Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL07 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:16 PM
· 5237 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
0
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL07.MCUP.LP2.1120 |
RPL07.MCUP.Loop 2 - Install Grounding Wire, Grounding Rod, Exothermic Weld & Backfill | Grounding UG | Not Started | 04/27/26 | 05/01/26 | 6.2 | 6.2 |
|
93.8 |
RPL07.VDC.1640 |
T2-4 (DH A & B) - Review & Approve BIM Shop | TIER 2 - 4 - DH A & B | Not Started | 04/27/26 | 06/01/26 | 31.2 | 31.2 |
|
50.0 |
RPL07.VDC.1700 |
T2-4 (EF) - Review & Approve BIM Shop | TIER 2 - 4 - EF | Not Started | 04/27/26 | 06/01/26 | 31.2 | 31.2 |
|
80.0 |
RPL07.MCUP.LP2.1260 |
RPL07.MCUP.Loop 2 - Install UG Generator Conduit Feed | Electrical UG | Not Started | 04/28/26 | 05/01/26 | 5.0 | 5.0 |
|
286.2 |
RPL07.CFCI.6760 |
RPL07 - Submittals Review & Approval - Cable Tray | (CFCI) Div. 26 - Power Equip. & Material | Not Started | 04/29/26 | 05/12/26 | 12.5 | 12.5 |
|
27.5 |
RPL07.EY.ENDC.01340 |
RPL07.EY.End - Install Grounding UG | Underground | Not Started | 04/29/26 | 05/05/26 | 6.2 | 6.2 |
|
371.2 |
RPL07.CFCI.5130 |
RPL07 - Fabricate / Deliver - Interior Expansion Joints (Spec 07 95 13.13) XX | Building Expansion Joints (Spec 07 95 13.13) | Not Started | 05/01/26 | 07/13/26 | 62.5 | 62.5 |
|
56.2 |
RPL07.STR.DHCD.01190 |
RPL07.Structure.DHCD - Steel Shake out, Erect Joist - Grid Lines 7-23/7-28 | Steel and Decking | Not Started | 05/01/26 | 05/07/26 | 6.2 | 6.2 |
|
53.8 |
RPL07.CFCI.3890 |
RPL07 - Fabricate / Deliver - Plumbing (OH Piping) (Prefab) | (CFCI) Div. 22 - Plumbing | Not Started | 05/04/26 | 05/08/26 | 6.2 | 6.2 |
|
221.2 |
RPL07.EY.ENDC.01030 |
RPL07.EY.End - Install Mechanical UG | Underground | Not Started | 05/04/26 | 05/08/26 | 6.2 | 6.2 |
|
352.5 |
ICM.B7.1835 |
[SSDCB2] Delivery of FCA - Fan Coil Assembly (First Delivery) | Construction | Not Started | 05/05/26 | 05/05/26 | 0.0 | 0.0 |
|
123.8 |
ICM.B7.1860 |
[SSDCB2] Delivery of Dry Cooling Towers (First Delivery) | Construction | Not Started | 05/05/26 | 05/05/26 | 0.0 | 0.0 |
|
123.8 |
RPL07.MCUP.LP1.1100 |
RPL07.MCUP.Loop 1 - F/R/P Pads (12'' larger) | Foundations | Not Started | 05/05/26 | 06/02/26 | 25.0 | 25.0 |
|
93.8 |
RPL07.EY.ENDC.01040 |
RPL07.EY.End - Install BMS UG | Underground | Not Started | 05/06/26 | 05/12/26 | 6.2 | 6.2 |
|
371.2 |
RPL07.VDC.1740 |
T2-4 (mCUP Yard / Ext.) - Procurement Equipments | TIER 2 - 4 - mCUP Yard / Exterior | Not Started | 05/06/26 | 05/27/26 | 18.8 | 18.8 |
|
105.0 |
RPL07.STR.DHAB.01000 |
RPL07.Structure.DHAB - Install Erect Steel Columns and Beams, Erect Joist Grid Lines 7-11/7-23 | Steel and Decking | Not Started | 05/07/26 | 05/18/26 | 10.0 | 10.0 |
