Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL07 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:16 PM · 5237 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
0
Completed
0
In Progress
0
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL07.EY.SSB.01210 RPL07.EY.SSB - Install LD Electrical In walls Loading Dock Not Started 08/04/26 08/07/26 5.0 5.0
0%
206.2
RPL07.EY.SSB.01220 RPL07.EY.SSB - Install LD French Drain (Not Designed) Loading Dock Not Started 08/04/26 08/07/26 5.0 5.0
0%
216.2
RPL07.INT.CTRC.01020 RPL07.Interior.Center-Corridor - Install Priority OH, Walls, OFE and Fitout - WBS Summary Center Corridor Not Started 08/04/26 04/28/27 228.8 228.8
0%
56.2
RPL07.INT.CTRC.03460 RPL07.Interior.Center-Corridor - Priority - Priority - WBS Summary Priority Walls & Overhead Not Started 08/04/26 10/16/26 66.2 66.2
0%
66.2
RPL07.INT.CTRC.1020 RPL07.Interior.Center-Corridor - Priority - Install Priority Soffit for Wall Tie-Ins/ Rock & HoW & Draft Blanket Priority Walls & Overhead Not Started 08/04/26 08/10/26 6.2 6.2
0%
37.5
RPL07.INT.CTRC.7740 RPL07.Interior.Center-Corridor - Priority - Install IMP Exterior Inwall Rough-In Priority Walls & Overhead Not Started 08/04/26 08/10/26 6.2 6.2
0%
43.8
RPL07.INT.DHA.03460 RPL07.Interior.DHA - Temp Conditions - Temp Conditioning Achieved & Acclimated for West of CC (SSB/DHB/DHA) Temp Conditions Not Started 08/04/26 08/10/26 6.2 6.2
0%
23.8
RPL07.MCUP.LP1.1780 RPL07.MCUP.Loop 1 - Tie-in EPMS #3 Tie-Ins EPMS Not Started 08/04/26 08/13/26 10.0 10.0
0%
83.8
RPL07.MCUP.LP1.1800 RPL07.MCUP.Loop 1 - Tie-in BMS #3 Tie-Ins BMS Not Started 08/04/26 08/13/26 10.0 10.0
0%
90.0
RPL07.MCUP.LP1.1980 RPL07.MCUP.Loop 1 - Tie-in Mechanical #4 Tie-Ins Mechanical Not Started 08/04/26 08/20/26 16.2 16.2
0%
83.8
RPL07.STR.DHCD.01140 RPL07.Structure.DHCD - SOG F/R/P #8 - Grid lines 7-25/7-28 F/R/P Not Started 08/04/26 08/10/26 6.2 6.2
0%
100.0
RPL07.CFCI.4700 RPL07 - Submittals Review & Approval - Security System (CFCI) Div. 28 - Security Syst. Not Started 08/05/26 09/01/26 25.0 25.0
0%
197.5
RPL07.CFCI.4820 Campus - Submittals Prep & Submit for Review - Asphalt / Paving (CFCI) Div. 32 - Asphalt/ Conc. Paving Not Started 08/05/26 08/25/26 18.8 18.8
0%
201.2
RPL07.INT.DHA.01040 RPL07.Interior.DHA - Priority - Install Temp Lighting Early Priority OH MEPF Not Started 08/05/26 08/07/26 3.8 3.8
0%
115.0
RPL07.INT.DHA.02140 RPL07.Interior.DHA - Priority - Install Plumbing OverHead Not Started 08/05/26 08/11/26 6.2 6.2
0%
47.5
RPL07.INT.DHB.01100 RPL07.Interior.DHB - Priority - Install Temp Doors Frame Hardware OverHead Not Started 08/05/26 08/07/26 3.8 3.8
0%
40.0
RPL07.INT.ENDC.1040 RPL07.Interior.End-Corridor - Priority - Install Fire Sprinkler (Highside OH space) Early Priority OH MEPF Not Started 08/05/26 08/07/26 3.8 3.8
0%
130.0
RPL.07.D.74120.XG Ready for MV Cable Pull mCUP - Loop#1 (Qty 4)* Give Milestones (XREFs) Not Started 08/06/26 08/06/26 0.0 0.0
