Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL07 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:16 PM
· 5237 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
0
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL07.INT.SSB.14140 |
RPL07.Interior.SSB LO #01 to #05 - Install Security Lowside OH and In-wall | OH & Framing | Not Started | 09/29/26 | 09/30/26 | 2.5 | 2.5 |
|
110.0 |
RPL07.CON.WP2.06240 |
RPL07.Conn - GSIDF/DH B2 - Install Cabling (Pull, Splice & terminate) | Cabling | Not Started | 09/30/26 | 10/07/26 | 7.5 | 7.5 |
|
352.5 |
RPL07.CON.WP2.06260 |
RPL07.Conn - GSIDF/DH B2 - Install Copper, WAPs, Security Camera & Access Control | Cabling | Not Started | 09/30/26 | 10/15/26 | 15.0 | 15.0 |
|
216.2 |
RPL07.CON.WP2.06440 |
RPL07.Conn - GSIDF/DH A2 - Install Cabling (Pull, Splice & terminate) | Cabling | Not Started | 09/30/26 | 10/07/26 | 7.5 | 7.5 |
|
352.5 |
RPL07.CON.WP2.06460 |
RPL07.Conn - GSIDF/DH A2 - Install Copper, WAPs, Security Camera & Access Control | Cabling | Not Started | 09/30/26 | 10/15/26 | 15.0 | 15.0 |
|
228.8 |
RPL07.EY.DHA.01220 |
RPL07.EY.DHA - Install MV, RMUs & Electrical Panels (Qty 10) | OFE | Not Started | 09/30/26 | 10/27/26 | 25.0 | 25.0 |
|
30.0 |
RPL07.INT.DHA.01110 |
RPL07.Interior.DHA - MES Skids Tie-ins (LOE) | DHA - MES Skids | Not Started | 09/30/26 | 11/13/26 | 40.0 | 40.0 |
|
67.5 |
RPL07.INT.DHA.01111 |
RPL07.Interior.DHA - MES Skids - Set & Anchor Interconnects | DHA - MES Skids | Not Started | 09/30/26 | 10/27/26 | 25.0 | 25.0 |
|
48.8 |
RPL07.INT.DHB.01204 |
RPL07.Interior.DHB - MES Skids - BMS Tie-Ins | DHB - MES Skids | Not Started | 09/30/26 | 10/27/26 | 25.0 | 25.0 |
|
80.0 |
RPL07.INT.DHB.01320 |
RPL07.Interior.DHB - OFE - Control Fault Domain 2 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | Control Fault Domain 2 | Not Started | 09/30/26 | 11/13/26 | 40.0 | 40.0 |
|
40.0 |
RPL07.INT.DHB.01330 |
RPL07.Interior.DHB - Control Fault Domain 1 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 09/30/26 | 10/06/26 | 6.2 | 6.2 |
|
57.5 |
RPL07.INT.DHB.02460 |
RPL07.Interior.DHB - OFE - Control Fault Domain 2 (LV Side Aisle) | Control Fault Domain 2 | Not Started | 09/30/26 | 10/05/26 | 5.0 | 5.0 |
|
48.8 |
RPL07.INT.DHD.02170 |
RPL07.Interior.DHD - Priority - Install Security | OverHead | Not Started | 09/30/26 | 10/01/26 | 2.5 | 2.5 |
|
331.2 |
RPL07.INT.ENDC.1140 |
RPL07.Interior.End-Corr - Priority - Install Plumbing (Highside OH space) | Priority Walls & Overhead | Not Started | 09/30/26 | 10/06/26 | 6.2 | 6.2 |
|
127.5 |
RPL07.INT.ENDC.1160 |
RPL07.Interior.End-Corr - Priority - Install FA (Highside OH space) | Priority Walls & Overhead | Not Started | 09/30/26 | 10/06/26 | 6.2 | 6.2 |
|
127.5 |
RPL07.INT.SSB.14160 |
RPL07.Interior.SSB LO #01 to #05 - Install Controls / EPMS / BMS OH and In-wall | OH & Framing | Not Started | 09/30/26 | 10/01/26 | 2.5 | 2.5 |
|
87.5 |
RPL07.CON.WP2.05000 |
