Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL07 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:16 PM
· 5237 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
0
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL07.INT.DHA.03820 |
RPL07.Interior.DHA - Control Fault Domain 3 - Install Duct (LV Side) | LV Side Tie-ins | Not Started | 10/22/26 | 10/27/26 | 5.0 | 5.0 |
|
95.0 |
RPL07.INT.DHB.01870 |
RPL07.Interior.DHB - Control Fault Domain 5 - Install LV Side Aisle HAC Busway | LV Side Tie-ins | Not Started | 10/22/26 | 10/27/26 | 5.0 | 5.0 |
|
155.0 |
RPL07.INT.DHB.02480 |
RPL07.Interior.DHB - OFE - Control Fault Domain 2 (HAC) | Control Fault Domain 2 | Not Started | 10/22/26 | 11/12/26 | 18.8 | 18.8 |
|
30.0 |
RPL07.INT.DHC.01090 |
RPL07.Interior.DHC - LV Skids and TopHat Tie-ins (LOE) | DHC - LV Skids and TopHat | Not Started | 10/22/26 | 11/20/26 | 26.2 | 26.2 |
|
192.5 |
RPL07.INT.DHC.01091 |
RPL07.Interior.DHC - LV Skids and TopHat - Set & Anchor Interconnects | DHC - LV Skids and TopHat | Not Started | 10/22/26 | 11/09/26 | 16.2 | 16.2 |
|
192.5 |
RPL07.INT.DHC.01100 |
RPL07.Interior.DHC - Tie-ins - WBS Summary | Tie-Ins | Not Started | 10/22/26 | 06/03/27 | 190.0 | 190.0 |
|
136.2 |
RPL07.INT.DHD.01120 |
RPL07.Interior.DHD - OFE - Control Fault Domain 1 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | Control Fault Domain 1 | Not Started | 10/22/26 | 02/12/27 | 95.0 | 95.0 |
|
37.5 |
RPL07.INT.DHD.02270 |
RPL07.Interior.DHD - OFE - Control Fault Domain 1 (LV Side Aisle) | Control Fault Domain 1 | Not Started | 10/22/26 | 10/28/26 | 6.2 | 6.2 |
|
103.8 |
RPL07.INT.SSB.03060 |
RPL07.Interior.SSB - Final Finishes & Fixtures - Hang Tape Bed and Fire/Caulking | Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) | Not Started | 10/22/26 | 10/28/26 | 6.2 | 6.2 |
|
222.5 |
RPL07.INT.SSB.06660 |
RPL07.Interior.SSB - Final Finishes & Fixtures - Framing RO Verification, Tile Finish & ADA Verification (Pre Drywall) | Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) | Not Started | 10/22/26 | 10/28/26 | 6.2 | 6.2 |
|
210.0 |
RPL.07.D.73210.XR |
500kva Temp Power Skids Energized (First 10 MW or Gen) | Receive Milestones (XREFs) | Not Started | 10/23/26 | 10/23/26 | 0.0 | 0.0 |
|
42.5 |
RPL.07.D.73320.XR |
Pull and Term MV Skids - RPL07 DHB | Receive Milestones (XREFs) | Not Started | 10/23/26 | 10/23/26 | 0.0 | 0.0 |
|
42.5 |
RPL.07.D.73410.XR |
SS Power to RPL07 MSG 1B Numeric (Cx Temp) | Receive Milestones (XREFs) | Not Started | 10/23/26 | 10/23/26 | 0.0 | 0.0 |
|
42.5 |
RPL.07.D.73510.XR |
Substation Perm Power Cutover - RPL07 DH & mCUPs | Receive Milestones (XREFs) | Not Started | 10/23/26 | 10/23/26 | 0.0 | 0.0 |
|
42.5 |
RPL.07.D.73820.XR |
100MW Cx Temp Power to MV Skids RPL07 DHB Available | Receive Milestones (XREFs) | Not Started | 10/23/26 | 10/23/26 | 0.0 | 0.0 |
|
42.5 |
RPL07.CON.WP2.06800 |
