Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL08 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:14 PM
· 5122 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
0
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL08.MR.1260 |
RPL08.MR - Mobilization Complete | Make Ready | Not Started | 06/01/26 | 06/01/26 | 0.0 | 0.0 |
|
128.8 |
RPL08.MR.1261 |
RPL08.MR - Site Checklist & Control Handoff | Make Ready | Not Started | 06/01/26 | 06/02/26 | 2.5 | 2.5 |
|
668.8 |
RPL08.SUB.1000 |
RPL08.SubStructure.BLDG - Install Deep/Foundations/Gradebeams/Stemwalls/UG Utilities - WBS Summary | SubStructure | Not Started | 06/01/26 | 07/29/26 | 52.5 | 52.5 |
|
156.2 |
RPL08.SUB.DHAB.01020 |
RPL08.SubStructure.DHAB - Install Deep/Foundations/Gradebeams/Stemwalls/UG Utilities - WBS Summary | DH B & DH A | Not Started | 06/01/26 | 07/20/26 | 43.8 | 43.8 |
|
128.8 |
RPL08.SUB.DHAB.01070 |
RPL08.SubStructure.DHAB - Install UG Utilities - WBS Summary | Underground | Not Started | 06/01/26 | 07/20/26 | 43.8 | 43.8 |
|
128.8 |
RPL08.SUB.DHAB.01090 |
RPL08.SubStructure.DHAB - Install UG Utilities - Electrical/Testing and Pathway Verification and Backfill - Part 1 | Underground | Not Started | 06/01/26 | 06/18/26 | 17.5 | 17.5 |
|
128.8 |
RPL08.SUB.SSB.01000 |
RPL08.SubStructure.SSB - Install Drilled Piers - Grid lines 6-01/6-10 | Foundations | Not Started | 06/01/26 | 06/04/26 | 5.0 | 5.0 |
|
128.8 |
RPL08.SUB.SSB.01010 |
RPL08.SubStructure.SSB - Install Deep/Foundations/Gradebeams/Stemwalls - WBS Summary | Foundations | Not Started | 06/01/26 | 07/08/26 | 33.8 | 33.8 |
|
128.8 |
RPL08.SUB.SSB.01020 |
RPL08.SubStructure.SSB - Install Deep/Foundations/Gradebeams/Stemwalls/UG Utilities - WBS Summary | SSB | Not Started | 06/01/26 | 07/10/26 | 36.2 | 36.2 |
|
126.2 |
RPL08.SUB.SSB.01140 |
RPL08.SubStructure.SSB - Piers Protection Concrete Capping | Foundations | Not Started | 06/01/26 | 06/04/26 | 5.0 | 5.0 |
|
133.8 |
RPL.08.D.82110.XG |
Trestle Construction Ready - SSB-1 - East side | Give Milestones (XREFs) | Not Started | 06/02/26 | 06/02/26 | 0.0 | 0.0 |
|
668.8 |
RPL.08.D.82120.XG |
Trestle Construction Ready - SSB-1 - South side | Give Milestones (XREFs) | Not Started | 06/02/26 | 06/02/26 | 0.0 | 0.0 |
|
668.8 |
RPL.08.D.82130.XG |
Trestle Construction Ready - SSB-1 - North | Give Milestones (XREFs) | Not Started | 06/02/26 | 06/02/26 | 0.0 | 0.0 |
|
668.8 |
RPL08.CFCI.4340 |
RPL08 - Submittals Review & Approval - Below Grade Waterproofing | Waterproofing | Not Started | 06/02/26 | 06/15/26 | 12.5 | 12.5 |
|
132.5 |
RPL08.CFCI.5190 |
RPL08 - Fabricate / Deliver - Vesda System | (CFCI) Div. 28 - VESDA System | Not Started | 06/02/26 | 07/28/26 | 50.0 | 50.0 |
|
257.5 |
RPL08.CFCI.5340 |
RPL08 - Fabricate / Deliver - Strut | (CFCI) Div. 05 - Slotted Channel Framing (Strut) | Not Started | 06/02/26 | 06/29/26 | 25.0 | 25.0 |
