Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL07 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:16 PM
· 5237 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
0
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL07.INT.DHA.01180 |
RPL07.Interior.DHA - Control Fault Domain 1 - Pull EMPS from panel to devices | Remaining Tie-ins post Mech Side Aisle install | Not Started | 11/03/26 | 12/03/26 | 25.0 | 25.0 |
|
46.2 |
RPL07.INT.DHA.01190 |
RPL07.Interior.DHA - Control Fault Domain 1 - Set UPS and Panel (2) | Remaining Tie-ins post Mech Side Aisle install | Not Started | 11/03/26 | 12/03/26 | 25.0 | 25.0 |
|
33.8 |
RPL07.INT.DHA.01710 |
RPL07.Interior.DHA - Tie-ins - Control Fault Domain 5 - WBS Summary | Control Fault Domain 5 | Not Started | 11/03/26 | 03/29/27 | 121.2 | 121.2 |
|
53.8 |
RPL07.INT.DHA.03860 |
RPL07.Interior.DHA - Control Fault Domain 5 - Install Duct (LV Side) | LV Side Tie-ins | Not Started | 11/03/26 | 11/06/26 | 5.0 | 5.0 |
|
123.8 |
RPL07.INT.DHB.01340 |
RPL07.Interior.DHB - Control Fault Domain 1 - Install copper from GS.IDF to BMS and EPMS panels | Remaining Tie-ins post Mech Side Aisle install | Not Started | 11/03/26 | 12/03/26 | 25.0 | 25.0 |
|
33.8 |
RPL07.INT.ENDC.06960 |
RPL07.Interior.End-Corridor - Final Finishes & Fixtures - Casework | Restrooms | Not Started | 11/03/26 | 11/12/26 | 8.8 | 8.8 |
|
173.8 |
RPL07.INT.ENDC.1280 |
RPL07.Interior.End-Corridor - BoW - Install Fire Life Safety Lowside OH and In-wall | Balance of Walls & Overhead | Not Started | 11/03/26 | 11/12/26 | 8.8 | 8.8 |
|
145.0 |
RPL07.INT.ENDC.1320 |
RPL07.Interior.End-Corridor - BoW - Install Security Lowside OH and In-wall | Balance of Walls & Overhead | Not Started | 11/03/26 | 11/12/26 | 8.8 | 8.8 |
|
216.2 |
RPL07.INT.SSBC.4280 |
RPL07.Interior.SSBC LO #07 - QC - Backings/Walls | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 11/03/26 | 11/04/26 | 2.5 | 2.5 |
|
87.5 |
RPL07.EY.DHB.01420 |
RPL07.EY.DHB - Install Condenser Units (Qty 4) | OFE | Not Started | 11/04/26 | 11/16/26 | 10.0 | 10.0 |
|
152.5 |
RPL07.INT.DHC.01093 |
RPL07.Interior.DHC - LV Skids and TopHat - Top Hat Busway | DHC - LV Skids and TopHat | Not Started | 11/04/26 | 11/20/26 | 15.0 | 15.0 |
|
192.5 |
RPL07.INT.DHC.01112 |
RPL07.Interior.DHC - MES Skids - Piping Tie-Ins & Inspections | DHC - MES Skids | Not Started | 11/04/26 | 11/30/26 | 20.0 | 20.0 |
|
171.2 |
RPL07.INT.DHD.01350 |
RPL07.Interior.DHD - OFE - Control Fault Domain 3 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | Control Fault Domain 3 | Not Started | 11/04/26 | 03/15/27 | 108.8 | 108.8 |
|
32.5 |
RPL07.INT.DHD.01370 |
RPL07.Interior.DHD - Control Fault Domain 2 - Install LV Side Aisle HAC Busway | LV Side Tie-ins | Not Started | 11/04/26 | 11/09/26 | 5.0 | 5.0 |
|
178.8 |
RPL07.INT.DHD.02390 |
RPL07.Interior.DHD - OFE - Control Fault Domain 3 (LV Side Aisle) | Control Fault Domain 3 | Not Started | 11/04/26 | 11/09/26 | 5.0 | 5.0 |
|
123.8 |
