
472.5
RPL08.MCUP.LP2.1060 RPL08.MCUP.Loop 2 - Install UG Utilities - WBS Summary Underground Not Started 06/30/26 08/04/26 31.2 31.2
0%
383.8
RPL08.MCUP.LP2.1080 RPL08.MCUP.Loop 2 - Install Mechanical UG Mechanical UG Not Started 06/30/26 07/09/26 8.8 8.8
0%
245.0
RPL08.SUB.DHCD.01110 RPL08.SubStructure.DHCD - Scan, Install Backfill - Grid lines 6-23/6-28 (1st Layer Backfill) Underground Not Started 06/30/26 07/08/26 7.5 7.5
0%
156.2
RPL08.SUB.SSB.01180 RPL08.SubStructure.SSB - Install UG Utilities - Electrical/Testing and Pathway Verification and Backfill - Part 2 Underground Not Started 06/30/26 07/10/26 10.0 10.0
0%
126.2
RPL08.VDC.1580 T2-4 (SSB) - Review & Approve BIM Shop TIER 2 - 4 - SSB Not Started 06/30/26 08/04/26 31.2 31.2
0%
111.2
RPL08.VDC.1600 T2-4 (EF) - Prepare & Submit BIM Shops TIER 2 - 4 - EF Not Started 06/30/26 07/14/26 12.5 12.5
0%
197.5