Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL07 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:16 PM · 5237 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
14
Completed
14
In Progress
14
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL07.STR.SSB.01210 RPL07.Structure.SSB - Install AB Rough Grade & Crane Road Prep - Grid lines 7-01/7-10 Steel and Decking Active 04/02/26 04/14/26 6.2 2.5
100%
30.0
RPL07.SUB.DHAB.01050 RPL07.SubStructure.DHAB - Strip Form Work And Apply Water Proofing System - Grid lines 7-10/7-17 (West of GL 17) Foundations Active 04/02/26 04/14/26 2.5 2.5
0%
48.8
RPL07.SUB.DHAB.01230 RPL07.SubStructure.DHAB - Scan, Install Backfill - Grid lines 7-17/7-23 (1st Layer Backfill) (East of GL 17) Underground Complete 04/02/26 04/07/26 2.5 0.0
100%
0.0
RPL07.SUB.SSB.01080 RPL07.SubStructure.SSB - Strip Form Work And Apply Water Proofing System Foundations Complete 04/02/26 04/10/26 3.8 0.0
100%
0.0
RPL07.SUB.DHCD.01110 RPL07.SubStructure.DHCD - Scan, Install Backfill - Grid lines 7-23/7-28 (1st Layer Backfill) Underground Complete 04/03/26 04/09/26 6.2 0.0
100%
0.0
RPL07.SUB.DHCD.01170 RPL07.SubStructure.DHCD - Install UG Utilities - Electrical/Testing and Pathway Verification and Backfill - Part 2 Underground Complete 04/03/26 04/09/26 7.5 0.0
100%
0.0
RPL07.CFCI.3580 RPL07 - Submittals Review & Approval - Plumbing (OH / In Wall) (CFCI) Div. 22 - Plumbing Active 04/06/26 05/01/26 25.0 18.8
0%
221.2
RPL07.CFCI.4140 RPL07 - Fabricate / Deliver - Power Equipment and Material (CFCI) Div. 26 - Power Equip. & Material Active 04/06/26 11/19/26 200.0 193.8
0%
77.5
RPL07.MCUP.LP1.1020 RPL07.MCUP.Loop 1 - Install Foundations - WBS Summary Foundations Active 04/06/26 06/09/26 51.2 38.8
0%
93.8
RPL07.MCUP.LP1.1120 Logistics Area #XX - Chewy Ct/ Smuggler St (DPR Laydown Area) - **(Update Descripton & Date) Foundations Complete 04/06/26 04/06/26 0.0 0.0
100%
0.0
RPL07.SUB.DHAB.01175 RPL07.SubStructure.DHAB - Install UG UT - Electrical/Testing, Pathway Verification & Backfill - Part 2 (East of GL 17) Underground Complete 04/06/26 04/07/26 2.5 0.0
100%
0.0
RPL07.VDC.1660 T2-4 (DH C & D) - Prepare & Submit BIM Shops TIER 2 - 4 - DH C & D Active 04/06/26 04/17/26 12.5 6.2
0%
17.5
RPL07.CFCI.6500 Submittals Review & Approval - Roof Drain Pipes (CFCI) Div. 33 - Utilities Storm / Sanitary Manholes and Inlets - Area 2 Active 04/07/26 05/08/26 25.0 25.0
0%
26.2
RPL07.MCUP.LP1.1160 RPL07.MCUP.Loop 1 - Install Grounding Wire, Grounding Rod, Exothermic Weld & Backfill Grounding UG Active 04/07/26 04/20/26 12.5 7.5
0%
98.8
RPL07.MCUP.LP1.2220 RPL07.MCUP.Loop 1 - Mechanical Pipe Hydro Testing Mechanical UG Active 04/07/26 04/15/26 8.8 3.8
0%
188.8
RPL07.MCUP.LP2.1000 RPL07.MCUP.Loop 2 - Install Foundations, UG Utilities, OFE - WBS Summary mCup Loop 2 Active 04/07/26 10/28/26 175.0 175.0
0%
368.8