RPL07.INT.SBC.03580 |
RPL07.Interior.SSB-Corridor - BoW - Tape Finish Paint (Both side of Corridor Wall) | Balance of Walls & Overhead | Not Started | 11/04/26 | 11/06/26 | 3.8 | 3.8 |
|
90.0 |
RPL07.INT.SSB.14360 |
RPL07.Interior.SSB LO #01 to #05 - Hang Drywall | OH & Framing | Not Started | 11/04/26 | 11/13/26 | 8.8 | 8.8 |
|
87.5 |
RPL07.SKN.S.LO.03120 |
RPL07.SKIN.LO#17 - Install IMP Flashing & Caulking | Build back Exterior Leave Out Walls #17 (CC - South) | Not Started | 11/04/26 | 11/05/26 | 2.5 | 2.5 |
|
91.2 |
ICM.B7.2550 |
[SSDCB2] L3/L4 Start mCUP [1-4] - RPL07 | Commissioning | Not Started | 11/05/26 | 11/05/26 | 0.0 | 0.0 |
|
220.0 |
RPL.07.D.73310.XR |
Pull and Term MV Skids - RPL07 DHA | Receive Milestones (XREFs) | Not Started | 11/05/26 | 11/05/26 | 0.0 | 0.0 |
|
43.8 |
RPL.07.D.73810.XR |
100MW Cx Temp Power to MV Skids RPL07 DHA Available | Receive Milestones (XREFs) | Not Started | 11/05/26 | 11/05/26 | 0.0 | 0.0 |
|
43.8 |
RPL07.CX.MCUP.01050 |
RPL07.CX.mCup Loop 1 - L3/L4 - mCUP | mCUP 1-4 | Not Started | 11/05/26 | 12/17/26 | 35.0 | 35.0 |
|
48.8 |
RPL07.INT.DHA.01780 |
RPL07.Interior.DHA - Control Fault Domain 5 - Install LV Side Aisle HAC Busway | LV Side Tie-ins | Not Started | 11/05/26 | 11/10/26 | 5.0 | 5.0 |
|
155.0 |
RPL07.INT.DHA.03560 |
RPL07.Interior.DHA - OFE - Control Fault Domain 2 (HAC) | Control Fault Domain 2 | Not Started | 11/05/26 | 11/30/26 | 18.8 | 18.8 |
|
12.5 |
RPL07.INT.DHC.01120 |
RPL07.Interior.DHC - OFE - Control Fault Domain 1 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | Control Fault Domain 1 | Not Started | 11/05/26 | 03/01/27 | 95.0 | 95.0 |
|
53.8 |
RPL07.INT.DHC.02270 |
RPL07.Interior.DHC - OFE - Control Fault Domain 1 (LV Side Aisle) | Control Fault Domain 1 | Not Started | 11/05/26 | 11/12/26 | 6.2 | 6.2 |
|
120.0 |
RPL07.INT.DHD.01390 |
RPL07.Interior.DHD - Control Fault Domain 2 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 11/05/26 | 11/10/26 | 5.0 | 5.0 |
|
178.8 |
RPL07.INT.SSB.01210 |
RPL07.Interior.SSB - BoW - Install Electrical Lowside OH and In-wall (Coordinate Lights) | Balance of Walls and OverHead | Not Started | 11/05/26 | 11/19/26 | 12.5 | 12.5 |
|
77.5 |
RPL07.INT.SSB.06700 |
RPL07.Interior.SSB - Final Finishes & Fixtures - Water Proofing/ Tape Paint | Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) | Not Started | 11/05/26 | 11/12/26 | 6.2 | 6.2 |
|
210.0 |
RPL07.INT.SSBC.4360 |
RPL07.Interior.SSBC LO #07 - Hang Drywall | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 11/05/26 | 11/06/26 | 2.5 | 2.5 |
|
87.5 |
RPL07.CON.WP2.06640 |
RPL07.Conn - GSIDF/DH D2 - Install Cabling (Pull, Splice & terminate) | Cabling | Not Started | 11/06/26 | 11/16/26 | 7.5 | 7.5 |
|
350.0 |
RPL07.CON.WP2.06660 |
RPL07.Conn - GSIDF/DH D2 - Install Copper, WAPs, Security Camera & Access Control | Cabling | Not Started | 11/06/26 | 11/24/26 | 15.0 | 15.0 |
|
278.8 |
RPL07.EY.DHA.01290 |