|
325.0 |
RPL08.VDC.1440 |
T2-4 (mCUP Yard / Ext.) - Review & Approve BIM Shop | TIER 2 - 4 - mCUP Yard / Exterior | Not Started | 06/02/26 | 07/07/26 | 31.2 | 31.2 |
|
203.8 |
RPL08.VDC.1460 |
T2-4 (EF) - BIM Model & Coordination | TIER 2 - 4 - EF | Not Started | 06/02/26 | 06/29/26 | 25.0 | 25.0 |
|
197.5 |
RPL08.SUB.SSB.01050 |
RPL08.SubStructure.SSB - Install UG Utilities - Plumbing/Testing/Backfill - Part 1 | Underground | Not Started | 06/03/26 | 06/15/26 | 11.2 | 11.2 |
|
131.2 |
RPL08.SUB.SSB.01060 |
RPL08.SubStructure.SSB - Install UG Utilities - WBS Summary | Underground | Not Started | 06/03/26 | 07/10/26 | 33.8 | 33.8 |
|
126.2 |
RPL08.CFCI.6240 |
RPL08 - Fabricate / Deliver - AHUs (EY.SSBC, EY.DHA) | (CFCI) Div. 23 - Air Handler Units (AHUs) | Not Started | 06/04/26 | 09/15/26 | 90.0 | 90.0 |
|
210.0 |
RPL08.CFCI.6920 |
RPL08 - Fabricate / Deliver - AHUs (EYEC) | (CFCI) Div. 23 - Air Handler Units (AHUs) | Not Started | 06/04/26 | 06/23/27 | 330.0 | 330.0 |
|
180.0 |
PRE.TPA.1160 |
Roofing - Award and Issue Subcontract | DPR issue Trade Parter Agreements | Not Started | 06/05/26 | 06/16/26 | 10.0 | 10.0 |
|
105.0 |
PRE.TPA.1240 |
Glass / Metal Panel / Glazing - Award and Issue Subcontract | DPR issue Trade Parter Agreements | Not Started | 06/05/26 | 06/16/26 | 10.0 | 10.0 |
|
312.5 |
PRE.TPA.1280 |
Kitchen Equipment - Award and Issue Subcontract | DPR issue Trade Parter Agreements | Not Started | 06/05/26 | 06/16/26 | 10.0 | 10.0 |
|
546.2 |
RPL08.CFCI.3900 |
RPL08 - Fabricate / Deliver - HVAC Materials and Equipment | (CFCI) Div. 23 - HVAC Materials and Equip. | Not Started | 06/05/26 | 06/11/26 | 6.2 | 6.2 |
|
207.5 |
RPL08.CFCI.4120 |
RPL08 - Fabricate / Deliver - Exterior Louvers | Fixed Louvers | Not Started | 06/05/26 | 08/28/26 | 75.0 | 75.0 |
|
392.5 |
RPL08.CFCI.4190 |
RPL08 - Fabricate / Deliver - Fire Suppression | (CFCI) Div. 21 - Fire Suppression | Not Started | 06/05/26 | 07/02/26 | 25.0 | 25.0 |
|
240.0 |
RPL08.CFCI.5130 |
RPL08 - Fabricate / Deliver - Interior Expansion Joints (Spec 07 95 13.13) XX | Building Expansion Joints (Spec 07 95 13.13) | Not Started | 06/05/26 | 08/14/26 | 62.5 | 62.5 |
|
202.5 |
RPL08.SUB.DHAB.01000 |
RPL08.SubStructure.DHAB - Install Drilled Piers - Grid lines 6-10/6-23 | Foundations | Not Started | 06/05/26 | 06/11/26 | 6.2 | 6.2 |
|
128.8 |
RPL08.SUB.DHAB.01010 |
RPL08.SubStructure.DHAB - Install Deep/Foundations/Gradebeams/Stemwalls - WBS Summary | Foundations | Not Started | 06/05/26 | 07/08/26 | 28.8 | 28.8 |
|
138.8 |
RPL08.SUB.DHAB.01130 |
RPL08.SubStructure.DHAB - Piers Protection Concrete Capping | Foundations | Not Started | 06/05/26 | 06/11/26 | 6.2 | 6.2 |
|
146.2 |
RPL08.SUB.SSB.01030 |
RPL08.SubStructure.SSB - Foundation For Storm Shelter Rebar CMU | Foundations | Not Started | 06/05/26 | 06/11/26 | 6.2 | 6.2 |