RPL07.MCUP.LP2.1060 RPL07.MCUP.Loop 2 - Install UG Utilities - WBS Summary Underground Active 04/07/26 05/01/26 18.8 18.8
0%
286.2
RPL07.MCUP.LP2.1080 RPL07.MCUP.Loop 2 - Install Mechanical UG Mechanical UG Active 04/07/26 04/15/26 8.8 3.8
0%
103.8
RPL07.SUB.DHAB.01105 RPL07.SubStructure.DHAB - Install UG UT - BMS/EPMS/Testing, Pathway Verification & Backfill (new GS scope East of 17) Underground Complete 04/07/26 04/07/26 1.2 0.0
100%
0.0
RPL07.SUB.DHAB.01155 RPL07.SubStructure.DHAB - Install UG UT - Plumbing/Testing/Backfill - Part 2 (East of GL 17) Underground Complete 04/07/26 04/08/26 2.5 0.0
100%
0.0
RPL07.SUB.DHAB.01250 RPL07.SubStructure.DHAB - Scan, Install Backfill - Grid lines 7-17/7-23 (2nd Layer Backfill) (East of GL 17) Underground Complete 04/07/26 04/08/26 2.5 0.0
100%
0.0
RPL07.SUB.DHCD.01080 RPL07.SubStructure.DHCD - Install Grounding Wire - Grid lines 7-22/7-28 Foundations Complete 04/07/26 04/08/26 2.5 0.0
100%
0.0
PRE.TPA.1180 Drywall Metal Studs - Award and Issue Subcontract DPR issue Trade Parter Agreements Complete 04/08/26 04/10/26 6.2 0.0
100%
0.0
RPL07.CFCI.4300 RPL07 - Fabricate / Deliver - Roofing Roofing Active 04/08/26 06/03/26 50.0 46.2
0%
23.8
RPL07.SUB.DHCD.01190 RPL07.SubStructure.DHCD - Scan, Install Backfill - Grid lines 7-23/7-28 (2nd Layer Backfill) Underground Complete 04/08/26 04/11/26 7.5 0.0
100%
0.0
PRE.FA.1160 Drywall Metal Studs - Final Agreement Trade Partner Final Agreement Complete 04/10/26 04/10/26 0.0 0.0
100%
0.0
PRE.FA.1220 Waterproofing / Caulking / Expansion Joints - Final Agreement Trade Partner Final Agreement Complete 04/10/26 04/10/26 0.0 0.0
100%
0.0
RPL07.SUB.DHCD.01050 RPL07.SubStructure.DHCD - Strip Form Work And Apply Water Proofing System Foundations Active 04/11/26 04/15/26 3.8 3.8
0%
41.2
GCD.RPL07.1010 Break Ground Construction Milestones Not Started 04/13/26 04/13/26 0.0 0.0
0%
543.8
PRE.TPA.1260 Doors / Frames / Hardware - Award and Issue Subcontract DPR issue Trade Parter Agreements Not Started 04/13/26 04/17/26 6.2 6.2
0%
217.5
PRE.TPBD.1080 Glass & Metal Panel Bid & Develop SA Package Trade Partner Bid Development Not Started 04/13/26 05/27/26 40.0 40.0
0%
146.2
PRE.TPBD.1240 Balance of Trades - Submit for Meta Review Trade Partner Bid Development Not Started 04/13/26 06/08/26 50.0 50.0
0%
117.5
PRE.TPBD.1260 Final Finishes & Fixtures Equipment - Submit for Meta Review Trade Partner Bid Development Not Started 04/13/26 05/08/26 25.0 25.0
0%
390.0
RPL.07.D.72110.XG Trestle Construction Ready - SSB-1 - East side Give Milestones (XREFs) Not Started 04/13/26 04/13/26 0.0 0.0
0%
543.8
RPL.07.D.72120.XG Trestle Construction Ready - SSB-1 - South side Give Milestones (XREFs) Not Started 04/13/26 04/13/26 0.0 0.0
0%
543.8
RPL.07.D.72130.XG Trestle Construction Ready - SSB-1 - North Give Milestones (XREFs) Not Started 04/13/26 04/13/26 0.0 0.0
0%
543.8
RPL.07.D.73340. XR Laydown Area 13 - RPL07 Ready Receive Milestones (XREFs) Not Started 04/13/26 04/13/26 0.0 0.0
