Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL07 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:16 PM · 5237 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
0
Completed
0
In Progress
0
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL07.CFCI.4620 RPL07 - Submittals Prep & Submit for Review -Epoxy Flooring (Spec 09 67 23) XX (CFCI) Div. 09 - Epoxy Flooring Not Started 08/19/26 09/16/26 25.0 25.0
0%
131.2
RPL07.CFCI.4810 RPL07 - Submittals Prep & Submit for Review - Specialities (CFCI) Div. 10 - Specialities Not Started 08/19/26 09/16/26 25.0 25.0
0%
117.5
RPL07.CFCI.4870 RPL07 - Submittals Review & Approval - Interior Painting (Spec 09 91 23) XX (CFCI) Div. 09 - Painting Not Started 08/19/26 09/16/26 25.0 25.0
0%
168.8
RPL07.CFCI.4890 RPL07 - Submittals Review & Approval - Fire Alarm (CFCI) Div. 26 - Fire Alarm Not Started 08/19/26 09/09/26 18.8 18.8
0%
192.5
RPL07.CFCI.4960 RPL07 - Fabricate / Deliver - Finished Carpentry (Millwork/Countertops) Finished Carpentry (Millwork/Tops) Not Started 08/19/26 09/30/26 37.5 37.5
0%
247.5
RPL07.SKN.DHCD.01030 RPL07.SKIN.DHCD - Install Awning over Doors Glazing, Doors and Ext Devices Not Started 08/19/26 08/25/26 6.2 6.2
0%
322.5
RPL.07.D.74160.XG Ready for MV Cable Pull mCUP - Loop#2 (Qty 2)* Give Milestones (XREFs) Not Started 08/20/26 08/20/26 0.0 0.0
0%
428.8
RPL07.INT.CTRC.1100 RPL07.Interior.Center-Corridor - Priority - Tape Finish Paint Priority Soffit both sides (Top Out) Priority Walls & Overhead Not Started 08/20/26 08/28/26 8.8 8.8
0%
37.5
RPL07.INT.ENDC.1180 RPL07.Interior.End-Corridor - Priority - Install Duct (Highside OH space) Early Priority OH MEPF Not Started 08/20/26 08/28/26 8.8 8.8
0%
191.2
RPL07.INT.ENDC.1060 RPL07.Interior.End-Corridor - Priority - Install Temp Lighting (Show In Model) Early Priority OH MEPF Not Started 08/21/26 08/25/26 3.8 3.8
0%
115.0
RPL07.INT.SSB.06920 RPL07.Interior.SSB - Priority - (P1) Remaining Wall Tape Finish Paint (Both Sides) Priority Wall - P0 Not Started 08/21/26 08/27/26 6.2 6.2
0%
192.5
RPL07.LOG.1100 MCUP 500 Ton Crane Demobilization 300 Ton Crane Not Started 08/21/26 08/26/26 5.0 5.0
0%
423.8
RPL07.MCUP.LP1.1920 RPL07.MCUP.Loop 1 - Install Early Mcup Paving Hardscape and Landscape Not Started 08/21/26 09/03/26 12.5 12.5
0%
378.8
RPL07.MCUP.LP1.2060 RPL07.MCUP.Loop 1 - Tie-in - Electrical L2 Checklist Completion Tie-ins Not Started 08/21/26 09/03/26 12.5 12.5
0%
77.5
RPL07.MCUP.LP2.1500 RPL07.MCUP.Loop 2 - Set Electrical Skids #6 OFE Not Started 08/21/26 08/24/26 2.5 2.5
0%
206.2
RPL07.MCUP.LP2.2000 RPL07.MCUP.Loop 2 - Tie-in Electrical #6 Tie-Ins Electrical Not Started 08/21/26 09/03/26 12.5 12.5
0%
202.5
RPL07.MCUP.LP2.2020 RPL07.MCUP.Loop 1 - Tie-in Mechanical #6 Tie-Ins Mechanical Not Started 08/21/26 09/09/26 16.2 16.2
0%
205.0
RPL.07.D.73760.XG RMUs Set - mCUP Loop 2 Give Milestones (XREFs) Not Started 08/24/26 08/24/26 0.0 0.0
0%
426.2
RPL07.EY.ENDC.1770 RPL07.EY.DHD.T2 - Install Electrical Tie-ins Tent 2 Not Started 08/24/26 08/26/26 3.8 3.8