|
138.8 |
RPL.08.D.70180.XR |
External Tie from RPL06 - Interior mCup Crew Flow (RPL06.MCUP.LP2.2000) | Internal Milestones (XREFs) | Not Started | 06/08/26 | 06/08/26 | 0.0 | 0.0 |
|
291.2 |
RPL08.CFCI.4700 |
RPL08 - Submittals Review & Approval - Security System | (CFCI) Div. 28 - Security Syst. | Not Started | 06/08/26 | 07/06/26 | 25.0 | 25.0 |
|
413.8 |
PRE.MIR.1260 |
Balance of Trades SA - Meta Review / Authorization | Meta Internal Review of Trade Partner Bids | Not Started | 06/09/26 | 06/18/26 | 10.0 | 10.0 |
|
186.2 |
RPL08.SUB.DHAB.01060 |
RPL08.SubStructure.DHAB - Install UG Utilities - Plumbing/Testing/Backfill - Part 1 | Underground | Not Started | 06/09/26 | 06/18/26 | 10.0 | 10.0 |
|
128.8 |
RPL08.SUB.SSB.01040 |
RPL08.SubStructure.SSB - Install Foundations/Anchor Bolts and Gradebeams - Grid lines 6-01/6-10 | Foundations | Not Started | 06/09/26 | 06/29/26 | 18.8 | 18.8 |
|
126.2 |
RPL08.SUB.SSB.01090 |
RPL08.SubStructure.SSB - Install UG Utilities - Electrical/Testing and Pathway Verification and Backfill - Part 1 | Underground | Not Started | 06/09/26 | 06/19/26 | 11.2 | 11.2 |
|
126.2 |
RPL08.VDC.1480 |
T2-4 (DH C & D) - BIM Model & Coordination | TIER 2 - 4 - DH C & D | Not Started | 06/09/26 | 07/07/26 | 25.0 | 25.0 |
|
247.5 |
RPL08.VDC.1520 |
T1 (SSB to Center EF) - GC QC BIM Model | TIER 1 - SSB to Center of EF | Not Started | 06/09/26 | 06/10/26 | 2.5 | 2.5 |
|
138.8 |
RPL08.VDC.1560 |
T1 (Center EF to End Corridor) - GC QC BIM Model | TIER 1 - Center of EF to End Corridor | Not Started | 06/09/26 | 06/22/26 | 12.5 | 12.5 |
|
152.5 |
RPL08.VDC.1680 |
T1 (SSB to Center EF) - Procure IMP Walls | TIER 1 - SSB to Center of EF | Not Started | 06/11/26 | 08/06/26 | 50.0 | 50.0 |
|
138.8 |
RPL08.STR.1000 |
RPL08.Structure.BLDG - Erect Steel/Joist/Decking, Remaining UG/SOG - WBS Summary | Structure | Not Started | 06/12/26 | 12/19/26 | 163.8 | 163.8 |
|
178.8 |
RPL08.STR.SSB.01000 |
RPL08.Structure.SSB - Install Storm Shelter Rebar, CMU | Storm Shelter | Not Started | 06/12/26 | 06/23/26 | 10.0 | 10.0 |
|
138.8 |
RPL08.STR.SSB.01010 |
RPL08.Structure.SSB - Erect Steel/Joist/Decking, Remaining UG/SOG - WBS Summary | SSB | Not Started | 06/12/26 | 10/28/26 | 121.2 | 121.2 |
|
195.0 |
RPL08.SUB.DHCD.01000 |
RPL08.SubStructure.DHCD - Install Drilled Piers - Grid lines 6-23/6-28 | Foundations | Not Started | 06/12/26 | 06/17/26 | 5.0 | 5.0 |
|
146.2 |
RPL08.SUB.DHCD.01010 |
RPL08.SubStructure.DHCD - Install Deep/Foundations/Gradebeams/Stemwalls - WBS Summary | Foundations | Not Started | 06/12/26 | 07/10/26 | 25.0 | 25.0 |
|
172.5 |
RPL08.SUB.DHCD.01020 |
RPL08.SubStructure.DHCD - Install Deep/Foundations/Gradebeams/Stemwalls/UG Utilities - WBS Summary | DH D & DH C | Not Started | 06/12/26 | 07/29/26 | 41.2 | 41.2 |
|
156.2 |