0%
101.2
RPL.07.D.74310.XR Water Available for Pressure Testing Receive Milestones (XREFs) Not Started 04/13/26 04/13/26 0.0 0.0
0%
235.0
RPL.07.D.74410.XR Discharge Available for Fill/Flush Cx - Utility connections Receive Milestones (XREFs) Not Started 04/13/26 04/13/26 0.0 0.0
0%
228.8
RPL07.CFCI.3360 RPL07 - Submittals Prep & Submit for Review - Fire Suppression (CFCI) Div. 21 - Fire Suppression Not Started 04/13/26 05/08/26 25.0 25.0
0%
63.8
RPL07.CFCI.4780 RPL07 - Fabricate / Deliver - Gypsum System (CFCI) Div. 09 - Gypsum System & Ceilings Not Started 04/13/26 05/08/26 25.0 25.0
0%
276.2
RPL07.CFCI.5180 RPL07 - Fabricate / Deliver - Finished Carpentry (FRP) FRP [Hallways] Not Started 04/13/26 05/11/26 26.2 26.2
0%
220.0
RPL07.CFCI.6800 RPL07 - Submittals Prep & Submit for Review - Stick Built IDF ( A1, B1, C1, D1) (CFCI) Div. XX - Technology IDFs (Stick Built) Not Started 04/13/26 05/08/26 25.0 25.0
0%
67.5
RPL07.CON.01000 RPL07.Conn BLDG - Install GS and Production Cabling - WBS Summary Connectivity Not Started 04/13/26 08/18/27 425.0 425.0
0%
118.8
RPL07.CON.WP2.01000 RPL07.Conn - General Service - WBS Summary WP#02 GS Not Started 04/13/26 06/01/27 356.2 356.2
0%
187.5
RPL07.CON.WP2.08580 RPL07.Conn - Construction Cx Server Ready - At GSMDF WP#02 GS Not Started 04/13/26 04/13/26 0.0 0.0
0%
367.5
RPL07.CON.WP2.08600 RPL07.Conn - Construction Cx Server Ready - At mCup WP#02 GS Not Started 04/13/26 04/13/26 0.0 0.0
0%
543.8
RPL07.CON.WP2.08620 RPL07.Conn - Construction Cx Server Ready - At DH B (LV) WP#02 GS Not Started 04/13/26 04/13/26 0.0 0.0
0%
543.8
RPL07.CON.WP2.08640 RPL07.Conn - Construction Cx Server Ready - At DH B EY (MV) WP#02 GS Not Started 04/13/26 04/13/26 0.0 0.0
0%
543.8
RPL07.CON.WP2.08680 RPL07.Conn - CorpNet & FacNet Live WP#02 GS Not Started 04/13/26 04/13/26 0.0 0.0
0%
543.8
RPL07.EY.DHC.01030 RPL07.EY.DHC - Install Foundations, UG Utilities, OFE - WBS Summary EY.DHC Not Started 04/13/26 06/18/27 372.5 372.5
0%
171.2
RPL07.EY.DHC.01050 RPL07.EY.DHC - Install Electrical UG Underground Not Started 04/13/26 04/24/26 12.5 12.5
0%
311.2
RPL07.EY.DHC.01060 RPL07.EY.DHC - Install UG Utilities - WBS Summary Underground Not Started 04/13/26 05/06/27 335.0 335.0
0%
101.2
RPL07.EY.DHD.01030 RPL07.EY.DHD - Install Foundations, UG Utilities, OFE - WBS Summary EY.DHD Not Started 04/13/26 06/16/27 370.0 370.0
0%
173.8
RPL07.EY.DHD.01070 RPL07.EY.DHD - Install Electrical UG Underground Not Started 04/13/26 04/24/26 12.5 12.5
0%
295.0
RPL07.EY.DHD.01080 RPL07.EY.DHD - Install UG Utilities - WBS Summary Underground Not Started 04/13/26 05/04/27 332.5 332.5
0%
96.2
RPL07.EY.SSB.01030 RPL07.EY.BLDG - Install Foundations, UG Utilities, OFE- WBS Summary Electrical Yard Not Started 04/13/26 08/11/27 418.8 418.8
0%
125.0
RPL07.MCUP.LP2.1100 RPL07.MCUP.Loop 2 - Install Electrical UG Electrical UG Not Started 04/13/26 05/01/26 18.8 18.8
