Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL07 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:16 PM · 5237 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
0
Completed
0
In Progress
0
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL07.STR.SSB.01150 RPL07.Structure.SSB - SOG F/R/P - WBS Summary F/R/P Not Started 06/08/26 06/28/26 18.8 18.8
0%
137.5
PRE.MIR.1260 Balance of Trades SA - Meta Review / Authorization Meta Internal Review of Trade Partner Bids Not Started 06/09/26 06/22/26 12.5 12.5
0%
117.5
RPL07.CFCI.3180 RPL07 - Coordinate Scope and Submittal Req's - Security System (Prod Dat) (CFCI) Div. 28 - Security Syst. Not Started 06/09/26 06/09/26 1.2 1.2
0%
197.5
RPL07.CFCI.3830 RPL07 - Submittals Prep & Submit for Review - Building Controls (CFCI) Div. 23 - Building Controls Not Started 06/09/26 07/07/26 25.0 25.0
0%
17.5
RPL07.CFCI.6840 RPL07 - Fabricate / Deliver - Stick Built IDF (B1) (CFCI) Div. XX - Technology IDFs (Stick Built) Not Started 06/09/26 11/12/26 137.5 137.5
0%
70.0
RPL07.CFCI.6860 RPL07 - Fabricate / Deliver - Stick Built IDF (A1) (CFCI) Div. XX - Technology IDFs (Stick Built) Not Started 06/09/26 12/02/26 152.5 152.5
0%
67.5
RPL07.CFCI.6880 RPL07 - Fabricate / Deliver - Stick Built IDF (D1) (CFCI) Div. XX - Technology IDFs (Stick Built) Not Started 06/09/26 02/23/27 221.2 221.2
0%
108.8
RPL07.CFCI.6900 RPL07 - Fabricate / Deliver - Stick Built IDF (C1) (CFCI) Div. XX - Technology IDFs (Stick Built) Not Started 06/09/26 03/16/27 240.0 240.0
0%
98.8
RPL07.CFCI.4690 RPL07 - Submittals Prep & Submit for Review - Security System (Prod Dat) (CFCI) Div. 28 - Security Syst. Not Started 06/10/26 09/01/26 73.8 73.8
0%
197.5
RPL07.EY.SSB.01050 RPL07.EY.SSB - Install Cure (High Early Mix) Foundations Not Started 06/10/26 06/16/26 8.8 8.8
0%
176.2
RPL07.EY.SSB.01180 RPL07.EY.SSB - Tie-ins - WBS Summary Tie-ins Not Started 06/10/26 09/29/26 97.5 97.5
0%
63.8
RPL07.EY.SSB.01400 RPL07.EY.SSB - Install Duct/ insulation into the building Main (include penetration detail) Tie-ins Not Started 06/10/26 06/30/26 18.8 18.8
0%
98.8
RPL07.MCUP.FWM.01000 RPL07.MCUP.FWM - Install PTX FWM Not Started 06/10/26 06/12/26 3.8 3.8
0%
121.2
RPL07.MCUP.FWM.01010 RPL07.MCUP.FWM - Install FWM FWM Not Started 06/10/26 06/12/26 3.8 3.8
0%
121.2
RPL07.MCUP.FWM.01030 RPL07.MCUP.FWM - Install MVS FWM Not Started 06/10/26 06/12/26 3.8 3.8
0%
121.2
RPL07.MCUP.LP1.1220 RPL07.MCUP.Loop 1 - Set mCup #1 & #2 - Dry Coolers (12) (4 per week) OFE Not Started 06/10/26 06/30/26 18.8 18.8
0%
93.8
RPL07.MCUP.LP1.1240 RPL07.MCUP.Loop 1 - Set GS.IDF Hut (1x GS.IDF) 7X01 (ROJ05.13.26) OFE Not Started 06/10/26 06/16/26 6.2 6.2
0%
116.2
RPL07.SKN.N.01030 RPL07.SKIN.North - Install IMP - Flashing,Panels & Caulking - Grid lines 7-11/7-23 (with temp closures for openings) DBC Move 2 - Grid (7-11 / 7-23) Not Started 06/10/26 06/11/26 2.5 2.5
0%
30.0
