Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL07 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:16 PM
· 5237 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
60
Completed
40
In Progress
60
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL07.OFE.7000 |
OFE Delivery ROJ: mCUP Elec Skid - mCUP3 - 1 (ROJ 06.02.26) (RVCD 06.04.26) Follows MCUPS 4 | (MOFE) - RPL07 - mCup Electrical Skids - Outside | Active | 07/25/25 | 06/04/26 | 282.5 | 47.5 |
|
133.8 |
RPL07.OFE.7040 |
OFE Delivery ROJ: mCUP Elec Skid - mCUP4 - 1 (ROJ 06.02.26) (RVCD 06.04.26) Follows MCUPS 4 | (MOFE) - RPL07 - mCup Electrical Skids - Outside | Active | 07/25/25 | 06/04/26 | 288.8 | 47.5 |
|
136.2 |
RPL07.OFE.7060 |
OFE Delivery ROJ: mCUP Elec Skid - mCUP6 - 1 (ROJ 06.16.26) (RVCD 06.11.26) Follows MCUPS 6 | (MOFE) - RPL07 - mCup Electrical Skids - Outside | Active | 07/25/25 | 06/11/26 | 310.0 | 53.8 |
|
267.5 |
RPL07.OFE.7080 |
OFE Delivery ROJ: SSB Elec Room Skid (SSB) - 1 (ROJ08.06.26) (RVCD 08.27.26) | (MOFE) - RPL07 - SSB Electrical Room Skid | Active | 07/25/25 | 08/27/26 | 313.8 | 121.2 |
|
83.8 |
RPL07.OFE.7100 |
OFE Delivery ROJ: Ancillary Elec Skid (DHB) - 1 (ROJ10.15.26) (RVCD 11.12.26) | (MOFE) - RPL07 - Ancillary Electrical Skids | Active | 07/25/25 | 11/12/26 | 357.5 | 187.5 |
|
111.2 |
RPL07.OFE.7120 |
OFE Delivery ROJ: Ancillary Elec Skid (DHA) - 1 (ROJ10.15.26) (RVCD 11.12.26) | (MOFE) - RPL07 - Ancillary Electrical Skids | Active | 07/25/25 | 11/12/26 | 357.5 | 187.5 |
|
102.5 |
RPL07.OFE.7140 |
OFE Delivery ROJ: Ancillary Elec Skid (DHD) - 1 (ROJ11.17.26) (RVCD 12.14.26) | (MOFE) - RPL07 - Ancillary Electrical Skids | Active | 07/25/25 | 12/14/26 | 558.8 | 212.5 |
|
172.5 |
RPL07.OFE.7160 |
OFE Delivery ROJ: Ancillary Elec Skid (DHC) - 1 (ROJ11.17.26) (RVCD 12.14.26) | (MOFE) - RPL07 - Ancillary Electrical Skids | Active | 07/25/25 | 12/14/26 | 560.0 | 212.5 |
|
172.5 |
RPL07.OFE.7200 |
OFE Delivery ROJ: MES TWMU (DHB) - 1 | (MOFE) - RPL07 - MES TWMU | Active | 07/25/25 | 08/11/26 | 345.0 | 106.2 |
|
91.2 |
RPL07.OFE.7220 |
OFE Delivery ROJ: MES TWMU (DHA) - 1 | (MOFE) - RPL07 - MES TWMU | Active | 07/25/25 | 08/31/26 | 356.2 | 123.8 |
|
73.8 |
RPL07.OFE.7240 |
OFE Delivery ROJ: MES TWMU (DHD) - 1 | (MOFE) - RPL07 - MES TWMU | Active | 07/25/25 | 09/22/26 | 365.0 | 142.5 |
|
201.2 |
RPL07.OFE.7260 |
OFE Delivery ROJ: MES TWMU (DHC) - 1 | (MOFE) - RPL07 - MES TWMU | Active | 07/25/25 | 10/09/26 | 401.2 | 158.8 |
|
185.0 |
RPL07.OFE.7280 |
