Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL07 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:16 PM
· 5237 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
0
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL07.EY.DHA.01100 |
RPL07.EY.DHA - Install Mechanical UG | Underground | Not Started | 06/26/26 | 07/10/26 | 12.5 | 12.5 |
|
115.0 |
RPL07.EY.DHA.01110 |
RPL07.EY.DHA - Install SD, DW, FW UG | Underground | Not Started | 06/26/26 | 07/10/26 | 12.5 | 12.5 |
|
125.0 |
RPL07.EY.SSB.01110 |
RPL07.EY.SSB - Install LD Electrical UG | Loading Dock | Not Started | 06/26/26 | 07/01/26 | 5.0 | 5.0 |
|
206.2 |
RPL07.EY.SSB.01120 |
RPL07.EY.SSB - Install AHU (3) - CFCI | OFE | Not Started | 06/26/26 | 07/07/26 | 8.8 | 8.8 |
|
115.0 |
RPL07.EY.SSB.01140 |
RPL07.EY.SSB - Install Loading Dock, UG Utilities, OFE - WBS Summary | Loading Dock | Not Started | 06/26/26 | 08/19/26 | 47.5 | 47.5 |
|
206.2 |
RPL07.SKN.S.01070 |
RPL07.SKIN.South - Install IMP EJ - Grid lines 7-22/7-23 | DBC Move 3 - Grid (7-23 / 7-28) | Not Started | 06/26/26 | 07/02/26 | 6.2 | 6.2 |
|
36.2 |
RPL07.SKN.S.01100 |
RPL07.SKIN.South - Secure All Exterior Mounted Boxes and Devices on Skin | IMP System | Not Started | 06/26/26 | 07/24/26 | 25.0 | 25.0 |
|
322.5 |
RPL07.SKN.S.01120 |
RPL07.SKIN.South - Install Stair Tower (DH C) | DBC Move 3 - Grid (7-23 / 7-28) | Not Started | 06/26/26 | 06/29/26 | 2.5 | 2.5 |
|
413.8 |
RPL07.EY.ENDC.1650 |
RPL07.EY.DHD.T2 - Install Tent 2 Saw Cut and Cure | Tent 2 | Not Started | 06/27/26 | 07/03/26 | 8.8 | 8.8 |
|
57.5 |
RPL07.STR.SSB.01270 |
RPL07.Structure.SSB - Install SOG Sealer and Cure | F/R/P | Not Started | 06/27/26 | 06/28/26 | 2.5 | 2.5 |
|
201.2 |
RPL07.INT.SSB.06640 |
RPL07.Interior.SSB - Priority - Install IMP Exterior Inwall Rough-In | Priority Walls and OverHead | Not Started | 06/29/26 | 07/06/26 | 6.2 | 6.2 |
|
90.0 |
RPL07.MCUP.LP1.2160 |
RPL07.MCUP.Loop 1 - Set Facility Water Pipe Rack (mCUP3) | OFE | Not Started | 06/29/26 | 07/09/26 | 10.0 | 10.0 |
|
105.0 |
RPL07.STR.DHCD.01090 |
RPL07.Structure.DHCD - Asphalt Emulsion and Wrap Steel Columns | Prep | Not Started | 06/29/26 | 07/01/26 | 3.8 | 3.8 |
|
51.2 |
RPL07.LOG.1140 |
Dry Cooler 230 Ton Crane Movement 01 | 100 Ton Crane | Not Started | 06/30/26 | 06/30/26 | 0.0 | 0.0 |
|
93.8 |
RPL07.SKN.DHAB.01040 |
RPL07.SKIN.DHAB - Install Louvers | Glazing, Doors and Ext Devices | Not Started | 06/30/26 | 07/07/26 | 6.2 | 6.2 |
|
53.8 |
RPL07.EY.ENDC.02080 |
RPL07.EY.End - Install Temp Duct to Permanent Duct | Temp Conditions | Not Started | 07/01/26 | 07/08/26 | 6.2 | 6.2 |
|
297.5 |
RPL07.INT.DHB.02160 |