RPL07.Conn - GSIDF/DH C2 - WBS Summary | Int. IDF OFE/MOFE - GSIDF7C2 | Not Started | 10/23/26 | 11/17/26 | 21.2 | 21.2 |
|
352.5 |
RPL07.CON.WP2.06820 |
RPL07.Conn - GSIDF/DH C2 - Install Infrastructure (Racks, Waterfalls etc.) | Infrastructure | Not Started | 10/23/26 | 10/29/26 | 6.2 | 6.2 |
|
293.8 |
RPL07.INT.CTRC.1960 |
RPL07.Interior.Center-Corridor - BoW - Install Horizontal Steel Supports for Cable Tray (IFP Add) | Balance of Walls & Overhead | Not Started | 10/23/26 | 10/30/26 | 7.5 | 7.5 |
|
66.2 |
RPL07.INT.DHB.01890 |
RPL07.Interior.DHB - Control Fault Domain 5 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 10/23/26 | 10/28/26 | 5.0 | 5.0 |
|
165.0 |
RPL07.INT.DHC.02170 |
RPL07.Interior.DHC - Priority - Install Security | OverHead | Not Started | 10/23/26 | 10/26/26 | 2.5 | 2.5 |
|
318.8 |
RPL07.INT.DHD.01113 |
RPL07.Interior.DHD - MES Skids - CDU Tie-Ins | DHD - MES Skids | Not Started | 10/23/26 | 11/16/26 | 20.0 | 20.0 |
|
183.8 |
RPL07.INT.ENDC.01190 |
RPL07.Interior.End-Corridor - OFE - DHD (1x GS.IDF) D2 | OFE/MOFE & CFCI | Not Started | 10/23/26 | 10/29/26 | 6.2 | 6.2 |
|
150.0 |
RPL07.INT.SSB.01300 |
RPL07.Interior.SSB - Loading Dock and Storage - Install Fire Life Safety | Loading Dock and Storage | Not Started | 10/23/26 | 11/02/26 | 8.8 | 8.8 |
|
188.8 |
RPL07.INT.SSBC.3220 |
RPL07.Interior.SSBC LO #06 - Fire Safing OH and In-wall | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 10/23/26 | 10/23/26 | 1.2 | 1.2 |
|
93.8 |
RPL07.INT.SSBC.4200 |
RPL07.Interior.SSBC LO #07 - Mechanical Tie-In | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 10/23/26 | 10/26/26 | 2.5 | 2.5 |
|
87.5 |
RPL07.INT.SSBC.4300 |
RPL07.Interior.SSBC LO #07 - Electrical Tie-In | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 10/23/26 | 10/29/26 | 6.2 | 6.2 |
|
87.5 |
DCC.B7.3225 |
[SSDCB2] CorpNet/Security/FacNet Ready [DHB] | Connectivity | Not Started | 10/26/26 | 10/26/26 | 0.0 | 0.0 |
|
306.2 |
RPL07.INT.CTRC.1340 |
RPL07.Interior.Center-Corridor - BoW - Install VAV's/Duct Branches | Balance of Walls & Overhead | Not Started | 10/26/26 | 10/30/26 | 6.2 | 6.2 |
|
130.0 |
RPL07.INT.CTRC.1440 |
RPL07.Interior.Center-Corridor - BoW - Mechanical Tie-In | Balance of Walls & Overhead | Not Started | 10/26/26 | 10/30/26 | 6.2 | 6.2 |
|
36.2 |
RPL07.INT.DHA.01490 |
RPL07.Interior.DHA - OFE - Control Fault Domain 4 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | Control Fault Domain 4 | Not Started | 10/26/26 | 01/14/27 | 67.5 | 67.5 |
|
48.8 |
RPL07.INT.DHA.01510 |
RPL07.Interior.DHA - Control Fault Domain 3 - Install LV Side Aisle HAC Busway | LV Side Tie-ins | Not Started | 10/26/26 | 10/29/26 | 5.0 | 5.0 |
|
125.0 |
RPL07.INT.DHA.03660 |
RPL07.Interior.DHA - OFE - Control Fault Domain 4 (LV Side Aisle) | Control Fault Domain 4 | Not Started | 10/26/26 | 10/29/26 | 5.0 | 5.0 |
|
58.8 |
RPL07.INT.DHD.01160 |
RPL07.Interior.DHD - Tie-ins - Control Fault Domain 1 - WBS Summary | Control Fault Domain 1 | Not Started | 10/26/26 | 04/06/27 | 136.2 | 136.2 |
