Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL07 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:16 PM · 5237 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
35
Completed
65
In Progress
35
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
PRE.EP.1000 Identify Program Directives, Initiatives, and Expectations - Precon/Estimating Precon- Early Precon Complete 05/20/24 07/08/24 47.5 0.0
100%
0.0
PRE.EP.1020 Precon Kick Off (Target Value, Risk, Schedule) Precon- Early Precon Complete 07/11/24 07/11/24 0.0 0.0
100%
0.0
PRE.EP.1040 Initial PWO Document Creation (GC) Precon- Early Precon Complete 07/29/24 08/16/24 6.2 0.0
100%
0.0
PRE.EP.1060 GC PWO Exhibits Received Precon- Early Precon Complete 07/29/24 07/29/24 0.0 0.0
100%
0.0
PRE.EP.1080 PWO Meta Legal Review Send Draft Precon- Early Precon Complete 08/16/24 10/18/24 5.0 0.0
100%
0.0
PRE.BNS.1000 Baseline 1 Development Precon - Budget & Schedule Complete 09/02/24 10/11/24 35.0 0.0
100%
0.0
PRE.BNS.1020 Develop Baseline 1 Budget & Schedule Precon - Budget & Schedule Complete 09/02/24 10/10/24 35.0 0.0
100%
0.0
PRE.BNS.1040 Baseline 1 Issuance Precon - Budget & Schedule Complete 10/11/24 10/11/24 0.0 0.0
100%
0.0
PRE.BNS.1060 Establish Baseline 1 Precon - Budget & Schedule Complete 10/11/24 10/11/24 0.0 0.0
100%
0.0
PRE.CIDD.1000 Issue Bid Package List with Subcontractors & Meta Approval Precon - Critical Information / Decision Dates Complete 10/11/24 10/11/24 0.0 0.0
100%
0.0
PRE.CIDD.1020 Initial Procurement Plan Approved Precon - Critical Information / Decision Dates Complete 10/11/24 10/11/24 0.0 0.0
100%
0.0
PRE.BNS.1080 Meta Review & Comment - Baseline 1 Precon - Budget & Schedule Complete 10/14/24 11/01/24 18.8 0.0
100%
0.0
DES.PRS.1000 Development of PRS PRS Complete 10/16/24 05/26/25 46.2 0.0
100%
0.0
PRE.EP.1100 Revised PWO Document Submission (GC) Precon- Early Precon Complete 10/21/24 11/04/24 6.2 0.0
100%
0.0
ICM.G.0001.2 RPL07 Commencement Date IMS P0 Milestones Complete 11/01/24 11/01/24 0.0 0.0
100%
0.0
PRE.EP.1120 PWO Meta Legal Review Precon- Early Precon Complete 11/05/24 12/03/24 18.8 0.0
100%
0.0
PRE.EP.1140 PWO Signed Precon- Early Precon Complete 12/04/24 12/04/24 0.0 0.0
100%
0.0
DES.EP.1120 Site BIM Coordination Package [Civil & Struct. Foundation] Early Packages Complete 01/03/25 03/31/25 75.0 0.0
100%
0.0
PRE.BNS.1100 Finalize GC/GRs for BL 2 (DPR to Meta) Precon - Budget & Schedule Complete 01/13/25 07/28/25 0.0 0.0
100%
