Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL07 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:16 PM
· 5237 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
0
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL07.INT.DHA.02400 |
RPL07.Interior.DHA - Priority - IMP Exterior Inwall Rough-In | OverHead | Not Started | 07/20/26 | 07/24/26 | 6.2 | 6.2 |
|
47.5 |
RPL07.INT.DHB.01000 |
RPL07.Interior.DHB - Priority OH - WBS Summary | OverHead | Not Started | 07/20/26 | 08/20/26 | 30.0 | 30.0 |
|
40.0 |
RPL07.INT.DHB.01020 |
RPL07.Interior.DHB - Install Priority OH, Walls, OFE and Tie-ins - WBS Summary | DHB | Not Started | 07/20/26 | 04/12/27 | 227.5 | 227.5 |
|
77.5 |
RPL07.INT.DHB.02140 |
RPL07.Interior.DHB - Priority - Install Unistruts & Hangers (All Trades) | OverHead | Not Started | 07/20/26 | 07/24/26 | 6.2 | 6.2 |
|
37.5 |
RPL07.INT.DHB.02340 |
RPL07.Interior.DHB - Priority - Install IMP Exterior Inwall Rough-In (These walls available early) | OverHead | Not Started | 07/20/26 | 07/24/26 | 6.2 | 6.2 |
|
37.5 |
RPL07.CON.WP2.07800 |
RPL07.Conn - Ext. GSIDF7X04 (South Elec Yard) - WBS Summary | Ext. IDF Hut - GSIDF7X04 | Not Started | 07/21/26 | 12/18/26 | 131.2 | 131.2 |
|
326.2 |
RPL07.CON.WP2.08460 |
RPL07.Conn - Ext. GSIDF7X04 - Install Infrastructure (Racks, Waterfalls etc.) ??pred?? | Infrastructure | Not Started | 07/21/26 | 07/27/26 | 6.2 | 6.2 |
|
362.5 |
RPL07.INT.CTRC.1180 |
RPL07.Interior.Center-Corridor - Priority - Install Duct (Highside OH space) | Early Priority OH MEPF | Not Started | 07/21/26 | 07/29/26 | 8.8 | 8.8 |
|
205.0 |
RPL07.INT.DHA.03380 |
RPL07.Interior.DHA - Temp Conditions - Drop Curtains (from Corridor to EJ) | Temp Conditions | Not Started | 07/21/26 | 07/30/26 | 10.0 | 10.0 |
|
23.8 |
RPL07.INT.DHB.01060 |
RPL07.Interior.DHB - Temp Conditions - Drop Curtains (from Corridor to EJ) | Temp Conditions | Not Started | 07/21/26 | 07/29/26 | 8.8 | 8.8 |
|
25.0 |
RPL07.INT.SSB.01040 |
RPL07.Interior.SSB - Priority - Install Temp Lighting (Show In Model) | Early Priority OH MEPF | Not Started | 07/21/26 | 07/27/26 | 6.2 | 6.2 |
|
40.0 |
RPL07.INT.SSBC.03260 |
RPL07.Interior.SSBC - Priority - Tape Finish Paint Priority Soffit both sides (Top Out) | Priority Walls & Overhead | Not Started | 07/21/26 | 07/27/26 | 6.2 | 6.2 |
|
112.5 |
RPL07.INT.SSBC.06660 |
RPL07.Interior.SSBC - Priority GL7.04 - (P0) Install MEP In-Wall/Backing | Priority Wall Grid Line 7-04 | Not Started | 07/21/26 | 07/24/26 | 5.0 | 5.0 |
|
92.5 |
RPL07.MCUP.LP1.1700 |
RPL07.MCUP.Loop 1 - Tie-in Electrical #2 | Tie-Ins Electrical | Not Started | 07/21/26 | 08/06/26 | 16.2 | 16.2 |
|
90.0 |
RPL07.STR.DHCD.01110 |