RPL07.Conn - GSMDF1 (South) - WBS Summary | GS.MDF1 (South) | Not Started | 10/01/26 | 12/16/26 | 65.0 | 65.0 |
|
266.2 |
RPL07.CON.WP2.07960 |
RPL07.Conn - GSMDF1 (South) Set Infrastructure (Wall mounting enclosures, Tier1 Basket Tray, Waterfalls etc.) | Infrastructure | Not Started | 10/01/26 | 10/05/26 | 3.8 | 3.8 |
|
205.0 |
RPL07.CON.WP4.00010 |
RPL07.Conn - Network - WBS Summary | WP#4 Network | Not Started | 10/01/26 | 08/11/27 | 268.8 | 268.8 |
|
125.0 |
RPL07.EY.ENDC.1930 |
RPL07.EY.DHD.T2 - HAC Prefab prior to install for DH A | Tent 2 | Not Started | 10/01/26 | 10/07/26 | 6.2 | 6.2 |
|
12.5 |
RPL07.INT.CTRC.1260 |
RPL07.Interior.Center-Corridor - BoW - Install Electrical Lowside OH and In-wall and Lights (Coordinate Lights location | Balance of Walls & Overhead | Not Started | 10/01/26 | 10/14/26 | 12.5 | 12.5 |
|
36.2 |
RPL07.INT.CTRC.1400 |
RPL07.Interior.Center-Corridor - BoW - Install Door Frames | Balance of Walls & Overhead | Not Started | 10/01/26 | 10/07/26 | 6.2 | 6.2 |
|
51.2 |
RPL07.INT.CTRC.8980 |
RPL07.Interior.Center-Corr - Priority - Tape, Paint & Finish Entry Fiber Rooms (Room #2.7) | Priority Wall Grid Line 7-16 / 7-17 | Not Started | 10/01/26 | 10/07/26 | 6.2 | 6.2 |
|
66.2 |
RPL07.INT.DHA.01092 |
RPL07.Interior.DHA - LV Skids and TopHat - Maintenance and Reserve Busways | DHA - LV Skids and TopHat | Not Started | 10/01/26 | 10/19/26 | 16.2 | 16.2 |
|
81.2 |
RPL07.INT.ENDC.01170 |
RPL07.Interior.End-Corridor - Install Security OH and In-wall | Fit out | Not Started | 10/01/26 | 10/09/26 | 8.8 | 8.8 |
|
161.2 |
RPL07.INT.ENDC.01180 |
RPL07.Interior.End-Corridor - Install Plumbing OH and In-wall | Fit out | Not Started | 10/01/26 | 10/13/26 | 11.2 | 11.2 |
|
163.8 |
RPL07.INT.SSB.01880 |
RPL07.Interior.SSB - Final Finishes & Fixtures - Frame/Blocking Walls & Ceilings | Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) | Not Started | 10/01/26 | 10/14/26 | 12.5 | 12.5 |
|
210.0 |
RPL07.INT.SSBC.3080 |
RPL07.Interior.SSBC LO #06 - Install Mechanical Piping Lowside OH and in-wall | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 10/01/26 | 10/02/26 | 2.5 | 2.5 |
|
93.8 |
RPL07.INT.SSBC.4000 |
RPL07.Interior.SSBC LO #07 - Close Interior LO #07 SSB/SSBC (For MDF1) WBS Summary | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 10/01/26 | 12/17/26 | 66.2 | 66.2 |
|
87.5 |
RPL07.INT.SSBC.4020 |
RPL07.Interior.SSBC LO #07 - Install Framing at LO | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 10/01/26 | 10/07/26 | 6.2 | 6.2 |
|
87.5 |
RPL07.MCUP.LP2.1860 |
RPL07.MCUP.Loop 2 - Install Mcup Paving | Hardscape and Landscape | Not Started | 10/01/26 | 10/14/26 | 12.5 | 12.5 |
|
368.8 |
RPL07.SKN.SSB.01125 |
RPL07.SKIN.SSB - Install Metal Canopy | Glazing, Doors and Ext Devices | Not Started | 10/01/26 | 10/02/26 | 2.5 | 2.5 |
|
206.2 |
RPL07.SKN.W.LO.01120 |
RPL07.SKIN.LO#16 - Close Exterior Leave Out #16 SSB (North of Loading Dock) WBS Summary | Build back Exterior Leave Out Walls #16 (SSB - North of Loading Dock) | Not Started | 10/01/26 | 11/16/26 | 40.0 | 40.0 |
