Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL07 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:16 PM
· 5237 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
0
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL07.CX.MCUP.01210 |
RPL07.CX.mCup Loop 1 - L3/L4 - mCUP - Flush and Fill - mCup2 and Dry Coolers | Fill and Flush | Not Started | 09/14/26 | 09/21/26 | 7.5 | 7.5 |
|
107.5 |
RPL07.INT.DHB.01180 |
RPL07.Interior.DHB - LV Skids and TopHat Tie-ins (LOE) | DHB - LV Skids and TopHat | Not Started | 09/14/26 | 10/13/26 | 27.5 | 27.5 |
|
80.0 |
RPL07.INT.DHB.01181 |
RPL07.Interior.DHB - LV Skids and TopHat - Set & Anchor Interconnects | DHB - LV Skids and TopHat | Not Started | 09/14/26 | 10/01/26 | 17.5 | 17.5 |
|
80.0 |
RPL07.INT.DHB.01190 |
RPL07.Interior.DHB - Tie-ins - WBS Summary | Tie-Ins | Not Started | 09/14/26 | 04/12/27 | 178.8 | 178.8 |
|
77.5 |
RPL07.INT.SSB.03080 |
RPL07.Interior.SSB - Loading Dock and Storage - Tape Finish Paint (Top Out) | Loading Dock and Storage | Not Started | 09/14/26 | 09/23/26 | 10.0 | 10.0 |
|
182.5 |
RPL07.INT.SSB.14000 |
RPL07.Interior.Center-Corridor Leave Out #01 #02 #03 #04 #5 - SSB (for Elec. Room) WBS Summary | Interior Leave Out Wall #01, #02, #03, #04, #05 SSB for Electrical Room | Not Started | 09/14/26 | 01/28/27 | 116.2 | 116.2 |
|
87.5 |
RPL07.INT.SSB.14020 |
RPL07.Interior.SSB LO #01 to #05 - Install LO Framing | OH & Framing | Not Started | 09/14/26 | 09/18/26 | 6.2 | 6.2 |
|
87.5 |
RPL07.MCUP.LP2.2060 |
RPL07.MCUP.Loop 2 - Tie-in - Electrical L2 Checklist Completion | Tie-ins | Not Started | 09/14/26 | 09/18/26 | 6.2 | 6.2 |
|
202.5 |
GCD.RPL07.1826 |
Delivery of RMU - (First Delivery) - RPL07 - DHA&B | Construction Milestones | Not Started | 09/15/26 | 09/15/26 | 0.0 | 0.0 |
|
23.8 |
RPL07.CX.MCUP.01040 |
RPL07.CX.mCup Loop 1 - L3/L4 - mCUP - FWM | mCUP 1-4 | Not Started | 09/15/26 | 09/28/26 | 12.5 | 12.5 |
|
82.5 |
RPL07.EY.DHB.01220 |
RPL07.EY.DHB - Install MV, RMUs & Electrical Panels (Qty 10) | OFE | Not Started | 09/16/26 | 10/13/26 | 25.0 | 25.0 |
|
23.8 |
RPL07.EY.DHB.01230 |
RPL07.EY.DHB - OFE - MV - WBS Summary | OFE | Not Started | 09/16/26 | 11/16/26 | 53.8 | 53.8 |
|
152.5 |
RPL07.EY.SSB.01260 |
RPL07.EY.SSB - L2 Checklist Completion | Tie-ins | Not Started | 09/16/26 | 09/29/26 | 12.5 | 12.5 |
|
63.8 |
RPL07.INT.CTRC.01070 |
RPL07.Interior.Center-Corridor - BoW - Early MEPF Inwall Rough-In for Ancillary Skid (Room #3.6) | Priority Wall Grid Line 7-16 / 7-17 | Not Started | 09/16/26 | 09/18/26 | 3.8 | 3.8 |