RPL07.Structure.DHCD - SOG F/R/P - WBS Summary | F/R/P | Not Started | 07/21/26 | 08/26/26 | 33.8 | 33.8 |
|
111.2 |
RPL07.STR.DHCD.01120 |
RPL07.Structure.DHCD - SOG F/R/P #6 - Grid lines 7-18/7-21 | F/R/P | Not Started | 07/21/26 | 07/27/26 | 6.2 | 6.2 |
|
36.2 |
RPL.GF.D.N7170.XR |
Natural Gas Available for Fill/Flush Cx - Utility connections | Receive Milestones (XREFs) | Not Started | 07/22/26 | 07/22/26 | 0.0 | 0.0 |
|
147.5 |
RPL07.CFCI.4380 |
RPL07 - Fabricate / Deliver - Building Controls | (CFCI) Div. 23 - Building Controls | Not Started | 07/22/26 | 09/16/26 | 50.0 | 50.0 |
|
17.5 |
RPL07.CFCI.4450 |
RPL07 - Submittals - Finished Carpentry (Millwork/Countertops) | Finished Carpentry (Millwork/Tops) | Not Started | 07/22/26 | 08/18/26 | 25.0 | 25.0 |
|
247.5 |
RPL07.CFCI.4610 |
RPL07 - Submittals Prep & Submit for Review - Interior Painting (Spec 09 91 23) XX | (CFCI) Div. 09 - Painting | Not Started | 07/22/26 | 08/18/26 | 25.0 | 25.0 |
|
156.2 |
RPL07.CFCI.4630 |
RPL07 - Submittals Prep & Submit for Review - Fire Alarm | (CFCI) Div. 26 - Fire Alarm | Not Started | 07/22/26 | 08/18/26 | 25.0 | 25.0 |
|
192.5 |
RPL07.CFCI.4730 |
RPL07 - Submittals Review & Approval - Finished Carpentry (Millwork/Countertops) | Finished Carpentry (Millwork/Tops) | Not Started | 07/22/26 | 08/18/26 | 25.0 | 25.0 |
|
247.5 |
RPL07.CFCI.4950 |
Campus - Submittals Prep & Submit for Review - Landscaping / Irrigation | (CFCI) Div. 32 - Landscape/ Irrigation | Not Started | 07/22/26 | 08/25/26 | 31.2 | 31.2 |
|
287.5 |
RPL07.INT.DHD.01030 |
RPL07.Interior.DHD - Priority - Install Fire Sprinkler | Early Priority OH MEPF | Not Started | 07/22/26 | 07/28/26 | 6.2 | 6.2 |
|
130.0 |
RPL07.LOG.1160 |
Dry Cooler 230 Ton Crane Movement 02 | 100 Ton Crane | Not Started | 07/22/26 | 07/22/26 | 0.0 | 0.0 |
|
210.0 |
RPL07.MCUP.LP2.1200 |
RPL07.MCUP.Loop 2 - OFE - WBS Summary | OFE | Not Started | 07/22/26 | 08/24/26 | 30.0 | 30.0 |
|
212.5 |
RPL07.MCUP.LP2.2100 |
RPL07.MCUP.Loop 2 - Set Facility Water Pipe Rack (mCUP5) | OFE | Not Started | 07/22/26 | 07/31/26 | 10.0 | 10.0 |
|
220.0 |
RPL07.EY.ENDC.1430 |
RPL07.EY.DHD.T1 - Install Overhead Doors | Tent 1 | Not Started | 07/23/26 | 07/29/26 | 6.2 | 6.2 |
|
41.2 |
RPL07.EY.ENDC.1450 |
RPL07.EY.DHD.T1 - Install Tent Fit-out | Tent 1 | Not Started | 07/23/26 | 08/05/26 | 12.5 | 12.5 |
|
51.2 |
RPL07.EY.SSB.01200 |
RPL07.EY.SSB - Install LD F/R/P Loading Dock Ramp | Loading Dock | Not Started | 07/23/26 | 08/03/26 | 10.0 | 10.0 |
|
206.2 |
RPL07.INT.DHA.03440 |
RPL07.Interior.DHA - Priority - Install Backing at Exterior Wall | OverHead | Not Started | 07/23/26 | 07/24/26 | 2.5 | 2.5 |
|
47.5 |
RPL07.INT.DHB.02380 |
