Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL07 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:16 PM
· 5237 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
0
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL07.EY.SSB.01210 |
RPL07.EY.SSB - Install LD Electrical In walls | Loading Dock | Not Started | 08/04/26 | 08/07/26 | 5.0 | 5.0 |
|
206.2 |
RPL07.EY.SSB.01220 |
RPL07.EY.SSB - Install LD French Drain (Not Designed) | Loading Dock | Not Started | 08/04/26 | 08/07/26 | 5.0 | 5.0 |
|
216.2 |
RPL07.INT.CTRC.01020 |
RPL07.Interior.Center-Corridor - Install Priority OH, Walls, OFE and Fitout - WBS Summary | Center Corridor | Not Started | 08/04/26 | 04/28/27 | 228.8 | 228.8 |
|
56.2 |
RPL07.INT.CTRC.03460 |
RPL07.Interior.Center-Corridor - Priority - Priority - WBS Summary | Priority Walls & Overhead | Not Started | 08/04/26 | 10/16/26 | 66.2 | 66.2 |
|
66.2 |
RPL07.INT.CTRC.1020 |
RPL07.Interior.Center-Corridor - Priority - Install Priority Soffit for Wall Tie-Ins/ Rock & HoW & Draft Blanket | Priority Walls & Overhead | Not Started | 08/04/26 | 08/10/26 | 6.2 | 6.2 |
|
37.5 |
RPL07.INT.CTRC.7740 |
RPL07.Interior.Center-Corridor - Priority - Install IMP Exterior Inwall Rough-In | Priority Walls & Overhead | Not Started | 08/04/26 | 08/10/26 | 6.2 | 6.2 |
|
43.8 |
RPL07.INT.DHA.03460 |
RPL07.Interior.DHA - Temp Conditions - Temp Conditioning Achieved & Acclimated for West of CC (SSB/DHB/DHA) | Temp Conditions | Not Started | 08/04/26 | 08/10/26 | 6.2 | 6.2 |
|
23.8 |
RPL07.MCUP.LP1.1780 |
RPL07.MCUP.Loop 1 - Tie-in EPMS #3 | Tie-Ins EPMS | Not Started | 08/04/26 | 08/13/26 | 10.0 | 10.0 |
|
83.8 |
RPL07.MCUP.LP1.1800 |
RPL07.MCUP.Loop 1 - Tie-in BMS #3 | Tie-Ins BMS | Not Started | 08/04/26 | 08/13/26 | 10.0 | 10.0 |
|
90.0 |
RPL07.MCUP.LP1.1980 |
RPL07.MCUP.Loop 1 - Tie-in Mechanical #4 | Tie-Ins Mechanical | Not Started | 08/04/26 | 08/20/26 | 16.2 | 16.2 |
|
83.8 |
RPL07.STR.DHCD.01140 |
RPL07.Structure.DHCD - SOG F/R/P #8 - Grid lines 7-25/7-28 | F/R/P | Not Started | 08/04/26 | 08/10/26 | 6.2 | 6.2 |
|
100.0 |
RPL07.CFCI.4700 |
RPL07 - Submittals Review & Approval - Security System | (CFCI) Div. 28 - Security Syst. | Not Started | 08/05/26 | 09/01/26 | 25.0 | 25.0 |
|
197.5 |
RPL07.CFCI.4820 |
Campus - Submittals Prep & Submit for Review - Asphalt / Paving | (CFCI) Div. 32 - Asphalt/ Conc. Paving | Not Started | 08/05/26 | 08/25/26 | 18.8 | 18.8 |
|
201.2 |
RPL07.INT.DHA.01040 |
RPL07.Interior.DHA - Priority - Install Temp Lighting | Early Priority OH MEPF | Not Started | 08/05/26 | 08/07/26 | 3.8 | 3.8 |
|
115.0 |
RPL07.INT.DHA.02140 |
RPL07.Interior.DHA - Priority - Install Plumbing | OverHead | Not Started | 08/05/26 | 08/11/26 | 6.2 | 6.2 |