|
140.0 |
RPL07.INT.CTRC.01130 |
RPL07.Interior.Center-Corridor - OFE - DHB (1x GS.IDF) B2 | OFE/MOFE & CFCI | Not Started | 09/16/26 | 09/22/26 | 6.2 | 6.2 |
|
110.0 |
RPL07.INT.CTRC.01200 |
RPL07.Interior.Center-Corridor - OFE - DHA (1x GS.IDF) A2 | OFE/MOFE & CFCI | Not Started | 09/16/26 | 09/22/26 | 6.2 | 6.2 |
|
110.0 |
RPL07.INT.CTRC.1120 |
RPL07.Interior.Center-Corridor - Priority - Install Plumbing (Highside OH space) | Priority Walls & Overhead | Not Started | 09/16/26 | 09/22/26 | 6.2 | 6.2 |
|
36.2 |
RPL07.INT.CTRC.8940 |
RPL07.Interior.Center-Corr - Priority - All MEP In-Wall in Entry Fiber Rooms (Room #2.7) | Priority Wall Grid Line 7-16 / 7-17 | Not Started | 09/16/26 | 09/24/26 | 8.8 | 8.8 |
|
66.2 |
RPL07.INT.CTRC.9080 |
RPL07.Interior.Center-Corr - Priority GL7.16/7.17 - (P2) Tape Finish Paint (Both Sides) | Priority Wall Grid Line 7-16 / 7-17 | Not Started | 09/16/26 | 09/22/26 | 6.2 | 6.2 |
|
37.5 |
RPL07.INT.DHA.02325 |
RPL07.Interior.DHA - Priority - Install Controls / EPMS / BMS | OverHead | Not Started | 09/16/26 | 09/21/26 | 5.0 | 5.0 |
|
261.2 |
RPL07.INT.DHB.01200 |
RPL07.Interior.DHB - MES Skids Tie-ins (LOE) | DHB - MES Skids | Not Started | 09/16/26 | 10/29/26 | 40.0 | 40.0 |
|
80.0 |
RPL07.INT.DHB.01201 |
RPL07.Interior.DHB - MES Skids - Set & Anchor Interconnects | DHB - MES Skids | Not Started | 09/16/26 | 10/13/26 | 25.0 | 25.0 |
|
61.2 |
RPL07.INT.DHC.02110 |
RPL07.Interior.DHC - Priority - Install Plumbing | OverHead | Not Started | 09/16/26 | 09/22/26 | 6.2 | 6.2 |
|
98.8 |
RPL07.INT.DHD.01050 |
RPL07.Interior.DHD - Priority - Install FA / Linear heat detection | OverHead | Not Started | 09/16/26 | 09/22/26 | 6.2 | 6.2 |
|
88.8 |
RPL07.INT.DHD.02130 |
RPL07.Interior.DHD - Priority - Install Mechanical Piping | OverHead | Not Started | 09/16/26 | 10/01/26 | 15.0 | 15.0 |
|
83.8 |
RPL07.INT.DHD.02150 |
RPL07.Interior.DHD - Priority - Install Electrical | OverHead | Not Started | 09/16/26 | 09/29/26 | 12.5 | 12.5 |
|
88.8 |
RPL07.INT.ENDC.01120 |
RPL07.Interior.End-Corridor - Frame Remaining Walls | Fit out | Not Started | 09/16/26 | 09/21/26 | 5.0 | 5.0 |
|
161.2 |
RPL07.INT.ENDC.01130 |
RPL07.Interior.End-Corridor - Install Fitout (Restroom, Janitor, Fire Riser, Humidifier) - WBS Summary | Fit out | Not Started | 09/16/26 | 07/13/27 | 256.2 | 256.2 |
|
102.5 |
RPL07.INT.ENDC.1920 |
RPL07.Interior.End-Corr - Priority - Install Drywall at Exterior Walls | Priority Walls & Overhead | Not Started | 09/16/26 | 09/22/26 | 6.2 | 6.2 |
