Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL07 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:16 PM
· 5237 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
0
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL07.INT.DHB.01600 |
RPL07.Interior.DHB - Control Fault Domain 3 - Install LV Side Aisle HAC Busway | LV Side Tie-ins | Not Started | 10/12/26 | 10/15/26 | 5.0 | 5.0 |
|
125.0 |
RPL07.INT.DHB.02580 |
RPL07.Interior.DHB - OFE - Control Fault Domain 4 (LV Side Aisle) | Control Fault Domain 4 | Not Started | 10/12/26 | 10/15/26 | 5.0 | 5.0 |
|
76.2 |
RPL07.INT.ENDC.01200 |
RPL07.Interior.End-Corridor - Install Controls / EPMS / BMS | Fit out | Not Started | 10/12/26 | 10/15/26 | 5.0 | 5.0 |
|
161.2 |
RPL07.INT.SBC.05820 |
RPL07.Interior.SSB-Corridor - BoW - Install Backing (Both side of Corridor Wall) | Balance of Walls & Overhead | Not Started | 10/12/26 | 10/16/26 | 6.2 | 6.2 |
|
90.0 |
RPL07.INT.SSBC.4100 |
RPL07.Interior.SSBC LO #07 - Install Fire Life Safety Lowside OH and In-wall | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 10/12/26 | 10/13/26 | 2.5 | 2.5 |
|
91.2 |
RPL07.INT.SSBC.4120 |
RPL07.Interior.SSBC LO #07 - Install Plumbing Lowside OH and In-wall | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 10/12/26 | 10/13/26 | 2.5 | 2.5 |
|
87.5 |
RPL.07.D.73720.XG |
RMUs/MV Skids Set (Ready for Longhorn Pulls) - DHB | Give Milestones (XREFs) | Not Started | 10/13/26 | 10/13/26 | 0.0 | 0.0 |
|
382.5 |
RPL.07.D.73960.XG |
Ready for MV Cable Pull DH B (MVs - Qty 10)* | Give Milestones (XREFs) | Not Started | 10/13/26 | 10/13/26 | 0.0 | 0.0 |
|
382.5 |
RPL07.EY.DHD.01220 |
RPL07.EY.DHD - Install MV, RMUs & Electrical Panels (Qty 8) | OFE | Not Started | 10/13/26 | 11/09/26 | 25.0 | 25.0 |
|
135.0 |
RPL07.EY.DHD.01230 |
RPL07.EY.DHD - OFE - MV - WBS Summary | OFE | Not Started | 10/13/26 | 05/24/27 | 190.0 | 190.0 |
|
95.0 |
RPL07.INT.DHA.01220 |
RPL07.Interior.DHA - Control Fault Domain 1 - Install LV Side Aisle HAC Busway | LV Side Tie-ins | Not Started | 10/13/26 | 10/19/26 | 6.2 | 6.2 |
|
57.5 |
RPL07.INT.DHA.03520 |
RPL07.Interior.DHA - OFE - Control Fault Domain 1 (Mech Side Aisle) | Control Fault Domain 1 | Not Started | 10/13/26 | 11/05/26 | 22.5 | 22.5 |
|
33.8 |
RPL07.INT.DHB.01220 |
RPL07.Interior.DHB - Control Fault Domain 1 - Install Duct (MES Side) | Remaining Tie-ins post Mech Side Aisle install | Not Started | 10/13/26 | 11/09/26 | 25.0 | 25.0 |
|
33.8 |
RPL07.INT.DHB.01230 |
RPL07.Interior.DHB - Control Fault Domain 1 - Install Vesda / FA | Remaining Tie-ins post Mech Side Aisle install | Not Started | 10/13/26 | 11/09/26 | 25.0 | 25.0 |
|
46.2 |
RPL07.INT.DHB.01240 |
RPL07.Interior.DHB - Control Fault Domain 1 - Install TW | Remaining Tie-ins post Mech Side Aisle install | Not Started | 10/13/26 | 11/09/26 | 25.0 | 25.0 |
|
33.8 |
RPL07.INT.DHB.01610 |
RPL07.Interior.DHB - Control Fault Domain 3 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 10/13/26 | 10/16/26 | 5.0 | 5.0 |