|
47.5 |
RPL07.INT.DHB.01100 |
RPL07.Interior.DHB - Priority - Install Temp Doors Frame Hardware | OverHead | Not Started | 08/05/26 | 08/07/26 | 3.8 | 3.8 |
|
40.0 |
RPL07.INT.ENDC.1040 |
RPL07.Interior.End-Corridor - Priority - Install Fire Sprinkler (Highside OH space) | Early Priority OH MEPF | Not Started | 08/05/26 | 08/07/26 | 3.8 | 3.8 |
|
130.0 |
RPL.07.D.74120.XG |
Ready for MV Cable Pull mCUP - Loop#1 (Qty 4)* | Give Milestones (XREFs) | Not Started | 08/06/26 | 08/06/26 | 0.0 | 0.0 |
|
441.2 |
RPL.GF.D.N7160.XG |
GS.IDF Hut 3 Install Complete for RPL 7 | Give Milestones (XREFs) | Not Started | 08/06/26 | 08/06/26 | 0.0 | 0.0 |
|
441.2 |
RPL07.EY.ENDC.1390 |
RPL07.EY.DHD.T1 - Install Panels | Tent 1 | Not Started | 08/06/26 | 08/12/26 | 6.2 | 6.2 |
|
41.2 |
RPL07.EY.ENDC.1490 |
RPL07.EY.DHD.T1 - Install Mechanical Tie-ins | Tent 1 | Not Started | 08/06/26 | 08/13/26 | 7.5 | 7.5 |
|
43.8 |
RPL07.LOG.1040 |
MCUP 500 Ton Crane Movement 2 | 300 Ton Crane | Not Started | 08/06/26 | 08/06/26 | 0.0 | 0.0 |
|
202.5 |
RPL07.CON.WP2.07460 |
RPL07.Conn - Ext. GSIDF7X02 - Install Copper, WAPs, Security Camera & Access Control | Cabling | Not Started | 08/07/26 | 08/24/26 | 15.0 | 15.0 |
|
262.5 |
RPL07.CON.WP2.07600 |
RPL07.Conn - Ext. GSIDF7X03 (mCUP yard) - WBS Summary | Ext. IDF Hut - GSIDF7X03 | Not Started | 08/07/26 | 12/10/26 | 107.5 | 107.5 |
|
333.8 |
RPL07.CON.WP2.08400 |
RPL07.Conn - Ext. GSIDF7X03 - Install Infrastructure (Racks, Waterfalls etc.) | Infrastructure | Not Started | 08/07/26 | 08/13/26 | 6.2 | 6.2 |
|
256.2 |
RPL07.INT.SBC.03240 |
RPL07.Interior.SSB-Corridor - Frame Balance of Wall | Balance of Walls & Overhead | Not Started | 08/07/26 | 08/13/26 | 6.2 | 6.2 |
|
90.0 |
RPL07.INT.SBC.03260 |
RPL07.Interior.SSB-Corridor - Balace Of Wall (ERAD, Maintance, Network infra, Spoke, Bathroom, etc) - WBS Summary | Balance of Walls & Overhead | Not Started | 08/07/26 | 02/01/27 | 150.0 | 150.0 |
|
87.5 |
RPL07.INT.SSBC.03320 |
RPL07.Interior.SSBC - Priority - Install Fire Safing/ Seal Penetrations through Soffit (Highside OH space) | Priority Walls & Overhead | Not Started | 08/07/26 | 08/11/26 | 3.8 | 3.8 |
|
90.0 |
RPL07.INT.SSBC.03340 |
RPL07.Interior.SSBC - Priority - Fixed Draft Smoke Curtains Patching | Priority Walls & Overhead | Not Started | 08/07/26 | 08/11/26 | 3.8 | 3.8 |
|
90.0 |
RPL07.MCUP.LP1.1680 |
RPL07.MCUP.Loop 1 - Set Electrical Skids #4 | OFE | Not Started | 08/07/26 | 08/10/26 | 2.5 | 2.5 |
|
81.2 |
RPL07.MCUP.LP1.1960 |
RPL07.MCUP.Loop 1 - Tie-in Electrical #4 | Tie-Ins Electrical | Not Started | 08/07/26 | 08/20/26 | 12.5 | 12.5 |
|
77.5 |
RPL07.MCUP.LP2.1280 |
RPL07.MCUP.Loop 2 - Set mCUPs XXMY.MCUP.05 (1 per 5 days) | OFE | Not Started | 08/07/26 | 08/13/26 | 6.2 | 6.2 |