0%
40.0
RPL07.INT.SSB.06820 RPL07.Interior.SSB - Priority - (P1) Hang Drywall (Both Sides) Priority Wall - P0 Not Started 08/24/26 08/28/26 6.2 6.2
0%
185.0
RPL07.MCUP.LP2.1660 RPL07.MCUP.Loop 2 - Tie-in BMS - WBS Summary Tie-Ins BMS Not Started 08/24/26 09/09/26 15.0 15.0
0%
205.0
RPL07.MCUP.LP2.1720 RPL07.MCUP.Loop 2 - Tie-in BMS #5 Tie-Ins BMS Not Started 08/24/26 09/02/26 10.0 10.0
0%
210.0
RPL07.EY.DHD.01120 RPL07.EY.DHD - Cure (High Early Mix) Foundations Not Started 08/25/26 08/31/26 8.8 8.8
0%
253.8
RPL07.INT.DHA.02360 RPL07.Interior.DHA - Priority - Install Temp Doors Frame Hardware OverHead Not Started 08/25/26 08/27/26 3.8 3.8
0%
270.0
RPL07.INT.DHD.02230 RPL07.Interior.DHD - Priority - Install Drywall at Exterior Walls OverHead Not Started 08/25/26 08/31/26 6.2 6.2
0%
96.2
RPL07.INT.SSB.01180 RPL07.Interior.SSB - BoW - Install Door Frames Balance of Walls and OverHead Not Started 08/25/26 08/31/26 6.2 6.2
0%
162.5
RPL07.MCUP.LP2.1940 RPL07.MCUP.Loop 2 - Tie-in EPMS #6 Tie-Ins EPMS Not Started 08/25/26 09/03/26 10.0 10.0
0%
202.5
RPL07.STR.DHCD.01230 RPL07.Structure.DHCD - Install SOG Sealer and Cure F/R/P Not Started 08/25/26 08/26/26 2.5 2.5
0%
166.2
RPL07.CFCI.5270 Campus - Fabricate / Deliver - Asphalt / Paving (CFCI) Div. 32 - Asphalt/ Conc. Paving Not Started 08/26/26 09/16/26 18.8 18.8
0%
201.2
RPL07.CFCI.5280 Campus - Submittals Review & Approval - Landscaping / Irrigation (CFCI) Div. 32 - Landscape/ Irrigation Not Started 08/26/26 09/23/26 25.0 25.0
0%
287.5
RPL07.CFCI.6940 RPL07 - Submittals Prep & Submit for Review - Gypsum Ceilings (CFCI) Div. 09 - Gypsum System & Ceilings Not Started 08/26/26 09/16/26 18.8 18.8
0%
115.0
RPL07.INT.ENDC.01020 RPL07.Interior.End-Corridor - Install Priority OH, Walls, OFE and Fitout - WBS Summary End Corridor Not Started 08/26/26 07/30/27 290.0 290.0
0%
86.2
RPL07.INT.ENDC.03480 RPL07.Interior.End-Corr - Priority - WBS Summary Priority Walls & Overhead Not Started 08/26/26 10/09/26 40.0 40.0
0%
127.5
RPL07.INT.ENDC.1020 RPL07.Interior.End-Corr - Priority - Install Priority Soffit for Wall Tie-Ins/ Rock & HoW & Draft Blanket Priority Walls & Overhead Not Started 08/26/26 09/01/26 6.2 6.2
0%
130.0
RPL07.INT.SBC.03280 RPL07.Interior.SSB-Corridor - BoW - Install Electrical Lowside OH and In-wall (Coordinate Lights location) Balance of Walls & Overhead Not Started 08/26/26 09/09/26 12.5 12.5
0%
90.0
RPL07.SKN.DHCD.01040 RPL07.SKIN.DHCD - Install Louvers Glazing, Doors and Ext Devices Not Started 08/26/26 09/01/26 6.2 6.2
0%
322.5
RPL07.SKN.DHCD.01100 RPL07.SKIN.DHCD - Install Scupper and Downspouts Glazing, Doors and Ext Devices Not Started 08/26/26 09/01/26 6.2 6.2
0%
335.0
ICM.B7.1840 [SSDCB2] Delivery of DES - Data Hall Electrical Room Skid (First Delivery) Construction Not Started 08/27/26 08/27/26 0.0 0.0
0%
83.8
RPL07.EY.ENDC.1810 RPL07.EY.DHD.T2 - Temp Conditioning Startup and Available Tent 2 Not Started 08/27/26 08/28/26 2.5 2.5
0%
40.0
