Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL07 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:16 PM
· 5237 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
14
Completed
14
In Progress
14
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL07.STR.SSB.01210 |
RPL07.Structure.SSB - Install AB Rough Grade & Crane Road Prep - Grid lines 7-01/7-10 | Steel and Decking | Active | 04/02/26 | 04/14/26 | 6.2 | 2.5 |
|
30.0 |
RPL07.SUB.DHAB.01050 |
RPL07.SubStructure.DHAB - Strip Form Work And Apply Water Proofing System - Grid lines 7-10/7-17 (West of GL 17) | Foundations | Active | 04/02/26 | 04/14/26 | 2.5 | 2.5 |
|
48.8 |
RPL07.SUB.DHAB.01230 |
RPL07.SubStructure.DHAB - Scan, Install Backfill - Grid lines 7-17/7-23 (1st Layer Backfill) (East of GL 17) | Underground | Complete | 04/02/26 | 04/07/26 | 2.5 | 0.0 |
|
0.0 |
RPL07.SUB.SSB.01080 |
RPL07.SubStructure.SSB - Strip Form Work And Apply Water Proofing System | Foundations | Complete | 04/02/26 | 04/10/26 | 3.8 | 0.0 |
|
0.0 |
RPL07.SUB.DHCD.01110 |
RPL07.SubStructure.DHCD - Scan, Install Backfill - Grid lines 7-23/7-28 (1st Layer Backfill) | Underground | Complete | 04/03/26 | 04/09/26 | 6.2 | 0.0 |
|
0.0 |
RPL07.SUB.DHCD.01170 |
RPL07.SubStructure.DHCD - Install UG Utilities - Electrical/Testing and Pathway Verification and Backfill - Part 2 | Underground | Complete | 04/03/26 | 04/09/26 | 7.5 | 0.0 |
|
0.0 |
RPL07.CFCI.3580 |
RPL07 - Submittals Review & Approval - Plumbing (OH / In Wall) | (CFCI) Div. 22 - Plumbing | Active | 04/06/26 | 05/01/26 | 25.0 | 18.8 |
|
221.2 |
RPL07.CFCI.4140 |
RPL07 - Fabricate / Deliver - Power Equipment and Material | (CFCI) Div. 26 - Power Equip. & Material | Active | 04/06/26 | 11/19/26 | 200.0 | 193.8 |
|
77.5 |
RPL07.MCUP.LP1.1020 |
RPL07.MCUP.Loop 1 - Install Foundations - WBS Summary | Foundations | Active | 04/06/26 | 06/09/26 | 51.2 | 38.8 |
|
93.8 |
RPL07.MCUP.LP1.1120 |
Logistics Area #XX - Chewy Ct/ Smuggler St (DPR Laydown Area) - **(Update Descripton & Date) | Foundations | Complete | 04/06/26 | 04/06/26 | 0.0 | 0.0 |
|
0.0 |
RPL07.SUB.DHAB.01175 |
RPL07.SubStructure.DHAB - Install UG UT - Electrical/Testing, Pathway Verification & Backfill - Part 2 (East of GL 17) | Underground | Complete | 04/06/26 | 04/07/26 | 2.5 | 0.0 |
|
0.0 |
RPL07.VDC.1660 |
T2-4 (DH C & D) - Prepare & Submit BIM Shops | TIER 2 - 4 - DH C & D | Active | 04/06/26 | 04/17/26 | 12.5 | 6.2 |
|
17.5 |
RPL07.CFCI.6500 |
Submittals Review & Approval - Roof Drain Pipes | (CFCI) Div. 33 - Utilities Storm / Sanitary Manholes and Inlets - Area 2 | Active | 04/07/26 | 05/08/26 | 25.0 | 25.0 |
|
26.2 |
RPL07.MCUP.LP1.1160 |