|
125.0 |
RPL07.CFCI.4830 |
RPL07 - Submittals Prep & Submit for Review - Carpet | (CFCI) Div. 09 - Carpet | Not Started | 09/17/26 | 10/14/26 | 25.0 | 25.0 |
|
131.2 |
RPL07.CFCI.4880 |
RPL07 - Submittals Review & Approval -Epoxy Flooring (Spec 09 67 23) XX | (CFCI) Div. 09 - Epoxy Flooring | Not Started | 09/17/26 | 10/14/26 | 25.0 | 25.0 |
|
187.5 |
RPL07.CFCI.5060 |
RPL07 - Fabricate / Deliver - Interior Painting (Spec 09 91 23) XX | (CFCI) Div. 09 - Painting | Not Started | 09/17/26 | 10/14/26 | 25.0 | 25.0 |
|
168.8 |
RPL07.CFCI.5070 |
RPL07 - Submittals Review & Approval - Specialities | (CFCI) Div. 10 - Specialities | Not Started | 09/17/26 | 10/14/26 | 25.0 | 25.0 |
|
117.5 |
RPL07.CX.MCUP.01020 |
RPL07.CX.mCup Loop 2 - L3, L4, IST - WBS Summary | mCUP 5-6 | Not Started | 09/17/26 | 02/11/27 | 125.0 | 125.0 |
|
235.0 |
RPL07.CX.MCUP.01100 |
RPL07.CX.mCup Loop 2 - L3/L4 - mCUP - Flush and Fill - mCup Yard - Loop 2 (mCUPs 5-6) (Phase 3) | Fill and Flush | Not Started | 09/17/26 | 09/23/26 | 6.2 | 6.2 |
|
235.0 |
RPL07.EY.ENDC.1910 |
RPL07.EY.DHD.T1 - HAC Prefab prior to install for DH B | Tent 1 | Not Started | 09/17/26 | 09/23/26 | 6.2 | 6.2 |
|
30.0 |
RPL07.INT.CTRC.1140 |
RPL07.Interior.Center-Corridor - Priority - Install FA/ VESDA/ hangers & Heat Trace (Highside OH space) | Priority Walls & Overhead | Not Started | 09/17/26 | 09/23/26 | 6.2 | 6.2 |
|
36.2 |
RPL07.INT.SSBC.01090 |
RPL07.Interior.SSB-Corridor - OFE - Early Equipment (1x GS.MDF piece 1 of 2) - 7GSMDF2 | OFE/MOFE & CFCI | Not Started | 09/17/26 | 09/23/26 | 6.2 | 6.2 |
|
67.5 |
RPL07.INT.DHB.01182 |
RPL07.Interior.DHB - LV Skids and TopHat - Maintenance and Reserve Busways | DHB - LV Skids and TopHat | Not Started | 09/18/26 | 10/06/26 | 16.2 | 16.2 |
|
80.0 |
GCD.RPL07.3985 |
MCUP Ready for Energization - (MCUPs Loop 2) | mCup | Not Started | 09/21/26 | 09/21/26 | 0.0 | 0.0 |
|
311.2 |
RPL07.CX.MCUP.01030 |
RPL07.CX.mCup Loop 2 - L3/L4 - MV Skids | mCUP 5-6 | Not Started | 09/21/26 | 09/24/26 | 5.0 | 5.0 |
|
202.5 |
RPL07.INT.CTRC.01090 |
RPL07.Interior.Center-Corridor - BoW - Early Install Drywall for Ancillary Skid (Room #3.6) | Priority Wall Grid Line 7-16 / 7-17 | Not Started | 09/21/26 | 09/23/26 | 3.8 | 3.8 |
|
140.0 |
RPL07.INT.SBC.03360 |
RPL07.Interior.SSB-Corridor - BoW - Install VAV's/Duct Branches | Balance of Walls & Overhead | Not Started | 09/21/26 | 09/25/26 | 6.2 | 6.2 |
|
161.2 |
RPL07.INT.SBC.03460 |