RPL07.Interior.DHB - Priority - Install Fixed Draft Smoke Curtains (#5) | Early Priority OH MEPF | Not Started | 07/01/26 | 07/14/26 | 11.2 | 11.2 |
|
61.2 |
RPL07.INT.SSBC.01030 |
RPL07.Interior.SSB-Corridor - Priority - Install Fire Sprinkler (Highside OH space) | Early Priority OH MEPF | Not Started | 07/01/26 | 07/01/26 | 1.2 | 1.2 |
|
62.5 |
RPL07.MCUP.LP1.1280 |
RPL07.MCUP.Loop 1 - Set MTRs (4 per day) | OFE | Not Started | 07/01/26 | 07/08/26 | 6.2 | 6.2 |
|
93.8 |
RPL07.MCUP.LP1.1320 |
RPL07.MCUP.Loop 1 - Set mCup #3 & #4 - Dry Coolers (12) (4 per week) | OFE | Not Started | 07/01/26 | 07/22/26 | 18.8 | 18.8 |
|
93.8 |
RPL07.SKN.DHAB.01110 |
RPL07.SKIN.DHAB - Install Scupper and Downspouts | Glazing, Doors and Ext Devices | Not Started | 07/01/26 | 07/08/26 | 6.2 | 6.2 |
|
306.2 |
RPL07.STR.DHAB.01180 |
RPL07.Structure.DHAB - SOG F/R/P #4 - Grid lines 7-11/7-14 | F/R/P | Not Started | 07/01/26 | 07/08/26 | 6.2 | 6.2 |
|
38.8 |
RPL07.EY.SSB.01150 |
RPL07.EY.SSB - Install LD Mechanical UG | Loading Dock | Not Started | 07/02/26 | 07/16/26 | 12.5 | 12.5 |
|
206.2 |
RPL07.INT.DHB.01030 |
RPL07.Interior.DHB - Priority - Install Fire Sprinkler | Early Priority OH MEPF | Not Started | 07/02/26 | 07/09/26 | 6.2 | 6.2 |
|
62.5 |
RPL07.INT.SSB.06560 |
RPL07.Interior.SSB - Priority - Install Backing at Exterior Wall | Priority Walls and OverHead | Not Started | 07/02/26 | 07/09/26 | 6.2 | 6.2 |
|
90.0 |
RPL07.INT.SSBC.01011 |
RPL07.Interior.SSB-Corridor - Priority - Install Duct (Highside OH space) | Early Priority OH MEPF | Not Started | 07/02/26 | 07/15/26 | 11.2 | 11.2 |
|
23.8 |
RPL07.INT.SSBC.02400 |
RPL07.Interior.SSBC - Priority - Install Layout, Unistruts & Hangers (All Trades) Both side of Corridor Wall | Priority Walls & Overhead | Not Started | 07/02/26 | 07/08/26 | 5.0 | 5.0 |
|
95.0 |
RPL07.INT.SSBC.03520 |
RPL07.Interior.SSBC - Priority - Install IMP Exterior Inwall Rough-In | Priority Walls & Overhead | Not Started | 07/02/26 | 07/07/26 | 3.8 | 3.8 |
|
95.0 |
RPL.07.D.70080.XR |
External Tie from RPL06 - EY MV Concrete Foundations Crew Flow (RPL06.EY.DHC.01010) | Internal Milestones (XREFs) | Not Started | 07/06/26 | 07/06/26 | 0.0 | 0.0 |
|
55.0 |
RPL07.EY.DHB.01090 |
RPL07.EY.DHB - Install Mechanical UG | Underground | Not Started | 07/06/26 | 07/17/26 | 12.5 | 12.5 |
|
90.0 |
RPL07.EY.DHB.01100 |
RPL07.EY.DHB - Install SD, DW, FW UG | Underground | Not Started | 07/06/26 | 07/17/26 | 12.5 | 12.5 |
|
100.0 |
RPL07.EY.ENDC.1670 |
RPL07.EY.DHD.T2 - Install Tent | Tent 2 | Not Started | 07/06/26 | 07/31/26 | 25.0 | 25.0 |
|
40.0 |
RPL07.LOG.1000 |