RPL08.SUB.DHCD.01130 |
RPL08.SubStructure.DHCD - Piers Protection Concrete Capping | Foundations | Not Started | 06/12/26 | 06/17/26 | 5.0 | 5.0 |
|
147.5 |
RPL08.CFCI.4320 |
RPL08 - Fabricate / Deliver - Lighting | (CFCI) Div. 26 - Lighting | Not Started | 06/15/26 | 02/03/27 | 200.0 | 200.0 |
|
227.5 |
RPL08.SUB.DHAB.01030 |
RPL08.SubStructure.DHAB - Install Foundations/Anchor Bolts and Gradebeams - Grid lines 6-10/6-23 | Foundations | Not Started | 06/15/26 | 06/30/26 | 15.0 | 15.0 |
|
138.8 |
PRE.FA.1140 |
Roofing - Final Agreement | Trade Partner Final Agreement | Not Started | 06/16/26 | 06/16/26 | 0.0 | 0.0 |
|
105.0 |
PRE.FA.1200 |
Glass / Glazing - Final Agreement | Trade Partner Final Agreement | Not Started | 06/16/26 | 06/16/26 | 0.0 | 0.0 |
|
337.5 |
PRE.FA.1260 |
Kitchen Equipment - Final Agreement | Trade Partner Final Agreement | Not Started | 06/16/26 | 06/16/26 | 0.0 | 0.0 |
|
546.2 |
RPL08.CFCI.4490 |
RPL08 - (SPW - Div 07) Fabricate / Deliver - Below Grade Waterproofing | Waterproofing | Not Started | 06/16/26 | 06/29/26 | 12.5 | 12.5 |
|
132.5 |
RPL08.CFCI.4760 |
RPL08 - Fabricate / Deliver - FSC Rough Carpentry (In Wall Backing / Blocking) | Rough Carpentry - FSC Wood | Not Started | 06/16/26 | 06/29/26 | 12.5 | 12.5 |
|
325.0 |
RPL08.CFCI.4920 |
RPL08 - Fabricate / Deliver - Security System | (CFCI) Div. 28 - Security Syst. | Not Started | 06/16/26 | 08/11/26 | 50.0 | 50.0 |
|
413.8 |
RPL08.CFCI.5180 |
RPL08 - (SPW-Div 10) Fabricate / Deliver - Finished Carpentry (FRP) | FRP [Hallways] | Not Started | 06/16/26 | 07/28/26 | 37.5 | 37.5 |
|
300.0 |
RPL08.MCUP.LP1.1000 |
RPL08.MCUP.Loop 1 - Install Foundations, UG Utilities, OFE - WBS Summary | mCup Loop 1 | Not Started | 06/16/26 | 12/09/26 | 152.5 | 152.5 |
|
505.0 |
RPL08.MCUP.LP1.1040 |
RPL08.MCUP.Loop 1 - Install UG Utilities - WBS Summary | Underground | Not Started | 06/16/26 | 07/14/26 | 25.0 | 25.0 |
|
238.8 |
RPL08.MCUP.LP1.1060 |
RPL08.MCUP.Loop 1 - Install Mechanical UG | Mechanical UG | Not Started | 06/16/26 | 06/29/26 | 12.5 | 12.5 |
|
195.0 |
RPL08.MCUP.LP1.1080 |
RPL08.MCUP.Loop 1 - Install Electrical UG | Electrical UG | Not Started | 06/16/26 | 07/14/26 | 25.0 | 25.0 |
|
195.0 |
RPL08.MCUP.LP1.1140 |
RPL08.MCUP.Loop 1 - Install Controls/EPMS/BMS UG | Controls/EPMS/BMS UG | Not Started | 06/16/26 | 07/14/26 | 25.0 | 25.0 |
|
237.5 |
RPL08.MCUP.LP1.1160 |
RPL08.MCUP.Loop 1 - Install Grounding Wire, Grounding Rod, Exothermic Weld & Backfill | Grounding UG | Not Started | 06/16/26 | 06/29/26 | 12.5 | 12.5 |
|
241.2 |
RPL08.SUB.DHCD.01060 |
RPL08.SubStructure.DHCD - Install UG Utilities - Plumbing/Testing/Backfill - Part 1 | Underground | Not Started | 06/16/26 | 06/25/26 | 10.0 | 10.0 |
|
158.8 |
RPL08.SUB.DHCD.01070 |
RPL08.SubStructure.DHCD - Install UG Utilities - WBS Summary | Underground | Not Started | 06/16/26 | 07/29/26 | 38.8 | 38.8 |