0%
441.2
RPL.GF.D.N7160.XG GS.IDF Hut 3 Install Complete for RPL 7 Give Milestones (XREFs) Not Started 08/06/26 08/06/26 0.0 0.0
0%
441.2
RPL07.EY.ENDC.1390 RPL07.EY.DHD.T1 - Install Panels Tent 1 Not Started 08/06/26 08/12/26 6.2 6.2
0%
41.2
RPL07.EY.ENDC.1490 RPL07.EY.DHD.T1 - Install Mechanical Tie-ins Tent 1 Not Started 08/06/26 08/13/26 7.5 7.5
0%
43.8
RPL07.LOG.1040 MCUP 500 Ton Crane Movement 2 300 Ton Crane Not Started 08/06/26 08/06/26 0.0 0.0
0%
202.5
RPL07.CON.WP2.07460 RPL07.Conn - Ext. GSIDF7X02 - Install Copper, WAPs, Security Camera & Access Control Cabling Not Started 08/07/26 08/24/26 15.0 15.0
0%
262.5
RPL07.CON.WP2.07600 RPL07.Conn - Ext. GSIDF7X03 (mCUP yard) - WBS Summary Ext. IDF Hut - GSIDF7X03 Not Started 08/07/26 12/10/26 107.5 107.5
0%
333.8
RPL07.CON.WP2.08400 RPL07.Conn - Ext. GSIDF7X03 - Install Infrastructure (Racks, Waterfalls etc.) Infrastructure Not Started 08/07/26 08/13/26 6.2 6.2
0%
256.2
RPL07.INT.SBC.03240 RPL07.Interior.SSB-Corridor - Frame Balance of Wall Balance of Walls & Overhead Not Started 08/07/26 08/13/26 6.2 6.2
0%
90.0
RPL07.INT.SBC.03260 RPL07.Interior.SSB-Corridor - Balace Of Wall (ERAD, Maintance, Network infra, Spoke, Bathroom, etc) - WBS Summary Balance of Walls & Overhead Not Started 08/07/26 02/01/27 150.0 150.0
0%
87.5
RPL07.INT.SSBC.03320 RPL07.Interior.SSBC - Priority - Install Fire Safing/ Seal Penetrations through Soffit (Highside OH space) Priority Walls & Overhead Not Started 08/07/26 08/11/26 3.8 3.8
0%
90.0
RPL07.INT.SSBC.03340 RPL07.Interior.SSBC - Priority - Fixed Draft Smoke Curtains Patching Priority Walls & Overhead Not Started 08/07/26 08/11/26 3.8 3.8
0%
90.0
RPL07.MCUP.LP1.1680 RPL07.MCUP.Loop 1 - Set Electrical Skids #4 OFE Not Started 08/07/26 08/10/26 2.5 2.5
0%
81.2
RPL07.MCUP.LP1.1960 RPL07.MCUP.Loop 1 - Tie-in Electrical #4 Tie-Ins Electrical Not Started 08/07/26 08/20/26 12.5 12.5
0%
77.5
RPL07.MCUP.LP2.1280 RPL07.MCUP.Loop 2 - Set mCUPs XXMY.MCUP.05 (1 per 5 days) OFE Not Started 08/07/26 08/13/26 6.2 6.2
0%
202.5
ICM.B7.1855 [SSDCB2] Delivery of MES - Multi Trade Rack (First Delivery) Construction Not Started 08/10/26 08/10/26 0.0 0.0
0%
86.2
RPL.07.D.73750.XG RMUs Set - mCUP Loop 1 Give Milestones (XREFs) Not Started 08/10/26 08/10/26 0.0 0.0
0%
438.8
RPL07.EY.ENDC.1710 RPL07.EY.DHD.T2 - Install Heating and Cooling Equipment Tent 2 Not Started 08/10/26 08/14/26 6.2 6.2
0%
40.0
RPL07.EY.SSB.01230 RPL07.EY.SSB - Install LD F/R/P Loading Dock Walls Loading Dock Not Started 08/10/26 08/19/26 10.0 10.0
0%
206.2
RPL07.INT.CTRC.1060 RPL07.Interior.Center-Corridor - Priority - Install Temp Lighting (Show In Model) Early Priority OH MEPF Not Started 08/10/26 08/12/26 3.8 3.8
0%
115.0
RPL07.INT.DHB.01120 RPL07.Interior.DHB - Priority - Install Security OverHead Not Started 08/10/26 08/14/26 6.2 6.2
0%
40.0
RPL07.SKN.DHCD.01000 RPL07.SKIN.DHCD - Install Temp Doors Glazing, Doors and Ext Devices Not Started 08/10/26 08/11/26 2.5 2.5