MCUP 500 Ton Crane Mobilization | 300 Ton Crane | Not Started | 07/06/26 | 07/09/26 | 5.0 | 5.0 |
|
77.5 |
RPL07.SKN.DHCD.01010 |
RPL07.SKIN.DHCD - IMP, Roof, Windows, Doors, Ext Devices - WBS Summary | DH D & DH C | Not Started | 07/06/26 | 05/17/27 | 271.2 | 271.2 |
|
153.8 |
RPL07.SKN.DHCD.01070 |
RPL07.SKIN.DHCD - Install Roof System - Exterior Wall Sheething | Roofing | Not Started | 07/06/26 | 07/09/26 | 5.0 | 5.0 |
|
36.2 |
RPL07.SKN.DHCD.01080 |
RPL07.SKIN.DHCD - Install Roof System - WBS Summary | Roofing | Not Started | 07/06/26 | 08/14/26 | 37.5 | 37.5 |
|
387.5 |
GCD.RPL07.1456 |
Start RPL07 EY RMU Equipment Pad Placement - RPL07 | Construction Milestones | Not Started | 07/07/26 | 07/07/26 | 0.0 | 0.0 |
|
327.5 |
RPL07.EY.DHA.01130 |
RPL07.EY.DHA - Cure (High Early Mix) | Foundations | Not Started | 07/07/26 | 07/13/26 | 8.8 | 8.8 |
|
140.0 |
RPL07.EY.DHB.01010 |
RPL07.EY.DHB - Install F/R/P Equipment Pads - 1-12(Grid 6-01/6-16) (12'' Larger For Tolerance) | Foundations | Not Started | 07/07/26 | 08/03/26 | 25.0 | 25.0 |
|
55.0 |
RPL07.EY.DHB.01020 |
RPL07.EY.DHB - Install Foundations - WBS Summary | Foundations | Not Started | 07/07/26 | 08/10/26 | 31.2 | 31.2 |
|
55.0 |
RPL07.INT.SSB.01006 |
RPL07.Interior - Priority - Install Hangers Support (Center Corr to End Corr) (All Trades) | Early Priority OH MEPF | Not Started | 07/07/26 | 07/20/26 | 12.5 | 12.5 |
|
131.2 |
RPL07.INT.SSBC.06600 |
RPL07.Interior.SSBC - Priority - Install Backing at Exterior Wall | Priority Walls & Overhead | Not Started | 07/07/26 | 07/07/26 | 1.2 | 1.2 |
|
95.0 |
RPL07.CFCI.4130 |
RPL07 - Submittals Review & Approval - Building Controls | (CFCI) Div. 23 - Building Controls | Not Started | 07/08/26 | 07/21/26 | 12.5 | 12.5 |
|
17.5 |
RPL07.EY.DHC.01130 |
RPL07.EY.DHC - Cure (High Early Mix) | Foundations | Not Started | 07/08/26 | 07/14/26 | 8.8 | 8.8 |
|
338.8 |
RPL07.EY.SSB.02060 |
RPL07.EY.SSB - Install Remaining Permanent Duct with insulation to AHU Units | Temp Conditions | Not Started | 07/08/26 | 07/17/26 | 10.0 | 10.0 |
|
115.0 |
RPL07.INT.SSBC.06620 |
RPL07.Interior.SSBC - Priority - QC - Backings/Walls | Priority Walls & Overhead | Not Started | 07/08/26 | 07/09/26 | 2.5 | 2.5 |
|
95.0 |
RPL07.INT.SSBC.06720 |
RPL07.Interior.SSBC - Priority - Install Drywall at Exterior Walls for SSB Electrical Room | Priority Walls & Overhead | Not Started | 07/08/26 | 07/09/26 | 2.5 | 2.5 |
|
97.5 |
RPL07.SKN.DHAB.01050 |
RPL07.SKIN.DHAB - Install Lighting | Glazing, Doors and Ext Devices | Not Started | 07/08/26 | 07/13/26 | 5.0 | 5.0 |
|
276.2 |
ICM.B7.1875 |
[SSDCB2] Delivery of mCUP (First Delivery) | Construction | Not Started | 07/09/26 | 07/09/26 | 0.0 | 0.0 |