|
156.2 |
RPL08.VDC.1500 |
T2-4 (SSB) - Prepare & Submit BIM Shops | TIER 2 - 4 - SSB | Not Started | 06/16/26 | 06/29/26 | 12.5 | 12.5 |
|
111.2 |
RPL08.mCUP.1060 |
RPL08.MCUP.BLDG - Install Foundations, UG Utilities, OFE 1-6 - WBS Summary | mCUP Yard | Not Started | 06/16/26 | 01/19/27 | 185.0 | 185.0 |
|
472.5 |
RPL08.CFCI.3710 |
RPL08 - Submittals Prep & Submit for Review - Roofing | Roofing | Not Started | 06/17/26 | 07/15/26 | 25.0 | 25.0 |
|
105.0 |
RPL08.CFCI.5680 |
RPL08 - Submittals Prep & Submit for Review - Glass / Frames | Glass & Glazing (Alum. Entrances & Curtainwall) | Not Started | 06/17/26 | 07/15/26 | 25.0 | 25.0 |
|
312.5 |
RPL08.CFCI.6490 |
Submittals Prep & Submit for Review - Roof Drain Pipes | (CFCI) Div. 33 - Utilities Storm / Sanitary Manholes and Inlets - Area 2 | Not Started | 06/17/26 | 07/15/26 | 25.0 | 25.0 |
|
105.0 |
RPL.08.D.70040.XR |
External Tie from RPL07 - Exterior IMP Crew Flow (RPL07.SKN.N.01050) | Internal Milestones (XREFs) | Not Started | 06/18/26 | 06/18/26 | 0.0 | 0.0 |
|
178.8 |
RPL08.SUB.DHAB.01110 |
RPL08.SubStructure.DHAB - Scan, Install Backfill - Grid lines 6-10/6-23 (1st Layer Backfill) | Underground | Not Started | 06/18/26 | 06/25/26 | 7.5 | 7.5 |
|
128.8 |
RPL08.SUB.SSB.01120 |
RPL08.SubStructure.SSB - Scan, Install Backfill - Grid lines 6-01/6-10 (1st Layer Backfill) | Underground | Not Started | 06/18/26 | 06/24/26 | 6.2 | 6.2 |
|
126.2 |
PRE.TPA.1300 |
Architectural/Security Fencing - Award and Issue Subcontract | DPR issue Trade Parter Agreements | Not Started | 06/19/26 | 06/30/26 | 10.0 | 10.0 |
|
625.0 |
PRE.TPA.1320 |
Non-Critical Trade Buyout - Award and Issue Subcontract | DPR issue Trade Parter Agreements | Not Started | 06/19/26 | 08/14/26 | 50.0 | 50.0 |
|
186.2 |
RPL08.CFCI.3890 |
RPL08 - Fabricate / Deliver - Plumbing (OH Piping) (Prefab) | (CFCI) Div. 22 - Plumbing | Not Started | 06/19/26 | 06/25/26 | 6.2 | 6.2 |
|
441.2 |
RPL08.CFCI.3910 |
RPL08 - Fabricate / Deliver - HVAC Insulation | (CFCI) Div. 23 - HVAC Insulation | Not Started | 06/19/26 | 06/25/26 | 6.2 | 6.2 |
|
195.0 |
RPL08.CFCI.5040 |
RPL08 - Fabricate / Deliver - Joint Sealants | Joint Sealants | Not Started | 06/19/26 | 07/02/26 | 12.5 | 12.5 |
|
171.2 |
RPL08.CFCI.4990 |
RPL08 - Submittals Review & Approval - Vesda System | (CFCI) Div. 28 - VESDA System | Not Started | 06/22/26 | 07/06/26 | 12.5 | 12.5 |
|
257.5 |
RPL08.SUB.DHCD.01030 |
RPL08.SubStructure.DHCD - Install Foundations/Anchor Bolts and Gradebeams - Grid lines 6-23/6-28 | Foundations | Not Started | 06/22/26 | 07/01/26 | 10.0 | 10.0 |
|
140.0 |
RPL08.SUB.DHCD.01090 |
RPL08.SubStructure.DHCD - Install UG Utilities - Electrical/Testing and Pathway Verification and Backfill - Part 1 | Underground | Not Started | 06/22/26 | 06/29/26 | 7.5 | 7.5 |
|
156.2 |