0%
322.5
RPL07.SKN.DHCD.01020 RPL07.SKIN.DHCD - Install Windows, Doors, Louvers and Ext Devices - WBS Summary Glazing, Doors and Ext Devices Not Started 08/10/26 05/17/27 240.0 240.0
0%
116.2
RPL07.SKN.SSB.01120 RPL07.SKIN.SSB - Install Scupper and Downspouts Glazing, Doors and Ext Devices Not Started 08/10/26 08/14/26 6.2 6.2
0%
266.2
RPL07.EY.SSB.01160 RPL07.EY.SSB - Install Electrical Tie-ins (include penetration detail) Tie-ins Not Started 08/11/26 09/08/26 25.0 25.0
0%
70.0
RPL07.EY.SSB.01170 RPL07.EY.SSB - Install Mechanical Main (include penetration detail) Tie-ins Not Started 08/11/26 08/31/26 18.8 18.8
0%
63.8
RPL07.INT.CTRC.1000 RPL07.Interior.Center-Corridor - Priority - Install Unistruts & Hangers (All Trades) Both side of Corridor Wall Priority Walls & Overhead Not Started 08/11/26 08/17/26 6.2 6.2
0%
37.5
RPL07.INT.SSB.01050 RPL07.Interior.SSB - Priority - (P1) Frame Walls (Frame full height Walls) Priority Wall - P0 Not Started 08/11/26 08/17/26 6.2 6.2
0%
141.2
RPL07.INT.SSB.06860 RPL07.Interior.SSB - Priority - (P1) Frame Remaining Walls Priority Wall - P0 Not Started 08/11/26 08/13/26 3.8 3.8
0%
192.5
RPL07.MCUP.LP1.1900 RPL07.MCUP.Loop 1 - Tie-in EPMS #4 Tie-Ins EPMS Not Started 08/11/26 08/20/26 10.0 10.0
0%
77.5
RPL07.MCUP.LP1.1940 RPL07.MCUP.Loop 1 - Tie-in BMS #4 Tie-Ins BMS Not Started 08/11/26 08/20/26 10.0 10.0
0%
83.8
RPL07.STR.DHCD.01150 RPL07.Structure.DHCD - Zone SOG Cure F/R/P Not Started 08/11/26 08/17/26 8.8 8.8
0%
146.2
RPL07.WA.OFE.01000 RPL07.WA - Weather Allowance - FDN to OFE Weather Allowance Not Started 08/11/26 08/26/26 20.0 20.0
0%
33.8
RPL07.SKN.DHCD.01140 RPL07.SKIN.DHCD - Install Blocking of Canopy & Backing of Exterior Wall *REMOVE FROM DRYWALL* Glazing, Doors and Ext Devices Not Started 08/12/26 08/18/26 6.2 6.2
0%
322.5
ICM.B7.1845 [SSDCB2] Delivery of FSHAC - Hot Aisle Containment (First Delivery) Construction Not Started 08/13/26 08/13/26 0.0 0.0
0%
46.2
RPL07.CFCI.4920 RPL07 - Fabricate / Deliver - Security System (CFCI) Div. 28 - Security Syst. Not Started 08/13/26 10/08/26 50.0 50.0
0%
197.5
RPL07.CON.WP2.08560 RPL07.Conn - Ext. GSIDF7X04 - Install Copper, WAPs, Security Camera & Access Control (EY-DH C) Cabling Not Started 08/13/26 08/28/26 15.0 15.0
0%
362.5
RPL07.EY.ENDC.1470 RPL07.EY.DHD.T1 - Install Electrical Tie-ins Tent 1 Not Started 08/13/26 08/17/26 3.8 3.8
0%
41.2
RPL07.EY.SSB.01240 RPL07.EY.SSB - Install BMS/EPMS Tie-ins Tie-ins Not Started 08/13/26 09/02/26 18.8 18.8
0%
73.8
RPL07.INT.DHD.01040 RPL07.Interior.DHD - Priority - Install Temp Lighting Early Priority OH MEPF Not Started 08/13/26 08/17/26 3.8 3.8
0%
115.0
RPL07.MCUP.LP2.1240 RPL07.MCUP.Loop 2 - Set MTRs (4 per day) OFE Not Started 08/13/26 08/14/26 2.5 2.5
0%
210.0
RPL07.CON.WP2.08520 RPL07.Conn - Ext. GSIDF7X03 - Install Copper, WAPs, Security Camera & Access Control Cabling Not Started 08/14/26 08/31/26 15.0 15.0