RPL07.STR.DHAB.01060 RPL07.Structure.DHAB - Adjust MEP Verts and Grounding wire Prep Not Started 06/10/26 06/16/26 6.2 6.2
0%
47.5
RPL07.STR.DHAB.01070 RPL07.Structure.DHAB - Install Remaining UG and Subgrade Prep - WBS Summary Prep Not Started 06/10/26 06/26/26 16.2 16.2
0%
47.5
RPL07.STR.DHCD.01035 RPL07.Structure.DHCD - Install Decking & Detailing turnover #8 - Grid lines 7-25/7-28 Steel and Decking Not Started 06/10/26 06/12/26 3.8 3.8
0%
38.8
PRE.TPA.1240 Glass / Metal Panel / Glazing - Award and Issue Subcontract DPR issue Trade Parter Agreements Not Started 06/11/26 06/17/26 6.2 6.2
0%
146.2
RPL07.SKN.SSB.01100 RPL07.SKIN.SSB - Install Roof System - Install Temp Flashing at EJ Roofing Not Started 06/11/26 06/12/26 2.5 2.5
0%
62.5
RPL07.SKN.SSB.01110 RPL07.SKIN.SSB - Install Roof System - DenseDeck & Flame Down Roofing Not Started 06/11/26 06/19/26 8.8 8.8
0%
23.8
GCD.RPL07.1320 Steel Complete - RPL07 Construction Milestones Not Started 06/12/26 06/12/26 0.0 0.0
0%
67.5
RPL07.EY.DHA.01060 RPL07.EY.DHA - Install Electrical UG Underground Not Started 06/12/26 06/25/26 12.5 12.5
0%
115.0
RPL07.EY.DHA.01070 RPL07.EY.DHA - Install UG Utilities - WBS Summary Underground Not Started 06/12/26 07/24/26 37.5 37.5
0%
115.0
RPL07.EY.ENDC.1350 RPL07.EY.DHD.T1 - Install Tent 1 Saw Cut and Cure Tent 1 Not Started 06/12/26 06/18/26 8.8 8.8
0%
66.2
RPL07.EY.SSB.01040 RPL07.EY.SSB - Install Electrical UG Underground Not Started 06/12/26 06/18/26 6.2 6.2
0%
90.0
RPL07.EY.SSB.01060 RPL07.EY.SSB - Install UG Utilities - WBS Summary Underground Not Started 06/12/26 07/02/26 18.8 18.8
0%
108.8
RPL07.SKN.DHAB.01000 RPL07.SKIN.DHAB - Install Temp Doors Glazing, Doors and Ext Devices Not Started 06/12/26 06/15/26 2.5 2.5
0%
53.8
RPL07.SKN.DHAB.01010 RPL07.SKIN.DHAB - IMP, Roof, Windows, Doors, Ext Devices - WBS Summary DH B & DH A Not Started 06/12/26 07/31/26 43.8 43.8
0%
285.0
RPL07.SKN.DHAB.01020 RPL07.SKIN.DHAB - Install Windows, Doors, Louvers and Ext Devices - WBS Summary Glazing, Doors and Ext Devices Not Started 06/12/26 07/17/26 31.2 31.2
0%
297.5
RPL07.SKN.DHAB.01070 RPL07.SKIN.DHAB - Install Roof System - Exterior Wall Sheething and EJ Roofing Not Started 06/12/26 06/15/26 2.5 2.5
0%
30.0
RPL07.SKN.DHAB.01080 RPL07.SKIN.DHAB - Install Roof System - WBS Summary Roofing Not Started 06/12/26 07/31/26 43.8 43.8
0%
133.8
RPL07.SKN.N.01040 RPL07.SKIN.North - Install IMP EJ - Grid lines 7-10/7-11 DBC Move 2 - Grid (7-11 / 7-23) Not Started 06/12/26 06/18/26 6.2 6.2
0%
38.8
RPL07.SKN.N.01080 RPL07.SKIN.North - Install IMP - Flashing,Panels & Caulking - Grid lines 7-11/7-23 (with temp closures for openings) DBC Move 2 - Grid (7-11 / 7-23) Not Started 06/12/26 06/15/26 2.5 2.5
0%
36.2
RPL07.SKN.N.01120 RPL07.SKIN.North - Install Stair Tower (DH B) DBC Move 2 - Grid (7-11 / 7-23) Not Started 06/12/26 06/15/26 2.5 2.5
0%
157.5
RPL07.STR.SSB.01190 RPL07.Structure.SSB - Zone SOG Cure F/R/P Not Started 06/13/26 06/19/26 8.8 8.8
0%
72.5