RPL07.EY.DHA - MV Loop - L2 Checklist Completion | Tie-ins | Not Started | 11/06/26 | 11/20/26 | 12.5 | 12.5 |
|
30.0 |
RPL07.EY.DHB.01330 |
RPL07.EY.DHB - Install Early EY Paving | Hardscape and Landscape | Not Started | 11/06/26 | 11/13/26 | 6.2 | 6.2 |
|
181.2 |
RPL07.INT.CC.9000 |
RPL07.Interior.CC Ext. LO #17 - Close Exterior Leave Out #17 (CC - South) WBS Summary | Exterior Leave Out Wall #17 (CC - South) | Not Started | 11/06/26 | 12/21/26 | 36.2 | 36.2 |
|
101.2 |
RPL07.INT.CC.9280 |
RPL07.Interior.CC Ext. LO #17 - Install Mechanical Piping/ Refrigerant Lowside OH and in-wall | Exterior Leave Out Wall #17 (CC - South) | Not Started | 11/06/26 | 11/10/26 | 3.8 | 3.8 |
|
77.5 |
RPL07.INT.CC.9560 |
RPL07.Interior.CC Ext. LO #17 - Tie In MEPF with IMP Wall buildback | Exterior Leave Out Wall #17 (CC - South) | Not Started | 11/06/26 | 11/09/26 | 2.5 | 2.5 |
|
88.8 |
RPL07.INT.DHA.01800 |
RPL07.Interior.DHA - Control Fault Domain 5 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 11/06/26 | 11/12/26 | 5.0 | 5.0 |
|
166.2 |
RPL07.INT.DHC.01113 |
RPL07.Interior.DHC - MES Skids - CDU Tie-Ins | DHC - MES Skids | Not Started | 11/06/26 | 12/02/26 | 20.0 | 20.0 |
|
171.2 |
RPL07.INT.DHD.01440 |
RPL07.Interior.DHD - Tie-ins - Control Fault Domain 3 (including IDF) - WBS Summary | Control Fault Domain 3 | Not Started | 11/06/26 | 05/04/27 | 150.0 | 150.0 |
|
108.8 |
RPL07.INT.DHD.02550 |
RPL07.Interior.DHD - Control Fault Domain 3 - Install Duct (LV Side) | LV Side Tie-ins | Not Started | 11/06/26 | 11/12/26 | 5.0 | 5.0 |
|
191.2 |
RPL07.INT.SSB.03120 |
RPL07.Interior.SSB - Loading Dock and Storage - Install Store Front Glazing | Loading Dock and Storage | Not Started | 11/06/26 | 11/09/26 | 2.5 | 2.5 |
|
190.0 |
DCC.B7.3035 |
[SSDCB2] Production Gear Delivered [DHB] Front End (SSW &FSW) | Connectivity | Not Started | 11/09/26 | 11/09/26 | 0.0 | 0.0 |
|
175.0 |
RPL.07.D.73740.XG |
RMUs/MV Skids Set (Ready for Longhorn Pulls) - DHD | Give Milestones (XREFs) | Not Started | 11/09/26 | 11/09/26 | 0.0 | 0.0 |
|
358.8 |
RPL.07.D.74040.XG |
Ready for MV Cable Pull DH D (MVs - Qty 8)* | Give Milestones (XREFs) | Not Started | 11/09/26 | 11/09/26 | 0.0 | 0.0 |
|
358.8 |
RPL07.CON.WP2.06880 |
RPL07.Conn - GSIDF/DH C2 - Install & Test Network (FIM) | Network | Not Started | 11/09/26 | 11/12/26 | 3.8 | 3.8 |
|
356.2 |
RPL07.CON.WP3B.0900 |
RPL07.Conn WP3B Pull/Install/Test Universal Fabric EF1(South)<>EF2 (North) | EF1 <> EF2 | Not Started | 11/09/26 | 11/16/26 | 6.2 | 6.2 |
|
187.5 |
RPL07.INT.CTRC.1480 |
RPL07.Interior.Center-Corridor - BoW - MEPF Hard Lid Rough-In/ Close of Inspection | Balance of Walls & Overhead | Not Started | 11/09/26 | 11/18/26 | 8.8 | 8.8 |
|
78.8 |
RPL07.INT.CTRC.1500 |
RPL07.Interior.Center-Corridor - BoW - Install Blocking/Steel support Assembly for Metal Canopy | Balance of Walls & Overhead | Not Started | 11/09/26 | 11/16/26 | 6.2 | 6.2 |
|
36.2 |
RPL07.INT.DHC.01160 |