OFE Delivery ROJ: MTR Exterior - mCUP1 - 4 | (MOFE) - RPL07 - MTR Exterior | Active | 07/25/25 | 05/27/26 | 256.2 | 40.0 |
|
123.8 |
RPL07.OFE.7300 |
OFE Delivery ROJ: MTR Exterior - mCUP5 - 4 | (MOFE) - RPL07 - MTR Exterior | Active | 07/25/25 | 07/09/26 | 295.0 | 77.5 |
|
240.0 |
RPL07.OFE.7320 |
OFE Delivery ROJ: MTR Exterior - mCUP2 - 4 | (MOFE) - RPL07 - MTR Exterior | Active | 07/25/25 | 05/27/26 | 256.2 | 40.0 |
|
123.8 |
RPL07.OFE.7360 |
OFE Delivery ROJ: MTR Exterior - mCUP3 - 4 | (MOFE) - RPL07 - MTR Exterior | Active | 07/25/25 | 05/27/26 | 256.2 | 40.0 |
|
123.8 |
RPL07.OFE.7400 |
OFE Delivery ROJ: MTR Exterior - mCUP4 - 4 | (MOFE) - RPL07 - MTR Exterior | Active | 07/25/25 | 05/27/26 | 256.2 | 40.0 |
|
123.8 |
RPL07.OFE.7420 |
OFE Delivery ROJ: MTR Exterior - mCUP6 - 4 | (MOFE) - RPL07 - MTR Exterior | Active | 07/25/25 | 07/09/26 | 295.0 | 77.5 |
|
240.0 |
RPL07.OFE.7440 |
OFE Delivery ROJ: LV Side Aisle (DHB) - 21 | (MOFE) - RPL07 - LV Side Aisle | Active | 07/25/25 | 08/26/26 | 348.8 | 120.0 |
|
35.0 |
RPL07.OFE.7460 |
OFE Delivery ROJ: LV Side Aisle (DHA) - 21 | (MOFE) - RPL07 - LV Side Aisle | Active | 07/25/25 | 09/14/26 | 363.8 | 135.0 |
|
32.5 |
RPL07.OFE.7480 |
OFE Delivery ROJ: LV Side Aisle (DHD) - 17 | (MOFE) - RPL07 - LV Side Aisle | Active | 07/25/25 | 10/05/26 | 472.5 | 153.8 |
|
118.8 |
RPL07.OFE.7500 |
OFE Delivery ROJ: LV Side Aisle (DHC) - 17 | (MOFE) - RPL07 - LV Side Aisle | Active | 07/25/25 | 10/22/26 | 485.0 | 170.0 |
|
131.2 |
RPL07.ORV3.010020 |
OFE - Delivery ROJ: ORv3 for CFD B.1 (ROJ 03.18.27) (RVCD ) | Data Hall B | Active | 07/25/25 | 03/17/27 | 6.2 | 291.2 |
|
32.5 |
RPL07.ORV3.010040 |
OFE - Delivery ROJ: ORv3 for CFD B.2 (ROJ 03.31.27) (RVCD ) | Data Hall B | Active | 07/25/25 | 03/30/27 | 6.2 | 301.2 |
|
32.5 |
RPL07.ORV3.010060 |
OFE - Delivery ROJ: ORv3 for CFD B.3 (ROJ 04.12.27) (RVCD ) | Data Hall B | Active | 07/25/25 | 04/09/27 | 6.2 | 311.2 |
|
32.5 |
RPL07.ORV3.010080 |
OFE - Delivery ROJ: ORv3 for CFD B.4 (ROJ 04.22.27) (RVCD ) | Data Hall B | Active | 07/25/25 | 04/21/27 | 6.2 | 321.2 |
|
32.5 |
RPL07.ORV3.010100 |
OFE - Delivery ROJ: ORv3 for CFD B.5 (ROJ 05.04.27) (RVCD ) | Data Hall B | Active | 07/25/25 | 05/03/27 | 6.2 | 331.2 |
|
32.5 |
RPL07.ORV3.010120 |
OFE - Delivery ROJ: ORv3 for CFD A.1 (ROJ 03.31.27) (RVCD ) | Data Hall A | Active | 07/25/25 | 05/01/26 | 6.2 | 18.8 |
|
322.5 |
RPL07.ORV3.010140 |
OFE - Delivery ROJ: ORv3 for CFD A.2 (ROJ 04.06.27) (RVCD ) | Data Hall A | Active | 07/25/25 | 04/05/27 | 6.2 | 306.2 |
|
40.0 |
RPL07.ORV3.010160 |