RPL07.Interior.SSB-Corridor - BoW - Mechanical Tie-In | Balance of Walls & Overhead | Not Started | 09/21/26 | 09/25/26 | 6.2 | 6.2 |
|
90.0 |
RPL07.INT.SSB.14060 |
RPL07.Interior.SSB LO #01 to #05 - Install In-Wall Rough-in | OH & Framing | Not Started | 09/21/26 | 09/22/26 | 2.5 | 2.5 |
|
87.5 |
RPL07.INT.SSBC.03380 |
RPL07.Interior.SSB-Corridor - Install Split Systems/Humidifiers | OFE/MOFE & CFCI | Not Started | 09/21/26 | 09/25/26 | 6.2 | 6.2 |
|
167.5 |
RPL07.MCUP.LP1.2040 |
RPL07.MCUP.Loop 1 - Install Mcup Paving | Hardscape and Landscape | Not Started | 09/21/26 | 10/02/26 | 12.5 | 12.5 |
|
378.8 |
RPL07.CX.MCUP.01230 |
RPL07.CX.mCup Loop 1 - L3/L4 - mCUP - Flush and Fill - mCup3 and Dry Coolers | Fill and Flush | Not Started | 09/22/26 | 09/29/26 | 7.5 | 7.5 |
|
107.5 |
RPL07.CX.MCUP.01250 |
RPL07.CX.mCup Loop 1 - L3/L4 - mCUP - Flush and Fill - mCup4 and Dry Coolers | Fill and Flush | Not Started | 09/22/26 | 09/29/26 | 7.5 | 7.5 |
|
110.0 |
RPL07.INT.ENDC.01140 |
RPL07.Interior.End-Corridor - Install Doors Frame Hardware | Fit out | Not Started | 09/22/26 | 09/28/26 | 6.2 | 6.2 |
|
163.8 |
RPL07.INT.ENDC.01150 |
RPL07.Interior.End-Corridor - Install Electrical OH and In-wall | Fit out | Not Started | 09/22/26 | 09/30/26 | 8.8 | 8.8 |
|
161.2 |
RPL07.INT.ENDC.06940 |
RPL07.Interior.End-Corridor - Final Finishes & Fixtures - Frame/Blocking Walls & Ceilings | Restrooms | Not Started | 09/22/26 | 10/05/26 | 12.5 | 12.5 |
|
173.8 |
RPL07.CON.WP2.06000 |
RPL07.Conn - Interior GSIDFs - WBS Summary | GS.IDF (Interior) | Not Started | 09/23/26 | 06/01/27 | 213.8 | 213.8 |
|
187.5 |
RPL07.CON.WP2.06200 |
RPL07.Conn - GSIDF/DH B2 - WBS Summary | Int. IDF OFE/MOFE - GSIDF7B2 | Not Started | 09/23/26 | 10/20/26 | 25.0 | 25.0 |
|
345.0 |
RPL07.CON.WP2.06220 |
RPL07.Conn - GSIDF/DH B2 - Install Infrastructure (Racks, Waterfalls etc.) | Infrastructure | Not Started | 09/23/26 | 09/29/26 | 6.2 | 6.2 |
|
216.2 |
RPL07.CON.WP2.06400 |
RPL07.Conn - GSIDF/DH A2 - WBS Summary | Int. IDF OFE/MOFE - GSIDF7A2 | Not Started | 09/23/26 | 10/20/26 | 25.0 | 25.0 |
|
345.0 |
RPL07.CON.WP2.06420 |
RPL07.Conn - GSIDF/DH A2 - Install Infrastructure (Racks, Waterfalls etc.) | Infrastructure | Not Started | 09/23/26 | 09/29/26 | 6.2 | 6.2 |
|
228.8 |
RPL07.INT.CTRC.01160 |
RPL07.Interior.Center-Corridor (N) - Install Fitout (Spoke Parts, Tech, SCR etc.) - WBS Summary | Fit out (North) | Not Started | 09/23/26 | 04/28/27 | 185.0 | 185.0 |
|
56.2 |
RPL07.INT.CTRC.01460 |