|
202.5 |
ICM.B7.1855 |
[SSDCB2] Delivery of MES - Multi Trade Rack (First Delivery) | Construction | Not Started | 08/10/26 | 08/10/26 | 0.0 | 0.0 |
|
86.2 |
RPL.07.D.73750.XG |
RMUs Set - mCUP Loop 1 | Give Milestones (XREFs) | Not Started | 08/10/26 | 08/10/26 | 0.0 | 0.0 |
|
438.8 |
RPL07.EY.ENDC.1710 |
RPL07.EY.DHD.T2 - Install Heating and Cooling Equipment | Tent 2 | Not Started | 08/10/26 | 08/14/26 | 6.2 | 6.2 |
|
40.0 |
RPL07.EY.SSB.01230 |
RPL07.EY.SSB - Install LD F/R/P Loading Dock Walls | Loading Dock | Not Started | 08/10/26 | 08/19/26 | 10.0 | 10.0 |
|
206.2 |
RPL07.INT.CTRC.1060 |
RPL07.Interior.Center-Corridor - Priority - Install Temp Lighting (Show In Model) | Early Priority OH MEPF | Not Started | 08/10/26 | 08/12/26 | 3.8 | 3.8 |
|
115.0 |
RPL07.INT.DHB.01120 |
RPL07.Interior.DHB - Priority - Install Security | OverHead | Not Started | 08/10/26 | 08/14/26 | 6.2 | 6.2 |
|
40.0 |
RPL07.SKN.DHCD.01000 |
RPL07.SKIN.DHCD - Install Temp Doors | Glazing, Doors and Ext Devices | Not Started | 08/10/26 | 08/11/26 | 2.5 | 2.5 |
|
322.5 |
RPL07.SKN.DHCD.01020 |
RPL07.SKIN.DHCD - Install Windows, Doors, Louvers and Ext Devices - WBS Summary | Glazing, Doors and Ext Devices | Not Started | 08/10/26 | 05/17/27 | 240.0 | 240.0 |
|
116.2 |
RPL07.SKN.SSB.01120 |
RPL07.SKIN.SSB - Install Scupper and Downspouts | Glazing, Doors and Ext Devices | Not Started | 08/10/26 | 08/14/26 | 6.2 | 6.2 |
|
266.2 |
RPL07.EY.SSB.01160 |
RPL07.EY.SSB - Install Electrical Tie-ins (include penetration detail) | Tie-ins | Not Started | 08/11/26 | 09/08/26 | 25.0 | 25.0 |
|
70.0 |
RPL07.EY.SSB.01170 |
RPL07.EY.SSB - Install Mechanical Main (include penetration detail) | Tie-ins | Not Started | 08/11/26 | 08/31/26 | 18.8 | 18.8 |
|
63.8 |
RPL07.INT.CTRC.1000 |
RPL07.Interior.Center-Corridor - Priority - Install Unistruts & Hangers (All Trades) Both side of Corridor Wall | Priority Walls & Overhead | Not Started | 08/11/26 | 08/17/26 | 6.2 | 6.2 |
|
37.5 |
RPL07.INT.SSB.01050 |
RPL07.Interior.SSB - Priority - (P1) Frame Walls (Frame full height Walls) | Priority Wall - P0 | Not Started | 08/11/26 | 08/17/26 | 6.2 | 6.2 |
|
141.2 |
RPL07.INT.SSB.06860 |
RPL07.Interior.SSB - Priority - (P1) Frame Remaining Walls | Priority Wall - P0 | Not Started | 08/11/26 | 08/13/26 | 3.8 | 3.8 |
|
192.5 |
RPL07.MCUP.LP1.1900 |
RPL07.MCUP.Loop 1 - Tie-in EPMS #4 | Tie-Ins EPMS | Not Started | 08/11/26 | 08/20/26 | 10.0 | 10.0 |
|
77.5 |
RPL07.MCUP.LP1.1940 |
RPL07.MCUP.Loop 1 - Tie-in BMS #4 | Tie-Ins BMS | Not Started | 08/11/26 | 08/20/26 | 10.0 | 10.0 |
|
83.8 |
RPL07.STR.DHCD.01150 |
RPL07.Structure.DHCD - Zone SOG Cure | F/R/P | Not Started | 08/11/26 | 08/17/26 | 8.8 | 8.8 |