RPL07.EY.ENDC.01360 RPL07.EY.DHD.T2 - Install Shallow Tent UG Tent 2 Not Started 06/15/26 06/17/26 3.8 3.8
0%
38.8
RPL07.STR.DHAB.01110 RPL07.Structure.DHAB - SOG F/R/P - Grid Lines 7-11/7-23 - WBS Summary F/R/P Not Started 06/15/26 07/31/26 42.5 42.5
0%
45.0
RPL07.STR.DHAB.01160 RPL07.Structure.DHAB - SOG F/R/P #2 - Grid lines 7-04/7-07 F/R/P Not Started 06/15/26 06/19/26 6.2 6.2
0%
41.2
RPL07.STR.DHCD.01060 RPL07.Structure.DHCD - Adjust MEP Verts and Grounding wire Prep Not Started 06/15/26 06/19/26 6.2 6.2
0%
51.2
RPL07.STR.DHCD.01070 RPL07.Structure.DHCD - Install Remaining UG and Subgrade Prep - WBS Summary Prep Not Started 06/15/26 07/01/26 16.2 16.2
0%
51.2
RPL.GF.D.N7140.XG GS.IDF Hut 1 Install Complete for RPL 7 Give Milestones (XREFs) Not Started 06/16/26 06/16/26 0.0 0.0
0%
486.2
RPL07.EY.DHA.01560 RPL07.EY.DHA - Install Grounding UG Underground Not Started 06/16/26 06/29/26 12.5 12.5
0%
125.0
RPL07.EY.DHC.01010 RPL07.EY.DHC - Install F/R/P Equipment Pads - 1-10 (Grid 6-17/6-28) (12'' Larger For Tolerance) Foundations Not Started 06/16/26 07/07/26 18.8 18.8
0%
230.0
RPL07.EY.DHC.01020 RPL07.EY.DHC - Install Foundations - WBS Summary Foundations Not Started 06/16/26 05/20/27 291.2 291.2
0%
101.2
RPL07.EY.SSB.01420 RPL07.EY.SSB - Install Grounding UG Underground Not Started 06/16/26 06/22/26 6.2 6.2
0%
112.5
RPL07.SKN.DHAB.01090 RPL07.SKIN.DHAB - Install Roof System - Install Temp Flashing at EJ Roofing Not Started 06/16/26 06/17/26 2.5 2.5
0%
70.0
RPL07.SKN.DHAB.01160 RPL07.SKIN.DHAB - Install Blocking of Canopy & Backing of Exterior Wall Glazing, Doors and Ext Devices Not Started 06/16/26 06/22/26 6.2 6.2
0%
53.8
RPL07.SKN.N.01050 RPL07.SKIN.North - Install IMP - Flashing,Panels & Caulking - Grid lines 7-23/7-28 (with temp closures for openings) DBC Move 3 - Grid (7-23 / 7-28) Not Started 06/16/26 06/17/26 2.5 2.5
0%
36.2
RPL07.SKN.N.01100 RPL07.SKIN.North - Secure All Exterior Mounted Boxes and Devices on Skin IMP System Not Started 06/16/26 07/14/26 25.0 25.0
0%
332.5
PRE.FA.1200 Glass / Glazing - Final Agreement Trade Partner Final Agreement Not Started 06/17/26 06/17/26 0.0 0.0
0%
171.2
RPL07.CON.WP2.07000 RPL07.Conn - Ext. GSIDFs - WBS Summary GS.IDF (Exterior) Not Started 06/17/26 12/18/26 160.0 160.0
0%
326.2
RPL07.CON.WP2.07200 RPL07.Conn - Ext. GSIDF7X01 (mCUP yard) - WBS Summary Ext. IDF Hut - GSIDF7X01 Not Started 06/17/26 12/10/26 152.5 152.5
0%
333.8
RPL07.CON.WP2.07220 RPL07.Conn - Ext. GSIDF7X01 - Install Infrastructure (Racks, Waterfalls etc.) Infrastructure Not Started 06/17/26 06/23/26 6.2 6.2
0%
301.2
RPL07.MCUP.LP1.2140 RPL07.MCUP.Loop 1 - Set Facility Water Pipe Rack (mCUP2) OFE Not Started 06/17/26 06/26/26 10.0 10.0
0%
105.0
RPL07.MCUP.LP2.1180 RPL07.MCUP.Loop 2 - Cure for Pads Foundations Not Started 06/17/26 06/23/26 8.8 8.8
0%
347.5
RPL07.STR.DHAB.01080 RPL07.Structure.DHAB - Install AB final grade and Vapor Barrier Prep Not Started 06/17/26 06/23/26 6.2 6.2
0%
47.5