RPL07.MCUP.Loop 1 - Install Grounding Wire, Grounding Rod, Exothermic Weld & Backfill | Grounding UG | Active | 04/07/26 | 04/20/26 | 12.5 | 7.5 |
|
98.8 |
RPL07.MCUP.LP1.2220 |
RPL07.MCUP.Loop 1 - Mechanical Pipe Hydro Testing | Mechanical UG | Active | 04/07/26 | 04/15/26 | 8.8 | 3.8 |
|
188.8 |
RPL07.MCUP.LP2.1000 |
RPL07.MCUP.Loop 2 - Install Foundations, UG Utilities, OFE - WBS Summary | mCup Loop 2 | Active | 04/07/26 | 10/28/26 | 175.0 | 175.0 |
|
368.8 |
RPL07.MCUP.LP2.1060 |
RPL07.MCUP.Loop 2 - Install UG Utilities - WBS Summary | Underground | Active | 04/07/26 | 05/01/26 | 18.8 | 18.8 |
|
286.2 |
RPL07.MCUP.LP2.1080 |
RPL07.MCUP.Loop 2 - Install Mechanical UG | Mechanical UG | Active | 04/07/26 | 04/15/26 | 8.8 | 3.8 |
|
103.8 |
RPL07.SUB.DHAB.01105 |
RPL07.SubStructure.DHAB - Install UG UT - BMS/EPMS/Testing, Pathway Verification & Backfill (new GS scope East of 17) | Underground | Complete | 04/07/26 | 04/07/26 | 1.2 | 0.0 |
|
0.0 |
RPL07.SUB.DHAB.01155 |
RPL07.SubStructure.DHAB - Install UG UT - Plumbing/Testing/Backfill - Part 2 (East of GL 17) | Underground | Complete | 04/07/26 | 04/08/26 | 2.5 | 0.0 |
|
0.0 |
RPL07.SUB.DHAB.01250 |
RPL07.SubStructure.DHAB - Scan, Install Backfill - Grid lines 7-17/7-23 (2nd Layer Backfill) (East of GL 17) | Underground | Complete | 04/07/26 | 04/08/26 | 2.5 | 0.0 |
|
0.0 |
RPL07.SUB.DHCD.01080 |
RPL07.SubStructure.DHCD - Install Grounding Wire - Grid lines 7-22/7-28 | Foundations | Complete | 04/07/26 | 04/08/26 | 2.5 | 0.0 |
|
0.0 |
PRE.TPA.1180 |
Drywall Metal Studs - Award and Issue Subcontract | DPR issue Trade Parter Agreements | Complete | 04/08/26 | 04/10/26 | 6.2 | 0.0 |
|
0.0 |
RPL07.CFCI.4300 |
RPL07 - Fabricate / Deliver - Roofing | Roofing | Active | 04/08/26 | 06/03/26 | 50.0 | 46.2 |
|
23.8 |
RPL07.SUB.DHCD.01190 |
RPL07.SubStructure.DHCD - Scan, Install Backfill - Grid lines 7-23/7-28 (2nd Layer Backfill) | Underground | Complete | 04/08/26 | 04/11/26 | 7.5 | 0.0 |
|
0.0 |
PRE.FA.1160 |
Drywall Metal Studs - Final Agreement | Trade Partner Final Agreement | Complete | 04/10/26 | 04/10/26 | 0.0 | 0.0 |
|
0.0 |
PRE.FA.1220 |
Waterproofing / Caulking / Expansion Joints - Final Agreement | Trade Partner Final Agreement | Complete | 04/10/26 | 04/10/26 | 0.0 | 0.0 |
|
0.0 |
RPL07.SUB.DHCD.01050 |
RPL07.SubStructure.DHCD - Strip Form Work And Apply Water Proofing System | Foundations | Active | 04/11/26 | 04/15/26 | 3.8 | 3.8 |
|
41.2 |
GCD.RPL07.1010 |
Break Ground | Construction Milestones | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
543.8 |
PRE.TPA.1260 |
Doors / Frames / Hardware - Award and Issue Subcontract | DPR issue Trade Parter Agreements | Not Started | 04/13/26 | 04/17/26 | 6.2 | 6.2 |
|
217.5 |
PRE.TPBD.1080 |