|
146.2 |
RPL07.WA.OFE.01000 |
RPL07.WA - Weather Allowance - FDN to OFE | Weather Allowance | Not Started | 08/11/26 | 08/26/26 | 20.0 | 20.0 |
|
33.8 |
RPL07.SKN.DHCD.01140 |
RPL07.SKIN.DHCD - Install Blocking of Canopy & Backing of Exterior Wall *REMOVE FROM DRYWALL* | Glazing, Doors and Ext Devices | Not Started | 08/12/26 | 08/18/26 | 6.2 | 6.2 |
|
322.5 |
ICM.B7.1845 |
[SSDCB2] Delivery of FSHAC - Hot Aisle Containment (First Delivery) | Construction | Not Started | 08/13/26 | 08/13/26 | 0.0 | 0.0 |
|
46.2 |
RPL07.CFCI.4920 |
RPL07 - Fabricate / Deliver - Security System | (CFCI) Div. 28 - Security Syst. | Not Started | 08/13/26 | 10/08/26 | 50.0 | 50.0 |
|
197.5 |
RPL07.CON.WP2.08560 |
RPL07.Conn - Ext. GSIDF7X04 - Install Copper, WAPs, Security Camera & Access Control (EY-DH C) | Cabling | Not Started | 08/13/26 | 08/28/26 | 15.0 | 15.0 |
|
362.5 |
RPL07.EY.ENDC.1470 |
RPL07.EY.DHD.T1 - Install Electrical Tie-ins | Tent 1 | Not Started | 08/13/26 | 08/17/26 | 3.8 | 3.8 |
|
41.2 |
RPL07.EY.SSB.01240 |
RPL07.EY.SSB - Install BMS/EPMS Tie-ins | Tie-ins | Not Started | 08/13/26 | 09/02/26 | 18.8 | 18.8 |
|
73.8 |
RPL07.INT.DHD.01040 |
RPL07.Interior.DHD - Priority - Install Temp Lighting | Early Priority OH MEPF | Not Started | 08/13/26 | 08/17/26 | 3.8 | 3.8 |
|
115.0 |
RPL07.MCUP.LP2.1240 |
RPL07.MCUP.Loop 2 - Set MTRs (4 per day) | OFE | Not Started | 08/13/26 | 08/14/26 | 2.5 | 2.5 |
|
210.0 |
RPL07.CON.WP2.08520 |
RPL07.Conn - Ext. GSIDF7X03 - Install Copper, WAPs, Security Camera & Access Control | Cabling | Not Started | 08/14/26 | 08/31/26 | 15.0 | 15.0 |
|
256.2 |
RPL07.INT.DHC.01010 |
RPL07.Interior.DHC - Priority - Install Duct | Early Priority OH MEPF | Not Started | 08/14/26 | 08/19/26 | 5.0 | 5.0 |
|
191.2 |
RPL07.INT.DHD.01010 |
RPL07.Interior.DHD - Priority - Install Duct | Early Priority OH MEPF | Not Started | 08/14/26 | 08/19/26 | 5.0 | 5.0 |
|
191.2 |
RPL07.INT.SBC.03420 |
RPL07.Interior.SSB-Corridor - BoW - Install Door Frames | Balance of Walls & Overhead | Not Started | 08/14/26 | 08/20/26 | 6.2 | 6.2 |
|
115.0 |
RPL07.INT.SBC.05800 |
RPL07.Interior.SSB-Corridor - BoW - Install Mechanical Piping/ Refrigerant Lowside OH and in-wall | Balance of Walls & Overhead | Not Started | 08/14/26 | 08/25/26 | 10.0 | 10.0 |
|
90.0 |
RPL07.INT.SSB.06880 |
RPL07.Interior.SSB - Priority - (P1) Install Remaining MEP In-Wall/Backing | Priority Wall - P0 | Not Started | 08/14/26 | 08/17/26 | 2.5 | 2.5 |
|
192.5 |
RPL07.MCUP.LP1.1820 |
RPL07.MCUP.Loop 1 - Install Hardscape and Landscape - WBS Summary | Hardscape and Landscape | Not Started | 08/14/26 | 10/16/26 | 56.2 | 56.2 |
|
378.8 |
RPL07.MCUP.LP1.1840 |
