Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL07 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:16 PM · 5237 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
0
Completed
0
In Progress
0
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL07.EY.DHA.01100 RPL07.EY.DHA - Install Mechanical UG Underground Not Started 06/26/26 07/10/26 12.5 12.5
0%
115.0
RPL07.EY.DHA.01110 RPL07.EY.DHA - Install SD, DW, FW UG Underground Not Started 06/26/26 07/10/26 12.5 12.5
0%
125.0
RPL07.EY.SSB.01110 RPL07.EY.SSB - Install LD Electrical UG Loading Dock Not Started 06/26/26 07/01/26 5.0 5.0
0%
206.2
RPL07.EY.SSB.01120 RPL07.EY.SSB - Install AHU (3) - CFCI OFE Not Started 06/26/26 07/07/26 8.8 8.8
0%
115.0
RPL07.EY.SSB.01140 RPL07.EY.SSB - Install Loading Dock, UG Utilities, OFE - WBS Summary Loading Dock Not Started 06/26/26 08/19/26 47.5 47.5
0%
206.2
RPL07.SKN.S.01070 RPL07.SKIN.South - Install IMP EJ - Grid lines 7-22/7-23 DBC Move 3 - Grid (7-23 / 7-28) Not Started 06/26/26 07/02/26 6.2 6.2
0%
36.2
RPL07.SKN.S.01100 RPL07.SKIN.South - Secure All Exterior Mounted Boxes and Devices on Skin IMP System Not Started 06/26/26 07/24/26 25.0 25.0
0%
322.5
RPL07.SKN.S.01120 RPL07.SKIN.South - Install Stair Tower (DH C) DBC Move 3 - Grid (7-23 / 7-28) Not Started 06/26/26 06/29/26 2.5 2.5
0%
413.8
RPL07.EY.ENDC.1650 RPL07.EY.DHD.T2 - Install Tent 2 Saw Cut and Cure Tent 2 Not Started 06/27/26 07/03/26 8.8 8.8
0%
57.5
RPL07.STR.SSB.01270 RPL07.Structure.SSB - Install SOG Sealer and Cure F/R/P Not Started 06/27/26 06/28/26 2.5 2.5
0%
201.2
RPL07.INT.SSB.06640 RPL07.Interior.SSB - Priority - Install IMP Exterior Inwall Rough-In Priority Walls and OverHead Not Started 06/29/26 07/06/26 6.2 6.2
0%
90.0
RPL07.MCUP.LP1.2160 RPL07.MCUP.Loop 1 - Set Facility Water Pipe Rack (mCUP3) OFE Not Started 06/29/26 07/09/26 10.0 10.0
0%
105.0
RPL07.STR.DHCD.01090 RPL07.Structure.DHCD - Asphalt Emulsion and Wrap Steel Columns Prep Not Started 06/29/26 07/01/26 3.8 3.8
0%
51.2
RPL07.LOG.1140 Dry Cooler 230 Ton Crane Movement 01 100 Ton Crane Not Started 06/30/26 06/30/26 0.0 0.0
0%
93.8
RPL07.SKN.DHAB.01040 RPL07.SKIN.DHAB - Install Louvers Glazing, Doors and Ext Devices Not Started 06/30/26 07/07/26 6.2 6.2
0%
53.8
RPL07.EY.ENDC.02080 RPL07.EY.End - Install Temp Duct to Permanent Duct Temp Conditions Not Started 07/01/26 07/08/26 6.2 6.2
0%
297.5
RPL07.INT.DHB.02160 RPL07.Interior.DHB - Priority - Install Fixed Draft Smoke Curtains (#5) Early Priority OH MEPF Not Started 07/01/26 07/14/26 11.2 11.2
0%
61.2
RPL07.INT.SSBC.01030 RPL07.Interior.SSB-Corridor - Priority - Install Fire Sprinkler (Highside OH space) Early Priority OH MEPF Not Started 07/01/26 07/01/26 1.2 1.2
0%
62.5
RPL07.MCUP.LP1.1280 RPL07.MCUP.Loop 1 - Set MTRs (4 per day) OFE Not Started 07/01/26 07/08/26 6.2 6.2
0%
93.8