0.0
PRE.BNS.1120 Site Logistics Create and Approval for BL 2 BL2 Complete 01/13/25 09/19/25 5.0 0.0
100%
0.0
PRE.BNS.1140 Develop Project Review Set - Baseline 2 Estimate & Schedule BL2 Complete 01/13/25 08/28/25 25.0 0.0
100%
0.0
DES.EP.1040 Design Kick Off ( with Product Development Design Package) Early Packages Complete 03/03/25 03/03/25 0.0 0.0
100%
0.0
RPL07.PRED PRED Obsolete Complete 03/03/25 03/03/25 0.0 0.0
100%
0.0
RPL07.SKN.E.01010 RPL07.SKIN.East - Install IMP Insulated Metal Panels System - WBS Summary - **OBSOLETE** Obsolete Complete 03/03/25 01/09/26 1051.2 0.0
100%
0.0
DES.PRS.1020 Project Review Set (PRS) PRS Complete 05/27/25 05/27/25 0.0 0.0
100%
0.0
DES.PRS.1040 PRS Issuance PRS Complete 05/27/25 05/27/25 0.0 0.0
100%
0.0
DES.PRS.1060 PRS Review Cycle PRS Complete 05/27/25 07/18/25 30.0 0.0
100%
0.0
DES.PRS.1080 PRS Page Turn PRS Complete 05/27/25 06/11/25 8.8 0.0
100%
0.0
PRE.BNS.1160 Preliminary Baseline 2 Development (Progress update only DD-6.22.25) BL2 Complete 05/27/25 08/04/25 30.0 0.0
100%
0.0
PRE.BNS.1170 Baseline 2 Development BL2 Complete 05/27/25 08/04/25 30.0 0.0
100%
0.0
RPL.PD.D.PX110.XR PRS Set - RPL-0 - Complete PRS Complete 05/27/25 05/27/25 0.0 0.0
100%
0.0
DES.PRS.1100 IFP Design Lock PRS Complete 07/18/25 07/18/25 0.0 0.0
100%
0.0
RPL07.OFCI.2020 OFE Delivery ROJ: PLC Panels to Integrator - DH Manager/RIO (DHB) - 12 (OFCI) - RPL07 - PLC Panels Active 07/25/25 05/01/26 376.2 18.8
0%
181.2
RPL07.OFCI.2030 OFE Delivery ROJ: PLC Panels to Integrator - DH Manager/RIO (DHA) - 12 (OFCI) - RPL07 - PLC Panels Active 07/25/25 05/01/26 390.0 18.8
0%
193.8
RPL07.OFCI.2240 OFE Delivery ROJ: 3MW Generator (DHD/DHC) - 2 (ROJ10.14.26) (OFCI) - RPL07 - Generators Active 07/25/25 10/14/26 391.2 162.5
0%
190.0
RPL07.OFCI.2260 OFE Delivery ROJ: 3MW Generator (DHA/DHB) - 1 (ROJ10.14.26) (OFCI) - RPL07 - Generators Active 07/25/25 10/14/26 368.8 162.5
0%
56.2
RPL07.OFCI.2300 OFE Delivery ROJ: GSB (DHD/DHC) - 2 (OFCI) - RPL07 - Generator Switchboard GSB Complete 07/25/25 02/12/26 401.2 0.0
100%
0.0
RPL07.OFCI.2320 OFE Delivery ROJ: GSB (DHA/DHB) - 1 (OFCI) - RPL07 - Generator Switchboard GSB Complete 07/25/25 02/12/26 368.8 0.0
100%
0.0
RPL07.OFCI.2830 OFE Delivery ROJ: UPS - Core UPS (DHB) - 12 (OFCI) - RPL07 - UPS Active 07/25/25 09/23/26 376.2 143.8
0%
56.2
RPL07.OFCI.3070 OFE Delivery ROJ: PLC Panels to Integrator - DH Manager/RIO (DHD) - 12 (OFCI) - RPL07 - PLC Panels Active 07/25/25 05/01/26 488.8 18.8