|
185.0 |
RPL07.INT.DHB.02120 |
RPL07.Interior.DHB - Control Fault Domain 1 - Install FW | Remaining Tie-ins post Mech Side Aisle install | Not Started | 10/13/26 | 11/09/26 | 25.0 | 25.0 |
|
33.8 |
RPL07.INT.DHD.01110 |
RPL07.Interior.DHD - MES Skids Tie-ins (LOE) | DHD - MES Skids | Not Started | 10/13/26 | 11/20/26 | 35.0 | 35.0 |
|
183.8 |
RPL07.INT.DHD.01111 |
RPL07.Interior.DHD - MES Skids - Set & Anchor Interconnects | DHD - MES Skids | Not Started | 10/13/26 | 11/03/26 | 20.0 | 20.0 |
|
183.8 |
RPL07.INT.ENDC.06860 |
RPL07.Interior.End-Corridor - Final Finishes & Fixtures - Hang Drywall and Fire/Caulking | Restrooms | Not Started | 10/13/26 | 10/19/26 | 6.2 | 6.2 |
|
186.2 |
RPL07.INT.ENDC.07040 |
RPL07.Interior.End-Corridor - Final Finishes & Fixtures - Framing RO Verification, Tile Finish & ADA Verification (P | Restrooms | Not Started | 10/13/26 | 10/19/26 | 6.2 | 6.2 |
|
173.8 |
RPL07.INT.ENDC.6240 |
RPL07.Interior.End-Corr - Priority GL7.27 - (P3) Hang Drywall (Both Sides) | Priority Wall Grid Line 7-27 | Not Started | 10/13/26 | 10/15/26 | 3.8 | 3.8 |
|
200.0 |
RPL07.INT.SSB.14260 |
RPL07.Interior.SSB LO #01 to #05 - Install Backing | OH & Framing | Not Started | 10/13/26 | 10/19/26 | 6.2 | 6.2 |
|
87.5 |
RPL07.EY.DHB.01250 |
RPL07.EY.DHB - Install Electrical Tie-ins (include penetration detail) | Tie-ins | Not Started | 10/14/26 | 10/27/26 | 12.5 | 12.5 |
|
23.8 |
RPL07.EY.DHB.01260 |
RPL07.EY.DHB - Tie-ins - WBS Summary | Tie-ins | Not Started | 10/14/26 | 12/09/26 | 47.5 | 47.5 |
|
152.5 |
RPL07.INT.DHA.01114 |
RPL07.Interior.DHA - MES Skids - BMS Tie-Ins ( 2 per day) | DHA - MES Skids | Not Started | 10/14/26 | 11/10/26 | 25.0 | 25.0 |
|
67.5 |
RPL07.INT.DHA.01210 |
RPL07.Interior.DHA - Control Fault Domain 1 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 10/14/26 | 10/20/26 | 6.2 | 6.2 |
|
57.5 |
RPL07.INT.DHA.01230 |
RPL07.Interior.DHA - OFE - Control Fault Domain 2 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | Control Fault Domain 2 | Not Started | 10/14/26 | 12/01/26 | 40.0 | 40.0 |
|
40.0 |
RPL07.INT.DHA.03540 |
RPL07.Interior.DHA - OFE - Control Fault Domain 2 (LV Side Aisle) | Control Fault Domain 2 | Not Started | 10/14/26 | 10/19/26 | 5.0 | 5.0 |
|
31.2 |
RPL07.INT.DHB.01660 |
RPL07.Interior.DHB - Tie-ins - Control Fault Domain 4 - WBS Summary | Control Fault Domain 4 | Not Started | 10/14/26 | 02/17/27 | 105.0 | 105.0 |
|
88.8 |
RPL07.INT.DHB.02760 |
RPL07.Interior.DHB - Control Fault Domain 4 - Install Duct (LV Side) | LV Side Tie-ins | Not Started | 10/14/26 | 10/19/26 | 5.0 | 5.0 |
|
110.0 |
RPL07.INT.DHD.01092 |
RPL07.Interior.DHD - LV Skids and TopHat - Maintenance and Reserve Busways | DHD - LV Skids and TopHat | Not Started | 10/14/26 | 10/29/26 | 15.0 | 15.0 |
|
196.2 |
RPL07.INT.ENDC.1205 |
RPL07.Interior.End-Corridor - Balance Of Wall - (ERAD, Maintance, Network infra, Spoke, Bathroom, etc) - WBS Summary | Balance of Walls & Overhead | Not Started | 10/14/26 | 06/28/27 | 218.8 | 218.8 |