RPL07.MCUP.Loop 1 - Install Sleeves MEPL | Hardscape and Landscape | Not Started | 08/14/26 | 08/20/26 | 6.2 | 6.2 |
|
378.8 |
RPL07.MCUP.LP1.2020 |
RPL07.MCUP.Loop 1 - Tie-in - MV Loop 2 L2 Checklist Completion | Tie-ins | Not Started | 08/14/26 | 08/27/26 | 12.5 | 12.5 |
|
77.5 |
RPL07.MCUP.LP1.2080 |
RPL07.MCUP.Loop 1 - Tie-in - Mechanical L2 Checklist Completion | Tie-ins | Not Started | 08/14/26 | 08/27/26 | 12.5 | 12.5 |
|
83.8 |
RPL07.MCUP.LP2.1360 |
RPL07.MCUP.Loop 2 - Set mCUPs XXMY.MCUP.06 (1 per 5 days) | OFE | Not Started | 08/14/26 | 08/20/26 | 6.2 | 6.2 |
|
202.5 |
RPL07.MCUP.LP2.1400 |
RPL07.MCUP.Loop 2 - Tie-ins - WBS Summary | Tie-ins | Not Started | 08/14/26 | 09/18/26 | 31.2 | 31.2 |
|
356.2 |
RPL07.MCUP.LP2.1420 |
RPL07.MCUP.Loop 2 - Tie-in SD, DW | Tie-ins | Not Started | 08/14/26 | 09/03/26 | 18.8 | 18.8 |
|
368.8 |
RPL07.MCUP.LP2.1440 |
RPL07.MCUP.Loop 2 - Set Electrical Skids #5 | OFE | Not Started | 08/14/26 | 08/17/26 | 2.5 | 2.5 |
|
210.0 |
RPL07.MCUP.LP2.1560 |
RPL07.MCUP.Loop 2 - Tie-in Electrical - WBS Summary | Tie-Ins Electrical | Not Started | 08/14/26 | 09/03/26 | 18.8 | 18.8 |
|
202.5 |
RPL07.MCUP.LP2.1620 |
RPL07.MCUP.Loop 2 - Tie-in Electrical #5 | Tie-Ins Electrical | Not Started | 08/14/26 | 08/27/26 | 12.5 | 12.5 |
|
208.8 |
RPL07.EY.ENDC.1690 |
RPL07.EY.DHD.T2 - Install Panels | Tent 2 | Not Started | 08/17/26 | 08/21/26 | 6.2 | 6.2 |
|
40.0 |
RPL07.EY.ENDC.1790 |
RPL07.EY.DHD.T2 - Install Mechanical Tie-ins | Tent 2 | Not Started | 08/17/26 | 08/24/26 | 7.5 | 7.5 |
|
42.5 |
RPL07.INT.DHB.01130 |
RPL07.Interior.DHB - Priority - Install Controls / EPMS / BMS | OverHead | Not Started | 08/17/26 | 08/20/26 | 5.0 | 5.0 |
|
40.0 |
RPL07.MCUP.LP2.1580 |
RPL07.MCUP.Loop 2 - Tie-in Mechanical - WBS Summary | Tie-Ins Mechanical | Not Started | 08/17/26 | 09/09/26 | 21.2 | 21.2 |
|
205.0 |
RPL07.MCUP.LP2.1600 |
RPL07.MCUP.Loop 1 - Tie-in Mechanical #5 | Tie-Ins Mechanical | Not Started | 08/17/26 | 09/02/26 | 16.2 | 16.2 |
|
210.0 |
PRE.FA.1300 |
Non-Critical Trade Buyout - Final Agreement | Trade Partner Final Agreement | Not Started | 08/18/26 | 08/18/26 | 0.0 | 0.0 |
|
117.5 |
RPL07.EY.ENDC.1510 |
RPL07.EY.DHD.T1 - Temp Conditioning Startup and Available | Tent 1 | Not Started | 08/18/26 | 08/19/26 | 2.5 | 2.5 |
|
41.2 |
RPL07.INT.CTRC.1920 |
RPL07.Interior.Center-Corridor - Priority - Install Drywall at Exterior Walls | Priority Walls & Overhead | Not Started | 08/18/26 | 08/24/26 | 6.2 | 6.2 |
|
37.5 |
RPL07.INT.DHA.01050 |
RPL07.Interior.DHA - Priority - Install FA / Linear heat detection | OverHead | Not Started | 08/18/26 | 08/24/26 | 6.2 | 6.2 |
|
37.5 |
RPL07.INT.DHA.02160 |
RPL07.Interior.DHA - Priority - Install Mechanical Piping | OverHead | Not Started | 08/18/26 | 09/08/26 | 18.8 | 18.8 |
