Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL07 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:16 PM · 5237 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
0
Completed
0
In Progress
0
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL07.INT.DHA.02400 RPL07.Interior.DHA - Priority - IMP Exterior Inwall Rough-In OverHead Not Started 07/20/26 07/24/26 6.2 6.2
0%
47.5
RPL07.INT.DHB.01000 RPL07.Interior.DHB - Priority OH - WBS Summary OverHead Not Started 07/20/26 08/20/26 30.0 30.0
0%
40.0
RPL07.INT.DHB.01020 RPL07.Interior.DHB - Install Priority OH, Walls, OFE and Tie-ins - WBS Summary DHB Not Started 07/20/26 04/12/27 227.5 227.5
0%
77.5
RPL07.INT.DHB.02140 RPL07.Interior.DHB - Priority - Install Unistruts & Hangers (All Trades) OverHead Not Started 07/20/26 07/24/26 6.2 6.2
0%
37.5
RPL07.INT.DHB.02340 RPL07.Interior.DHB - Priority - Install IMP Exterior Inwall Rough-In (These walls available early) OverHead Not Started 07/20/26 07/24/26 6.2 6.2
0%
37.5
RPL07.CON.WP2.07800 RPL07.Conn - Ext. GSIDF7X04 (South Elec Yard) - WBS Summary Ext. IDF Hut - GSIDF7X04 Not Started 07/21/26 12/18/26 131.2 131.2
0%
326.2
RPL07.CON.WP2.08460 RPL07.Conn - Ext. GSIDF7X04 - Install Infrastructure (Racks, Waterfalls etc.) ??pred?? Infrastructure Not Started 07/21/26 07/27/26 6.2 6.2
0%
362.5
RPL07.INT.CTRC.1180 RPL07.Interior.Center-Corridor - Priority - Install Duct (Highside OH space) Early Priority OH MEPF Not Started 07/21/26 07/29/26 8.8 8.8
0%
205.0
RPL07.INT.DHA.03380 RPL07.Interior.DHA - Temp Conditions - Drop Curtains (from Corridor to EJ) Temp Conditions Not Started 07/21/26 07/30/26 10.0 10.0
0%
23.8
RPL07.INT.DHB.01060 RPL07.Interior.DHB - Temp Conditions - Drop Curtains (from Corridor to EJ) Temp Conditions Not Started 07/21/26 07/29/26 8.8 8.8
0%
25.0
RPL07.INT.SSB.01040 RPL07.Interior.SSB - Priority - Install Temp Lighting (Show In Model) Early Priority OH MEPF Not Started 07/21/26 07/27/26 6.2 6.2
0%
40.0
RPL07.INT.SSBC.03260 RPL07.Interior.SSBC - Priority - Tape Finish Paint Priority Soffit both sides (Top Out) Priority Walls & Overhead Not Started 07/21/26 07/27/26 6.2 6.2
0%
112.5
RPL07.INT.SSBC.06660 RPL07.Interior.SSBC - Priority GL7.04 - (P0) Install MEP In-Wall/Backing Priority Wall Grid Line 7-04 Not Started 07/21/26 07/24/26 5.0 5.0
0%
92.5
RPL07.MCUP.LP1.1700 RPL07.MCUP.Loop 1 - Tie-in Electrical #2 Tie-Ins Electrical Not Started 07/21/26 08/06/26 16.2 16.2
0%
90.0
RPL07.STR.DHCD.01110 RPL07.Structure.DHCD - SOG F/R/P - WBS Summary F/R/P Not Started 07/21/26 08/26/26 33.8 33.8
0%
111.2
RPL07.STR.DHCD.01120 RPL07.Structure.DHCD - SOG F/R/P #6 - Grid lines 7-18/7-21 F/R/P Not Started 07/21/26 07/27/26 6.2 6.2
0%
36.2
RPL.GF.D.N7170.XR Natural Gas Available for Fill/Flush Cx - Utility connections Receive Milestones (XREFs) Not Started 07/22/26 07/22/26 0.0 0.0
0%
147.5