|
37.5 |
RPL07.STR.SSB.01060 |
RPL07.Structure.SSB - Install Decking & Detailing turnover #1 - Grid lines 7-01/7-04 | Steel and Decking | Not Started | 05/07/26 | 05/12/26 | 5.0 | 5.0 |
|
30.0 |
RPL07.MCUP.LP1.2240 |
RPL07.MCUP.Loop 2 - Flow Fill & Backfill (Loop 2) | Foundations | Not Started | 05/08/26 | 05/20/26 | 11.2 | 11.2 |
|
246.2 |
RPL07.MCUP.LP2.1020 |
RPL07.MCUP.Loop 2 - Install Foundations - WBS Summary | Foundations | Not Started | 05/08/26 | 06/23/26 | 40.0 | 40.0 |
|
235.0 |
PRE.MIR.1280 |
Final Finishes & Fixtures Equipment SA - Meta Review / Authorization | Meta Internal Review of Trade Partner Bids | Not Started | 05/11/26 | 05/22/26 | 12.5 | 12.5 |
|
390.0 |
RPL07.CFCI.3570 |
RPL07 - Submittals Review & Approval - Fire Suppression (AHJ) | (CFCI) Div. 21 - Fire Suppression | Not Started | 05/11/26 | 05/22/26 | 12.5 | 12.5 |
|
63.8 |
RPL07.CFCI.4320 |
RPL07 - Fabricate / Deliver - Lighting | (CFCI) Div. 26 - Lighting | Not Started | 05/11/26 | 12/29/26 | 200.0 | 200.0 |
|
92.5 |
RPL07.CFCI.5190 |
RPL07 - Fabricate / Deliver - Vesda System | (CFCI) Div. 28 - VESDA System | Not Started | 05/11/26 | 07/07/26 | 50.0 | 50.0 |
|
111.2 |
RPL07.CFCI.6510 |
Fabricate / Deliver - Roof Drain Pipes | (CFCI) Div. 33 - Utilities Storm / Sanitary Manholes and Inlets - Area 2 | Not Started | 05/11/26 | 06/01/26 | 18.8 | 18.8 |
|
26.2 |
RPL07.CFCI.6820 |
RPL07 - Submittals Review & Approval - Stick Built IDF ( A1, B1, C1, D1) | (CFCI) Div. XX - Technology IDFs (Stick Built) | Not Started | 05/11/26 | 06/08/26 | 25.0 | 25.0 |
|
67.5 |
RPL07.EY.ENDC.01050 |
RPL07.EY.End - Install SD, DW, FW UG | Underground | Not Started | 05/11/26 | 05/22/26 | 12.5 | 12.5 |
|
355.0 |
RPL.07.D.70040.XR |
External Tie from RPL06 - Exterior IMP Crew Flow (RPL06.SKN.N.01050) | Internal Milestones (XREFs) | Not Started | 05/12/26 | 05/12/26 | 0.0 | 0.0 |
|
33.8 |
RPL07.CFCI.6780 |
RPL07 - Fabricate / Deliver - Cable Tray | (CFCI) Div. 26 - Power Equip. & Material | Not Started | 05/13/26 | 09/03/26 | 100.0 | 100.0 |
|
27.5 |
RPL07.STR.DHAB.01015 |
RPL07.Structure.DHAB - Install Decking & Detailing turnover #2 - Grid lines 7-04/7-07 | Steel and Decking | Not Started | 05/13/26 | 05/15/26 | 3.8 | 3.8 |
|
30.0 |
RPL07.SKIN.01000 |
RPL07.SKIN.BLDG - Install Insulated Metal Panels (IMP), Roof, Windows, Doors, Louvers - WBS Summary | Skin | Not Started | 05/18/26 | 05/17/27 | 312.5 | 312.5 |
|
153.8 |
RPL07.SKN.W.01000 |
RPL07.SKIN - Install Metal Panel Sealant & Starter Flashing - West North South East | IMP System | Not Started | 05/18/26 | 06/01/26 | 12.5 | 12.5 |
|
30.0 |
RPL07.STR.DHAB.01025 |
RPL07.Structure.DHAB - Install Decking & Detailing turnover #3 - Grid lines 7-07/7-10 | Steel and Decking | Not Started | 05/18/26 | 05/20/26 | 3.8 | 3.8 |