RPL07.MCUP.LP1.1320 RPL07.MCUP.Loop 1 - Set mCup #3 & #4 - Dry Coolers (12) (4 per week) OFE Not Started 07/01/26 07/22/26 18.8 18.8
0%
93.8
RPL07.SKN.DHAB.01110 RPL07.SKIN.DHAB - Install Scupper and Downspouts Glazing, Doors and Ext Devices Not Started 07/01/26 07/08/26 6.2 6.2
0%
306.2
RPL07.STR.DHAB.01180 RPL07.Structure.DHAB - SOG F/R/P #4 - Grid lines 7-11/7-14 F/R/P Not Started 07/01/26 07/08/26 6.2 6.2
0%
38.8
RPL07.EY.SSB.01150 RPL07.EY.SSB - Install LD Mechanical UG Loading Dock Not Started 07/02/26 07/16/26 12.5 12.5
0%
206.2
RPL07.INT.DHB.01030 RPL07.Interior.DHB - Priority - Install Fire Sprinkler Early Priority OH MEPF Not Started 07/02/26 07/09/26 6.2 6.2
0%
62.5
RPL07.INT.SSB.06560 RPL07.Interior.SSB - Priority - Install Backing at Exterior Wall Priority Walls and OverHead Not Started 07/02/26 07/09/26 6.2 6.2
0%
90.0
RPL07.INT.SSBC.01011 RPL07.Interior.SSB-Corridor - Priority - Install Duct (Highside OH space) Early Priority OH MEPF Not Started 07/02/26 07/15/26 11.2 11.2
0%
23.8
RPL07.INT.SSBC.02400 RPL07.Interior.SSBC - Priority - Install Layout, Unistruts & Hangers (All Trades) Both side of Corridor Wall Priority Walls & Overhead Not Started 07/02/26 07/08/26 5.0 5.0
0%
95.0
RPL07.INT.SSBC.03520 RPL07.Interior.SSBC - Priority - Install IMP Exterior Inwall Rough-In Priority Walls & Overhead Not Started 07/02/26 07/07/26 3.8 3.8
0%
95.0
RPL.07.D.70080.XR External Tie from RPL06 - EY MV Concrete Foundations Crew Flow (RPL06.EY.DHC.01010) Internal Milestones (XREFs) Not Started 07/06/26 07/06/26 0.0 0.0
0%
55.0
RPL07.EY.DHB.01090 RPL07.EY.DHB - Install Mechanical UG Underground Not Started 07/06/26 07/17/26 12.5 12.5
0%
90.0
RPL07.EY.DHB.01100 RPL07.EY.DHB - Install SD, DW, FW UG Underground Not Started 07/06/26 07/17/26 12.5 12.5
0%
100.0
RPL07.EY.ENDC.1670 RPL07.EY.DHD.T2 - Install Tent Tent 2 Not Started 07/06/26 07/31/26 25.0 25.0
0%
40.0
RPL07.LOG.1000 MCUP 500 Ton Crane Mobilization 300 Ton Crane Not Started 07/06/26 07/09/26 5.0 5.0
0%
77.5
RPL07.SKN.DHCD.01010 RPL07.SKIN.DHCD - IMP, Roof, Windows, Doors, Ext Devices - WBS Summary DH D & DH C Not Started 07/06/26 05/17/27 271.2 271.2
0%
153.8
RPL07.SKN.DHCD.01070 RPL07.SKIN.DHCD - Install Roof System - Exterior Wall Sheething Roofing Not Started 07/06/26 07/09/26 5.0 5.0
0%
36.2
RPL07.SKN.DHCD.01080 RPL07.SKIN.DHCD - Install Roof System - WBS Summary Roofing Not Started 07/06/26 08/14/26 37.5 37.5
0%
387.5
GCD.RPL07.1456 Start RPL07 EY RMU Equipment Pad Placement - RPL07 Construction Milestones Not Started 07/07/26 07/07/26 0.0 0.0
0%
327.5
RPL07.EY.DHA.01130 RPL07.EY.DHA - Cure (High Early Mix) Foundations Not Started 07/07/26 07/13/26 8.8 8.8
0%
140.0
RPL07.EY.DHB.01010 RPL07.EY.DHB - Install F/R/P Equipment Pads - 1-12(Grid 6-01/6-16) (12'' Larger For Tolerance) Foundations Not Started 07/07/26 08/03/26 25.0 25.0
0%