0%
256.2
RPL07.INT.DHC.01010 RPL07.Interior.DHC - Priority - Install Duct Early Priority OH MEPF Not Started 08/14/26 08/19/26 5.0 5.0
0%
191.2
RPL07.INT.DHD.01010 RPL07.Interior.DHD - Priority - Install Duct Early Priority OH MEPF Not Started 08/14/26 08/19/26 5.0 5.0
0%
191.2
RPL07.INT.SBC.03420 RPL07.Interior.SSB-Corridor - BoW - Install Door Frames Balance of Walls & Overhead Not Started 08/14/26 08/20/26 6.2 6.2
0%
115.0
RPL07.INT.SBC.05800 RPL07.Interior.SSB-Corridor - BoW - Install Mechanical Piping/ Refrigerant Lowside OH and in-wall Balance of Walls & Overhead Not Started 08/14/26 08/25/26 10.0 10.0
0%
90.0
RPL07.INT.SSB.06880 RPL07.Interior.SSB - Priority - (P1) Install Remaining MEP In-Wall/Backing Priority Wall - P0 Not Started 08/14/26 08/17/26 2.5 2.5
0%
192.5
RPL07.MCUP.LP1.1820 RPL07.MCUP.Loop 1 - Install Hardscape and Landscape - WBS Summary Hardscape and Landscape Not Started 08/14/26 10/16/26 56.2 56.2
0%
378.8
RPL07.MCUP.LP1.1840 RPL07.MCUP.Loop 1 - Install Sleeves MEPL Hardscape and Landscape Not Started 08/14/26 08/20/26 6.2 6.2
0%
378.8
RPL07.MCUP.LP1.2020 RPL07.MCUP.Loop 1 - Tie-in - MV Loop 2 L2 Checklist Completion Tie-ins Not Started 08/14/26 08/27/26 12.5 12.5
0%
77.5
RPL07.MCUP.LP1.2080 RPL07.MCUP.Loop 1 - Tie-in - Mechanical L2 Checklist Completion Tie-ins Not Started 08/14/26 08/27/26 12.5 12.5
0%
83.8
RPL07.MCUP.LP2.1360 RPL07.MCUP.Loop 2 - Set mCUPs XXMY.MCUP.06 (1 per 5 days) OFE Not Started 08/14/26 08/20/26 6.2 6.2
0%
202.5
RPL07.MCUP.LP2.1400 RPL07.MCUP.Loop 2 - Tie-ins - WBS Summary Tie-ins Not Started 08/14/26 09/18/26 31.2 31.2
0%
356.2
RPL07.MCUP.LP2.1420 RPL07.MCUP.Loop 2 - Tie-in SD, DW Tie-ins Not Started 08/14/26 09/03/26 18.8 18.8
0%
368.8
RPL07.MCUP.LP2.1440 RPL07.MCUP.Loop 2 - Set Electrical Skids #5 OFE Not Started 08/14/26 08/17/26 2.5 2.5
0%
210.0
RPL07.MCUP.LP2.1560 RPL07.MCUP.Loop 2 - Tie-in Electrical - WBS Summary Tie-Ins Electrical Not Started 08/14/26 09/03/26 18.8 18.8
0%
202.5
RPL07.MCUP.LP2.1620 RPL07.MCUP.Loop 2 - Tie-in Electrical #5 Tie-Ins Electrical Not Started 08/14/26 08/27/26 12.5 12.5
0%
208.8
RPL07.EY.ENDC.1690 RPL07.EY.DHD.T2 - Install Panels Tent 2 Not Started 08/17/26 08/21/26 6.2 6.2
0%
40.0
RPL07.EY.ENDC.1790 RPL07.EY.DHD.T2 - Install Mechanical Tie-ins Tent 2 Not Started 08/17/26 08/24/26 7.5 7.5
0%
42.5
RPL07.INT.DHB.01130 RPL07.Interior.DHB - Priority - Install Controls / EPMS / BMS OverHead Not Started 08/17/26 08/20/26 5.0 5.0
0%
40.0
RPL07.MCUP.LP2.1580 RPL07.MCUP.Loop 2 - Tie-in Mechanical - WBS Summary Tie-Ins Mechanical Not Started 08/17/26 09/09/26 21.2 21.2
0%
205.0
RPL07.MCUP.LP2.1600 RPL07.MCUP.Loop 1 - Tie-in Mechanical #5 Tie-Ins Mechanical Not Started 08/17/26 09/02/26 16.2 16.2
0%
210.0
PRE.FA.1300 Non-Critical Trade Buyout - Final Agreement Trade Partner Final Agreement Not Started 08/18/26 08/18/26 0.0 0.0
0%
117.5