|
70.0 |
RPL07.INT.DHD.02510 |
RPL07.Interior.DHD - Control Fault Domain 1 - Install Duct (LV Side) | LV Side Tie-ins | Not Started | 10/26/26 | 10/30/26 | 6.2 | 6.2 |
|
156.2 |
RPL07.INT.SBC.03540 |
RPL07.Interior.SSB-Corridor - BoW - Hang Drywall (Both side of Corridor Wall) | Balance of Walls & Overhead | Not Started | 10/26/26 | 11/03/26 | 8.8 | 8.8 |
|
90.0 |
RPL07.INT.SSBC.3260 |
RPL07.Interior.SSBC LO #06 - Install Backing | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 10/26/26 | 10/26/26 | 1.2 | 1.2 |
|
93.8 |
RPL07.SKN.W.LO.01395 |
RPL07.SKIN.LO#16 - Install IMP Flashing | Build back Exterior Leave Out Walls #16 (SSB - North of Loading Dock) | Not Started | 10/26/26 | 10/30/26 | 6.2 | 6.2 |
|
67.5 |
RPL.07.D.73710.XG |
RMUs/MV Skids Set (Ready for Longhorn Pulls) - DHA | Give Milestones (XREFs) | Not Started | 10/27/26 | 10/27/26 | 0.0 | 0.0 |
|
370.0 |
RPL.07.D.74000.XG |
Ready for MV Cable Pull DH A (MVs - Qty 10)* | Give Milestones (XREFs) | Not Started | 10/27/26 | 10/27/26 | 0.0 | 0.0 |
|
370.0 |
RPL07.EY.DHC.01220 |
RPL07.EY.DHC - Install MV, RMUs & Electrical Panels (Qty 8) | OFE | Not Started | 10/27/26 | 11/24/26 | 25.0 | 25.0 |
|
138.8 |
RPL07.EY.DHC.01230 |
RPL07.EY.DHC - OFE - MV - WBS Summary | OFE | Not Started | 10/27/26 | 05/26/27 | 180.0 | 180.0 |
|
101.2 |
RPL07.INT.DHA.01130 |
RPL07.Interior.DHA - Control Fault Domain 1 - Install Duct (MES Side) | Remaining Tie-ins post Mech Side Aisle install | Not Started | 10/27/26 | 11/24/26 | 25.0 | 25.0 |
|
33.8 |
RPL07.INT.DHA.01140 |
RPL07.Interior.DHA - Control Fault Domain 1 - Install Vesda / FA | Remaining Tie-ins post Mech Side Aisle install | Not Started | 10/27/26 | 11/24/26 | 25.0 | 25.0 |
|
46.2 |
RPL07.INT.DHA.01150 |
RPL07.Interior.DHA - Control Fault Domain 1 - Install FW | Remaining Tie-ins post Mech Side Aisle install | Not Started | 10/27/26 | 11/24/26 | 25.0 | 25.0 |
|
33.8 |
RPL07.INT.DHA.01520 |
RPL07.Interior.DHA - Control Fault Domain 3 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 10/27/26 | 10/30/26 | 5.0 | 5.0 |
|
185.0 |
RPL07.INT.DHA.02180 |
RPL07.Interior.DHA - Control Fault Domain 1 - Install TW | Remaining Tie-ins post Mech Side Aisle install | Not Started | 10/27/26 | 11/24/26 | 25.0 | 25.0 |
|
33.8 |
RPL07.INT.DHB.01300 |
RPL07.Interior.DHB - Control Fault Domain 1 - Install Mechanical Side Aisle Cable Tray | Remaining Tie-ins post Mech Side Aisle install | Not Started | 10/27/26 | 11/24/26 | 25.0 | 25.0 |
|
33.8 |
RPL07.INT.DHB.02500 |
RPL07.Interior.DHB - OFE - Control Fault Domain 2 (Mech Side Aisle) | Control Fault Domain 2 | Not Started | 10/27/26 | 11/13/26 | 16.2 | 16.2 |
|
40.0 |
RPL07.INT.DHC.01110 |
RPL07.Interior.DHC - MES Skids Tie-ins (LOE) | DHC - MES Skids | Not Started | 10/27/26 | 12/08/26 | 35.0 | 35.0 |
|
171.2 |
RPL07.INT.DHC.01111 |