RPL07.Interior.DHB - Priority - Install Backing at Exterior Wall | OverHead | Not Started | 07/23/26 | 07/24/26 | 2.5 | 2.5 |
|
37.5 |
RPL07.INT.SSBC.06640 |
RPL07.Interior.SSBC - Priority GL7.04 - (P0) Install IMP Walls | Priority Wall Grid Line 7-04 | Not Started | 07/23/26 | 07/28/26 | 5.0 | 5.0 |
|
98.8 |
RPL07.INT.SSBC.06680 |
RPL07.Interior.SSBC - Priority GL7.04 - (P0) Hang Drywall (Both SIdes) | Priority Wall Grid Line 7-04 | Not Started | 07/23/26 | 07/28/26 | 5.0 | 5.0 |
|
92.5 |
RPL07.LOG.1020 |
MCUP 500 Ton Crane Movement 1 | 300 Ton Crane | Not Started | 07/23/26 | 07/23/26 | 0.0 | 0.0 |
|
77.5 |
RPL07.LOG.1300 |
Dry Cooler 230 Ton Crane Demobilization | 100 Ton Crane | Not Started | 07/23/26 | 07/27/26 | 3.8 | 3.8 |
|
385.0 |
RPL07.MCUP.LP2.1220 |
RPL07.MCUP.Loop 2 - Set mCup #5 & #6 - Dry Coolers (12) (4 per week) | OFE | Not Started | 07/23/26 | 08/12/26 | 18.8 | 18.8 |
|
210.0 |
RPL07.STR.DHAB.01240 |
RPL07.Structure.DHAB - Moisture requirements for floor Sealer | F/R/P | Not Started | 07/23/26 | 07/29/26 | 8.8 | 8.8 |
|
66.2 |
RPL07.INT.SSB.01660 |
RPL07.Interior.SSB - Priority - Install Plumbing (Highside OH space) | Priority Walls and OverHead | Not Started | 07/24/26 | 07/30/26 | 6.2 | 6.2 |
|
90.0 |
RPL07.INT.SSB.01680 |
RPL07.Interior.SSB - Priority - Install Mechanical Piping/ Refrigerant (Highside OH space) | Priority Walls and OverHead | Not Started | 07/24/26 | 07/30/26 | 6.2 | 6.2 |
|
90.0 |
RPL07.INT.SSB.03200 |
RPL07.Interior.SSB - Priority - Install Fire Alarm hangers & members (Highside OH space) | Priority Walls and OverHead | Not Started | 07/24/26 | 07/30/26 | 6.2 | 6.2 |
|
277.5 |
RPL07.MCUP.LP1.1260 |
RPL07.MCUP.Loop 1 - Set GS.IDF Hut (1x GS.IDF) 7X02 (ROJ05.13.26) | OFE | Not Started | 07/24/26 | 07/30/26 | 6.2 | 6.2 |
|
83.8 |
RPL07.MCUP.LP1.1500 |
RPL07.MCUP.Loop 1 - Set mCUPs XXMY.MCUP.03 (1 per 5 days) | OFE | Not Started | 07/24/26 | 07/30/26 | 6.2 | 6.2 |
|
77.5 |
RPL07.MCUP.LP1.1520 |
RPL07.MCUP.Loop 1 - Set Electrical Skids #2 | OFE | Not Started | 07/24/26 | 07/27/26 | 2.5 | 2.5 |
|
88.8 |
RPL07.MCUP.LP1.1660 |
RPL07.MCUP.Loop 1 - Tie-in SD, DW | Tie-ins | Not Started | 07/24/26 | 08/13/26 | 18.8 | 18.8 |
|
368.8 |
RPL07.MCUP.LP1.1720 |
RPL07.MCUP.Loop 1 - Tie-in EPMS #2 | Tie-Ins EPMS | Not Started | 07/24/26 | 08/06/26 | 12.5 | 12.5 |
|
90.0 |
RPL07.MCUP.LP1.1740 |
RPL07.MCUP.Loop 1 - Tie-in BMS #2 | Tie-Ins BMS | Not Started | 07/24/26 | 08/06/26 | 12.5 | 12.5 |
|
96.2 |
GCD.RPL07.1280 |
Interior fit-out Start RPL07 - DHA&B | Construction Milestones | Not Started | 07/27/26 | 07/27/26 | 0.0 | 0.0 |
|
310.0 |
RPL07.INT.DHA.02380 |
RPL07.Interior.DHA - Priority - Install Drywall at Exterior Walls | OverHead | Not Started | 07/27/26 | 08/04/26 | 8.8 | 8.8 |