OFE - Delivery ROJ: ORv3 for CFD A.3 (ROJ 04.16.27) (RVCD ) | Data Hall A | Active | 07/25/25 | 04/15/27 | 6.2 | 316.2 |
|
40.0 |
RPL07.ORV3.010180 |
OFE - Delivery ROJ: ORv3 for CFD A.4 (ROJ 04.28.27) (RVCD ) | Data Hall A | Active | 07/25/25 | 04/27/27 | 6.2 | 326.2 |
|
40.0 |
RPL07.ORV3.010200 |
OFE - Delivery ROJ: ORv3 for CFD A.5 (ROJ 05.10.27) (RVCD ) | Data Hall A | Active | 07/25/25 | 05/07/27 | 6.2 | 336.2 |
|
40.0 |
RPL07.ORV3.010220 |
OFE - Delivery ROJ: ORv3 for CFD D.1 (ROJ 06.03.27) (RVCD ) | Data Hall D | Active | 07/25/25 | 06/02/27 | 6.2 | 357.5 |
|
57.5 |
RPL07.ORV3.010240 |
OFE - Delivery ROJ: ORv3 for CFD D.2 (ROJ 06.15.27) (RVCD ) | Data Hall D | Active | 07/25/25 | 06/14/27 | 6.2 | 367.5 |
|
67.5 |
RPL07.ORV3.010260 |
OFE - Delivery ROJ: ORv3 for CFD D.3 (ROJ 06.25.27) (RVCD ) | Data Hall D | Active | 07/25/25 | 06/24/27 | 6.2 | 377.5 |
|
67.5 |
RPL07.ORV3.010280 |
OFE - Delivery ROJ: ORv3 for CFD D.4 (ROJ 07.08.27) (RVCD ) | Data Hall D | Active | 07/25/25 | 07/07/27 | 6.2 | 387.5 |
|
67.5 |
RPL07.ORV3.010300 |
OFE - Delivery ROJ: ORv3 for CFD C.1 (ROJ 06.15.27) (RVCD ) | Data Hall C | Active | 07/25/25 | 06/14/27 | 6.2 | 367.5 |
|
57.5 |
RPL07.ORV3.010320 |
OFE - Delivery ROJ: ORv3 for CFD C.2 (ROJ 06.25.27) (RVCD ) | Data Hall C | Active | 07/25/25 | 06/24/27 | 6.2 | 377.5 |
|
57.5 |
RPL07.ORV3.010340 |
OFE - Delivery ROJ: ORv3 for CFD C.3 (ROJ 07.08.27) (RVCD ) | Data Hall C | Active | 07/25/25 | 07/07/27 | 6.2 | 387.5 |
|
57.5 |
RPL07.ORV3.010360 |
OFE - Delivery ROJ: ORv3 for CFD C.4 (ROJ 07.20.27) (RVCD ) | Data Hall C | Active | 07/25/25 | 07/19/27 | 6.2 | 397.5 |
|
57.5 |
DES.IFP.1000 |
Building Permit Package - 100% IFP Development | IFP | Complete | 07/28/25 | 08/11/25 | 13.8 | 0.0 |
|
0.0 |
PRE.CIDD.1180 |
Submit Documentation for Building Permits | Precon - Critical Information / Decision Dates | Complete | 07/28/25 | 07/28/25 | 0.0 | 0.0 |
|
0.0 |
PRE.CIDD.1200 |
Local AHJ Review and Approval of Building Permits (PCM to confirm durations with AHJ/SS) | Precon - Critical Information / Decision Dates | Complete | 07/29/25 | 10/24/25 | 12.5 | 0.0 |
|
0.0 |
PRE.BNS.1200 |
Baseline 2 Issuance | BL2 | Complete | 08/04/25 | 08/04/25 | 0.0 | 0.0 |
|
0.0 |
PRE.BNS.1220 |
Meta / DPR Baseline 2 Review | BL2 | Complete | 08/05/25 | 09/02/25 | 25.0 | 0.0 |
|
0.0 |
PRE.CIDD.1120 |
Finalize Site Logistics * Obsolete | Obsolete | Complete | 08/05/25 | 10/17/25 | 35.0 | 0.0 |
|
0.0 |
DES.IFP.1020 |
Building IFP Design Completion | IFP | Complete | 08/11/25 | 08/11/25 | 0.0 | 0.0 |