Glass & Metal Panel Bid & Develop SA Package | Trade Partner Bid Development | Not Started | 04/13/26 | 05/27/26 | 40.0 | 40.0 |
|
146.2 |
PRE.TPBD.1240 |
Balance of Trades - Submit for Meta Review | Trade Partner Bid Development | Not Started | 04/13/26 | 06/08/26 | 50.0 | 50.0 |
|
117.5 |
PRE.TPBD.1260 |
Final Finishes & Fixtures Equipment - Submit for Meta Review | Trade Partner Bid Development | Not Started | 04/13/26 | 05/08/26 | 25.0 | 25.0 |
|
390.0 |
RPL.07.D.72110.XG |
Trestle Construction Ready - SSB-1 - East side | Give Milestones (XREFs) | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
543.8 |
RPL.07.D.72120.XG |
Trestle Construction Ready - SSB-1 - South side | Give Milestones (XREFs) | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
543.8 |
RPL.07.D.72130.XG |
Trestle Construction Ready - SSB-1 - North | Give Milestones (XREFs) | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
543.8 |
RPL.07.D.73340. XR |
Laydown Area 13 - RPL07 Ready | Receive Milestones (XREFs) | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
101.2 |
RPL.07.D.74310.XR |
Water Available for Pressure Testing | Receive Milestones (XREFs) | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
235.0 |
RPL.07.D.74410.XR |
Discharge Available for Fill/Flush Cx - Utility connections | Receive Milestones (XREFs) | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
228.8 |
RPL07.CFCI.3360 |
RPL07 - Submittals Prep & Submit for Review - Fire Suppression | (CFCI) Div. 21 - Fire Suppression | Not Started | 04/13/26 | 05/08/26 | 25.0 | 25.0 |
|
63.8 |
RPL07.CFCI.4780 |
RPL07 - Fabricate / Deliver - Gypsum System | (CFCI) Div. 09 - Gypsum System & Ceilings | Not Started | 04/13/26 | 05/08/26 | 25.0 | 25.0 |
|
276.2 |
RPL07.CFCI.5180 |
RPL07 - Fabricate / Deliver - Finished Carpentry (FRP) | FRP [Hallways] | Not Started | 04/13/26 | 05/11/26 | 26.2 | 26.2 |
|
220.0 |
RPL07.CFCI.6800 |
RPL07 - Submittals Prep & Submit for Review - Stick Built IDF ( A1, B1, C1, D1) | (CFCI) Div. XX - Technology IDFs (Stick Built) | Not Started | 04/13/26 | 05/08/26 | 25.0 | 25.0 |
|
67.5 |
RPL07.CON.01000 |
RPL07.Conn BLDG - Install GS and Production Cabling - WBS Summary | Connectivity | Not Started | 04/13/26 | 08/18/27 | 425.0 | 425.0 |
|
118.8 |
RPL07.CON.WP2.01000 |
RPL07.Conn - General Service - WBS Summary | WP#02 GS | Not Started | 04/13/26 | 06/01/27 | 356.2 | 356.2 |
|
187.5 |
RPL07.CON.WP2.08580 |
RPL07.Conn - Construction Cx Server Ready - At GSMDF | WP#02 GS | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
367.5 |
RPL07.CON.WP2.08600 |
RPL07.Conn - Construction Cx Server Ready - At mCup | WP#02 GS | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
543.8 |
RPL07.CON.WP2.08620 |
