Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL07 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:16 PM
· 5237 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
0
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL07.CFCI.4620 |
RPL07 - Submittals Prep & Submit for Review -Epoxy Flooring (Spec 09 67 23) XX | (CFCI) Div. 09 - Epoxy Flooring | Not Started | 08/19/26 | 09/16/26 | 25.0 | 25.0 |
|
131.2 |
RPL07.CFCI.4810 |
RPL07 - Submittals Prep & Submit for Review - Specialities | (CFCI) Div. 10 - Specialities | Not Started | 08/19/26 | 09/16/26 | 25.0 | 25.0 |
|
117.5 |
RPL07.CFCI.4870 |
RPL07 - Submittals Review & Approval - Interior Painting (Spec 09 91 23) XX | (CFCI) Div. 09 - Painting | Not Started | 08/19/26 | 09/16/26 | 25.0 | 25.0 |
|
168.8 |
RPL07.CFCI.4890 |
RPL07 - Submittals Review & Approval - Fire Alarm | (CFCI) Div. 26 - Fire Alarm | Not Started | 08/19/26 | 09/09/26 | 18.8 | 18.8 |
|
192.5 |
RPL07.CFCI.4960 |
RPL07 - Fabricate / Deliver - Finished Carpentry (Millwork/Countertops) | Finished Carpentry (Millwork/Tops) | Not Started | 08/19/26 | 09/30/26 | 37.5 | 37.5 |
|
247.5 |
RPL07.SKN.DHCD.01030 |
RPL07.SKIN.DHCD - Install Awning over Doors | Glazing, Doors and Ext Devices | Not Started | 08/19/26 | 08/25/26 | 6.2 | 6.2 |
|
322.5 |
RPL.07.D.74160.XG |
Ready for MV Cable Pull mCUP - Loop#2 (Qty 2)* | Give Milestones (XREFs) | Not Started | 08/20/26 | 08/20/26 | 0.0 | 0.0 |
|
428.8 |
RPL07.INT.CTRC.1100 |
RPL07.Interior.Center-Corridor - Priority - Tape Finish Paint Priority Soffit both sides (Top Out) | Priority Walls & Overhead | Not Started | 08/20/26 | 08/28/26 | 8.8 | 8.8 |
|
37.5 |
RPL07.INT.ENDC.1180 |
RPL07.Interior.End-Corridor - Priority - Install Duct (Highside OH space) | Early Priority OH MEPF | Not Started | 08/20/26 | 08/28/26 | 8.8 | 8.8 |
|
191.2 |
RPL07.INT.ENDC.1060 |
RPL07.Interior.End-Corridor - Priority - Install Temp Lighting (Show In Model) | Early Priority OH MEPF | Not Started | 08/21/26 | 08/25/26 | 3.8 | 3.8 |
|
115.0 |
RPL07.INT.SSB.06920 |
RPL07.Interior.SSB - Priority - (P1) Remaining Wall Tape Finish Paint (Both Sides) | Priority Wall - P0 | Not Started | 08/21/26 | 08/27/26 | 6.2 | 6.2 |
|
192.5 |
RPL07.LOG.1100 |
MCUP 500 Ton Crane Demobilization | 300 Ton Crane | Not Started | 08/21/26 | 08/26/26 | 5.0 | 5.0 |
|
423.8 |
RPL07.MCUP.LP1.1920 |
RPL07.MCUP.Loop 1 - Install Early Mcup Paving | Hardscape and Landscape | Not Started | 08/21/26 | 09/03/26 | 12.5 | 12.5 |
|
378.8 |
RPL07.MCUP.LP1.2060 |
RPL07.MCUP.Loop 1 - Tie-in - Electrical L2 Checklist Completion | Tie-ins | Not Started | 08/21/26 | 09/03/26 | 12.5 | 12.5 |
|
77.5 |
RPL07.MCUP.LP2.1500 |
RPL07.MCUP.Loop 2 - Set Electrical Skids #6 | OFE | Not Started | 08/21/26 | 08/24/26 | 2.5 | 2.5 |
|
206.2 |
RPL07.MCUP.LP2.2000 |