RPL07.INT.DHC.01020 RPL07.Interior.DHC - Install Priority OH, Walls, OFE and Tie-ins - WBS Summary DHC Not Started 08/27/26 06/03/27 238.8 238.8
0%
136.2
RPL07.INT.DHC.01080 RPL07.Interior.DHC - OFE - WBS Summary OFE/MOFE & CFCI Not Started 08/27/26 04/13/27 193.8 193.8
0%
46.2
RPL07.INT.DHC.02670 RPL07.Interior.DHC - CFCI - Pre Set 16"" FW Pipe OFE/MOFE & CFCI Not Started 08/27/26 09/10/26 12.5 12.5
0%
111.2
RPL07.INT.DHD.01080 RPL07.Interior.DHD - OFE - WBS Summary OFE/MOFE & CFCI Not Started 08/27/26 03/30/27 181.2 181.2
0%
30.0
RPL07.INT.DHD.02670 RPL07.Interior.DHD - CFCI - Pre Set 16"" FW Pipe OFE/MOFE & CFCI Not Started 08/27/26 09/10/26 12.5 12.5
0%
111.2
RPL07.CON.WP2.09200 RPL07.Conn - CorpNet & FacNet Available (South EY) - All IDFS WP#02 GS Not Started 08/28/26 08/28/26 0.0 0.0
0%
421.2
RPL07.CX.1180 RPL07.CX.BLDG - L3, L4, IST - WBS Summary Commissioning Not Started 08/28/26 11/09/27 376.2 376.2
0%
46.2
RPL07.CX.MCUP.01000 RPL07.CX.mCup Loop 1 - L3, L4, IST - WBS Summary mCUP 1-4 Not Started 08/28/26 01/04/27 107.5 107.5
0%
172.5
RPL07.CX.MCUP.01350 RPL07.CX.mCup Loop 1 - L3/L4 - mCUP - Flush and Fill - Temp Flush Skid (PR) Fill and Flush Not Started 08/28/26 09/03/26 6.2 6.2
0%
107.5
RPL07.Conn.MS.01100 RPL07.Conn Wifi Ready - South EY (Pred from RPL10 CorpNet needed?) Connectivity Milestones Not Started 08/28/26 08/28/26 0.0 0.0
0%
362.5
RPL07.INT.ENDC.6060 RPL07.Interior.End-Corr - Priority - Install IMP Exterior Inwall Rough-In Priority Walls & Overhead Not Started 08/28/26 09/01/26 3.8 3.8
0%
136.2
RPL07.INT.SSB.01510 RPL07.Interior.SSB - Loading Dock and Storage - Install Door Frames Loading Dock and Storage Not Started 08/28/26 09/03/26 6.2 6.2
0%
191.2
RPL07.INT.SSB.02900 RPL07.Interior.SSB - Loading Dock and Storage - Pre Priority OH & Walls Tasks (Unistruts,Hangers,Track) Loading Dock and Storage Not Started 08/28/26 09/03/26 6.2 6.2
0%
191.2
RPL07.INT.SSB.02920 RPL07.Interior.SSB - Loading Dock and Storage - Install Headers and Top Out and Fire/Caulking Loading Dock and Storage Not Started 08/28/26 09/11/26 12.5 12.5
0%
182.5
RPL07.INT.SSBC.01060 RPL07.Interior.SSB-Corridor - OFE - Early Equipment (1x SSB Elect) OFE/MOFE & CFCI Not Started 08/28/26 09/11/26 12.5 12.5
0%
83.8
RPL07.MCUP.LP2.1980 RPL07.MCUP.Loop 2 - Tie-in BMS #6 Tie-Ins BMS Not Started 08/28/26 09/09/26 10.0 10.0
0%
205.0
RPL07.CON.WP2.09180 RPL07.Conn - CorpNet & FacNet Available (mCUP) - All IDFS WP#02 GS Not Started 08/31/26 08/31/26 0.0 0.0
0%
420.0
RPL07.Conn.MS.01080 RPL07.Conn Wifi Ready - mCUP Yard (Pred from RPL10 CorpNet needed?) Connectivity Milestones Not Started 08/31/26 08/31/26 0.0 0.0
0%
256.2
RPL07.INT.CTRC.1160 RPL07.Interior.Center-Corr - Priority GL7.16/7.17 - (P2) Frame Walls (Incl. Entry Fiber Rooms #3.7, Ancillary Room #3.6) Priority Wall Grid Line 7-16 / 7-17 Not Started 08/31/26 09/09/26 8.8 8.8
0%
37.5
RPL07.INT.SSB.06840 RPL07.Interior.SSB - Priority - (P1) Tape Finish Paint (Both Sides) Priority Wall - P0 Not Started 08/31/26 09/04/26 6.2 6.2
0%
185.0
RPL07.EY.SSB.01175 RPL07.EY.SSB - Install Mechanical/refrigerantTie-ins Tie-ins Not Started 09/01/26 09/15/26 12.5 12.5