0%
93.8
RPL07.MCUP.LP2.1140 RPL07.MCUP.Loop 2 - Install Controls/EPMS/BMS UG Control/EPMS/BMS UG Not Started 04/13/26 05/01/26 18.8 18.8
0%
153.8
RPL07.MILE.1540 Overall Duration - FDN to SC DHB & DHA & CCN/S - (LOE) Overall Durations Summary Not Started 04/13/26 07/09/27 390.0 390.0
0%
12.5
RPL07.MILE.1570 Overall Duration - FDN to SC DHD & DHC - (LOE) Overall Durations Summary Not Started 04/13/26 10/06/27 467.5 467.5
0%
38.8
RPL07.MR.1000 RPL07.MR - Logistics Area 09 and Roads Ready **(Update Description & Date) Make Ready Not Started 04/13/26 04/13/26 0.0 0.0
0%
61.2
RPL07.STR.DHAB.01010 RPL07.Structure.DHAB - Erect Steel/Joist/Decking - WBS Summary Steel and Decking Not Started 04/13/26 06/01/26 43.8 43.8
0%
30.0
RPL07.STR.DHAB.01020 RPL07.Structure.DHAB - Erect Steel/Joist/Decking, Remaining UG/SOG - WBS Summary DH B & DH A Not Started 04/13/26 07/31/26 97.5 97.5
0%
45.0
RPL07.STR.DHAB.01200 RPL07.Structure.DHAB - Install AB Rough Grade & Crane Road Prep - Grid Lines 7-11/7-23 Steel and Decking Not Started 04/13/26 04/15/26 3.8 3.8
0%
32.5
RPL07.STR.SSB.01020 RPL07.Structure.SSB - Install Storm Shelter Steel and Decking Storm Shelter Not Started 04/13/26 04/17/26 6.2 6.2
0%
77.5
RPL07.VDC.1540 T2-4 (DH A & B) - Prepare & Submit BIM Shops TIER 2 - 4 - DH A & B Not Started 04/13/26 04/24/26 12.5 12.5
0%
50.0
RPL07.VDC.1580 T2-4 (SSB) - Review & Approve BIM Shop TIER 2 - 4 - SSB Not Started 04/13/26 05/15/26 31.2 31.2
0%
25.0
RPL07.VDC.1600 T2-4 (EF) - Prepare & Submit BIM Shops TIER 2 - 4 - EF Not Started 04/13/26 04/24/26 12.5 12.5
0%
80.0
PRE.FA.1180 Ceiling - Final Agreement Trade Partner Final Agreement Not Started 04/14/26 04/14/26 0.0 0.0
0%
82.5
RPL07.CFCI.3900 RPL07 - Fabricate / Deliver - HVAC Materials and Equipment (CFCI) Div. 23 - HVAC Materials and Equip. Not Started 04/15/26 04/21/26 6.2 6.2
0%
78.8
RPL07.EY.DHC.01120 RPL07.EY.DHC - Install BMS UG Underground Not Started 04/15/26 04/28/26 12.5 12.5
0%
323.8
RPL07.EY.DHC.01530 RPL07.EY.DHC - Install Grounding UG Underground Not Started 04/15/26 04/28/26 12.5 12.5
0%
415.0
RPL07.EY.DHD.01130 RPL07.EY.DHD - Install Grounding UG Underground Not Started 04/15/26 04/28/26 12.5 12.5
0%
307.5
RPL07.MCUP.LP1.1300 RPL07.MCUP.Loop 1 - Install UG Generator Conduit Feed Electrical UG Not Started 04/15/26 04/20/26 5.0 5.0
0%
147.5
RPL07.STR.SSB.01230 RPL07.Structure.SSB - Steel Shake out - Grid lines 7-01/7-10 Steel and Decking Not Started 04/15/26 04/23/26 8.8 8.8
0%
30.0
RPL07.SUB.DHAB.01290 RPL07.SubStructure.DHAB - Strip Form Work And Apply Water Proofing System - Grid lines 7-17/7-23 Foundations Not Started 04/15/26 04/16/26 2.5 2.5
0%
48.8
RPL07.CFCI.3910 RPL07 - Fabricate / Deliver - HVAC Insulation (CFCI) Div. 23 - HVAC Insulation Not Started 04/16/26 04/22/26 6.2 6.2
0%
77.5
RPL07.STR.DHCD.01010 RPL07.Structure.DHCD - Erect Steel/Joist/Decking - WBS Summary Steel and Decking Not Started 04/16/26 06/12/26 51.2 51.2