RPL07.MCUP.Loop 2 - Tie-in Electrical #6 | Tie-Ins Electrical | Not Started | 08/21/26 | 09/03/26 | 12.5 | 12.5 |
|
202.5 |
RPL07.MCUP.LP2.2020 |
RPL07.MCUP.Loop 1 - Tie-in Mechanical #6 | Tie-Ins Mechanical | Not Started | 08/21/26 | 09/09/26 | 16.2 | 16.2 |
|
205.0 |
RPL.07.D.73760.XG |
RMUs Set - mCUP Loop 2 | Give Milestones (XREFs) | Not Started | 08/24/26 | 08/24/26 | 0.0 | 0.0 |
|
426.2 |
RPL07.EY.ENDC.1770 |
RPL07.EY.DHD.T2 - Install Electrical Tie-ins | Tent 2 | Not Started | 08/24/26 | 08/26/26 | 3.8 | 3.8 |
|
40.0 |
RPL07.INT.SSB.06820 |
RPL07.Interior.SSB - Priority - (P1) Hang Drywall (Both Sides) | Priority Wall - P0 | Not Started | 08/24/26 | 08/28/26 | 6.2 | 6.2 |
|
185.0 |
RPL07.MCUP.LP2.1660 |
RPL07.MCUP.Loop 2 - Tie-in BMS - WBS Summary | Tie-Ins BMS | Not Started | 08/24/26 | 09/09/26 | 15.0 | 15.0 |
|
205.0 |
RPL07.MCUP.LP2.1720 |
RPL07.MCUP.Loop 2 - Tie-in BMS #5 | Tie-Ins BMS | Not Started | 08/24/26 | 09/02/26 | 10.0 | 10.0 |
|
210.0 |
RPL07.EY.DHD.01120 |
RPL07.EY.DHD - Cure (High Early Mix) | Foundations | Not Started | 08/25/26 | 08/31/26 | 8.8 | 8.8 |
|
253.8 |
RPL07.INT.DHA.02360 |
RPL07.Interior.DHA - Priority - Install Temp Doors Frame Hardware | OverHead | Not Started | 08/25/26 | 08/27/26 | 3.8 | 3.8 |
|
270.0 |
RPL07.INT.DHD.02230 |
RPL07.Interior.DHD - Priority - Install Drywall at Exterior Walls | OverHead | Not Started | 08/25/26 | 08/31/26 | 6.2 | 6.2 |
|
96.2 |
RPL07.INT.SSB.01180 |
RPL07.Interior.SSB - BoW - Install Door Frames | Balance of Walls and OverHead | Not Started | 08/25/26 | 08/31/26 | 6.2 | 6.2 |
|
162.5 |
RPL07.MCUP.LP2.1940 |
RPL07.MCUP.Loop 2 - Tie-in EPMS #6 | Tie-Ins EPMS | Not Started | 08/25/26 | 09/03/26 | 10.0 | 10.0 |
|
202.5 |
RPL07.STR.DHCD.01230 |
RPL07.Structure.DHCD - Install SOG Sealer and Cure | F/R/P | Not Started | 08/25/26 | 08/26/26 | 2.5 | 2.5 |
|
166.2 |
RPL07.CFCI.5270 |
Campus - Fabricate / Deliver - Asphalt / Paving | (CFCI) Div. 32 - Asphalt/ Conc. Paving | Not Started | 08/26/26 | 09/16/26 | 18.8 | 18.8 |
|
201.2 |
RPL07.CFCI.5280 |
Campus - Submittals Review & Approval - Landscaping / Irrigation | (CFCI) Div. 32 - Landscape/ Irrigation | Not Started | 08/26/26 | 09/23/26 | 25.0 | 25.0 |
|
287.5 |
RPL07.CFCI.6940 |
RPL07 - Submittals Prep & Submit for Review - Gypsum Ceilings | (CFCI) Div. 09 - Gypsum System & Ceilings | Not Started | 08/26/26 | 09/16/26 | 18.8 | 18.8 |
|
115.0 |
RPL07.INT.ENDC.01020 |
RPL07.Interior.End-Corridor - Install Priority OH, Walls, OFE and Fitout - WBS Summary | End Corridor | Not Started | 08/26/26 | 07/30/27 | 290.0 | 290.0 |
|
86.2 |
RPL07.INT.ENDC.03480 |
RPL07.Interior.End-Corr - Priority - WBS Summary | Priority Walls & Overhead | Not Started | 08/26/26 | 10/09/26 | 40.0 | 40.0 |
|
127.5 |
RPL07.INT.ENDC.1020 |