|
43.8 |
RPL07.INT.ENDC.1220 |
RPL07.Interior.End-Corridor - Frame Balance of Wall | Balance of Walls & Overhead | Not Started | 10/14/26 | 10/20/26 | 6.2 | 6.2 |
|
125.0 |
RPL07.INT.ENDC.6120 |
RPL07.Interior.End-Corridor - Early In-wall for Ancillary Skids (Room #3.6) | Priority Wall Grid Line 7-27 | Not Started | 10/14/26 | 10/16/26 | 3.8 | 3.8 |
|
197.5 |
RPL07.INT.SSB.01530 |
RPL07.Interior.SSB - Loading Dock and Storage - Install OverHead Doors | Loading Dock and Storage | Not Started | 10/14/26 | 10/27/26 | 12.5 | 12.5 |
|
190.0 |
RPL07.INT.SSBC.3180 |
RPL07.Interior.SSBC LO #06 - Install Door Frames | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 10/14/26 | 10/15/26 | 2.5 | 2.5 |
|
93.8 |
RPL07.INT.SSBC.4140 |
RPL07.Interior.SSBC LO #07 - Install Security Lowside OH and In-wall | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 10/14/26 | 10/15/26 | 2.5 | 2.5 |
|
91.2 |
RPL07.INT.SSBC.4160 |
RPL07.Interior.SSBC LO #07 - Install Controls / EPMS / BMS OH and In-wall | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 10/14/26 | 10/15/26 | 2.5 | 2.5 |
|
87.5 |
RPL07.SKN.S.LO.01100 |
RPL07.SKIN.LO#17 - Close Exterior Leave Out #17 CC (South) WBS Summary | Build back Exterior Leave Out Walls #17 (CC - South) | Not Started | 10/14/26 | 11/05/26 | 21.2 | 21.2 |
|
91.2 |
RPL07.SKN.S.LO.03020 |
RPL07.SKIN.LO#17 - Pour back Stemwall | Build back Exterior Leave Out Walls #17 (CC - South) | Not Started | 10/14/26 | 10/15/26 | 2.5 | 2.5 |
|
91.2 |
DCC.B7.3145 |
[SSDCB2] GS Gear Delivered [DHC] | Connectivity | Not Started | 10/15/26 | 10/15/26 | 0.0 | 0.0 |
|
381.2 |
RPL07.CFCI.5110 |
RPL07 - Submittals Review & Approval - Carpet | (CFCI) Div. 09 - Carpet | Not Started | 10/15/26 | 11/12/26 | 25.0 | 25.0 |
|
131.2 |
RPL07.CFCI.5140 |
RPL07 - Fabricate / Deliver -Epoxy Flooring (Spec 09 67 23) XX | (CFCI) Div. 09 - Epoxy Flooring | Not Started | 10/15/26 | 11/04/26 | 18.8 | 18.8 |
|
187.5 |
RPL07.CFCI.5260 |
RPL07 - Fabricate / Deliver - Specialities | (CFCI) Div. 10 - Specialities | Not Started | 10/15/26 | 11/30/26 | 37.5 | 37.5 |
|
117.5 |
RPL07.EY.DHB.01520 |
RPL07.EY.DHB - Install Generator (#1 of Qty 2) | OFE | Not Started | 10/15/26 | 10/21/26 | 6.2 | 6.2 |
|
56.2 |
RPL07.INT.CTRC.1300 |
RPL07.Interior.Center-Corridor - BoW - Install Plumbing Lowside OH and In-wall | Balance of Walls & Overhead | Not Started | 10/15/26 | 10/23/26 | 8.8 | 8.8 |
|
36.2 |
RPL07.INT.SSB.01350 |
RPL07.Interior.SSB - Loading Dock and Storage - Tape Finish Paint | Loading Dock and Storage | Not Started | 10/15/26 | 10/19/26 | 3.8 | 3.8 |
|
168.8 |
RPL07.INT.SSB.02860 |
RPL07.Interior.SSB - Final Finishes & Fixtures - MEP Rough-In | Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) | Not Started | 10/15/26 | 10/21/26 | 6.2 | 6.2 |
|
210.0 |
RPL07.MCUP.LP2.1960 |