|
77.5 |
PRE.FA.1280 |
Architectural/Security Fencing - Final Agreement | Trade Partner Final Agreement | Not Started | 07/09/26 | 07/09/26 | 0.0 | 0.0 |
|
447.5 |
RPL07.EY.ENDC.01150 |
RPL07.EY.End - Tie-ins - WBS Summary | Tie-ins | Not Started | 07/09/26 | 07/14/27 | 317.5 | 317.5 |
|
30.0 |
RPL07.EY.ENDC.01320 |
RPL07.EY.End - Install Duct/ insulation into the building Main (include penetration detail) | Tie-ins | Not Started | 07/09/26 | 07/22/26 | 12.5 | 12.5 |
|
297.5 |
RPL07.STR.DHAB.01100 |
RPL07.Structure.DHAB - SOG F/R/P #5 - Grid lines 7-14/7-18 | F/R/P | Not Started | 07/09/26 | 07/15/26 | 6.2 | 6.2 |
|
38.8 |
GCD.RPL07.1182 |
Start mCUP Unit Set-In-Place - RPL07 | Construction Milestones | Not Started | 07/10/26 | 07/10/26 | 0.0 | 0.0 |
|
323.8 |
RPL07.INT.DHA.01030 |
RPL07.Interior.DHA - Priority - Install Fire Sprinkler | Early Priority OH MEPF | Not Started | 07/10/26 | 07/16/26 | 6.2 | 6.2 |
|
130.0 |
RPL07.INT.SSB.06580 |
RPL07.Interior.SSB - Priority - QC - Backings/Walls | Priority Walls and OverHead | Not Started | 07/10/26 | 07/16/26 | 6.2 | 6.2 |
|
90.0 |
RPL07.INT.SSBC.06740 |
RPL07.Interior.SSBC - Priority - Frame, Hang Drywall, Tape Finish Paint for SSB Electrical Room | Priority Walls & Overhead | Not Started | 07/10/26 | 07/20/26 | 8.8 | 8.8 |
|
118.8 |
RPL07.MCUP.LP1.1340 |
RPL07.MCUP.Loop 1 - Set mCUPs XXMY.MCUP.01 (1 per 5 days) | OFE | Not Started | 07/10/26 | 07/16/26 | 6.2 | 6.2 |
|
77.5 |
RPL07.MCUP.LP1.1400 |
RPL07.MCUP.Loop 1 - Tie-ins - WBS Summary | Tie-ins | Not Started | 07/10/26 | 09/03/26 | 50.0 | 50.0 |
|
350.0 |
RPL07.MCUP.LP1.1440 |
RPL07.MCUP.Loop 1 - Tie-in Mechanical - WBS Summary | Tie-Ins Mechanical | Not Started | 07/10/26 | 08/20/26 | 37.5 | 37.5 |
|
83.8 |
RPL07.MCUP.LP1.1460 |
RPL07.MCUP.Loop 1 - Tie-in Mechanical #1 (Includes FWM) | Tie-Ins Mechanical | Not Started | 07/10/26 | 07/30/26 | 18.8 | 18.8 |
|
102.5 |
RPL07.MCUP.LP1.2180 |
RPL07.MCUP.Loop 1 - Set Facility Water Pipe Rack (mCUP4) | OFE | Not Started | 07/10/26 | 07/21/26 | 10.0 | 10.0 |
|
105.0 |
RPL07.SKN.DHCD.01090 |
RPL07.SKIN.DHCD - Install Roof System - DenseDeck & Flame Down | Roofing | Not Started | 07/10/26 | 07/20/26 | 8.8 | 8.8 |
|
36.2 |
RPL07.EY.DHA.01120 |
RPL07.EY.DHA - Install BMS UG | Underground | Not Started | 07/13/26 | 07/24/26 | 12.5 | 12.5 |
|
115.0 |
RPL07.EY.DHA.01230 |
RPL07.EY.DHA - OFE - MV - WBS Summary | OFE | Not Started | 07/13/26 | 12/04/26 | 126.2 | 126.2 |
|
243.8 |
RPL07.EY.DHA.01540 |
RPL07.EY.DHA - Install AHUs (Qty 1) | OFE | Not Started | 07/13/26 | 07/22/26 | 10.0 | 10.0 |
|
266.2 |
RPL07.EY.DHA.01530 |