RPL07.Interior.End-Corr - Priority - Install Priority Soffit for Wall Tie-Ins/ Rock & HoW & Draft Blanket | Priority Walls & Overhead | Not Started | 08/26/26 | 09/01/26 | 6.2 | 6.2 |
|
130.0 |
RPL07.INT.SBC.03280 |
RPL07.Interior.SSB-Corridor - BoW - Install Electrical Lowside OH and In-wall (Coordinate Lights location) | Balance of Walls & Overhead | Not Started | 08/26/26 | 09/09/26 | 12.5 | 12.5 |
|
90.0 |
RPL07.SKN.DHCD.01040 |
RPL07.SKIN.DHCD - Install Louvers | Glazing, Doors and Ext Devices | Not Started | 08/26/26 | 09/01/26 | 6.2 | 6.2 |
|
322.5 |
RPL07.SKN.DHCD.01100 |
RPL07.SKIN.DHCD - Install Scupper and Downspouts | Glazing, Doors and Ext Devices | Not Started | 08/26/26 | 09/01/26 | 6.2 | 6.2 |
|
335.0 |
ICM.B7.1840 |
[SSDCB2] Delivery of DES - Data Hall Electrical Room Skid (First Delivery) | Construction | Not Started | 08/27/26 | 08/27/26 | 0.0 | 0.0 |
|
83.8 |
RPL07.EY.ENDC.1810 |
RPL07.EY.DHD.T2 - Temp Conditioning Startup and Available | Tent 2 | Not Started | 08/27/26 | 08/28/26 | 2.5 | 2.5 |
|
40.0 |
RPL07.INT.DHC.01020 |
RPL07.Interior.DHC - Install Priority OH, Walls, OFE and Tie-ins - WBS Summary | DHC | Not Started | 08/27/26 | 06/03/27 | 238.8 | 238.8 |
|
136.2 |
RPL07.INT.DHC.01080 |
RPL07.Interior.DHC - OFE - WBS Summary | OFE/MOFE & CFCI | Not Started | 08/27/26 | 04/13/27 | 193.8 | 193.8 |
|
46.2 |
RPL07.INT.DHC.02670 |
RPL07.Interior.DHC - CFCI - Pre Set 16"" FW Pipe | OFE/MOFE & CFCI | Not Started | 08/27/26 | 09/10/26 | 12.5 | 12.5 |
|
111.2 |
RPL07.INT.DHD.01080 |
RPL07.Interior.DHD - OFE - WBS Summary | OFE/MOFE & CFCI | Not Started | 08/27/26 | 03/30/27 | 181.2 | 181.2 |
|
30.0 |
RPL07.INT.DHD.02670 |
RPL07.Interior.DHD - CFCI - Pre Set 16"" FW Pipe | OFE/MOFE & CFCI | Not Started | 08/27/26 | 09/10/26 | 12.5 | 12.5 |
|
111.2 |
RPL07.CON.WP2.09200 |
RPL07.Conn - CorpNet & FacNet Available (South EY) - All IDFS | WP#02 GS | Not Started | 08/28/26 | 08/28/26 | 0.0 | 0.0 |
|
421.2 |
RPL07.CX.1180 |
RPL07.CX.BLDG - L3, L4, IST - WBS Summary | Commissioning | Not Started | 08/28/26 | 11/09/27 | 376.2 | 376.2 |
|
46.2 |
RPL07.CX.MCUP.01000 |
RPL07.CX.mCup Loop 1 - L3, L4, IST - WBS Summary | mCUP 1-4 | Not Started | 08/28/26 | 01/04/27 | 107.5 | 107.5 |
|
172.5 |
RPL07.CX.MCUP.01350 |
RPL07.CX.mCup Loop 1 - L3/L4 - mCUP - Flush and Fill - Temp Flush Skid (PR) | Fill and Flush | Not Started | 08/28/26 | 09/03/26 | 6.2 | 6.2 |
|
107.5 |
RPL07.Conn.MS.01100 |
RPL07.Conn Wifi Ready - South EY (Pred from RPL10 CorpNet needed?) | Connectivity Milestones | Not Started | 08/28/26 | 08/28/26 | 0.0 | 0.0 |
|
362.5 |
RPL07.INT.ENDC.6060 |
RPL07.Interior.End-Corr - Priority - Install IMP Exterior Inwall Rough-In | Priority Walls & Overhead | Not Started | 08/28/26 | 09/01/26 | 3.8 | 3.8 |
|
136.2 |
RPL07.INT.SSB.01510 |