|
0.0 |
RPL.PD.D.PX210.XR |
IFP Set and Model - RPL-0 - Complete | IFP | Complete | 08/11/25 | 08/11/25 | 0.0 | 0.0 |
|
0.0 |
DES.IFC.1000 |
IFC Package - Development | IFC | Complete | 08/12/25 | 09/23/25 | 36.2 | 0.0 |
|
0.0 |
PRE.BNS.1180 |
Meta Review & Comment - Baseline 2 | BL2 | Complete | 08/29/25 | 09/19/25 | 18.8 | 0.0 |
|
0.0 |
PRE.CIDD.1220 |
Steel Mill Order Package Release (After IFP) | Precon - Critical Information / Decision Dates | Complete | 09/09/25 | 09/09/25 | 0.0 | 0.0 |
|
0.0 |
PRE.BNS.1240 |
GC Project Review Package Budget Estimate Agreed | IGMP | Complete | 09/19/25 | 09/19/25 | 0.0 | 0.0 |
|
0.0 |
PRE.TPBD.1020 |
Electrical Allocation SA Package | Trade Partner Bid Development | Complete | 09/22/25 | 10/03/25 | 35.0 | 0.0 |
|
0.0 |
RPL07.VDC.1000 |
BIM Milestone (Coordination Start) | VDC Coordination | Complete | 09/22/25 | 09/22/25 | 0.0 | 0.0 |
|
0.0 |
RPL07.VDC.1020 |
BIM Milestone (Coordination GC QC) | VDC Coordination | Complete | 09/22/25 | 09/26/25 | 6.2 | 0.0 |
|
0.0 |
DES.IFC.1020 |
IFC Package - Design Completion | IFC | Complete | 09/23/25 | 09/23/25 | 0.0 | 0.0 |
|
0.0 |
PRE.BNS.1260 |
iGMP Development | IGMP | Complete | 09/23/25 | 09/23/25 | 0.0 | 0.0 |
|
0.0 |
PRE.BNS.1340 |
iGMP Review by Meta | IGMP | Complete | 09/23/25 | 10/13/25 | 18.8 | 0.0 |
|
0.0 |
RPL.PD.D.PX310.XR |
IFC Set - RPL-07- Complete | IFC | Complete | 09/23/25 | 09/23/25 | 0.0 | 0.0 |
|
0.0 |
PRE.BNS.1300 |
fGMP Development * Obsolete | Obsolete | Complete | 09/24/25 | 10/17/25 | 41.2 | 0.0 |
|
0.0 |
PRE.TPBD.1120 |
Fire Protection - Submit for Meta Review | Trade Partner Bid Development | Complete | 09/24/25 | 09/24/25 | 18.8 | 0.0 |
|
0.0 |
PRE.TPBD.1200 |
Hot Aisle Containment - Submit for Meta Review | Trade Partner Bid Development | Complete | 09/24/25 | 10/13/25 | 37.5 | 0.0 |
|
0.0 |
PRE.TPBD.1220 |
Doors / Frames / Hardware - Submit for Meta Review | Trade Partner Bid Development | Complete | 09/24/25 | 10/03/25 | 25.0 | 0.0 |
|
0.0 |
PRE.MIR.1080 |
Fire Protection SA - Meta Review / Authorization | Meta Internal Review of Trade Partner Bids | Complete | 09/25/25 | 10/22/25 | 12.5 | 0.0 |
|
0.0 |
PRE.CIDD.1240 |
Approval of Building Permits (starting Foundations) | Precon - Critical Information / Decision Dates | Complete | 09/26/25 | 09/26/25 | 0.0 | 0.0 |
|
0.0 |
RPL07.VDC.1040 |
T0 (mCUP Yard/Ext.) - BIM Model & Coordination | TIER 0 - mCUP Yard / Exterior | Complete | 09/29/25 | 12/05/25 | 32.5 | 0.0 |
|
0.0 |
ICM.B7.1830 |