RPL07.CFCI.4380 RPL07 - Fabricate / Deliver - Building Controls (CFCI) Div. 23 - Building Controls Not Started 07/22/26 09/16/26 50.0 50.0
0%
17.5
RPL07.CFCI.4450 RPL07 - Submittals - Finished Carpentry (Millwork/Countertops) Finished Carpentry (Millwork/Tops) Not Started 07/22/26 08/18/26 25.0 25.0
0%
247.5
RPL07.CFCI.4610 RPL07 - Submittals Prep & Submit for Review - Interior Painting (Spec 09 91 23) XX (CFCI) Div. 09 - Painting Not Started 07/22/26 08/18/26 25.0 25.0
0%
156.2
RPL07.CFCI.4630 RPL07 - Submittals Prep & Submit for Review - Fire Alarm (CFCI) Div. 26 - Fire Alarm Not Started 07/22/26 08/18/26 25.0 25.0
0%
192.5
RPL07.CFCI.4730 RPL07 - Submittals Review & Approval - Finished Carpentry (Millwork/Countertops) Finished Carpentry (Millwork/Tops) Not Started 07/22/26 08/18/26 25.0 25.0
0%
247.5
RPL07.CFCI.4950 Campus - Submittals Prep & Submit for Review - Landscaping / Irrigation (CFCI) Div. 32 - Landscape/ Irrigation Not Started 07/22/26 08/25/26 31.2 31.2
0%
287.5
RPL07.INT.DHD.01030 RPL07.Interior.DHD - Priority - Install Fire Sprinkler Early Priority OH MEPF Not Started 07/22/26 07/28/26 6.2 6.2
0%
130.0
RPL07.LOG.1160 Dry Cooler 230 Ton Crane Movement 02 100 Ton Crane Not Started 07/22/26 07/22/26 0.0 0.0
0%
210.0
RPL07.MCUP.LP2.1200 RPL07.MCUP.Loop 2 - OFE - WBS Summary OFE Not Started 07/22/26 08/24/26 30.0 30.0
0%
212.5
RPL07.MCUP.LP2.2100 RPL07.MCUP.Loop 2 - Set Facility Water Pipe Rack (mCUP5) OFE Not Started 07/22/26 07/31/26 10.0 10.0
0%
220.0
RPL07.EY.ENDC.1430 RPL07.EY.DHD.T1 - Install Overhead Doors Tent 1 Not Started 07/23/26 07/29/26 6.2 6.2
0%
41.2
RPL07.EY.ENDC.1450 RPL07.EY.DHD.T1 - Install Tent Fit-out Tent 1 Not Started 07/23/26 08/05/26 12.5 12.5
0%
51.2
RPL07.EY.SSB.01200 RPL07.EY.SSB - Install LD F/R/P Loading Dock Ramp Loading Dock Not Started 07/23/26 08/03/26 10.0 10.0
0%
206.2
RPL07.INT.DHA.03440 RPL07.Interior.DHA - Priority - Install Backing at Exterior Wall OverHead Not Started 07/23/26 07/24/26 2.5 2.5
0%
47.5
RPL07.INT.DHB.02380 RPL07.Interior.DHB - Priority - Install Backing at Exterior Wall OverHead Not Started 07/23/26 07/24/26 2.5 2.5
0%
37.5
RPL07.INT.SSBC.06640 RPL07.Interior.SSBC - Priority GL7.04 - (P0) Install IMP Walls Priority Wall Grid Line 7-04 Not Started 07/23/26 07/28/26 5.0 5.0
0%
98.8
RPL07.INT.SSBC.06680 RPL07.Interior.SSBC - Priority GL7.04 - (P0) Hang Drywall (Both SIdes) Priority Wall Grid Line 7-04 Not Started 07/23/26 07/28/26 5.0 5.0
0%
92.5
RPL07.LOG.1020 MCUP 500 Ton Crane Movement 1 300 Ton Crane Not Started 07/23/26 07/23/26 0.0 0.0
0%
77.5
RPL07.LOG.1300 Dry Cooler 230 Ton Crane Demobilization 100 Ton Crane Not Started 07/23/26 07/27/26 3.8 3.8
0%
385.0
RPL07.MCUP.LP2.1220 RPL07.MCUP.Loop 2 - Set mCup #5 & #6 - Dry Coolers (12) (4 per week) OFE Not Started 07/23/26 08/12/26 18.8 18.8
0%
210.0
RPL07.STR.DHAB.01240 RPL07.Structure.DHAB - Moisture requirements for floor Sealer F/R/P Not Started 07/23/26 07/29/26 8.8 8.8
0%
66.2