RPL07.Interior.DHC - Tie-ins - Control Fault Domain 1 - WBS Summary | Control Fault Domain 1 | Not Started | 11/09/26 | 04/22/27 | 138.8 | 138.8 |
|
63.8 |
RPL07.INT.DHC.02510 |
RPL07.Interior.DHC - Control Fault Domain 1 - Install Duct (LV Side) | LV Side Tie-ins | Not Started | 11/09/26 | 11/16/26 | 6.2 | 6.2 |
|
152.5 |
RPL07.INT.SBC.03600 |
RPL07.Interior.SSB-Corridor - BoW - Electrical Trim Out (Both side of Corridor Wall) | Balance of Walls & Overhead | Not Started | 11/09/26 | 11/18/26 | 8.8 | 8.8 |
|
90.0 |
RPL07.INT.SBC.03620 |
RPL07.Interior.SSB-Corridor - BoW - Duct Drops / Trim out | Balance of Walls & Overhead | Not Started | 11/09/26 | 11/16/26 | 6.2 | 6.2 |
|
90.0 |
RPL07.INT.SBC.03700 |
RPL07.Interior.SSB-Corridor - BoW - Install Balance Of Refrigerant Line | Balance of Walls & Overhead | Not Started | 11/09/26 | 11/16/26 | 6.2 | 6.2 |
|
130.0 |
RPL07.INT.SBC.03720 |
RPL07.Interior.SSB-Corridor - BoW - Security Trim Out (Both side of Corridor Wall) | Balance of Walls & Overhead | Not Started | 11/09/26 | 11/18/26 | 8.8 | 8.8 |
|
90.0 |
RPL07.INT.SBC.03840 |
RPL07.Interior.SSB-Corridor - BoW - Install Lights | Balance of Walls & Overhead | Not Started | 11/09/26 | 11/23/26 | 12.5 | 12.5 |
|
100.0 |
RPL07.INT.SSB.01540 |
RPL07.Interior.SSB - Loading Dock and Storage - Fire Life Safety Trim Out / Fire Alarm Trim Out | Loading Dock and Storage | Not Started | 11/09/26 | 11/18/26 | 8.8 | 8.8 |
|
168.8 |
RPL07.INT.SSBC.3560 |
RPL07.Interior.SSBC LO #06 - Install Remaining Lights | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 11/09/26 | 11/12/26 | 3.8 | 3.8 |
|
95.0 |
RPL07.INT.SSBC.3580 |
RPL07.Interior.SSBC LO #06 - Install Flooring Tiles/Resinous Flooring in specific rooms | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 11/09/26 | 11/12/26 | 3.8 | 3.8 |
|
97.5 |
RPL07.INT.SSBC.3720 |
RPL07.Interior.SSBC LO #06 - Fire Safing / Wall Finishes | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 11/09/26 | 11/10/26 | 2.5 | 2.5 |
|
93.8 |
RPL07.INT.SSBC.4400 |
RPL07.Interior.SSBC LO #07 - Tape Finish Paint | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 11/09/26 | 11/16/26 | 6.2 | 6.2 |
|
87.5 |
RPL07.SKN.W.LO.01440 |
RPL07.SKIN.LO#16 - Install IMP Flashing & Caulking | Build back Exterior Leave Out Walls #16 (SSB - North of Loading Dock) | Not Started | 11/09/26 | 11/16/26 | 6.2 | 6.2 |
|
67.5 |
RPL07.EY.DHA.01420 |
RPL07.EY.DHA - Install Condenser Units (Qty 4) | OFE | Not Started | 11/10/26 | 11/20/26 | 10.0 | 10.0 |
|
137.5 |
RPL07.EY.DHA.02060 |
RPL07.EY.DHA - Install reminder of Wall mounted ACs post LO buildback (Qty2) | OFE | Not Started | 11/10/26 | 11/16/26 | 5.0 | 5.0 |
|
162.5 |
RPL07.EY.DHD.01240 |
RPL07.EY.DHD - Install Generator (#2 of Qty 2) | OFE | Not Started | 11/10/26 | 11/17/26 | 6.2 | 6.2 |
|
167.5 |
RPL07.EY.DHD.01250 |
RPL07.EY.DHD - Install Electrical Tie-ins (include penetration detail) | Tie-ins | Not Started | 11/10/26 | 11/24/26 | 12.5 | 12.5 |
|
135.0 |
RPL07.EY.DHD.01260 |