0%
315.0
RPL07.OFCI.3090 OFE Delivery ROJ: PLC Panels to Integrator - DH Manager/RIO (DHC) - 12 (OFCI) - RPL07 - PLC Panels Active 07/25/25 05/01/26 520.0 18.8
0%
323.8
RPL07.OFCI.3110 OFE Delivery ROJ: UPS - Core UPS (DHA) - 12 (OFCI) - RPL07 - UPS Active 07/25/25 10/09/26 390.0 158.8
0%
53.8
RPL07.OFCI.3130 OFE Delivery ROJ: UPS - Core UPS (DHD) - 10 (OFCI) - RPL07 - UPS Active 07/25/25 01/19/27 488.8 241.2
0%
92.5
RPL07.OFCI.3150 OFE Delivery ROJ: UPS - Core UPS (DHC) - 10 (OFCI) - RPL07 - UPS Active 07/25/25 02/08/27 520.0 258.8
0%
83.8
RPL07.OFCI.3190 OFE Delivery ROJ: UPS - Control Power UPS (EC) - **?? (OFCI) - RPL07 - UPS Active 07/25/25 11/16/26 390.0 190.0
0%
181.2
RPL07.OFCI.3210 OFE Delivery ROJ: PLC Panels to Site - Misc I/O (DHB) - 4 (OFCI) - RPL07 - PLC Panels Active 07/25/25 09/23/26 386.2 143.8
0%
56.2
RPL07.OFCI.3230 OFE Delivery ROJ: PLC Panels to Site - Misc I/O (DHA) - 4 (OFCI) - RPL07 - PLC Panels Active 07/25/25 10/09/26 398.8 158.8
0%
53.8
RPL07.OFCI.3250 OFE Delivery ROJ: PLC Panels to Site - Misc I/O (DHD) - 4 (OFCI) - RPL07 - PLC Panels Active 07/25/25 01/19/27 488.8 241.2
0%
92.5
RPL07.OFCI.3270 OFE Delivery ROJ: PLC Panels to Site - Misc I/O (DHC) - 4 (OFCI) - RPL07 - PLC Panels Active 07/25/25 02/08/27 512.5 258.8
0%
83.8
RPL07.OFCI.3290 OFE Delivery ROJ: PLC Panels to Integrator - FCM I/O (DHB) - 1 (OFCI) - RPL07 - PLC Panels Active 07/25/25 05/01/26 351.2 18.8
0%
142.5
RPL07.OFCI.3310 OFE Delivery ROJ: PLC Panels to Integrator - FCM I/O (DHA) - 1 (OFCI) - RPL07 - PLC Panels Active 07/25/25 05/01/26 363.8 18.8
0%
155.0
RPL07.OFCI.3330 OFE Delivery ROJ: PLC Panels to Integrator - FCM I/O (DHD) - 1 (OFCI) - RPL07 - PLC Panels Active 07/25/25 05/01/26 472.5 18.8
0%
260.0
RPL07.OFCI.3350 OFE Delivery ROJ: PLC Panels to Integrator - FCM I/O (DHC) - 1 (OFCI) - RPL07 - PLC Panels Active 07/25/25 05/01/26 485.0 18.8
0%
288.8
RPL07.OFCI.6620 OFE Delivery ROJ: PTX-FWM (CUP) (OFCI) - RPL07 - PTX Complete 07/25/25 09/30/25 237.5 0.0
100%
0.0
RPL07.OFCI.6640 OFE Delivery ROJ: Interior Dry Coolers - mCUP1 (CUP) - 3 pcs (VCD06.16.26) (OFCI) - RPL07 - Dry Coolers Active 07/25/25 05/05/26 237.5 21.2
0%
123.8
RPL07.OFCI.6660 OFE Delivery ROJ: Interior Dry Coolers - mCUP2 (CUP) - 3 pcs (VCD06.23.26) (OFCI) - RPL07 - Dry Coolers Active 07/25/25 05/05/26 237.5 21.2
0%
123.8
RPL07.OFCI.6680 OFE Delivery ROJ: Interior Dry Coolers - mCUP3 (CUP) - 3 pcs (VCD07.01.26) (OFCI) - RPL07 - Dry Coolers Active 07/25/25 05/27/26 256.2 40.0