|
47.5 |
RPL07.INT.DHB.02320 |
RPL07.Interior.DHB - Priority - Install Drywall at Exterior Walls | OverHead | Not Started | 07/27/26 | 08/04/26 | 8.8 | 8.8 |
|
37.5 |
RPL07.SKN.E.01040 |
RPL07.SKIN.East - Secure All Exterior Mounted Boxes and Devices on Skin | IMP System | Not Started | 07/27/26 | 08/07/26 | 12.5 | 12.5 |
|
322.5 |
RPL07.SKN.SSB.01040 |
RPL07.SKIN.SSB - Install Louvers | Glazing, Doors and Ext Devices | Not Started | 07/27/26 | 07/31/26 | 6.2 | 6.2 |
|
258.8 |
RPL07.CON.WP2.08540 |
RPL07.Conn - Ext. GSIDF7X04 - Install Copper, WAPs, Security Camera & Access Control (EY-DH A) | Cabling | Not Started | 07/28/26 | 08/12/26 | 15.0 | 15.0 |
|
362.5 |
RPL07.INT.DHB.01090 |
RPL07.Interior.DHB - Temp Conditions - Install Early Temp Conditions | Temp Conditions | Not Started | 07/28/26 | 07/29/26 | 2.5 | 2.5 |
|
25.0 |
RPL07.INT.DHB.02100 |
RPL07.Interior.DHB - Priority - Install Mechanical Piping | OverHead | Not Started | 07/28/26 | 08/17/26 | 18.8 | 18.8 |
|
36.2 |
RPL07.INT.SSB.02840 |
RPL07.Interior.SSB - Priority - Tape Finish Paint Priority Soffit (Top Out) | Priority Walls and OverHead | Not Started | 07/28/26 | 08/10/26 | 12.5 | 12.5 |
|
141.2 |
RPL07.INT.SSBC.01040 |
RPL07.Interior.SSB-Corridor - Priority - Install Temp Lighting (Show In Model) | Early Priority OH MEPF | Not Started | 07/28/26 | 07/30/26 | 3.8 | 3.8 |
|
40.0 |
RPL07.MCUP.LP1.1880 |
RPL07.MCUP.Loop 1 - Tie-in Mechanical #3 | Tie-Ins Mechanical | Not Started | 07/28/26 | 08/13/26 | 16.2 | 16.2 |
|
90.0 |
RPL07.STR.DHCD.01130 |
RPL07.Structure.DHCD - SOG F/R/P #7 - Grid lines 7-21/7-25 | F/R/P | Not Started | 07/28/26 | 08/03/26 | 6.2 | 6.2 |
|
37.5 |
GCD.RPL07.1020 |
Weather tight SSB and DHA&B | Construction Milestones | Not Started | 07/29/26 | 07/29/26 | 0.0 | 0.0 |
|
306.2 |
RPL07.CFCI.5100 |
Campus - Submittal Review & Approval - Asphalt / Paving | (CFCI) Div. 32 - Asphalt/ Conc. Paving | Not Started | 07/29/26 | 08/25/26 | 25.0 | 25.0 |
|
201.2 |
RPL07.INT.DHA.03400 |
RPL07.Interior.DHA - Temp Conditions - Install Early Temp Conditions | Temp Conditions | Not Started | 07/29/26 | 07/30/26 | 2.5 | 2.5 |
|
23.8 |
RPL07.INT.DHB.01050 |
RPL07.Interior.DHB - Priority - Install FA / Linear heat detection | OverHead | Not Started | 07/29/26 | 08/04/26 | 6.2 | 6.2 |
|
40.0 |
RPL07.INT.DHB.02300 |
RPL07.Interior.DHB - Priority - Install Electrical | OverHead | Not Started | 07/29/26 | 08/17/26 | 17.5 | 17.5 |
|
37.5 |
RPL07.INT.DHC.01030 |
RPL07.Interior.DHC - Priority - Install Fire Sprinkler | Early Priority OH MEPF | Not Started | 07/29/26 | 08/04/26 | 6.2 | 6.2 |
|
130.0 |
RPL07.INT.SSBC.06700 |