RPL07.EY.DHD - Tie-ins - WBS Summary | Tie-ins | Not Started | 11/10/26 | 06/08/27 | 177.5 | 177.5 |
|
95.0 |
RPL07.INT.DHA.01240 |
RPL07.Interior.DHA - Control Fault Domain 1 - Install Mechanical Side Aisle Cable Tray | Remaining Tie-ins post Mech Side Aisle install | Not Started | 11/10/26 | 12/10/26 | 25.0 | 25.0 |
|
33.8 |
RPL07.INT.DHA.03580 |
RPL07.Interior.DHA - OFE - Control Fault Domain 2 (Mech Side Aisle) | Control Fault Domain 2 | Not Started | 11/10/26 | 12/01/26 | 16.2 | 16.2 |
|
40.0 |
RPL07.INT.DHB.01350 |
RPL07.Interior.DHB - Control Fault Domain 2 - Install Duct (MES Side) | Remaining Tie-ins post Mech Side Aisle install | Not Started | 11/10/26 | 12/10/26 | 25.0 | 25.0 |
|
40.0 |
RPL07.INT.DHB.01360 |
RPL07.Interior.DHB - Control Fault Domain 2 - Install Vesda / FA | Remaining Tie-ins post Mech Side Aisle install | Not Started | 11/10/26 | 12/10/26 | 25.0 | 25.0 |
|
52.5 |
RPL07.INT.DHB.01370 |
RPL07.Interior.DHB - Control Fault Domain 2 - Install FW | Remaining Tie-ins post Mech Side Aisle install | Not Started | 11/10/26 | 12/10/26 | 25.0 | 25.0 |
|
40.0 |
RPL07.INT.DHB.01430 |
RPL07.Interior.DHB - Control Fault Domain 1 - L2 Checklist Completion | Remaining Tie-ins post Mech Side Aisle install | Not Started | 11/10/26 | 12/10/26 | 25.0 | 25.0 |
|
33.8 |
RPL07.INT.DHB.02220 |
RPL07.Interior.DHB - Control Fault Domain 2 - Install TW | Remaining Tie-ins post Mech Side Aisle install | Not Started | 11/10/26 | 12/10/26 | 25.0 | 25.0 |
|
40.0 |
RPL07.INT.DHC.01114 |
RPL07.Interior.DHC - MES Skids - BMS Tie-Ins | DHC - MES Skids | Not Started | 11/10/26 | 12/04/26 | 20.0 | 20.0 |
|
171.2 |
RPL07.INT.DHD.01490 |
RPL07.Interior.DHD - OFE - Control Fault Domain 4 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | Control Fault Domain 4 | Not Started | 11/10/26 | 03/30/27 | 116.2 | 116.2 |
|
30.0 |
RPL07.INT.DHD.01510 |
RPL07.Interior.DHD - Control Fault Domain 3 - Install LV Side Aisle HAC Busway | LV Side Tie-ins | Not Started | 11/10/26 | 11/16/26 | 5.0 | 5.0 |
|
221.2 |
RPL07.INT.DHD.02450 |
RPL07.Interior.DHD - OFE - Control Fault Domain 4 (LV Side Aisle) | Control Fault Domain 4 | Not Started | 11/10/26 | 11/16/26 | 5.0 | 5.0 |
|
131.2 |
RPL07.INT.ENDC.01240 |
RPL07.Interior.End-Corridor - Tape Finish Paint | Fit out | Not Started | 11/10/26 | 11/13/26 | 3.8 | 3.8 |
|
161.2 |
RPL07.INT.CC.9320 |
RPL07.Interior.CC Ext. LO #17 - Install Fire Life Safety Lowside OH and In-wall | Exterior Leave Out Wall #17 (CC - South) | Not Started | 11/12/26 | 11/16/26 | 3.8 | 3.8 |
|
93.8 |
RPL07.INT.CC.9340 |
RPL07.Interior.CC Ext. LO #17 - Install Plumbing Lowside OH and In-wall | Exterior Leave Out Wall #17 (CC - South) | Not Started | 11/12/26 | 11/16/26 | 3.8 | 3.8 |
|
77.5 |
RPL07.INT.DHC.01230 |
RPL07.Interior.DHC - Control Fault Domain 1 - Install LV Side Aisle HAC Busway | LV Side Tie-ins | Not Started | 11/12/26 | 11/18/26 | 6.2 | 6.2 |
|
161.2 |
RPL07.INT.DHD.01530 |
RPL07.Interior.DHD - Control Fault Domain 3 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 11/12/26 | 11/17/26 | 5.0 | 5.0 |