RPL07.MCUP.Loop 2 - Install Exterior Signage | Hardscape and Landscape | Not Started | 10/15/26 | 10/28/26 | 12.5 | 12.5 |
|
368.8 |
DCC.B7.3245 |
[SSDCB2] CorpNet/Security/FacNet Ready [DHC] | Connectivity | Not Started | 10/16/26 | 10/16/26 | 0.0 | 0.0 |
|
345.0 |
DCC.B7.3255 |
[SSDCB2] CorpNet/Security/FacNet Ready [DHD] | Connectivity | Not Started | 10/16/26 | 10/16/26 | 0.0 | 0.0 |
|
345.0 |
RPL07.CON.WP2.06280 |
RPL07.Conn - GSIDF/DH B2 - Install & Test Network (FIM) | Network | Not Started | 10/16/26 | 10/20/26 | 3.8 | 3.8 |
|
345.0 |
RPL07.CON.WP2.06480 |
RPL07.Conn - GSIDF/DH A2 - Install & Test Network (FIM) | Network | Not Started | 10/16/26 | 10/20/26 | 3.8 | 3.8 |
|
345.0 |
RPL07.EY.DHB.01280 |
RPL07.EY.DHB - Install BMS/EPMS Tie-ins | Tie-ins | Not Started | 10/16/26 | 10/29/26 | 12.5 | 12.5 |
|
23.8 |
RPL07.INT.CTRC.1320 |
RPL07.Interior.Center-Corridor - BoW - Install Security Lowside OH and In-wall | Balance of Walls & Overhead | Not Started | 10/16/26 | 10/26/26 | 8.8 | 8.8 |
|
141.2 |
RPL07.INT.DHA.01115 |
RPL07.Interior.DHA - MES Skids - EPMS Tie-Ins ( 2 per day) | DHA - MES Skids | Not Started | 10/16/26 | 11/13/26 | 25.0 | 25.0 |
|
67.5 |
RPL07.INT.DHA.01300 |
RPL07.Interior.DHA - Tie-ins - Control Fault Domain 2 - WBS Summary | Control Fault Domain 2 | Not Started | 10/16/26 | 01/26/27 | 83.8 | 83.8 |
|
40.0 |
RPL07.INT.DHA.03800 |
RPL07.Interior.DHA - Control Fault Domain 2 - Install Duct (LV Side) | LV Side Tie-ins | Not Started | 10/16/26 | 10/21/26 | 5.0 | 5.0 |
|
73.8 |
RPL07.INT.DHB.01720 |
RPL07.Interior.DHB - OFE - Control Fault Domain 5 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | Control Fault Domain 5 | Not Started | 10/16/26 | 01/26/27 | 83.8 | 83.8 |
|
37.5 |
RPL07.INT.DHB.01740 |
RPL07.Interior.DHB - Control Fault Domain 4 - Install LV Side Aisle HAC Busway | LV Side Tie-ins | Not Started | 10/16/26 | 10/21/26 | 5.0 | 5.0 |
|
140.0 |
RPL07.INT.DHB.02640 |
RPL07.Interior.DHB - OFE - Control Fault Domain 5 (LV Side Aisle) | Control Fault Domain 5 | Not Started | 10/16/26 | 10/21/26 | 5.0 | 5.0 |
|
90.0 |
RPL07.INT.ENDC.01160 |
RPL07.Interior.End-Corridor - OFE - DHC (1x GS.IDF) C2 | OFE/MOFE & CFCI | Not Started | 10/16/26 | 10/22/26 | 6.2 | 6.2 |
|
150.0 |
RPL07.INT.ENDC.01210 |
RPL07.Interior.End-Corridor - Install Fire Life Safety OH and In-wall | Fit out | Not Started | 10/16/26 | 10/29/26 | 12.5 | 12.5 |
|
161.2 |
RPL07.INT.ENDC.6260 |
RPL07.Interior.End-Corr - Priority GL7.27 - (P3) Tape Finish Paint (Both Sides) | Priority Wall Grid Line 7-27 | Not Started | 10/16/26 | 10/22/26 | 6.2 | 6.2 |
|
200.0 |
RPL07.INT.SSBC.3200 |
RPL07.Interior.SSBC LO #06 - Mechanical Tie-In | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 10/16/26 | 10/19/26 | 2.5 | 2.5 |
|
93.8 |
RPL07.INT.SSBC.3300 |
RPL07.Interior.SSBC LO #06 - Electrical Tie-In | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 10/16/26 | 10/22/26 | 6.2 | 6.2 |
|
93.8 |
RPL07.INT.SSBC.4240 |