RPL07.Interior.SSBC - Priority GL7.04 - (P0) Tape Finish Paint (Both SIdes) | Priority Wall Grid Line 7-04 | Not Started | 07/29/26 | 08/04/26 | 6.2 | 6.2 |
|
92.5 |
ICM.B7.1750 |
[SSDCB2] Room Ready for GS.MDF Module Placement | Construction | Not Started | 07/30/26 | 07/30/26 | 0.0 | 0.0 |
|
305.0 |
ICM.B7.1865 |
[SSDCB2] Delivery of MDF GS.MDF Module (First Delivery) | Construction | Not Started | 07/30/26 | 07/30/26 | 0.0 | 0.0 |
|
108.8 |
RPL.GF.D.N7150.XG |
GS.IDF Hut 2 Install Complete for RPL 7 | Give Milestones (XREFs) | Not Started | 07/30/26 | 07/30/26 | 0.0 | 0.0 |
|
447.5 |
RPL07.EY.ENDC.1410 |
RPL07.EY.DHD.T1 - Install Heating and Cooling Equipment | Tent 1 | Not Started | 07/30/26 | 08/05/26 | 6.2 | 6.2 |
|
41.2 |
RPL07.INT.DHB.02360 |
RPL07.Interior.DHB - Temp Conditions - CC West Duct Work Complete for Temp Conditioning (LVs) | Temp Conditions | Not Started | 07/30/26 | 07/31/26 | 2.5 | 2.5 |
|
25.0 |
RPL07.SKN.DHAB.01130 |
RPL07.SKIN.DHAB - Install Roof System - Install EJ | Roofing | Not Started | 07/30/26 | 07/31/26 | 2.5 | 2.5 |
|
133.8 |
RPL07.SKN.DHCD.01110 |
RPL07.SKIN.DHCD - Install Roof System - Final Roof | Roofing | Not Started | 07/30/26 | 08/14/26 | 15.0 | 15.0 |
|
387.5 |
RPL07.STR.DHAB.01260 |
RPL07.Structure.DHAB - Install SOG Sealer and Cure | F/R/P | Not Started | 07/30/26 | 07/31/26 | 2.5 | 2.5 |
|
66.2 |
DCC.B7.3125 |
[SSDCB2] GS Gear Delivered [DHB] | Connectivity | Not Started | 07/31/26 | 07/31/26 | 0.0 | 0.0 |
|
447.5 |
DCC.B7.3135 |
[SSDCB2] GS Gear Delivered [DHA] | Connectivity | Not Started | 07/31/26 | 07/31/26 | 0.0 | 0.0 |
|
447.5 |
RPL07.CFCI.5690 |
RPL07 - Fabricate / Deliver - Glass / Frames | Glass & Glazing (Alum. Entrances & Curtainwall) | Not Started | 07/31/26 | 10/02/26 | 56.2 | 56.2 |
|
146.2 |
RPL07.CON.WP2.07400 |
RPL07.Conn - Ext. GSIDF7X02 (mCUP yard) - WBS Summary | Ext. IDF Hut - GSIDF7X02 | Not Started | 07/31/26 | 12/10/26 | 113.8 | 113.8 |
|
333.8 |
RPL07.CON.WP2.07420 |
RPL07.Conn - Ext. GSIDF7X02 - Install Infrastructure (Racks, Waterfalls etc.) | Infrastructure | Not Started | 07/31/26 | 08/06/26 | 6.2 | 6.2 |
|
262.5 |
RPL07.INT.DHA.03420 |
RPL07.Interior.DHA - Temp Conditions - CC West Duct Work Complete for Temp Conditioning (LVs) | Temp Conditions | Not Started | 07/31/26 | 08/03/26 | 2.5 | 2.5 |
|
23.8 |
RPL07.INT.DHB.01040 |
RPL07.Interior.DHB - Priority - Install Temp Lighting | Early Priority OH MEPF | Not Started | 07/31/26 | 08/04/26 | 3.8 | 3.8 |
|
40.0 |
RPL07.INT.SSB.03220 |
RPL07.Interior.SSB - Priority - Install Fire Safing/ Seal all Penetrations through Soffit (Highside OH space) | Priority Walls and OverHead | Not Started | 07/31/26 | 08/06/26 | 6.2 | 6.2 |
|
150.0 |
RPL07.INT.SSBC.02180 |