RPL07.Interior.SSB - Loading Dock and Storage - Install Door Frames | Loading Dock and Storage | Not Started | 08/28/26 | 09/03/26 | 6.2 | 6.2 |
|
191.2 |
RPL07.INT.SSB.02900 |
RPL07.Interior.SSB - Loading Dock and Storage - Pre Priority OH & Walls Tasks (Unistruts,Hangers,Track) | Loading Dock and Storage | Not Started | 08/28/26 | 09/03/26 | 6.2 | 6.2 |
|
191.2 |
RPL07.INT.SSB.02920 |
RPL07.Interior.SSB - Loading Dock and Storage - Install Headers and Top Out and Fire/Caulking | Loading Dock and Storage | Not Started | 08/28/26 | 09/11/26 | 12.5 | 12.5 |
|
182.5 |
RPL07.INT.SSBC.01060 |
RPL07.Interior.SSB-Corridor - OFE - Early Equipment (1x SSB Elect) | OFE/MOFE & CFCI | Not Started | 08/28/26 | 09/11/26 | 12.5 | 12.5 |
|
83.8 |
RPL07.MCUP.LP2.1980 |
RPL07.MCUP.Loop 2 - Tie-in BMS #6 | Tie-Ins BMS | Not Started | 08/28/26 | 09/09/26 | 10.0 | 10.0 |
|
205.0 |
RPL07.CON.WP2.09180 |
RPL07.Conn - CorpNet & FacNet Available (mCUP) - All IDFS | WP#02 GS | Not Started | 08/31/26 | 08/31/26 | 0.0 | 0.0 |
|
420.0 |
RPL07.Conn.MS.01080 |
RPL07.Conn Wifi Ready - mCUP Yard (Pred from RPL10 CorpNet needed?) | Connectivity Milestones | Not Started | 08/31/26 | 08/31/26 | 0.0 | 0.0 |
|
256.2 |
RPL07.INT.CTRC.1160 |
RPL07.Interior.Center-Corr - Priority GL7.16/7.17 - (P2) Frame Walls (Incl. Entry Fiber Rooms #3.7, Ancillary Room #3.6) | Priority Wall Grid Line 7-16 / 7-17 | Not Started | 08/31/26 | 09/09/26 | 8.8 | 8.8 |
|
37.5 |
RPL07.INT.SSB.06840 |
RPL07.Interior.SSB - Priority - (P1) Tape Finish Paint (Both Sides) | Priority Wall - P0 | Not Started | 08/31/26 | 09/04/26 | 6.2 | 6.2 |
|
185.0 |
RPL07.EY.SSB.01175 |
RPL07.EY.SSB - Install Mechanical/refrigerantTie-ins | Tie-ins | Not Started | 09/01/26 | 09/15/26 | 12.5 | 12.5 |
|
63.8 |
RPL07.INT.DHC.01000 |
RPL07.Interior.DHC - Priority OH - WBS Summary | OverHead | Not Started | 09/01/26 | 10/29/26 | 52.5 | 52.5 |
|
318.8 |
RPL07.INT.DHC.01980 |
RPL07.Interior.DHC - Priority - Install Unistruts & Hangers (All Trades) Both side of Corridor Wall | OverHead | Not Started | 09/01/26 | 09/08/26 | 6.2 | 6.2 |
|
98.8 |
RPL07.INT.DHC.02000 |
RPL07.Interior.DHC - Priority - Install Draft Curtains (#2 - 3 Days Each) | OverHead | Not Started | 09/01/26 | 09/09/26 | 7.5 | 7.5 |
|
112.5 |
RPL07.INT.DHC.02250 |
RPL07.Interior.DHC - Priority - Install IMP Exterior Inwall Rough-In | OverHead | Not Started | 09/01/26 | 09/08/26 | 6.2 | 6.2 |
|
98.8 |
RPL07.INT.SBC.03300 |
RPL07.Interior.SSB-Corridor - BoW - Install Fire Life Safety Lowside OH and In-wall | Balance of Walls & Overhead | Not Started | 09/01/26 | 09/10/26 | 8.8 | 8.8 |
|
103.8 |
RPL07.INT.SBC.03340 |
RPL07.Interior.SSB-Corridor - BoW - Install Security Lowside OH and In-wall | Balance of Walls & Overhead | Not Started | 09/01/26 | 09/10/26 | 8.8 | 8.8 |
|
132.5 |
RPL07.SKN.DHCD.01050 |