RPL07.Interior.SSBC LO #07 - Install Electrical Lowside OH and In-wall | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 10/16/26 | 10/20/26 | 3.8 | 3.8 |
|
87.5 |
RPL07.SKN.S.LO.03040 |
RPL07.SKIN.LO#17 - Cure Stemwall | Build back Exterior Leave Out Walls #17 (CC - South) | Not Started | 10/16/26 | 10/26/26 | 8.8 | 8.8 |
|
91.2 |
RPL07.INT.CTRC.1940 |
RPL07.Interior.Center-Corridor - BoW - Install Vertical Tube Steel Support for Cable Tray (IFP Add) | Balance of Walls & Overhead | Not Started | 10/19/26 | 10/22/26 | 5.0 | 5.0 |
|
66.2 |
RPL07.INT.CTRC.8860 |
RPL07.Interior.Center-Corridor - BoW - Electrical Tie-In | Balance of Walls & Overhead | Not Started | 10/19/26 | 10/23/26 | 6.2 | 6.2 |
|
142.5 |
RPL07.INT.DHB.01750 |
RPL07.Interior.DHB - Control Fault Domain 4 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 10/19/26 | 10/22/26 | 5.0 | 5.0 |
|
185.0 |
RPL07.INT.ENDC.6140 |
RPL07.Interior.End-Corridor - Hang Early Drywall & DFH for Ancillary Skids (Room #3.6) | Priority Wall Grid Line 7-27 | Not Started | 10/19/26 | 10/20/26 | 2.5 | 2.5 |
|
197.5 |
RPL07.INT.SBC.05840 |
RPL07.Interior.SSB-Corridor - BoW - QC - Backings/Walls (Both side of Corridor Wall) | Balance of Walls & Overhead | Not Started | 10/19/26 | 10/23/26 | 6.2 | 6.2 |
|
90.0 |
RPL07.INT.SSB.01270 |
RPL07.Interior.SSB - Loading Dock and Storage - Install Controls / EPMS / BMS | Loading Dock and Storage | Not Started | 10/19/26 | 10/22/26 | 5.0 | 5.0 |
|
188.8 |
RPL07.SKN.W.LO.01390 |
RPL07.SKIN.LO#16 - Stemwall Water Proofing | Build back Exterior Leave Out Walls #16 (SSB - North of Loading Dock) | Not Started | 10/19/26 | 10/23/26 | 6.2 | 6.2 |
|
67.5 |
RPL07.INT.DHA.01350 |
RPL07.Interior.DHA - OFE - Control Fault Domain 3 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | Control Fault Domain 3 | Not Started | 10/20/26 | 12/22/26 | 53.8 | 53.8 |
|
47.5 |
RPL07.INT.DHA.01370 |
RPL07.Interior.DHA - Control Fault Domain 2 - Install LV Side Aisle HAC Busway | LV Side Tie-ins | Not Started | 10/20/26 | 10/23/26 | 5.0 | 5.0 |
|
82.5 |
RPL07.INT.DHA.03600 |
RPL07.Interior.DHA - OFE - Control Fault Domain 3 (LV Side Aisle, HAC) | Control Fault Domain 3 | Not Started | 10/20/26 | 10/23/26 | 5.0 | 5.0 |
|
45.0 |
RPL07.INT.DHB.01260 |
RPL07.Interior.DHB - Control Fault Domain 1 - Pull BMS from panel to devices | Remaining Tie-ins post Mech Side Aisle install | Not Started | 10/20/26 | 11/17/26 | 25.0 | 25.0 |
|
46.2 |
RPL07.INT.DHB.01270 |
RPL07.Interior.DHB - Control Fault Domain 1 - Pull EMPS from panel to devices | Remaining Tie-ins post Mech Side Aisle install | Not Started | 10/20/26 | 11/17/26 | 25.0 | 25.0 |
|
46.2 |
RPL07.INT.DHB.01280 |
RPL07.Interior.DHB - Control Fault Domain 1 - Set UPS and Panel (2) | Remaining Tie-ins post Mech Side Aisle install | Not Started | 10/20/26 | 11/17/26 | 25.0 | 25.0 |
|
33.8 |
RPL07.INT.DHB.01800 |
RPL07.Interior.DHB - Tie-ins - Control Fault Domain 5 - WBS Summary | Control Fault Domain 5 | Not Started | 10/20/26 | 03/12/27 | 121.2 | 121.2 |