RPL07.Interior.DHC - MES Skids - Set & Anchor Interconnects | DHC - MES Skids | Not Started | 10/27/26 | 11/18/26 | 20.0 | 20.0 |
|
171.2 |
RPL07.INT.DHC.02190 |
RPL07.Interior.DHC - Priority - Install Controls / EPMS / BMS | OverHead | Not Started | 10/27/26 | 10/29/26 | 3.8 | 3.8 |
|
318.8 |
RPL07.INT.DHD.01114 |
RPL07.Interior.DHD - MES Skids - BMS Tie-Ins | DHD - MES Skids | Not Started | 10/27/26 | 11/18/26 | 20.0 | 20.0 |
|
183.8 |
RPL07.INT.ENDC.07080 |
RPL07.Interior.End-Corridor - Final Finishes & Fixtures - Water Proofing/ Tape Paint | Restrooms | Not Started | 10/27/26 | 11/02/26 | 6.2 | 6.2 |
|
173.8 |
RPL07.INT.SSB.14180 |
RPL07.Interior.SSB LO #01 to #05 - Install Door Frames | OH & Framing | Not Started | 10/27/26 | 10/28/26 | 2.5 | 2.5 |
|
87.5 |
RPL07.INT.SSBC.3280 |
RPL07.Interior.SSBC LO #06 - QC - Backings/Walls | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 10/27/26 | 10/28/26 | 2.5 | 2.5 |
|
93.8 |
RPL07.SKN.S.LO.03060 |
RPL07.SKIN.LO#17 - Stemwall Water Proofing | Build back Exterior Leave Out Walls #17 (CC - South) | Not Started | 10/27/26 | 10/28/26 | 2.5 | 2.5 |
|
91.2 |
RPL07.EY.DHA.01250 |
RPL07.EY.DHA - Install Electrical Tie-ins (include penetration detail) | Tie-ins | Not Started | 10/28/26 | 11/10/26 | 12.5 | 12.5 |
|
30.0 |
RPL07.EY.DHA.01260 |
RPL07.EY.DHA - Tie-ins - WBS Summary | Tie-ins | Not Started | 10/28/26 | 01/12/27 | 62.5 | 62.5 |
|
137.5 |
RPL07.INT.DHA.01570 |
RPL07.Interior.DHA - Tie-ins - Control Fault Domain 4 - WBS Summary | Control Fault Domain 4 | Not Started | 10/28/26 | 03/03/27 | 105.0 | 105.0 |
|
86.2 |
RPL07.INT.DHA.03840 |
RPL07.Interior.DHA - Control Fault Domain 4 - Install Duct (LV Side) | LV Side Tie-ins | Not Started | 10/28/26 | 11/02/26 | 5.0 | 5.0 |
|
110.0 |
RPL07.INT.DHC.01092 |
RPL07.Interior.DHC - LV Skids and TopHat - Maintenance and Reserve Busways | DHC - LV Skids and TopHat | Not Started | 10/28/26 | 11/13/26 | 15.0 | 15.0 |
|
192.5 |
RPL07.INT.DHD.01230 |
RPL07.Interior.DHD - Control Fault Domain 1 - Install LV Side Aisle HAC Busway | LV Side Tie-ins | Not Started | 10/28/26 | 11/03/26 | 6.2 | 6.2 |
|
165.0 |
RPL07.INT.ENDC.1260 |
RPL07.Interior.End-Corridor - BoW - Install Electrical Lowside OH and In-wall and Lights (Coordinate Lights location to | Balance of Walls & Overhead | Not Started | 10/28/26 | 11/10/26 | 12.5 | 12.5 |
|
125.0 |
RPL07.INT.SSB.01440 |
RPL07.Interior.SSB - Loading Dock and Storage - Install Store Front Frames | Loading Dock and Storage | Not Started | 10/28/26 | 11/05/26 | 8.8 | 8.8 |
|
190.0 |
RPL07.INT.DHD.01115 |
RPL07.Interior.DHD - MES Skids - EPMS Tie-In | DHD - MES Skids | Not Started | 10/29/26 | 11/20/26 | 20.0 | 20.0 |
|
183.8 |
RPL07.INT.DHD.01210 |
RPL07.Interior.DHD - OFE - Control Fault Domain 2 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | Control Fault Domain 2 | Not Started | 10/29/26 | 03/01/27 | 101.2 | 101.2 |
|
35.0 |
RPL07.INT.DHD.01250 |