RPL07.CFCI.5680 RPL07 - Submittals - Glass / Frames Glass & Glazing (Alum. Entrances & Curtainwall) Not Started 06/18/26 07/16/26 25.0 25.0
0%
146.2
RPL07.EY.ENDC.1610 RPL07.EY.DHD.T2 - Install Final Grading Tent 2 Not Started 06/18/26 06/19/26 2.5 2.5
0%
38.8
RPL07.SKN.E.01000 RPL07.SKIN.East - Install IMP - Flashing,Panels & Caulking - Gird lines 7A/7F (with temp closures for openings) DBC Move 3 - Grid (7-23 / 7-28) Not Started 06/18/26 06/23/26 5.0 5.0
0%
36.2
RPL07.SKN.N.01060 RPL07.SKIN.North - Install IMP EJ - Grid lines 7-22/7-23 DBC Move 3 - Grid (7-23 / 7-28) Not Started 06/18/26 06/24/26 6.2 6.2
0%
43.8
RPL07.SKN.N.01140 RPL07.SKIN.North - Install Stair Tower (DH D) DBC Move 2 - Grid (7-11 / 7-23) Not Started 06/18/26 06/19/26 2.5 2.5
0%
421.2
RPL07.EY.DHB.01030 RPL07.EY.DHB - Install Foundations, UG Utilities, OFE - WBS Summary EY.DHB Not Started 06/19/26 01/07/27 172.5 172.5
0%
311.2
RPL07.EY.DHB.01060 RPL07.EY.DHB - Install Electrical UG Underground Not Started 06/19/26 07/02/26 12.5 12.5
0%
90.0
RPL07.EY.DHB.01070 RPL07.EY.DHB - Install UG Utilities - WBS Summary Underground Not Started 06/19/26 07/31/26 37.5 37.5
0%
90.0
RPL07.EY.SSB.01070 RPL07.EY.SSB - Install Mechanical UG Underground Not Started 06/19/26 06/25/26 6.2 6.2
0%
102.5
RPL07.EY.SSB.01130 RPL07.EY.SSB - Install SD, DW, FW UG Underground Not Started 06/19/26 07/02/26 12.5 12.5
0%
102.5
RPL07.STR.SSB.01250 RPL07.Structure.SSB - Moisture requirements for floor Sealer F/R/P Not Started 06/20/26 06/26/26 8.8 8.8
0%
201.2
RPL07.EY.ENDC.1630 RPL07.EY.DHD.T2 - Install F/R/P Tent 2 Slab Tent 2 Not Started 06/22/26 06/26/26 6.2 6.2
0%
38.8
RPL07.INT.1000 RPL07.Interior.BLDG - Install Priority OH, Walls, OFE and Fitout - WBS Summary Interior Build-out Not Started 06/22/26 07/30/27 347.5 347.5
0%
86.2
RPL07.INT.SSB.01000 RPL07.Interior.SSB - Priority - WBS Summary Priority Walls and OverHead Not Started 06/22/26 08/10/26 43.8 43.8
0%
268.8
RPL07.INT.SSB.01005 RPL07.Interior - Priority - Install Hangers Support (SSB to Center Corr) (All Trades) Early Priority OH MEPF Not Started 06/22/26 07/06/26 12.5 12.5
0%
23.8
RPL07.INT.SSB.01020 RPL07.Interior.SSB - Install Priority OH, Walls and Fitout - WBS Summary SSB Not Started 06/22/26 04/08/27 248.8 248.8
0%
158.8
RPL07.INT.SSB.03180 RPL07.Interior.SSB - Priority - Install Priority Soffit for Wall Tie-Ins/ Rock & HoW & Draft Blanket Priority Walls and OverHead Not Started 06/22/26 07/06/26 12.5 12.5
0%
90.0
RPL07.INT.SSBC.01020 RPL07.Interior.SSB-Corridor - Install Priority OH, Walls, OFE and Fitout - WBS Summary SSB Corridor Not Started 06/22/26 02/24/27 211.2 211.2
0%
115.0
RPL07.INT.SSBC.03420 RPL07.Interior.SSBC - Priority GL7.04 - (P0) Apply Intumescent Paint to Deck Priority Wall Grid Line 7-04 Not Started 06/22/26 07/13/26 18.8 18.8
0%
45.0
RPL07.SKN.DHAB.01100 RPL07.SKIN.DHAB - Install Roof System - DenseDeck & Flame Down Roofing Not Started 06/22/26 06/30/26 8.8 8.8
0%