|
30.0 |
RPL07.STR.SSB.01100 |
RPL07.Structure.SSB - Adjust MEP Verts and Grounding wire | Prep | Not Started | 05/18/26 | 05/22/26 | 6.2 | 6.2 |
|
41.2 |
RPL07.STR.SSB.01110 |
RPL07.Structure.SSB - Install Remaining UG and Subgrade Prep - WBS Summary | Prep | Not Started | 05/18/26 | 06/05/26 | 17.5 | 17.5 |
|
41.2 |
RPL07.VDC.1760 |
T2-4 (SSB) - GC QC BIM Model | TIER 2 - 4 - SSB | Not Started | 05/18/26 | 06/01/26 | 12.5 | 12.5 |
|
25.0 |
RPL07.STR.DHCD.01000 |
RPL07.Structure.DHCD - Install Erect Steel Columns and Beams, Erect Joist - Grid Lines 7-23/7-28 | Steel and Decking | Not Started | 05/19/26 | 05/28/26 | 8.8 | 8.8 |
|
45.0 |
GCD.RPL07.1380 |
IMP Start - RPL07 | Construction Milestones | Not Started | 05/20/26 | 05/20/26 | 0.0 | 0.0 |
|
367.5 |
RPL07.SKN.W.01005 |
RPL07.SKIN.West - Install IMP - Flashing,Panels & Caulking - Gird lines 7A/7F (with temp closures for openings) | DBC Move 1 - Grid (7-01 / 7-10) | Not Started | 05/20/26 | 05/26/26 | 5.0 | 5.0 |
|
30.0 |
RPL07.SKN.W.01010 |
RPL07.SKIN.West - Install IMP Insulated Metal Panels System - WBS Summary | DBC Move 1 - Grid (7-01 / 7-10) | Not Started | 05/20/26 | 06/03/26 | 12.5 | 12.5 |
|
30.0 |
RPL07.STR.DHAB.01030 |
RPL07.Structure.DHAB - Install Decking & Detailing turnover #4 - Grid lines 7-10/7-14 | Steel and Decking | Not Started | 05/21/26 | 05/27/26 | 5.0 | 5.0 |
|
30.0 |
PRE.TPA.1280 |
Kitchen Equipment - Award and Issue Subcontract | DPR issue Trade Parter Agreements | Not Started | 05/26/26 | 06/01/26 | 6.2 | 6.2 |
|
390.0 |
RPL.07.D.74510.XR |
Storm Drain Available for Roof Drain Tie-ins | Receive Milestones (XREFs) | Not Started | 05/26/26 | 05/26/26 | 0.0 | 0.0 |
|
38.8 |
RPL07.CFCI.4190 |
RPL07 - Fabricate / Deliver - Fire Suppression | (CFCI) Div. 21 - Fire Suppression | Not Started | 05/26/26 | 06/22/26 | 25.0 | 25.0 |
|
63.8 |
RPL07.STR.SSB.01120 |
RPL07.Structure.SSB - Install AB final grade and Vapor Barrier | Prep | Not Started | 05/26/26 | 06/01/26 | 6.2 | 6.2 |
|
41.2 |
RPL07.VDC.1840 |
T2-4 (DH C & D) - GC QC BIM Model | TIER 2 - 4 - DH C & D | Not Started | 05/26/26 | 06/08/26 | 12.5 | 12.5 |
|
17.5 |
RPL07.EY.SSB.01000 |
RPL07.EY.SSB - Install F/R/P Equipment Pads | Foundations | Not Started | 05/27/26 | 06/09/26 | 12.5 | 12.5 |
|
123.8 |
RPL07.EY.SSB.01010 |
RPL07.EY.SSB - Install Foundations - WBS Summary | Foundations | Not Started | 05/27/26 | 06/16/26 | 18.8 | 18.8 |
|
123.8 |
RPL07.EY.SSB.01020 |
RPL07.EY.SSB - Install Foundations, UG Utilities, OFE - WBS Summary | EY.SSB | Not Started | 05/27/26 | 06/03/27 | 320.0 | 320.0 |
|
185.0 |
RPL07.EY.SSB.01100 |
RPL07.EY.SSB - OFE - WBS Summary | OFE | Not Started | 05/27/26 | 07/07/26 | 36.2 | 36.2 |