RPL07.Conn - Construction Cx Server Ready - At DH B (LV) | WP#02 GS | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
543.8 |
RPL07.CON.WP2.08640 |
RPL07.Conn - Construction Cx Server Ready - At DH B EY (MV) | WP#02 GS | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
543.8 |
RPL07.CON.WP2.08680 |
RPL07.Conn - CorpNet & FacNet Live | WP#02 GS | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
543.8 |
RPL07.EY.DHC.01030 |
RPL07.EY.DHC - Install Foundations, UG Utilities, OFE - WBS Summary | EY.DHC | Not Started | 04/13/26 | 06/18/27 | 372.5 | 372.5 |
|
171.2 |
RPL07.EY.DHC.01050 |
RPL07.EY.DHC - Install Electrical UG | Underground | Not Started | 04/13/26 | 04/24/26 | 12.5 | 12.5 |
|
311.2 |
RPL07.EY.DHC.01060 |
RPL07.EY.DHC - Install UG Utilities - WBS Summary | Underground | Not Started | 04/13/26 | 05/06/27 | 335.0 | 335.0 |
|
101.2 |
RPL07.EY.DHD.01030 |
RPL07.EY.DHD - Install Foundations, UG Utilities, OFE - WBS Summary | EY.DHD | Not Started | 04/13/26 | 06/16/27 | 370.0 | 370.0 |
|
173.8 |
RPL07.EY.DHD.01070 |
RPL07.EY.DHD - Install Electrical UG | Underground | Not Started | 04/13/26 | 04/24/26 | 12.5 | 12.5 |
|
295.0 |
RPL07.EY.DHD.01080 |
RPL07.EY.DHD - Install UG Utilities - WBS Summary | Underground | Not Started | 04/13/26 | 05/04/27 | 332.5 | 332.5 |
|
96.2 |
RPL07.EY.SSB.01030 |
RPL07.EY.BLDG - Install Foundations, UG Utilities, OFE- WBS Summary | Electrical Yard | Not Started | 04/13/26 | 08/11/27 | 418.8 | 418.8 |
|
125.0 |
RPL07.MCUP.LP2.1100 |
RPL07.MCUP.Loop 2 - Install Electrical UG | Electrical UG | Not Started | 04/13/26 | 05/01/26 | 18.8 | 18.8 |
|
93.8 |
RPL07.MCUP.LP2.1140 |
RPL07.MCUP.Loop 2 - Install Controls/EPMS/BMS UG | Control/EPMS/BMS UG | Not Started | 04/13/26 | 05/01/26 | 18.8 | 18.8 |
|
153.8 |
RPL07.MILE.1540 |
Overall Duration - FDN to SC DHB & DHA & CCN/S - (LOE) | Overall Durations Summary | Not Started | 04/13/26 | 07/09/27 | 390.0 | 390.0 |
|
12.5 |
RPL07.MILE.1570 |
Overall Duration - FDN to SC DHD & DHC - (LOE) | Overall Durations Summary | Not Started | 04/13/26 | 10/06/27 | 467.5 | 467.5 |
|
38.8 |
RPL07.MR.1000 |
RPL07.MR - Logistics Area 09 and Roads Ready **(Update Description & Date) | Make Ready | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
61.2 |
RPL07.STR.DHAB.01010 |
RPL07.Structure.DHAB - Erect Steel/Joist/Decking - WBS Summary | Steel and Decking | Not Started | 04/13/26 | 06/01/26 | 43.8 | 43.8 |
|
30.0 |
RPL07.STR.DHAB.01020 |
RPL07.Structure.DHAB - Erect Steel/Joist/Decking, Remaining UG/SOG - WBS Summary | DH B & DH A | Not Started | 04/13/26 | 07/31/26 | 97.5 | 97.5 |
|
45.0 |
RPL07.STR.DHAB.01200 |