RPL07.EY.DHA - Set GS.IDF Hut (1x GS.IDF) 7X04 | OFE | Not Started | 07/14/26 | 07/20/26 | 6.2 | 6.2 |
|
362.5 |
RPL07.INT.SSBC.03500 |
RPL07.Interior.SSBC - Priority - Install Drywall at Exterior Walls | Priority Walls & Overhead | Not Started | 07/14/26 | 07/16/26 | 3.8 | 3.8 |
|
92.5 |
RPL07.MCUP.LP1.1420 |
RPL07.MCUP.Loop 1 - Tie-in Electrical - WBS Summary | Tie-Ins Electrical | Not Started | 07/14/26 | 08/20/26 | 35.0 | 35.0 |
|
77.5 |
RPL07.MCUP.LP1.1480 |
RPL07.MCUP.Loop 1 - Tie-in Electrical #1 (Includes FWM) | Tie-Ins Electrical | Not Started | 07/14/26 | 07/30/26 | 16.2 | 16.2 |
|
96.2 |
RPL07.SKN.DHAB.01060 |
RPL07.SKIN.DHAB - Install Security | Glazing, Doors and Ext Devices | Not Started | 07/14/26 | 07/15/26 | 2.5 | 2.5 |
|
276.2 |
RPL07.SKN.DHAB.01120 |
RPL07.SKIN.DHAB - Install Roof System - Final Roof | Roofing | Not Started | 07/14/26 | 07/29/26 | 15.0 | 15.0 |
|
133.8 |
RPL07.SKN.SSB.01140 |
RPL07.SKIN.SSB - Install Roof System - Install EJ | Roofing | Not Started | 07/14/26 | 07/20/26 | 6.2 | 6.2 |
|
56.2 |
RPL.07.D.73350.XR |
Pull and Term mCUP Skids - RPL07 | Receive Milestones (XREFs) | Not Started | 07/15/26 | 07/15/26 | 0.0 | 0.0 |
|
123.8 |
RPL.07.D.73850.XR |
100MW Cx Temp Power to MV Skids RPL07 mCUPs Available | Receive Milestones (XREFs) | Not Started | 07/15/26 | 07/15/26 | 0.0 | 0.0 |
|
123.8 |
RPL.07.D.74210.XR |
FW Water Available for mCUP Flush/Fill - Utility connections | Receive Milestones (XREFs) | Not Started | 07/15/26 | 07/15/26 | 0.0 | 0.0 |
|
147.5 |
RPL07.INT.DHA.01010 |
RPL07.Interior.DHA - Priority - Install Duct (*Day Shift) | Early Priority OH MEPF | Not Started | 07/16/26 | 07/20/26 | 3.8 | 3.8 |
|
23.8 |
RPL07.INT.DHA.01015 |
RPL07.Interior.DHA - Priority - Install Duct (*Swing Shift) | Early Priority OH MEPF | Not Started | 07/16/26 | 07/20/26 | 3.8 | 3.8 |
|
23.8 |
RPL07.INT.DHB.01010 |
RPL07.Interior.DHB - Priority - Install Duct (*Day Shift) | Early Priority OH MEPF | Not Started | 07/16/26 | 07/20/26 | 3.8 | 3.8 |
|
23.8 |
RPL07.INT.DHB.01015 |
RPL07.Interior.DHB - Priority - Install Duct (*Swing Shift) | Early Priority OH MEPF | Not Started | 07/16/26 | 07/20/26 | 3.8 | 3.8 |
|
23.8 |
RPL07.INT.SSBC.03280 |
RPL07.Interior.SSBC - Priority GL7.04 - (P0) Frame Walls (All full height Walls) | Priority Wall Grid Line 7-04 | Not Started | 07/16/26 | 07/22/26 | 6.2 | 6.2 |
|
92.5 |
RPL07.SKN.DHAB.01140 |
RPL07.SKIN.DHAB - Install Perm Doors | Glazing, Doors and Ext Devices | Not Started | 07/16/26 | 07/17/26 | 2.5 | 2.5 |
|
276.2 |
RPL07.STR.DHAB.01140 |
RPL07.Structure.DHAB - Zone SOG Cure | F/R/P | Not Started | 07/16/26 | 07/22/26 | 8.8 | 8.8 |