0%
63.8
RPL07.INT.DHC.01000 RPL07.Interior.DHC - Priority OH - WBS Summary OverHead Not Started 09/01/26 10/29/26 52.5 52.5
0%
318.8
RPL07.INT.DHC.01980 RPL07.Interior.DHC - Priority - Install Unistruts & Hangers (All Trades) Both side of Corridor Wall OverHead Not Started 09/01/26 09/08/26 6.2 6.2
0%
98.8
RPL07.INT.DHC.02000 RPL07.Interior.DHC - Priority - Install Draft Curtains (#2 - 3 Days Each) OverHead Not Started 09/01/26 09/09/26 7.5 7.5
0%
112.5
RPL07.INT.DHC.02250 RPL07.Interior.DHC - Priority - Install IMP Exterior Inwall Rough-In OverHead Not Started 09/01/26 09/08/26 6.2 6.2
0%
98.8
RPL07.INT.SBC.03300 RPL07.Interior.SSB-Corridor - BoW - Install Fire Life Safety Lowside OH and In-wall Balance of Walls & Overhead Not Started 09/01/26 09/10/26 8.8 8.8
0%
103.8
RPL07.INT.SBC.03340 RPL07.Interior.SSB-Corridor - BoW - Install Security Lowside OH and In-wall Balance of Walls & Overhead Not Started 09/01/26 09/10/26 8.8 8.8
0%
132.5
RPL07.SKN.DHCD.01050 RPL07.SKIN.DHCD - Install Lighting Glazing, Doors and Ext Devices Not Started 09/02/26 09/08/26 5.0 5.0
0%
322.5
RPL07.EY.SSB.01250 RPL07.EY.SSB - Install Sleeves MEPL Hardscape and Landscape Not Started 09/03/26 09/10/26 6.2 6.2
0%
193.8
RPL07.EY.SSB.01270 RPL07.EY.SSB - Hardscape and Landscape - WBS Summary Hardscape and Landscape Not Started 09/03/26 06/03/27 232.5 232.5
0%
185.0
GCD.RPL07.2051 MCUP Ready for Energization - (MCUPs Loop 1) mCup Not Started 09/04/26 09/04/26 0.0 0.0
0%
102.5
ICM.B7.1212 [SSDCB2] Start Flush & Fill of Chilled Water System Commissioning Not Started 09/04/26 09/04/26 0.0 0.0
0%
113.8
RPL07.CFCI.6960 RPL07 - Submittals Review & Approval - Gypsum Ceilings (CFCI) Div. 09 - Gypsum System & Ceilings Not Started 09/04/26 10/02/26 25.0 25.0
0%
115.0
RPL07.CX.MCUP.01010 RPL07.CX.mCup Loop 1 - L3/L4 - MV Skids mCUP 1-4 Not Started 09/04/26 09/14/26 7.5 7.5
0%
77.5
RPL07.CX.MCUP.01150 RPL07.CX.mCup Loop 1 - L3/L4 - mCUP - Flush and Fill - mCup Yard & FWM - Loop 1 (mCUPs 1-4) (Phase 1) Fill and Flush Not Started 09/04/26 09/11/26 6.2 6.2
0%
107.5
RPL07.INT.SSB.01330 RPL07.Interior.SSB - Loading Dock and Storage - Hang Drywall Loading Dock and Storage Not Started 09/04/26 09/18/26 12.5 12.5
0%
191.2
RPL07.MCUP.LP1.2000 RPL07.MCUP.Loop 1 - Install Lighting Hardscape and Landscape Not Started 09/04/26 09/18/26 12.5 12.5
0%
378.8
RPL07.MCUP.LP2.1520 RPL07.MCUP.Loop 2 - Install Hardscape and Landscape - WBS Summary Hardscape and Landscape Not Started 09/04/26 10/28/26 47.5 47.5
0%
368.8
RPL07.MCUP.LP2.1540 RPL07.MCUP.Loop 2 - Install Sleeves MEPL Hardscape and Landscape Not Started 09/04/26 09/09/26 3.8 3.8
0%
368.8
RPL07.MCUP.LP2.2040 RPL07.MCUP.Loop 2 - Tie-in - MV Loop 2 L2 Checklist Completion Tie-ins Not Started 09/04/26 09/11/26 6.2 6.2
0%
202.5
RPL07.INT.CTRC.9040 RPL07.Interior.Center-Corr - Priority GL7.16/7.17 - (P2) Install MEP In-Wall/Backing Priority Wall Grid Line 7-16 / 7-17 Not Started 09/08/26 09/11/26 5.0 5.0
0%
37.5