55.0
RPL07.EY.DHB.01020 RPL07.EY.DHB - Install Foundations - WBS Summary Foundations Not Started 07/07/26 08/10/26 31.2 31.2
0%
55.0
RPL07.INT.SSB.01006 RPL07.Interior - Priority - Install Hangers Support (Center Corr to End Corr) (All Trades) Early Priority OH MEPF Not Started 07/07/26 07/20/26 12.5 12.5
0%
131.2
RPL07.INT.SSBC.06600 RPL07.Interior.SSBC - Priority - Install Backing at Exterior Wall Priority Walls & Overhead Not Started 07/07/26 07/07/26 1.2 1.2
0%
95.0
RPL07.CFCI.4130 RPL07 - Submittals Review & Approval - Building Controls (CFCI) Div. 23 - Building Controls Not Started 07/08/26 07/21/26 12.5 12.5
0%
17.5
RPL07.EY.DHC.01130 RPL07.EY.DHC - Cure (High Early Mix) Foundations Not Started 07/08/26 07/14/26 8.8 8.8
0%
338.8
RPL07.EY.SSB.02060 RPL07.EY.SSB - Install Remaining Permanent Duct with insulation to AHU Units Temp Conditions Not Started 07/08/26 07/17/26 10.0 10.0
0%
115.0
RPL07.INT.SSBC.06620 RPL07.Interior.SSBC - Priority - QC - Backings/Walls Priority Walls & Overhead Not Started 07/08/26 07/09/26 2.5 2.5
0%
95.0
RPL07.INT.SSBC.06720 RPL07.Interior.SSBC - Priority - Install Drywall at Exterior Walls for SSB Electrical Room Priority Walls & Overhead Not Started 07/08/26 07/09/26 2.5 2.5
0%
97.5
RPL07.SKN.DHAB.01050 RPL07.SKIN.DHAB - Install Lighting Glazing, Doors and Ext Devices Not Started 07/08/26 07/13/26 5.0 5.0
0%
276.2
ICM.B7.1875 [SSDCB2] Delivery of mCUP (First Delivery) Construction Not Started 07/09/26 07/09/26 0.0 0.0
0%
77.5
PRE.FA.1280 Architectural/Security Fencing - Final Agreement Trade Partner Final Agreement Not Started 07/09/26 07/09/26 0.0 0.0
0%
447.5
RPL07.EY.ENDC.01150 RPL07.EY.End - Tie-ins - WBS Summary Tie-ins Not Started 07/09/26 07/14/27 317.5 317.5
0%
30.0
RPL07.EY.ENDC.01320 RPL07.EY.End - Install Duct/ insulation into the building Main (include penetration detail) Tie-ins Not Started 07/09/26 07/22/26 12.5 12.5
0%
297.5
RPL07.STR.DHAB.01100 RPL07.Structure.DHAB - SOG F/R/P #5 - Grid lines 7-14/7-18 F/R/P Not Started 07/09/26 07/15/26 6.2 6.2
0%
38.8
GCD.RPL07.1182 Start mCUP Unit Set-In-Place - RPL07 Construction Milestones Not Started 07/10/26 07/10/26 0.0 0.0
0%
323.8
RPL07.INT.DHA.01030 RPL07.Interior.DHA - Priority - Install Fire Sprinkler Early Priority OH MEPF Not Started 07/10/26 07/16/26 6.2 6.2
0%
130.0
RPL07.INT.SSB.06580 RPL07.Interior.SSB - Priority - QC - Backings/Walls Priority Walls and OverHead Not Started 07/10/26 07/16/26 6.2 6.2
0%
90.0
RPL07.INT.SSBC.06740 RPL07.Interior.SSBC - Priority - Frame, Hang Drywall, Tape Finish Paint for SSB Electrical Room Priority Walls & Overhead Not Started 07/10/26 07/20/26 8.8 8.8
0%
118.8
RPL07.MCUP.LP1.1340 RPL07.MCUP.Loop 1 - Set mCUPs XXMY.MCUP.01 (1 per 5 days) OFE Not Started 07/10/26 07/16/26 6.2 6.2
0%
77.5
RPL07.MCUP.LP1.1400 RPL07.MCUP.Loop 1 - Tie-ins - WBS Summary Tie-ins Not Started 07/10/26 09/03/26 50.0 50.0