RPL07.Interior.DHD - Control Fault Domain 1 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 10/29/26 | 11/04/26 | 6.2 | 6.2 |
|
165.0 |
RPL07.INT.DHD.02330 |
RPL07.Interior.DHD - OFE - Control Fault Domain 2 (LV Side Aisle) | Control Fault Domain 2 | Not Started | 10/29/26 | 11/03/26 | 5.0 | 5.0 |
|
116.2 |
RPL07.INT.SSB.01480 |
RPL07.Interior.SSB - Loading Dock and Storage - Security Trim Out | Loading Dock and Storage | Not Started | 10/29/26 | 11/06/26 | 8.8 | 8.8 |
|
168.8 |
RPL07.INT.SSB.06680 |
RPL07.Interior.SSB - Final Finishes & Fixtures - Install Cement Board/ Drywall | Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) | Not Started | 10/29/26 | 11/04/26 | 6.2 | 6.2 |
|
210.0 |
RPL07.INT.SSB.14340 |
RPL07.Interior.SSB LO #01 to #05 - MEPF Hard Lid Rough-In/ Close up Inspection | OH & Framing | Not Started | 10/29/26 | 11/03/26 | 5.0 | 5.0 |
|
87.5 |
RPL07.INT.SSBC.3360 |
RPL07.Interior.SSBC LO #06 - Hang Drywall | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 10/29/26 | 10/30/26 | 2.5 | 2.5 |
|
93.8 |
RPL07.SKN.S.LO.03080 |
RPL07.SKIN.LO#17 - Install IMP Flashing | Build back Exterior Leave Out Walls #17 (CC - South) | Not Started | 10/29/26 | 10/30/26 | 2.5 | 2.5 |
|
91.2 |
RPL07.CON.WP2.06600 |
RPL07.Conn - GSIDF/DH D2 - WBS Summary | Int. IDF OFE/MOFE - GSIDF7D2 | Not Started | 10/30/26 | 11/24/26 | 21.2 | 21.2 |
|
346.2 |
RPL07.CON.WP2.06620 |
RPL07.Conn - GSIDF/DH D2 - Install Infrastructure (Racks, Waterfalls etc.) | Infrastructure | Not Started | 10/30/26 | 11/05/26 | 6.2 | 6.2 |
|
278.8 |
RPL07.CON.WP2.06840 |
RPL07.Conn - GSIDF/DH C2 - Install Cabling (Pull, Splice & terminate) | Cabling | Not Started | 10/30/26 | 11/06/26 | 7.5 | 7.5 |
|
356.2 |
RPL07.CON.WP2.06860 |
RPL07.Conn - GSIDF/DH C2 - Install Copper, WAPs, Security Camera & Access Control | Cabling | Not Started | 10/30/26 | 11/17/26 | 15.0 | 15.0 |
|
293.8 |
RPL07.EY.DHA.01280 |
RPL07.EY.DHA - Install BMS/EPMS Tie-ins | Tie-ins | Not Started | 10/30/26 | 11/13/26 | 12.5 | 12.5 |
|
30.0 |
RPL07.EY.DHB.01290 |
RPL07.EY.DHB - Install Sleeves MEPL | Hardscape and Landscape | Not Started | 10/30/26 | 11/05/26 | 6.2 | 6.2 |
|
181.2 |
RPL07.EY.DHB.01300 |
RPL07.EY.DHB - MV Loop - L2 Checklist Completion | Tie-ins | Not Started | 10/30/26 | 11/13/26 | 12.5 | 12.5 |
|
23.8 |
RPL07.EY.DHB.01320 |
RPL07.EY.DHB - Install Hardscape and Landscape - WBS Summary | Hardscape and Landscape | Not Started | 10/30/26 | 01/07/27 | 56.2 | 56.2 |
|
311.2 |
RPL07.INT.DHA.01630 |
RPL07.Interior.DHA - OFE - Control Fault Domain 5 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | Control Fault Domain 5 | Not Started | 10/30/26 | 02/09/27 | 83.8 | 83.8 |
|
46.2 |
RPL07.INT.DHA.01650 |
RPL07.Interior.DHA - Control Fault Domain 4 - Install LV Side Aisle HAC Busway | LV Side Tie-ins | Not Started | 10/30/26 | 11/04/26 | 5.0 | 5.0 |
|
140.0 |
RPL07.INT.DHA.03720 |