RPL07.INT.SSB.01660 RPL07.Interior.SSB - Priority - Install Plumbing (Highside OH space) Priority Walls and OverHead Not Started 07/24/26 07/30/26 6.2 6.2
0%
90.0
RPL07.INT.SSB.01680 RPL07.Interior.SSB - Priority - Install Mechanical Piping/ Refrigerant (Highside OH space) Priority Walls and OverHead Not Started 07/24/26 07/30/26 6.2 6.2
0%
90.0
RPL07.INT.SSB.03200 RPL07.Interior.SSB - Priority - Install Fire Alarm hangers & members (Highside OH space) Priority Walls and OverHead Not Started 07/24/26 07/30/26 6.2 6.2
0%
277.5
RPL07.MCUP.LP1.1260 RPL07.MCUP.Loop 1 - Set GS.IDF Hut (1x GS.IDF) 7X02 (ROJ05.13.26) OFE Not Started 07/24/26 07/30/26 6.2 6.2
0%
83.8
RPL07.MCUP.LP1.1500 RPL07.MCUP.Loop 1 - Set mCUPs XXMY.MCUP.03 (1 per 5 days) OFE Not Started 07/24/26 07/30/26 6.2 6.2
0%
77.5
RPL07.MCUP.LP1.1520 RPL07.MCUP.Loop 1 - Set Electrical Skids #2 OFE Not Started 07/24/26 07/27/26 2.5 2.5
0%
88.8
RPL07.MCUP.LP1.1660 RPL07.MCUP.Loop 1 - Tie-in SD, DW Tie-ins Not Started 07/24/26 08/13/26 18.8 18.8
0%
368.8
RPL07.MCUP.LP1.1720 RPL07.MCUP.Loop 1 - Tie-in EPMS #2 Tie-Ins EPMS Not Started 07/24/26 08/06/26 12.5 12.5
0%
90.0
RPL07.MCUP.LP1.1740 RPL07.MCUP.Loop 1 - Tie-in BMS #2 Tie-Ins BMS Not Started 07/24/26 08/06/26 12.5 12.5
0%
96.2
GCD.RPL07.1280 Interior fit-out Start RPL07 - DHA&B Construction Milestones Not Started 07/27/26 07/27/26 0.0 0.0
0%
310.0
RPL07.INT.DHA.02380 RPL07.Interior.DHA - Priority - Install Drywall at Exterior Walls OverHead Not Started 07/27/26 08/04/26 8.8 8.8
0%
47.5
RPL07.INT.DHB.02320 RPL07.Interior.DHB - Priority - Install Drywall at Exterior Walls OverHead Not Started 07/27/26 08/04/26 8.8 8.8
0%
37.5
RPL07.SKN.E.01040 RPL07.SKIN.East - Secure All Exterior Mounted Boxes and Devices on Skin IMP System Not Started 07/27/26 08/07/26 12.5 12.5
0%
322.5
RPL07.SKN.SSB.01040 RPL07.SKIN.SSB - Install Louvers Glazing, Doors and Ext Devices Not Started 07/27/26 07/31/26 6.2 6.2
0%
258.8
RPL07.CON.WP2.08540 RPL07.Conn - Ext. GSIDF7X04 - Install Copper, WAPs, Security Camera & Access Control (EY-DH A) Cabling Not Started 07/28/26 08/12/26 15.0 15.0
0%
362.5
RPL07.INT.DHB.01090 RPL07.Interior.DHB - Temp Conditions - Install Early Temp Conditions Temp Conditions Not Started 07/28/26 07/29/26 2.5 2.5
0%
25.0
RPL07.INT.DHB.02100 RPL07.Interior.DHB - Priority - Install Mechanical Piping OverHead Not Started 07/28/26 08/17/26 18.8 18.8
0%
36.2
RPL07.INT.SSB.02840 RPL07.Interior.SSB - Priority - Tape Finish Paint Priority Soffit (Top Out) Priority Walls and OverHead Not Started 07/28/26 08/10/26 12.5 12.5
0%
141.2
RPL07.INT.SSBC.01040 RPL07.Interior.SSB-Corridor - Priority - Install Temp Lighting (Show In Model) Early Priority OH MEPF Not Started 07/28/26 07/30/26 3.8 3.8
0%
40.0
RPL07.MCUP.LP1.1880 RPL07.MCUP.Loop 1 - Tie-in Mechanical #3 Tie-Ins Mechanical Not Started 07/28/26 08/13/26 16.2 16.2
0%
90.0
RPL07.STR.DHCD.01130 RPL07.Structure.DHCD - SOG F/R/P #7 - Grid lines 7-21/7-25 F/R/P Not Started 07/28/26 08/03/26 6.2 6.2