0%
350.0
RPL07.MCUP.LP1.1440 RPL07.MCUP.Loop 1 - Tie-in Mechanical - WBS Summary Tie-Ins Mechanical Not Started 07/10/26 08/20/26 37.5 37.5
0%
83.8
RPL07.MCUP.LP1.1460 RPL07.MCUP.Loop 1 - Tie-in Mechanical #1 (Includes FWM) Tie-Ins Mechanical Not Started 07/10/26 07/30/26 18.8 18.8
0%
102.5
RPL07.MCUP.LP1.2180 RPL07.MCUP.Loop 1 - Set Facility Water Pipe Rack (mCUP4) OFE Not Started 07/10/26 07/21/26 10.0 10.0
0%
105.0
RPL07.SKN.DHCD.01090 RPL07.SKIN.DHCD - Install Roof System - DenseDeck & Flame Down Roofing Not Started 07/10/26 07/20/26 8.8 8.8
0%
36.2
RPL07.EY.DHA.01120 RPL07.EY.DHA - Install BMS UG Underground Not Started 07/13/26 07/24/26 12.5 12.5
0%
115.0
RPL07.EY.DHA.01230 RPL07.EY.DHA - OFE - MV - WBS Summary OFE Not Started 07/13/26 12/04/26 126.2 126.2
0%
243.8
RPL07.EY.DHA.01540 RPL07.EY.DHA - Install AHUs (Qty 1) OFE Not Started 07/13/26 07/22/26 10.0 10.0
0%
266.2
RPL07.EY.DHA.01530 RPL07.EY.DHA - Set GS.IDF Hut (1x GS.IDF) 7X04 OFE Not Started 07/14/26 07/20/26 6.2 6.2
0%
362.5
RPL07.INT.SSBC.03500 RPL07.Interior.SSBC - Priority - Install Drywall at Exterior Walls Priority Walls & Overhead Not Started 07/14/26 07/16/26 3.8 3.8
0%
92.5
RPL07.MCUP.LP1.1420 RPL07.MCUP.Loop 1 - Tie-in Electrical - WBS Summary Tie-Ins Electrical Not Started 07/14/26 08/20/26 35.0 35.0
0%
77.5
RPL07.MCUP.LP1.1480 RPL07.MCUP.Loop 1 - Tie-in Electrical #1 (Includes FWM) Tie-Ins Electrical Not Started 07/14/26 07/30/26 16.2 16.2
0%
96.2
RPL07.SKN.DHAB.01060 RPL07.SKIN.DHAB - Install Security Glazing, Doors and Ext Devices Not Started 07/14/26 07/15/26 2.5 2.5
0%
276.2
RPL07.SKN.DHAB.01120 RPL07.SKIN.DHAB - Install Roof System - Final Roof Roofing Not Started 07/14/26 07/29/26 15.0 15.0
0%
133.8
RPL07.SKN.SSB.01140 RPL07.SKIN.SSB - Install Roof System - Install EJ Roofing Not Started 07/14/26 07/20/26 6.2 6.2
0%
56.2
RPL.07.D.73350.XR Pull and Term mCUP Skids - RPL07 Receive Milestones (XREFs) Not Started 07/15/26 07/15/26 0.0 0.0
0%
123.8
RPL.07.D.73850.XR 100MW Cx Temp Power to MV Skids RPL07 mCUPs Available Receive Milestones (XREFs) Not Started 07/15/26 07/15/26 0.0 0.0
0%
123.8
RPL.07.D.74210.XR FW Water Available for mCUP Flush/Fill - Utility connections Receive Milestones (XREFs) Not Started 07/15/26 07/15/26 0.0 0.0
0%
147.5
RPL07.INT.DHA.01010 RPL07.Interior.DHA - Priority - Install Duct (*Day Shift) Early Priority OH MEPF Not Started 07/16/26 07/20/26 3.8 3.8
0%
23.8
RPL07.INT.DHA.01015 RPL07.Interior.DHA - Priority - Install Duct (*Swing Shift) Early Priority OH MEPF Not Started 07/16/26 07/20/26 3.8 3.8
0%
23.8
RPL07.INT.DHB.01010 RPL07.Interior.DHB - Priority - Install Duct (*Day Shift) Early Priority OH MEPF Not Started 07/16/26 07/20/26 3.8 3.8
0%
23.8