0%
123.8
RPL07.OFCI.6720 OFE Delivery ROJ: Interior Dry Coolers - mCUP4 (CUP) - 3 pcs (VCD07.02.26) (OFCI) - RPL07 - Dry Coolers Active 07/25/25 05/27/26 256.2 40.0
0%
123.8
RPL07.OFCI.6760 OFE Delivery ROJ: Interior Dry Coolers - mCUP5 (CUP) - 3 pcs (VCD07.09.26) (OFCI) - RPL07 - Dry Coolers Active 07/25/25 06/17/26 275.0 58.8
0%
240.0
RPL07.OFCI.6780 OFE Delivery ROJ: Interior Dry Coolers - mCUP6 (CUP) - 3 pcs (VCD07.10.26) (OFCI) - RPL07 - Dry Coolers Active 07/25/25 06/17/26 275.0 58.8
0%
240.0
RPL07.OFCI.6785 OFE Delivery ROJ: Exterior Dry Coolers - mCUP1 (CUP) - 3 pcs (VCD06.16.26) (OFCI) - RPL07 - Dry Coolers Active 07/25/25 05/05/26 237.5 21.2
0%
123.8
RPL07.OFCI.6790 OFE Delivery ROJ: Exterior Dry Coolers - mCUP2 (CUP) - 3 pcs (VCD06.23.26) (OFCI) - RPL07 - Dry Coolers Active 07/25/25 05/05/26 237.5 21.2
0%
123.8
RPL07.OFCI.6795 OFE Delivery ROJ: Exterior Dry Coolers - mCUP3 (CUP) - 3 pcs (VCD06.30.26) (OFCI) - RPL07 - Dry Coolers Active 07/25/25 05/27/26 256.2 40.0
0%
123.8
RPL07.OFCI.6805 OFE Delivery ROJ: Exterior Dry Coolers - mCUP4 (CUP) - 3 pcs (VCD07.02.26) (OFCI) - RPL07 - Dry Coolers Active 07/25/25 05/27/26 256.2 40.0
0%
123.8
RPL07.OFCI.6815 OFE Delivery ROJ: Exterior Dry Coolers - mCUP5 (CUP) - 3 pcs (VCD07.09.26) (OFCI) - RPL07 - Dry Coolers Active 07/25/25 06/17/26 275.0 58.8
0%
240.0
RPL07.OFCI.6820 OFE Delivery ROJ: Exterior Dry Coolers - mCUP6 (CUP) - 3 pcs (VCD07.10.26) (OFCI) - RPL07 - Dry Coolers Active 07/25/25 06/17/26 275.0 58.8
0%
240.0
RPL07.OFE.1050 OFE Delivery ROJ: MV Skid (DHB) - 12 (ROJ 08.17.26) (RVCD 09.14.26) (MOFE) - RPL07 - RMU Electrical Yard / MV Skids - Outside Active 07/25/25 09/14/26 342.5 135.0
0%
25.0
RPL07.OFE.1060 OFE Delivery ROJ: MV Skid (DHA) - 12 (ROJ 09.04.26) (RVCD 09.21.26) (MOFE) - RPL07 - RMU Electrical Yard / MV Skids - Outside Active 07/25/25 09/21/26 356.2 141.2
0%
37.5
RPL07.OFE.1080 OFE Delivery ROJ: MV Skid (DHD) - 10 (ROJ 09.28.26) (RVCD 10.12.26) (MOFE) - RPL07 - RMU Electrical Yard / MV Skids - Outside Active 07/25/25 10/12/26 365.0 160.0
0%
135.0
RPL07.OFE.1100 OFE Delivery ROJ: MV Skid (DHC) - 10 (ROJ 10.15.26) (RVCD 10.26.26) (MOFE) - RPL07 - RMU Electrical Yard / MV Skids - Outside Active 07/25/25 10/26/26 401.2 172.5
0%
138.8
RPL07.OFE.1110 OFE Delivery ROJ: GS.MDF (DHB) - 1 (VCD07.30.26) (MOFE) - RPL07 - GS.MDF Module (Facnet) Active 07/25/25 07/30/26 313.8 96.2
0%
108.8