RPL08.VDC.1540 |
T2-4 (DH A & B) - Prepare & Submit BIM Shops | TIER 2 - 4 - DH A & B | Not Started | 06/23/26 | 07/07/26 | 12.5 | 12.5 |
|
161.2 |
RPL08.STR.SSB.01020 |
RPL08.Structure.SSB - Install Storm Shelter Steel and Decking | Storm Shelter | Not Started | 06/24/26 | 06/30/26 | 6.2 | 6.2 |
|
138.8 |
RPL08.SUB.SSB.01070 |
RPL08.SubStructure.SSB - Install Stem Walls - Grid lines 6-01/6-10 | Foundations | Not Started | 06/25/26 | 07/02/26 | 7.5 | 7.5 |
|
128.8 |
RPL08.SUB.SSB.01200 |
RPL08.SubStructure.SSB - Scan, Install Backfill - Grid lines 6-01/6-10 (2nd Layer Backfill) | Underground | Not Started | 06/25/26 | 06/30/26 | 5.0 | 5.0 |
|
126.2 |
RPL08.SUB.DHAB.01040 |
RPL08.SubStructure.DHAB - Install Stem Walls - Grid lines 6-10/6-23 | Foundations | Not Started | 06/26/26 | 07/06/26 | 7.5 | 7.5 |
|
138.8 |
RPL08.SUB.DHAB.01190 |
RPL08.SubStructure.DHAB - Scan, Install Backfill - Grid lines 6-10/6-23 (2nd Layer Backfill) | Underground | Not Started | 06/26/26 | 07/06/26 | 7.5 | 7.5 |
|
128.8 |
RPL08.SUB.SSB.01110 |
RPL08.SubStructure.SSB - Install UG Utilities - BMS/EPMS/Testing and Pathway Verification and Backfill | Underground | Not Started | 06/26/26 | 07/10/26 | 12.5 | 12.5 |
|
126.2 |
RPL08.SUB.DHCD.01040 |
RPL08.SubStructure.DHCD - Install Stem walls - Grid lines 6-23/6-28 | Foundations | Not Started | 06/29/26 | 07/07/26 | 7.5 | 7.5 |
|
140.0 |
PRE.FA.1280 |
Architectural/Security Fencing - Final Agreement | Trade Partner Final Agreement | Not Started | 06/30/26 | 06/30/26 | 0.0 | 0.0 |
|
625.0 |
RPL08.MCUP.LP1.2220 |
RPL08.MCUP.Loop 1 - Install Mechanical Pipe Hydro Testing | Mechanical UG | Not Started | 06/30/26 | 07/09/26 | 8.8 | 8.8 |
|
198.8 |
RPL08.MCUP.LP2.1000 |
RPL08.MCUP.Loop 2 - Install Foundations, UG Utilities, OFE - WBS Summary | mCup Loop 2 | Not Started | 06/30/26 | 01/19/27 | 172.5 | 172.5 |
|
472.5 |
RPL08.MCUP.LP2.1060 |
RPL08.MCUP.Loop 2 - Install UG Utilities - WBS Summary | Underground | Not Started | 06/30/26 | 08/04/26 | 31.2 | 31.2 |
|
383.8 |
RPL08.MCUP.LP2.1080 |
RPL08.MCUP.Loop 2 - Install Mechanical UG | Mechanical UG | Not Started | 06/30/26 | 07/09/26 | 8.8 | 8.8 |
|
245.0 |
RPL08.SUB.DHCD.01110 |
RPL08.SubStructure.DHCD - Scan, Install Backfill - Grid lines 6-23/6-28 (1st Layer Backfill) | Underground | Not Started | 06/30/26 | 07/08/26 | 7.5 | 7.5 |
|
156.2 |
RPL08.SUB.SSB.01180 |
RPL08.SubStructure.SSB - Install UG Utilities - Electrical/Testing and Pathway Verification and Backfill - Part 2 | Underground | Not Started | 06/30/26 | 07/10/26 | 10.0 | 10.0 |
|
126.2 |
RPL08.VDC.1580 |
T2-4 (SSB) - Review & Approve BIM Shop | TIER 2 - 4 - SSB | Not Started | 06/30/26 | 08/04/26 | 31.2 | 31.2 |
|
111.2 |
RPL08.VDC.1600 |
T2-4 (EF) - Prepare & Submit BIM Shops | TIER 2 - 4 - EF | Not Started | 06/30/26 | 07/14/26 | 12.5 | 12.5 |
|
197.5 |