|
52.5 |
RPL07.INT.DHB.02780 |
RPL07.Interior.DHB - Control Fault Domain 5 - Install Duct (LV Side) | LV Side Tie-ins | Not Started | 10/20/26 | 10/23/26 | 5.0 | 5.0 |
|
123.8 |
RPL07.INT.DHC.01060 |
RPL07.Interior.DHC - OFE - LV Skids and TopHat - Set / Place / Anchor | OFE/MOFE & CFCI | Not Started | 10/20/26 | 11/05/26 | 16.2 | 16.2 |
|
77.5 |
RPL07.INT.DHC.01070 |
RPL07.Interior.DHC - OFE - MES Skids - Set / Place / Anchor | OFE/MOFE & CFCI | Not Started | 10/20/26 | 11/05/26 | 16.2 | 16.2 |
|
77.5 |
RPL07.INT.DHC.02210 |
RPL07.Interior.DHC - Priority - Install Temp Doors Frame Hardware | OverHead | Not Started | 10/20/26 | 10/22/26 | 3.8 | 3.8 |
|
318.8 |
RPL07.INT.ENDC.07060 |
RPL07.Interior.End-Corridor - Final Finishes & Fixtures - Install Cement Board/ Drywall | Restrooms | Not Started | 10/20/26 | 10/26/26 | 6.2 | 6.2 |
|
173.8 |
RPL07.INT.SSB.01430 |
RPL07.Interior.SSB - Loading Dock and Storage - Electrical Trim Out | Loading Dock and Storage | Not Started | 10/20/26 | 10/28/26 | 8.8 | 8.8 |
|
168.8 |
RPL07.INT.SSB.01920 |
RPL07.Interior.SSB - Loading Dock and Storage - Install Remaining Refrigerant Line | Loading Dock and Storage | Not Started | 10/20/26 | 10/26/26 | 6.2 | 6.2 |
|
195.0 |
RPL07.INT.SSB.14280 |
RPL07.Interior.SSB LO #01 to #05 - QC - Backings/Walls | OH & Framing | Not Started | 10/20/26 | 10/26/26 | 6.2 | 6.2 |
|
87.5 |
RPL07.INT.DHA.01380 |
RPL07.Interior.DHA - Control Fault Domain 2 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 10/21/26 | 10/26/26 | 5.0 | 5.0 |
|
82.5 |
RPL07.INT.DHD.01093 |
RPL07.Interior.DHD - LV Skids and TopHat - Top Hat Busway | DHD - LV Skids and TopHat | Not Started | 10/21/26 | 11/05/26 | 15.0 | 15.0 |
|
196.2 |
RPL07.INT.DHD.01112 |
RPL07.Interior.DHD - MES Skids - Piping Tie-Ins & Inspections | DHD - MES Skids | Not Started | 10/21/26 | 11/12/26 | 20.0 | 20.0 |
|
183.8 |
RPL07.INT.ENDC.1240 |
RPL07.Interior.End-Corridor - BoW - Install Mechanical Piping/ Refrigerant Lowside OH and in-wall | Balance of Walls & Overhead | Not Started | 10/21/26 | 10/27/26 | 6.2 | 6.2 |
|
125.0 |
RPL07.INT.ENDC.1400 |
RPL07.Interior.End-Corridor - BoW - Install Door Frames | Balance of Walls & Overhead | Not Started | 10/21/26 | 10/27/26 | 6.2 | 6.2 |
|
221.2 |
RPL07.INT.ENDC.6160 |
RPL07.Interior.End-Corridor - Early Tape Finish Paint for Ancillary Skids (Room #3.6) | Priority Wall Grid Line 7-27 | Not Started | 10/21/26 | 10/27/26 | 6.2 | 6.2 |
|
197.5 |
RPL07.INT.SSBC.4180 |
RPL07.Interior.SSBC LO #07 - Install Door Frames | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 10/21/26 | 10/22/26 | 2.5 | 2.5 |
|
87.5 |
DCC.B7.3235 |
[SSDCB2] CorpNet/Security/FacNet Ready [DHA] | Connectivity | Not Started | 10/22/26 | 10/22/26 | 0.0 | 0.0 |
|
308.8 |
RPL07.INT.DHA.01430 |
RPL07.Interior.DHA - Tie-ins - Control Fault Domain 3 (including IDF) - WBS Summary | Control Fault Domain 3 | Not Started | 10/22/26 | 02/09/27 | 91.2 | 91.2 |
|
102.5 |