|
67.5 |
RPL07.SKN.W.LO.01380 |
RPL07.SKIN.LO#16 - Pour back Stemwall | Build back Exterior Leave Out Walls #16 (SSB - North of Loading Dock) | Not Started | 10/01/26 | 10/07/26 | 6.2 | 6.2 |
|
67.5 |
RPL07.WP4.010000 |
RPL07.Conn GSMDF1 Pull Fanout (5F) [PON (Active, In-Row)] | GSMDF1 | Not Started | 10/01/26 | 10/01/26 | 1.2 | 1.2 |
|
217.5 |
RPL07.INT.DHB.01205 |
RPL07.Interior.DHB - MES Skids - EPMS Tie-Ins | DHB - MES Skids | Not Started | 10/02/26 | 10/29/26 | 25.0 | 25.0 |
|
80.0 |
RPL07.INT.DHB.01380 |
RPL07.Interior.DHB - Tie-ins - Control Fault Domain 2 - WBS Summary | Control Fault Domain 2 | Not Started | 10/02/26 | 01/11/27 | 83.8 | 83.8 |
|
40.0 |
RPL07.INT.DHB.02720 |
RPL07.Interior.DHB - Control Fault Domain 2 - Install Duct (LV Side) | LV Side Tie-ins | Not Started | 10/02/26 | 10/07/26 | 5.0 | 5.0 |
|
73.8 |
RPL07.INT.DHC.02130 |
RPL07.Interior.DHC - Priority - Install Mechanical Piping | OverHead | Not Started | 10/02/26 | 10/19/26 | 15.0 | 15.0 |
|
83.8 |
RPL07.INT.DHD.02190 |
RPL07.Interior.DHD - Priority - Install Controls / EPMS / BMS | OverHead | Not Started | 10/02/26 | 10/06/26 | 3.8 | 3.8 |
|
331.2 |
RPL07.INT.ENDC.1120 |
RPL07.Interior.End-Corr - Priority GL7.27 - (P3) Frame Wall (Incl. Ancillary Room #3.6) | Priority Wall Grid Line 7-27 | Not Started | 10/02/26 | 10/08/26 | 6.2 | 6.2 |
|
125.0 |
RPL07.INT.SSB.14240 |
RPL07.Interior.SSB LO #01 to #05 - Install Electrical Lowside OH and In-wall | OH & Framing | Not Started | 10/02/26 | 10/12/26 | 8.8 | 8.8 |
|
87.5 |
RPL07.WP4.010020 |
RPL07.Conn GSMDF2 Pull Fanout (5F) [PON (Active, In-Row)] | GSMDF2 | Not Started | 10/02/26 | 10/02/26 | 1.2 | 1.2 |
|
217.5 |
RPL07.WP4.010040 |
RPL07.Conn GSMDF1 Install Fanout (5F) [PON (Active, In-Row)] | GSMDF1 | Not Started | 10/02/26 | 10/16/26 | 13.8 | 13.8 |
|
218.8 |
RPL07.CFCI.6980 |
RPL07 - Fabricate / Deliver - Gypsum Ceilings | (CFCI) Div. 09 - Gypsum System & Ceilings | Not Started | 10/05/26 | 10/30/26 | 25.0 | 25.0 |
|
115.0 |
RPL07.INT.SBC.03500 |
RPL07.Interior.SSB-Corridor - BoW - MEPF Hard Lid Rough-In/ Close of Inspection | Balance of Walls & Overhead | Not Started | 10/05/26 | 10/13/26 | 8.8 | 8.8 |
|
100.0 |
RPL07.INT.SBC.03520 |
RPL07.Interior.SSB-Corridor - BoW - Install Blocking/Steel support Assembly for Metal Canopy | Balance of Walls & Overhead | Not Started | 10/05/26 | 10/09/26 | 6.2 | 6.2 |
|
90.0 |
RPL07.INT.SSB.01200 |
RPL07.Interior.SSB - Priority - Install Store Front Frames & Glass (Testing if Required) | Balance of Walls and OverHead | Not Started | 10/05/26 | 10/23/26 | 18.8 | 18.8 |
|
146.2 |
RPL07.INT.SSB.01420 |
RPL07.Interior.SSB - Loading Dock and Storage - Install Dock Levelers, Pads, Exterior lights and Lock | Loading Dock and Storage | Not Started | 10/05/26 | 10/13/26 | 8.8 | 8.8 |
|
190.0 |
RPL07.INT.SSBC.3100 |