|
250.0 |
RPL07.INT.ENDC.1300 |
RPL07.Interior.End-Corridor - BoW - Install Plumbing Lowside OH and In-wall | Balance of Walls & Overhead | Not Started | 11/12/26 | 11/20/26 | 8.8 | 8.8 |
|
125.0 |
RPL07.INT.SBC.03740 |
RPL07.Interior.SSB-Corridor - BoW - Plumbing Trim Out | Balance of Walls & Overhead | Not Started | 11/12/26 | 11/18/26 | 6.2 | 6.2 |
|
90.0 |
RPL07.INT.SBC.03760 |
RPL07.Interior.SSB-Corridor - BoW - Fire Life Safety Trim Out / Fire Alarm Trim Out | Balance of Walls & Overhead | Not Started | 11/12/26 | 11/20/26 | 8.8 | 8.8 |
|
90.0 |
RPL07.INT.SSBC.3420 |
RPL07.Interior.SSBC LO #06 - Electrical Trim Out | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 11/12/26 | 11/13/26 | 2.5 | 2.5 |
|
93.8 |
RPL07.INT.SSBC.3440 |
RPL07.Interior.SSBC LO #06 - Security Trim Out | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 11/12/26 | 11/13/26 | 2.5 | 2.5 |
|
93.8 |
RPL07.CFCI.5290 |
RPL07 - Fabricate / Deliver - Carpet Tile | (CFCI) Div. 09 - Carpet | Not Started | 11/13/26 | 01/13/27 | 50.0 | 50.0 |
|
131.2 |
RPL07.EY.DHD.01280 |
RPL07.EY.DHD - Install BMS/EPMS Tie-ins | Tie-ins | Not Started | 11/13/26 | 11/30/26 | 12.5 | 12.5 |
|
135.0 |
RPL07.INT.CTRC.01670 |
RPL07.Interior.Center-Corridor - MOFE - Ancillary Skids Qty2 (DH A) | OFE/MOFE & CFCI | Not Started | 11/13/26 | 11/30/26 | 12.5 | 12.5 |
|
102.5 |
RPL07.INT.CTRC.01690 |
RPL07.Interior.Center-Corridor - MOFE - Ancillary Skids Qty2 (DH B) | OFE/MOFE & CFCI | Not Started | 11/13/26 | 11/30/26 | 12.5 | 12.5 |
|
111.2 |
RPL07.INT.DHB.02540 |
RPL07.Interior.DHB - OFE - Control Fault Domain 3 (HAC) | Control Fault Domain 3 | Not Started | 11/13/26 | 12/07/26 | 18.8 | 18.8 |
|
30.0 |
RPL07.INT.DHC.01115 |
RPL07.Interior.DHC - MES Skids - EPMS Tie-Ins | DHC - MES Skids | Not Started | 11/13/26 | 12/08/26 | 20.0 | 20.0 |
|
171.2 |
RPL07.INT.DHC.01210 |
RPL07.Interior.DHC - OFE - Control Fault Domain 2 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | Control Fault Domain 2 | Not Started | 11/13/26 | 03/15/27 | 101.2 | 101.2 |
|
51.2 |
RPL07.INT.DHC.01250 |
RPL07.Interior.DHC - Control Fault Domain 1 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 11/13/26 | 11/19/26 | 6.2 | 6.2 |
|
161.2 |
RPL07.INT.DHC.02330 |
RPL07.Interior.DHC - OFE - Control Fault Domain 2 (LV Side Aisle) | Control Fault Domain 2 | Not Started | 11/13/26 | 11/18/26 | 5.0 | 5.0 |
|
132.5 |
RPL07.INT.DHD.01580 |
RPL07.Interior.DHD - Tie-ins - Control Fault Domain 4 - WBS Summary | Control Fault Domain 4 | Not Started | 11/13/26 | 05/18/27 | 157.5 | 157.5 |
|
101.2 |
RPL07.INT.DHD.02570 |
RPL07.Interior.DHD - Control Fault Domain 4 - Install Duct (LV Side) | LV Side Tie-ins | Not Started | 11/13/26 | 11/18/26 | 5.0 | 5.0 |
|
193.8 |
RPL07.INT.ENDC.07020 |
RPL07.Interior.End-Corridor - Final Finishes & Fixtures - Fixture Install (Lights) | Restrooms | Not Started | 11/13/26 | 11/23/26 | 8.8 | 8.8 |
|
201.2 |