|
115.0 |
RPL07.EY.SSB.01380 |
RPL07.EY.SSB - Install Wall Mounted AC units (5) - CFCI | OFE | Not Started | 05/27/26 | 06/04/26 | 8.8 | 8.8 |
|
140.0 |
RPL07.EY.SSB.02020 |
RPL07.EY.SSB - Install Temp Conditioning Units - CFCI | Temp Conditions | Not Started | 05/27/26 | 06/02/26 | 6.2 | 6.2 |
|
71.2 |
RPL07.SKN.N.01000 |
RPL07.SKIN.North - Install IMP - Flashing,Panels & Caulking - Grid lines 7-01/7-10 (with temp closures for openings) | DBC Move 1 - Grid (7-01 / 7-10) | Not Started | 05/27/26 | 05/29/26 | 3.8 | 3.8 |
|
30.0 |
RPL07.SKN.SSB.01000 |
RPL07.SKIN.SSB - Install Temp Doors | Glazing, Doors and Ext Devices | Not Started | 05/27/26 | 05/28/26 | 2.5 | 2.5 |
|
322.5 |
RPL07.SKN.SSB.01020 |
RPL07.SKIN.SSB - IMP, Roof, Windows, Doors, Ext Devices - WBS Summary | SSB | Not Started | 05/27/26 | 10/06/26 | 116.2 | 116.2 |
|
221.2 |
RPL07.SKN.SSB.01030 |
RPL07.SKIN.SSB - Install Windows, Doors, Louvers and Ext Devices - WBS Summary | Glazing, Doors and Ext Devices | Not Started | 05/27/26 | 10/06/26 | 116.2 | 116.2 |
|
221.2 |
RPL07.SKN.SSB.01050 |
RPL07.SKIN.SSB - Install Lighting | Glazing, Doors and Ext Devices | Not Started | 05/27/26 | 06/01/26 | 5.0 | 5.0 |
|
312.5 |
RPL07.SKN.SSB.01170 |
RPL07.SKIN.SSB - Install Blocking of Canopy & Backing of Exterior Wall | Glazing, Doors and Ext Devices | Not Started | 05/27/26 | 06/02/26 | 6.2 | 6.2 |
|
106.2 |
PRE.MIR.1200 |
Glass & Metal Panel SA - Meta Review / Authorization | Meta Internal Review of Trade Partner Bids | Not Started | 05/28/26 | 06/10/26 | 12.5 | 12.5 |
|
146.2 |
RPL07.STR.DHAB.01035 |
RPL07.Structure.DHAB - Install Decking & Detailing turnover #5 - Grid lines 7-14/7-18 | Steel and Decking | Not Started | 05/28/26 | 06/01/26 | 3.8 | 3.8 |
|
30.0 |
RPL07.EY.ENDC.01300 |
RPL07.EY.DHD.T1 - Install Shallow Tent UG | Tent 1 | Not Started | 05/29/26 | 06/02/26 | 3.8 | 3.8 |
|
45.0 |
RPL07.LOG.1860 |
Steel Crane #1 Demobilzation | Steel Crane 1 | Not Started | 05/29/26 | 05/29/26 | 0.0 | 0.0 |
|
81.2 |
RPL07.LOG.1880 |
Steel Crane #2 Demobilization | Steel Crane 2 | Not Started | 05/29/26 | 05/29/26 | 0.0 | 0.0 |
|
81.2 |
PRE.FA.1260 |
Kitchen Equipment - Final Agreement | Trade Partner Final Agreement | Not Started | 06/01/26 | 06/01/26 | 0.0 | 0.0 |
|
390.0 |
RPL.GF.D.N6251.XR |
RPL10 FacNet Live - GS - Core (ICM.B10.3355) | Internal Milestones (XREFs) | Not Started | 06/01/26 | 06/01/26 | 0.0 | 0.0 |
|
438.8 |
RPL.GF.D.N7180.XR |
Fiber Pulls, Test & Term within GS EF 1 Complete | Receive Milestones (XREFs) | Not Started | 06/01/26 | 06/01/26 | 0.0 | 0.0 |
|
422.5 |
RPL.GF.D.N7190.XR |
Fiber Pulls, Test & Term within GS EF 2 Complete | Receive Milestones (XREFs) | Not Started | 06/01/26 | 06/01/26 | 0.0 | 0.0 |
|