[SSDCB2] Delivery of PTX - Pad Mounted Transformers (First Delivery) | Construction | Complete | 09/30/25 | 09/30/25 | 0.0 | 0.0 |
|
0.0 |
PRE.TPBD.1000 |
Mechanical Allocation SA Package | Trade Partner Bid Development | Complete | 10/01/25 | 10/03/25 | 35.0 | 0.0 |
|
0.0 |
PRE.MIR.1240 |
Doors / Frames / Hardware SA - Meta Review / Authorization | Meta Internal Review of Trade Partner Bids | Complete | 10/03/25 | 10/03/25 | 12.5 | 0.0 |
|
0.0 |
PRE.MIR.1000 |
Electrical SA - Meta Review / Authorization | Meta Internal Review of Trade Partner Bids | Complete | 10/06/25 | 10/17/25 | 12.5 | 0.0 |
|
0.0 |
PRE.MIR.1020 |
Mechanical SA - Meta Review / Authorization | Meta Internal Review of Trade Partner Bids | Complete | 10/06/25 | 10/22/25 | 12.5 | 0.0 |
|
0.0 |
RPL07.VDC.1060 |
T0 (Bldg07) - BIM Model & Coordination | TIER 0 - Building 07 | Complete | 10/06/25 | 12/12/25 | 25.0 | 0.0 |
|
0.0 |
RPL07.CFCI.1000 |
RPL07 - Submittals Prep & Submit for Review - Struc. Conc. (Fdn Ready Mix) | (CFCI) Div. 03 - (Foundation) Struc. Concrete | Complete | 10/09/25 | 10/09/25 | 6.2 | 0.0 |
|
0.0 |
RPL07.CFCI.1010 |
RPL07 - Submittals Review & Approval - Struc. Conc. (Fdn Ready Mix) | (CFCI) Div. 03 - (Foundation) Struc. Concrete | Complete | 10/10/25 | 10/15/25 | 12.5 | 0.0 |
|
0.0 |
PRE.BNS.1360 |
Meta iGMP Submission Comments sent to GC | IGMP | Complete | 10/13/25 | 10/13/25 | 0.0 | 0.0 |
|
0.0 |
PRE.MIR.1220 |
Hot Aisle Containment SA - Meta Review / Authorization | Meta Internal Review of Trade Partner Bids | Complete | 10/14/25 | 01/14/26 | 12.5 | 0.0 |
|
0.0 |
RPL07.CFCI.1030 |
RPL07 - Submittals Prep & Submit for Review - Struc. Conc. (SOG/SOMD Ready Mix) | (CFCI) Div. 03 - (SOG/SOMD) Struc. Concrete | Complete | 10/14/25 | 10/14/25 | 6.2 | 0.0 |
|
0.0 |
RPL07.CFCI.1040 |
RPL07 - Submittals Review & Approval - Struc. Conc. (SOG/SOMD/Pads Ready Mix) | (CFCI) Div. 03 - (SOG/SOMD) Struc. Concrete | Complete | 10/15/25 | 10/24/25 | 12.5 | 0.0 |
|
0.0 |
GCD.RPL07.1056 |
Pad Ready - RPL07 - **OBSOLETE** | Obsolete | Complete | 10/17/25 | 10/17/25 | 0.0 | 0.0 |
|
0.0 |
PRE.BNS.1320 |
iGMP Submission to Meta | IGMP | Complete | 10/17/25 | 10/17/25 | 0.0 | 0.0 |
|
0.0 |
RPL.07.D.61011.XR |
Pad Ready - RPL07 (Remaining 50%) OBSOLETE | Obsolete | Complete | 10/17/25 | 10/17/25 | 0.0 | 0.0 |
|
0.0 |
RPL.07.D.70100.XR |
External Tie from RPL06 - mCup Equipment Crane Crew Flow (RPL06.MCUP.LP2.1500) *OBSOLETE | Obsolete | Complete | 10/17/25 | 10/17/25 | 0.0 | 0.0 |
|
0.0 |
RPL.07.D.73910.XG |