0%
37.5
GCD.RPL07.1020 Weather tight SSB and DHA&B Construction Milestones Not Started 07/29/26 07/29/26 0.0 0.0
0%
306.2
RPL07.CFCI.5100 Campus - Submittal Review & Approval - Asphalt / Paving (CFCI) Div. 32 - Asphalt/ Conc. Paving Not Started 07/29/26 08/25/26 25.0 25.0
0%
201.2
RPL07.INT.DHA.03400 RPL07.Interior.DHA - Temp Conditions - Install Early Temp Conditions Temp Conditions Not Started 07/29/26 07/30/26 2.5 2.5
0%
23.8
RPL07.INT.DHB.01050 RPL07.Interior.DHB - Priority - Install FA / Linear heat detection OverHead Not Started 07/29/26 08/04/26 6.2 6.2
0%
40.0
RPL07.INT.DHB.02300 RPL07.Interior.DHB - Priority - Install Electrical OverHead Not Started 07/29/26 08/17/26 17.5 17.5
0%
37.5
RPL07.INT.DHC.01030 RPL07.Interior.DHC - Priority - Install Fire Sprinkler Early Priority OH MEPF Not Started 07/29/26 08/04/26 6.2 6.2
0%
130.0
RPL07.INT.SSBC.06700 RPL07.Interior.SSBC - Priority GL7.04 - (P0) Tape Finish Paint (Both SIdes) Priority Wall Grid Line 7-04 Not Started 07/29/26 08/04/26 6.2 6.2
0%
92.5
ICM.B7.1750 [SSDCB2] Room Ready for GS.MDF Module Placement Construction Not Started 07/30/26 07/30/26 0.0 0.0
0%
305.0
ICM.B7.1865 [SSDCB2] Delivery of MDF GS.MDF Module (First Delivery) Construction Not Started 07/30/26 07/30/26 0.0 0.0
0%
108.8
RPL.GF.D.N7150.XG GS.IDF Hut 2 Install Complete for RPL 7 Give Milestones (XREFs) Not Started 07/30/26 07/30/26 0.0 0.0
0%
447.5
RPL07.EY.ENDC.1410 RPL07.EY.DHD.T1 - Install Heating and Cooling Equipment Tent 1 Not Started 07/30/26 08/05/26 6.2 6.2
0%
41.2
RPL07.INT.DHB.02360 RPL07.Interior.DHB - Temp Conditions - CC West Duct Work Complete for Temp Conditioning (LVs) Temp Conditions Not Started 07/30/26 07/31/26 2.5 2.5
0%
25.0
RPL07.SKN.DHAB.01130 RPL07.SKIN.DHAB - Install Roof System - Install EJ Roofing Not Started 07/30/26 07/31/26 2.5 2.5
0%
133.8
RPL07.SKN.DHCD.01110 RPL07.SKIN.DHCD - Install Roof System - Final Roof Roofing Not Started 07/30/26 08/14/26 15.0 15.0
0%
387.5
RPL07.STR.DHAB.01260 RPL07.Structure.DHAB - Install SOG Sealer and Cure F/R/P Not Started 07/30/26 07/31/26 2.5 2.5
0%
66.2
DCC.B7.3125 [SSDCB2] GS Gear Delivered [DHB] Connectivity Not Started 07/31/26 07/31/26 0.0 0.0
0%
447.5
DCC.B7.3135 [SSDCB2] GS Gear Delivered [DHA] Connectivity Not Started 07/31/26 07/31/26 0.0 0.0
0%
447.5
RPL07.CFCI.5690 RPL07 - Fabricate / Deliver - Glass / Frames Glass & Glazing (Alum. Entrances & Curtainwall) Not Started 07/31/26 10/02/26 56.2 56.2
0%
146.2
RPL07.CON.WP2.07400 RPL07.Conn - Ext. GSIDF7X02 (mCUP yard) - WBS Summary Ext. IDF Hut - GSIDF7X02 Not Started 07/31/26 12/10/26 113.8 113.8
0%
333.8
RPL07.CON.WP2.07420 RPL07.Conn - Ext. GSIDF7X02 - Install Infrastructure (Racks, Waterfalls etc.) Infrastructure Not Started 07/31/26 08/06/26 6.2 6.2
0%
262.5
RPL07.INT.DHA.03420 RPL07.Interior.DHA - Temp Conditions - CC West Duct Work Complete for Temp Conditioning (LVs) Temp Conditions Not Started 07/31/26 08/03/26 2.5 2.5