RPL07.Interior.SSBC LO #06 - Install Fire Life Safety Lowside OH and In-wall | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 10/05/26 | 10/06/26 | 2.5 | 2.5 |
|
97.5 |
RPL07.INT.SSBC.3120 |
RPL07.Interior.SSBC LO #06 - Install Plumbing Lowside OH and In-wall | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 10/05/26 | 10/06/26 | 2.5 | 2.5 |
|
93.8 |
RPL07.MCUP.LP1.2100 |
RPL07.MCUP.Loop 1 - Install Exterior Signage | Hardscape and Landscape | Not Started | 10/05/26 | 10/16/26 | 12.5 | 12.5 |
|
378.8 |
RPL07.SKN.SSB.01150 |
RPL07.SKIN.SSB - Install Perm Doors | Glazing, Doors and Ext Devices | Not Started | 10/05/26 | 10/06/26 | 2.5 | 2.5 |
|
206.2 |
RPL07.WP4.010060 |
RPL07.Conn GSMDF2 Install Fanout (5F) [PON (Active, In-Row)] | GSMDF2 | Not Started | 10/05/26 | 10/19/26 | 13.8 | 13.8 |
|
217.5 |
RPL07.CON.WP2.07900 |
RPL07.Conn - MDF1<>MDF2 Install Cabling (Pull, Splice & Terminate) | ISP (MDF RPL07 <> MDF RPL07) | Not Started | 10/06/26 | 10/09/26 | 5.0 | 5.0 |
|
306.2 |
RPL07.CON.WP2.07980 |
RPL07.Conn - MDF1<>MDF2 Install Cabling (Pull, Splice & Terminate) | ISP (MDF RPL07 <> MDF RPL07) | Not Started | 10/06/26 | 10/09/26 | 5.0 | 5.0 |
|
313.8 |
RPL07.CON.WP2.09260 |
RPL07.Conn - GSMDF1 (South) - Install Copper, WAPs, Security Camera & Access Control | ISP (MDF RPL07 <> MDF RPL07) | Not Started | 10/06/26 | 10/21/26 | 15.0 | 15.0 |
|
223.8 |
RPL07.INT.DHB.01440 |
RPL07.Interior.DHB - OFE - Control Fault Domain 3 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | Control Fault Domain 3 | Not Started | 10/06/26 | 12/08/26 | 53.8 | 53.8 |
|
45.0 |
RPL07.INT.DHB.01460 |
RPL07.Interior.DHB - Control Fault Domain 2 - Install LV Side Aisle HAC Busway | LV Side Tie-ins | Not Started | 10/06/26 | 10/09/26 | 5.0 | 5.0 |
|
82.5 |
RPL07.INT.DHB.02520 |
RPL07.Interior.DHB - OFE - Control Fault Domain 3 (LV Side Aisle) | Control Fault Domain 3 | Not Started | 10/06/26 | 10/09/26 | 5.0 | 5.0 |
|
62.5 |
RPL07.INT.DHC.01050 |
RPL07.Interior.DHC - Priority - Install FA / Linear heat detection | OverHead | Not Started | 10/06/26 | 10/12/26 | 6.2 | 6.2 |
|
83.8 |
RPL07.INT.DHC.02150 |
RPL07.Interior.DHC - Priority - Install Electrical | OverHead | Not Started | 10/06/26 | 10/19/26 | 12.5 | 12.5 |
|
83.8 |
RPL07.INT.DHD.01060 |
RPL07.Interior.DHD - OFE - LV Skids and TopHat - Set / Place / Anchor | OFE/MOFE & CFCI | Not Started | 10/06/26 | 10/22/26 | 16.2 | 16.2 |
|
77.5 |
RPL07.INT.DHD.01070 |
RPL07.Interior.DHD - OFE - MES Skids - Set / Place / Anchor | OFE/MOFE & CFCI | Not Started | 10/06/26 | 10/22/26 | 16.2 | 16.2 |
|
101.2 |
RPL07.INT.ENDC.06820 |
RPL07.Interior.End-Corridor - Final Finishes & Fixtures - MEP Rough-In | Restrooms | Not Started | 10/06/26 | 10/12/26 | 6.2 | 6.2 |
|
173.8 |
RPL07.INT.CTRC.1280 |
RPL07.Interior.Center-Corridor - BoW - Install Fire Life Safety Lowside OH and In-wall | Balance of Walls & Overhead | Not Started | 10/07/26 | 10/15/26 | 8.8 | 8.8 |
|
50.0 |
RPL07.INT.DHA.01120 |