RPL07.Structure.DHAB - Install AB Rough Grade & Crane Road Prep - Grid Lines 7-11/7-23 | Steel and Decking | Not Started | 04/13/26 | 04/15/26 | 3.8 | 3.8 |
|
32.5 |
RPL07.STR.SSB.01020 |
RPL07.Structure.SSB - Install Storm Shelter Steel and Decking | Storm Shelter | Not Started | 04/13/26 | 04/17/26 | 6.2 | 6.2 |
|
77.5 |
RPL07.VDC.1540 |
T2-4 (DH A & B) - Prepare & Submit BIM Shops | TIER 2 - 4 - DH A & B | Not Started | 04/13/26 | 04/24/26 | 12.5 | 12.5 |
|
50.0 |
RPL07.VDC.1580 |
T2-4 (SSB) - Review & Approve BIM Shop | TIER 2 - 4 - SSB | Not Started | 04/13/26 | 05/15/26 | 31.2 | 31.2 |
|
25.0 |
RPL07.VDC.1600 |
T2-4 (EF) - Prepare & Submit BIM Shops | TIER 2 - 4 - EF | Not Started | 04/13/26 | 04/24/26 | 12.5 | 12.5 |
|
80.0 |
PRE.FA.1180 |
Ceiling - Final Agreement | Trade Partner Final Agreement | Not Started | 04/14/26 | 04/14/26 | 0.0 | 0.0 |
|
82.5 |
RPL07.CFCI.3900 |
RPL07 - Fabricate / Deliver - HVAC Materials and Equipment | (CFCI) Div. 23 - HVAC Materials and Equip. | Not Started | 04/15/26 | 04/21/26 | 6.2 | 6.2 |
|
78.8 |
RPL07.EY.DHC.01120 |
RPL07.EY.DHC - Install BMS UG | Underground | Not Started | 04/15/26 | 04/28/26 | 12.5 | 12.5 |
|
323.8 |
RPL07.EY.DHC.01530 |
RPL07.EY.DHC - Install Grounding UG | Underground | Not Started | 04/15/26 | 04/28/26 | 12.5 | 12.5 |
|
415.0 |
RPL07.EY.DHD.01130 |
RPL07.EY.DHD - Install Grounding UG | Underground | Not Started | 04/15/26 | 04/28/26 | 12.5 | 12.5 |
|
307.5 |
RPL07.MCUP.LP1.1300 |
RPL07.MCUP.Loop 1 - Install UG Generator Conduit Feed | Electrical UG | Not Started | 04/15/26 | 04/20/26 | 5.0 | 5.0 |
|
147.5 |
RPL07.STR.SSB.01230 |
RPL07.Structure.SSB - Steel Shake out - Grid lines 7-01/7-10 | Steel and Decking | Not Started | 04/15/26 | 04/23/26 | 8.8 | 8.8 |
|
30.0 |
RPL07.SUB.DHAB.01290 |
RPL07.SubStructure.DHAB - Strip Form Work And Apply Water Proofing System - Grid lines 7-17/7-23 | Foundations | Not Started | 04/15/26 | 04/16/26 | 2.5 | 2.5 |
|
48.8 |
RPL07.CFCI.3910 |
RPL07 - Fabricate / Deliver - HVAC Insulation | (CFCI) Div. 23 - HVAC Insulation | Not Started | 04/16/26 | 04/22/26 | 6.2 | 6.2 |
|
77.5 |
RPL07.STR.DHCD.01010 |
RPL07.Structure.DHCD - Erect Steel/Joist/Decking - WBS Summary | Steel and Decking | Not Started | 04/16/26 | 06/12/26 | 51.2 | 51.2 |
|
38.8 |
RPL07.STR.DHCD.01020 |
RPL07.Structure.DHCD - Erect Steel/Joist/Decking, Remaining UG/SOG - WBS Summary | DH D & DH C | Not Started | 04/16/26 | 08/26/26 | 116.2 | 116.2 |
|
111.2 |
RPL07.STR.DHCD.01170 |
RPL07.Structure.DHCD - Install AB Rough Grade & Crane Road Prep - Grid Lines 7-23/7-28 | Steel and Decking | Not Started | 04/16/26 | 04/20/26 | 3.8 | 3.8 |
|
63.8 |
PRE.FA.1240 |
Doors / Frames / Hardware - Final Agreement | Trade Partner Final Agreement | Not Started | 04/17/26 | 04/17/26 | 0.0 | 0.0 |