RPL07.Interior.DHA - OFE - Control Fault Domain 5 (LV Side Aisle) | Control Fault Domain 5 | Not Started | 10/30/26 | 11/04/26 | 5.0 | 5.0 |
|
72.5 |
RPL07.INT.ENDC.01220 |
RPL07.Interior.End-Corridor - Hang Drywall | Fit out | Not Started | 10/30/26 | 11/09/26 | 8.8 | 8.8 |
|
161.2 |
RPL07.INT.SSBC.4220 |
RPL07.Interior.SSBC LO #07 - Fire Safing OH and In-wall | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 10/30/26 | 10/30/26 | 1.2 | 1.2 |
|
87.5 |
RPL07.INT.CTRC.01380 |
RPL07.Interior.Center-Corridor (N) - Install Cable Tray - North (Early) | Fit out (North) | Not Started | 11/02/26 | 11/06/26 | 6.2 | 6.2 |
|
156.2 |
RPL07.INT.CTRC.01910 |
RPL07.Interior.Center-Corridor (S) - Install Cable Tray- South (Early) | Fit out (South) | Not Started | 11/02/26 | 11/06/26 | 6.2 | 6.2 |
|
170.0 |
RPL07.INT.CTRC.02030 |
RPL07.Interior.Center-Corridor (S) - Install Fitout (Spoke Parts, Tech, SCR etc.) - WBS Summary | Fit out (South) | Not Started | 11/02/26 | 04/16/27 | 140.0 | 140.0 |
|
36.2 |
RPL07.INT.CTRC.07160 |
RPL07.Interior.Center-Corridor - CFCI - Pre Set 16"" FW Pipe | Center Corridor | Not Started | 11/02/26 | 11/16/26 | 12.5 | 12.5 |
|
66.2 |
RPL07.INT.CTRC.1380 |
RPL07.Interior.Center-Corridor - BoW - Install Controls / EPMS / BMS OH and In-wall | Balance of Walls & Overhead | Not Started | 11/02/26 | 11/06/26 | 6.2 | 6.2 |
|
130.0 |
RPL07.INT.CTRC.1460 |
RPL07.Interior.Center-Corridor - BoW - Frame Hard Lid | Balance of Walls & Overhead | Not Started | 11/02/26 | 11/06/26 | 6.2 | 6.2 |
|
36.2 |
RPL07.INT.DHA.01660 |
RPL07.Interior.DHA - Control Fault Domain 4 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 11/02/26 | 11/05/26 | 5.0 | 5.0 |
|
182.5 |
RPL07.INT.DHD.01300 |
RPL07.Interior.DHD - Tie-ins - Control Fault Domain 2 - WBS Summary | Control Fault Domain 2 | Not Started | 11/02/26 | 04/27/27 | 148.8 | 148.8 |
|
71.2 |
RPL07.INT.DHD.02530 |
RPL07.Interior.DHD - Control Fault Domain 2 - Install Duct (LV Side) | LV Side Tie-ins | Not Started | 11/02/26 | 11/05/26 | 5.0 | 5.0 |
|
170.0 |
RPL07.INT.SSBC.3400 |
RPL07.Interior.SSBC LO #06 - Tape Finish Paint | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 11/02/26 | 11/06/26 | 6.2 | 6.2 |
|
93.8 |
RPL07.INT.SSBC.4260 |
RPL07.Interior.SSBC LO #07 - Install Backing | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 11/02/26 | 11/02/26 | 1.2 | 1.2 |
|
87.5 |
RPL07.SKN.S.LO.03100 |
RPL07.SKIN.LO#17 - Install IMP Insulated Metal Panels | Build back Exterior Leave Out Walls #17 (CC - South) | Not Started | 11/02/26 | 11/03/26 | 2.5 | 2.5 |
|
91.2 |
RPL07.SKN.W.LO.01420 |
RPL07.SKIN.LO#16 - Install IMP Insulated Metal Panels | Build back Exterior Leave Out Walls #16 (SSB - North of Loading Dock) | Not Started | 11/02/26 | 11/06/26 | 6.2 | 6.2 |
|
67.5 |
RPL07.INT.DHA.01170 |
RPL07.Interior.DHA - Control Fault Domain 1 - Pull BMS from panel to devices | Remaining Tie-ins post Mech Side Aisle install | Not Started | 11/03/26 | 12/03/26 | 25.0 | 25.0 |
|
46.2 |