RPL07.Interior.DHA - OFE - Control Fault Domain 1 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | Control Fault Domain 1 | Not Started | 10/07/26 | 11/05/26 | 27.5 | 27.5 |
|
33.8 |
RPL07.INT.DHA.03480 |
RPL07.Interior.DHA - OFE - Control Fault Domain 1 (LV Side Aisle) | Control Fault Domain 1 | Not Started | 10/07/26 | 10/13/26 | 6.2 | 6.2 |
|
12.5 |
RPL07.INT.DHB.01470 |
RPL07.Interior.DHB - Control Fault Domain 2 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 10/07/26 | 10/12/26 | 5.0 | 5.0 |
|
82.5 |
RPL07.INT.ENDC.1200 |
RPL07.Interior.End-Corr - Priority - Install Fire Safing/ Seal Penetrations through Soffit (HighS. OH space) | Priority Walls & Overhead | Not Started | 10/07/26 | 10/09/26 | 3.8 | 3.8 |
|
127.5 |
RPL07.INT.ENDC.1420 |
RPL07.Interior.End-Corr - Priority - Fixed Draft Smoke Curtains Patching | Priority Walls & Overhead | Not Started | 10/07/26 | 10/09/26 | 3.8 | 3.8 |
|
127.5 |
RPL07.INT.SSBC.3140 |
RPL07.Interior.SSBC LO #06 - Install Security Lowside OH and In-wall | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 10/07/26 | 10/08/26 | 2.5 | 2.5 |
|
97.5 |
RPL07.INT.SSBC.3160 |
RPL07.Interior.SSBC LO #06 - Install Controls / EPMS / BMS OH and In-wall | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 10/07/26 | 10/08/26 | 2.5 | 2.5 |
|
93.8 |
DCC.B7.3155 |
[SSDCB2] GS Gear Delivered [DHD] | Connectivity | Not Started | 10/08/26 | 10/08/26 | 0.0 | 0.0 |
|
387.5 |
RPL07.INT.CTRC.1420 |
RPL07.Interior.Center-Corridor - BoW - Install Electrical - Lighitng Inverter Room (XX.S2.XX) | Balance of Walls & Overhead | Not Started | 10/08/26 | 10/16/26 | 8.8 | 8.8 |
|
133.8 |
RPL07.INT.CTRC.9000 |
RPL07.Interior.Center-Corridor - Priority - MEP OH over Cable Tray | Priority Walls & Overhead | Not Started | 10/08/26 | 10/16/26 | 8.8 | 8.8 |
|
66.2 |
RPL07.INT.DHA.01093 |
RPL07.Interior.DHA - LV Skids and TopHat - Top Hat Busway | DHA - LV Skids and TopHat | Not Started | 10/08/26 | 10/26/26 | 16.2 | 16.2 |
|
81.2 |
RPL07.INT.DHA.01112 |
RPL07.Interior.DHA - MES Skids - Piping Tie-Ins & Inspections | DHA - MES Skids | Not Started | 10/08/26 | 11/04/26 | 25.0 | 25.0 |
|
48.8 |
RPL07.INT.DHA.03500 |
RPL07.Interior.DHA - OFE - Control Fault Domain 1 (HAC) | Control Fault Domain 1 | Not Started | 10/08/26 | 11/04/26 | 25.0 | 25.0 |
|
12.5 |
RPL07.INT.DHB.01520 |
RPL07.Interior.DHB - Tie-ins - Control Fault Domain 3 (including IDF) - WBS Summary | Control Fault Domain 3 | Not Started | 10/08/26 | 01/26/27 | 91.2 | 91.2 |
|
102.5 |
RPL07.INT.DHB.02740 |
RPL07.Interior.DHB - Control Fault Domain 3 - Install Duct (LV Side) | LV Side Tie-ins | Not Started | 10/08/26 | 10/13/26 | 5.0 | 5.0 |
|
95.0 |
RPL07.INT.DHD.01090 |
RPL07.Interior.DHD - LV Skids and TopHat Tie-ins (LOE) | DHD - LV Skids and TopHat | Not Started | 10/08/26 | 11/05/26 | 26.2 | 26.2 |
|
196.2 |
RPL07.INT.DHD.01091 |
RPL07.Interior.DHD - LV Skids and TopHat - Set & Anchor Interconnects | DHD - LV Skids and TopHat | Not Started | 10/08/26 | 10/26/26 | 16.2 | 16.2 |
|
196.2 |
RPL07.INT.DHD.01100 |