422.5 |
RPL07.CFCI.4990 |
RPL07 - Submittals Review & Approval - Vesda System | (CFCI) Div. 28 - VESDA System | Not Started | 06/01/26 | 06/12/26 | 12.5 | 12.5 |
|
111.2 |
RPL07.CON.WP2.09320 |
RPL06.- CorpNet & FacNet Ready - GS - Core | WP#02 GS | Not Started | 06/01/26 | 06/01/26 | 0.0 | 0.0 |
|
438.8 |
RPL07.SKN.S.01000 |
RPL07.SKIN.South - Install IMP - Flashing,Panels & Caulking - Grid lines 7-01/7-10 (with temp closures for openings) | DBC Move 1 - Grid (7-01 / 7-10) | Not Started | 06/01/26 | 06/03/26 | 3.8 | 3.8 |
|
30.0 |
RPL07.SKN.SSB.01070 |
RPL07.SKIN.SSB - Install Security | Glazing, Doors and Ext Devices | Not Started | 06/02/26 | 06/03/26 | 2.5 | 2.5 |
|
312.5 |
RPL07.SKN.W.01040 |
RPL07.SKIN.West - Secure All Exterior Mounted Boxes and Devices on Skin | IMP System | Not Started | 06/02/26 | 06/15/26 | 12.5 | 12.5 |
|
32.5 |
RPL07.STR.DHCD.01015 |
RPL07.Structure.DHCD - Install Decking & Detailing turnover #6 - Grid lines 7-18/7-21 | Steel and Decking | Not Started | 06/02/26 | 06/04/26 | 3.8 | 3.8 |
|
30.0 |
RPL07.STR.SSB.01130 |
RPL07.Structure.SSB - Asphalt Emulsion and Wrap Steel Columns | Prep | Not Started | 06/02/26 | 06/05/26 | 5.0 | 5.0 |
|
41.2 |
RPL07.VDC.1780 |
T2-4 (DH A & B) - GC QC BIM Model | TIER 2 - 4 - DH A & B | Not Started | 06/02/26 | 06/15/26 | 12.5 | 12.5 |
|
50.0 |
RPL07.VDC.1800 |
T2-4 (EF) - GC QC BIM Model | TIER 2 - 4 - EF | Not Started | 06/02/26 | 06/15/26 | 12.5 | 12.5 |
|
80.0 |
RPL07.VDC.1820 |
T2-4 (SSB) - Create Spool Sheet for Fab | TIER 2 - 4 - SSB | Not Started | 06/02/26 | 06/22/26 | 18.8 | 18.8 |
|
25.0 |
RPL07.EY.ENDC.1310 |
RPL07.EY.DHD.T1 - Install Final Grading | Tent 1 | Not Started | 06/03/26 | 06/04/26 | 2.5 | 2.5 |
|
45.0 |
RPL07.EY.SSB.02040 |
RPL07.EY.SSB - Install Temp Duct to Permanent Duct | Temp Conditions | Not Started | 06/03/26 | 06/09/26 | 6.2 | 6.2 |
|
71.2 |
RPL07.MCUP.LP1.1180 |
RPL07.MCUP.Loop 1 - Cure for Pads | Foundations | Not Started | 06/03/26 | 06/09/26 | 8.8 | 8.8 |
|
133.8 |
RPL07.MCUP.LP1.1200 |
RPL07.MCUP.Loop 1 - OFE - WBS Summary | OFE | Not Started | 06/03/26 | 08/10/26 | 60.0 | 60.0 |
|
87.5 |
RPL07.MCUP.LP1.2120 |
RPL07.MCUP.Loop 1 - Set Facility Water Pipe Rack (mCUP1) | OFE | Not Started | 06/03/26 | 06/16/26 | 12.5 | 12.5 |
|
105.0 |
RPL07.MCUP.LP2.1160 |
RPL07.MCUP.Loop 2 - F/R/P Pads (12'' larger) | Foundations | Not Started | 06/03/26 | 06/16/26 | 12.5 | 12.5 |
|
236.2 |
RPL07.SKN.SSB.01075 |
RPL07.SKIN.SSB - QC Blocking | Glazing, Doors and Ext Devices | Not Started | 06/03/26 | 06/04/26 | 2.5 | 2.5 |
|
308.8 |
RPL07.SKN.N.01010 |
RPL07.SKIN.North - Install IMP Insulated Metal Panels System - WBS Summary | DBC Move 2 - Grid (7-11 / 7-23) | Not Started | 06/04/26 | 06/19/26 | 15.0 | 15.0 |