RPL07.Interior.SSBC - Priority - Install Plumbing (Highside OH space) | Priority Walls & Overhead | Not Started | 07/31/26 | 08/06/26 | 6.2 | 6.2 |
|
90.0 |
RPL07.INT.SSBC.02200 |
RPL07.Interior.SSBC - Priority - Install Mechanical Piping/ Refrigerant (Highside OH space) | Priority Walls & Overhead | Not Started | 07/31/26 | 08/06/26 | 6.2 | 6.2 |
|
90.0 |
RPL07.INT.SSBC.03300 |
RPL07.Interior.SSBC - Priority - Install FA/ VESDA/ hangers & Heat Trace (Highside OH space) | Priority Walls & Overhead | Not Started | 07/31/26 | 08/06/26 | 6.2 | 6.2 |
|
90.0 |
RPL07.MCUP.LP1.1620 |
RPL07.MCUP.Loop 1 - Set mCUPs XXMY.MCUP.04 (1 per 5 days) | OFE | Not Started | 07/31/26 | 08/06/26 | 6.2 | 6.2 |
|
77.5 |
RPL07.MCUP.LP1.1640 |
RPL07.MCUP.Loop 1 - Set Electrical Skids #3 | OFE | Not Started | 07/31/26 | 08/03/26 | 2.5 | 2.5 |
|
85.0 |
RPL07.MCUP.LP1.1860 |
RPL07.MCUP.Loop 1 - Tie-in Electrical #3 | Tie-Ins Electrical | Not Started | 07/31/26 | 08/13/26 | 12.5 | 12.5 |
|
83.8 |
RPL07.MCUP.LP2.1300 |
RPL07.MCUP.Loop 2 - Set GS.IDF Hut (1x GS.IDF) 7X03 (ROJ05.13.26) | OFE | Not Started | 07/31/26 | 08/06/26 | 6.2 | 6.2 |
|
215.0 |
RPL07.EY.ENDC.1730 |
RPL07.EY.DHD.T2 - Install Overhead Doors | Tent 2 | Not Started | 08/03/26 | 08/07/26 | 6.2 | 6.2 |
|
40.0 |
RPL07.EY.ENDC.1750 |
RPL07.EY.DHD.T2 - Install Tent Fit-out | Tent 2 | Not Started | 08/03/26 | 08/14/26 | 12.5 | 12.5 |
|
50.0 |
RPL07.INT.DHA.01080 |
RPL07.Interior.DHA - OFE - WBS Summary | OFE/MOFE & CFCI | Not Started | 08/03/26 | 02/09/27 | 162.5 | 162.5 |
|
46.2 |
RPL07.INT.DHA.03980 |
RPL07.Interior.DHA - CFCI - Pre Set 16"" FW Pipe | OFE/MOFE & CFCI | Not Started | 08/03/26 | 08/14/26 | 12.5 | 12.5 |
|
81.2 |
RPL07.INT.DHB.01160 |
RPL07.Interior.DHB - OFE - WBS Summary | OFE/MOFE & CFCI | Not Started | 08/03/26 | 01/26/27 | 150.0 | 150.0 |
|
37.5 |
RPL07.INT.DHB.02900 |
RPL07.Interior.DHB - CFCI - Pre Set 16"" FW Pipe | OFE/MOFE & CFCI | Not Started | 08/03/26 | 08/14/26 | 12.5 | 12.5 |
|
81.2 |
RPL07.MCUP.LP2.2120 |
RPL07.MCUP.Loop 2 - Set Facility Water Pipe Rack (mCUP6) | OFE | Not Started | 08/03/26 | 08/14/26 | 12.5 | 12.5 |
|
220.0 |
RPL07.SKN.SSB.01060 |
RPL07.SKIN.SSB - Install Awning over Doors | Glazing, Doors and Ext Devices | Not Started | 08/03/26 | 08/07/26 | 6.2 | 6.2 |
|
266.2 |
RPL07.EY.DHB.01130 |
RPL07.EY.DHB - Cure (High Early Mix) | Foundations | Not Started | 08/04/26 | 08/10/26 | 8.8 | 8.8 |
|
78.8 |
RPL07.EY.DHD.01010 |
RPL07.EY.DHD - Install F/R/P Equipment Pads - 1-10 (Grid 6-17/6-28) (12'' Larger For Tolerance) | Foundations | Not Started | 08/04/26 | 08/24/26 | 18.8 | 18.8 |
|
171.2 |
RPL07.EY.DHD.01020 |
RPL07.EY.DHD - Install Foundations - WBS Summary | Foundations | Not Started | 08/04/26 | 05/18/27 | 246.2 | 246.2 |
|
95.0 |