RPL07.Interior.DHD - Tie-ins - WBS Summary | Tie-Ins | Not Started | 10/08/26 | 05/19/27 | 190.0 | 190.0 |
|
140.0 |
RPL07.INT.ENDC.6220 |
RPL07.Interior.End-Corr - Priority GL7.27 - (P3) Install MEP In-Wall/Backing | Priority Wall Grid Line 7-27 | Not Started | 10/08/26 | 10/12/26 | 3.8 | 3.8 |
|
200.0 |
RPL07.INT.SSB.01250 |
RPL07.Interior.SSB - Loading Dock and Storage - Install Security | Loading Dock and Storage | Not Started | 10/08/26 | 10/16/26 | 8.8 | 8.8 |
|
188.8 |
RPL07.INT.SSB.01470 |
RPL07.Interior.SSB - Loading Dock and Storage - Install Unit Heaters | Loading Dock and Storage | Not Started | 10/08/26 | 10/14/26 | 6.2 | 6.2 |
|
205.0 |
RPL07.INT.SSB.01760 |
RPL07.Interior.SSB - Loading Dock and Storage - Mechanical Tie-In | Loading Dock and Storage | Not Started | 10/08/26 | 10/14/26 | 6.2 | 6.2 |
|
205.0 |
RPL07.INT.SSB.01780 |
RPL07.Interior.SSB - Loading Dock and Storage - Install Split Systems/Humidifiers | Loading Dock and Storage | Not Started | 10/08/26 | 10/14/26 | 6.2 | 6.2 |
|
198.8 |
RPL07.INT.SSBC.4080 |
RPL07.Interior.SSBC LO #07 - Install Mechanical Piping Lowside OH and in-wall | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 10/08/26 | 10/09/26 | 2.5 | 2.5 |
|
87.5 |
RPL07.SKN.W.LO.01385 |
RPL07.SKIN.LO#16 - Cure Stemwall | Build back Exterior Leave Out Walls #16 (SSB - North of Loading Dock) | Not Started | 10/08/26 | 10/16/26 | 8.8 | 8.8 |
|
67.5 |
RPL07.INT.DHA.01160 |
RPL07.Interior.DHA - Tie-ins - Control Fault Domain 1 - WBS Summary | Control Fault Domain 1 | Not Started | 10/09/26 | 12/24/26 | 65.0 | 65.0 |
|
33.8 |
RPL07.INT.DHA.03780 |
RPL07.Interior.DHA - Control Fault Domain 1 - Install Duct (LV Side) | LV Side Tie-ins | Not Started | 10/09/26 | 10/15/26 | 6.2 | 6.2 |
|
48.8 |
RPL07.INT.ENDC.6200 |
RPL07.Interior.End-Corr - Priority GL7.27 - (P3) Install IMP Walls | Priority Wall Grid Line 7-27 | Not Started | 10/09/26 | 10/13/26 | 3.8 | 3.8 |
|
125.0 |
RPL07.INT.SSBC.3240 |
RPL07.Interior.SSBC LO #06 - Install Electrical Lowside OH and In-wall | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 10/09/26 | 10/13/26 | 3.8 | 3.8 |
|
93.8 |
GCD.RPL07.1827 |
Delivery of RMU - (First Delivery) - RPL07 - DHC&D | Construction Milestones | Not Started | 10/12/26 | 10/12/26 | 0.0 | 0.0 |
|
135.0 |
RPL07.CON.WP2.09280 |
RPL07.Conn Misc P/S/T and R/S/P @ MDF2 | ISP (MDF RPL07 <> MDF RPL07) | Not Started | 10/12/26 | 10/23/26 | 12.5 | 12.5 |
|
306.2 |
RPL07.CON.WP2.09300 |
RPL07.Conn Misc P/S/T and R/S/P @ MDF1 | ISP (MDF RPL07 <> MDF RPL07) | Not Started | 10/12/26 | 10/15/26 | 5.0 | 5.0 |
|
313.8 |
RPL07.INT.DHA.01113 |
RPL07.Interior.DHA - MES Skids - CDU Tie-Ins ( 2 per day) | DHA - MES Skids | Not Started | 10/12/26 | 11/06/26 | 25.0 | 25.0 |
|
67.5 |
RPL07.INT.DHB.01580 |
RPL07.Interior.DHB - OFE - Control Fault Domain 4 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | Control Fault Domain 4 | Not Started | 10/12/26 | 12/30/26 | 67.5 | 67.5 |
|
42.5 |