RPL07.SKIN.DHCD - Install Lighting | Glazing, Doors and Ext Devices | Not Started | 09/02/26 | 09/08/26 | 5.0 | 5.0 |
|
322.5 |
RPL07.EY.SSB.01250 |
RPL07.EY.SSB - Install Sleeves MEPL | Hardscape and Landscape | Not Started | 09/03/26 | 09/10/26 | 6.2 | 6.2 |
|
193.8 |
RPL07.EY.SSB.01270 |
RPL07.EY.SSB - Hardscape and Landscape - WBS Summary | Hardscape and Landscape | Not Started | 09/03/26 | 06/03/27 | 232.5 | 232.5 |
|
185.0 |
GCD.RPL07.2051 |
MCUP Ready for Energization - (MCUPs Loop 1) | mCup | Not Started | 09/04/26 | 09/04/26 | 0.0 | 0.0 |
|
102.5 |
ICM.B7.1212 |
[SSDCB2] Start Flush & Fill of Chilled Water System | Commissioning | Not Started | 09/04/26 | 09/04/26 | 0.0 | 0.0 |
|
113.8 |
RPL07.CFCI.6960 |
RPL07 - Submittals Review & Approval - Gypsum Ceilings | (CFCI) Div. 09 - Gypsum System & Ceilings | Not Started | 09/04/26 | 10/02/26 | 25.0 | 25.0 |
|
115.0 |
RPL07.CX.MCUP.01010 |
RPL07.CX.mCup Loop 1 - L3/L4 - MV Skids | mCUP 1-4 | Not Started | 09/04/26 | 09/14/26 | 7.5 | 7.5 |
|
77.5 |
RPL07.CX.MCUP.01150 |
RPL07.CX.mCup Loop 1 - L3/L4 - mCUP - Flush and Fill - mCup Yard & FWM - Loop 1 (mCUPs 1-4) (Phase 1) | Fill and Flush | Not Started | 09/04/26 | 09/11/26 | 6.2 | 6.2 |
|
107.5 |
RPL07.INT.SSB.01330 |
RPL07.Interior.SSB - Loading Dock and Storage - Hang Drywall | Loading Dock and Storage | Not Started | 09/04/26 | 09/18/26 | 12.5 | 12.5 |
|
191.2 |
RPL07.MCUP.LP1.2000 |
RPL07.MCUP.Loop 1 - Install Lighting | Hardscape and Landscape | Not Started | 09/04/26 | 09/18/26 | 12.5 | 12.5 |
|
378.8 |
RPL07.MCUP.LP2.1520 |
RPL07.MCUP.Loop 2 - Install Hardscape and Landscape - WBS Summary | Hardscape and Landscape | Not Started | 09/04/26 | 10/28/26 | 47.5 | 47.5 |
|
368.8 |
RPL07.MCUP.LP2.1540 |
RPL07.MCUP.Loop 2 - Install Sleeves MEPL | Hardscape and Landscape | Not Started | 09/04/26 | 09/09/26 | 3.8 | 3.8 |
|
368.8 |
RPL07.MCUP.LP2.2040 |
RPL07.MCUP.Loop 2 - Tie-in - MV Loop 2 L2 Checklist Completion | Tie-ins | Not Started | 09/04/26 | 09/11/26 | 6.2 | 6.2 |
|
202.5 |
RPL07.INT.CTRC.9040 |
RPL07.Interior.Center-Corr - Priority GL7.16/7.17 - (P2) Install MEP In-Wall/Backing | Priority Wall Grid Line 7-16 / 7-17 | Not Started | 09/08/26 | 09/11/26 | 5.0 | 5.0 |
|
37.5 |
GCD.RPL07.1290 |
Interior fit-out Start RPL07 - DHC&D | Construction Milestones | Not Started | 09/09/26 | 09/09/26 | 0.0 | 0.0 |
|
367.5 |
GCD.RPL07.1655 |
Start MES Installation - RPL07 | Construction Milestones | Not Started | 09/09/26 | 09/09/26 | 0.0 | 0.0 |
|
67.5 |
GCD.RPL07.1700 |
Start LV Electrical Skid Set-In-Place - RPL07 | Construction Milestones | Not Started | 09/09/26 | 09/09/26 | 0.0 | 0.0 |
|
271.2 |
RPL07.INT.CTRC.1080 |
RPL07.Interior.Center-Corridor - Priority - Install Mechanical Piping/ Refrigerant (Highside OH space) | Priority Walls & Overhead | Not Started | 09/09/26 | 09/15/26 | 6.2 | 6.2 |