RPL07.Interior.Center-Corridor (N) - Install Lighting | Fit out (North) | Not Started | 09/23/26 | 10/01/26 | 8.8 | 8.8 |
|
170.0 |
RPL07.INT.DHA.01060 |
RPL07.Interior.DHA - OFE - LV Skids and TopHat - Set / Place / Anchor | OFE/MOFE & CFCI | Not Started | 09/23/26 | 10/13/26 | 18.8 | 18.8 |
|
12.5 |
RPL07.INT.DHA.01070 |
RPL07.Interior.DHA - OFE - MES Skids - Set / Place / Anchor | OFE/MOFE & CFCI | Not Started | 09/23/26 | 10/13/26 | 18.8 | 18.8 |
|
48.8 |
RPL07.INT.DHB.01210 |
RPL07.Interior.DHB - OFE - Control Fault Domain 1 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | Control Fault Domain 1 | Not Started | 09/23/26 | 10/22/26 | 27.5 | 27.5 |
|
33.8 |
RPL07.INT.DHB.02400 |
RPL07.Interior.DHB - OFE - Control Fault Domain 1 (LV Side Aisle) | Control Fault Domain 1 | Not Started | 09/23/26 | 09/29/26 | 6.2 | 6.2 |
|
12.5 |
RPL07.INT.DHD.02210 |
RPL07.Interior.DHD - Priority - Install Temp Doors Frame Hardware | OverHead | Not Started | 09/23/26 | 09/25/26 | 3.8 | 3.8 |
|
333.8 |
RPL07.INT.ENDC.1080 |
RPL07.Interior.End-Corr - Priority - Tape Finish Paint Priority Soffit both sides (Top Out) & Draft Blanket | Priority Walls & Overhead | Not Started | 09/23/26 | 10/01/26 | 8.8 | 8.8 |
|
125.0 |
RPL07.INT.ENDC.1100 |
RPL07.Interior.End-Corr - Priority - Install Mechanical Piping/ Refrigerant (Highside OH space) | Priority Walls & Overhead | Not Started | 09/23/26 | 09/29/26 | 6.2 | 6.2 |
|
127.5 |
RPL07.INT.SSB.14080 |
RPL07.Interior.SSB LO #01 to #05 - Install Mechanical Piping & Refrigerant Lowside OH and in-wall | OH & Framing | Not Started | 09/23/26 | 09/25/26 | 3.8 | 3.8 |
|
87.5 |
RPL07.CFCI.5370 |
Campus - Fabricate / Deliver - Landscaping / Irrigation | (CFCI) Div. 32 - Landscape/ Irrigation | Not Started | 09/24/26 | 12/21/26 | 75.0 | 75.0 |
|
287.5 |
RPL07.CON.WP2.04000 |
RPL07.Conn - GSMDF2 (North) - WBS Summary | GS.MDF2 (North) | Not Started | 09/24/26 | 12/16/26 | 71.2 | 71.2 |
|
266.2 |
RPL07.CON.WP2.07880 |
RPL07.Conn - GSMDF2 (North) Set Infrastructure (Wall mounting enclosures, Tier1 Basket Tray, Waterfalls etc.) | Infrastructure | Not Started | 09/24/26 | 09/28/26 | 3.8 | 3.8 |
|
198.8 |
RPL07.INT.CTRC.01110 |
RPL07.Interior.Center-Corridor - BoW - Early Tape Finish Paint for Ancillary Skid (Room #3.6) | Priority Wall Grid Line 7-16 / 7-17 | Not Started | 09/24/26 | 09/30/26 | 6.2 | 6.2 |
|
140.0 |
RPL07.INT.CTRC.1200 |
RPL07.Interior.Center-Corridor - Priority - Install Fire Safing/ Seal Penetrations through Soffit (Highside OH space) | Priority Walls & Overhead | Not Started | 09/24/26 | 09/28/26 | 3.8 | 3.8 |