|
53.8 |
RPL07.CFCI.5700 |
RPL07 - Submittals Review & Approval - Glass / Frames | Glass & Glazing (Alum. Entrances & Curtainwall) | Not Started | 07/17/26 | 07/30/26 | 12.5 | 12.5 |
|
146.2 |
RPL07.EY.SSB.01190 |
RPL07.EY.SSB - Set LD Grade and Prep | Loading Dock | Not Started | 07/17/26 | 07/22/26 | 5.0 | 5.0 |
|
206.2 |
RPL07.INT.CTRC.1040 |
RPL07.Interior.Center-Corridor - Priority - Install Fire Sprinkler (Highside OH space) | Early Priority OH MEPF | Not Started | 07/17/26 | 07/21/26 | 3.8 | 3.8 |
|
130.0 |
RPL07.INT.SSB.06540 |
RPL07.Interior.SSB - Priority - Install Drywall at Exterior Walls | Priority Walls and OverHead | Not Started | 07/17/26 | 07/30/26 | 12.5 | 12.5 |
|
90.0 |
RPL07.MCUP.LP1.1360 |
RPL07.MCUP.Loop 1 - Set Electrical Skids #1 | OFE | Not Started | 07/17/26 | 07/20/26 | 2.5 | 2.5 |
|
92.5 |
RPL07.MCUP.LP1.1380 |
RPL07.MCUP.Loop 1 - Set mCUPs XXMY.MCUP.02 (1 per 5 days) | OFE | Not Started | 07/17/26 | 07/23/26 | 6.2 | 6.2 |
|
77.5 |
RPL07.MCUP.LP1.1540 |
RPL07.MCUP.Loop 1 - Tie-in BMS - WBS Summary | Tie-Ins BMS | Not Started | 07/17/26 | 08/20/26 | 31.2 | 31.2 |
|
83.8 |
RPL07.MCUP.LP1.1560 |
RPL07.MCUP.Loop 1 - Tie-in BMS #1 (Includes FWM) | Tie-Ins BMS | Not Started | 07/17/26 | 07/30/26 | 12.5 | 12.5 |
|
102.5 |
RPL07.MCUP.LP1.1580 |
RPL07.MCUP.Loop 1 - Tie-in EPMS - WBS Summary | Tie-Ins EPMS | Not Started | 07/17/26 | 08/20/26 | 31.2 | 31.2 |
|
77.5 |
RPL07.MCUP.LP1.1600 |
RPL07.MCUP.Loop 1 - Tie-in EPMS #1 (Includes FWM) | Tie-Ins EPMS | Not Started | 07/17/26 | 07/30/26 | 12.5 | 12.5 |
|
96.2 |
RPL07.MCUP.LP1.1760 |
RPL07.MCUP.Loop 1 - Tie-in Mechanical #2 | Tie-Ins Mechanical | Not Started | 07/17/26 | 08/06/26 | 18.8 | 18.8 |
|
96.2 |
RPL.GF.D.N7170.XG |
GS.IDF Hut 4 Install Complete for RPL 7 | Give Milestones (XREFs) | Not Started | 07/20/26 | 07/20/26 | 0.0 | 0.0 |
|
457.5 |
RPL07.EY.DHB.01120 |
RPL07.EY.DHB - Install BMS/EPMS UG | Underground | Not Started | 07/20/26 | 07/31/26 | 12.5 | 12.5 |
|
90.0 |
RPL07.INT.DHA.01000 |
RPL07.Interior.DHA - Priority OH - WBS Summary | OverHead | Not Started | 07/20/26 | 09/21/26 | 56.2 | 56.2 |
|
261.2 |
RPL07.INT.DHA.01020 |
RPL07.Interior.DHA - Install Priority OH, Walls, OFE and Tie-ins - WBS Summary | DHA | Not Started | 07/20/26 | 03/30/27 | 216.2 | 216.2 |
|
101.2 |
RPL07.INT.DHA.01820 |
RPL07.Interior.DHA - Priority - Install Draft Curtains (#3 - 3 Days Each) | OverHead | Not Started | 07/20/26 | 07/30/26 | 11.2 | 11.2 |
|
58.8 |
RPL07.INT.DHA.01980 |
RPL07.Interior.DHA - Priority - Install Unistruts & Hangers (All Trades) | OverHead | Not Started | 07/20/26 | 07/24/26 | 6.2 | 6.2 |
|
47.5 |