RPL07.INT.DHB.01015 RPL07.Interior.DHB - Priority - Install Duct (*Swing Shift) Early Priority OH MEPF Not Started 07/16/26 07/20/26 3.8 3.8
0%
23.8
RPL07.INT.SSBC.03280 RPL07.Interior.SSBC - Priority GL7.04 - (P0) Frame Walls (All full height Walls) Priority Wall Grid Line 7-04 Not Started 07/16/26 07/22/26 6.2 6.2
0%
92.5
RPL07.SKN.DHAB.01140 RPL07.SKIN.DHAB - Install Perm Doors Glazing, Doors and Ext Devices Not Started 07/16/26 07/17/26 2.5 2.5
0%
276.2
RPL07.STR.DHAB.01140 RPL07.Structure.DHAB - Zone SOG Cure F/R/P Not Started 07/16/26 07/22/26 8.8 8.8
0%
53.8
RPL07.CFCI.5700 RPL07 - Submittals Review & Approval - Glass / Frames Glass & Glazing (Alum. Entrances & Curtainwall) Not Started 07/17/26 07/30/26 12.5 12.5
0%
146.2
RPL07.EY.SSB.01190 RPL07.EY.SSB - Set LD Grade and Prep Loading Dock Not Started 07/17/26 07/22/26 5.0 5.0
0%
206.2
RPL07.INT.CTRC.1040 RPL07.Interior.Center-Corridor - Priority - Install Fire Sprinkler (Highside OH space) Early Priority OH MEPF Not Started 07/17/26 07/21/26 3.8 3.8
0%
130.0
RPL07.INT.SSB.06540 RPL07.Interior.SSB - Priority - Install Drywall at Exterior Walls Priority Walls and OverHead Not Started 07/17/26 07/30/26 12.5 12.5
0%
90.0
RPL07.MCUP.LP1.1360 RPL07.MCUP.Loop 1 - Set Electrical Skids #1 OFE Not Started 07/17/26 07/20/26 2.5 2.5
0%
92.5
RPL07.MCUP.LP1.1380 RPL07.MCUP.Loop 1 - Set mCUPs XXMY.MCUP.02 (1 per 5 days) OFE Not Started 07/17/26 07/23/26 6.2 6.2
0%
77.5
RPL07.MCUP.LP1.1540 RPL07.MCUP.Loop 1 - Tie-in BMS - WBS Summary Tie-Ins BMS Not Started 07/17/26 08/20/26 31.2 31.2
0%
83.8
RPL07.MCUP.LP1.1560 RPL07.MCUP.Loop 1 - Tie-in BMS #1 (Includes FWM) Tie-Ins BMS Not Started 07/17/26 07/30/26 12.5 12.5
0%
102.5
RPL07.MCUP.LP1.1580 RPL07.MCUP.Loop 1 - Tie-in EPMS - WBS Summary Tie-Ins EPMS Not Started 07/17/26 08/20/26 31.2 31.2
0%
77.5
RPL07.MCUP.LP1.1600 RPL07.MCUP.Loop 1 - Tie-in EPMS #1 (Includes FWM) Tie-Ins EPMS Not Started 07/17/26 07/30/26 12.5 12.5
0%
96.2
RPL07.MCUP.LP1.1760 RPL07.MCUP.Loop 1 - Tie-in Mechanical #2 Tie-Ins Mechanical Not Started 07/17/26 08/06/26 18.8 18.8
0%
96.2
RPL.GF.D.N7170.XG GS.IDF Hut 4 Install Complete for RPL 7 Give Milestones (XREFs) Not Started 07/20/26 07/20/26 0.0 0.0
0%
457.5
RPL07.EY.DHB.01120 RPL07.EY.DHB - Install BMS/EPMS UG Underground Not Started 07/20/26 07/31/26 12.5 12.5
0%
90.0
RPL07.INT.DHA.01000 RPL07.Interior.DHA - Priority OH - WBS Summary OverHead Not Started 07/20/26 09/21/26 56.2 56.2
0%
261.2
RPL07.INT.DHA.01020 RPL07.Interior.DHA - Install Priority OH, Walls, OFE and Tie-ins - WBS Summary DHA Not Started 07/20/26 03/30/27 216.2 216.2
0%
101.2
RPL07.INT.DHA.01820 RPL07.Interior.DHA - Priority - Install Draft Curtains (#3 - 3 Days Each) OverHead Not Started 07/20/26 07/30/26 11.2 11.2
0%
58.8
RPL07.INT.DHA.01980 RPL07.Interior.DHA - Priority - Install Unistruts & Hangers (All Trades) OverHead Not Started 07/20/26 07/24/26 6.2 6.2
0%
47.5