RPL07.EY.ENDC.1510 RPL07.EY.DHD.T1 - Temp Conditioning Startup and Available Tent 1 Not Started 08/18/26 08/19/26 2.5 2.5
0%
41.2
RPL07.INT.CTRC.1920 RPL07.Interior.Center-Corridor - Priority - Install Drywall at Exterior Walls Priority Walls & Overhead Not Started 08/18/26 08/24/26 6.2 6.2
0%
37.5
RPL07.INT.DHA.01050 RPL07.Interior.DHA - Priority - Install FA / Linear heat detection OverHead Not Started 08/18/26 08/24/26 6.2 6.2
0%
37.5
RPL07.INT.DHA.02160 RPL07.Interior.DHA - Priority - Install Mechanical Piping OverHead Not Started 08/18/26 09/08/26 18.8 18.8
0%
36.2
RPL07.INT.DHA.02320 RPL07.Interior.DHA - Priority - Install Electrical OverHead Not Started 08/18/26 09/08/26 18.8 18.8
0%
37.5
RPL07.INT.DHC.01040 RPL07.Interior.DHC - Priority - Install Temp Lighting Early Priority OH MEPF Not Started 08/18/26 08/20/26 3.8 3.8
0%
115.0
RPL07.INT.DHD.01000 RPL07.Interior.DHD - Priority OH - WBS Summary OverHead Not Started 08/18/26 10/06/26 43.8 43.8
0%
331.2
RPL07.INT.DHD.01020 RPL07.Interior.DHD - Install Priority OH, Walls, OFE and Tie-ins - WBS Summary DHD Not Started 08/18/26 05/19/27 235.0 235.0
0%
140.0
RPL07.INT.DHD.01700 RPL07.Interior.DHD - Priority - Install Draft Curtains (#2 - 3 Days Each) OverHead Not Started 08/18/26 08/25/26 7.5 7.5
0%
112.5
RPL07.INT.DHD.01980 RPL07.Interior.DHD - Priority - Install Unistruts & Hangers (All Trades) Both side of Corridor Wall OverHead Not Started 08/18/26 08/24/26 6.2 6.2
0%
96.2
RPL07.INT.DHD.02250 RPL07.Interior.DHD - Priority - Install IMP Exterior Inwall Rough-In OverHead Not Started 08/18/26 08/24/26 6.2 6.2
0%
96.2
RPL07.INT.SSB.01140 RPL07.Interior.SSB - Loading Dock and Storage - Frame Walls Loading Dock and Storage Not Started 08/18/26 08/27/26 10.0 10.0
0%
182.5
RPL07.INT.SSB.01150 RPL07.Interior.SSB - BoW - BoW - Framing Balance of Wall Balance of Walls and OverHead Not Started 08/18/26 08/24/26 6.2 6.2
0%
141.2
RPL07.INT.SSB.01160 RPL07.Interior.SSB - BoW - Balace Of Wall (ERAD, Maintance, Network infra, Spoke, Bathroom, etc) - WBS Summary Balance of Walls and OverHead Not Started 08/18/26 04/08/27 198.8 198.8
0%
77.5
RPL07.INT.SSB.01170 RPL07.Interior.SSB - Loading Dock and Storage - WBS Summary Loading Dock and Storage Not Started 08/18/26 02/09/27 148.8 148.8
0%
127.5
RPL07.INT.SSB.06800 RPL07.Interior.SSB - Priority - (P1) Install MEP In-Wall/Backing Priority Wall - P0 Not Started 08/18/26 08/21/26 5.0 5.0
0%
185.0
RPL07.INT.SSB.06900 RPL07.Interior.SSB - Priority - (P1) Remaining Wall Hang Drywall (Both Sides) Priority Wall - P0 Not Started 08/18/26 08/20/26 3.8 3.8
0%
192.5
RPL07.MCUP.LP2.1680 RPL07.MCUP.Loop 2 - Tie-in EPMS - WBS Summary Tie-Ins EPMS Not Started 08/18/26 09/03/26 16.2 16.2
0%
202.5
RPL07.MCUP.LP2.1700 RPL07.MCUP.Loop 2 - Tie-in EPMS #5 Tie-Ins EPMS Not Started 08/18/26 08/27/26 10.0 10.0
0%
208.8
RPL07.STR.DHCD.01210 RPL07.Structure.DHCD - Moisture requirements for floor Sealer F/R/P Not Started 08/18/26 08/24/26 8.8 8.8
0%
166.2