Production Cabling Start - SS-1 Entry to SS-1 DH-A - Obsolete | Obsolete | Complete | 10/17/25 | 10/17/25 | 0.0 | 0.0 |
|
0.0 |
RPL.07.D.73910.XG |
Production Cabling Start - SS-1 Entry to SS-1 DH-A - Obsolete | Obsolete | Complete | 10/17/25 | 10/17/25 | 0.0 | 0.0 |
|
0.0 |
RPL.07.D.73910.XG |
Production Cabling Start - SS-1 Entry to SS-1 DH-A - Obsolete | Obsolete | Complete | 10/17/25 | 10/17/25 | 0.0 | 0.0 |
|
0.0 |
RPL.07.D.73920.XG |
Production Cabling Start - SS-1 Entry to SS-1 DH-B - **OBSOLETE** | Obsolete | Complete | 10/17/25 | 10/17/25 | 0.0 | 0.0 |
|
0.0 |
RPL.07.D.73930.XG |
Production Cabling Start - SS-1 Entry to SS-1 DH-C - **OBSOLETE** | Obsolete | Complete | 10/17/25 | 10/17/25 | 0.0 | 0.0 |
|
0.0 |
RPL.07.D.73940.XG |
Production Cabling Start - SS-1 Entry to SS-1 DH-D - **OBSOLETE** | Obsolete | Complete | 10/17/25 | 10/17/25 | 0.0 | 0.0 |
|
0.0 |
RPL.GF.D.G3971.XG |
GS.MDF to GS.IDF DH Complete - DHA - RPL7 - **OBSOLETE** | Obsolete | Complete | 10/17/25 | 10/17/25 | 0.0 | 0.0 |
|
0.0 |
RPL.GF.D.G3972.XG |
GS.MDF to GS.IDF DH Complete - DHB - RPL7 - **OBSOLETE** | Obsolete | Complete | 10/17/25 | 10/17/25 | 0.0 | 0.0 |
|
0.0 |
RPL.GF.D.G3973.XG |
GS.MDF to GS.IDF DH Complete - DHC - RPL7 - **OBSOLETE** | Obsolete | Complete | 10/17/25 | 10/17/25 | 0.0 | 0.0 |
|
0.0 |
RPL.GF.D.G3974.XG |
GS.MDF to GS.IDF DH Complete - DHD - RPL7 - **OBSOLETE** | Obsolete | Complete | 10/17/25 | 10/17/25 | 0.0 | 0.0 |
|
0.0 |
RPL.GF.D.G3975.XG |
EF1 to GS.MDF Complete - RPL7 - **OBSOLETE** | Obsolete | Complete | 10/17/25 | 10/17/25 | 0.0 | 0.0 |
|
0.0 |
RPL.GF.D.G3976.XG |
EF2 to GS.MDF Complete - RPL7 - **OBSOLETE** | Obsolete | Complete | 10/17/25 | 10/17/25 | 0.0 | 0.0 |
|
0.0 |
RPL.GF.D.G4715.XG |
Rack & Cabinets Complete - DHA - RPL7 - **OBSOLETE** | Obsolete | Complete | 10/17/25 | 10/17/25 | 0.0 | 0.0 |
|
0.0 |
RPL.GF.D.G4725.XG |
Rack & Cabinets Complete - DHB - RPL7 - **OBSOLETE** | Obsolete | Complete | 10/17/25 | 10/17/25 | 0.0 | 0.0 |
|
0.0 |
RPL.GF.D.G4730.XG |
Rack & Cabinets Complete - DHC - RPL7 - **OBSOLETE** | Obsolete | Complete | 10/17/25 | 10/17/25 | 0.0 | 0.0 |
|
0.0 |
RPL.GF.D.G4745.XG |
Rack & Cabinets Complete - DHD - RPL7 - **OBSOLETE** | Obsolete | Complete | 10/17/25 | 10/17/25 | 0.0 | 0.0 |
|
0.0 |
RPL.GF.D.G4871.XG |
EF to DH Conveyance Complete - DHA - RPL7 - **OBSOLETE** | Obsolete | Complete | 10/17/25 | 10/17/25 | 0.0 | 0.0 |
|
0.0 |
RPL.GF.D.G4872.XG |
EF to DH Conveyance Complete - DHB - RPL7 - **OBSOLETE** | Obsolete | Complete | 10/17/25 | 10/17/25 | 0.0 | 0.0 |
|
0.0 |