25.0
RPL07.SKN.SSB.01130 RPL07.SKIN.SSB - Install Roof System - Final Roof Roofing Not Started 06/22/26 07/13/26 18.8 18.8
0%
56.2
RPL07.STR.DHAB.01170 RPL07.Structure.DHAB - SOG F/R/P #3 - Grid lines 7-07/7-11 F/R/P Not Started 06/22/26 06/26/26 6.2 6.2
0%
41.2
RPL07.STR.DHCD.01080 RPL07.Structure.DHCD - Install AB final grade and Vapor Barrier Prep Not Started 06/22/26 06/26/26 6.2 6.2
0%
51.2
PRE.TPA.1300 Architectural/Security Fencing - Award and Issue Subcontract DPR issue Trade Parter Agreements Not Started 06/23/26 07/09/26 15.0 15.0
0%
447.5
PRE.TPA.1320 Non-Critical Trade Buyout - Award and Issue Subcontract DPR issue Trade Parter Agreements Not Started 06/23/26 08/18/26 50.0 50.0
0%
117.5
RPL07.EY.DHB.01540 RPL07.EY.DHB - Install Grounding UG Underground Not Started 06/23/26 07/07/26 12.5 12.5
0%
100.0
RPL07.EY.SSB.01080 RPL07.EY.SSB - Install BMS UG Underground Not Started 06/23/26 06/29/26 6.2 6.2
0%
112.5
RPL07.SKN.DHAB.01030 RPL07.SKIN.DHAB - Install Awning over Doors Glazing, Doors and Ext Devices Not Started 06/23/26 06/29/26 6.2 6.2
0%
53.8
RPL07.VDC.1860 T2-4 (SSB) - Procurement Materials TIER 2 - 4 - SSB Not Started 06/23/26 07/14/26 18.8 18.8
0%
25.0
RPL07.CON.WP2.07260 RPL07.Conn - Ext. GSIDF7X01 - Install Copper, WAPs, Security Camera & Access Control Cabling Not Started 06/24/26 07/10/26 15.0 15.0
0%
301.2
RPL07.EY.ENDC.02100 RPL07.EY.End - Install Temp Conditioning Units - CFCI Temp Conditions Not Started 06/24/26 06/30/26 6.2 6.2
0%
297.5
RPL07.EY.ENDC.1370 RPL07.EY.DHD.T1 - Install Tent Tent 1 Not Started 06/24/26 07/22/26 25.0 25.0
0%
41.2
RPL07.INT.SSB.01010 RPL07.Interior.SSB - Priority - Install Duct (Highside OH space) Early Priority OH MEPF Not Started 06/24/26 07/01/26 7.5 7.5
0%
23.8
RPL07.INT.SSB.01030 RPL07.Interior.SSB - Priority - Install Fire Sprinkler (Highside OH space) Early Priority OH MEPF Not Started 06/24/26 06/30/26 6.2 6.2
0%
62.5
RPL07.INT.SSB.06780 RPL07.Interior.SSB - Priority - Install Duct (Highside OH space) **Swing Shift** Early Priority OH MEPF Not Started 06/24/26 07/01/26 7.5 7.5
0%
23.8
RPL07.SKN.S.01050 RPL07.SKIN.South - Install IMP - Flashing,Panels & Caulking - Grid lines 7-23/7-28 (with temp closures for openings) DBC Move 3 - Grid (7-23 / 7-28) Not Started 06/24/26 06/25/26 2.5 2.5
0%
36.2
RPL07.STR.DHAB.01090 RPL07.Structure.DHAB - Asphalt Emulsion and Wrap Steel Columns Prep Not Started 06/24/26 06/26/26 3.8 3.8
0%
47.5
RPL07.INT.SSB.02680 RPL07.Interior.SSB - Priority - Install Layout, Unistruts & Hangers (All Trades) Priority Walls and OverHead Not Started 06/25/26 07/09/26 12.5 12.5
0%
90.0
RPL07.INT.SSBC.01000 RPL07.Interior.SSBC - Priority - WBS Summary Priority Walls & Overhead Not Started 06/25/26 08/11/26 41.2 41.2
0%
98.8
RPL07.INT.SSBC.03240 RPL07.Interior.SSBC - Priority - Install Priority Soffit for Wall Tie-Ins/ Rock & HoW & Draft Blanket Priority Walls & Overhead Not Started 06/25/26 07/01/26 6.2 6.2
0%
45.0