RPL07.OFE.1140 OFE Delivery ROJ: GS.IDF Hut - Exterior (CUP) - 3 qty (GS.IDF7X01,02,03) (VCD05.13.26) (MOFE) - RPL07 - GS.IDF (Exterior and Interior) Active 07/25/25 05/13/26 237.5 28.8
0%
138.8
RPL07.OFE.1150 OFE Delivery ROJ: GS.IDF Hut - Exterior (South Yard*) - 1qty (GS.IDF7X04) (VCD07.09.26) (MOFE) - RPL07 - GS.IDF (Exterior and Interior) Active 07/25/25 07/09/26 308.8 77.5
0%
365.0
RPL07.OFE.1200 OFE Delivery ROJ: GS.IDF Room - Interior (GSIDF7B2) - 1 qty (ROJ09.16.26) (MOFE) - RPL07 - GS.IDF (Exterior and Interior) Active 07/25/25 07/30/26 312.5 96.2
0%
150.0
RPL07.OFE.1220 OFE Delivery ROJ: GS.IDF Room - Interior (GSIDF7A2) - 1 qty (ROJ09.16.26) (MOFE) - RPL07 - GS.IDF (Exterior and Interior) Active 07/25/25 07/30/26 378.8 96.2
0%
150.0
RPL07.OFE.1228 OFE Delivery ROJ: FWM (CUP) - 1 (MOFE) - RPL07 - Facility Water Active 07/25/25 05/04/26 238.8 20.0
0%
152.5
RPL07.OFE.1230 OFE Delivery ROJ: GS.IDF Room - Interior (GSIDF7D2) - 1 qty (ROJ10.14.26) (MOFE) - RPL07 - GS.IDF (Exterior and Interior) Active 07/25/25 10/14/26 382.5 162.5
0%
157.5
RPL07.OFE.1240 OFE Delivery ROJ: GS.MDF (DHA) - 1 (VCD07.30.26) (MOFE) - RPL07 - GS.MDF Module (Facnet) Active 07/25/25 07/30/26 320.0 96.2
0%
115.0
RPL07.OFE.1250 OFE Delivery ROJ: GS.IDF Room - Interior (GSIDF7C2) - 1 qty (ROJ10.14.26) (MOFE) - RPL07 - GS.IDF (Exterior and Interior) Active 07/25/25 10/07/26 376.2 156.2
0%
157.5
RPL07.OFE.1400 OFE Delivery ROJ: MES CDU/MTR (DHB) - 12 (MOFE) - RPL07 - MES CDU/MTR Active 07/25/25 08/10/26 336.2 105.0
0%
86.2
RPL07.OFE.1420 OFE Delivery ROJ: MES CDU/MTR (DHA) - 12 (MOFE) - RPL07 - MES CDU/MTR Active 07/25/25 08/28/26 350.0 122.5
0%
68.8
RPL07.OFE.1440 OFE Delivery ROJ: MES CDU/MTR (DHD) - 12 (MOFE) - RPL07 - MES CDU/MTR Active 07/25/25 09/21/26 358.8 141.2
0%
113.8
RPL07.OFE.1460 OFE Delivery ROJ: MES CDU/MTR (DHC) - 12 (MOFE) - RPL07 - MES CDU/MTR Active 07/25/25 10/05/26 395.0 153.8
0%
90.0
RPL07.OFE.2050 OFE Delivery ROJ: mCUP - mCUP1 - 1 (6 Pieces) (ROJ 05.04.26) (RVCD 07.09.26) (MOFE) - RPL07 - mCUP Active 07/25/25 07/09/26 263.8 77.5
0%
77.5
RPL07.OFE.3480 OFE Delivery ROJ: mCUP - mCUP5 - 1 (6 Pieces) (ROJ 06.03.26) (RVCD 08.06.26) (MOFE) - RPL07 - mCUP Active 07/25/25 08/06/26 297.5 102.5
0%
202.5
RPL07.OFE.3490 OFE Delivery ROJ: mCUP - mCUP2 - 1 (6 Pieces) (ROJ 05.12.26) (RVCD 07.16.26) (MOFE) - RPL07 - mCUP Active 07/25/25 07/16/26 270.0 83.8
0%
77.5
RPL07.OFE.3510 OFE Delivery ROJ: mCUP - mCUP3 - 1 (6 Pieces) (ROJ 05.19.26) (RVCD 07.23.26) (MOFE) - RPL07 - mCUP Active 07/25/25 07/23/26 276.2 90.0