0%
38.8
RPL07.STR.DHCD.01020 RPL07.Structure.DHCD - Erect Steel/Joist/Decking, Remaining UG/SOG - WBS Summary DH D & DH C Not Started 04/16/26 08/26/26 116.2 116.2
0%
111.2
RPL07.STR.DHCD.01170 RPL07.Structure.DHCD - Install AB Rough Grade & Crane Road Prep - Grid Lines 7-23/7-28 Steel and Decking Not Started 04/16/26 04/20/26 3.8 3.8
0%
63.8
PRE.FA.1240 Doors / Frames / Hardware - Final Agreement Trade Partner Final Agreement Not Started 04/17/26 04/17/26 0.0 0.0
0%
217.5
RPL07.CFCI.4770 RPL07 - Fabricate / Deliver - Doors, Frames and Hardware Doors, Frames & Hardware (HM and Wood) Not Started 04/20/26 06/22/26 56.2 56.2
0%
217.5
RPL07.STR.SSB.01030 RPL07.Structure.SSB - Install Storm Shelter F/R/P Deck Storm Shelter Not Started 04/20/26 04/24/26 6.2 6.2
0%
77.5
RPL07.VDC.1720 T2-4 (DH C & D) - Review & Approve BIM Shop TIER 2 - 4 - DH C & D Not Started 04/20/26 05/22/26 31.2 31.2
0%
17.5
RPL07.LOG.1340 Steel Crane #1 Mobilization Steel Crane 1 Not Started 04/21/26 04/21/26 0.0 0.0
0%
115.0
RPL07.LOG.1360 Steel Crane #2 Mobilization Steel Crane 2 Not Started 04/21/26 04/21/26 0.0 0.0
0%
115.0
RPL.07.D.70020.XR External Tie from RPL06 - Structural Steel Crew Flow (RPL06.STR.DHCD.01000) Internal Milestones (XREFs) Not Started 04/23/26 04/23/26 0.0 0.0
0%
30.0
GCD.RPL07.1360 Steel Erection Start - RPL07 Construction Milestones Not Started 04/24/26 04/24/26 0.0 0.0
0%
390.0
RPL07.STR.DHAB.01220 RPL07.Structure.DHAB - Steel Shake out - Grid Lines 7-11/7-23 Steel and Decking Not Started 04/24/26 04/30/26 6.2 6.2
0%
42.5
RPL07.STR.SSB.01040 RPL07.Structure.SSB - Install Erect Steel Columns and Beams, Erect Joist - Grid lines 7-01/7-10 Steel and Decking Not Started 04/24/26 05/06/26 11.2 11.2
0%
30.0
RPL07.CFCI.4040 RPL07 - Submittals Review & Approval - Lighting (CFCI) Div. 26 - Lighting Not Started 04/27/26 05/08/26 12.5 12.5
0%
92.5
RPL07.EY.DHC.01090 RPL07.EY.DHC - Install Mechanical UG Underground Not Started 04/27/26 05/08/26 12.5 12.5
0%
405.0
RPL07.EY.DHC.01100 RPL07.EY.DHC - Install SD, DW, FW UG Underground Not Started 04/27/26 05/08/26 12.5 12.5
0%
311.2
RPL07.EY.DHD.01100 RPL07.EY.DHD - Install Mechanical UG Underground Not Started 04/27/26 05/08/26 12.5 12.5
0%
297.5
RPL07.EY.DHD.01110 RPL07.EY.DHD - Install SD, DW, FW UG Underground Not Started 04/27/26 05/08/26 12.5 12.5
0%
295.0
RPL07.EY.ENDC.01000 RPL07.EY.End - Install Electrical UG Underground Not Started 04/27/26 05/01/26 6.2 6.2
0%
352.5
RPL07.EY.ENDC.01010 RPL07.EY.End - Install UG Utilities - WBS Summary Underground Not Started 04/27/26 05/22/26 25.0 25.0
0%
361.2
RPL07.EY.ENDC.01020 RPL07.EY.End - Install Foundations, UG Utilities, OFE - WBS Summary EY.EC Not Started 04/27/26 08/11/27 406.2 406.2
0%
125.0
RPL07.MCUP.LP1.2200 RPL07.MCUP.Loop 1 - Flow Fill & Backfill (Loop 1) Foundations Not Started 04/27/26 05/07/26 11.2 11.2
0%
93.8