|
421.2 |
RPL07.SKN.S.01030 |
RPL07.SKIN.South - Install IMP - Flashing,Panels & Caulking - Grid lines 7-11/7-23 (with temp closures for openings) | DBC Move 2 - Grid (7-11 / 7-23) | Not Started | 06/04/26 | 06/05/26 | 2.5 | 2.5 |
|
30.0 |
RPL07.SKN.SSB.01080 |
RPL07.SKIN.SSB - Install Roof System - Exterior Wall Sheathing and EJ | Roofing | Not Started | 06/04/26 | 06/10/26 | 6.2 | 6.2 |
|
23.8 |
RPL07.SKN.SSB.01090 |
RPL07.SKIN.SSB - Install Roof System - WBS Summary | Roofing | Not Started | 06/04/26 | 07/20/26 | 40.0 | 40.0 |
|
56.2 |
RPL.07.D.70060.XR |
External Tie from RPL06 - Roofing DenseDeck & Flame Down Crew Flow (RPL06.SKN.DHCD.01090) | Internal Milestones (XREFs) | Not Started | 06/05/26 | 06/05/26 | 0.0 | 0.0 |
|
27.5 |
RPL07.EY.ENDC.1330 |
RPL07.EY.DHD.T1 - Install F/R/P Tent 1 Slab | Tent 1 | Not Started | 06/05/26 | 06/11/26 | 6.2 | 6.2 |
|
45.0 |
RPL07.LOG.1120 |
Dry Cooler 230 Ton Crane Mobilization | 100 Ton Crane | Not Started | 06/05/26 | 06/09/26 | 3.8 | 3.8 |
|
93.8 |
RPL07.STR.DHCD.01025 |
RPL07.Structure.DHCD - Install Decking & Detailing turnover #7 - Grid lines 7-21/7-25 | Steel and Decking | Not Started | 06/05/26 | 06/09/26 | 3.8 | 3.8 |
|
38.8 |
GCD.RPL07.1500 |
Start Slab-On-Grade Concrete - RPL07 | Construction Milestones | Not Started | 06/08/26 | 06/08/26 | 0.0 | 0.0 |
|
352.5 |
RPL07.EY.DHA.01010 |
RPL07.EY.DHA - Install F/R/P Equipment Pads - 1-12 (Grid 6-01/6-16) (12'' Larger For Tolerance) | Foundations | Not Started | 06/08/26 | 07/06/26 | 25.0 | 25.0 |
|
98.8 |
RPL07.EY.DHA.01020 |
RPL07.EY.DHA - Install Foundations - WBS Summary | Foundations | Not Started | 06/08/26 | 07/13/26 | 31.2 | 31.2 |
|
98.8 |
RPL07.EY.DHA.01030 |
RPL07.EY.DHA - Install Foundations, UG Utilities, OFE- WBS Summary | EY.DHA | Not Started | 06/08/26 | 01/22/27 | 196.2 | 196.2 |
|
298.8 |
RPL07.SKN.S.01010 |
RPL07.SKIN.South - Install IMP Insulated Metal Panels System - WBS Summary | DBC Move 3 - Grid (7-23 / 7-28) | Not Started | 06/08/26 | 07/02/26 | 23.8 | 23.8 |
|
410.0 |
RPL07.SKN.S.01040 |
RPL07.SKIN.South - Install IMP EJ - Grid lines 7-10/7-11 | DBC Move 2 - Grid (7-11 / 7-23) | Not Started | 06/08/26 | 06/12/26 | 6.2 | 6.2 |
|
30.0 |
RPL07.SKN.S.01080 |
RPL07.SKIN.South - Install IMP - Flashing,Panels & Caulking - Grid lines 7-11/7-23 (with temp closures for openings) | DBC Move 2 - Grid (7-11 / 7-23) | Not Started | 06/08/26 | 06/09/26 | 2.5 | 2.5 |
|
30.0 |
RPL07.SKN.S.01140 |
RPL07.SKIN.South - Install Stair Tower (DH A) | DBC Move 3 - Grid (7-23 / 7-28) | Not Started | 06/08/26 | 06/09/26 | 2.5 | 2.5 |
|
162.5 |
RPL07.STR.SSB.01140 |
RPL07.Structure.SSB - SOG F/R/P #1 - Grid lines 7-01/7-04 | F/R/P | Not Started | 06/08/26 | 06/12/26 | 6.2 | 6.2 |
|
41.2 |