GCD.RPL07.1290 Interior fit-out Start RPL07 - DHC&D Construction Milestones Not Started 09/09/26 09/09/26 0.0 0.0
0%
367.5
GCD.RPL07.1655 Start MES Installation - RPL07 Construction Milestones Not Started 09/09/26 09/09/26 0.0 0.0
0%
67.5
GCD.RPL07.1700 Start LV Electrical Skid Set-In-Place - RPL07 Construction Milestones Not Started 09/09/26 09/09/26 0.0 0.0
0%
271.2
RPL07.INT.CTRC.1080 RPL07.Interior.Center-Corridor - Priority - Install Mechanical Piping/ Refrigerant (Highside OH space) Priority Walls & Overhead Not Started 09/09/26 09/15/26 6.2 6.2
0%
36.2
RPL07.INT.DHA.02340 RPL07.Interior.DHA - Priority - Install Security OverHead Not Started 09/09/26 09/15/26 6.2 6.2
0%
261.2
RPL07.INT.DHB.01140 RPL07.Interior.DHB - OFE - LV Skids and TopHat - Set / Place / Anchor OFE/MOFE & CFCI Not Started 09/09/26 09/29/26 18.8 18.8
0%
12.5
RPL07.INT.DHB.01150 RPL07.Interior.DHB - OFE - MES Skids - Set / Place / Anchor OFE/MOFE & CFCI Not Started 09/09/26 09/29/26 18.8 18.8
0%
61.2
RPL07.INT.DHC.02230 RPL07.Interior.DHC - Priority - Install Drywall at Exterior Walls OverHead Not Started 09/09/26 09/15/26 6.2 6.2
0%
98.8
RPL07.INT.ENDC.1000 RPL07.Interior.End-Corr - Priority - Install Unistruts & Hangers (All Trades) Both side of Corridor Wall Priority Walls & Overhead Not Started 09/09/26 09/15/26 6.2 6.2
0%
125.0
RPL07.SKN.DHCD.01060 RPL07.SKIN.DHCD - Install Security Glazing, Doors and Ext Devices Not Started 09/09/26 09/10/26 2.5 2.5
0%
322.5
RPL07.CFCI.5090 RPL07 - Fabricate / Deliver - Fire Alarm (CFCI) Div. 26 - Fire Alarm Not Started 09/10/26 11/04/26 50.0 50.0
0%
192.5
RPL07.INT.CTRC.9020 RPL07.Interior.Center-Corr - Priority GL7.16/7.17 - (P2) Install IMP Walls Priority Wall Grid Line 7-16 / 7-17 Not Started 09/10/26 09/15/26 5.0 5.0
0%
43.8
RPL07.INT.CTRC.9060 RPL07.Interior.Center-Corr - Priority GL7.16/7.17 - (P2) Hang Drywall (Both Sides) Priority Wall Grid Line 7-16 / 7-17 Not Started 09/10/26 09/15/26 5.0 5.0
0%
37.5
RPL07.INT.SBC.03320 RPL07.Interior.SSB-Corridor - BoW - Install Plumbing Lowside OH and In-wall Balance of Walls & Overhead Not Started 09/10/26 09/18/26 8.8 8.8
0%
90.0
RPL07.MCUP.LP2.1640 RPL07.MCUP.Loop 2 - Install Early Mcup Paving Hardscape and Landscape Not Started 09/10/26 09/23/26 12.5 12.5
0%
368.8
RPL07.MCUP.LP2.2080 RPL07.MCUP.Loop 2 - Tie-in - Mechanical L2 Checklist Completion Tie-ins Not Started 09/10/26 09/16/26 6.2 6.2
0%
205.0
RPL07.EY.SSB.01290 RPL07.EY.SSB - Install Trash Enclosure (CMU) Hardscape and Landscape Not Started 09/11/26 10/08/26 25.0 25.0
0%
218.8
RPL07.INT.SBC.03440 RPL07.Interior.SSB-Corridor - BoW - Install Electrical - Lighitng Inverter Room (XX.S2.XX) Balance of Walls & Overhead Not Started 09/11/26 09/21/26 8.8 8.8
0%
132.5
ICM.B7.1825 [SSDCB2] Delivery of MVS - Medium Voltage Switches (First Delivery) Construction Not Started 09/14/26 09/14/26 0.0 0.0
0%
25.0
RPL07.CX.MCUP.01190 RPL07.CX.mCup Loop 1 - L3/L4 - mCUP - Flush and Fill - mCup1 and Dry Coolers Fill and Flush Not Started 09/14/26 09/21/26 7.5 7.5
0%
107.5