0%
23.8
RPL07.INT.DHB.01040 RPL07.Interior.DHB - Priority - Install Temp Lighting Early Priority OH MEPF Not Started 07/31/26 08/04/26 3.8 3.8
0%
40.0
RPL07.INT.SSB.03220 RPL07.Interior.SSB - Priority - Install Fire Safing/ Seal all Penetrations through Soffit (Highside OH space) Priority Walls and OverHead Not Started 07/31/26 08/06/26 6.2 6.2
0%
150.0
RPL07.INT.SSBC.02180 RPL07.Interior.SSBC - Priority - Install Plumbing (Highside OH space) Priority Walls & Overhead Not Started 07/31/26 08/06/26 6.2 6.2
0%
90.0
RPL07.INT.SSBC.02200 RPL07.Interior.SSBC - Priority - Install Mechanical Piping/ Refrigerant (Highside OH space) Priority Walls & Overhead Not Started 07/31/26 08/06/26 6.2 6.2
0%
90.0
RPL07.INT.SSBC.03300 RPL07.Interior.SSBC - Priority - Install FA/ VESDA/ hangers & Heat Trace (Highside OH space) Priority Walls & Overhead Not Started 07/31/26 08/06/26 6.2 6.2
0%
90.0
RPL07.MCUP.LP1.1620 RPL07.MCUP.Loop 1 - Set mCUPs XXMY.MCUP.04 (1 per 5 days) OFE Not Started 07/31/26 08/06/26 6.2 6.2
0%
77.5
RPL07.MCUP.LP1.1640 RPL07.MCUP.Loop 1 - Set Electrical Skids #3 OFE Not Started 07/31/26 08/03/26 2.5 2.5
0%
85.0
RPL07.MCUP.LP1.1860 RPL07.MCUP.Loop 1 - Tie-in Electrical #3 Tie-Ins Electrical Not Started 07/31/26 08/13/26 12.5 12.5
0%
83.8
RPL07.MCUP.LP2.1300 RPL07.MCUP.Loop 2 - Set GS.IDF Hut (1x GS.IDF) 7X03 (ROJ05.13.26) OFE Not Started 07/31/26 08/06/26 6.2 6.2
0%
215.0
RPL07.EY.ENDC.1730 RPL07.EY.DHD.T2 - Install Overhead Doors Tent 2 Not Started 08/03/26 08/07/26 6.2 6.2
0%
40.0
RPL07.EY.ENDC.1750 RPL07.EY.DHD.T2 - Install Tent Fit-out Tent 2 Not Started 08/03/26 08/14/26 12.5 12.5
0%
50.0
RPL07.INT.DHA.01080 RPL07.Interior.DHA - OFE - WBS Summary OFE/MOFE & CFCI Not Started 08/03/26 02/09/27 162.5 162.5
0%
46.2
RPL07.INT.DHA.03980 RPL07.Interior.DHA - CFCI - Pre Set 16"" FW Pipe OFE/MOFE & CFCI Not Started 08/03/26 08/14/26 12.5 12.5
0%
81.2
RPL07.INT.DHB.01160 RPL07.Interior.DHB - OFE - WBS Summary OFE/MOFE & CFCI Not Started 08/03/26 01/26/27 150.0 150.0
0%
37.5
RPL07.INT.DHB.02900 RPL07.Interior.DHB - CFCI - Pre Set 16"" FW Pipe OFE/MOFE & CFCI Not Started 08/03/26 08/14/26 12.5 12.5
0%
81.2
RPL07.MCUP.LP2.2120 RPL07.MCUP.Loop 2 - Set Facility Water Pipe Rack (mCUP6) OFE Not Started 08/03/26 08/14/26 12.5 12.5
0%
220.0
RPL07.SKN.SSB.01060 RPL07.SKIN.SSB - Install Awning over Doors Glazing, Doors and Ext Devices Not Started 08/03/26 08/07/26 6.2 6.2
0%
266.2
RPL07.EY.DHB.01130 RPL07.EY.DHB - Cure (High Early Mix) Foundations Not Started 08/04/26 08/10/26 8.8 8.8
0%
78.8
RPL07.EY.DHD.01010 RPL07.EY.DHD - Install F/R/P Equipment Pads - 1-10 (Grid 6-17/6-28) (12'' Larger For Tolerance) Foundations Not Started 08/04/26 08/24/26 18.8 18.8
0%
171.2
RPL07.EY.DHD.01020 RPL07.EY.DHD - Install Foundations - WBS Summary Foundations Not Started 08/04/26 05/18/27 246.2 246.2
0%
95.0