|
217.5 |
RPL07.CFCI.4770 |
RPL07 - Fabricate / Deliver - Doors, Frames and Hardware | Doors, Frames & Hardware (HM and Wood) | Not Started | 04/20/26 | 06/22/26 | 56.2 | 56.2 |
|
217.5 |
RPL07.STR.SSB.01030 |
RPL07.Structure.SSB - Install Storm Shelter F/R/P Deck | Storm Shelter | Not Started | 04/20/26 | 04/24/26 | 6.2 | 6.2 |
|
77.5 |
RPL07.VDC.1720 |
T2-4 (DH C & D) - Review & Approve BIM Shop | TIER 2 - 4 - DH C & D | Not Started | 04/20/26 | 05/22/26 | 31.2 | 31.2 |
|
17.5 |
RPL07.LOG.1340 |
Steel Crane #1 Mobilization | Steel Crane 1 | Not Started | 04/21/26 | 04/21/26 | 0.0 | 0.0 |
|
115.0 |
RPL07.LOG.1360 |
Steel Crane #2 Mobilization | Steel Crane 2 | Not Started | 04/21/26 | 04/21/26 | 0.0 | 0.0 |
|
115.0 |
RPL.07.D.70020.XR |
External Tie from RPL06 - Structural Steel Crew Flow (RPL06.STR.DHCD.01000) | Internal Milestones (XREFs) | Not Started | 04/23/26 | 04/23/26 | 0.0 | 0.0 |
|
30.0 |
GCD.RPL07.1360 |
Steel Erection Start - RPL07 | Construction Milestones | Not Started | 04/24/26 | 04/24/26 | 0.0 | 0.0 |
|
390.0 |
RPL07.STR.DHAB.01220 |
RPL07.Structure.DHAB - Steel Shake out - Grid Lines 7-11/7-23 | Steel and Decking | Not Started | 04/24/26 | 04/30/26 | 6.2 | 6.2 |
|
42.5 |
RPL07.STR.SSB.01040 |
RPL07.Structure.SSB - Install Erect Steel Columns and Beams, Erect Joist - Grid lines 7-01/7-10 | Steel and Decking | Not Started | 04/24/26 | 05/06/26 | 11.2 | 11.2 |
|
30.0 |
RPL07.CFCI.4040 |
RPL07 - Submittals Review & Approval - Lighting | (CFCI) Div. 26 - Lighting | Not Started | 04/27/26 | 05/08/26 | 12.5 | 12.5 |
|
92.5 |
RPL07.EY.DHC.01090 |
RPL07.EY.DHC - Install Mechanical UG | Underground | Not Started | 04/27/26 | 05/08/26 | 12.5 | 12.5 |
|
405.0 |
RPL07.EY.DHC.01100 |
RPL07.EY.DHC - Install SD, DW, FW UG | Underground | Not Started | 04/27/26 | 05/08/26 | 12.5 | 12.5 |
|
311.2 |
RPL07.EY.DHD.01100 |
RPL07.EY.DHD - Install Mechanical UG | Underground | Not Started | 04/27/26 | 05/08/26 | 12.5 | 12.5 |
|
297.5 |
RPL07.EY.DHD.01110 |
RPL07.EY.DHD - Install SD, DW, FW UG | Underground | Not Started | 04/27/26 | 05/08/26 | 12.5 | 12.5 |
|
295.0 |
RPL07.EY.ENDC.01000 |
RPL07.EY.End - Install Electrical UG | Underground | Not Started | 04/27/26 | 05/01/26 | 6.2 | 6.2 |
|
352.5 |
RPL07.EY.ENDC.01010 |
RPL07.EY.End - Install UG Utilities - WBS Summary | Underground | Not Started | 04/27/26 | 05/22/26 | 25.0 | 25.0 |
|
361.2 |
RPL07.EY.ENDC.01020 |
RPL07.EY.End - Install Foundations, UG Utilities, OFE - WBS Summary | EY.EC | Not Started | 04/27/26 | 08/11/27 | 406.2 | 406.2 |
|
125.0 |
RPL07.MCUP.LP1.2200 |
RPL07.MCUP.Loop 1 - Flow Fill & Backfill (Loop 1) | Foundations | Not Started | 04/27/26 | 05/07/26 | 11.2 | 11.2 |
|
93.8 |