|
36.2 |
RPL07.INT.CTRC.1220 |
RPL07.Interior.Center-Corridor - BoW - Frame Balance of Wall | Balance of Walls & Overhead | Not Started | 09/24/26 | 09/30/26 | 6.2 | 6.2 |
|
36.2 |
RPL07.INT.CTRC.1230 |
RPL07.Interior.Center-Corridor - BoW - Balance Of Wall (ERAD, Maintance, Network infra, Spoke, Bathroom,etc)-WBS Summary | Balance of Walls & Overhead | Not Started | 09/24/26 | 04/01/27 | 160.0 | 160.0 |
|
36.2 |
RPL07.INT.CTRC.2020 |
RPL07.Interior.Center-Corridor - Priority - Fixed Draft Smoke Curtains Patching | Priority Walls & Overhead | Not Started | 09/24/26 | 09/28/26 | 3.8 | 3.8 |
|
36.2 |
RPL07.INT.DHB.01202 |
RPL07.Interior.DHB - MES Skids - Piping Tie-Ins & Inspections | DHB - MES Skids | Not Started | 09/24/26 | 10/21/26 | 25.0 | 25.0 |
|
61.2 |
RPL07.INT.DHB.02420 |
RPL07.Interior.DHB - OFE - Control Fault Domain 1 (HAC) | Control Fault Domain 1 | Not Started | 09/24/26 | 10/21/26 | 25.0 | 25.0 |
|
30.0 |
RPL07.INT.SSB.01190 |
RPL07.Interior.SSB - Loading Dock and Storage - Install Electrical Rough-In | Loading Dock and Storage | Not Started | 09/24/26 | 10/02/26 | 8.8 | 8.8 |
|
182.5 |
RPL07.INT.SSB.01740 |
RPL07.Interior.SSB - Loading Dock and Storage - Install VAV's/Duct Branches | Loading Dock and Storage | Not Started | 09/24/26 | 10/07/26 | 12.5 | 12.5 |
|
188.8 |
RPL07.INT.SSB.02940 |
RPL07.Interior.SSB - Loading Dock and Storage - Install Blocking/Steel support Assembly for Metal Canopy | Loading Dock and Storage | Not Started | 09/24/26 | 09/30/26 | 6.2 | 6.2 |
|
192.5 |
RPL07.INT.SSBC.01140 |
RPL07.Interior.SSB-Corridor - OFE - Early Equipment (1x GS.MDF piece 2 of 2) - 7GSMDF1 | OFE/MOFE & CFCI | Not Started | 09/24/26 | 09/30/26 | 6.2 | 6.2 |
|
67.5 |
RPL07.INT.SSBC.3000 |
RPL07.Interior.SSBC LO #06 - Close Interior LO #06 SSB/SSBC (For MDF2) WBS Summary | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 09/24/26 | 12/10/26 | 66.2 | 66.2 |
|
93.8 |
RPL07.INT.SSBC.3020 |
RPL07.Interior.SSBC LO #06 - Install Framing at LO | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 09/24/26 | 09/30/26 | 6.2 | 6.2 |
|
93.8 |
RPL07.MCUP.LP2.1760 |
RPL07.MCUP.Loop 2 - Install Lighting | Hardscape and Landscape | Not Started | 09/24/26 | 09/30/26 | 6.2 | 6.2 |
|
368.8 |
RPL07.INT.CTRC.8960 |
RPL07.Interior.Center-Corr - Priority - Hang Drywall Rock all Entry Fiber Rooms (Room #2.7) | Priority Wall Grid Line 7-16 / 7-17 | Not Started | 09/25/26 | 09/30/26 | 5.0 | 5.0 |
|
66.2 |
RPL07.INT.DHA.01090 |