0%
77.5
RPL07.OFE.3540 OFE Delivery ROJ: mCUP - mCUP4 - 1 (6 Pieces) (ROJ 05.27.26) (RVCD 07.30.26) (MOFE) - RPL07 - mCUP Active 07/25/25 07/30/26 282.5 96.2
0%
77.5
RPL07.OFE.3560 OFE Delivery ROJ: mCUP - mCUP6 - 1 (6 Pieces) (ROJ 06.10.26) (RVCD 08.13.26) (MOFE) - RPL07 - mCUP Active 07/25/25 08/13/26 303.8 108.8
0%
202.5
RPL07.OFE.5460 OFE Delivery ROJ: FSHAC & Mech Side Aisle (DHB) - 21 (MOFE) - RPL07 - Floor Supported Hot Aisle Containment & Mech. Side Aisle Active 07/25/25 08/13/26 337.5 108.8
0%
46.2
RPL07.OFE.5470 OFE Delivery ROJ: FSHAC & Mech Side Aisle (DHA) - 21 (MOFE) - RPL07 - Floor Supported Hot Aisle Containment & Mech. Side Aisle Active 07/25/25 08/31/26 363.8 123.8
0%
38.8
RPL07.OFE.5480 OFE Delivery ROJ: FSHAC & Mech Side Aisle (DHD) - 17 (MOFE) - RPL07 - Floor Supported Hot Aisle Containment & Mech. Side Aisle Active 07/25/25 12/09/26 472.5 208.8
0%
58.8
RPL07.OFE.5490 OFE Delivery ROJ: FSHAC & Mech Side Aisle (DHC) - 17 (MOFE) - RPL07 - Floor Supported Hot Aisle Containment & Mech. Side Aisle Active 07/25/25 12/28/26 485.0 223.8
0%
72.5
RPL07.OFE.6800 OFE Delivery ROJ: LV Skid (DHB) - 12 (ROJ 08.10.26) (RVCD 09.08.26) (MOFE) - RPL07 - LV Electrical Gallery / LV Skids - Inside NS Active 07/25/25 09/08/26 337.5 130.0
0%
12.5
RPL07.OFE.6820 OFE Delivery ROJ: LV Skid (DHA) - 12 (ROJ 08.28.26) (RVCD 09.14.26) (MOFE) - RPL07 - LV Electrical Gallery / LV Skids - Inside NS Active 07/25/25 09/14/26 350.0 135.0
0%
20.0
RPL07.OFE.6840 OFE Delivery ROJ: LV Skid (DHD) - 10 (ROJ 09.21.26) (RVCD 10.05.26) (MOFE) - RPL07 - LV Electrical Gallery / LV Skids - Inside NS Active 07/25/25 10/05/26 358.8 153.8
0%
77.5
RPL07.OFE.6860 OFE Delivery ROJ: LV Skid (DHC) - 10 (ROJ 10.08.26) (RVCD 10.19.26) (MOFE) - RPL07 - LV Electrical Gallery / LV Skids - Inside NS Active 07/25/25 10/19/26 395.0 166.2
0%
77.5
RPL07.OFE.6920 OFE Delivery ROJ: mCUP Elec Skid - mCUP1 - 1 (ROJ 05.19.26) (RVCD 05.21.26) Follows MCUPS 2 (MOFE) - RPL07 - mCup Electrical Skids - Outside Active 07/25/25 05/21/26 270.0 36.2
0%
140.0
RPL07.OFE.6940 OFE Delivery ROJ: mCUP Elec Skid - mCUP5 - 1 (ROJ 06.16.26) (RVCD 06.11.26) Follows MCUPS 6 (MOFE) - RPL07 - mCup Electrical Skids - Outside Active 07/25/25 06/11/26 303.8 53.8
0%
265.0
RPL07.OFE.6960 OFE Delivery ROJ: mCUP Elec Skid - mCUP2 - 1 (ROJ 05.19.26) (RVCD 05.21.26) Follows MCUPS 2 (MOFE) - RPL07 - mCup Electrical Skids - Outside Active 07/25/25 05/21/26 276.2 36.2
0%
142.5