|
36.2 |
RPL07.INT.DHA.02340 |
RPL07.Interior.DHA - Priority - Install Security | OverHead | Not Started | 09/09/26 | 09/15/26 | 6.2 | 6.2 |
|
261.2 |
RPL07.INT.DHB.01140 |
RPL07.Interior.DHB - OFE - LV Skids and TopHat - Set / Place / Anchor | OFE/MOFE & CFCI | Not Started | 09/09/26 | 09/29/26 | 18.8 | 18.8 |
|
12.5 |
RPL07.INT.DHB.01150 |
RPL07.Interior.DHB - OFE - MES Skids - Set / Place / Anchor | OFE/MOFE & CFCI | Not Started | 09/09/26 | 09/29/26 | 18.8 | 18.8 |
|
61.2 |
RPL07.INT.DHC.02230 |
RPL07.Interior.DHC - Priority - Install Drywall at Exterior Walls | OverHead | Not Started | 09/09/26 | 09/15/26 | 6.2 | 6.2 |
|
98.8 |
RPL07.INT.ENDC.1000 |
RPL07.Interior.End-Corr - Priority - Install Unistruts & Hangers (All Trades) Both side of Corridor Wall | Priority Walls & Overhead | Not Started | 09/09/26 | 09/15/26 | 6.2 | 6.2 |
|
125.0 |
RPL07.SKN.DHCD.01060 |
RPL07.SKIN.DHCD - Install Security | Glazing, Doors and Ext Devices | Not Started | 09/09/26 | 09/10/26 | 2.5 | 2.5 |
|
322.5 |
RPL07.CFCI.5090 |
RPL07 - Fabricate / Deliver - Fire Alarm | (CFCI) Div. 26 - Fire Alarm | Not Started | 09/10/26 | 11/04/26 | 50.0 | 50.0 |
|
192.5 |
RPL07.INT.CTRC.9020 |
RPL07.Interior.Center-Corr - Priority GL7.16/7.17 - (P2) Install IMP Walls | Priority Wall Grid Line 7-16 / 7-17 | Not Started | 09/10/26 | 09/15/26 | 5.0 | 5.0 |
|
43.8 |
RPL07.INT.CTRC.9060 |
RPL07.Interior.Center-Corr - Priority GL7.16/7.17 - (P2) Hang Drywall (Both Sides) | Priority Wall Grid Line 7-16 / 7-17 | Not Started | 09/10/26 | 09/15/26 | 5.0 | 5.0 |
|
37.5 |
RPL07.INT.SBC.03320 |
RPL07.Interior.SSB-Corridor - BoW - Install Plumbing Lowside OH and In-wall | Balance of Walls & Overhead | Not Started | 09/10/26 | 09/18/26 | 8.8 | 8.8 |
|
90.0 |
RPL07.MCUP.LP2.1640 |
RPL07.MCUP.Loop 2 - Install Early Mcup Paving | Hardscape and Landscape | Not Started | 09/10/26 | 09/23/26 | 12.5 | 12.5 |
|
368.8 |
RPL07.MCUP.LP2.2080 |
RPL07.MCUP.Loop 2 - Tie-in - Mechanical L2 Checklist Completion | Tie-ins | Not Started | 09/10/26 | 09/16/26 | 6.2 | 6.2 |
|
205.0 |
RPL07.EY.SSB.01290 |
RPL07.EY.SSB - Install Trash Enclosure (CMU) | Hardscape and Landscape | Not Started | 09/11/26 | 10/08/26 | 25.0 | 25.0 |
|
218.8 |
RPL07.INT.SBC.03440 |
RPL07.Interior.SSB-Corridor - BoW - Install Electrical - Lighitng Inverter Room (XX.S2.XX) | Balance of Walls & Overhead | Not Started | 09/11/26 | 09/21/26 | 8.8 | 8.8 |
|
132.5 |
ICM.B7.1825 |
[SSDCB2] Delivery of MVS - Medium Voltage Switches (First Delivery) | Construction | Not Started | 09/14/26 | 09/14/26 | 0.0 | 0.0 |
|
25.0 |
RPL07.CX.MCUP.01190 |
RPL07.CX.mCup Loop 1 - L3/L4 - mCUP - Flush and Fill - mCup1 and Dry Coolers | Fill and Flush | Not Started | 09/14/26 | 09/21/26 | 7.5 | 7.5 |
|
107.5 |