RPL07.Interior.DHA - LV Skids and TopHat Tie-ins (LOE) | DHA - LV Skids and TopHat | Not Started | 09/25/26 | 10/26/26 | 27.5 | 27.5 |
|
81.2 |
RPL07.INT.DHA.01091 |
RPL07.Interior.DHA - LV Skids and TopHat - Set & Anchor Interconnects | DHA - LV Skids and TopHat | Not Started | 09/25/26 | 10/14/26 | 17.5 | 17.5 |
|
81.2 |
RPL07.INT.DHA.01100 |
RPL07.Interior.DHA - Tie-ins - WBS Summary | Tie-Ins | Not Started | 09/25/26 | 03/30/27 | 156.2 | 156.2 |
|
101.2 |
RPL07.INT.DHB.01183 |
RPL07.Interior.DHB - LV Skids and TopHat - Top Hat Busway | DHB - LV Skids and TopHat | Not Started | 09/25/26 | 10/13/26 | 16.2 | 16.2 |
|
80.0 |
RPL07.INT.DHB.01250 |
RPL07.Interior.DHB - Tie-ins - Control Fault Domain 1 - WBS Summary | Control Fault Domain 1 | Not Started | 09/25/26 | 12/10/26 | 65.0 | 65.0 |
|
33.8 |
RPL07.INT.DHB.02700 |
RPL07.Interior.DHB - Control Fault Domain 1 - Install Duct (LV Side) | LV Side Tie-ins | Not Started | 09/25/26 | 10/01/26 | 6.2 | 6.2 |
|
48.8 |
RPL07.INT.DHB.01203 |
RPL07.Interior.DHB - MES Skids - CDU Tie-Ins | DHB - MES Skids | Not Started | 09/28/26 | 10/23/26 | 25.0 | 25.0 |
|
80.0 |
RPL07.INT.SBC.03400 |
RPL07.Interior.SSB-Corridor - BoW - Install Controls / EPMS / BMS OH and In-wall | Balance of Walls & Overhead | Not Started | 09/28/26 | 10/02/26 | 6.2 | 6.2 |
|
161.2 |
RPL07.INT.SBC.03480 |
RPL07.Interior.SSB-Corridor - BoW - Frame Hard Lid | Balance of Walls & Overhead | Not Started | 09/28/26 | 10/02/26 | 6.2 | 6.2 |
|
90.0 |
RPL07.INT.SSB.14100 |
RPL07.Interior.SSB LO #01 to #05 - Install Fire Life Safety Lowside OH and In-wall | OH & Framing | Not Started | 09/28/26 | 09/28/26 | 1.2 | 1.2 |
|
110.0 |
RPL07.INT.SSB.14120 |
RPL07.Interior.SSB LO #01 to #05 - Install Plumbing Lowside OH and In-wall | OH & Framing | Not Started | 09/28/26 | 09/29/26 | 2.5 | 2.5 |
|
87.5 |
GCD.RPL07.1725 |
Start FSHAC set in place - RPL07 - DHA&B | Construction Milestones | Not Started | 09/29/26 | 09/29/26 | 0.0 | 0.0 |
|
253.8 |
RPL07.CON.WP2.09240 |
RPL07.Conn - GSMDF2 (North) - Install Copper, WAPs, Security Camera & Access Control | ISP (MDF RPL07 <> MDF RPL07) | Not Started | 09/29/26 | 10/14/26 | 15.0 | 15.0 |
|
217.5 |
RPL07.INT.DHB.01310 |
RPL07.Interior.DHB - Control Fault Domain 1 - Install LV Side Aisle HAC Busway | LV Side Tie-ins | Not Started | 09/29/26 | 10/05/26 | 6.2 | 6.2 |
|
57.5 |
RPL07.INT.DHB.02440 |
RPL07.Interior.DHB - OFE - Control Fault Domain 1 (Mech Side Aisle) | Control Fault Domain 1 | Not Started | 09/29/26 | 10/22/26 | 22.5 | 22.5 |
|
33.8 |