|
36.2 |
RPL07.INT.DHA.02320 |
RPL07.Interior.DHA - Priority - Install Electrical | OverHead | Not Started | 08/18/26 | 09/08/26 | 18.8 | 18.8 |
|
37.5 |
RPL07.INT.DHC.01040 |
RPL07.Interior.DHC - Priority - Install Temp Lighting | Early Priority OH MEPF | Not Started | 08/18/26 | 08/20/26 | 3.8 | 3.8 |
|
115.0 |
RPL07.INT.DHD.01000 |
RPL07.Interior.DHD - Priority OH - WBS Summary | OverHead | Not Started | 08/18/26 | 10/06/26 | 43.8 | 43.8 |
|
331.2 |
RPL07.INT.DHD.01020 |
RPL07.Interior.DHD - Install Priority OH, Walls, OFE and Tie-ins - WBS Summary | DHD | Not Started | 08/18/26 | 05/19/27 | 235.0 | 235.0 |
|
140.0 |
RPL07.INT.DHD.01700 |
RPL07.Interior.DHD - Priority - Install Draft Curtains (#2 - 3 Days Each) | OverHead | Not Started | 08/18/26 | 08/25/26 | 7.5 | 7.5 |
|
112.5 |
RPL07.INT.DHD.01980 |
RPL07.Interior.DHD - Priority - Install Unistruts & Hangers (All Trades) Both side of Corridor Wall | OverHead | Not Started | 08/18/26 | 08/24/26 | 6.2 | 6.2 |
|
96.2 |
RPL07.INT.DHD.02250 |
RPL07.Interior.DHD - Priority - Install IMP Exterior Inwall Rough-In | OverHead | Not Started | 08/18/26 | 08/24/26 | 6.2 | 6.2 |
|
96.2 |
RPL07.INT.SSB.01140 |
RPL07.Interior.SSB - Loading Dock and Storage - Frame Walls | Loading Dock and Storage | Not Started | 08/18/26 | 08/27/26 | 10.0 | 10.0 |
|
182.5 |
RPL07.INT.SSB.01150 |
RPL07.Interior.SSB - BoW - BoW - Framing Balance of Wall | Balance of Walls and OverHead | Not Started | 08/18/26 | 08/24/26 | 6.2 | 6.2 |
|
141.2 |
RPL07.INT.SSB.01160 |
RPL07.Interior.SSB - BoW - Balace Of Wall (ERAD, Maintance, Network infra, Spoke, Bathroom, etc) - WBS Summary | Balance of Walls and OverHead | Not Started | 08/18/26 | 04/08/27 | 198.8 | 198.8 |
|
77.5 |
RPL07.INT.SSB.01170 |
RPL07.Interior.SSB - Loading Dock and Storage - WBS Summary | Loading Dock and Storage | Not Started | 08/18/26 | 02/09/27 | 148.8 | 148.8 |
|
127.5 |
RPL07.INT.SSB.06800 |
RPL07.Interior.SSB - Priority - (P1) Install MEP In-Wall/Backing | Priority Wall - P0 | Not Started | 08/18/26 | 08/21/26 | 5.0 | 5.0 |
|
185.0 |
RPL07.INT.SSB.06900 |
RPL07.Interior.SSB - Priority - (P1) Remaining Wall Hang Drywall (Both Sides) | Priority Wall - P0 | Not Started | 08/18/26 | 08/20/26 | 3.8 | 3.8 |
|
192.5 |
RPL07.MCUP.LP2.1680 |
RPL07.MCUP.Loop 2 - Tie-in EPMS - WBS Summary | Tie-Ins EPMS | Not Started | 08/18/26 | 09/03/26 | 16.2 | 16.2 |
|
202.5 |
RPL07.MCUP.LP2.1700 |
RPL07.MCUP.Loop 2 - Tie-in EPMS #5 | Tie-Ins EPMS | Not Started | 08/18/26 | 08/27/26 | 10.0 | 10.0 |
|
208.8 |
RPL07.STR.DHCD.01210 |
RPL07.Structure.DHCD - Moisture requirements for floor Sealer | F/R/P | Not Started | 08/18/26 | 08/24/26 | 8.8 | 8.8 |
|
166.2 |